1. Production Schedule
Date What needs to be done Location By Who Equipment Needed
11th December
2015
Pre-Production Tasks: Fully
Completed and on Blogger
Ringwood
School
Matt Lumley Computer
12th December
2015
Pre-Production: Health and
Safety Risk Assessment of my
locations: Garage, Lounge, Fish
Inn road, Avon Valley Bridge
locations:
Garage, Lounge,
Fish Inn road,
Avon Valley
Bridge
Matt Lumley Pen, Paper and Risk assessment forms
15th December
2015
Pre-Production: Run through the
script and let the cast get to know
it better so that they will be able to
get into character quicker on the
days we film.
Ringwood
School
All Cast Pen, Paper, Script
28th December
2015
Production: Filming scene 1,
Shots 1-5 Start at 8:30PM as
need it to be night time and clear
therefore due to the location and
rush hour it needs to be late so
the traffic is quiet. Will take about
half an hour to an hour and then
will drop cast off home and the
filming will be done for the days
after all shots for the scene are
done.
The Fish Inn, will
get there by car
from my parents
and so will the
rest of the crew
All Cast Camera
Tripod
Microphone
Beer can
Costumes
Phone
9th January
2016
Production: Filming scene 2,
Shots 6-9, Can start earlier with
this shot as the Avon Valley
Bridge is secluded and quiet at
night, therefore filming will start at
about 5:30PM as it will be dark
and will take about half an hour to
an hour also. We will all be
dropped off in a car as well as
picked up again and filming will be
done after all shots obtained at
around 6:30PM.
The Avon Valley
Bridge
All Cast Camera
Tripod
Microphone
Costumes
Phone
10th January
2016
Production: Filming scene 3,
shots 10-15, Cast will be dropped
off round my house at 10 to 6 to
prepare and get ready. The
My Garage All Cast Camera
Tripod
Microphone
Costumes
2. filming will take place around 6PM
as it will need to be dark for my
film to have the right affect and so
I can use the right lighting. Scene
is more in depth and will take
longer therefore the filming time
will last about an hour and a half
will all the right clips taken and
taken right. Therefore filming on
this day will end about half 7 at
night, Then the cast will go inside
and eat as it will be late and then
picked up by their parents at
around 8 when the cast will be
separated once more.
Phone
Knife
Rope
Fake Blood
Muddy Water
Lighting
Smashed Light
Chair
Go-Pro Camera
Head Strap
16th January
2016
Production: Filming scene 4,
Shots 16-21, This will be filmed at
6 so its dark and it will benefit my
filming style. Cast will be dropped
off 10 minutes before filming to
get ready and get into role so can
get straight into filming. Filming is
short and only with a few shots
and therefore if done correctly
should only take about 45 minutes
maybe an hour. Afterwards Cast
split and get picked up individually
by parents and taken home and
filming is complete for my film.
My Lounge/
Outside window
of Lounge
All Cast Camera
Tripod
Microphone
Costumes
Phone
18th January
2016
Production: Sound check and
upload all footage to school
computer
Ringwood
School/ Home
Matt Lumley Computer
USB to SD card converter
Headphones
18th January
2016
Post Production: All clips will be
added to my computer and ready
to develop and edit into my film.
Ringwood
School
Matt Lumley Computer
Headphones
19th January
2016
Post Production: Create my logo
for my company and my film intro
title.
Ringwood
School
Matt Lumley Computer
Headphones
20th January
2016
Post Production: Upload my
clips onto Adobe Premier Pro and
begin editing scenes 1 and two.
This will take about an hour on
each scene and therefore will take
Ringwood
school
Matt Lumley Computer
Headphones
Adobe Premier Pro
3. two hours overall and then will be
done.
21st January
2016
Post Production: Upload my
clips onto Adobe Premier Pro and
begin editing scenes 3 and 4. This
will take about an hour on each
scene and therefore will take two
hours overall and then will be
done
Ringwood
School
Matt Lumley Computer
Headphones
Adobe Premier Pro
24th January
2016
Post Production: Add the credits
and music and sound effects to
the video edit so that it is
complete.
Ringwood
School
Matt Lumley Computer
Headphones
Adobe Premier Pro
24th January
2016
Post Production: Uploading my
finished exported clip to Youtube
and Blogger to get it finished and
finalised.
Ringwood
School
Matt Lumley Computer
Headphones
Adobe Premier Pro
Youtube
Blogger
15th February
2016
Evaluation: Completed evaluation
questions:1,2 and 3
Ringwood
School
Matt Lumley Computer
Microsoft Word
25th February
2016
Evaluation: Completed
evaluation questions: 4 and 5
Ringwood
School
Matt Lumley Computer
Microsoft Word
5th March
2016
Evaluation: Completed
evaluation questions: 6&7 and
then uploaded all evaluation
questions to Blogger
Ringwood
School
Matt Lumley Computer
Microsoft Word
Blogger