SlideShare a Scribd company logo
1 of 47
Material Source: Lean Enterprise Institute
1
Value Stream Mapping
Material Source: Lean Enterprise Institute
2
Learning to See
A Value Stream Mapping Workshop
Purpose:
1. Introduce value stream mapping in a hands-on
manner.
2. Develop your ability to “see the flow” and design
future state value streams.
Material Source: Lean Enterprise Institute
3
stamping welding assembly
Value Stream Mapping
• Helps you visualize more than the single process level
• Links the material and information flows
• Provides a common language
• Provides a blueprint for implementation
• More useful than quantitative tools
• Ties together lean concepts and techniques
Material Source: Lean Enterprise Institute
4
Material Source: Lean Enterprise Institute
5
Value Stream Mapping
A) Follow a product’s production path from beginning to
end, and draw a visual representation of every process
in the material & information flows.
B) Then draw (using icons) a “future state” map of how
value should flow
Material Source: Lean Enterprise Institute
6
Material Source: Lean Enterprise Institute
7
Waste
Things to Remember about Waste
• Waste is really a symptom rather than a root cause of the
problem
• Waste points to problems within the system (at both process
and value-stream levels)
• We need to find the address causes of waste
• The elements of production that add no value to the product
• Waste only adds cost and time
Material Source: Lean Enterprise Institute
8
Overproduction
= Making more than is required by the next process
= Making earlier than is required by the next process
= Making faster than is required by the next process
Material Source: Lean Enterprise Institute
9
Individual Efficiency vs. System Efficiency
How fast should we produce ?
Material Source: Lean Enterprise Institute
10
Understanding how the shop floor
currently operates. The foundation
for the future state.
Designing a lean flow.
Using the Value Stream Mapping Tool
product family
current state
drawing
future state
drawing
plan and
implementation
Material Source: Lean Enterprise Institute
11
Focus on one product family
Determine Product Families via:
Similar downstream “assembly” steps and equipment
Process Steps & Equipment
Spot
Weld
Robot
Weld
Flash
Remove
Paint
Manual
Assm.
Fixtures
Assm.
Electronic
Test
LH Steering
Bracket X X X X
RH Steering
Bracket X X X X
Instrument
Panel Brace X X X
Seat Rail X X
Bumper
Brackets X X X
PRODUCTS
Material Source: Lean Enterprise Institute
12
across companies
multiple plants
process level
single plant
(door to door)
begin here
Levels of a Value Stream
Material Source: Lean Enterprise Institute
13
Material Source: Lean Enterprise Institute
14
Current State Drawing
Understanding how the shop floor
currently operates
 Material and Information flows
 Draw using icons
 Start with the “door to door” flow
 Have to walk the flow and get actuals
– No standard times
– Draw by hand, with pencil
 Foundation for the Future State
product family
current state
drawing
future state
drawing
plan and
implementation
Material Source: Lean Enterprise Institute
15
“ACME Stamping” Data Set
Acme Stamping Company produces several components for vehicle assembly plants.
This case concerns one product family: a steel instrument-panel bracket subassembly
in two types: one each for left-hand and right-hand drive versions of the same
automobile model. These components are sent to the State Street Vehicle Assembly
Plant (the customer).
CUSTOMER REQUIREMENTS :
• 18,400 pieces per month
12,000 per month of Type “LH”
6,400 per month of Type “RH”
• Customer plant operates on two shifts
• Palletized returnable tray packaging with 20 brackets in a tray and up to 10 trays
on a pallet. The customer orders in multiples of trays.
• One daily shipment to the assembly plant by truck
WORK TIME :
• 20 days in a month
• Two shift operation in all production departments
• Eight (8) hours every shift, with overtime if necessary
• Two 10-minute breaks during each shift
Manual processes stop during breaks
Unpaid lunch
Material Source: Lean Enterprise Institute
16
“ACME Stamping” Data Set (continued)
PRODUCTION PROCESSES :
• Acme’s process for this product family involves stamping a metal part followed by
welding and subsequent assembly. The components are then staged & shipped to
the vehicle assembly plant on a daily basis.
• Switching between Type “LH” (left-hand drive) and Type “RH” (right-hand drive)
brackets requires 1 hour changeover in stamping and 10-minute fixture change in
the welding processes.
• Steel coils are supplied by Michigan Steel Co.
Deliveries are made to Acme on Tuesdays and Thursdays.
ACME PRODUCTION CONTROL DEPARTMENT :
• Receives State Street’s 90/60/30-day forecasts and enters them to MRP
• Issues Acme 6-week forecast to Michigan Steel Co. via MRP
• Secures coil steel by weekly faxed order release to Michigan Steel Co.
• Receives daily firm order from State Street
• Generates MRP-based weekly departmental requirements based upon customer
order, WIP inventory levels, F/G inventory levels, and anticipated scrap and
downtime
• Issues weekly build schedules to Stamping, Welding, and Assembly processes
• Issues daily shipping schedule to Shipping Department
Material Source: Lean Enterprise Institute
17
“ACME Stamping” Data Set (continued)
PROCESS INFORMATION :
All processes occur in the following order and each piece goes through all processes.
1) STAMPING
(The press makes parts for many Acme products)
• Automated 200 Ton press with coil (automatic material feed)
• Cycle Time: 1 second (60 pieces per minute)
• Changeover time: 1 hour (good piece to good piece)
• Machine reliability: 85%
• Observed Inventory:
5 days of coils before stamping
4,600 pieces of Type “LH” finished stampings
2,400 pieces of Type “RH” finished stampings
2) SPOT-WELD WORKSTATION I
(dedicated to this product family)
• Manual process with one operator
• Cycle Time: 39 seconds
• Changeover time: 10 minutes (fixture change)
• Reliability: 100%
• Observed Inventory:
1,100 pieces of Type “LH”
600 pieces of Type “RH”
3) SPOT-WELD WORKSTATION II
(dedicated to this product family)
• Manual process with one operator
• Cycle Time: 46 seconds
• Changeover time: 10 minutes (fixture change)
• Reliability: 80%
• Observed Inventory:
1,600 pieces of Type “LH”
850 pieces of Type “RH”
4) ASSEMBLY WORKSTATION I
(dedicated to this product family)
• Manual process with one operator
• Cycle Time: 62 seconds
• Changeover time: none
• Reliability: 100%
• Observed inventory:
1,200 pieces of Type “LH”
640 pieces of Type “RH”
5) ASSEMBLY WORKSTATION II
(dedicated to this product family)
• Manual process with one operator
• Cycle Time: 40 seconds
• Changeover time: none
• Reliability: 100%
• Observed Finished-Goods Inventory in
Warehouse:
2,700 pieces of Type “LH”
1,440 pieces of Type “RH”
6) SHIPPING DEPARTMENT
Removes parts from finished goods warehouse
and stages them for truck shipment to customer
Material Source: Lean Enterprise Institute
18
Develop the Current State Map
Material Source: Lean Enterprise Institute
19
Current State Map : Icons
MATERIAL FLOW ICONS
XYZ
Corporation
Outside Sources
ASSEMBLY
Manufacturing
Process
C/T = 45 sec.
C/O = 30 min
3 Shifts
2% Scrap
Data Box
300 pieces
1 Day
Inventory
Truck Shipment
Mon.
+ Wed.
PUSH
Arrow
Finished Goods
To Customer
First-In-First-Out
Sequence Flow
Max. 20 pieces
FIFO
Buffer or
Safety Stock
Operator
Manual
Information Flow
Electronic
Information Flow
Schedule
Weekly Schedule
Load Leveling
INFORMATION FLOW ICONS
GENERAL ICONS
Material Source: Lean Enterprise Institute
20
Material Source: Lean Enterprise Institute
21
Future State Drawing
Designing a Lean Flow
• The power behind Value Stream Mapping is you
always need a future state !
• 70% & Keep Updating. Use pencil !
• Material & Information flows
• Basis for your Work Plan – like a “blueprint”
• Begin by drawing on Current State
• 1st iteration assumes existing steps & equipment
Can move equipment, combine, take out
conveyors, make minor purchases, etc.
product family
current state
drawing
future state
drawing
plan and
implementation
But there is a Problem!
Material Source: Lean Enterprise Institute
22
Notice that on this future-state map the four welding
and assembly process boxes have been combined into
one process box to indicate the continuous flow. A
small schematic sketch of a cell inside the process box
also indicates the cellular manufacturing idea.
First View of the Future-State Map
Showing Takt Time, Weld/Assembly
Cell, and the Finished-Goods
Supermarket
Building the Future State Map :
Stage
Material Source: Lean Enterprise Institute
23
Material Source: Lean Enterprise Institute
24
Key Questions for the Future State
1. What is the takt time, based on the available working time of your downstream processes that
are closest to the customer?
2. Will you build to a finished goods supermarket from which the customer pulls, or directly to
shipping? (The answer to this question depends on several factors such as customer buying
patterns, the reliability of your processes, and the characteristics of your product. Building
directly to shipping will require either a reliable, short-lead-time, order-to-delivery lead time
involves only those processes from the pacemaker process downstream to delivery.)
3. Where can you use continuous flow processing?
4. Where will you need to use supermarket pull systems in order to control production of
upstream process?
5. At what single point in the production chain (the “pacemaker process”) will you schedule
production? (Remember that all material transfers downstream of the pacemaker process
need to occur as a flow.)
6. How will you level the production mix at the pacemaker process?
7. What increment of work will you consistently release and take away at the pacemaker
process?
8. What process improvements will be necessary for the value stream to flow as your future-
state design specifies? (This is the place to note any equipment and procedural improvements
that will be necessary, such as reducing changeover time or improving machine uptime. We
use the kaizen lightning burst icon to indicate these points in the process.)
Material Source: Lean Enterprise Institute
25
Produce to your Takt Time
Takt time synchronizes pace of production to match pace of sales.
Takt Time =
Available Work Time / Shift
Customer Demand Rate / Shift
Calculate Takt Time for ACME
Answer :
Available work time = 28,800 – 1200 = 27,600 seconds/shift
Customer demand = 640 units per shift
Takt Time = 60 seconds
Takt Time is like ‘Asking Rate’
Material Source: Lean Enterprise Institute
26
TAKT Time
Synchronizes pace of assembly to match pace of sales.
Rate for assembling a product based on sales rate.
Effective Working Time per Shift
Takt Time =
Customer Requirement per Shift
27,000 sec
= 59 sec
460 pieces
Material Source: Lean Enterprise Institute
27
Should Acme build steering brackets to a finished goods
supermarket or directly ship?
To move towards ‘Produce to Shipping’, ship from a supermarket
There are two varieties “RH” & “LH”
Since Customer requirement is in multiples of 20-bracket trays, this is the choice
for KANBAN size.
When we ship a tray of 20 brackets, a KANBAN to demand shipping to replenish
20 brackets from PRODUCTION is issued.
KANBAN
ASSEMBLY
LH
RH
Shipping
Customer
Customer
Requirement
Material Source: Lean Enterprise Institute
28
Material Source: Lean Enterprise Institute
29
Material Source: Lean Enterprise Institute
30
Where can ACME
introduce continuous flow?
BEFORE AFTER
Acme Stamping
current cycle times
Acme Stamping
weld/assembly cell cycle times
after process kaizen
Takt time
60
seconds
Takt time
60
seconds
Material Source: Lean Enterprise Institute
31
Problem Points in the Flow
Where One-Piece Flow Ends
How can we control production between flows ?
MRP-based schedules ?
Stamping Welding Assembly
customer
Material Source: Lean Enterprise Institute
32
Material Source: Lean Enterprise Institute
33
Where will ACME need to use
supermarket pull system?
1. Difference in C/T of Stamping machine and other machines is high. Ideally we need a
‘smaller’ Stamping machine. Let us adopt a supermarket.
2. Stamping machine produces at the rate of 60 Stampings / hour. Let us adopt that as the
KANBAN quantity.
3. Design a supermarket between stamping and weld cum assembly station to withdraw 60
Stampings at a time.
4. Improve changeover time on Stamping machine so that quick changeover allows making LH
and RH pieces for one hour each and keep switching every hour.
5. Until we reduce the change over time, let us make a super market having 15 days of parts to
provide for replenishment delays and some quality & breakdown problems.
Material Source: Lean Enterprise Institute
34
What should be the frequency to receive coils
(raw material)?
1. Move to once a day supplies to reduce inventory by 80%.
2. Keep inventory only for 2 days.
Coils
Stamped
Parts
Weld/Assy
WIP
Finished
Good
Production
Lead Time
Total
Inventory
Turns
5 Days 7.6 Days 6.5 Days 4.5 Days 23.6 Days 10
2 Days 1.5 Days 4.5 Days 8 Days 30After
Before
Acme Stamping Lead Time Improvement
Material Source: Lean Enterprise Institute
35
Material Source: Lean Enterprise Institute
36
What single point in the production chain
(the pacemaker process) should ACME Schedule?
Since all process steps downstream of the pacemaker process need to
occur in flow, in ACME, the scheduling point should be the welding /
assembly cell.
Material Source: Lean Enterprise Institute
37
Material Source: Lean Enterprise Institute
38
Paced Withdrawal at the Pacemaker
• What amount of work do you schedule and take away at the
pacemaker?
• This amount = your management time frame.
(How often do you know your performance to customer demand?)
• Are you providing takt image ?
1 Week
1 Day
1 Shift
1 Hour
1 Pitch
1 Takt
?
Material Source: Lean Enterprise Institute
39
What process improvements will be necessary for Acme’s value
stream to flow as the future-state design describes?
Achieving the material and information flows we envision for Acme Stamping requires
the following process improvements:
 Reduction in changeover time and batch sizes at the stamping press, to allow
faster response to downstream usage. The goals are “ every part every day” and
then “ every part every shift”.
 Elimination of the time (10 minutes) required to change between left-drive and
right fixtures in welding, to make possible continuous flow and mixed production
from welding through assembly.
 Improvement in on-demand uptime of the second spot-weld machine, as it will
now be tied to other processes in a continuous flow.
 Elimination of waste in the weld/assembly cell, to reduce total work content down
to 168 seconds or less. (Which allows use of 3 operators at the current demand
level.
We mark these items on our future-state map with the kaizen lightening burst icon.
Material Source: Lean Enterprise Institute
40
AIM:
To bring cycle time at each work station lower than takt time.
How:
Identify KAIZENS’ that would help in this direction.
How Much:
1. Total time for welding and assembly work (39 + 46 + 62 + 40) = 187 seconds
2. Divide by takt time (60s) to get 3.12 operator requirement
3. Plan for Kaizens to reduce 4 work stations to 3 manned by 3 operators with
each station operating with cycle time less than takt time (60 seconds)
KAIZENS REQUIRED:
1. Total work < 168 seconds.
2. Weld changeover time reduction
3. Welder uptime increase.
KAIZEN
BURST
Material Source: Lean Enterprise Institute
41
Future State Map : Material and Information Flow
Material Source: Lean Enterprise Institute
42
Implementation
A Plan to Get There
• Don’t Wait !
• To “manage the exceptions” you need a plan!
1. Tie it to business objectives.
2. Break your future state into “loops”.
3. Make a VS Plan: What to do by when.
4. Now relate the FS Map to your layout.
5. VS Manager completes VS Review from in advance.
6. Conduct VS Reviews walking the flow.
Material Source: Lean Enterprise Institute
43
Material Source: Lean Enterprise Institute
44
Material Source: Lean Enterprise Institute
45
Material Source: Lean Enterprise Institute
46
Material Source: Lean Enterprise Institute
47

More Related Content

What's hot

Identify 7 Wastes
Identify 7 WastesIdentify 7 Wastes
Identify 7 WastesLean for U
 
Value stream mapping
Value stream mappingValue stream mapping
Value stream mappingShaunak Kale
 
Unit iv Shop floor control and FMS
Unit iv Shop floor control and FMSUnit iv Shop floor control and FMS
Unit iv Shop floor control and FMSmanimaran m
 
2006 pfmea presentation
2006 pfmea presentation2006 pfmea presentation
2006 pfmea presentationilker kayar
 
Lean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training ModuleLean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training ModuleFrank-G. Adler
 
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSMSedhuSiddarth
 
Value stream mapping study with example
Value stream mapping study with exampleValue stream mapping study with example
Value stream mapping study with exampleMouhcine Nahal
 
Pull system of manufacturing
Pull system of manufacturingPull system of manufacturing
Pull system of manufacturingMohit Singla
 
460 operations - 4.20
460   operations - 4.20460   operations - 4.20
460 operations - 4.20Kyle Bakken
 
Lean manufacturing basics
Lean manufacturing basicsLean manufacturing basics
Lean manufacturing basicssarah bridge
 
Value Stream Mapping Process
Value Stream Mapping ProcessValue Stream Mapping Process
Value Stream Mapping ProcessAnand Subramaniam
 
Value Stream Mapping Overview Update
Value Stream Mapping Overview UpdateValue Stream Mapping Overview Update
Value Stream Mapping Overview Updatejheaton418
 
value stream mapping
value stream mappingvalue stream mapping
value stream mappingJitesh Gaurav
 

What's hot (20)

Lean Manufacturing
Lean ManufacturingLean Manufacturing
Lean Manufacturing
 
Identify 7 Wastes
Identify 7 WastesIdentify 7 Wastes
Identify 7 Wastes
 
Value stream mapping
Value stream mappingValue stream mapping
Value stream mapping
 
Unit iv Shop floor control and FMS
Unit iv Shop floor control and FMSUnit iv Shop floor control and FMS
Unit iv Shop floor control and FMS
 
2006 pfmea presentation
2006 pfmea presentation2006 pfmea presentation
2006 pfmea presentation
 
Downtime 8 Wastes
Downtime 8 WastesDowntime 8 Wastes
Downtime 8 Wastes
 
Lean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training ModuleLean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training Module
 
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
 
VSM – Current & Future
VSM – Current & FutureVSM – Current & Future
VSM – Current & Future
 
Value stream mapping study with example
Value stream mapping study with exampleValue stream mapping study with example
Value stream mapping study with example
 
Pull system of manufacturing
Pull system of manufacturingPull system of manufacturing
Pull system of manufacturing
 
460 operations - 4.20
460   operations - 4.20460   operations - 4.20
460 operations - 4.20
 
Lean manufacturing basics
Lean manufacturing basicsLean manufacturing basics
Lean manufacturing basics
 
Fmea handout
Fmea handoutFmea handout
Fmea handout
 
Value stream mapping
Value stream mappingValue stream mapping
Value stream mapping
 
Value Stream Mapping Process
Value Stream Mapping ProcessValue Stream Mapping Process
Value Stream Mapping Process
 
Lean section 2
Lean section 2Lean section 2
Lean section 2
 
Lean Process Improvement Techniques
Lean Process Improvement TechniquesLean Process Improvement Techniques
Lean Process Improvement Techniques
 
Value Stream Mapping Overview Update
Value Stream Mapping Overview UpdateValue Stream Mapping Overview Update
Value Stream Mapping Overview Update
 
value stream mapping
value stream mappingvalue stream mapping
value stream mapping
 

Similar to VSM Workshop Teaches Lean Process Flow Design

Value stream mapping (1)
Value stream mapping (1)Value stream mapping (1)
Value stream mapping (1)jmachado33
 
AUTOMATE 2015 - Is Automation Right for Your Company - Craig Salvalaggio 3-2015
AUTOMATE 2015 - Is Automation Right for Your Company - Craig Salvalaggio 3-2015AUTOMATE 2015 - Is Automation Right for Your Company - Craig Salvalaggio 3-2015
AUTOMATE 2015 - Is Automation Right for Your Company - Craig Salvalaggio 3-2015Craig Salvalaggio
 
MFG4 2016 - Is Automation Right for Your Company - 4-2016
MFG4 2016 -  Is Automation Right for Your Company - 4-2016MFG4 2016 -  Is Automation Right for Your Company - 4-2016
MFG4 2016 - Is Automation Right for Your Company - 4-2016Craig Salvalaggio
 
Effective Microservices In a Data-centric World
Effective Microservices In a Data-centric WorldEffective Microservices In a Data-centric World
Effective Microservices In a Data-centric WorldRandy Shoup
 
eeMba ii pmom_unit-3.2 modern pm tools a
eeMba ii pmom_unit-3.2 modern pm tools aeeMba ii pmom_unit-3.2 modern pm tools a
eeMba ii pmom_unit-3.2 modern pm tools aRai University
 
Ch12 jit+&+lean+systems
Ch12 jit+&+lean+systemsCh12 jit+&+lean+systems
Ch12 jit+&+lean+systemsvideoaakash15
 
Project Management (Practical Qustion Paper) [CBSGS - 75:25 Pattern] {2013-20...
Project Management (Practical Qustion Paper) [CBSGS - 75:25 Pattern] {2013-20...Project Management (Practical Qustion Paper) [CBSGS - 75:25 Pattern] {2013-20...
Project Management (Practical Qustion Paper) [CBSGS - 75:25 Pattern] {2013-20...Mumbai B.Sc.IT Study
 
ThoughtWorks Continuous Delivery
ThoughtWorks Continuous DeliveryThoughtWorks Continuous Delivery
ThoughtWorks Continuous DeliveryKyle Hodgson
 
Scaling Your Architecture for the Long Term
Scaling Your Architecture for the Long TermScaling Your Architecture for the Long Term
Scaling Your Architecture for the Long TermRandy Shoup
 
Job order costing and Process costing
Job order costing and Process costingJob order costing and Process costing
Job order costing and Process costingHurriya Saeed rana
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturingJitesh Gaurav
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturingJitesh Gaurav
 

Similar to VSM Workshop Teaches Lean Process Flow Design (20)

VSM (Méthode HOSHIN)
VSM (Méthode HOSHIN)VSM (Méthode HOSHIN)
VSM (Méthode HOSHIN)
 
Vsm 8 que_future
Vsm 8 que_futureVsm 8 que_future
Vsm 8 que_future
 
Vsm 8 que_future
Vsm 8 que_futureVsm 8 que_future
Vsm 8 que_future
 
Value stream mapping (1)
Value stream mapping (1)Value stream mapping (1)
Value stream mapping (1)
 
AUTOMATE 2015 - Is Automation Right for Your Company - Craig Salvalaggio 3-2015
AUTOMATE 2015 - Is Automation Right for Your Company - Craig Salvalaggio 3-2015AUTOMATE 2015 - Is Automation Right for Your Company - Craig Salvalaggio 3-2015
AUTOMATE 2015 - Is Automation Right for Your Company - Craig Salvalaggio 3-2015
 
MFG4 2016 - Is Automation Right for Your Company - 4-2016
MFG4 2016 -  Is Automation Right for Your Company - 4-2016MFG4 2016 -  Is Automation Right for Your Company - 4-2016
MFG4 2016 - Is Automation Right for Your Company - 4-2016
 
Effective Microservices In a Data-centric World
Effective Microservices In a Data-centric WorldEffective Microservices In a Data-centric World
Effective Microservices In a Data-centric World
 
eeMba ii pmom_unit-3.2 modern pm tools a
eeMba ii pmom_unit-3.2 modern pm tools aeeMba ii pmom_unit-3.2 modern pm tools a
eeMba ii pmom_unit-3.2 modern pm tools a
 
Ch12 jit+&+lean+systems
Ch12 jit+&+lean+systemsCh12 jit+&+lean+systems
Ch12 jit+&+lean+systems
 
UNIT VI-3.pptx
UNIT VI-3.pptxUNIT VI-3.pptx
UNIT VI-3.pptx
 
Project Management (Practical Qustion Paper) [CBSGS - 75:25 Pattern] {2013-20...
Project Management (Practical Qustion Paper) [CBSGS - 75:25 Pattern] {2013-20...Project Management (Practical Qustion Paper) [CBSGS - 75:25 Pattern] {2013-20...
Project Management (Practical Qustion Paper) [CBSGS - 75:25 Pattern] {2013-20...
 
ThoughtWorks Continuous Delivery
ThoughtWorks Continuous DeliveryThoughtWorks Continuous Delivery
ThoughtWorks Continuous Delivery
 
Scaling Your Architecture for the Long Term
Scaling Your Architecture for the Long TermScaling Your Architecture for the Long Term
Scaling Your Architecture for the Long Term
 
Job order costing and Process costing
Job order costing and Process costingJob order costing and Process costing
Job order costing and Process costing
 
Value_Streams.ppt
Value_Streams.pptValue_Streams.ppt
Value_Streams.ppt
 
Chapter 7.pptx
Chapter 7.pptxChapter 7.pptx
Chapter 7.pptx
 
Building a Lean Business System
Building a Lean Business SystemBuilding a Lean Business System
Building a Lean Business System
 
Manufacturing systems
Manufacturing systems Manufacturing systems
Manufacturing systems
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
 

More from Jitesh Gaurav (20)

What i es do iie iab v2
What i es do iie iab v2What i es do iie iab v2
What i es do iie iab v2
 
Weld material
Weld materialWeld material
Weld material
 
Six sigma
Six sigmaSix sigma
Six sigma
 
Spi link
Spi linkSpi link
Spi link
 
6 Sigma - Chapter3
6 Sigma - Chapter36 Sigma - Chapter3
6 Sigma - Chapter3
 
6 Sigma - Chapter2
6 Sigma - Chapter26 Sigma - Chapter2
6 Sigma - Chapter2
 
6 Sigma - Chapter1
6 Sigma - Chapter16 Sigma - Chapter1
6 Sigma - Chapter1
 
6 Sigma - Chapter8
6 Sigma - Chapter86 Sigma - Chapter8
6 Sigma - Chapter8
 
6 Sigma - Chapter7
6 Sigma - Chapter76 Sigma - Chapter7
6 Sigma - Chapter7
 
6 Sigma - Chapter6
6 Sigma - Chapter66 Sigma - Chapter6
6 Sigma - Chapter6
 
6 Sigma - Chapter5
6 Sigma - Chapter56 Sigma - Chapter5
6 Sigma - Chapter5
 
6 Sigma - Chapter4
6 Sigma - Chapter46 Sigma - Chapter4
6 Sigma - Chapter4
 
Pattern production
Pattern productionPattern production
Pattern production
 
smed
smedsmed
smed
 
Methods of kaizen
Methods of kaizenMethods of kaizen
Methods of kaizen
 
Dfmea rating
Dfmea ratingDfmea rating
Dfmea rating
 
Qip
QipQip
Qip
 
Rodebaugh sixsigma[1]
Rodebaugh sixsigma[1]Rodebaugh sixsigma[1]
Rodebaugh sixsigma[1]
 
Tqm
TqmTqm
Tqm
 
Tpm+basics
Tpm+basicsTpm+basics
Tpm+basics
 

Recently uploaded

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 

VSM Workshop Teaches Lean Process Flow Design

  • 1. Material Source: Lean Enterprise Institute 1 Value Stream Mapping
  • 2. Material Source: Lean Enterprise Institute 2 Learning to See A Value Stream Mapping Workshop Purpose: 1. Introduce value stream mapping in a hands-on manner. 2. Develop your ability to “see the flow” and design future state value streams.
  • 3. Material Source: Lean Enterprise Institute 3 stamping welding assembly Value Stream Mapping • Helps you visualize more than the single process level • Links the material and information flows • Provides a common language • Provides a blueprint for implementation • More useful than quantitative tools • Ties together lean concepts and techniques
  • 4. Material Source: Lean Enterprise Institute 4
  • 5. Material Source: Lean Enterprise Institute 5 Value Stream Mapping A) Follow a product’s production path from beginning to end, and draw a visual representation of every process in the material & information flows. B) Then draw (using icons) a “future state” map of how value should flow
  • 6. Material Source: Lean Enterprise Institute 6
  • 7. Material Source: Lean Enterprise Institute 7 Waste Things to Remember about Waste • Waste is really a symptom rather than a root cause of the problem • Waste points to problems within the system (at both process and value-stream levels) • We need to find the address causes of waste • The elements of production that add no value to the product • Waste only adds cost and time
  • 8. Material Source: Lean Enterprise Institute 8 Overproduction = Making more than is required by the next process = Making earlier than is required by the next process = Making faster than is required by the next process
  • 9. Material Source: Lean Enterprise Institute 9 Individual Efficiency vs. System Efficiency How fast should we produce ?
  • 10. Material Source: Lean Enterprise Institute 10 Understanding how the shop floor currently operates. The foundation for the future state. Designing a lean flow. Using the Value Stream Mapping Tool product family current state drawing future state drawing plan and implementation
  • 11. Material Source: Lean Enterprise Institute 11 Focus on one product family Determine Product Families via: Similar downstream “assembly” steps and equipment Process Steps & Equipment Spot Weld Robot Weld Flash Remove Paint Manual Assm. Fixtures Assm. Electronic Test LH Steering Bracket X X X X RH Steering Bracket X X X X Instrument Panel Brace X X X Seat Rail X X Bumper Brackets X X X PRODUCTS
  • 12. Material Source: Lean Enterprise Institute 12 across companies multiple plants process level single plant (door to door) begin here Levels of a Value Stream
  • 13. Material Source: Lean Enterprise Institute 13
  • 14. Material Source: Lean Enterprise Institute 14 Current State Drawing Understanding how the shop floor currently operates  Material and Information flows  Draw using icons  Start with the “door to door” flow  Have to walk the flow and get actuals – No standard times – Draw by hand, with pencil  Foundation for the Future State product family current state drawing future state drawing plan and implementation
  • 15. Material Source: Lean Enterprise Institute 15 “ACME Stamping” Data Set Acme Stamping Company produces several components for vehicle assembly plants. This case concerns one product family: a steel instrument-panel bracket subassembly in two types: one each for left-hand and right-hand drive versions of the same automobile model. These components are sent to the State Street Vehicle Assembly Plant (the customer). CUSTOMER REQUIREMENTS : • 18,400 pieces per month 12,000 per month of Type “LH” 6,400 per month of Type “RH” • Customer plant operates on two shifts • Palletized returnable tray packaging with 20 brackets in a tray and up to 10 trays on a pallet. The customer orders in multiples of trays. • One daily shipment to the assembly plant by truck WORK TIME : • 20 days in a month • Two shift operation in all production departments • Eight (8) hours every shift, with overtime if necessary • Two 10-minute breaks during each shift Manual processes stop during breaks Unpaid lunch
  • 16. Material Source: Lean Enterprise Institute 16 “ACME Stamping” Data Set (continued) PRODUCTION PROCESSES : • Acme’s process for this product family involves stamping a metal part followed by welding and subsequent assembly. The components are then staged & shipped to the vehicle assembly plant on a daily basis. • Switching between Type “LH” (left-hand drive) and Type “RH” (right-hand drive) brackets requires 1 hour changeover in stamping and 10-minute fixture change in the welding processes. • Steel coils are supplied by Michigan Steel Co. Deliveries are made to Acme on Tuesdays and Thursdays. ACME PRODUCTION CONTROL DEPARTMENT : • Receives State Street’s 90/60/30-day forecasts and enters them to MRP • Issues Acme 6-week forecast to Michigan Steel Co. via MRP • Secures coil steel by weekly faxed order release to Michigan Steel Co. • Receives daily firm order from State Street • Generates MRP-based weekly departmental requirements based upon customer order, WIP inventory levels, F/G inventory levels, and anticipated scrap and downtime • Issues weekly build schedules to Stamping, Welding, and Assembly processes • Issues daily shipping schedule to Shipping Department
  • 17. Material Source: Lean Enterprise Institute 17 “ACME Stamping” Data Set (continued) PROCESS INFORMATION : All processes occur in the following order and each piece goes through all processes. 1) STAMPING (The press makes parts for many Acme products) • Automated 200 Ton press with coil (automatic material feed) • Cycle Time: 1 second (60 pieces per minute) • Changeover time: 1 hour (good piece to good piece) • Machine reliability: 85% • Observed Inventory: 5 days of coils before stamping 4,600 pieces of Type “LH” finished stampings 2,400 pieces of Type “RH” finished stampings 2) SPOT-WELD WORKSTATION I (dedicated to this product family) • Manual process with one operator • Cycle Time: 39 seconds • Changeover time: 10 minutes (fixture change) • Reliability: 100% • Observed Inventory: 1,100 pieces of Type “LH” 600 pieces of Type “RH” 3) SPOT-WELD WORKSTATION II (dedicated to this product family) • Manual process with one operator • Cycle Time: 46 seconds • Changeover time: 10 minutes (fixture change) • Reliability: 80% • Observed Inventory: 1,600 pieces of Type “LH” 850 pieces of Type “RH” 4) ASSEMBLY WORKSTATION I (dedicated to this product family) • Manual process with one operator • Cycle Time: 62 seconds • Changeover time: none • Reliability: 100% • Observed inventory: 1,200 pieces of Type “LH” 640 pieces of Type “RH” 5) ASSEMBLY WORKSTATION II (dedicated to this product family) • Manual process with one operator • Cycle Time: 40 seconds • Changeover time: none • Reliability: 100% • Observed Finished-Goods Inventory in Warehouse: 2,700 pieces of Type “LH” 1,440 pieces of Type “RH” 6) SHIPPING DEPARTMENT Removes parts from finished goods warehouse and stages them for truck shipment to customer
  • 18. Material Source: Lean Enterprise Institute 18 Develop the Current State Map
  • 19. Material Source: Lean Enterprise Institute 19 Current State Map : Icons MATERIAL FLOW ICONS XYZ Corporation Outside Sources ASSEMBLY Manufacturing Process C/T = 45 sec. C/O = 30 min 3 Shifts 2% Scrap Data Box 300 pieces 1 Day Inventory Truck Shipment Mon. + Wed. PUSH Arrow Finished Goods To Customer First-In-First-Out Sequence Flow Max. 20 pieces FIFO Buffer or Safety Stock Operator Manual Information Flow Electronic Information Flow Schedule Weekly Schedule Load Leveling INFORMATION FLOW ICONS GENERAL ICONS
  • 20. Material Source: Lean Enterprise Institute 20
  • 21. Material Source: Lean Enterprise Institute 21 Future State Drawing Designing a Lean Flow • The power behind Value Stream Mapping is you always need a future state ! • 70% & Keep Updating. Use pencil ! • Material & Information flows • Basis for your Work Plan – like a “blueprint” • Begin by drawing on Current State • 1st iteration assumes existing steps & equipment Can move equipment, combine, take out conveyors, make minor purchases, etc. product family current state drawing future state drawing plan and implementation But there is a Problem!
  • 22. Material Source: Lean Enterprise Institute 22 Notice that on this future-state map the four welding and assembly process boxes have been combined into one process box to indicate the continuous flow. A small schematic sketch of a cell inside the process box also indicates the cellular manufacturing idea. First View of the Future-State Map Showing Takt Time, Weld/Assembly Cell, and the Finished-Goods Supermarket Building the Future State Map : Stage
  • 23. Material Source: Lean Enterprise Institute 23
  • 24. Material Source: Lean Enterprise Institute 24 Key Questions for the Future State 1. What is the takt time, based on the available working time of your downstream processes that are closest to the customer? 2. Will you build to a finished goods supermarket from which the customer pulls, or directly to shipping? (The answer to this question depends on several factors such as customer buying patterns, the reliability of your processes, and the characteristics of your product. Building directly to shipping will require either a reliable, short-lead-time, order-to-delivery lead time involves only those processes from the pacemaker process downstream to delivery.) 3. Where can you use continuous flow processing? 4. Where will you need to use supermarket pull systems in order to control production of upstream process? 5. At what single point in the production chain (the “pacemaker process”) will you schedule production? (Remember that all material transfers downstream of the pacemaker process need to occur as a flow.) 6. How will you level the production mix at the pacemaker process? 7. What increment of work will you consistently release and take away at the pacemaker process? 8. What process improvements will be necessary for the value stream to flow as your future- state design specifies? (This is the place to note any equipment and procedural improvements that will be necessary, such as reducing changeover time or improving machine uptime. We use the kaizen lightning burst icon to indicate these points in the process.)
  • 25. Material Source: Lean Enterprise Institute 25 Produce to your Takt Time Takt time synchronizes pace of production to match pace of sales. Takt Time = Available Work Time / Shift Customer Demand Rate / Shift Calculate Takt Time for ACME Answer : Available work time = 28,800 – 1200 = 27,600 seconds/shift Customer demand = 640 units per shift Takt Time = 60 seconds Takt Time is like ‘Asking Rate’
  • 26. Material Source: Lean Enterprise Institute 26 TAKT Time Synchronizes pace of assembly to match pace of sales. Rate for assembling a product based on sales rate. Effective Working Time per Shift Takt Time = Customer Requirement per Shift 27,000 sec = 59 sec 460 pieces
  • 27. Material Source: Lean Enterprise Institute 27 Should Acme build steering brackets to a finished goods supermarket or directly ship? To move towards ‘Produce to Shipping’, ship from a supermarket There are two varieties “RH” & “LH” Since Customer requirement is in multiples of 20-bracket trays, this is the choice for KANBAN size. When we ship a tray of 20 brackets, a KANBAN to demand shipping to replenish 20 brackets from PRODUCTION is issued. KANBAN ASSEMBLY LH RH Shipping Customer Customer Requirement
  • 28. Material Source: Lean Enterprise Institute 28
  • 29. Material Source: Lean Enterprise Institute 29
  • 30. Material Source: Lean Enterprise Institute 30 Where can ACME introduce continuous flow? BEFORE AFTER Acme Stamping current cycle times Acme Stamping weld/assembly cell cycle times after process kaizen Takt time 60 seconds Takt time 60 seconds
  • 31. Material Source: Lean Enterprise Institute 31 Problem Points in the Flow Where One-Piece Flow Ends How can we control production between flows ? MRP-based schedules ? Stamping Welding Assembly customer
  • 32. Material Source: Lean Enterprise Institute 32
  • 33. Material Source: Lean Enterprise Institute 33 Where will ACME need to use supermarket pull system? 1. Difference in C/T of Stamping machine and other machines is high. Ideally we need a ‘smaller’ Stamping machine. Let us adopt a supermarket. 2. Stamping machine produces at the rate of 60 Stampings / hour. Let us adopt that as the KANBAN quantity. 3. Design a supermarket between stamping and weld cum assembly station to withdraw 60 Stampings at a time. 4. Improve changeover time on Stamping machine so that quick changeover allows making LH and RH pieces for one hour each and keep switching every hour. 5. Until we reduce the change over time, let us make a super market having 15 days of parts to provide for replenishment delays and some quality & breakdown problems.
  • 34. Material Source: Lean Enterprise Institute 34 What should be the frequency to receive coils (raw material)? 1. Move to once a day supplies to reduce inventory by 80%. 2. Keep inventory only for 2 days. Coils Stamped Parts Weld/Assy WIP Finished Good Production Lead Time Total Inventory Turns 5 Days 7.6 Days 6.5 Days 4.5 Days 23.6 Days 10 2 Days 1.5 Days 4.5 Days 8 Days 30After Before Acme Stamping Lead Time Improvement
  • 35. Material Source: Lean Enterprise Institute 35
  • 36. Material Source: Lean Enterprise Institute 36 What single point in the production chain (the pacemaker process) should ACME Schedule? Since all process steps downstream of the pacemaker process need to occur in flow, in ACME, the scheduling point should be the welding / assembly cell.
  • 37. Material Source: Lean Enterprise Institute 37
  • 38. Material Source: Lean Enterprise Institute 38 Paced Withdrawal at the Pacemaker • What amount of work do you schedule and take away at the pacemaker? • This amount = your management time frame. (How often do you know your performance to customer demand?) • Are you providing takt image ? 1 Week 1 Day 1 Shift 1 Hour 1 Pitch 1 Takt ?
  • 39. Material Source: Lean Enterprise Institute 39 What process improvements will be necessary for Acme’s value stream to flow as the future-state design describes? Achieving the material and information flows we envision for Acme Stamping requires the following process improvements:  Reduction in changeover time and batch sizes at the stamping press, to allow faster response to downstream usage. The goals are “ every part every day” and then “ every part every shift”.  Elimination of the time (10 minutes) required to change between left-drive and right fixtures in welding, to make possible continuous flow and mixed production from welding through assembly.  Improvement in on-demand uptime of the second spot-weld machine, as it will now be tied to other processes in a continuous flow.  Elimination of waste in the weld/assembly cell, to reduce total work content down to 168 seconds or less. (Which allows use of 3 operators at the current demand level. We mark these items on our future-state map with the kaizen lightening burst icon.
  • 40. Material Source: Lean Enterprise Institute 40 AIM: To bring cycle time at each work station lower than takt time. How: Identify KAIZENS’ that would help in this direction. How Much: 1. Total time for welding and assembly work (39 + 46 + 62 + 40) = 187 seconds 2. Divide by takt time (60s) to get 3.12 operator requirement 3. Plan for Kaizens to reduce 4 work stations to 3 manned by 3 operators with each station operating with cycle time less than takt time (60 seconds) KAIZENS REQUIRED: 1. Total work < 168 seconds. 2. Weld changeover time reduction 3. Welder uptime increase. KAIZEN BURST
  • 41. Material Source: Lean Enterprise Institute 41 Future State Map : Material and Information Flow
  • 42. Material Source: Lean Enterprise Institute 42 Implementation A Plan to Get There • Don’t Wait ! • To “manage the exceptions” you need a plan! 1. Tie it to business objectives. 2. Break your future state into “loops”. 3. Make a VS Plan: What to do by when. 4. Now relate the FS Map to your layout. 5. VS Manager completes VS Review from in advance. 6. Conduct VS Reviews walking the flow.
  • 43. Material Source: Lean Enterprise Institute 43
  • 44. Material Source: Lean Enterprise Institute 44
  • 45. Material Source: Lean Enterprise Institute 45
  • 46. Material Source: Lean Enterprise Institute 46
  • 47. Material Source: Lean Enterprise Institute 47