1. JYOTINDRA NIRALA
Mob: +917089675776, +91 9137921558
E-Mail: Jyotindra.nirala@yahoo.com
Summary of Skills and Experience
I am Hard core civil engineer of 49 years and have worked in best of civil engineering
projects at various location in India. During my more than 27 years of experience.
I have handled man and Material successfully. Many projects were completed in targeted
time under my leadership. My track record shows that work wise I have delivered to the
best of my ability and the satisfaction of my employers. My work record in handling man
and material stand testimony to my humble claim of my suitability to the post offered to
me.
I have completed Projects like :- ROADWORKS, PIPELINE WORKS, R.C.C. ROAD WORKS,
Infrastructures &
HYDROPROJECTS: -
(1) 192MW A.D.H.P.L. PRINI-MANALI (H.P.) By: LNJ Bhilwara
Group
(2) 330 MW Alaknanda SRINAGAR By: (GVK)
(3) 100 MW SORANG
H.E.P.JEORI (H.P.) By: (N.C.C.L.)
(4) Rangit Hydro Electric Projects (stage –IV ) 120 MW By: Coastal Projects
Ltd.
EXPERIENCE: 27 years
DETAILS OF EXPERIENCE:-
Diploma in civil engineering with more than 27 years experience
in Supervision, Project Execution & Quality control
Key Skills: Construction Management, Man and Material Management, timely project
completion, expertise in carrying out the works.
August-2015 onward to till date.
Employer : TUV Rheinland India Pvt.Ltd.
Project :- (100 MW) Orange Agar Wind Power Pvt.Ltd.
Client: Orange Agar Wind Power Pvt.Ltd. New Delhi
Scope of work :- Day to day monitoring of all ongoing works related
to quality & progress of work. Coordination with client & contractor &
attending all critical activities like Excavation, P.C.C., Concreting,
Levelling & Reinforcement of the WTG Foundation as per Drawings &
2. Specification. Review of all quality certificates & Witness of material
testing. Assist client during trouble shooting.
Witness for the concreting from making to placing
& Curing & Testing for compressive strength, witness for the gradation,
Review all concern documents for the steel &Cement. Witnesss for the
calibration of the Batching plants.
NOV-2014 To JUNE-2015
Employer: TUV Rheinland India Pvt.Ltd.
Project : 50.4 MW Wind Power Project Tejuva-Jaisalmer ( Rajasthan )
Client : OSTRO Energy
Scope of work: - Day to day monitoring of all ongoing works related
to quality & progress of work. Coordination with client & contractor &
attending all critical activities like Excavation, P.C.C., Concreting,
Levelling & Reinforcement of the WTG Foundation as per Drawings &
Specification. Review of all quality certificates & Witness of material
testing. Assist client during trouble shooting.
Witness for the concreting from making to placing
& Curing & Testing for compressive strength, witness for the gradation,
Review all concern documents for the steel &Cement. Witnesss for the
calibration of the Batching plants.
Maintaining all quality documents of cube testing, steel testing, Gradation
of coarse & Fine Aggregates, M.D.D. Test, Calibration reports.
MAY-2013 To Till Date :-
• Current Employer : TUV RHEINLAND INDIA PVT.LTD.
(German based company.)
Client :- Ahmedabad Municipal Corporation. Ahmedabad.
Scope of work: - Day to day monitoring of all ongoing works related
to quality & progress of work. Coordination with client & contractor &
attending all critical activities like Excavation, P.C.C., Concreting,
Levelling & Reinforcement of the WTG Foundation as per Drawings &
Specification. Review of all quality certificates & Witness of material
testing. Assist client during trouble shooting.
Witness for the concreting from making to placing
& Curing & Testing for compressive strength, witness for the gradation,
Review all concern documents for the steel &Cement. Witnesss for the
calibration of the Batching plants.
3. Maintaining all quality documents of cube testing, steel testing, Gradation
of coarse & Fine Aggregates, M.D.D. Test, Calibration reports.
• OCT-2012 TO MAY-2013 :
• Current Employer: TUV RHEINLAND INDIA PVT.LTD.
(German based company.)
• SITE: 50.4 MW WIND POWER PROJECT Tadas-karnataka.
•
• CLIENT: Renew power Ventures Pvt.Ltd.
• Contractor : M/S Enercon india ltd. (german based )
• JAN-2010 TO SEPT-2011
• FROM: 14.01.2010 TO: 28.09.12
• EMPLOYER: COASTAL PROJECTS LIMITED
• DESIGNATION : SR. DY. MANAGER (Q.C.)
• LOCATION: RANGIT H.E.PROJECT STAGE –IV (120MW) PIPALAY, VIA:
JORETHANG, DIST:GAYZING. WEST-SIKKIM.
• Glimpse about Project: - Project is successfully run by COASTAL PROJECTS LTD.
For the electricity generation for SIKKIM for 120 MW. In this project there is a
massive construction work regarding water storage, supply structures and Tunnel
work also. The Financing agencies achieve quality of work about construction with
the help of our team in this project. Here I am working AS A HEAD OF
QUALITY CONTROL DEPARTMENT. Here we have to prepare mix designs for
various structures concrete as well as of shot Crete. We provide concrete of
required quality with the help of more than 03 batching plants. Main work is to
provide quality control as well as makes daily testing regarding concrete and
tunnel work also. Here we have to make testing of materials like
aggregates, cement, steel, concrete, water stopper, Resin Capsules(Gels),
Wire crates, soil, rock bolts, diesel, etc. and make quality checks and
Monitoring & quality inspection.
• Salary Drawn: - RS. 1090695/- PER ANNUM
• APRIL-2010 TO DEC-2010
• FROM: 14.04.2010 TO: 29.12.2010.
• EMPLOYER: HIMACHAL SORANG POWER LTD. (N.C.C.L.)
• DESIGNATION : SR. ENGINEER (Q.C.)
• LOCATION : SORANG HYDRO ELECTRIC PROJECT 100MW
AT: DUMATI, POST: NIGULSARI, DISTT: KINNAUR (H.P.)
• Glimpse about Project: - Project (SORANG HYDRO ELECTRIC PROJECT ) Ltd.) is
successfully run by H.S.P..L. For the electricity generation for Himachal Pradesh
for 100 MW. In this project there is a massive construction work regarding water
storage, supply structures and Tunnel work also. The Financing agencies achieve
4. quality of work about construction with the help of our team in this project. Here
I am working AS A HEAD OF QUALITY CONTROL DEPARTMENT. Here we
have to prepare mix designs for various structures concrete as well as of shot
Crete. We provide concrete of required quality with the help of more than 03
batching plants. Main work is to provide quality control as well as makes daily
testing regarding concrete and tunnel work also. Here we have to make testing
of materials like aggregates, cement, steel, concrete, water stopper,
Resin Capsules(Gels), Wire crates, soil, rock bolts, diesel, etc. and make
quality checks and Monitoring third party quality inspection.
April 2006 to March 2010
(Duration: 04 Years.)
• Organization:-. S.G.S. India private Ltd (Swiss- Based ) Multinational
company)
• Position - Inspector Civil.
Job Profile: From 01.08.2009 to 31.03.2010
Looking after the project of O.N.G.C. TWO PIPELINE REPLACEMENT
PROJECT AHMEDABAD-MEHSANA ASSET. (Gujarat)
Glimpse about Project: - Oil and natural gas corporation limited (O.N.G.C.) is engaged
in exploitation of hydrocarbon in western onshore fields in the state of Gujarat of
western India. The field are well developed with the ageing of fields, condition of some
Of its existing pipelines has deteriorated. Company is planning for replacement of these
pipelines in phased manner.
Replacement of following 02 oil trunk pipe lines.
S.NO. Description Length (kms.)
1 KALOL CTF TO NAWAGAM CTF (12 inch dia.) 60.5
2 MEHSANA CTF TO NAWAGAM CTF (14 inch dia.) 77.5
The pipeline Route survey along with the soil investigation & soil resistivity has been
carried out by o.n.g.c and. Right of way and approval for Railway, Road, River Canal
crossing.
CONCRETE MIX: (1) PCC: M15
(2)RCC: M20 Conforming IS: 456
Client: L.N.J. Bhilwara and S.N.Power Norway joint venture.
• Location- Manali, H.P.
• Name of Project: A.D.Hydro.Power Project (192MW) Prini, Manali
Nature of job
From july-2007 to july-2009 looking after the project of Hydro power project at
Manali, named A.D. Hydro Power Ltd. The joint venture of LNJ Bhilwara group and S.N.
Power, Norway.
5. 1. Glimpse about Project: - Project (A.D.Hydroc Power Project Ltd.) is
successfully run by LNJ Group Bhilwara and SN Power Norway joint venture.
For the electricity generation for Himachal Pradesh for 192 MW (2*96). In this
project there is a massive construction work regarding water storage, supply
structures and Tunnel work also. The Financing agencies achieve quality of
work about construction with the help of our kind institute in this project. Here
I am working as a Team-leader of Q.C.engineers. Here we have to
prepare mix designs for various structures concrete as well as of shotcrete. We
provide concrete of required quality with the help of more than SIX batching
plants. Up to today we furnish more than 1, 50, 000 m3
concrete. Main work
is to provide quality control as well as makes daily testing regarding concrete
and tunnel work also. Here we have to make testing of materials like
aggregates, cement, steel, concrete, water stopper, Resin
Capsules(Gels), Wire crates, soil, rock bolts, diesel, etc. and make
quality checks and third party quality inspection.
APR-2006 TO JULY-2007
Client: G.W.R.D.C.L. (Kadi)
• Location- Kadi, Mehsana (Gujarat)
• Name of Project: Andudara to Kherwa Pipe line Project.- (Dia.-2150mm )
Nature of job
1. Formation level and Bed level Checking.
2. Witness for concreting works.
3. Checking and certified pump house as per drawing and specification.
Aug. 2003 to March 2006
Duration: 02 Years and 06 Months
• Organization:-. Desai Engineers and contractors Ahmadabad
• Position- Sr. ENGINEER
• Location- Adani-Port (Navinal-island )Mundra Distt- Kutchh, GUJARAT.
Nature of job
1. RCC Road works.
2. Drainage works
May 2000 to July 2003
Duration: 03 Years and 02 Months
• Organization:-. SHIVAM CONSTRUCTION COMPANY
• Position- Sr. ENGINEER
• Location- MEHSANA. GUJARAT
Nature of job
1. Excavation work for 400 KV sub station at Kansari-Deesa(B.K.)
2. Building constructions works.
3. RCC and Matte ling Road works.
4. PVC pipeline works.
5. Colours works
6. Jan. 1996 to April. 2000
Duration: 04 Years and 03 Months.
• Organization:-M/S LALIT.K.MAKWANA. (ENGINEERS & GOVT.APPROVED
CONTRACTOR).
• Position- Sr. ENGINEER
• Location- MEHSANA. GUJARAT
Nature of job
1 Building constructions works.
2 RCC and Asphalt Road works.
3 PVC pipeline works.
4 Colours works
May 1988 to Dec. 1995
Duration: 07 Year, 07 month.
• Organization:- M/S RAJENDRASINH R CHAVDA. (ENGINEERA & GOVT.APPROVED
CONTRACTOR) AT-HIMATNAGAR. DIST-SABARKANTHA. GUJARAT
• Position- SITE ENGINEER
• Location-Prantij, Himatnagar District sabar Kantha (Gujrat)
Nature of job
1. Building constructions works.
2. RCC and Asphalt Road works.
3. PVC pipeline works.
4. Colours works
Education Qualification:
Diploma in civil engineering from B. & B. POLYTECHNIC, Vallabh-
Vidhyanagar. (Dist. Kheda) Gujarat in 1988
STANDARD NAME OF
BOARD/UNI.
SP.
SUBJECT
YEAR
OF
PASSING
DIVISION PERCENTAGE
OF MARKS
OBTAINED
S.S.C H.S.E.B. GUJ. Science 1982 FIRST 63.3 %
D.C.E. TECHNICAL
EXAM
BOARD
G’NAGAR
CIVIL 1988 SECOND 56.6 %
Other Qualification(s)/ Certification(s)/ Programme(s) Attended
I get best Cadet Certificate and “C” Certificate in NCC.
PERSONL DETAILS:-
7. • Date of Birth : 21.10.1966.
• Fathers Name : Late M.A.NIRALA
• Marital Status : Married.
• Nationality : Indian.
• Gender : Male.
Permanent Address: A-101, Devnandan Sky, Opp–Dhanvihar Residency,
off New C.G.Road, Chankheda, Ahmedabad, Gujarat, India. Pin code:
382424.
REFERENCES: - Will be given as required.
Expected Salary: - As per rules and regulations.
OVER AND ABOVE
» I KNOW COMPUTERS FUNDAMENTS.
JYOTINDRA NIRALA
AHMEDABAD.
07.09.2015.