SlideShare a Scribd company logo
1 of 28
Flanders Electric – Engineering Division   Welcomes You to an Overview of  Reconditioned Switchgear
Reasons for Reconditioning Switchgear Cost Savings Reuse material Buswork Building/enclosure Components Energy Efficiencies Shorter Production outages often required with  switchgear upgrades
Technology Upgrade Obsolete Parts Replacement Vacuum Contactors/Breakers Solid State Protection Web Enabled Power Monitoring Equipment (wireless Ethernet) Reasons for Reconditioning Switchgear – con’t Environmental Considerations Removal of Equipment From Old Mines More Energy Efficient Components
Meggar/Hi Pot Line and Load Conductors Visually inspect for hot spots/fluid leaks etc. Thoroughly Clean Compartment Remove:  Dirt,  Rocks, Excess oils, Rodent infestation Inspect all components for excess wear and damage Basic inspections/cleanings on all components Visually inspect all Connections – i.e.  Power Cable Clamps (draglines)   Fuse Clips (loose, corrosion) Inspect Insulators, Bushings and Surge Arrestors
For Load Break Switches Adjust and lubricate linkages as necessary Clean and Calibrate Electro-Mechanical Protection Devices  (if not being replaced) Oil Analysis where necessary Basic inspections/cleanings on all components (con’t)
Technology Upgrades Typically  Recommended Change OCB’s (Oil Filled Circuit Breakers) to Vacuum  Circuit Breakers Replace Capacitive Trip Devices – Depending upon Age Change Electro-Mechanical Overload protection devices to  Solid State – Improve Repeatability and Accuracy
Replace low voltage, air contactor size 4 and above with  vacuum contactors and any medium voltage with vacuum contactor   -Improves contactor life (number of cycles) -Minimizes effect of environmental elements on contacts Replace old lighting with more energy efficient lighting -High pressure sodium or Metal Halide on outside  -Replace incandescent lights with fluorescent bulbs in  sockets Technology Upgrades Typically  Recommended  (con’t)
Safety Related items – must do Upgrade all receptacles to GFCI type Install new safety signage/warning labels Simulate all Ground Faults Repair all door interlocks per MSHA Check Ground Monitor (Coal Mines)
Standards Followed National Electrical Code Mining Safety and Health Administration UL/c UL – Underwriters Laboratory ANSI – American National Standards Institute NFPA 79 – Electrical Standard for Industrial Machinery EIA RS821 – Electronics Industries Assoc.: Construction Standards
Just a few examples
EXAMPLES – 1  BEFORE
EXAMPLE - 2
EXAMPLE -3  INSTALLATIONS
EXAMPLE 4
EXAMPLE -5
EXAMPLE – 6  BEFORE
EXAMPLE – 7  AFTER
Example # 1  Medium Voltage Pump Sub  Specifications 7200/480Y, 225KVA Description of operation - Transformer and Breaker to Feed Pumps for  Water Removal
Material  Cost $6,500.00 Repair Load Switch Replace two 480VAC Breakers Labor cost  $1,200.00 Total Cost  $7,700.00 Example # 1  Medium Voltage Pump Sub Summary  Estimated Cost of new  $30,000
Example # 2  OCB – Vacuum Retrofit  Specifications Voltage: 7200VAC Current:  400 Amp Description of Operation – Dragline Contactor for Motor Starting with  Overload and Ground Fault Protection
Material  Cost $9,000.00 Labor cost  $1000.00 Total Cost  $10,000.00 Example # 2  OCB - Vacuum Retrofit Summary  Other Savings/Benefits:  Installation of new contactor  during normal outage time.  Estimated Cost of new  Switchgear:  $55,000.00
Example # 3 Portable Breaker House Specifications Voltage: 4160 VAC Current:  1200 Amps Description of operation – Converted 7200VAC Portable Breaker House to 4160 Line Drop Station
Items Replaced  (2) Potential Transformers (PT’s) (3) 5kV Bushing Assemblies Labor cost  $8,000.00 Total Cost  $13,000.00 Example # 3  Portable Breaker House Summary  Estimated Cost of new  $50,000.00 Material Cost  $5,000.00
Example # 4 -  3 Way Switch House Specifications Voltage  7200 VAC Current  400 amps Description of operation  - Switches to Provide Alternative Feed for  Distribution.  Single Main to 3 feeds
Material Cost  $900.00 Mechanical Interlocks Calibration  Labor cost  $1,000.00 Total Cost  $1,900.00 Example # 4  3 Way Switch House Summary  Estimated Cost of new  $25,000.00
Example # 5 Large Portable Substation Specifications Voltage  23,000VAC Current  1000 amps Description of operation - Power Feed and Distribution to Dragline
Items Replaced  Replaced 25KV OCB Contacts and Changed Oil Ground Monitor GE Potential Transformer Labor cost  $11,000.00 Total Cost   $27,000.00 Example # 5  Large Portable Switchgear Summary  Estimated Cost of new  $75,000.00 Material Cost $16,000.00  (includes purchase of used skid)
Questions ???

More Related Content

What's hot

Brian Jonathan - FYP Extended Summary
Brian Jonathan - FYP Extended SummaryBrian Jonathan - FYP Extended Summary
Brian Jonathan - FYP Extended SummaryBrian Jonathan
 
JIE_hybrid_PVT_model
JIE_hybrid_PVT_modelJIE_hybrid_PVT_model
JIE_hybrid_PVT_modelSam Sim
 
BTECH/MTECH PROJECTS 2015
BTECH/MTECH PROJECTS 2015BTECH/MTECH PROJECTS 2015
BTECH/MTECH PROJECTS 2015Aditya Undralla
 
Latest 2016 IEEE Electrical Projects List for BTech and MTech
Latest 2016 IEEE Electrical Projects List for BTech and MTechLatest 2016 IEEE Electrical Projects List for BTech and MTech
Latest 2016 IEEE Electrical Projects List for BTech and MTechAsoka Technologies
 
IRJET-Study of Three State Switching Cell Based DC-To-DC Converter
IRJET-Study of Three State Switching Cell Based DC-To-DC ConverterIRJET-Study of Three State Switching Cell Based DC-To-DC Converter
IRJET-Study of Three State Switching Cell Based DC-To-DC ConverterIRJET Journal
 
Wind Loads on PV roof top solar installations.
Wind Loads on PV roof top solar installations.Wind Loads on PV roof top solar installations.
Wind Loads on PV roof top solar installations.David Cohen
 
A laboratory model of a dual active bridge dc-dc converter for a smart user n...
A laboratory model of a dual active bridge dc-dc converter for a smart user n...A laboratory model of a dual active bridge dc-dc converter for a smart user n...
A laboratory model of a dual active bridge dc-dc converter for a smart user n...Alessandro Burgio
 
Design of a Single Phase Isolated Bidirectional AC to DC Converter for Batter...
Design of a Single Phase Isolated Bidirectional AC to DC Converter for Batter...Design of a Single Phase Isolated Bidirectional AC to DC Converter for Batter...
Design of a Single Phase Isolated Bidirectional AC to DC Converter for Batter...Tom Gibson
 

What's hot (11)

Brian Jonathan - FYP Extended Summary
Brian Jonathan - FYP Extended SummaryBrian Jonathan - FYP Extended Summary
Brian Jonathan - FYP Extended Summary
 
JIE_hybrid_PVT_model
JIE_hybrid_PVT_modelJIE_hybrid_PVT_model
JIE_hybrid_PVT_model
 
BTECH/MTECH PROJECTS 2015
BTECH/MTECH PROJECTS 2015BTECH/MTECH PROJECTS 2015
BTECH/MTECH PROJECTS 2015
 
Power[1]
Power[1]Power[1]
Power[1]
 
Improved Time Responses of PI & FL Controlled SEPIC Converter based Series Re...
Improved Time Responses of PI & FL Controlled SEPIC Converter based Series Re...Improved Time Responses of PI & FL Controlled SEPIC Converter based Series Re...
Improved Time Responses of PI & FL Controlled SEPIC Converter based Series Re...
 
Latest 2016 IEEE Electrical Projects List for BTech and MTech
Latest 2016 IEEE Electrical Projects List for BTech and MTechLatest 2016 IEEE Electrical Projects List for BTech and MTech
Latest 2016 IEEE Electrical Projects List for BTech and MTech
 
IRJET-Study of Three State Switching Cell Based DC-To-DC Converter
IRJET-Study of Three State Switching Cell Based DC-To-DC ConverterIRJET-Study of Three State Switching Cell Based DC-To-DC Converter
IRJET-Study of Three State Switching Cell Based DC-To-DC Converter
 
Wind Loads on PV roof top solar installations.
Wind Loads on PV roof top solar installations.Wind Loads on PV roof top solar installations.
Wind Loads on PV roof top solar installations.
 
A laboratory model of a dual active bridge dc-dc converter for a smart user n...
A laboratory model of a dual active bridge dc-dc converter for a smart user n...A laboratory model of a dual active bridge dc-dc converter for a smart user n...
A laboratory model of a dual active bridge dc-dc converter for a smart user n...
 
Design of a Single Phase Isolated Bidirectional AC to DC Converter for Batter...
Design of a Single Phase Isolated Bidirectional AC to DC Converter for Batter...Design of a Single Phase Isolated Bidirectional AC to DC Converter for Batter...
Design of a Single Phase Isolated Bidirectional AC to DC Converter for Batter...
 
Project list 2019-2020
Project list 2019-2020Project list 2019-2020
Project list 2019-2020
 

Viewers also liked

Qs 7001
Qs 7001Qs 7001
Qs 7001ACN
 
Five o'clock tea...
Five o'clock tea...Five o'clock tea...
Five o'clock tea...Kadi Mitt
 
Nd pharma green science for life
 Nd pharma green science for life Nd pharma green science for life
Nd pharma green science for lifeND PHARMA BIOTECH
 
Are you going to fight or fleet.pptx (1)
Are you going to fight or fleet.pptx (1)Are you going to fight or fleet.pptx (1)
Are you going to fight or fleet.pptx (1)Shardae17
 
Alokraj Resume
Alokraj ResumeAlokraj Resume
Alokraj ResumeALOK RAJ
 
7 mangus intestinal transplantation
7 mangus intestinal transplantation7 mangus intestinal transplantation
7 mangus intestinal transplantationangel4567
 
Alokraj Application
Alokraj ApplicationAlokraj Application
Alokraj ApplicationALOK RAJ
 

Viewers also liked (8)

Qs 7001
Qs 7001Qs 7001
Qs 7001
 
Five o'clock tea...
Five o'clock tea...Five o'clock tea...
Five o'clock tea...
 
Nd pharma green science for life
 Nd pharma green science for life Nd pharma green science for life
Nd pharma green science for life
 
Are you going to fight or fleet.pptx (1)
Are you going to fight or fleet.pptx (1)Are you going to fight or fleet.pptx (1)
Are you going to fight or fleet.pptx (1)
 
Alokraj Resume
Alokraj ResumeAlokraj Resume
Alokraj Resume
 
7 mangus intestinal transplantation
7 mangus intestinal transplantation7 mangus intestinal transplantation
7 mangus intestinal transplantation
 
Alokraj Application
Alokraj ApplicationAlokraj Application
Alokraj Application
 
Decrecimiento en la escuela.
Decrecimiento en la escuela.Decrecimiento en la escuela.
Decrecimiento en la escuela.
 

Similar to Prsn

CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxLiewChiaPing
 
Legend Power Overview 97 2003 120410 1256 Do
Legend Power   Overview 97 2003 120410 1256 DoLegend Power   Overview 97 2003 120410 1256 Do
Legend Power Overview 97 2003 120410 1256 DoLegend Power
 
Ramendra summer training presentation
Ramendra summer training presentationRamendra summer training presentation
Ramendra summer training presentationRamendra Dhiman
 
Session 05 grid connected inverter
Session 05   grid connected inverterSession 05   grid connected inverter
Session 05 grid connected inverterChirag Jain
 
Electrical component at airport for airfield lighting circuit
Electrical component at airport for airfield lighting circuitElectrical component at airport for airfield lighting circuit
Electrical component at airport for airfield lighting circuitRLarivee
 
Power factor corrector
Power factor correctorPower factor corrector
Power factor correctorJoeChueng
 
Designing an Uninterruptible Power Supply
Designing an Uninterruptible Power SupplyDesigning an Uninterruptible Power Supply
Designing an Uninterruptible Power SupplyLeonardo ENERGY
 
Getting the Most out of your Electrical Room
Getting the Most out of your Electrical RoomGetting the Most out of your Electrical Room
Getting the Most out of your Electrical Roommichaeljmack
 
A Five – Level Integrated AC – DC Converter
A Five – Level Integrated AC – DC ConverterA Five – Level Integrated AC – DC Converter
A Five – Level Integrated AC – DC ConverterIJTET Journal
 
Distributed Generation By Roland Desouza
Distributed Generation By Roland DesouzaDistributed Generation By Roland Desouza
Distributed Generation By Roland DesouzaIEEEP Karachi
 
ELECHTRICAL COMMISSIONING TECHNICIAN 2201622
ELECHTRICAL   COMMISSIONING  TECHNICIAN   2201622ELECHTRICAL   COMMISSIONING  TECHNICIAN   2201622
ELECHTRICAL COMMISSIONING TECHNICIAN 2201622MOHAMMAD KHALID MUSTAFA
 
UPS operation, Rev 2.pptx
UPS operation, Rev 2.pptxUPS operation, Rev 2.pptx
UPS operation, Rev 2.pptxJaimohan15
 
Power transformers rating
Power transformers ratingPower transformers rating
Power transformers ratingLeonardo ENERGY
 
Integrating fuel cell systems in critical industrial processes
Integrating fuel cell systems in critical industrial processesIntegrating fuel cell systems in critical industrial processes
Integrating fuel cell systems in critical industrial processesZondits
 
Permaculutre Renewable Energy
Permaculutre Renewable EnergyPermaculutre Renewable Energy
Permaculutre Renewable EnergyKevin Bayuk
 
Electrical Engineering Basics - What Design Engineers Need to Know
Electrical Engineering Basics - What Design Engineers Need to KnowElectrical Engineering Basics - What Design Engineers Need to Know
Electrical Engineering Basics - What Design Engineers Need to Knowmilestoneseng
 
Power electronics and its applications.pptx
Power electronics and its applications.pptxPower electronics and its applications.pptx
Power electronics and its applications.pptxSHIVANICHAUUHAN1
 

Similar to Prsn (20)

CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptxCHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
CHAPTER 2 Design of Building Electrical Systems (2).pptx.pptx
 
Legend Power Overview 97 2003 120410 1256 Do
Legend Power   Overview 97 2003 120410 1256 DoLegend Power   Overview 97 2003 120410 1256 Do
Legend Power Overview 97 2003 120410 1256 Do
 
Ramendra summer training presentation
Ramendra summer training presentationRamendra summer training presentation
Ramendra summer training presentation
 
Shivesh ntpc ppt
Shivesh ntpc pptShivesh ntpc ppt
Shivesh ntpc ppt
 
Session 05 grid connected inverter
Session 05   grid connected inverterSession 05   grid connected inverter
Session 05 grid connected inverter
 
Electrical component at airport for airfield lighting circuit
Electrical component at airport for airfield lighting circuitElectrical component at airport for airfield lighting circuit
Electrical component at airport for airfield lighting circuit
 
Power factor corrector
Power factor correctorPower factor corrector
Power factor corrector
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
 
Designing an Uninterruptible Power Supply
Designing an Uninterruptible Power SupplyDesigning an Uninterruptible Power Supply
Designing an Uninterruptible Power Supply
 
Getting the Most out of your Electrical Room
Getting the Most out of your Electrical RoomGetting the Most out of your Electrical Room
Getting the Most out of your Electrical Room
 
A Five – Level Integrated AC – DC Converter
A Five – Level Integrated AC – DC ConverterA Five – Level Integrated AC – DC Converter
A Five – Level Integrated AC – DC Converter
 
Distributed Generation By Roland Desouza
Distributed Generation By Roland DesouzaDistributed Generation By Roland Desouza
Distributed Generation By Roland Desouza
 
ELECHTRICAL COMMISSIONING TECHNICIAN 2201622
ELECHTRICAL   COMMISSIONING  TECHNICIAN   2201622ELECHTRICAL   COMMISSIONING  TECHNICIAN   2201622
ELECHTRICAL COMMISSIONING TECHNICIAN 2201622
 
UPS operation, Rev 2.pptx
UPS operation, Rev 2.pptxUPS operation, Rev 2.pptx
UPS operation, Rev 2.pptx
 
Power transformers rating
Power transformers ratingPower transformers rating
Power transformers rating
 
Integrating fuel cell systems in critical industrial processes
Integrating fuel cell systems in critical industrial processesIntegrating fuel cell systems in critical industrial processes
Integrating fuel cell systems in critical industrial processes
 
Permaculutre Renewable Energy
Permaculutre Renewable EnergyPermaculutre Renewable Energy
Permaculutre Renewable Energy
 
Electrical Engineering Basics - What Design Engineers Need to Know
Electrical Engineering Basics - What Design Engineers Need to KnowElectrical Engineering Basics - What Design Engineers Need to Know
Electrical Engineering Basics - What Design Engineers Need to Know
 
Basics of Power Inverters
Basics of Power InvertersBasics of Power Inverters
Basics of Power Inverters
 
Power electronics and its applications.pptx
Power electronics and its applications.pptxPower electronics and its applications.pptx
Power electronics and its applications.pptx
 

Recently uploaded

Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxnegromaestrong
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17Celine George
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin ClassesCeline George
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxheathfieldcps1
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Jisc
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and ModificationsMJDuyan
 
Magic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxMagic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxdhanalakshmis0310
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseAnaAcapella
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxVishalSingh1417
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSCeline George
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docxPoojaSen20
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfNirmal Dwivedi
 

Recently uploaded (20)

Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Magic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxMagic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptx
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
Asian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptxAsian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
How to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POSHow to Manage Global Discount in Odoo 17 POS
How to Manage Global Discount in Odoo 17 POS
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 

Prsn

  • 1. Flanders Electric – Engineering Division Welcomes You to an Overview of Reconditioned Switchgear
  • 2. Reasons for Reconditioning Switchgear Cost Savings Reuse material Buswork Building/enclosure Components Energy Efficiencies Shorter Production outages often required with switchgear upgrades
  • 3. Technology Upgrade Obsolete Parts Replacement Vacuum Contactors/Breakers Solid State Protection Web Enabled Power Monitoring Equipment (wireless Ethernet) Reasons for Reconditioning Switchgear – con’t Environmental Considerations Removal of Equipment From Old Mines More Energy Efficient Components
  • 4. Meggar/Hi Pot Line and Load Conductors Visually inspect for hot spots/fluid leaks etc. Thoroughly Clean Compartment Remove: Dirt, Rocks, Excess oils, Rodent infestation Inspect all components for excess wear and damage Basic inspections/cleanings on all components Visually inspect all Connections – i.e. Power Cable Clamps (draglines) Fuse Clips (loose, corrosion) Inspect Insulators, Bushings and Surge Arrestors
  • 5. For Load Break Switches Adjust and lubricate linkages as necessary Clean and Calibrate Electro-Mechanical Protection Devices (if not being replaced) Oil Analysis where necessary Basic inspections/cleanings on all components (con’t)
  • 6. Technology Upgrades Typically Recommended Change OCB’s (Oil Filled Circuit Breakers) to Vacuum Circuit Breakers Replace Capacitive Trip Devices – Depending upon Age Change Electro-Mechanical Overload protection devices to Solid State – Improve Repeatability and Accuracy
  • 7. Replace low voltage, air contactor size 4 and above with vacuum contactors and any medium voltage with vacuum contactor -Improves contactor life (number of cycles) -Minimizes effect of environmental elements on contacts Replace old lighting with more energy efficient lighting -High pressure sodium or Metal Halide on outside -Replace incandescent lights with fluorescent bulbs in sockets Technology Upgrades Typically Recommended (con’t)
  • 8. Safety Related items – must do Upgrade all receptacles to GFCI type Install new safety signage/warning labels Simulate all Ground Faults Repair all door interlocks per MSHA Check Ground Monitor (Coal Mines)
  • 9. Standards Followed National Electrical Code Mining Safety and Health Administration UL/c UL – Underwriters Laboratory ANSI – American National Standards Institute NFPA 79 – Electrical Standard for Industrial Machinery EIA RS821 – Electronics Industries Assoc.: Construction Standards
  • 10. Just a few examples
  • 11. EXAMPLES – 1 BEFORE
  • 13. EXAMPLE -3 INSTALLATIONS
  • 16. EXAMPLE – 6 BEFORE
  • 17. EXAMPLE – 7 AFTER
  • 18. Example # 1 Medium Voltage Pump Sub Specifications 7200/480Y, 225KVA Description of operation - Transformer and Breaker to Feed Pumps for Water Removal
  • 19. Material Cost $6,500.00 Repair Load Switch Replace two 480VAC Breakers Labor cost $1,200.00 Total Cost $7,700.00 Example # 1 Medium Voltage Pump Sub Summary Estimated Cost of new $30,000
  • 20. Example # 2 OCB – Vacuum Retrofit Specifications Voltage: 7200VAC Current: 400 Amp Description of Operation – Dragline Contactor for Motor Starting with Overload and Ground Fault Protection
  • 21. Material Cost $9,000.00 Labor cost $1000.00 Total Cost $10,000.00 Example # 2 OCB - Vacuum Retrofit Summary Other Savings/Benefits: Installation of new contactor during normal outage time. Estimated Cost of new Switchgear: $55,000.00
  • 22. Example # 3 Portable Breaker House Specifications Voltage: 4160 VAC Current: 1200 Amps Description of operation – Converted 7200VAC Portable Breaker House to 4160 Line Drop Station
  • 23. Items Replaced (2) Potential Transformers (PT’s) (3) 5kV Bushing Assemblies Labor cost $8,000.00 Total Cost $13,000.00 Example # 3 Portable Breaker House Summary Estimated Cost of new $50,000.00 Material Cost $5,000.00
  • 24. Example # 4 - 3 Way Switch House Specifications Voltage 7200 VAC Current 400 amps Description of operation - Switches to Provide Alternative Feed for Distribution. Single Main to 3 feeds
  • 25. Material Cost $900.00 Mechanical Interlocks Calibration Labor cost $1,000.00 Total Cost $1,900.00 Example # 4 3 Way Switch House Summary Estimated Cost of new $25,000.00
  • 26. Example # 5 Large Portable Substation Specifications Voltage 23,000VAC Current 1000 amps Description of operation - Power Feed and Distribution to Dragline
  • 27. Items Replaced Replaced 25KV OCB Contacts and Changed Oil Ground Monitor GE Potential Transformer Labor cost $11,000.00 Total Cost $27,000.00 Example # 5 Large Portable Switchgear Summary Estimated Cost of new $75,000.00 Material Cost $16,000.00 (includes purchase of used skid)