2. Topics
What are the different topologies and interconnection methods for a PV
system?
What are the various components that are used in a rooftop PV system?
How do we do preliminary sizing of a grid-connected PV System?
How do we arrive at detailed sizing of a grid-connected PV system?
What should be the sizing and specifications of these components?
How to make the necessary drawings/ diagrams of a grid-connected rooftop
PV system?
Topic : SOLAR POWER PLANT DESIGN
3. Stand-alone PV system.
Hybrid PV system.
Grid-connected PV system.
Types of PV System
Topic : SOLAR POWER PLANT DESIGN
4. Metering Arrangements for Rooftop PV Systems
A typical metered home. Gross-metered system.
Net-metered system (hybrid).
Net-metered system.
Topic : SOLAR POWER PLANT DESIGN
5. List of Equipment & Material
PV Module
DC Cable (PV modules to SJB)
String Junction Box (SJB)
DC Cable (SJB to Inverter)
Cable Tray/ Conduit
DC Isolator*
Inverter
AC Cable
Isolation Transformer*
AC Distribution Box
Lightning Arrestor*
Earthing Cable
Earthing Strip
Earth Pit (2 or 4 or more)
Generation Meter
Bi-directional Net-meter
DC Fuse
DC Surge Protection Device (SPD)
AC Surge Protection Device (SPD)
Isolator: MCB/ ELCB/ RCCB
Labels
Topic : SOLAR POWER PLANT DESIGN
6. 2-Step System Sizing
Step 1: PV System Capacity
Where we specify:
DC Capacity
AC Capacity
Battery Capacity
Capacity is based on:
Energy requirement
Space limitation
Budget limitation
Policy limitation
Step 2: Specific Equipment
Specifications
Where we specify:
Make and model
Quantities & Sizing
Dimensions (e.g. cable length)
Repute Brand
Selection is based on:
Specification
Availability
Cost
Topic : SOLAR POWER PLANT DESIGN
7. Step 1 (Given)
Case study:
Type of system: Grid-connected
Capacity constraint: Available space
Capacity for which space is available: 30 kW
That’s it!!!
Topic : SOLAR POWER PLANT DESIGN
8. Step 2.1: Site Survey
Undertake a detailed site survey (if not already done so) to identify:
Shadow-casting features and shadow-free area
Location for mounting inverter(s) and AC Junction Boxes, typically on terrace/ roof
Location for interconnection point (distribution panel of house/ building), typically
on ground floor
Location where earth pits will be installed
(Check if distribution panel has extra feeder/ interconnection point of sufficient
capacity)
[Note: These are in addition to other steps involved in a site survey.]
Topic : SOLAR POWER PLANT DESIGN
9. Room, 3 meter up
Site Survey Drawing
Location for PV Arrays Location for:
• String (DC) Junction Box
• Inverter(s)
• AC Junction Box
DC Cable Routing
Earth Pit Location
AC Cable Routing
Earthing Strip Routing
17.77 m X 13.10 m
= 232.79 m2
(~19.4 kW)
22.07 m X 5.45 m = 120.28
m2
(~10.02 kW)
Topic : SOLAR POWER PLANT DESIGN
12. Modules and Strings (1/5)
Let’s count PV modules…
PV Module (DC) Capacity:
20 kW; 10 kW
Estimate the total number of PV Modules:
20,000 / 300 = 67; 10,000 / 300 = 33
Which inverters can be used? (Ref. Max. PV Power)
17 kW; 10 kW
Topic : SOLAR POWER PLANT DESIGN
13. Modules and Strings (2/5)
How many modules in series (i.e. string size) can the inverter accept?
What is the inverter’s MPPT range?
410 … 850 V; 460 … 850 V
What is the maximum number of modules per string that the inverter can accept
within the ‘MPPT range’?
850 / VMP = 850 / 36.72 = ~23; 850 / VMP = 850 / 36.72 = ~23
What is the maximum number of modules per string without exceeding the inverter’s
‘Max. DC Voltage’?
1000 / VOC = 1000 / 45.50 = ~21; 1000 / VOC = 1000 / 45.50 = ~21
What is the maximum number of modules per string acceptable to the inverter?
21; 21
Topic : SOLAR POWER PLANT DESIGN
14. Modules and Strings (3/5)
Let’s converge…
Can we have 1 string per inverter?
i.e. 67 modules per string? i.e. 33 modules per string?
NO NO
Can we have 2 strings per inverter?
i.e. 34 modules per string? i.e. 17 modules per string?
NO Maybe!!! Let’s freeze this for now.
Can we have 3 strings per inverter?
i.e. 22 modules per string?
NO
Can we have 4 strings per inverter?
i.e. 17 modules per string?
Maybe!!! Let’s freeze this for now.
Topic : SOLAR POWER PLANT DESIGN
15. Modules and Strings (4/5)
Let’s check…
What is the VMP of the string be within MPPT range at STC?
VMP: 17 x 36.72 V = 624.24 V; VMP: 17 x 36.72 V = 624.24 V
YES; YES;
Will the VMP of the string be within MPPT range on a bright sunny day?
Bright sunny day: 1000 W/m2; Max. TAMB: 42°C Max. TMOD: 73°C
VMP: 17 x 31.07 V = 528.19 V; VMP: 17 x 31.07 V = 528.19 V
YES; YES
Will the maximum string voltage be less than inverter’s ‘Max. DC Voltage’?
VOC: 17 x 45.50 V = 773.50 V; VOC: 17 x 45.50 V = 773.50 V
Hence, 17 modules per string is suitable for the inverter.
DC Capacity: DC Capacity:
300 W x 17 x 4 = 20.4 kW; 300 W x 17 x 2 = 10.2 kW
Topic : SOLAR POWER PLANT DESIGN
16. Modules and Strings (5/5)
Let’s try to push the string size further…
Can we use 18 modules per string instead of 17?
DC Capacity for 20 kW system:
300 W per module x 18 modules per string x 4 strings
= 21.6 kW
NO! This is more than inverter’s ‘Recommended Max. PV Power’.
DC Capacity for 10 kW system:
300 W per module x 18 modules per string x 2 strings
= 10.8 kW
YES! This is within the inverter’s ‘Recommended Max. PV Power’.
Topic : SOLAR POWER PLANT DESIGN
17. String Junction Box (SJB) Specification (1/3)
How many inputs and outputs are required in the String Junction Box…
For 20 kW system? For 10 kW system?
If the number of PV strings are greater than number of input DC connections to the
inverter, then we will have to connect strings in parallel in the SJB.
No. of PV strings:
4 2
No. of input DC connections to the inverter:
6 3
Hence, are the strings required to be connected in parallel?
NO NO
SJB input-output specification:
4-in 4-out 2-in 2-out
These can be combined as 6-in 6-out
Topic : SOLAR POWER PLANT DESIGN
18. String Junction Box (SJB) Specification (2/3)
Let’s specify the 4-in 4-out SJB…
Cable Gland/ Connector
Incoming DC: 4 pairs of male/ female panel-mount MC4 connectors
Earthing: 1 Nos. of (M16) Cable Gland for 6 mm2 earthing cable.
Fuse-holders and Fuses
Fuse rating > ISC x 1.25 x 1.25 = 8.65 x 1.25 x 1.25 = 13.51 A 15A, 1000 VDC
Fuse-holder (Fuse-base) > Fuse rating 30 A, 1000VDC
8 Nos., each
Surge Protection Device (SPD) (i.e. Surge Arrestors)
1 Nos. Type II, 1000 VDC, 40 kA
Terminal Blocks
Required when connecting SPD are connected in parallel.
Topic : SOLAR POWER PLANT DESIGN
19. String Junction Box (SJB) Specification (3/3)
Internal cables:
DC (positive and negative): 4 mm2 PV cables
Earthing Cable: 6 mm2 copper cable
Enclosure
Thermoplastic Polycarbonate
Degree of protection: IP65
Design Temperature > 50 °C Ambient
Topic : SOLAR POWER PLANT DESIGN
20. DC Cable Sizing
DC Cables need to conform to 2 requirements:
Ampacity
Ampacity is the current-carrying capacity of the conductor
Ampacity of conductor should be more than ISC x 1.25 x 1.25 of the string
Voltage Drop
Should be less than 2%
Note that these values should be calculated at the:
Actual PV module temperatures (E.g. 70°C), and
Actual/ ambient (E.g. 45°C) temperature of PV cable.
Topic : SOLAR POWER PLANT DESIGN
23. Check for Ampacity
Step 1: For PV string:
ISC = 8.65 A
Hence, Ampacity of cable should be more than 13.51 A.
Step 2: For 4 mm2 PV cable:
Ampacity @ 20°C = 44 A
(Because multiple cables will be laid together in the cable tray.)
Ampacity deration factor @ 41-45°C ambient temperature = 0.87
Hence, Ampacity of the PV cable is 38.28 A.
Ampacity of the PV cable is more than the PV string current.
Hence, first condition is met.
Topic : SOLAR POWER PLANT DESIGN
24. Check for Voltage Drop
Step 1: Maximum length of the PV cable is from the farthest PV module
(17 + 13 + 3 + 3 + 22 + 12 + 5.5 + 3 + 4.5) m + Extra 10%
= ~100 m
Step 2: Resistance of the PV cable
R @ 20°C = 5.09 Ω/ km x 0.1 km = 0.51 Ω
R @ 70°C = R20°C x [ 1 + α ( T Cable – 20 ) ] = 0.61 Ω
Where,
For copper, α = 0.393 % / °C
Assume PV cable is at 70°C
Step 3: Voltage drop = IMP x R = 8.17 A x 0.61 Ω = 5 V
Step 4: VMP, String @ 70°C = 17 x 31.43 V = 534.3 V
Step 5: Voltage Drop in % = 0.93%, which is less than 2%
Hence, second condition is also met.
Topic : SOLAR POWER PLANT DESIGN
25. AC Cable Sizing
AC cables are required from:
Inverter to nearby AC Distribution Box
AC Distribution Box to Main AC Distribution Box
Note: Same ampacity and voltage drop rules apply as in DC cables.
Topic : SOLAR POWER PLANT DESIGN
26. AC Cable: Inverter to nearby AC Distribution Box
Let’s calculate for two inverters:
20 kW System; 10 kW System
What is the maximum output AC current?
3 x 29 A (i.e. 3φ); 3 x 16 A (i.e. 3φ)
After safety factor…
3 x 36.25 A; 3 x 20 A
Which 4-C AC cable from the datasheet can carry this current?
Note: Usually, the length of this cable is not substantial, and hence, voltage drops
are very minor.
Aluminium,10 mm2; Aluminium, 4 mm2
Note: Often for uniformity and convenience of procurement, we may use the
same AC Cables for both inverters:
Aluminium,10 mm2; Aluminium, 10 mm2
Topic : SOLAR POWER PLANT DESIGN
27. AC Cable: ACDB to ACDB (Ampacity)
Once all the inverter outputs are combined in the ACDB near the inverter, it will add up the
currents and evacuate power using a single AC cable.
In our case, combined AC current: 3 x 45 A (i.e. 3φ)
Hence, after considering safety factor: 3 x 56.25 A
Which AC cable is suitable from the datasheet?
Aluminium, 25 mm2
Note: For long distances, it is preferred to used armoured cables.
Topic : SOLAR POWER PLANT DESIGN
28. AC Cable: ACDB to ACDB (Voltage Drop)
Let’s assume that:
The installation (including inverter) is on the terrace/ roof above the 3rd floor of the building,
and main ACDB of the building is on the ground floor, and
The surveyor determines this cable routing distance to be 25 m.
From datasheet, resistance of 25 mm2 Aluminium cable, R:
R @ 20 °C = 1.2 Ω per km x 0.025 km = 0.03 Ω
Therefore:
R @ 75°C = R20°C x [ 1 + α ( T Cable – 20 ) ] = 0.036 Ω
Voltage drop = I x R = 45 A x 0.036 Ω = 1.6 V
Voltage drop in % = 1.6 / 230 = 0.7%
This is within the 2% limit, hence 25 mm2 Aluminium cable is acceptable.
Topic : SOLAR POWER PLANT DESIGN
29. AC Distribution Box (ACDB)
How many in? How many out?
2-in, because two separate inputs will come from the two inverters
In our example, each wire is 10 mm2
1-out, because we combine the above two and evacuate in a single wire.
In our example, this wire is 25 mm2
What do we need in the AC Junction Box?
MCB (Miniature Circuit Breaker) for each incomer from inverter
To individually disconnect each inverter, and protect from overcurrent.
From datasheet: Rated current: 40 A, 240 V, Breaking Capacity: 10 kA
SPD (Surge Protection Device)
From datasheet: 400 VAC, Type 2 (4-pole)
RCCB (Residual Current Circuit Breaker)
To protect inverter from residual current and earth leakage faults
From datasheet: 63 Amp, 100 mA (4-pole))
Topic : SOLAR POWER PLANT DESIGN
30. Drawings
Single Line Diagram
Equipment/ Module/ Project Layout Diagram
Cable Route Plan
Earthing Layout Diagram
Topic : SOLAR POWER PLANT DESIGN