SlideShare a Scribd company logo
1 of 33
MEP Fundamentals
Power
MEP Fundamentals
Power
MEP Fundamentals
Power
MEP Training
Power
Examples of Questions we will answer:

1. What is AIC?
2. If 3-phase is better, why not 4 or 5?
3. Do all tenants have a transformer? Why or
why not?

September, 2007
MEP Training
Power
Electricity is created
by:
Nature - lightning
Battery - chemical
Generatormechanical




Creates alternating
current as it rotates
Why three phases,
why not four?

Motor in reverse September, 2007
MEP Training
Power
Generation:
Heat > steam > turbine > generator
Voltage boosted for distance
Substations step down to 7,200-15,000v
On-site transformer steps down to 480 or 208v

September, 2007
MEP Training
Power
Ground:
The earth safely
absorbs
electricity
Not just one of
those NEC things
September, 2007
MEP Training
Power
Grounding and bonding:
Ground is a connection to the earth that only
carries current when there is a short (green wire)
Bond is connection between components to the
ground
Grounding is required:



At service initiation
At low voltage side of transformer
 Initiation of new voltage (480v to 208v)

Grounds need to be where inspectors can find
them
September, 2007
MEP Training
Power
Transformers:

September, 2007
MEP Training
Power
Fault Current:
How much current will flow when a fault (short)
occurs?
What limits the current?
Common panel/breaker rating is 10,000 amps
How do you know?




Utility company transformer
available fault current
Fuses in landlord or tenants main
September, 2007
MEP Training
Power
Transformers


Typically 480/277 to 208/120
 30 KVA to 83 Amps
 45 KVA to 125 Amps
 75 KVA to 208 Amps

September, 2007

(290 Lbs.)
(400 Lbs.)
(500 Lbs.)

$ 2,300
$ 2,800
$ 4,000
MEP Training
Power
Breakers vs. Fuses

September, 2007
MEP Training
Power
Types of Landlord distribution equipment:
Utility metered




Wireway
Switchgear
Meter Center

Landlord redistribution, no meters



Distribution Panelboard / Switchboard
Buss duct

September, 2007
MEP Training
Power
Wireway (Utility Metered)

September, 2007
MEP Training
Power
Switchgear (Utility Metered)

September, 2007
MEP Training
Power
Meter Center (Utility Metered)

September, 2007
MEP Training
Power

Distribution
Panelboard/
Switchboar
(Landlord
d
Redistribution,
no meters)

September, 2007
MEP Training
Power

Buss duct
(Landlord
Redistribution,
no meters)

September, 2007
CT’s / CT Cabinet

September, 2007
MEP Training
Power
Load Center




Residential
Not bolt-on breakers
Breakers not switch duty rated

Panelboards


Grouping of 20A breakers

Distribution Panelboards


Larger breakers, 60A – 400A

Switchboards


Distribution panelboard with fused switches

Switchgear


Large utility rated equipment
September, 2007
MEP Training
Power
Breakers:
Rating (maximum continuous current)
Some appliances create short
duration surges at start-up
(ex. electric motor)

September, 2007
MEP Training
Power
Ground fault:
Hot conductor connected to
ground
Create arc/spark
Caution: intermittent fault will
not trip breaker
Ground fault interrupters

September, 2007
MEP Training
Power
Common voltages:
Single phase:


120v – household outlet

Three phase:




240v = 120v x 2 wires for larger load (dryer)
208v/120v/3ph/4w
480v/277v/3ph/4w

What’s the last number?




Three wires are power
Four wire – neutral
Ground isn’t counted, it’s 2007
assumed
September,
MEP Training
Power
Neutral






Another path to ground (white
wire)
One hot (black) wire plus
neutral = single phase
277v or 120v

Why not 277v x 3 or 120v x 3
for three phase?


Power triangle, really is
geometry.
September, 2007
MEP Training
Power
Load calculation:
NEC rules



No consideration for diversity permitted.
Actual load rarely exceeds 65% of service size

Actual rating of equipment/lighting is required



Equipment nameplates
Lighting ballast inefficiencies must be considered

Continuous loads (operating for three + hours)




Rated load x 1.25
Lights
What about AC and heat?

Track lighting considered 75 watts per foot for service size,
but not branching size
September, 2007
MEP Training
Power
Load
calculation:

September, 2007
MEP Training
Power
Wire size:
Sized like pipe (velocity, diameter and pressure)
Continuous loads de-rate wire capacity



Heat
Defined as 3+ hours (lights)

Multiple conductors de-rate wire capacity


Heat (more wires = more heat)

Voltage drops




Wire acts as resistor based on
length of wire
Long distance with continuous
load = larger diameter
September, 2007
MEP Training
Power
Wire size:

September, 2007
MEP Training
Power
Wire size / Voltage Drop:
How long?


Wire can run as far as voltage (ex. 480v = 480 feet)
 Single phase in out and back
 Three phase is out only
 Don’t ask why

Conduit sizing


Never consume more than 40% of cross-sectional area
 Heat
 Pulling wire through conduit

40%
Max
September, 2007
MEP Training
Power
Electrical formulas:
Energy = power for a period of time




Energy = usage, watts x time
Electric meters use this measurement
Units are watt hours

Power = voltage x amperage





Similar to auto horsepower
Power = demand, kilowatts (1 kw = one thousand watts)
Voltage = the pressure (pushing) on the current
Amperage = current, the flow rate
September, 2007
MEP Training
Power
Electrical formulas continued
Examples of calculations


Single Phase: 2.4 kw = 120v x 20 amperes
 What is 115v or 110v?



Three phase: 16.6 kw = 480v x 20 amperes x 1.73
 1.73 is the square root of three (for three phase)

September, 2007
MEP Training
Power
Rules of thumb:
20 watts per square foot for retail tenants with
their own rooftop units.
15 watts per square foot for retail tenants with
landlord central air conditioning.
40 watts per square foot for sit-down restaurants.
100 watts per square foot for food court type
tenants.

September, 2007
MEP Training
Power
1. What is AIC?
2. If 3-phase is better, why not 4 or 5?
3. Do all tenants have a transformer? Why or
why not?

September, 2007

More Related Content

What's hot

Grade9, U2-L7-Power generation, efficiency and cost of electricity
Grade9, U2-L7-Power generation, efficiency and cost of electricityGrade9, U2-L7-Power generation, efficiency and cost of electricity
Grade9, U2-L7-Power generation, efficiency and cost of electricitygruszecki1
 
Electric Power Systems Fundamentals for Non-Electrical Engineers
Electric Power Systems Fundamentals for Non-Electrical EngineersElectric Power Systems Fundamentals for Non-Electrical Engineers
Electric Power Systems Fundamentals for Non-Electrical EngineersLiving Online
 
P2 investigating resistance
P2 investigating resistanceP2 investigating resistance
P2 investigating resistancedlesquerre
 
Combined sci p12 syllabus
Combined sci p12 syllabusCombined sci p12 syllabus
Combined sci p12 syllabuscartlidge
 
6 d electronics 231110
6 d electronics 2311106 d electronics 231110
6 d electronics 231110drgav2005
 
Y source boost dc dc converter for distributed generation
Y source boost dc dc converter for distributed generationY source boost dc dc converter for distributed generation
Y source boost dc dc converter for distributed generationI3E Technologies
 
Introducing Rrs
Introducing RrsIntroducing Rrs
Introducing Rrsrichardrs
 
2.12 producing electrical energy
2.12 producing electrical energy2.12 producing electrical energy
2.12 producing electrical energymrrayner
 
Low Frequency Electromagnetics Training with ANSYS Maxwell
Low Frequency Electromagnetics Training with ANSYS MaxwellLow Frequency Electromagnetics Training with ANSYS Maxwell
Low Frequency Electromagnetics Training with ANSYS MaxwellSIMTEC Software and Services
 
Modeling and Analysis of a Maximum Power Point Tracking Control for Double St...
Modeling and Analysis of a Maximum Power Point Tracking Control for Double St...Modeling and Analysis of a Maximum Power Point Tracking Control for Double St...
Modeling and Analysis of a Maximum Power Point Tracking Control for Double St...IRJET Journal
 
Combined sci p11 syllabus
Combined sci p11 syllabusCombined sci p11 syllabus
Combined sci p11 syllabuscartlidge
 
Performance of FACTS Devices for Power System Stability
Performance of FACTS Devices for Power System StabilityPerformance of FACTS Devices for Power System Stability
Performance of FACTS Devices for Power System Stabilityijeei-iaes
 

What's hot (18)

155 iit bomby
155 iit bomby155 iit bomby
155 iit bomby
 
Grade9, U2-L7-Power generation, efficiency and cost of electricity
Grade9, U2-L7-Power generation, efficiency and cost of electricityGrade9, U2-L7-Power generation, efficiency and cost of electricity
Grade9, U2-L7-Power generation, efficiency and cost of electricity
 
Electric Power Systems Fundamentals for Non-Electrical Engineers
Electric Power Systems Fundamentals for Non-Electrical EngineersElectric Power Systems Fundamentals for Non-Electrical Engineers
Electric Power Systems Fundamentals for Non-Electrical Engineers
 
Electrical concepts
Electrical conceptsElectrical concepts
Electrical concepts
 
Unit 34 Electricity
Unit 34 ElectricityUnit 34 Electricity
Unit 34 Electricity
 
P2 investigating resistance
P2 investigating resistanceP2 investigating resistance
P2 investigating resistance
 
Combined sci p12 syllabus
Combined sci p12 syllabusCombined sci p12 syllabus
Combined sci p12 syllabus
 
6 d electronics 231110
6 d electronics 2311106 d electronics 231110
6 d electronics 231110
 
Y source boost dc dc converter for distributed generation
Y source boost dc dc converter for distributed generationY source boost dc dc converter for distributed generation
Y source boost dc dc converter for distributed generation
 
04 final - hobbs lave wvm solar portfolios - pvpmc
04 final - hobbs lave wvm solar portfolios - pvpmc04 final - hobbs lave wvm solar portfolios - pvpmc
04 final - hobbs lave wvm solar portfolios - pvpmc
 
10 ashwini pavgi_pvpmc
10 ashwini pavgi_pvpmc10 ashwini pavgi_pvpmc
10 ashwini pavgi_pvpmc
 
Introducing Rrs
Introducing RrsIntroducing Rrs
Introducing Rrs
 
2.12 producing electrical energy
2.12 producing electrical energy2.12 producing electrical energy
2.12 producing electrical energy
 
Low Frequency Electromagnetics Training with ANSYS Maxwell
Low Frequency Electromagnetics Training with ANSYS MaxwellLow Frequency Electromagnetics Training with ANSYS Maxwell
Low Frequency Electromagnetics Training with ANSYS Maxwell
 
12 wittmer p_vsyst_pvpmc_7
12 wittmer p_vsyst_pvpmc_712 wittmer p_vsyst_pvpmc_7
12 wittmer p_vsyst_pvpmc_7
 
Modeling and Analysis of a Maximum Power Point Tracking Control for Double St...
Modeling and Analysis of a Maximum Power Point Tracking Control for Double St...Modeling and Analysis of a Maximum Power Point Tracking Control for Double St...
Modeling and Analysis of a Maximum Power Point Tracking Control for Double St...
 
Combined sci p11 syllabus
Combined sci p11 syllabusCombined sci p11 syllabus
Combined sci p11 syllabus
 
Performance of FACTS Devices for Power System Stability
Performance of FACTS Devices for Power System StabilityPerformance of FACTS Devices for Power System Stability
Performance of FACTS Devices for Power System Stability
 

Viewers also liked (18)

Power distribution options[1]
Power distribution options[1]Power distribution options[1]
Power distribution options[1]
 
Ebc codes[1]
Ebc codes[1]Ebc codes[1]
Ebc codes[1]
 
Ebc lighting sources[1]
Ebc lighting sources[1]Ebc lighting sources[1]
Ebc lighting sources[1]
 
Daylighting[1]
Daylighting[1]Daylighting[1]
Daylighting[1]
 
Ebc lighting sources[1]
Ebc lighting sources[1]Ebc lighting sources[1]
Ebc lighting sources[1]
 
Fire alarm system_nec_september[1]
Fire alarm system_nec_september[1]Fire alarm system_nec_september[1]
Fire alarm system_nec_september[1]
 
Eb cvoltages[1]
Eb cvoltages[1]Eb cvoltages[1]
Eb cvoltages[1]
 
Power[1]
Power[1]Power[1]
Power[1]
 
Fire alarm -_internal[1]
Fire alarm -_internal[1]Fire alarm -_internal[1]
Fire alarm -_internal[1]
 
Eb cvoltages[1]
Eb cvoltages[1]Eb cvoltages[1]
Eb cvoltages[1]
 
Power[1]
Power[1]Power[1]
Power[1]
 
Ebc lighting sources[1]
Ebc lighting sources[1]Ebc lighting sources[1]
Ebc lighting sources[1]
 
Power distribution options[1]
Power distribution options[1]Power distribution options[1]
Power distribution options[1]
 
Daylighting[1]
Daylighting[1]Daylighting[1]
Daylighting[1]
 
130906 fire alarm_2013_nfpa_72_changes[1]
130906 fire alarm_2013_nfpa_72_changes[1]130906 fire alarm_2013_nfpa_72_changes[1]
130906 fire alarm_2013_nfpa_72_changes[1]
 
Ebc sustainable quality_lighting[1]
Ebc sustainable quality_lighting[1]Ebc sustainable quality_lighting[1]
Ebc sustainable quality_lighting[1]
 
New hire orientation
New hire orientationNew hire orientation
New hire orientation
 
Breakers v. fuses[1]
Breakers v. fuses[1]Breakers v. fuses[1]
Breakers v. fuses[1]
 

Similar to Power[1]

PROBLEM ON THE POWERFACTOR CORRRECTION IN POWER PLANT
PROBLEM ON THE POWERFACTOR CORRRECTION IN POWER PLANTPROBLEM ON THE POWERFACTOR CORRRECTION IN POWER PLANT
PROBLEM ON THE POWERFACTOR CORRRECTION IN POWER PLANTsanjay kumar pediredla
 
BEEM UII.pptx
BEEM UII.pptxBEEM UII.pptx
BEEM UII.pptxMalathyN5
 
Modeling Of Converter “Single Phase to Three Phase by Using Single Phase Sup...
Modeling Of Converter “Single Phase to Three Phase by Using Single Phase  Sup...Modeling Of Converter “Single Phase to Three Phase by Using Single Phase  Sup...
Modeling Of Converter “Single Phase to Three Phase by Using Single Phase Sup...IJMER
 
Permaculutre Renewable Energy
Permaculutre Renewable EnergyPermaculutre Renewable Energy
Permaculutre Renewable EnergyKevin Bayuk
 
Electrical Basic and Classic Control
Electrical Basic and Classic ControlElectrical Basic and Classic Control
Electrical Basic and Classic ControlGaurav Singh Rajput
 
Final Presentation - 23-03-10
Final Presentation - 23-03-10Final Presentation - 23-03-10
Final Presentation - 23-03-10Luigi Pinna
 
PPT Samples (1).pptx
PPT Samples (1).pptxPPT Samples (1).pptx
PPT Samples (1).pptxAryaA44
 
Improvement of Load Power Factor by Using Capacitor
Improvement of Load Power Factor by Using CapacitorImprovement of Load Power Factor by Using Capacitor
Improvement of Load Power Factor by Using CapacitorIOSRJEEE
 
A Novel Three Phase Multi-string Multilevel Inverter with High DC-DC Closed o...
A Novel Three Phase Multi-string Multilevel Inverter with High DC-DC Closed o...A Novel Three Phase Multi-string Multilevel Inverter with High DC-DC Closed o...
A Novel Three Phase Multi-string Multilevel Inverter with High DC-DC Closed o...rnvsubbarao koppineni
 
Sag tension calculations-a_tutorial_deve
Sag tension calculations-a_tutorial_deveSag tension calculations-a_tutorial_deve
Sag tension calculations-a_tutorial_deveRaghavTripathi11
 
L26 - BET - Transformers _ DC motors.pptx
L26 - BET - Transformers _ DC motors.pptxL26 - BET - Transformers _ DC motors.pptx
L26 - BET - Transformers _ DC motors.pptxhappycocoman
 
presentations for the project of solar energy
presentations for the project of solar energypresentations for the project of solar energy
presentations for the project of solar energyH2SO43
 
Design of Tesla Coil
Design of Tesla CoilDesign of Tesla Coil
Design of Tesla CoilIRJET Journal
 
Power(2)-EPM320-L01-16 Lectures of Power System Analysis.pdf
Power(2)-EPM320-L01-16 Lectures of Power System Analysis.pdfPower(2)-EPM320-L01-16 Lectures of Power System Analysis.pdf
Power(2)-EPM320-L01-16 Lectures of Power System Analysis.pdfssuser621d9d
 
overvoltage in distribution network
overvoltage in distribution networkovervoltage in distribution network
overvoltage in distribution networkmegala venkatesan
 
IRJET- Fault Location using Discrete Wavelet Transform for Smart Grid Distrib...
IRJET- Fault Location using Discrete Wavelet Transform for Smart Grid Distrib...IRJET- Fault Location using Discrete Wavelet Transform for Smart Grid Distrib...
IRJET- Fault Location using Discrete Wavelet Transform for Smart Grid Distrib...IRJET Journal
 

Similar to Power[1] (20)

PROBLEM ON THE POWERFACTOR CORRRECTION IN POWER PLANT
PROBLEM ON THE POWERFACTOR CORRRECTION IN POWER PLANTPROBLEM ON THE POWERFACTOR CORRRECTION IN POWER PLANT
PROBLEM ON THE POWERFACTOR CORRRECTION IN POWER PLANT
 
BEEM UII.pptx
BEEM UII.pptxBEEM UII.pptx
BEEM UII.pptx
 
Modeling Of Converter “Single Phase to Three Phase by Using Single Phase Sup...
Modeling Of Converter “Single Phase to Three Phase by Using Single Phase  Sup...Modeling Of Converter “Single Phase to Three Phase by Using Single Phase  Sup...
Modeling Of Converter “Single Phase to Three Phase by Using Single Phase Sup...
 
2010 August Harmonics & Energy Efficiency
2010 August Harmonics & Energy Efficiency2010 August Harmonics & Energy Efficiency
2010 August Harmonics & Energy Efficiency
 
Permaculutre Renewable Energy
Permaculutre Renewable EnergyPermaculutre Renewable Energy
Permaculutre Renewable Energy
 
Electrical Basic and Classic Control
Electrical Basic and Classic ControlElectrical Basic and Classic Control
Electrical Basic and Classic Control
 
Final Presentation - 23-03-10
Final Presentation - 23-03-10Final Presentation - 23-03-10
Final Presentation - 23-03-10
 
PPT Samples (1).pptx
PPT Samples (1).pptxPPT Samples (1).pptx
PPT Samples (1).pptx
 
Improvement of Load Power Factor by Using Capacitor
Improvement of Load Power Factor by Using CapacitorImprovement of Load Power Factor by Using Capacitor
Improvement of Load Power Factor by Using Capacitor
 
A Novel Three Phase Multi-string Multilevel Inverter with High DC-DC Closed o...
A Novel Three Phase Multi-string Multilevel Inverter with High DC-DC Closed o...A Novel Three Phase Multi-string Multilevel Inverter with High DC-DC Closed o...
A Novel Three Phase Multi-string Multilevel Inverter with High DC-DC Closed o...
 
Sag tension calculations-a_tutorial_deve
Sag tension calculations-a_tutorial_deveSag tension calculations-a_tutorial_deve
Sag tension calculations-a_tutorial_deve
 
L26 - BET - Transformers _ DC motors.pptx
L26 - BET - Transformers _ DC motors.pptxL26 - BET - Transformers _ DC motors.pptx
L26 - BET - Transformers _ DC motors.pptx
 
Question bank Electrical Engineering
Question bank Electrical Engineering Question bank Electrical Engineering
Question bank Electrical Engineering
 
presentations for the project of solar energy
presentations for the project of solar energypresentations for the project of solar energy
presentations for the project of solar energy
 
electrical system
electrical system electrical system
electrical system
 
Design of Tesla Coil
Design of Tesla CoilDesign of Tesla Coil
Design of Tesla Coil
 
Power(2)-EPM320-L01-16 Lectures of Power System Analysis.pdf
Power(2)-EPM320-L01-16 Lectures of Power System Analysis.pdfPower(2)-EPM320-L01-16 Lectures of Power System Analysis.pdf
Power(2)-EPM320-L01-16 Lectures of Power System Analysis.pdf
 
overvoltage in distribution network
overvoltage in distribution networkovervoltage in distribution network
overvoltage in distribution network
 
IRJET- Fault Location using Discrete Wavelet Transform for Smart Grid Distrib...
IRJET- Fault Location using Discrete Wavelet Transform for Smart Grid Distrib...IRJET- Fault Location using Discrete Wavelet Transform for Smart Grid Distrib...
IRJET- Fault Location using Discrete Wavelet Transform for Smart Grid Distrib...
 
Ba33301306
Ba33301306Ba33301306
Ba33301306
 

More from Jennifer Kleinhenz

More from Jennifer Kleinhenz (16)

Daylighting[1]
Daylighting[1]Daylighting[1]
Daylighting[1]
 
Light trespass and_pollution[1]
Light trespass and_pollution[1]Light trespass and_pollution[1]
Light trespass and_pollution[1]
 
Ebc sustainable quality_lighting[1]
Ebc sustainable quality_lighting[1]Ebc sustainable quality_lighting[1]
Ebc sustainable quality_lighting[1]
 
Daylighting[1]
Daylighting[1]Daylighting[1]
Daylighting[1]
 
Daylighting[1]
Daylighting[1]Daylighting[1]
Daylighting[1]
 
Fire alarm system_nec_september[1]
Fire alarm system_nec_september[1]Fire alarm system_nec_september[1]
Fire alarm system_nec_september[1]
 
Fire alarm system_ne-audible_signaling[1]
Fire alarm system_ne-audible_signaling[1]Fire alarm system_ne-audible_signaling[1]
Fire alarm system_ne-audible_signaling[1]
 
Fire alarm system_ne-audible_signaling[1]
Fire alarm system_ne-audible_signaling[1]Fire alarm system_ne-audible_signaling[1]
Fire alarm system_ne-audible_signaling[1]
 
Fire alarm system_ne-audible_signaling[1]
Fire alarm system_ne-audible_signaling[1]Fire alarm system_ne-audible_signaling[1]
Fire alarm system_ne-audible_signaling[1]
 
Fire alarm -_internal[1]
Fire alarm -_internal[1]Fire alarm -_internal[1]
Fire alarm -_internal[1]
 
130920 fire alarm_intelligibility[1]
130920 fire alarm_intelligibility[1]130920 fire alarm_intelligibility[1]
130920 fire alarm_intelligibility[1]
 
130920 fire alarm_intelligibility[1]
130920 fire alarm_intelligibility[1]130920 fire alarm_intelligibility[1]
130920 fire alarm_intelligibility[1]
 
Power[1]
Power[1]Power[1]
Power[1]
 
Nec 15th november[1]
Nec 15th november[1]Nec 15th november[1]
Nec 15th november[1]
 
Nec 15th november[1]
Nec 15th november[1]Nec 15th november[1]
Nec 15th november[1]
 
111111 elevator design_review[1]
111111 elevator design_review[1]111111 elevator design_review[1]
111111 elevator design_review[1]
 

Recently uploaded

(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...lizamodels9
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadAyesha Khan
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 

Recently uploaded (20)

(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 

Power[1]

Editor's Notes

  1. We will answer all these questions in this presentation. The questions will be repeated at the end.
  2. Why 3 phases? Structural loads are balanced on the generator shaft with 3 phases. Balances the output of energy. More than three is simply the law of diminishing returns. Therefore a motor is as close to a “perfect” electric user as it gets.
  3. Distribution voltage is 155,000 to 760,000 volts. Transmission distances are up to 300 miles.
  4. The top wire between poles is usually the ground wire. Poles themselves are grounded at the base.
  5. Short circuit is an unplanned connection between any of the hot wires and a grounded metal part. Service initiation is also the end point of utility responsibility. “Demarkation” Do not ground to water pipe. Water pipes snake all over a mall with only one connection to ground. Dangerous. Building steel is carefully grounded at many columns and even has wires connecting across expansion joints to ensure good ground.
  6. Notice: No wire connection from low to high voltage. Ground. Fewer “twists” on low voltage side.
  7. Intro: Let’s go back to ground. Earth has an infinite ability to absorb electricity and when given a chance, will do just that, attempt to absorb infinite energy. How much current will flow when a fault or short occurs? Can far exceeds breaker rating 30,000 – 65,000 common in malls Each component must be selected for correct fault current or Ampere Interrupting Capacity (AIC) Problem: Our systems can not deal with “infinite loads” and remember the breaker is designed for continuous load and allow higher loads for short periods. What limits the current? Resistance of wire and components Transformers Fuses (one of the best devices) Panels may literally explode if not designed (rated) properly.
  8. Metering is the key first off. If redistribution, owner can not meter unless they are a “utility” registered with the state’s Utility Commission. Cost is also a key. Order is by increasing cost to owner (not necessarily tenant)
  9. Owner/Landlord installs trough if anything. Often trough is by the utility company. Wireway is most basic of group distribution systems, multiple individual disconnect switches. Wireways take a lot of space and are tough to coordinate space. Often outdoors due the their size. Simply wires laid in a trough. Notice some have switches, some do not. Switch before/after meter. Often these were installed by the utility company and therefore not subject to NEC rules. Today NEC rules most of these installations. NEC limits the number of switches to make a service safe (shut off all power) to six (6). Photo on left has six switches. One on right has ten meters and fewer switches. This one often needs to be upgraded if touched. Ok if left alone, but no new services or upsized services.
  10. Big, solid units. Still less space and more organized than wireways. Outdoor unit has meters inside doors.
  11. Specialized form of switchgear 208V and 1600A maximum Space saving
  12. Note no meters! Redistribution of power by landlord. Small space. 13 services in space of 3 or 4 on a wireway. All owner purchased equipment. Flexible. Easy to add a service, just plug in one more, or provide spares as in this photo.
  13. Again, no meters. Redistribution here too. Essentially no floor space is used. This one is overhead in service corridor. Much like a wireway, except there is copper bars in the center section. Switches are the boxes on left and right.
  14. Not rated for instantaneous, short overcurrents. Those happen often at startup and the breaker is designed to ignore them. Motors for instance can draw much more than rated amperage at startup, but we don’t want the breakers to trip.
  15. A special condition of short circuit. Not any different, just defined for engineers. Need ground fault interrupted rated breakers to trip on short duration overcurrents.
  16. Equipment is often rated at 208v and 240v
  17. Diversity for cooking equipment. Outlets in large spaces. Services are “oversized” for safety factor when actual loads can not be measured. Who can be sure of diversity? After the fact, NEC allows us to measure load on landlord main service to prove we can add more load.
  18. Amperage is velocity. Diameter is wire size. Voltage is pressure.
  19. Wire types, really speaking about the insulation. More H’s = higher rating. N = Nylon, slippery. W = Wet locations.
  20. Ampere Interrupting Capacity. The rating of tenant panels, consistent with utility transformer rating.