SlideShare a Scribd company logo
1 of 31
Solar Power Plant
Design
BY:
KAPIL JOSHI
Topics
 What are the different topologies and interconnection methods for a PV
system?
 What are the various components that are used in a rooftop PV system?
 How do we do preliminary sizing of a grid-connected PV System?
 How do we arrive at detailed sizing of a grid-connected PV system?
 What should be the sizing and specifications of these components?
 How to make the necessary drawings/ diagrams of a grid-connected rooftop
PV system?
Topic : SOLAR POWER PLANT DESIGN
Stand-alone PV system.
Hybrid PV system.
Grid-connected PV system.
Types of PV System
Topic : SOLAR POWER PLANT DESIGN
Metering Arrangements for Rooftop PV Systems
A typical metered home. Gross-metered system.
Net-metered system (hybrid).
Net-metered system.
Topic : SOLAR POWER PLANT DESIGN
List of Equipment & Material
 PV Module
 DC Cable (PV modules to SJB)
 String Junction Box (SJB)
 DC Cable (SJB to Inverter)
 Cable Tray/ Conduit
 DC Isolator*
 Inverter
 AC Cable
 Isolation Transformer*
 AC Distribution Box
 Lightning Arrestor*
 Earthing Cable
 Earthing Strip
 Earth Pit (2 or 4 or more)
 Generation Meter
 Bi-directional Net-meter
 DC Fuse
 DC Surge Protection Device (SPD)
 AC Surge Protection Device (SPD)
 Isolator: MCB/ ELCB/ RCCB
 Labels
Topic : SOLAR POWER PLANT DESIGN
2-Step System Sizing
 Step 1: PV System Capacity
 Where we specify:
 DC Capacity
 AC Capacity
 Battery Capacity
 Capacity is based on:
 Energy requirement
 Space limitation
 Budget limitation
 Policy limitation
 Step 2: Specific Equipment
Specifications
 Where we specify:
 Make and model
 Quantities & Sizing
 Dimensions (e.g. cable length)
 Repute Brand
 Selection is based on:
 Specification
 Availability
 Cost
Topic : SOLAR POWER PLANT DESIGN
Step 1 (Given)
 Case study:
 Type of system: Grid-connected
 Capacity constraint: Available space
 Capacity for which space is available: 30 kW
 That’s it!!!
Topic : SOLAR POWER PLANT DESIGN
Step 2.1: Site Survey
 Undertake a detailed site survey (if not already done so) to identify:
 Shadow-casting features and shadow-free area
 Location for mounting inverter(s) and AC Junction Boxes, typically on terrace/ roof
 Location for interconnection point (distribution panel of house/ building), typically
on ground floor
 Location where earth pits will be installed
 (Check if distribution panel has extra feeder/ interconnection point of sufficient
capacity)
[Note: These are in addition to other steps involved in a site survey.]
Topic : SOLAR POWER PLANT DESIGN
Room, 3 meter up
Site Survey Drawing
Location for PV Arrays Location for:
• String (DC) Junction Box
• Inverter(s)
• AC Junction Box
DC Cable Routing
Earth Pit Location
AC Cable Routing
Earthing Strip Routing
17.77 m X 13.10 m
= 232.79 m2
(~19.4 kW)
22.07 m X 5.45 m = 120.28
m2
(~10.02 kW)
Topic : SOLAR POWER PLANT DESIGN
Step 2.2: PV Module Selection
Step 2.2: Grid-connected Inverter Selection
Topic : SOLAR POWER PLANT DESIGN
Modules and Strings (1/5)
 Let’s count PV modules…
 PV Module (DC) Capacity:
 20 kW; 10 kW
 Estimate the total number of PV Modules:
 20,000 / 300 = 67; 10,000 / 300 = 33
 Which inverters can be used? (Ref. Max. PV Power)
 17 kW; 10 kW
Topic : SOLAR POWER PLANT DESIGN
Modules and Strings (2/5)
 How many modules in series (i.e. string size) can the inverter accept?
 What is the inverter’s MPPT range?
 410 … 850 V; 460 … 850 V
 What is the maximum number of modules per string that the inverter can accept
within the ‘MPPT range’?
 850 / VMP = 850 / 36.72 = ~23; 850 / VMP = 850 / 36.72 = ~23
 What is the maximum number of modules per string without exceeding the inverter’s
‘Max. DC Voltage’?
 1000 / VOC = 1000 / 45.50 = ~21; 1000 / VOC = 1000 / 45.50 = ~21
 What is the maximum number of modules per string acceptable to the inverter?
 21; 21
Topic : SOLAR POWER PLANT DESIGN
Modules and Strings (3/5)
 Let’s converge…
 Can we have 1 string per inverter?
 i.e. 67 modules per string? i.e. 33 modules per string?
 NO NO
 Can we have 2 strings per inverter?
 i.e. 34 modules per string? i.e. 17 modules per string?
 NO Maybe!!! Let’s freeze this for now.
 Can we have 3 strings per inverter?
 i.e. 22 modules per string?
 NO
 Can we have 4 strings per inverter?
 i.e. 17 modules per string?
 Maybe!!! Let’s freeze this for now.
Topic : SOLAR POWER PLANT DESIGN
Modules and Strings (4/5)
 Let’s check…
 What is the VMP of the string be within MPPT range at STC?
 VMP: 17 x 36.72 V = 624.24 V; VMP: 17 x 36.72 V = 624.24 V
 YES; YES;
 Will the VMP of the string be within MPPT range on a bright sunny day?
 Bright sunny day: 1000 W/m2; Max. TAMB: 42°C  Max. TMOD: 73°C
 VMP: 17 x 31.07 V = 528.19 V; VMP: 17 x 31.07 V = 528.19 V
 YES; YES
 Will the maximum string voltage be less than inverter’s ‘Max. DC Voltage’?
 VOC: 17 x 45.50 V = 773.50 V; VOC: 17 x 45.50 V = 773.50 V
 Hence, 17 modules per string is suitable for the inverter.
 DC Capacity: DC Capacity:
 300 W x 17 x 4 = 20.4 kW; 300 W x 17 x 2 = 10.2 kW
Topic : SOLAR POWER PLANT DESIGN
Modules and Strings (5/5)
 Let’s try to push the string size further…
 Can we use 18 modules per string instead of 17?
 DC Capacity for 20 kW system:
 300 W per module x 18 modules per string x 4 strings
 = 21.6 kW
 NO! This is more than inverter’s ‘Recommended Max. PV Power’.
 DC Capacity for 10 kW system:
 300 W per module x 18 modules per string x 2 strings
 = 10.8 kW
 YES! This is within the inverter’s ‘Recommended Max. PV Power’.
Topic : SOLAR POWER PLANT DESIGN
String Junction Box (SJB) Specification (1/3)
 How many inputs and outputs are required in the String Junction Box…
 For 20 kW system? For 10 kW system?
 If the number of PV strings are greater than number of input DC connections to the
inverter, then we will have to connect strings in parallel in the SJB.
 No. of PV strings:
 4 2
 No. of input DC connections to the inverter:
 6 3
 Hence, are the strings required to be connected in parallel?
 NO NO
 SJB input-output specification:
 4-in 4-out 2-in 2-out
 These can be combined as 6-in 6-out
Topic : SOLAR POWER PLANT DESIGN
String Junction Box (SJB) Specification (2/3)
 Let’s specify the 4-in 4-out SJB…
 Cable Gland/ Connector
 Incoming DC: 4 pairs of male/ female panel-mount MC4 connectors
 Earthing: 1 Nos. of (M16) Cable Gland for 6 mm2 earthing cable.
 Fuse-holders and Fuses
 Fuse rating > ISC x 1.25 x 1.25 = 8.65 x 1.25 x 1.25 = 13.51 A  15A, 1000 VDC
 Fuse-holder (Fuse-base) > Fuse rating  30 A, 1000VDC
 8 Nos., each
 Surge Protection Device (SPD) (i.e. Surge Arrestors)
 1 Nos. Type II, 1000 VDC, 40 kA
 Terminal Blocks
 Required when connecting SPD are connected in parallel.
Topic : SOLAR POWER PLANT DESIGN
String Junction Box (SJB) Specification (3/3)
 Internal cables:
 DC (positive and negative): 4 mm2 PV cables
 Earthing Cable: 6 mm2 copper cable
 Enclosure
 Thermoplastic Polycarbonate
 Degree of protection: IP65
 Design Temperature > 50 °C Ambient
Topic : SOLAR POWER PLANT DESIGN
DC Cable Sizing
 DC Cables need to conform to 2 requirements:
 Ampacity
 Ampacity is the current-carrying capacity of the conductor
 Ampacity of conductor should be more than ISC x 1.25 x 1.25 of the string
 Voltage Drop
 Should be less than 2%
 Note that these values should be calculated at the:
 Actual PV module temperatures (E.g. 70°C), and
 Actual/ ambient (E.g. 45°C) temperature of PV cable.
Topic : SOLAR POWER PLANT DESIGN
DC Cable Resistivity & Ampacity
Topic : SOLAR POWER PLANT DESIGN
Ampacity Deration due to Temperature
Topic : SOLAR POWER PLANT DESIGN
Check for Ampacity
 Step 1: For PV string:
 ISC = 8.65 A
 Hence, Ampacity of cable should be more than 13.51 A.
 Step 2: For 4 mm2 PV cable:
 Ampacity @ 20°C = 44 A
 (Because multiple cables will be laid together in the cable tray.)
 Ampacity deration factor @ 41-45°C ambient temperature = 0.87
 Hence, Ampacity of the PV cable is 38.28 A.
 Ampacity of the PV cable is more than the PV string current.
 Hence, first condition is met.
Topic : SOLAR POWER PLANT DESIGN
Check for Voltage Drop
 Step 1: Maximum length of the PV cable is from the farthest PV module
 (17 + 13 + 3 + 3 + 22 + 12 + 5.5 + 3 + 4.5) m + Extra 10%
 = ~100 m
 Step 2: Resistance of the PV cable
 R @ 20°C = 5.09 Ω/ km x 0.1 km = 0.51 Ω
 R @ 70°C = R20°C x [ 1 + α ( T Cable – 20 ) ] = 0.61 Ω
 Where,
 For copper, α = 0.393 % / °C
 Assume PV cable is at 70°C
 Step 3: Voltage drop = IMP x R = 8.17 A x 0.61 Ω = 5 V
 Step 4: VMP, String @ 70°C = 17 x 31.43 V = 534.3 V
 Step 5: Voltage Drop in % = 0.93%, which is less than 2%
 Hence, second condition is also met.
Topic : SOLAR POWER PLANT DESIGN
AC Cable Sizing
 AC cables are required from:
 Inverter to nearby AC Distribution Box
 AC Distribution Box to Main AC Distribution Box
 Note: Same ampacity and voltage drop rules apply as in DC cables.
Topic : SOLAR POWER PLANT DESIGN
AC Cable: Inverter to nearby AC Distribution Box
 Let’s calculate for two inverters:
 20 kW System; 10 kW System
 What is the maximum output AC current?
 3 x 29 A (i.e. 3φ); 3 x 16 A (i.e. 3φ)
 After safety factor…
 3 x 36.25 A; 3 x 20 A
 Which 4-C AC cable from the datasheet can carry this current?
 Note: Usually, the length of this cable is not substantial, and hence, voltage drops
are very minor.
 Aluminium,10 mm2; Aluminium, 4 mm2
 Note: Often for uniformity and convenience of procurement, we may use the
same AC Cables for both inverters:
 Aluminium,10 mm2; Aluminium, 10 mm2
Topic : SOLAR POWER PLANT DESIGN
AC Cable: ACDB to ACDB (Ampacity)
 Once all the inverter outputs are combined in the ACDB near the inverter, it will add up the
currents and evacuate power using a single AC cable.
 In our case, combined AC current: 3 x 45 A (i.e. 3φ)
 Hence, after considering safety factor: 3 x 56.25 A
 Which AC cable is suitable from the datasheet?
 Aluminium, 25 mm2
 Note: For long distances, it is preferred to used armoured cables.
Topic : SOLAR POWER PLANT DESIGN
AC Cable: ACDB to ACDB (Voltage Drop)
 Let’s assume that:
 The installation (including inverter) is on the terrace/ roof above the 3rd floor of the building,
and main ACDB of the building is on the ground floor, and
 The surveyor determines this cable routing distance to be 25 m.
 From datasheet, resistance of 25 mm2 Aluminium cable, R:
 R @ 20 °C = 1.2 Ω per km x 0.025 km = 0.03 Ω
 Therefore:
 R @ 75°C = R20°C x [ 1 + α ( T Cable – 20 ) ] = 0.036 Ω
 Voltage drop = I x R = 45 A x 0.036 Ω = 1.6 V
 Voltage drop in % = 1.6 / 230 = 0.7%
 This is within the 2% limit, hence 25 mm2 Aluminium cable is acceptable.
Topic : SOLAR POWER PLANT DESIGN
AC Distribution Box (ACDB)
 How many in? How many out?
 2-in, because two separate inputs will come from the two inverters
 In our example, each wire is 10 mm2
 1-out, because we combine the above two and evacuate in a single wire.
 In our example, this wire is 25 mm2
 What do we need in the AC Junction Box?
 MCB (Miniature Circuit Breaker) for each incomer from inverter
 To individually disconnect each inverter, and protect from overcurrent.
 From datasheet: Rated current: 40 A, 240 V, Breaking Capacity: 10 kA
 SPD (Surge Protection Device)
 From datasheet: 400 VAC, Type 2 (4-pole)
 RCCB (Residual Current Circuit Breaker)
 To protect inverter from residual current and earth leakage faults
 From datasheet: 63 Amp, 100 mA (4-pole))
Topic : SOLAR POWER PLANT DESIGN
Drawings
 Single Line Diagram
 Equipment/ Module/ Project Layout Diagram
 Cable Route Plan
 Earthing Layout Diagram
Topic : SOLAR POWER PLANT DESIGN
THANK YOU…

More Related Content

Similar to presentations for the project of solar energy

Seektronics.com 64 skills about switching power supply design
Seektronics.com 64 skills about switching power supply designSeektronics.com 64 skills about switching power supply design
Seektronics.com 64 skills about switching power supply designPaddyWang4
 
PV SYSTEMS, COMPONENTS DEVICES AND APPLICATIONS.ppt
PV SYSTEMS, COMPONENTS DEVICES AND APPLICATIONS.pptPV SYSTEMS, COMPONENTS DEVICES AND APPLICATIONS.ppt
PV SYSTEMS, COMPONENTS DEVICES AND APPLICATIONS.pptArpoMukherjee1
 
Solar Fundametals - K. Jayaweera May 2022.pdf
Solar Fundametals - K. Jayaweera May 2022.pdfSolar Fundametals - K. Jayaweera May 2022.pdf
Solar Fundametals - K. Jayaweera May 2022.pdfssuserfd91eb
 
Iv curve parameters
Iv curve parametersIv curve parameters
Iv curve parametersSunil R
 
#Solar #Design #TOOL PV System Design Calculations Report at Neotia Universit...
#Solar #Design #TOOL PV System Design Calculations Report at Neotia Universit...#Solar #Design #TOOL PV System Design Calculations Report at Neotia Universit...
#Solar #Design #TOOL PV System Design Calculations Report at Neotia Universit...Saikat Bhandari
 
Electrical Engineering Interview Questions
Electrical Engineering Interview QuestionsElectrical Engineering Interview Questions
Electrical Engineering Interview Questionsashiesh0007
 
Sinusoidal Response of RC & RL Circuits
Sinusoidal Response of RC & RL CircuitsSinusoidal Response of RC & RL Circuits
Sinusoidal Response of RC & RL CircuitsSachin Mehta
 
UPS operation, Rev 2.pptx
UPS operation, Rev 2.pptxUPS operation, Rev 2.pptx
UPS operation, Rev 2.pptxJaimohan15
 
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxLiewChiaPing
 
#SolarMOOC Random Problems from 2009 NABCEP STUDY GUIDE
#SolarMOOC Random Problems from 2009 NABCEP STUDY GUIDE#SolarMOOC Random Problems from 2009 NABCEP STUDY GUIDE
#SolarMOOC Random Problems from 2009 NABCEP STUDY GUIDEsolpowerpeople
 
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTREUNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTREPremanandDesai
 
Your electrical safety specilist for all equipments Powered AC and DC
Your electrical safety specilist for all equipments   Powered AC and DCYour electrical safety specilist for all equipments   Powered AC and DC
Your electrical safety specilist for all equipments Powered AC and DCMahesh Chandra Manav
 
Photovoltaic Training Course - Module 1.2 choosing components
Photovoltaic Training Course - Module 1.2 choosing componentsPhotovoltaic Training Course - Module 1.2 choosing components
Photovoltaic Training Course - Module 1.2 choosing componentsLeonardo ENERGY
 
Eesat 2017 Yunasko by Sergii Tychina
Eesat 2017 Yunasko by Sergii TychinaEesat 2017 Yunasko by Sergii Tychina
Eesat 2017 Yunasko by Sergii TychinaYunasko
 

Similar to presentations for the project of solar energy (20)

Seektronics.com 64 skills about switching power supply design
Seektronics.com 64 skills about switching power supply designSeektronics.com 64 skills about switching power supply design
Seektronics.com 64 skills about switching power supply design
 
Capacitores
CapacitoresCapacitores
Capacitores
 
High voltage module
High voltage moduleHigh voltage module
High voltage module
 
PV SYSTEMS, COMPONENTS DEVICES AND APPLICATIONS.ppt
PV SYSTEMS, COMPONENTS DEVICES AND APPLICATIONS.pptPV SYSTEMS, COMPONENTS DEVICES AND APPLICATIONS.ppt
PV SYSTEMS, COMPONENTS DEVICES AND APPLICATIONS.ppt
 
Solar Fundametals - K. Jayaweera May 2022.pdf
Solar Fundametals - K. Jayaweera May 2022.pdfSolar Fundametals - K. Jayaweera May 2022.pdf
Solar Fundametals - K. Jayaweera May 2022.pdf
 
mosfet scaling_
mosfet scaling_mosfet scaling_
mosfet scaling_
 
Iv curve parameters
Iv curve parametersIv curve parameters
Iv curve parameters
 
#Solar #Design #TOOL PV System Design Calculations Report at Neotia Universit...
#Solar #Design #TOOL PV System Design Calculations Report at Neotia Universit...#Solar #Design #TOOL PV System Design Calculations Report at Neotia Universit...
#Solar #Design #TOOL PV System Design Calculations Report at Neotia Universit...
 
Maximum power point tracking algorithms for solar(pv) systems
Maximum power point tracking algorithms for solar(pv) systemsMaximum power point tracking algorithms for solar(pv) systems
Maximum power point tracking algorithms for solar(pv) systems
 
Electrical Engineering Interview Questions
Electrical Engineering Interview QuestionsElectrical Engineering Interview Questions
Electrical Engineering Interview Questions
 
Sinusoidal Response of RC & RL Circuits
Sinusoidal Response of RC & RL CircuitsSinusoidal Response of RC & RL Circuits
Sinusoidal Response of RC & RL Circuits
 
UPS operation, Rev 2.pptx
UPS operation, Rev 2.pptxUPS operation, Rev 2.pptx
UPS operation, Rev 2.pptx
 
Solar ppt
Solar pptSolar ppt
Solar ppt
 
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
 
#SolarMOOC Random Problems from 2009 NABCEP STUDY GUIDE
#SolarMOOC Random Problems from 2009 NABCEP STUDY GUIDE#SolarMOOC Random Problems from 2009 NABCEP STUDY GUIDE
#SolarMOOC Random Problems from 2009 NABCEP STUDY GUIDE
 
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTREUNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
 
Your electrical safety specilist for all equipments Powered AC and DC
Your electrical safety specilist for all equipments   Powered AC and DCYour electrical safety specilist for all equipments   Powered AC and DC
Your electrical safety specilist for all equipments Powered AC and DC
 
Grid connected
Grid connectedGrid connected
Grid connected
 
Photovoltaic Training Course - Module 1.2 choosing components
Photovoltaic Training Course - Module 1.2 choosing componentsPhotovoltaic Training Course - Module 1.2 choosing components
Photovoltaic Training Course - Module 1.2 choosing components
 
Eesat 2017 Yunasko by Sergii Tychina
Eesat 2017 Yunasko by Sergii TychinaEesat 2017 Yunasko by Sergii Tychina
Eesat 2017 Yunasko by Sergii Tychina
 

Recently uploaded

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 

Recently uploaded (20)

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 

presentations for the project of solar energy

  • 2. Topics  What are the different topologies and interconnection methods for a PV system?  What are the various components that are used in a rooftop PV system?  How do we do preliminary sizing of a grid-connected PV System?  How do we arrive at detailed sizing of a grid-connected PV system?  What should be the sizing and specifications of these components?  How to make the necessary drawings/ diagrams of a grid-connected rooftop PV system? Topic : SOLAR POWER PLANT DESIGN
  • 3. Stand-alone PV system. Hybrid PV system. Grid-connected PV system. Types of PV System Topic : SOLAR POWER PLANT DESIGN
  • 4. Metering Arrangements for Rooftop PV Systems A typical metered home. Gross-metered system. Net-metered system (hybrid). Net-metered system. Topic : SOLAR POWER PLANT DESIGN
  • 5. List of Equipment & Material  PV Module  DC Cable (PV modules to SJB)  String Junction Box (SJB)  DC Cable (SJB to Inverter)  Cable Tray/ Conduit  DC Isolator*  Inverter  AC Cable  Isolation Transformer*  AC Distribution Box  Lightning Arrestor*  Earthing Cable  Earthing Strip  Earth Pit (2 or 4 or more)  Generation Meter  Bi-directional Net-meter  DC Fuse  DC Surge Protection Device (SPD)  AC Surge Protection Device (SPD)  Isolator: MCB/ ELCB/ RCCB  Labels Topic : SOLAR POWER PLANT DESIGN
  • 6. 2-Step System Sizing  Step 1: PV System Capacity  Where we specify:  DC Capacity  AC Capacity  Battery Capacity  Capacity is based on:  Energy requirement  Space limitation  Budget limitation  Policy limitation  Step 2: Specific Equipment Specifications  Where we specify:  Make and model  Quantities & Sizing  Dimensions (e.g. cable length)  Repute Brand  Selection is based on:  Specification  Availability  Cost Topic : SOLAR POWER PLANT DESIGN
  • 7. Step 1 (Given)  Case study:  Type of system: Grid-connected  Capacity constraint: Available space  Capacity for which space is available: 30 kW  That’s it!!! Topic : SOLAR POWER PLANT DESIGN
  • 8. Step 2.1: Site Survey  Undertake a detailed site survey (if not already done so) to identify:  Shadow-casting features and shadow-free area  Location for mounting inverter(s) and AC Junction Boxes, typically on terrace/ roof  Location for interconnection point (distribution panel of house/ building), typically on ground floor  Location where earth pits will be installed  (Check if distribution panel has extra feeder/ interconnection point of sufficient capacity) [Note: These are in addition to other steps involved in a site survey.] Topic : SOLAR POWER PLANT DESIGN
  • 9. Room, 3 meter up Site Survey Drawing Location for PV Arrays Location for: • String (DC) Junction Box • Inverter(s) • AC Junction Box DC Cable Routing Earth Pit Location AC Cable Routing Earthing Strip Routing 17.77 m X 13.10 m = 232.79 m2 (~19.4 kW) 22.07 m X 5.45 m = 120.28 m2 (~10.02 kW) Topic : SOLAR POWER PLANT DESIGN
  • 10. Step 2.2: PV Module Selection
  • 11. Step 2.2: Grid-connected Inverter Selection Topic : SOLAR POWER PLANT DESIGN
  • 12. Modules and Strings (1/5)  Let’s count PV modules…  PV Module (DC) Capacity:  20 kW; 10 kW  Estimate the total number of PV Modules:  20,000 / 300 = 67; 10,000 / 300 = 33  Which inverters can be used? (Ref. Max. PV Power)  17 kW; 10 kW Topic : SOLAR POWER PLANT DESIGN
  • 13. Modules and Strings (2/5)  How many modules in series (i.e. string size) can the inverter accept?  What is the inverter’s MPPT range?  410 … 850 V; 460 … 850 V  What is the maximum number of modules per string that the inverter can accept within the ‘MPPT range’?  850 / VMP = 850 / 36.72 = ~23; 850 / VMP = 850 / 36.72 = ~23  What is the maximum number of modules per string without exceeding the inverter’s ‘Max. DC Voltage’?  1000 / VOC = 1000 / 45.50 = ~21; 1000 / VOC = 1000 / 45.50 = ~21  What is the maximum number of modules per string acceptable to the inverter?  21; 21 Topic : SOLAR POWER PLANT DESIGN
  • 14. Modules and Strings (3/5)  Let’s converge…  Can we have 1 string per inverter?  i.e. 67 modules per string? i.e. 33 modules per string?  NO NO  Can we have 2 strings per inverter?  i.e. 34 modules per string? i.e. 17 modules per string?  NO Maybe!!! Let’s freeze this for now.  Can we have 3 strings per inverter?  i.e. 22 modules per string?  NO  Can we have 4 strings per inverter?  i.e. 17 modules per string?  Maybe!!! Let’s freeze this for now. Topic : SOLAR POWER PLANT DESIGN
  • 15. Modules and Strings (4/5)  Let’s check…  What is the VMP of the string be within MPPT range at STC?  VMP: 17 x 36.72 V = 624.24 V; VMP: 17 x 36.72 V = 624.24 V  YES; YES;  Will the VMP of the string be within MPPT range on a bright sunny day?  Bright sunny day: 1000 W/m2; Max. TAMB: 42°C  Max. TMOD: 73°C  VMP: 17 x 31.07 V = 528.19 V; VMP: 17 x 31.07 V = 528.19 V  YES; YES  Will the maximum string voltage be less than inverter’s ‘Max. DC Voltage’?  VOC: 17 x 45.50 V = 773.50 V; VOC: 17 x 45.50 V = 773.50 V  Hence, 17 modules per string is suitable for the inverter.  DC Capacity: DC Capacity:  300 W x 17 x 4 = 20.4 kW; 300 W x 17 x 2 = 10.2 kW Topic : SOLAR POWER PLANT DESIGN
  • 16. Modules and Strings (5/5)  Let’s try to push the string size further…  Can we use 18 modules per string instead of 17?  DC Capacity for 20 kW system:  300 W per module x 18 modules per string x 4 strings  = 21.6 kW  NO! This is more than inverter’s ‘Recommended Max. PV Power’.  DC Capacity for 10 kW system:  300 W per module x 18 modules per string x 2 strings  = 10.8 kW  YES! This is within the inverter’s ‘Recommended Max. PV Power’. Topic : SOLAR POWER PLANT DESIGN
  • 17. String Junction Box (SJB) Specification (1/3)  How many inputs and outputs are required in the String Junction Box…  For 20 kW system? For 10 kW system?  If the number of PV strings are greater than number of input DC connections to the inverter, then we will have to connect strings in parallel in the SJB.  No. of PV strings:  4 2  No. of input DC connections to the inverter:  6 3  Hence, are the strings required to be connected in parallel?  NO NO  SJB input-output specification:  4-in 4-out 2-in 2-out  These can be combined as 6-in 6-out Topic : SOLAR POWER PLANT DESIGN
  • 18. String Junction Box (SJB) Specification (2/3)  Let’s specify the 4-in 4-out SJB…  Cable Gland/ Connector  Incoming DC: 4 pairs of male/ female panel-mount MC4 connectors  Earthing: 1 Nos. of (M16) Cable Gland for 6 mm2 earthing cable.  Fuse-holders and Fuses  Fuse rating > ISC x 1.25 x 1.25 = 8.65 x 1.25 x 1.25 = 13.51 A  15A, 1000 VDC  Fuse-holder (Fuse-base) > Fuse rating  30 A, 1000VDC  8 Nos., each  Surge Protection Device (SPD) (i.e. Surge Arrestors)  1 Nos. Type II, 1000 VDC, 40 kA  Terminal Blocks  Required when connecting SPD are connected in parallel. Topic : SOLAR POWER PLANT DESIGN
  • 19. String Junction Box (SJB) Specification (3/3)  Internal cables:  DC (positive and negative): 4 mm2 PV cables  Earthing Cable: 6 mm2 copper cable  Enclosure  Thermoplastic Polycarbonate  Degree of protection: IP65  Design Temperature > 50 °C Ambient Topic : SOLAR POWER PLANT DESIGN
  • 20. DC Cable Sizing  DC Cables need to conform to 2 requirements:  Ampacity  Ampacity is the current-carrying capacity of the conductor  Ampacity of conductor should be more than ISC x 1.25 x 1.25 of the string  Voltage Drop  Should be less than 2%  Note that these values should be calculated at the:  Actual PV module temperatures (E.g. 70°C), and  Actual/ ambient (E.g. 45°C) temperature of PV cable. Topic : SOLAR POWER PLANT DESIGN
  • 21. DC Cable Resistivity & Ampacity Topic : SOLAR POWER PLANT DESIGN
  • 22. Ampacity Deration due to Temperature Topic : SOLAR POWER PLANT DESIGN
  • 23. Check for Ampacity  Step 1: For PV string:  ISC = 8.65 A  Hence, Ampacity of cable should be more than 13.51 A.  Step 2: For 4 mm2 PV cable:  Ampacity @ 20°C = 44 A  (Because multiple cables will be laid together in the cable tray.)  Ampacity deration factor @ 41-45°C ambient temperature = 0.87  Hence, Ampacity of the PV cable is 38.28 A.  Ampacity of the PV cable is more than the PV string current.  Hence, first condition is met. Topic : SOLAR POWER PLANT DESIGN
  • 24. Check for Voltage Drop  Step 1: Maximum length of the PV cable is from the farthest PV module  (17 + 13 + 3 + 3 + 22 + 12 + 5.5 + 3 + 4.5) m + Extra 10%  = ~100 m  Step 2: Resistance of the PV cable  R @ 20°C = 5.09 Ω/ km x 0.1 km = 0.51 Ω  R @ 70°C = R20°C x [ 1 + α ( T Cable – 20 ) ] = 0.61 Ω  Where,  For copper, α = 0.393 % / °C  Assume PV cable is at 70°C  Step 3: Voltage drop = IMP x R = 8.17 A x 0.61 Ω = 5 V  Step 4: VMP, String @ 70°C = 17 x 31.43 V = 534.3 V  Step 5: Voltage Drop in % = 0.93%, which is less than 2%  Hence, second condition is also met. Topic : SOLAR POWER PLANT DESIGN
  • 25. AC Cable Sizing  AC cables are required from:  Inverter to nearby AC Distribution Box  AC Distribution Box to Main AC Distribution Box  Note: Same ampacity and voltage drop rules apply as in DC cables. Topic : SOLAR POWER PLANT DESIGN
  • 26. AC Cable: Inverter to nearby AC Distribution Box  Let’s calculate for two inverters:  20 kW System; 10 kW System  What is the maximum output AC current?  3 x 29 A (i.e. 3φ); 3 x 16 A (i.e. 3φ)  After safety factor…  3 x 36.25 A; 3 x 20 A  Which 4-C AC cable from the datasheet can carry this current?  Note: Usually, the length of this cable is not substantial, and hence, voltage drops are very minor.  Aluminium,10 mm2; Aluminium, 4 mm2  Note: Often for uniformity and convenience of procurement, we may use the same AC Cables for both inverters:  Aluminium,10 mm2; Aluminium, 10 mm2 Topic : SOLAR POWER PLANT DESIGN
  • 27. AC Cable: ACDB to ACDB (Ampacity)  Once all the inverter outputs are combined in the ACDB near the inverter, it will add up the currents and evacuate power using a single AC cable.  In our case, combined AC current: 3 x 45 A (i.e. 3φ)  Hence, after considering safety factor: 3 x 56.25 A  Which AC cable is suitable from the datasheet?  Aluminium, 25 mm2  Note: For long distances, it is preferred to used armoured cables. Topic : SOLAR POWER PLANT DESIGN
  • 28. AC Cable: ACDB to ACDB (Voltage Drop)  Let’s assume that:  The installation (including inverter) is on the terrace/ roof above the 3rd floor of the building, and main ACDB of the building is on the ground floor, and  The surveyor determines this cable routing distance to be 25 m.  From datasheet, resistance of 25 mm2 Aluminium cable, R:  R @ 20 °C = 1.2 Ω per km x 0.025 km = 0.03 Ω  Therefore:  R @ 75°C = R20°C x [ 1 + α ( T Cable – 20 ) ] = 0.036 Ω  Voltage drop = I x R = 45 A x 0.036 Ω = 1.6 V  Voltage drop in % = 1.6 / 230 = 0.7%  This is within the 2% limit, hence 25 mm2 Aluminium cable is acceptable. Topic : SOLAR POWER PLANT DESIGN
  • 29. AC Distribution Box (ACDB)  How many in? How many out?  2-in, because two separate inputs will come from the two inverters  In our example, each wire is 10 mm2  1-out, because we combine the above two and evacuate in a single wire.  In our example, this wire is 25 mm2  What do we need in the AC Junction Box?  MCB (Miniature Circuit Breaker) for each incomer from inverter  To individually disconnect each inverter, and protect from overcurrent.  From datasheet: Rated current: 40 A, 240 V, Breaking Capacity: 10 kA  SPD (Surge Protection Device)  From datasheet: 400 VAC, Type 2 (4-pole)  RCCB (Residual Current Circuit Breaker)  To protect inverter from residual current and earth leakage faults  From datasheet: 63 Amp, 100 mA (4-pole)) Topic : SOLAR POWER PLANT DESIGN
  • 30. Drawings  Single Line Diagram  Equipment/ Module/ Project Layout Diagram  Cable Route Plan  Earthing Layout Diagram Topic : SOLAR POWER PLANT DESIGN

Editor's Notes

  1. Vmp(STC) = 36.7 V, ΔT = 73-25= 48°C , ΔV = -0.32 % / °C x 48°C = -15.36 % . Vmp (73°) = 36.72 x 84.64 = 31.07 (100-15.36=84.64%)