Refurbishment5*Inter-ContinentalHotel Madrid
The $40m project involved the full renovation of 300 guest rooms, Hotel facilities and all back of
house areas. Health and Safety was paramount in all phased construction activities. The
original building had been developed as 3 separate apartment buildings in 1940. A four phase
redevelopment plan was agreed consisting of mock up rooms, new lifts, enabling works and
then 3 separate room phases. The planning aimed to minimize operational disruption, utilize low
occupancy periods to maximize work and keep the hotel at minimum 65% occupancy
throughout the 3 year construction period.
Major risks were identified - change orders due to unknown base build condition, choice of
contractor/sub-trades, material delays, management of deficiencies, missing operational
windows (e.g. low summer occupancy), noise/vibration/dust, design coordination to meet
schedule requirements and importantly delays in client sign off. Risks were allocated, managed
and reported on and risk management came second on all meeting agendas after Health and
Safety.
Brief included the tender process and contract development for Architect, Engineers, Interior
Designer and Construction Manager.
All FF&E (over 50 suppliers) and OS&E was identified, procured, expedited and delivered to
local warehouse in Madrid. Sub trades installed as required.
Over 600 change orders were managed during the construction process, 25 provisional sum
items were identified at tender phase – as the project developed the provisional sum items were
reviewed and included in the ongoing scope growth, always maintaining the agreed overall
budget levels.
Daily site meetings with the Construction Manager and the Project Manager, weekly meetings
between the PM and Hotel Operations, the identification of the Hotel Representative all
contributed to the success of the project.
The project was the largest refurbishment in Inter-Continental’s history in Europe. It was
completed 2% under the approved CAPEX and all phases were completed on time to a
extremely high quality.
Inter-Continental Hotel
Madrid, Spain
Client: Bass Hotels & Resorts
Location: Madrid, Spain
Building Area: 259,000 SF
Project Cost: $40,000,000
Completion: 2004
Contract Type: CM / Stipulated Sum
Scope of Services:
Project Management
Cost Management
FF&E, OS&E Procurement

More Related Content

Viewers also liked

Holistic Management of Grass, Cattle and Wildlife on Carrizo Valley Ranch.
Holistic Management of Grass, Cattle and Wildlife on Carrizo Valley Ranch.Holistic Management of Grass, Cattle and Wildlife on Carrizo Valley Ranch.
Holistic Management of Grass, Cattle and Wildlife on Carrizo Valley Ranch.SWGLA
 
InterConnect 2016, OpenJPA and EclipseLink Usage Scenarios (PEJ-5303)
InterConnect 2016, OpenJPA and EclipseLink Usage Scenarios (PEJ-5303)InterConnect 2016, OpenJPA and EclipseLink Usage Scenarios (PEJ-5303)
InterConnect 2016, OpenJPA and EclipseLink Usage Scenarios (PEJ-5303)Kevin Sutter
 
La inseminación artificial y la presunción de paternidad mb.
La inseminación artificial y la presunción de paternidad mb.La inseminación artificial y la presunción de paternidad mb.
La inseminación artificial y la presunción de paternidad mb.maryelenabolivar
 
Chatham house 2016 sg speech slides (1)
Chatham house 2016 sg speech slides (1)Chatham house 2016 sg speech slides (1)
Chatham house 2016 sg speech slides (1)James Kennedy
 
Panel de expertos en jamón, test de calidad para evolucionar al máximo un pro...
Panel de expertos en jamón, test de calidad para evolucionar al máximo un pro...Panel de expertos en jamón, test de calidad para evolucionar al máximo un pro...
Panel de expertos en jamón, test de calidad para evolucionar al máximo un pro...ainia centro tecnológico
 
Harvard University - Meeting Request December 2012
Harvard University - Meeting Request December 2012Harvard University - Meeting Request December 2012
Harvard University - Meeting Request December 2012Peace Walk With Muslims
 

Viewers also liked (12)

Tabla dinamica
Tabla dinamicaTabla dinamica
Tabla dinamica
 
Manual de la aplicación edico 1
Manual de la aplicación edico 1Manual de la aplicación edico 1
Manual de la aplicación edico 1
 
Desarrollo de competencias
Desarrollo de competencias Desarrollo de competencias
Desarrollo de competencias
 
Holistic Management of Grass, Cattle and Wildlife on Carrizo Valley Ranch.
Holistic Management of Grass, Cattle and Wildlife on Carrizo Valley Ranch.Holistic Management of Grass, Cattle and Wildlife on Carrizo Valley Ranch.
Holistic Management of Grass, Cattle and Wildlife on Carrizo Valley Ranch.
 
DOC002.PDF
DOC002.PDFDOC002.PDF
DOC002.PDF
 
InterConnect 2016, OpenJPA and EclipseLink Usage Scenarios (PEJ-5303)
InterConnect 2016, OpenJPA and EclipseLink Usage Scenarios (PEJ-5303)InterConnect 2016, OpenJPA and EclipseLink Usage Scenarios (PEJ-5303)
InterConnect 2016, OpenJPA and EclipseLink Usage Scenarios (PEJ-5303)
 
La inseminación artificial y la presunción de paternidad mb.
La inseminación artificial y la presunción de paternidad mb.La inseminación artificial y la presunción de paternidad mb.
La inseminación artificial y la presunción de paternidad mb.
 
Chatham house 2016 sg speech slides (1)
Chatham house 2016 sg speech slides (1)Chatham house 2016 sg speech slides (1)
Chatham house 2016 sg speech slides (1)
 
Panel de expertos en jamón, test de calidad para evolucionar al máximo un pro...
Panel de expertos en jamón, test de calidad para evolucionar al máximo un pro...Panel de expertos en jamón, test de calidad para evolucionar al máximo un pro...
Panel de expertos en jamón, test de calidad para evolucionar al máximo un pro...
 
funciones
funciones funciones
funciones
 
Habitat for Humanity of Utah County breakfast invitation
Habitat for Humanity of Utah County breakfast invitationHabitat for Humanity of Utah County breakfast invitation
Habitat for Humanity of Utah County breakfast invitation
 
Harvard University - Meeting Request December 2012
Harvard University - Meeting Request December 2012Harvard University - Meeting Request December 2012
Harvard University - Meeting Request December 2012
 

Similar to iNTERCONTINENTAL - PROJECT PAGE (20)

Loutfy_Monif November 2014
Loutfy_Monif  November  2014Loutfy_Monif  November  2014
Loutfy_Monif November 2014
 
C.V mr.srdc@yahoo.com DCM
C.V mr.srdc@yahoo.com DCMC.V mr.srdc@yahoo.com DCM
C.V mr.srdc@yahoo.com DCM
 
Eugenia Tzelardonis - Project Portfolio
Eugenia Tzelardonis - Project PortfolioEugenia Tzelardonis - Project Portfolio
Eugenia Tzelardonis - Project Portfolio
 
New brochure 240311
New brochure 240311New brochure 240311
New brochure 240311
 
Tarek Hassanain Eladawi - Final
Tarek Hassanain Eladawi - FinalTarek Hassanain Eladawi - Final
Tarek Hassanain Eladawi - Final
 
John Nelson CV 29 Oct 2015
John Nelson CV 29 Oct 2015John Nelson CV 29 Oct 2015
John Nelson CV 29 Oct 2015
 
CV MZ
CV MZCV MZ
CV MZ
 
Ziad Roushdy (Resume + Projects)_2016
Ziad Roushdy (Resume + Projects)_2016Ziad Roushdy (Resume + Projects)_2016
Ziad Roushdy (Resume + Projects)_2016
 
NASEER CV JUNE 2015
NASEER CV JUNE 2015NASEER CV JUNE 2015
NASEER CV JUNE 2015
 
CURRICULUM VITAE 12.03.16
CURRICULUM VITAE  12.03.16CURRICULUM VITAE  12.03.16
CURRICULUM VITAE 12.03.16
 
NASEERCV UPDATED IN SEPT 2015
NASEERCV UPDATED IN SEPT 2015NASEERCV UPDATED IN SEPT 2015
NASEERCV UPDATED IN SEPT 2015
 
Johnson Controls case studies - Commercial Project Management
Johnson Controls case studies - Commercial Project ManagementJohnson Controls case studies - Commercial Project Management
Johnson Controls case studies - Commercial Project Management
 
Adly CV111
Adly CV111Adly CV111
Adly CV111
 
Baha Cv 2015
Baha Cv 2015Baha Cv 2015
Baha Cv 2015
 
Steven Castellano.resume.2016
Steven Castellano.resume.2016Steven Castellano.resume.2016
Steven Castellano.resume.2016
 
lindsey horton 20160323
lindsey horton 20160323lindsey horton 20160323
lindsey horton 20160323
 
Appendices
AppendicesAppendices
Appendices
 
Perth metro
Perth metroPerth metro
Perth metro
 
cv1 Spass Merdjanoff
cv1 Spass Merdjanoffcv1 Spass Merdjanoff
cv1 Spass Merdjanoff
 
AnthonyCurrent HTR
AnthonyCurrent HTRAnthonyCurrent HTR
AnthonyCurrent HTR
 

iNTERCONTINENTAL - PROJECT PAGE

  • 1. Refurbishment5*Inter-ContinentalHotel Madrid The $40m project involved the full renovation of 300 guest rooms, Hotel facilities and all back of house areas. Health and Safety was paramount in all phased construction activities. The original building had been developed as 3 separate apartment buildings in 1940. A four phase redevelopment plan was agreed consisting of mock up rooms, new lifts, enabling works and then 3 separate room phases. The planning aimed to minimize operational disruption, utilize low occupancy periods to maximize work and keep the hotel at minimum 65% occupancy throughout the 3 year construction period. Major risks were identified - change orders due to unknown base build condition, choice of contractor/sub-trades, material delays, management of deficiencies, missing operational windows (e.g. low summer occupancy), noise/vibration/dust, design coordination to meet schedule requirements and importantly delays in client sign off. Risks were allocated, managed and reported on and risk management came second on all meeting agendas after Health and Safety. Brief included the tender process and contract development for Architect, Engineers, Interior Designer and Construction Manager. All FF&E (over 50 suppliers) and OS&E was identified, procured, expedited and delivered to local warehouse in Madrid. Sub trades installed as required. Over 600 change orders were managed during the construction process, 25 provisional sum items were identified at tender phase – as the project developed the provisional sum items were reviewed and included in the ongoing scope growth, always maintaining the agreed overall budget levels. Daily site meetings with the Construction Manager and the Project Manager, weekly meetings between the PM and Hotel Operations, the identification of the Hotel Representative all contributed to the success of the project. The project was the largest refurbishment in Inter-Continental’s history in Europe. It was completed 2% under the approved CAPEX and all phases were completed on time to a extremely high quality.
  • 2. Inter-Continental Hotel Madrid, Spain Client: Bass Hotels & Resorts Location: Madrid, Spain Building Area: 259,000 SF Project Cost: $40,000,000 Completion: 2004 Contract Type: CM / Stipulated Sum Scope of Services: Project Management Cost Management FF&E, OS&E Procurement