SlideShare a Scribd company logo
1 of 11
QUANTITY SURVEYING AND
VALUATION
Lecture #1
INTRODUCTION
“What is the purpose and necessity of studying this subject?”
This is the first question which arises in mind
The answer lies in the following questions
Has one got enough money to spend on the construction ?
Has one got ample time that one can wait for the completion of the
construction ?
Has one got resources that one can arrange any amount of desired material
to be used in construction ?
Yes
Then the study of this subject is useless.
But if the answer is
NO
then the question arises,
“which are the factors necessitating the study of this subject.”
Set amount of fund
Costly labour ( skilled and unskilled)
Difficulty in getting good building
materials, particularly cement
And day to day rising cost of steel,
bricks, timber etc.
Also economy and standard of the construction are two important
things required.
.
Standard of
construction can
be achieved by
careful
supervision and
selecting proper
specifications
whereas for
Economy,
planning is a
must
The total
quantity of
various materials
used in
construction, if
known before
hand, can help
the planning
towards
economy.
OBJECTIVES
Covers the various aspects of estimating of quantities
of items of works involved
Buildings, water supply works, sanitary works, road
works and irrigation works
Rate analysis
Valuation of properties
Preparation of reports for estimation of various items.
Able to estimate the material quantities, prepare a bill
of quantities, make specifications and prepare tender
documents.
GENERAL INTRODUCTION
ESTIMATE
• An estimate for any construction work may be defined as
the Process of calculating the quantities and cost of various
items required in connection with the work
• To prepare an estimate:
Plan, elevation, section, detailed specifications are required
Quantity Surveying or Quantity Estimate
This is a complete estimate or list of quantities for all items of works
required to complete the concerned project
Purpose of Estimate
To ascertain necessary amount of money required by the
owner to complete the work
To ascertain quantities of materials required for timely
procurement
To calculate the number of workers
To assess the requirement of tools, plants and equipment's
To fix up completion period
To draw up the construction schedule
To invite tenders
valuation
Types of Estimates
(1) Preliminary or Approximate estimate
(2) Rough cost estimate based on plinth area
(3) Rough cost estimate based on cubic contents
(4) Detailed estimate
(5) Annual repair estimate
(6) Special repair estimate
(7) Revised estimate
(8) Supplementary estimate
Thank you

More Related Content

What's hot

estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveyingsooricivil
 
Mode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkMode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkAshwiniChaudhari13
 
Process of Building Construction
Process of Building ConstructionProcess of Building Construction
Process of Building ConstructionAyushHajare
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of RatesRaj Shah
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionAshwiniChaudhari13
 
Terminology used in estimating and costing
Terminology used in estimating and costingTerminology used in estimating and costing
Terminology used in estimating and costingJanak Mehta
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methodsgayu pandian
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimationDhavalMithaiwala
 
Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2ArunRavi43
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tendersgayu pandian
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-IKishor Ade
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and CostingSakshi Kirar
 
Construction Materials and Engineering - Module I - Lecture Notes
Construction Materials and Engineering - Module I - Lecture NotesConstruction Materials and Engineering - Module I - Lecture Notes
Construction Materials and Engineering - Module I - Lecture NotesSHAMJITH KM
 
Fundamentals of Estimating and Costing
 Fundamentals of Estimating and Costing Fundamentals of Estimating and Costing
Fundamentals of Estimating and CostingGanesh Tatikonda
 
6. intro to building materials
6. intro to building materials6. intro to building materials
6. intro to building materialsHamdija Velagic
 
01_Introduction_to_Estimation.pdf
01_Introduction_to_Estimation.pdf01_Introduction_to_Estimation.pdf
01_Introduction_to_Estimation.pdfkiransreekumar6
 

What's hot (20)

estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
Mode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickworkMode of measurement, rules for deduction of plastering & brickwork
Mode of measurement, rules for deduction of plastering & brickwork
 
Process of Building Construction
Process of Building ConstructionProcess of Building Construction
Process of Building Construction
 
Schedule of Rates
Schedule of RatesSchedule of Rates
Schedule of Rates
 
Estimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provisionEstimating, administrative approval, technical sanction, budget provision
Estimating, administrative approval, technical sanction, budget provision
 
Terminology used in estimating and costing
Terminology used in estimating and costingTerminology used in estimating and costing
Terminology used in estimating and costing
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
Estimating part 2
Estimating part 2Estimating part 2
Estimating part 2
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tenders
 
Specification writing-I
Specification writing-ISpecification writing-I
Specification writing-I
 
Bills of quantities
Bills of quantitiesBills of quantities
Bills of quantities
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and Costing
 
Construction Materials and Engineering - Module I - Lecture Notes
Construction Materials and Engineering - Module I - Lecture NotesConstruction Materials and Engineering - Module I - Lecture Notes
Construction Materials and Engineering - Module I - Lecture Notes
 
Rate analysis
Rate analysisRate analysis
Rate analysis
 
Fundamentals of Estimating and Costing
 Fundamentals of Estimating and Costing Fundamentals of Estimating and Costing
Fundamentals of Estimating and Costing
 
Estimation
EstimationEstimation
Estimation
 
6. intro to building materials
6. intro to building materials6. intro to building materials
6. intro to building materials
 
Building Components
Building ComponentsBuilding Components
Building Components
 
01_Introduction_to_Estimation.pdf
01_Introduction_to_Estimation.pdf01_Introduction_to_Estimation.pdf
01_Introduction_to_Estimation.pdf
 

Similar to 1# introduction to Quantity Surveying

Thesis presentation (wu 2016)
Thesis presentation  (wu 2016)Thesis presentation  (wu 2016)
Thesis presentation (wu 2016)Jifara Chimdi
 
ESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfsuchitamantry2002
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptTauheedKhan45
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxNSHYAMANANDASINGH
 
Estimating presentation (question 1)
Estimating presentation (question 1)Estimating presentation (question 1)
Estimating presentation (question 1)Shze Hwa Lee
 
Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsmeghajain275
 
1.Cost Estimation of Civil Structures Orientation.pptx
1.Cost Estimation of Civil Structures Orientation.pptx1.Cost Estimation of Civil Structures Orientation.pptx
1.Cost Estimation of Civil Structures Orientation.pptxVenkataRamana602302
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for buildingHimani762003
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial buildinglckr117
 
A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...
A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...
A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...IAEME Publication
 
Running Head Construction Project ProposalIntroductionTifwil .docx
Running Head Construction Project ProposalIntroductionTifwil .docxRunning Head Construction Project ProposalIntroductionTifwil .docx
Running Head Construction Project ProposalIntroductionTifwil .docxjoellemurphey
 
lecture ppt for contract administration and governing
lecture ppt for contract administration and governinglecture ppt for contract administration and governing
lecture ppt for contract administration and governing2cd
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Padmasinh Patil
 
ITD Presentation
ITD PresentationITD Presentation
ITD Presentationmasonsth
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONAr Naveen Naveen
 
Estimation Costing and Valuation Unit 1
Estimation Costing and Valuation Unit 1Estimation Costing and Valuation Unit 1
Estimation Costing and Valuation Unit 1Padmasinh Patil
 

Similar to 1# introduction to Quantity Surveying (20)

Thesis presentation (wu 2016)
Thesis presentation  (wu 2016)Thesis presentation  (wu 2016)
Thesis presentation (wu 2016)
 
ESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdfESTIMATION_AND_COSTING assignmentt-1.pdf
ESTIMATION_AND_COSTING assignmentt-1.pdf
 
COE
COECOE
COE
 
Quantity Surveying & valuation.ppt
Quantity Surveying & valuation.pptQuantity Surveying & valuation.ppt
Quantity Surveying & valuation.ppt
 
Introduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptxIntroduction to Quantity Surveying .pptx
Introduction to Quantity Surveying .pptx
 
Estimating presentation (question 1)
Estimating presentation (question 1)Estimating presentation (question 1)
Estimating presentation (question 1)
 
Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic terms
 
1.Cost Estimation of Civil Structures Orientation.pptx
1.Cost Estimation of Civil Structures Orientation.pptx1.Cost Estimation of Civil Structures Orientation.pptx
1.Cost Estimation of Civil Structures Orientation.pptx
 
Unit 1 - General Items used for building
Unit 1 - General Items used for buildingUnit 1 - General Items used for building
Unit 1 - General Items used for building
 
Estimation and costing of a commercial building
Estimation and costing of a commercial buildingEstimation and costing of a commercial building
Estimation and costing of a commercial building
 
A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...
A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...
A CASE STUDY ON TIME AND COST DRIVEN FACTORS OF COMMERCIAL COMPLEX BY USING E...
 
Ecm442 lecture 1 latest
Ecm442 lecture 1 latestEcm442 lecture 1 latest
Ecm442 lecture 1 latest
 
Running Head Construction Project ProposalIntroductionTifwil .docx
Running Head Construction Project ProposalIntroductionTifwil .docxRunning Head Construction Project ProposalIntroductionTifwil .docx
Running Head Construction Project ProposalIntroductionTifwil .docx
 
lecture ppt for contract administration and governing
lecture ppt for contract administration and governinglecture ppt for contract administration and governing
lecture ppt for contract administration and governing
 
Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2Estimation Costing and Valuation Unit 2
Estimation Costing and Valuation Unit 2
 
ITD Presentation
ITD PresentationITD Presentation
ITD Presentation
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
IV -I - EQS - .pptx
IV -I - EQS - .pptxIV -I - EQS - .pptx
IV -I - EQS - .pptx
 
Estimation Costing and Valuation Unit 1
Estimation Costing and Valuation Unit 1Estimation Costing and Valuation Unit 1
Estimation Costing and Valuation Unit 1
 
CPM 1 .pdf
CPM 1 .pdfCPM 1 .pdf
CPM 1 .pdf
 

More from LIJI A

Estimation of one room building
Estimation of one room buildingEstimation of one room building
Estimation of one room buildingLIJI A
 
Estimation of wall
Estimation of  wallEstimation of  wall
Estimation of wallLIJI A
 
5#rate analysis problems
5#rate analysis   problems5#rate analysis   problems
5#rate analysis problemsLIJI A
 
4#Rate analysis
4#Rate analysis4#Rate analysis
4#Rate analysisLIJI A
 
3#specifications
3#specifications3#specifications
3#specificationsLIJI A
 
2# types of estimate
2# types of estimate2# types of estimate
2# types of estimateLIJI A
 

More from LIJI A (6)

Estimation of one room building
Estimation of one room buildingEstimation of one room building
Estimation of one room building
 
Estimation of wall
Estimation of  wallEstimation of  wall
Estimation of wall
 
5#rate analysis problems
5#rate analysis   problems5#rate analysis   problems
5#rate analysis problems
 
4#Rate analysis
4#Rate analysis4#Rate analysis
4#Rate analysis
 
3#specifications
3#specifications3#specifications
3#specifications
 
2# types of estimate
2# types of estimate2# types of estimate
2# types of estimate
 

Recently uploaded

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

1# introduction to Quantity Surveying

  • 2. INTRODUCTION “What is the purpose and necessity of studying this subject?” This is the first question which arises in mind The answer lies in the following questions Has one got enough money to spend on the construction ? Has one got ample time that one can wait for the completion of the construction ? Has one got resources that one can arrange any amount of desired material to be used in construction ? Yes Then the study of this subject is useless.
  • 3. But if the answer is NO then the question arises, “which are the factors necessitating the study of this subject.” Set amount of fund Costly labour ( skilled and unskilled) Difficulty in getting good building materials, particularly cement And day to day rising cost of steel, bricks, timber etc.
  • 4. Also economy and standard of the construction are two important things required. . Standard of construction can be achieved by careful supervision and selecting proper specifications whereas for Economy, planning is a must The total quantity of various materials used in construction, if known before hand, can help the planning towards economy.
  • 5. OBJECTIVES Covers the various aspects of estimating of quantities of items of works involved Buildings, water supply works, sanitary works, road works and irrigation works Rate analysis Valuation of properties Preparation of reports for estimation of various items. Able to estimate the material quantities, prepare a bill of quantities, make specifications and prepare tender documents.
  • 6. GENERAL INTRODUCTION ESTIMATE • An estimate for any construction work may be defined as the Process of calculating the quantities and cost of various items required in connection with the work • To prepare an estimate: Plan, elevation, section, detailed specifications are required
  • 7. Quantity Surveying or Quantity Estimate This is a complete estimate or list of quantities for all items of works required to complete the concerned project
  • 8. Purpose of Estimate To ascertain necessary amount of money required by the owner to complete the work To ascertain quantities of materials required for timely procurement To calculate the number of workers To assess the requirement of tools, plants and equipment's
  • 9. To fix up completion period To draw up the construction schedule To invite tenders valuation
  • 10. Types of Estimates (1) Preliminary or Approximate estimate (2) Rough cost estimate based on plinth area (3) Rough cost estimate based on cubic contents (4) Detailed estimate (5) Annual repair estimate (6) Special repair estimate (7) Revised estimate (8) Supplementary estimate