SlideShare a Scribd company logo
1 of 23
1
Renewable Energy & Storage
State Energy Minister’s Conference
Udaipur,
14th -16th October, 2022
2
 Present Status and by 2030
a. Renewables: Break up of RES as on 31.08.2022 is given below (in MW)
b. Current Share of RE in Total Installed Capacity (IC): 38.98% - RE Variations in Grid
are presently being handled by flexibilization of Thermal Power Plants, flexible Hydro
based storage projects & other existing Storages such as PSPs (3305.60 MW) etc.
c. Share of RE in Total IC by 2030 (as per CEA Generation Planning Study): 58.7%
d. Share of Storage by 2030: 24,977 MW (5-hour) of BESS and 14,526 MW of
Pumped Storage Plants (PSPs). Storage requirement would further increase as the
RE gains deeper penetration in the process of net zero emissions target of the country
by the year 2070.
Renewable Integration
Hydro Small
Hydro
Power
Wind
Power
Bio-Power Solar
Power
Total
Capacity
BM Power/
Cogen.
Waste to
Energy
46850.17 4887.90 41204.68 10205.61 476.75 59302.70 162927.81
3
a. Recent grid incidents in the major RE complexes in Rajasthan:
i. Incident on 09th July, 2022 at 13:42 hrs.- Tripping of multiple elements in Rajasthan Solar
Complex initiated by fault on 400 kV Bikaner(PG) – Bikaner(RS) (PG) Ckt-1. There was a drop
of approximately 3485 MW in Solar Generation connected at different RE pooling stations.
The Solar Generation recovered to around 2300 MW within three (3) minutes.
ii. Incident on 11th August, 2022 at 11:23 hrs.- Loss of RE Generation of around 6000 MW and
tripping of major associated transmission lines. Grid frequency dropped from 50.16 Hz to
49.46 Hz.
 The frequency quickly recovered to 49.62 Hz with the activation of primary frequency
response and df/dt based load shedding.
 Complete outage of two major RE pooling stations plus a significant generation loss
at two other pooling stations.
iii. Incident on 11th September,2022 at 12:22 hrs.- The incident was due to tripping of 220 kV
Bhadla – Hero Solar Energy line.
 RE generation loss of 1100 MW and tripping of few lines on over-voltage.
Issues cropping up due to RE Integration
4
 Use Based
a. ESS shall be designated as a Power System element which can be utilized
as a Generator, Transmission element or Distribution element.
b. ESS may be entitled to provide grid flexibility services arising out of RE
capacity addition such as grid support/ ancillary services, fast response/
ramping up/ ramping down and peak shifting either on standalone basis or
in conjunction with other power system elements.
 Business Cases
a. RE supply with Energy Storage System (ESS): These projects may also
be utilized to meet Peak power and firm dispatchable RE requirements of
Procurers.
Application of Storage
5
 Business Case
b. ESS with transmission infrastructure: Aimed at maximization of the
utilization of the transmission Asset, increasing duration of usage of
transmission system and strengthen Grid stability.
c. Storage for ancillary services/ balancing services / flexible operations
d. Storage for Distribution: Maximization of the utilization of the Storage
Asset and strengthening DISCOM operations. Connected at the load centres,
it may be suitably utilized by the Discoms to manage its peak load, grid
resilience, portfolio management and flexible operations.
Application of Storage
6
 Battery Energy Storage System (BESS)
• The process for tendering/ award for 1000 MW BESS is in underway by SECI.
• Details of Grid Scale Energy Storage project developed in India are given as below:
Status of Energy Storage Development in India
Sr. No. Location Capacity
Above 5 MW
1. TPDDL, Rohini, Delhi 10 MW/10 MWh
2. Sun Temple, Mehsana,
Gujarat
19.2 MWh
3. Dollygunj and Attampahad
in South Andaman
16 MW/8 MWh
Under 5 MW
4. BHEL R&D Campus,
Hyderabad
200 kWh Flow Battery, 300 kWh Advanced Lead
Acid and 500 kWh Li-Ion
5. Bangalore 400 kWh
6. Puducherry 500 kW/250kWh (Li- ion)
7. Chennai 270 kWph
7
 Pumped Storage Projects (PSPs)
• Types of PSPs
a. Conventional PSP - Both upper and lower reservoirs to be constructed are on
natural river course.
b. Off-Stream PSPs:
i. Open Loop PSP - All newly constructed components (including at least
one reservoir) are located away from river stream and utilizing one of the
existing reservoirs which can be on the river stream.
ii. Off-Stream Closed Loop PSP - Both upper and lower reservoirs which
are to be constructed newly are away from natural river course.
• Considering the benefits of widespread flexibility in location of project, lesser forest,
environmental and R&R issues, lower gestation period and lower cost viz-a-viz
river based schemes, the category of Off-Stream/ River PSPs need to be prioritized
for faster implementation & lower tariff benefits.
Status of Energy Storage Development in India
8
• The list of in-operation PSPs in the country is given as below:
Status of Energy Storage Development in India
S.No.
SCHEMES STATE INSTALLED CAPACITY REMARKS
No. of
units x
Unit
size(MW)
MW
a. Working in Pumping Mode
1. Nagarjuna Sagar Telangana 7x100.80 705.60
2. Srisailam LBPH Telangana 6x150 900
3. Kadamparai Tamil Nadu 4x100 400
4. Bhira
Maharashtr
a
1x150 150
5. Ghatgar
Maharashtr
a
2x125 250
6. Purulia
West
Bengal
4x225 900
Sub Total 3305.60
9
• Installed PSPs (2 nos.) but presently not working in Pumping Mode (1440 MW)
Contd….
Status of PSPs Development in India
S.No.
SCHEMES STATE INSTALLED CAPACITY REMARKS
No. of units x
Unit size(MW)
MW
b. Installed PSPs but presently not working in Pumping Mode
7.
Kadana
PSP
Gujarat 2x60+2x60 240
 Operation in pumping mode not taken due
to vibration problem in the machines.
 Tender for new units for capable of working
in pumping mode to be floated in Oct’22.
Estimated cost is Rs. 750 Crs.
8
Sardar
Sarovar
Project
Gujarat 6x200 1200
 The Generation of SSHEP is shared between
Gujarat (16%), Maharashtra (27%) &
Madhya Pradesh (57%) States, as per the
Narmada Water Disputes Tribunal (NWDT)
Award.
 Additional cost on procurement of relevant
E&M equipment to make it operational in
pumping mode is about Rs. 300 Crs.
 Out of three partner states of M.P. Gujarat
and Maharashtra, only M.P. Govt. is not
agreeable to pumping mode operation of
project.
Sub total 1440
Grand Total
(Working + Non-
working PSPs)
4745.60
10
a. Large Potential Availability of PSPs in India.
b. Assessment of Potential of PSPs – 103 GW (89 nos.)
i. PSPs in operation – 3305.6 MW (6 nos.)
ii. PSPs not in operation – 1440 MW (2 nos.)
iii. Under Construction – 2780 MW (4 nos.)
iv. Cleared by CEA and yet to be taken up for construction – 1000 MW (1 no. of
Scheme)
v. Under Survey & Investigation (S&I) Stage – 24280 MW (22 nos.)
i. River Based – 9000 MW (9 nos.)
ii. Off-River Closed Loop - 8260 MW (6 nos.)
iii. Off-River Open Loop – 7020 MW (7 nos.)
c. Likely additional PSPs by 2029-30 – 11380 MW ( 12 nos.)
d. Likely additional PSPs by 2030-32 - 28060 MW ( 27 nos.)
Potential and Development Status of PSPs
11
S.NO NAME OF PROJECT/ AGENCY STATE TOTAL
CAPACITY (MW)
TENTATIVE DATE OF
COMMISSIONING
Under Construction
1 Tehri PSS (THDC) Uttarakhand 1000 Oct, 2023
2 Kundah Pumped Storage Phase-I,II&III) Tamil Nadu 500 Dec, 2024
3 Pinnapuram (Greenko AP01 IREP
Private Limited)
Andhra Pradesh 1200 May,2025
4 Koyna Left Bank (WRD,MAH) Maharashtra 80 2027-28
Sub Total 2780
Cleared by CEA and yet to be taken up for construction
5 Turga / WBSEDCL West Bengal 1000 2029-30
Under S&I
6 MP 30 Gandhi Sagar PSP/ Greenko Madhya Pradesh 1440 2026-27
7 Upper Indravati PSP / OHPCL Odisha 600 2027-28
8 Sharavathy PSP / KPCL Karnataka 2000 2027-28
9 Saundatti PSP / Greenko Karnataka 1260 2027-28
10 Chitravathi / ADANI GREEN ENERGY
LTD.
Andhra Pradesh 500 2028-29
11 Gandikota / ADANI GREEN ENERGY
LTD.
Andhra Pradesh 1000 2029-30
12 Owk / NREDCAP Andhra Pradesh 800 2029-30
Sub Total 7600
List of Additional PSPs by 2032
12
S.NO NAME OF PROJECT STATE TOTAL CAPACITY
(MW)
TENTATIVE DATE OF
COMMISSIONING
13 Kodayar PSP / TANGEDCO Tamil Nadu 500 2030-31
14 Balimela / OHPCL Odisha 500 2030-31
15 Sillahalla PSP / TANGEDCO Tamil Nadu 1000 2030-31
16 Upper Kolab PSP / OHPCL Odisha 320 2030-31
17 Kurukutti PSP / ADANI GREEN ENERGY LTD. Andhra Pradesh 1200 2030-31
18 Karrivalasa PSP / ADANI GREEN ENERGY LTD. Andhra Pradesh 1000 2030-31
19 Warasgaon / WRD Mah. Maharashtra 1200 2030-31
20 Bhavali PSP / JSW * Maharashtra 1500 2030-31
21 Yerravaram/ NREDCAP Andhra Pradesh 1200 2031-32
22 Somasila PSP / NREDCAP Andhra Pradesh 900 2031-32
23 Sukhpura Off Stream PSP / Greenko Rajasthan 2560 2031-32
24 Shahpur/ Greenko Rajasthan 1800 2031-32
25 Singanamala / NREDCAP Andhra Pradesh 800 2031-32
26 Paidipalem East / NREDCAP Andhra Pradesh 1200 2031-32
27 Paidipalem North / NREDCAP Andhra Pradesh 1000 2031-32
Sub Total 16680
Total 28060
*- Captives have lot of potential for tying up with PSPs.
List of Additional PSPs by 2032
13
Agency Number of Projects Capacity (in MW)
NHPC 10 14700
SJVNL 11 12745
THDCIL 10 12555
NEEPCO 10 14880
DVC 4 5010
BBMB 1 1800
NTPC 9 11550
Total 55 73240
Identification of the CPSUs for Development of PSPs
14
S. No. State/UT
Probable
IC (MW)
Revised indication /
Changes proposed
1 Jammu & Kashmir 1650 NHPC
2 Himachal Pradesh 4445
BBMB ,SJVN
3 Uttarakhand 1935 THDCIL
4 Punjab BBMB
5 Haryana BBMB
6 Rajasthan BBMB
7
Uttar Pradesh
THDCIL
8 Maharashtra 28127 NHPC, SJVN, THDCIL, NTPC
9 Gujrat SJVN
10 Madhya Pradesh 500 NHPC
Identified Projects by the CPSUs for Allocation
15
S. No. State/UT
Probable
IC (MW)
Revised indication /
Changes proposed
11 Chhattisgarh THDCIL
12 Jharkhand 3300 DVC
13 Bihar SJVN
14 Odisha 2500 NHPC
15 West Bengal 1710 DVC
16 Sikkim NHPC
17 Andhra Pradesh 1650 NTPC
18 Telangana NHPC
19 Tamil Nadu 7100 NTPC
20 Karnataka 2200 KPCL, NTPC
Identified Projects by the CPSUs for Allocation
16
S. No. State/UT
Probable
IC (MW)
Revised indication /
Changes proposed
21 Kerala 900 THDCIL
22 Manipur 4350 NEEPCO
23 Assam 2420 NEEPCO
24 Mizoram 10450 NEEPCO
25 Arunachal Pradesh
660 NEEPCO
Identified Projects by the CPSUs for Allocation
17
a. Waiver of ISTS Charges provided in full up to 30.06.2025 and in reduced
graded manner vide MoP order dated 23rd November, 2021.
b. Legal Status for Energy Storage Systems issued by MoP on 29th January,
2022.
c. RE Bundling: Scheme for Scheduling of Thermal/ Hydro Power Stations
through bundling with Renewable energy and Hydro Power notified vide
MoP order dated 12th April, 2022.
d. Renewable Purchase Obligations (43.33% by 2029-30) and Energy
Storage Obligations (4% by 2029-30) notified vide MoP order dt. 22nd
Jul, 2022.
Measures taken up/ proposed for the Promotion of Storage
18
e. Formulation of Comprehensive National Energy Storage Policy is in
progress.
f. Viability Gap Funding (VGF)
g. Issue of Bidding Guidelines for ESS
i. Bidding Guidelines Issued by MoP
a. After notifying Bidding Guidelines for BESS in March, 2022, the tendering/
award for development of 1000 MWh BESS by SECI is underway.
ii. Bidding Guidelines proposed to be Issued by MoP
a. Long Duration Energy Storage (LDES) for Long Term Procurement:
For storage requirement beyond six hours per day, gestation/ delivery
period of 54 months from date of signing of agreement and a
procurement contract of at least 12 years.
Measures taken up/ proposed for the Promotion of Storage
19
b. Short Duration Energy Storage (SDES) for Medium-Term Procurement:
Four hours per day, gestation/ delivery period of 18 to 24 months from date
of signing of agreement and a procurement contract of up to 10 years.
c. SDES for Ancillary Services:
Feature of SDES less than four hours per day, gestation/ delivery period
of 3-4 months from date of signing of agreement and a procurement contract
of up to 3 years.
Measures taken up/ proposed for the Promotion of Storage
20
h. Prioritization of Off-River PSPs
Considering the benefits of wider Geographical/ Locational flexibility, lesser
forest, environmental and R&R issues, lower gestation period and lower cost
viz-a-viz river based schemes, the category of Off-Stream/ River PSPs need to be
prioritized for faster implementation & lower tariff benefits.
i. Potential assessment for Off-Stream Pumped Storage projects.
ii. CEA has revised its guidelines for faster concurrence from earlier 150 days
to 75 days (for projects construction on Competitive Bidding process) and
150 days to 125 days (for projects construction on Cost-plus basis).
Measures taken up/ proposed for the Promotion of Storage
21
Prioritization of Off-River Schemes (Contd….)
iii. Off-Stream Pumped Storage Projects (Closed & Open Loop) to be
classified as separate category for Environmental Clearance because of
its location away from riverine system.
iv. Data collection to be limited to one (1) season (as is for Thermal Plants).
v. Allow degraded forest lands for compensatory afforestation for Off-river
PSPs.
vi. Allow construction of Project works on Forest Land & Non-Forest Land
after Stage-I Approval.
vii. EC, Forest land Diversion and DPR Concurrence are Concurrent &
Independent Processes so there may be no precondition of obtaining
one clearance prior to the other.
Measures taken up/ proposed for the Promotion of Storage
22
States to facilitate in faster implementation of Hydro PSP.
Identification of use cases in Generation, Transmission,
Distribution. Ancillary Services.
Encourage large captive users also to go for Hydro PSPs.
Allot projects to CPSUs or may bid out the projects.
Way Forward
23
THANK YOU

More Related Content

Similar to 12 B .Storage CEA.pptx

15. Future Power System for the year 2030.pptx
15. Future Power System for the year 2030.pptx15. Future Power System for the year 2030.pptx
15. Future Power System for the year 2030.pptxssuser0f80df
 
BRICS-Indian Power sector
BRICS-Indian Power sector BRICS-Indian Power sector
BRICS-Indian Power sector Vijay Menghani
 
Solar power plants in rajasthan
Solar power plants in rajasthanSolar power plants in rajasthan
Solar power plants in rajasthanAsafak Husain
 
Cea psp potential assessed 1978 87
Cea psp potential assessed 1978 87Cea psp potential assessed 1978 87
Cea psp potential assessed 1978 87Probodh Mallick
 
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEF
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEFRenewable Energy status and road-map of Bangladesh and support of UNDP-GEF
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEFDr. Md. Taibur Rahman
 
Solar Power Technology in India by S Kumar
Solar Power Technology in India by S Kumar Solar Power Technology in India by S Kumar
Solar Power Technology in India by S Kumar Private Consultants
 
National Transmission And Dispatch Company (NTDC)
National Transmission And Dispatch Company (NTDC)National Transmission And Dispatch Company (NTDC)
National Transmission And Dispatch Company (NTDC)Aneel-k Suthar
 
26900721058_OE-ME701D.pptx
26900721058_OE-ME701D.pptx26900721058_OE-ME701D.pptx
26900721058_OE-ME701D.pptxSukantaMandal17
 
Ntpc information
Ntpc informationNtpc information
Ntpc informationNTPC
 
Future of Hydro Power Development in India
Future of Hydro Power Development in IndiaFuture of Hydro Power Development in India
Future of Hydro Power Development in IndiaIPPAI
 
15,000 MW in 10 years: dream or reality?
15,000 MW in 10 years:  dream or reality?15,000 MW in 10 years:  dream or reality?
15,000 MW in 10 years: dream or reality?Kushal Gurung
 
bhadla solar park.pptx world's largest solar park
bhadla solar park.pptx  world's largest solar parkbhadla solar park.pptx  world's largest solar park
bhadla solar park.pptx world's largest solar parkHusainUlHasanKhan
 
Power Sector in Pakistan - 2017
Power Sector in Pakistan - 2017Power Sector in Pakistan - 2017
Power Sector in Pakistan - 2017Salman Haider
 
MP-SLDC DSM account solar wind aug 2018
MP-SLDC DSM account solar wind aug 2018MP-SLDC DSM account solar wind aug 2018
MP-SLDC DSM account solar wind aug 2018Das A. K.
 
Grid solar demo_performance
Grid solar demo_performanceGrid solar demo_performance
Grid solar demo_performanceSanman Rajput
 
CEA's Monthly Review of Indian Power Sector
CEA's Monthly Review of Indian Power SectorCEA's Monthly Review of Indian Power Sector
CEA's Monthly Review of Indian Power SectorSpark Network
 

Similar to 12 B .Storage CEA.pptx (20)

15. Future Power System for the year 2030.pptx
15. Future Power System for the year 2030.pptx15. Future Power System for the year 2030.pptx
15. Future Power System for the year 2030.pptx
 
BRICS-Indian Power sector
BRICS-Indian Power sector BRICS-Indian Power sector
BRICS-Indian Power sector
 
Solar power plants in rajasthan
Solar power plants in rajasthanSolar power plants in rajasthan
Solar power plants in rajasthan
 
Cea psp potential assessed 1978 87
Cea psp potential assessed 1978 87Cea psp potential assessed 1978 87
Cea psp potential assessed 1978 87
 
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEF
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEFRenewable Energy status and road-map of Bangladesh and support of UNDP-GEF
Renewable Energy status and road-map of Bangladesh and support of UNDP-GEF
 
Kerala sw
Kerala swKerala sw
Kerala sw
 
A n srivastava
A n srivastavaA n srivastava
A n srivastava
 
Solar Power Technology in India by S Kumar
Solar Power Technology in India by S Kumar Solar Power Technology in India by S Kumar
Solar Power Technology in India by S Kumar
 
National Transmission And Dispatch Company (NTDC)
National Transmission And Dispatch Company (NTDC)National Transmission And Dispatch Company (NTDC)
National Transmission And Dispatch Company (NTDC)
 
26900721058_OE-ME701D.pptx
26900721058_OE-ME701D.pptx26900721058_OE-ME701D.pptx
26900721058_OE-ME701D.pptx
 
Ntpc information
Ntpc informationNtpc information
Ntpc information
 
southern grid
southern grid southern grid
southern grid
 
Future of Hydro Power Development in India
Future of Hydro Power Development in IndiaFuture of Hydro Power Development in India
Future of Hydro Power Development in India
 
Report its
Report itsReport its
Report its
 
15,000 MW in 10 years: dream or reality?
15,000 MW in 10 years:  dream or reality?15,000 MW in 10 years:  dream or reality?
15,000 MW in 10 years: dream or reality?
 
bhadla solar park.pptx world's largest solar park
bhadla solar park.pptx  world's largest solar parkbhadla solar park.pptx  world's largest solar park
bhadla solar park.pptx world's largest solar park
 
Power Sector in Pakistan - 2017
Power Sector in Pakistan - 2017Power Sector in Pakistan - 2017
Power Sector in Pakistan - 2017
 
MP-SLDC DSM account solar wind aug 2018
MP-SLDC DSM account solar wind aug 2018MP-SLDC DSM account solar wind aug 2018
MP-SLDC DSM account solar wind aug 2018
 
Grid solar demo_performance
Grid solar demo_performanceGrid solar demo_performance
Grid solar demo_performance
 
CEA's Monthly Review of Indian Power Sector
CEA's Monthly Review of Indian Power SectorCEA's Monthly Review of Indian Power Sector
CEA's Monthly Review of Indian Power Sector
 

Recently uploaded

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 

Recently uploaded (20)

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 

12 B .Storage CEA.pptx

  • 1. 1 Renewable Energy & Storage State Energy Minister’s Conference Udaipur, 14th -16th October, 2022
  • 2. 2  Present Status and by 2030 a. Renewables: Break up of RES as on 31.08.2022 is given below (in MW) b. Current Share of RE in Total Installed Capacity (IC): 38.98% - RE Variations in Grid are presently being handled by flexibilization of Thermal Power Plants, flexible Hydro based storage projects & other existing Storages such as PSPs (3305.60 MW) etc. c. Share of RE in Total IC by 2030 (as per CEA Generation Planning Study): 58.7% d. Share of Storage by 2030: 24,977 MW (5-hour) of BESS and 14,526 MW of Pumped Storage Plants (PSPs). Storage requirement would further increase as the RE gains deeper penetration in the process of net zero emissions target of the country by the year 2070. Renewable Integration Hydro Small Hydro Power Wind Power Bio-Power Solar Power Total Capacity BM Power/ Cogen. Waste to Energy 46850.17 4887.90 41204.68 10205.61 476.75 59302.70 162927.81
  • 3. 3 a. Recent grid incidents in the major RE complexes in Rajasthan: i. Incident on 09th July, 2022 at 13:42 hrs.- Tripping of multiple elements in Rajasthan Solar Complex initiated by fault on 400 kV Bikaner(PG) – Bikaner(RS) (PG) Ckt-1. There was a drop of approximately 3485 MW in Solar Generation connected at different RE pooling stations. The Solar Generation recovered to around 2300 MW within three (3) minutes. ii. Incident on 11th August, 2022 at 11:23 hrs.- Loss of RE Generation of around 6000 MW and tripping of major associated transmission lines. Grid frequency dropped from 50.16 Hz to 49.46 Hz.  The frequency quickly recovered to 49.62 Hz with the activation of primary frequency response and df/dt based load shedding.  Complete outage of two major RE pooling stations plus a significant generation loss at two other pooling stations. iii. Incident on 11th September,2022 at 12:22 hrs.- The incident was due to tripping of 220 kV Bhadla – Hero Solar Energy line.  RE generation loss of 1100 MW and tripping of few lines on over-voltage. Issues cropping up due to RE Integration
  • 4. 4  Use Based a. ESS shall be designated as a Power System element which can be utilized as a Generator, Transmission element or Distribution element. b. ESS may be entitled to provide grid flexibility services arising out of RE capacity addition such as grid support/ ancillary services, fast response/ ramping up/ ramping down and peak shifting either on standalone basis or in conjunction with other power system elements.  Business Cases a. RE supply with Energy Storage System (ESS): These projects may also be utilized to meet Peak power and firm dispatchable RE requirements of Procurers. Application of Storage
  • 5. 5  Business Case b. ESS with transmission infrastructure: Aimed at maximization of the utilization of the transmission Asset, increasing duration of usage of transmission system and strengthen Grid stability. c. Storage for ancillary services/ balancing services / flexible operations d. Storage for Distribution: Maximization of the utilization of the Storage Asset and strengthening DISCOM operations. Connected at the load centres, it may be suitably utilized by the Discoms to manage its peak load, grid resilience, portfolio management and flexible operations. Application of Storage
  • 6. 6  Battery Energy Storage System (BESS) • The process for tendering/ award for 1000 MW BESS is in underway by SECI. • Details of Grid Scale Energy Storage project developed in India are given as below: Status of Energy Storage Development in India Sr. No. Location Capacity Above 5 MW 1. TPDDL, Rohini, Delhi 10 MW/10 MWh 2. Sun Temple, Mehsana, Gujarat 19.2 MWh 3. Dollygunj and Attampahad in South Andaman 16 MW/8 MWh Under 5 MW 4. BHEL R&D Campus, Hyderabad 200 kWh Flow Battery, 300 kWh Advanced Lead Acid and 500 kWh Li-Ion 5. Bangalore 400 kWh 6. Puducherry 500 kW/250kWh (Li- ion) 7. Chennai 270 kWph
  • 7. 7  Pumped Storage Projects (PSPs) • Types of PSPs a. Conventional PSP - Both upper and lower reservoirs to be constructed are on natural river course. b. Off-Stream PSPs: i. Open Loop PSP - All newly constructed components (including at least one reservoir) are located away from river stream and utilizing one of the existing reservoirs which can be on the river stream. ii. Off-Stream Closed Loop PSP - Both upper and lower reservoirs which are to be constructed newly are away from natural river course. • Considering the benefits of widespread flexibility in location of project, lesser forest, environmental and R&R issues, lower gestation period and lower cost viz-a-viz river based schemes, the category of Off-Stream/ River PSPs need to be prioritized for faster implementation & lower tariff benefits. Status of Energy Storage Development in India
  • 8. 8 • The list of in-operation PSPs in the country is given as below: Status of Energy Storage Development in India S.No. SCHEMES STATE INSTALLED CAPACITY REMARKS No. of units x Unit size(MW) MW a. Working in Pumping Mode 1. Nagarjuna Sagar Telangana 7x100.80 705.60 2. Srisailam LBPH Telangana 6x150 900 3. Kadamparai Tamil Nadu 4x100 400 4. Bhira Maharashtr a 1x150 150 5. Ghatgar Maharashtr a 2x125 250 6. Purulia West Bengal 4x225 900 Sub Total 3305.60
  • 9. 9 • Installed PSPs (2 nos.) but presently not working in Pumping Mode (1440 MW) Contd…. Status of PSPs Development in India S.No. SCHEMES STATE INSTALLED CAPACITY REMARKS No. of units x Unit size(MW) MW b. Installed PSPs but presently not working in Pumping Mode 7. Kadana PSP Gujarat 2x60+2x60 240  Operation in pumping mode not taken due to vibration problem in the machines.  Tender for new units for capable of working in pumping mode to be floated in Oct’22. Estimated cost is Rs. 750 Crs. 8 Sardar Sarovar Project Gujarat 6x200 1200  The Generation of SSHEP is shared between Gujarat (16%), Maharashtra (27%) & Madhya Pradesh (57%) States, as per the Narmada Water Disputes Tribunal (NWDT) Award.  Additional cost on procurement of relevant E&M equipment to make it operational in pumping mode is about Rs. 300 Crs.  Out of three partner states of M.P. Gujarat and Maharashtra, only M.P. Govt. is not agreeable to pumping mode operation of project. Sub total 1440 Grand Total (Working + Non- working PSPs) 4745.60
  • 10. 10 a. Large Potential Availability of PSPs in India. b. Assessment of Potential of PSPs – 103 GW (89 nos.) i. PSPs in operation – 3305.6 MW (6 nos.) ii. PSPs not in operation – 1440 MW (2 nos.) iii. Under Construction – 2780 MW (4 nos.) iv. Cleared by CEA and yet to be taken up for construction – 1000 MW (1 no. of Scheme) v. Under Survey & Investigation (S&I) Stage – 24280 MW (22 nos.) i. River Based – 9000 MW (9 nos.) ii. Off-River Closed Loop - 8260 MW (6 nos.) iii. Off-River Open Loop – 7020 MW (7 nos.) c. Likely additional PSPs by 2029-30 – 11380 MW ( 12 nos.) d. Likely additional PSPs by 2030-32 - 28060 MW ( 27 nos.) Potential and Development Status of PSPs
  • 11. 11 S.NO NAME OF PROJECT/ AGENCY STATE TOTAL CAPACITY (MW) TENTATIVE DATE OF COMMISSIONING Under Construction 1 Tehri PSS (THDC) Uttarakhand 1000 Oct, 2023 2 Kundah Pumped Storage Phase-I,II&III) Tamil Nadu 500 Dec, 2024 3 Pinnapuram (Greenko AP01 IREP Private Limited) Andhra Pradesh 1200 May,2025 4 Koyna Left Bank (WRD,MAH) Maharashtra 80 2027-28 Sub Total 2780 Cleared by CEA and yet to be taken up for construction 5 Turga / WBSEDCL West Bengal 1000 2029-30 Under S&I 6 MP 30 Gandhi Sagar PSP/ Greenko Madhya Pradesh 1440 2026-27 7 Upper Indravati PSP / OHPCL Odisha 600 2027-28 8 Sharavathy PSP / KPCL Karnataka 2000 2027-28 9 Saundatti PSP / Greenko Karnataka 1260 2027-28 10 Chitravathi / ADANI GREEN ENERGY LTD. Andhra Pradesh 500 2028-29 11 Gandikota / ADANI GREEN ENERGY LTD. Andhra Pradesh 1000 2029-30 12 Owk / NREDCAP Andhra Pradesh 800 2029-30 Sub Total 7600 List of Additional PSPs by 2032
  • 12. 12 S.NO NAME OF PROJECT STATE TOTAL CAPACITY (MW) TENTATIVE DATE OF COMMISSIONING 13 Kodayar PSP / TANGEDCO Tamil Nadu 500 2030-31 14 Balimela / OHPCL Odisha 500 2030-31 15 Sillahalla PSP / TANGEDCO Tamil Nadu 1000 2030-31 16 Upper Kolab PSP / OHPCL Odisha 320 2030-31 17 Kurukutti PSP / ADANI GREEN ENERGY LTD. Andhra Pradesh 1200 2030-31 18 Karrivalasa PSP / ADANI GREEN ENERGY LTD. Andhra Pradesh 1000 2030-31 19 Warasgaon / WRD Mah. Maharashtra 1200 2030-31 20 Bhavali PSP / JSW * Maharashtra 1500 2030-31 21 Yerravaram/ NREDCAP Andhra Pradesh 1200 2031-32 22 Somasila PSP / NREDCAP Andhra Pradesh 900 2031-32 23 Sukhpura Off Stream PSP / Greenko Rajasthan 2560 2031-32 24 Shahpur/ Greenko Rajasthan 1800 2031-32 25 Singanamala / NREDCAP Andhra Pradesh 800 2031-32 26 Paidipalem East / NREDCAP Andhra Pradesh 1200 2031-32 27 Paidipalem North / NREDCAP Andhra Pradesh 1000 2031-32 Sub Total 16680 Total 28060 *- Captives have lot of potential for tying up with PSPs. List of Additional PSPs by 2032
  • 13. 13 Agency Number of Projects Capacity (in MW) NHPC 10 14700 SJVNL 11 12745 THDCIL 10 12555 NEEPCO 10 14880 DVC 4 5010 BBMB 1 1800 NTPC 9 11550 Total 55 73240 Identification of the CPSUs for Development of PSPs
  • 14. 14 S. No. State/UT Probable IC (MW) Revised indication / Changes proposed 1 Jammu & Kashmir 1650 NHPC 2 Himachal Pradesh 4445 BBMB ,SJVN 3 Uttarakhand 1935 THDCIL 4 Punjab BBMB 5 Haryana BBMB 6 Rajasthan BBMB 7 Uttar Pradesh THDCIL 8 Maharashtra 28127 NHPC, SJVN, THDCIL, NTPC 9 Gujrat SJVN 10 Madhya Pradesh 500 NHPC Identified Projects by the CPSUs for Allocation
  • 15. 15 S. No. State/UT Probable IC (MW) Revised indication / Changes proposed 11 Chhattisgarh THDCIL 12 Jharkhand 3300 DVC 13 Bihar SJVN 14 Odisha 2500 NHPC 15 West Bengal 1710 DVC 16 Sikkim NHPC 17 Andhra Pradesh 1650 NTPC 18 Telangana NHPC 19 Tamil Nadu 7100 NTPC 20 Karnataka 2200 KPCL, NTPC Identified Projects by the CPSUs for Allocation
  • 16. 16 S. No. State/UT Probable IC (MW) Revised indication / Changes proposed 21 Kerala 900 THDCIL 22 Manipur 4350 NEEPCO 23 Assam 2420 NEEPCO 24 Mizoram 10450 NEEPCO 25 Arunachal Pradesh 660 NEEPCO Identified Projects by the CPSUs for Allocation
  • 17. 17 a. Waiver of ISTS Charges provided in full up to 30.06.2025 and in reduced graded manner vide MoP order dated 23rd November, 2021. b. Legal Status for Energy Storage Systems issued by MoP on 29th January, 2022. c. RE Bundling: Scheme for Scheduling of Thermal/ Hydro Power Stations through bundling with Renewable energy and Hydro Power notified vide MoP order dated 12th April, 2022. d. Renewable Purchase Obligations (43.33% by 2029-30) and Energy Storage Obligations (4% by 2029-30) notified vide MoP order dt. 22nd Jul, 2022. Measures taken up/ proposed for the Promotion of Storage
  • 18. 18 e. Formulation of Comprehensive National Energy Storage Policy is in progress. f. Viability Gap Funding (VGF) g. Issue of Bidding Guidelines for ESS i. Bidding Guidelines Issued by MoP a. After notifying Bidding Guidelines for BESS in March, 2022, the tendering/ award for development of 1000 MWh BESS by SECI is underway. ii. Bidding Guidelines proposed to be Issued by MoP a. Long Duration Energy Storage (LDES) for Long Term Procurement: For storage requirement beyond six hours per day, gestation/ delivery period of 54 months from date of signing of agreement and a procurement contract of at least 12 years. Measures taken up/ proposed for the Promotion of Storage
  • 19. 19 b. Short Duration Energy Storage (SDES) for Medium-Term Procurement: Four hours per day, gestation/ delivery period of 18 to 24 months from date of signing of agreement and a procurement contract of up to 10 years. c. SDES for Ancillary Services: Feature of SDES less than four hours per day, gestation/ delivery period of 3-4 months from date of signing of agreement and a procurement contract of up to 3 years. Measures taken up/ proposed for the Promotion of Storage
  • 20. 20 h. Prioritization of Off-River PSPs Considering the benefits of wider Geographical/ Locational flexibility, lesser forest, environmental and R&R issues, lower gestation period and lower cost viz-a-viz river based schemes, the category of Off-Stream/ River PSPs need to be prioritized for faster implementation & lower tariff benefits. i. Potential assessment for Off-Stream Pumped Storage projects. ii. CEA has revised its guidelines for faster concurrence from earlier 150 days to 75 days (for projects construction on Competitive Bidding process) and 150 days to 125 days (for projects construction on Cost-plus basis). Measures taken up/ proposed for the Promotion of Storage
  • 21. 21 Prioritization of Off-River Schemes (Contd….) iii. Off-Stream Pumped Storage Projects (Closed & Open Loop) to be classified as separate category for Environmental Clearance because of its location away from riverine system. iv. Data collection to be limited to one (1) season (as is for Thermal Plants). v. Allow degraded forest lands for compensatory afforestation for Off-river PSPs. vi. Allow construction of Project works on Forest Land & Non-Forest Land after Stage-I Approval. vii. EC, Forest land Diversion and DPR Concurrence are Concurrent & Independent Processes so there may be no precondition of obtaining one clearance prior to the other. Measures taken up/ proposed for the Promotion of Storage
  • 22. 22 States to facilitate in faster implementation of Hydro PSP. Identification of use cases in Generation, Transmission, Distribution. Ancillary Services. Encourage large captive users also to go for Hydro PSPs. Allot projects to CPSUs or may bid out the projects. Way Forward