This document is a project report on the Kota Super Thermal Power Station submitted by Shri Akash Bhai Sundarkand Wale for their Bachelor of Technology degree. It provides details of the power station, which has four stages with a total generation capacity of 1,045 MW. It describes the key components of the power station including the coal handling plant, boilers, steam turbines, generators, transformers and other electrical equipment. The report also includes figures and tables providing technical specifications of the various equipment.
The document is a training report submitted by Shri Akash Bhai Sundarkand Wale, a final year BTech student in the Electrical and Electronics Engineering department of Vedant College of Engineering and Technology. The report details his 30 day training at the Kota Super Thermal Power Station, during which he learned about the various systems and operations at the power plant. It includes sections on the electricity generator, switchyard, turbine generator, steam turbine, coal handling plant, ash handling plant, water treatment plant, control room, and other salient features of the Kota Super Thermal Power Station.
The document summarizes a student's 60-day summer internship at the Rana Pratap Sagar Hydroelectric Power Station located on the Chambal River in Rajasthan, India. It includes an introduction to the power station, classifications of hydroelectric plants, diagrams of the single line diagram and feeders, explanations of how it works and the components involved, specifications of the turbine, generator and other equipment, advantages and disadvantages of hydroelectric power, and a conclusion on the benefits of practical training.
Alberto R. Santos is a Filipino senior turbine mechanical fitter and foreman with over 30 years of experience working on gas turbines, steam turbines, generators and other power plant equipment around the world. He has a B.S. in Mechanical Engineering and has worked extensively in Southeast Asia, the Middle East and Africa on inspection, maintenance, overhaul and repair projects. His work history details the various positions he has held and projects he has worked on for numerous companies specializing in power generation and petrochemical facilities.
The document is a summer training report submitted by Sunil Kumar detailing his training from June to July 2015 at the Electric Locomotive Shed in Gomoh, Dhanbad. It includes an acknowledgement, contents listing the topics covered, and sections about the company providing an overview of electric locomotive maintenance. Key topics discussed include the operation of electric locomotives, equipment such as the pantograph and traction motors, and the installation process for carbon brushes.
This technical report summarizes a visit to an electric locomotive workshop. It describes the key internal parts of an electric locomotive such as the transformer, rectifier, armature converter and traction motors. It provides photos and explanations of the control desk, instrumentation, electrical equipment and auxiliary systems used for cooling. Advantages of electric locomotives are highlighted like reduced emissions, maintenance and noise compared to diesel. The report concludes the workshop helped learn about electric locomotives used extensively in Indian railways.
PRESENTATION ON DIESEL TRACTION CENTRE GONDA ABDUS SAMAD
This document provides a presentation on the Diesel Traction Centre in N.E.R Gonda. It summarizes that the centre was established in 1982 with 22 locomotives and now houses 160 locomotives. It also discusses the classification system for locomotives, indicating gauge, power source, and service type. It highlights several innovations the centre has developed, including an SFC recorder to measure locomotive performance, a governor test stand to test diesel engine control, and tools to aid locomotive maintenance like a bogie frame manipulator.
Chittaranjan locomotive works (Summer Training Report)Deo Nath Jha
This document provides information about Chittaranjan Locomotive Works (CLW) in India. It summarizes CLW's history and production, including that it was established in 1947, produced its first steam locomotive in 1950, and has since produced various electric and diesel locomotives. It also gives technical details about the development of CLW's 3-phase locomotives, describing their electrical features, converter systems, and different brake systems. Finally, it provides specifications for some of CLW's most common locomotive models like the WAG-9, WAP-7, WAP-5, and WAP-4.
The document provides details about a project on vocational training in an electric locomotive shed in India from 2015-2016. It includes a history of electric locomotives, an overview of electric locomotive components like the pantograph and transformer, and descriptions of key parts of the locomotive cab. The document aims to educate students on electric locomotive functioning and components through detailed explanations and diagrams.
The document is a training report submitted by Shri Akash Bhai Sundarkand Wale, a final year BTech student in the Electrical and Electronics Engineering department of Vedant College of Engineering and Technology. The report details his 30 day training at the Kota Super Thermal Power Station, during which he learned about the various systems and operations at the power plant. It includes sections on the electricity generator, switchyard, turbine generator, steam turbine, coal handling plant, ash handling plant, water treatment plant, control room, and other salient features of the Kota Super Thermal Power Station.
The document summarizes a student's 60-day summer internship at the Rana Pratap Sagar Hydroelectric Power Station located on the Chambal River in Rajasthan, India. It includes an introduction to the power station, classifications of hydroelectric plants, diagrams of the single line diagram and feeders, explanations of how it works and the components involved, specifications of the turbine, generator and other equipment, advantages and disadvantages of hydroelectric power, and a conclusion on the benefits of practical training.
Alberto R. Santos is a Filipino senior turbine mechanical fitter and foreman with over 30 years of experience working on gas turbines, steam turbines, generators and other power plant equipment around the world. He has a B.S. in Mechanical Engineering and has worked extensively in Southeast Asia, the Middle East and Africa on inspection, maintenance, overhaul and repair projects. His work history details the various positions he has held and projects he has worked on for numerous companies specializing in power generation and petrochemical facilities.
The document is a summer training report submitted by Sunil Kumar detailing his training from June to July 2015 at the Electric Locomotive Shed in Gomoh, Dhanbad. It includes an acknowledgement, contents listing the topics covered, and sections about the company providing an overview of electric locomotive maintenance. Key topics discussed include the operation of electric locomotives, equipment such as the pantograph and traction motors, and the installation process for carbon brushes.
This technical report summarizes a visit to an electric locomotive workshop. It describes the key internal parts of an electric locomotive such as the transformer, rectifier, armature converter and traction motors. It provides photos and explanations of the control desk, instrumentation, electrical equipment and auxiliary systems used for cooling. Advantages of electric locomotives are highlighted like reduced emissions, maintenance and noise compared to diesel. The report concludes the workshop helped learn about electric locomotives used extensively in Indian railways.
PRESENTATION ON DIESEL TRACTION CENTRE GONDA ABDUS SAMAD
This document provides a presentation on the Diesel Traction Centre in N.E.R Gonda. It summarizes that the centre was established in 1982 with 22 locomotives and now houses 160 locomotives. It also discusses the classification system for locomotives, indicating gauge, power source, and service type. It highlights several innovations the centre has developed, including an SFC recorder to measure locomotive performance, a governor test stand to test diesel engine control, and tools to aid locomotive maintenance like a bogie frame manipulator.
Chittaranjan locomotive works (Summer Training Report)Deo Nath Jha
This document provides information about Chittaranjan Locomotive Works (CLW) in India. It summarizes CLW's history and production, including that it was established in 1947, produced its first steam locomotive in 1950, and has since produced various electric and diesel locomotives. It also gives technical details about the development of CLW's 3-phase locomotives, describing their electrical features, converter systems, and different brake systems. Finally, it provides specifications for some of CLW's most common locomotive models like the WAG-9, WAP-7, WAP-5, and WAP-4.
The document provides details about a project on vocational training in an electric locomotive shed in India from 2015-2016. It includes a history of electric locomotives, an overview of electric locomotive components like the pantograph and transformer, and descriptions of key parts of the locomotive cab. The document aims to educate students on electric locomotive functioning and components through detailed explanations and diagrams.
This training report summarizes information about Chittaranjan Locomotive Works (CLW) in India. CLW is one of the largest locomotive manufacturers in the world. It produces various types of electric locomotives for Indian Railways, including freight locomotives like the WAG-9 and WAG-7, and passenger locomotives such as the WAP-7, WAP-5, and WAP-4. The report describes the key components of electric locomotives, CLW's manufacturing process across its various shops, and provides specifications for different locomotive types.
The document provides details about Nand Lal Prajapati's industrial training at Chittaranjan Locomotive Works (CLW). It includes sections on the history and layout of CLW, the types of locomotives produced, and activities in different workshops and departments. CLW is the only major electric locomotive manufacturer in India, located in West Bengal. It began producing locomotives in 1961 and has steadily increased production. Prajapati thanks various CLW departments for their assistance during his training.
The document outlines test requirements and procedures for electrical equipment on locomotives. It details:
1) Safety precautions that must be taken before conducting high potential tests, such as checking insulation resistance is above 1 megohm.
2) Steps for connecting equipment, applying power, and conducting insulation resistance tests between circuits and the locomotive frame.
3) Procedures for applying high voltages of up to 2000V for new locomotives or 1500V for in-service locomotives to check insulation.
The document summarizes a seminar presentation on the Railway Locomotive Works in Chittranjan, West Bengal, India. It discusses the history of CLW, the largest electric locomotive manufacturer in Asia, and the types of locomotives produced, including DC motor, induction motor, and static equipment. It also describes testing and assembly sections, the braking system, and concludes that CLW is India's sole electric locomotive manufacturer, producing 225 locomotives per year with equipment supplied by companies like BHEL and ABB.
Electrical loco tripshed,sawai madhopurAkash Karol
Indian railways and loco tripshed ppt. it's my college ppt.in this ppt all information about Locomotives and indian Railway. The history of Indian railways is awesome. This ppt is helps you to make a better ppt.
Best of luck
Thank you.
This document describes an industrial training report on the Electric Locomotive Workshop in Bhusawal, India. It provides background on the history of Indian railways and introduces the POH (Periodic Overhauling) workshop in Bhusawal. It then describes the various sections of the workshop and their functions, such as repairing locomotives, traction motors, transformers, and performing tests. The workshop overhauls different types of electric locomotives and aims to improve the efficiency of the country's rail network.
The document provides details about the ISO 9001-2008 certified electric loco shed located in Santragachi, India. It maintains WAP-4 electric locomotives. The shed has three main sections: E-3 inspects and overhauls traction motors; E-4 maintains relays, speedometers, and microprocessors; E-5 inspects and services transformers, graduators, and SMGRs. The shed ensures locomotives are properly inspected and maintained to operate throughout the year.
Seawind is developing an innovative 6.2 MW offshore wind turbine system that can be fully assembled and installed without heavy cranes. The two-bladed turbine integrates with self-installing support structures to allow assembly at harbor and installation by simple tug boats. This novel approach aims to significantly reduce offshore wind costs by simplifying installation and maintenance compared to adapting three-bladed onshore designs.
This document provides information on different shops in a railway workshop, including the air conditioning shop, power shop, production control organization (PCO) shop, and train lighting shop. In the air conditioning shop sections, it describes the specifications and safety protections of roof mounted package units used for air conditioning trains. The power shop section outlines the substation and protective devices used. The PCO shop discusses the electrical inspections conducted on trains. Finally, the train lighting shop explains the fan and battery sections, including the types of fans and maintenance of lead acid and VRLA batteries.
This document provides a summary of Selvarajan G's work experience and qualifications. It outlines his 25 years of experience in electrical work, including 16 years of international experience in Yemen, Oman, and Libya oil fields. His roles have included chief electrician, rig electrician, electrical foreman, and senior electrician. He has experience maintaining electrical equipment on drilling rigs and camps according to maintenance plans and specifications. He is skilled in areas like inventory management, electrical installations, troubleshooting, and safety compliance. He holds qualifications like an electrical supervisor license and BOSIET certification.
Diesel Locomotive Works (DLW) in Varanasi manufactures diesel-electric locomotives for Indian Railways. It was established in 1956 and produced its first locomotive in 1964. DLW has supplied locomotives to other countries and produces up to 250 locomotives annually. Modern locomotives use an alternator, rectifier and AC induction traction motors in place of the older DC series motors. The diesel engine powers the alternator which produces electricity to run the traction motors and propel the locomotive.
The document discusses electric propulsion solutions from Nidec ASI. It provides a history of electric ship propulsion dating back to the 1920s. It then outlines the advantages of electric propulsion such as optimization of power generation, noise reduction, and reduced maintenance costs. The document proceeds to discuss Nidec ASI's long experience in marine propulsion systems and lists applications such as cruise vessels, ferries, and navy vessels. Configuration diagrams are provided for typical electric propulsion systems along with the components that Nidec ASI can supply.
The document provides a project report summary of Sohag Sarkar's 4-week vocational training at Chittaranjan Locomotive Works (CLW) in India. It includes an acknowledgement, history of CLW, milestones, descriptions of locomotive components like bogies and braking systems, manufacturing shops visited, and new projects. CLW is India's largest electric locomotive manufacturer, producing locomotives since 1950. The report describes CLW's production of various locomotive types over the years including the latest 3-phase AC locomotives.
BHARAT HEAVY ELECTRICALS LIMITED.JHANSI LOCOMOTIVE PPTRavindra Rawat
This document provides information about a 4-week industrial training at Bharat Heavy Electricals Limited (BHEL) in Jhansi, India. It discusses BHEL's diesel locomotive department and includes sections on diesel locomotive parts like the diesel engine, traction motors, pneumatic control systems, and bogie assembly. Diagrams show aspects like the layout of a diesel locomotive engine and its various components.
Juliet Joseph is applying for the position of Electrical Engineer. She holds a Bachelor of Technology degree in Electrical and Electronics Engineering from 2013. She has over 5 years of experience as an Electrical Engineer working on projects in the UAE and Saudi Arabia for companies like Tebodin, JSE Engineering, and ADCO. Her experience includes performing load flow and short circuit studies, preparing engineering drawings and specifications, and reviewing designs. She is proficient in software like ETAP, AutoCAD, and Enervista.
Diesel Locomotive Shed, North Western Railway123jaya
This Presentation is for those students who done their Training
from Diesel locomotive shed,Indian Railway.In this Power Point presentation i have gave a Brief introduction about loco and some important devices that we used in our loco. I think this is the only presentation that makes you easy to understand about diesel locomotive.
The document provides information about Pradeep Vyas's practical training at the Northern-Western Railway Workshop. It discusses the various shops within the workshop including the power shop, air conditioning shop, train lighting shop, and production and control department. It describes the key equipment and processes used in each shop's operations for maintaining railway equipment. The workshop provides hands-on training for engineering graduates and technicians.
Training ppt on Chittaranjan Locomotive WorksDhruv Upadhaya
This training presentation provides an overview of Chittaranjan Locomotive Works (CLW). It discusses the history of CLW including key dates of its establishment and production milestones. It then describes various types of locomotives produced at CLW, including diesel, electric, DC, and three-phase locomotives. Key components of electric locomotives such as traction motors, transformers, and static equipment are also explained. Finally, it summarizes the advantages of electric locomotives over diesel locomotives.
The document provides details about a summer training conducted at the North Western Railway workshop in Jodhpur. It discusses train lighting systems including axle driven and roof mounted alternator systems. It also describes roof mounted air conditioning units, train lighting accessories like regulators and fuses, and battery specifications. Finally, it gives an overview of the power supply system from generating stations to distribution substations and consumers.
This document describes a project report submitted by four students for their bachelor's degree in computer science and engineering. The report details their work on developing algorithms to efficiently mine frequent itemsets from transactional datasets using FP-tree data structures. It includes an introduction, literature review on existing techniques, problem formulation, system requirements, design of their proposed system and algorithms, implementation details, and conclusions.
The key elements of a hydroelectric power plant include a dam and reservoir to store water, a penstock to channel water from the reservoir to the powerhouse under pressure, and a turbine coupled to a generator in the powerhouse to convert the kinetic energy of the flowing water into electrical energy which is then transmitted via power lines. Other important components are trash racks to screen debris, a draft tube to recover water's kinetic energy after passing through the turbine, transformers to increase the voltage for transmission, and control systems to regulate water flow and generator output.
This training report summarizes information about Chittaranjan Locomotive Works (CLW) in India. CLW is one of the largest locomotive manufacturers in the world. It produces various types of electric locomotives for Indian Railways, including freight locomotives like the WAG-9 and WAG-7, and passenger locomotives such as the WAP-7, WAP-5, and WAP-4. The report describes the key components of electric locomotives, CLW's manufacturing process across its various shops, and provides specifications for different locomotive types.
The document provides details about Nand Lal Prajapati's industrial training at Chittaranjan Locomotive Works (CLW). It includes sections on the history and layout of CLW, the types of locomotives produced, and activities in different workshops and departments. CLW is the only major electric locomotive manufacturer in India, located in West Bengal. It began producing locomotives in 1961 and has steadily increased production. Prajapati thanks various CLW departments for their assistance during his training.
The document outlines test requirements and procedures for electrical equipment on locomotives. It details:
1) Safety precautions that must be taken before conducting high potential tests, such as checking insulation resistance is above 1 megohm.
2) Steps for connecting equipment, applying power, and conducting insulation resistance tests between circuits and the locomotive frame.
3) Procedures for applying high voltages of up to 2000V for new locomotives or 1500V for in-service locomotives to check insulation.
The document summarizes a seminar presentation on the Railway Locomotive Works in Chittranjan, West Bengal, India. It discusses the history of CLW, the largest electric locomotive manufacturer in Asia, and the types of locomotives produced, including DC motor, induction motor, and static equipment. It also describes testing and assembly sections, the braking system, and concludes that CLW is India's sole electric locomotive manufacturer, producing 225 locomotives per year with equipment supplied by companies like BHEL and ABB.
Electrical loco tripshed,sawai madhopurAkash Karol
Indian railways and loco tripshed ppt. it's my college ppt.in this ppt all information about Locomotives and indian Railway. The history of Indian railways is awesome. This ppt is helps you to make a better ppt.
Best of luck
Thank you.
This document describes an industrial training report on the Electric Locomotive Workshop in Bhusawal, India. It provides background on the history of Indian railways and introduces the POH (Periodic Overhauling) workshop in Bhusawal. It then describes the various sections of the workshop and their functions, such as repairing locomotives, traction motors, transformers, and performing tests. The workshop overhauls different types of electric locomotives and aims to improve the efficiency of the country's rail network.
The document provides details about the ISO 9001-2008 certified electric loco shed located in Santragachi, India. It maintains WAP-4 electric locomotives. The shed has three main sections: E-3 inspects and overhauls traction motors; E-4 maintains relays, speedometers, and microprocessors; E-5 inspects and services transformers, graduators, and SMGRs. The shed ensures locomotives are properly inspected and maintained to operate throughout the year.
Seawind is developing an innovative 6.2 MW offshore wind turbine system that can be fully assembled and installed without heavy cranes. The two-bladed turbine integrates with self-installing support structures to allow assembly at harbor and installation by simple tug boats. This novel approach aims to significantly reduce offshore wind costs by simplifying installation and maintenance compared to adapting three-bladed onshore designs.
This document provides information on different shops in a railway workshop, including the air conditioning shop, power shop, production control organization (PCO) shop, and train lighting shop. In the air conditioning shop sections, it describes the specifications and safety protections of roof mounted package units used for air conditioning trains. The power shop section outlines the substation and protective devices used. The PCO shop discusses the electrical inspections conducted on trains. Finally, the train lighting shop explains the fan and battery sections, including the types of fans and maintenance of lead acid and VRLA batteries.
This document provides a summary of Selvarajan G's work experience and qualifications. It outlines his 25 years of experience in electrical work, including 16 years of international experience in Yemen, Oman, and Libya oil fields. His roles have included chief electrician, rig electrician, electrical foreman, and senior electrician. He has experience maintaining electrical equipment on drilling rigs and camps according to maintenance plans and specifications. He is skilled in areas like inventory management, electrical installations, troubleshooting, and safety compliance. He holds qualifications like an electrical supervisor license and BOSIET certification.
Diesel Locomotive Works (DLW) in Varanasi manufactures diesel-electric locomotives for Indian Railways. It was established in 1956 and produced its first locomotive in 1964. DLW has supplied locomotives to other countries and produces up to 250 locomotives annually. Modern locomotives use an alternator, rectifier and AC induction traction motors in place of the older DC series motors. The diesel engine powers the alternator which produces electricity to run the traction motors and propel the locomotive.
The document discusses electric propulsion solutions from Nidec ASI. It provides a history of electric ship propulsion dating back to the 1920s. It then outlines the advantages of electric propulsion such as optimization of power generation, noise reduction, and reduced maintenance costs. The document proceeds to discuss Nidec ASI's long experience in marine propulsion systems and lists applications such as cruise vessels, ferries, and navy vessels. Configuration diagrams are provided for typical electric propulsion systems along with the components that Nidec ASI can supply.
The document provides a project report summary of Sohag Sarkar's 4-week vocational training at Chittaranjan Locomotive Works (CLW) in India. It includes an acknowledgement, history of CLW, milestones, descriptions of locomotive components like bogies and braking systems, manufacturing shops visited, and new projects. CLW is India's largest electric locomotive manufacturer, producing locomotives since 1950. The report describes CLW's production of various locomotive types over the years including the latest 3-phase AC locomotives.
BHARAT HEAVY ELECTRICALS LIMITED.JHANSI LOCOMOTIVE PPTRavindra Rawat
This document provides information about a 4-week industrial training at Bharat Heavy Electricals Limited (BHEL) in Jhansi, India. It discusses BHEL's diesel locomotive department and includes sections on diesel locomotive parts like the diesel engine, traction motors, pneumatic control systems, and bogie assembly. Diagrams show aspects like the layout of a diesel locomotive engine and its various components.
Juliet Joseph is applying for the position of Electrical Engineer. She holds a Bachelor of Technology degree in Electrical and Electronics Engineering from 2013. She has over 5 years of experience as an Electrical Engineer working on projects in the UAE and Saudi Arabia for companies like Tebodin, JSE Engineering, and ADCO. Her experience includes performing load flow and short circuit studies, preparing engineering drawings and specifications, and reviewing designs. She is proficient in software like ETAP, AutoCAD, and Enervista.
Diesel Locomotive Shed, North Western Railway123jaya
This Presentation is for those students who done their Training
from Diesel locomotive shed,Indian Railway.In this Power Point presentation i have gave a Brief introduction about loco and some important devices that we used in our loco. I think this is the only presentation that makes you easy to understand about diesel locomotive.
The document provides information about Pradeep Vyas's practical training at the Northern-Western Railway Workshop. It discusses the various shops within the workshop including the power shop, air conditioning shop, train lighting shop, and production and control department. It describes the key equipment and processes used in each shop's operations for maintaining railway equipment. The workshop provides hands-on training for engineering graduates and technicians.
Training ppt on Chittaranjan Locomotive WorksDhruv Upadhaya
This training presentation provides an overview of Chittaranjan Locomotive Works (CLW). It discusses the history of CLW including key dates of its establishment and production milestones. It then describes various types of locomotives produced at CLW, including diesel, electric, DC, and three-phase locomotives. Key components of electric locomotives such as traction motors, transformers, and static equipment are also explained. Finally, it summarizes the advantages of electric locomotives over diesel locomotives.
The document provides details about a summer training conducted at the North Western Railway workshop in Jodhpur. It discusses train lighting systems including axle driven and roof mounted alternator systems. It also describes roof mounted air conditioning units, train lighting accessories like regulators and fuses, and battery specifications. Finally, it gives an overview of the power supply system from generating stations to distribution substations and consumers.
This document describes a project report submitted by four students for their bachelor's degree in computer science and engineering. The report details their work on developing algorithms to efficiently mine frequent itemsets from transactional datasets using FP-tree data structures. It includes an introduction, literature review on existing techniques, problem formulation, system requirements, design of their proposed system and algorithms, implementation details, and conclusions.
The key elements of a hydroelectric power plant include a dam and reservoir to store water, a penstock to channel water from the reservoir to the powerhouse under pressure, and a turbine coupled to a generator in the powerhouse to convert the kinetic energy of the flowing water into electrical energy which is then transmitted via power lines. Other important components are trash racks to screen debris, a draft tube to recover water's kinetic energy after passing through the turbine, transformers to increase the voltage for transmission, and control systems to regulate water flow and generator output.
This document presents a project report on a mobile charging system using hybrid solar energy. It was submitted by three students to partially fulfill the requirements for a Bachelor of Technology degree in Electrical and Electronics Engineering.
The system uses both solar panels and wind turbines to generate electricity. The solar panels convert sunlight to DC current, while the wind turbines use wind power to rotate a generator and produce DC current. Both sources charge a circuit board simultaneously that is used to charge connected mobile phones. A digital clock and temperature display are also included.
The report includes an abstract, table of contents, introduction on renewable energy and hybrid power systems, literature review on solar, wind and hybrid systems, methodology and implementation details, results from testing, and
This thesis analyzes the stability of pillars and subsidence in an underground coal mine. It presents the objectives, methodology, and structure of the thesis. The literature review covers the basic principles of pillar design, including estimating pillar load using tributary area theory, pillar strength formulas, and pillar safety factors. Pillar design aims to maximize coal extraction while maintaining stable pillars. Subsidence from mining needs to be managed. The case study describes the mine site and presents observations of maximum subsidence, subsidence profiles, and how subsidence changes over time and distance from mining panels. Geo-mining parameters, lithology, empirical modeling, and numerical modeling are discussed to analyze pillar stability and subsidence behavior at the mine site. Results and
The document summarizes a 6-month internship project report on developing a solar tracking system. It provides background on the company where the internship was completed, Visesh Transmission Pvt. Ltd., an engineering company in Bangalore, India. It then describes the purpose and components of a solar tracking system, including photovoltaic panels, motors, microcontrollers, and actuators. The system works by using a microcontroller programmed with the sun's position over the year to orient the solar panels towards the sun for maximum efficiency. Solar tracking can increase energy output by 30% compared to fixed panels.
This document is a mini project report on developing an air bag crash sensor using MEMS. It discusses the hardware and software requirements for the system. The hardware includes a power supply, microcontroller, MEMS sensor, and LCD display. The power supply steps down AC voltage using a transformer. The microcontroller monitors the MEMS sensor for vibrations and controls the LCD display. The software requirements involve programming the microcontroller to detect crashes and trigger the air bag.
This document describes an energy audit conducted at Aryanet Institute of Technology in Palakkad, Kerala, India. It was a group project conducted by 5 students to fulfill the requirements of a Bachelor of Technology degree. The project involved measuring the energy consumption of various buildings and facilities on campus, identifying opportunities for energy savings, and making recommendations. Instruments used included lux meters, power factor meters, and energy meters. Load details were collected for the main block, seminar hall, canteen, labs, and other buildings. Designs for energy savings through LED lighting, automatic fans, efficient water coolers, computers, and photocopiers were proposed. The report also discussed power factor correction, tips for reducing thermal and electrical utility usage
This document describes a project report for an automatic solar night lamp created by a group of students. It includes sections on the principle, block diagram, circuit diagram, component descriptions, components used, working principle, uses, and conclusion of the project. The project aims to develop a lamp that can automatically turn on at night powered by a solar panel and turn off during the day using a light dependent resistor sensor.
Solar Bag for mobile charging with battery statusshivam singh
This document is a project report submitted by four students for their Bachelor of Engineering degree. It presents the design and implementation of a solar bag for mobile charging with battery status indication. The introduction provides background on solar energy and outlines the advantages and applications of a solar bag. Subsequent chapters describe the components used, including solar panels, relays, voltage regulators, an ADC, microcontroller, and LCD. The literature survey reviews similar past projects. Later chapters discuss the project implementation including the block diagram, circuit design, and interfacing the LCD with the microcontroller. The conclusion describes the basic working model of the solar bag.
Trackers direct solar panels or modules towards sun. These devices change their orientation throughout the day to follow the sun's path to maximize energy capture.In photovoltaic systems, trackers help minimize the angle of incidence (the angle that a ray of light makes with a line perpendicular to the surface) between the incoming light and the panel, which increases the amount of energy the installation produces. Concentrated solar photovoltaics and concentrated solar thermal have optics that directly accepts sunlight, so solar trackers must be angled correctly to collect energy
This document is a seminar report on Li-Fi technology submitted by Sanjush S. in partial fulfillment of a Bachelor of Technology degree. It provides an abstract, table of contents, and covers topics such as the history of Li-Fi, how Li-Fi works using visible light communication, Li-Fi technology components including transmitters and receivers, modulation techniques, standards, applications, and comparisons with Wi-Fi technology. The report was certified and acknowledged by faculty members at Aryanet Institute of Technology in Palakkad, India.
This document is a mini project report on the operation and maintenance of a 132/33kV substation. It contains 5 chapters that discuss key topics such as the classification of substations, single line diagrams, descriptions of common instruments in a substation like lightning arrestors, circuit breakers and transformers. It also covers protection for equipment like transformers and feeders. The last chapter provides conclusions and references. The overall document provides a comprehensive overview of the components, functions and maintenance of a high voltage substation.
The document discusses the 33/11 kV substation in Indiranagar, Lucknow. Key details include:
1) The substation receives power at 33kV from the main grid and contains transformers that step down the voltage to 11kV.
2) It has a total transformer capacity of 160MVA split between four transformers connected in parallel.
3) The substation contains equipment like circuit breakers, current transformers, lightning arrestors to monitor and regulate power flow.
4) Power is distributed from the substation through six 33kV feeders and multiple 11kV feeders to the surrounding Indiranagar area.
The document is a report on practical training conducted at the Kota Super Thermal Power Station. It provides details about the power plant layout, various circuits and components. Some key points:
- The report covers the coal handling plant, ash handling plant, electrostatic precipitator, boiler, steam turbine, turbo generator, cooling system, excitation system, water treatment plant and control room.
- The power plant has a generation capacity of 2x110 MW, 2x195 MW and 3x210 MW. It uses coal as its primary fuel and has various circuits to handle fuel, air/gas, feedwater and steam, and cooling water.
- Components described in detail include the boiler, steam turbine
Project report of kota super thermal power plantHîmãńshu Mêęńä
This document provides a summary of a practical training report submitted by Himanshu Derwal at the Kota Super Thermal Power Station from June 1-30, 2013. The report describes the power station's layout and key components including the coal handling plant, ash handling plant, boiler, steam turbine, turbo generator, cooling system, water treatment plant, and control room. It provides technical details and specifications of the various units and aims to document the practical experience and knowledge gained during the training.
This document provides a practical training report on Kota Super Thermal Power Station submitted by Arpit Budania. It includes an introduction describing the design and layout of the power station. The report then covers various sections including the coal handling plant, ash handling plant, electrostatic precipitator, boiler, steam turbine, turbo generator, cooling system, excitation system, water treatment plant and control room. It concludes with salient features of KSTPS such as its location, capacity, water source, boilers and fuels used.
The document provides details about the Kota Super Thermal Power Station located on the left bank of the Chambal River in Kota, India. It was designed and built in multiple stages to reach its current total installed capacity of 1240 MW. The power station uses coal from nearby mines as its primary fuel and water from the Kota Barrage on the Chambal River for its cooling system. It provides electricity to various parts of the local grid through 11 outgoing transmission lines. The document discusses the design process and includes diagrams of the various systems within the power station including the coal handling plant, boiler, steam turbine, generator, cooling system and control room.
Industrial training report on dlw varanasi for Main Receiving Substation, Tra...Devendra Kumar
Industrial training report on dlw Varanasi for Main Receiving Substation, Traction assembly shop, Maintenance area 2 and Loco Testing Shop(LTS).The industrial training report of DLW (DIESEL LOCOMOTIVE WORKS) is a different trade. i.e. Electronics and Communication, Electrical, Mechanical, Electrical & Electronics and many engineering holders have participated. The content of my industrial topic Main Receiving Substation, TRACTION ASSEMBLY SHOP, Maintenance area 2 and Loco Testing Shop
This document summarizes a practical training report on a 132 kV gas insulated substation (GSS) in Jalore, submitted in partial fulfillment of a Bachelor of Technology degree in electrical engineering. The 30-day training took place at the 132 kV GSS Jalore and covered topics like the single line diagram, bus bars, isolators, insulators, protective relays, circuit breakers, power transformers, current and potential transformers, transformer oil testing, lightning arrestors, the control room, earthing systems, and power line carrier communication.
The document provides details about a main project report submitted by four students for their Bachelor of Technology degree. It discusses studying various systems in a 500MW thermal power plant. The report includes chapters on the coal handling plant, ash handling plant, electrostatic precipitator, boiler, steam turbine, generator, condenser and cooling towers, water treatment plant, transformers, switchyard, and the start up procedure for Dr. NTTPS Stage-4 plant. The objective of the project is to study the operation, maintenance and protection of power transformers used in Stage-IV of Dr. NTTPS thermal power plant.
Sagar mehta summer training thermal power station full reportSagar Mehta
This document provides a practical training report submitted by Sagar Mehta to Rajasthan Technical University in partial fulfillment of the requirements for a Bachelor of Technology degree. The report details Mehta's summer training at the Nashik Thermal Power Station in Maharashtra, India. It includes sections on the history of the power sector and thermal power generation in India, an overview of the Nashik Thermal Power Station, descriptions of the key components and operations of a steam power plant, and summaries of Mehta's experiences working in various parts of the plant during the training.
HELLO FRINDS THIS REPORT IS OF INDUSTRIAL TRAINING ON DIESEL LOCOMOTIVE TECHNOLOGY.
IT IS VERY HELP FULL FOR YOU .
SO GO THROUGH IT .
**********************Best Of Luck ************************
INTRODUCTION OF INDIAN RAILWAY
DIESEL LOCOMOTIVE WORKSHOP .CHARBAGH
DIESEL ELECTRIC LOCOMOTIVE
WORKING MECHANISIM
IMPORTANT COMPONENTS OF LOCOMOTIVES
a) POWER PACK
b) FUEL SECTION
c) LUBE OIL CONTROL SECTION
i. FUEL INJECTION PUMP (FIP)
ii. INJECTORS
d) TURBO SUPER CHARGING (TSC)
e) BRAKES
f) COMPRESSOR / EXPRESSOR
g) GOVERNORS
h) TRACTION MOTER
i) BOGIE
j) GENERATOR
k) RADIATOR
l) ENGINE SECTION
m) CROSS HEAD
i. INLET AND EXHAUST VALVE
FAILURE ANALYSIS
a) MAGNAFLUX LAB
b) ULTRASONIC TEST
c) ZYGLO TEST
d) RDP TEST
This document is a report on a 6-week industrial training completed by Shubham Patel at the 220/132/33 KV substation in Barahuwa, Gorakhpur, Uttar Pradesh, India. It provides an overview of the substation, including its equipment like transformers ranging from 160MVA to 40MVA, incoming and outgoing transmission lines, and components within the substation like busbars, circuit breakers, protective relays, and current and voltage transformers. The report also discusses the selection of substation sites and provides a definition and overview of different types of substations.
This document discusses a study on the electrical equipment used at the Adani Vizag Coal Terminal Private Ltd (AVCTPL) facility in Visakhapatnam, India. It describes the various working modules at AVCTPL, including intermediate transfer towers, intermediate belt conveyors, stackers and reclaimers, silos, and a pump house. It also discusses the control room and AVCTPL substation grid, including the main objective of the distribution system, functional parts of the substation, and safety equipment. The document provides technical specifications for some of the electrical equipment used across the different modules.
Operational description of 400kv switchyard NTPC Ramagundam RSTPSPradeep Avanigadda
400 KV Switchyard of Ramagundam Super Thermal Power Station is the most vital switching station in the southern Grid. 2600 MW of Bulk Power generated by three 200 MW Units and four 500 MW Units of NTPC Ramagundam is evacuated for supplying to the southern states.
Switchyard consists of four 400 KV busbars fed by 7 Nos. of generators, 10 Nos. of 400 KV feeders, 3 Nos of 220 KV feeders and two nos. of 132 Kv feeders as shown in the single line diagram of 400 Kv switch yard.
In addition to the above, four nos. of Tie Transformers, five nos. of Auto transformers, two nos. of Shunt Reactors and one Bus reactor are provided.
Priyanshu Pal completed a vocational training at the Technical Training Centre of Banaras Locomotive Works in Varanasi, India. The report provides details of the training, including acknowledging those who helped with the training. It introduces Banaras Locomotive Works, which was established in 1961 in collaboration with the American Locomotive Company to manufacture diesel-electric locomotives for Indian Railways. It produces various types of locomotives and diesel generators. The report describes the Traction Assembly Shop where locomotive components are assembled, including the control panel, alternator, traction motors, diesel engine, and other systems. It provides details on the control panel, dynamic braking system, and alternator.
This document is a curriculum vitae for D. Sheik Syedali, an electrical engineer with over 5 years of experience in Saudi Arabia and Oman. He has experience installing and coordinating the erection of 380kV, 132kV, and 13.8kV switchyards and substations for companies like ABB, Hyundai, and Siemens. Currently he works as a site electrical engineer in Saudi Arabia coordinating the installation of equipment like GIS, transformers, reactors, and switchgear.
This document provides details about Avisekh Ghosh's 2-week training project at the Titagarh Generating Station (TGS) of CESC Limited from June 13-25, 2016. It thanks the various people who helped with the project, provides background on CESC and TGS, and outlines the content that will be covered in the project report, including the basic cycles and components of a thermal power plant.
training report on thermal power plant & thermal power generation by sagar me...Sagar Mehta
This document provides a practical training report submitted by Sagar Mehta to Rajasthan Technical University in partial fulfillment of the requirements for a Bachelor of Technology degree. The report details Mehta's summer training at the Nashik Thermal Power Station in Maharashtra, India. It includes sections on the history of the power sector and thermal power generation in India, an overview of the Nashik Thermal Power Station, descriptions of the various systems and processes within a thermal power plant including the steam power plant, coal handling plant, water treatment plant, boilers, turbines, generators, condensers and ash handling plant. The report concludes with discussions on energy conservation, auditing, and suggestions.
training reportON Thermal power plantt (nashik tps)pdfSagar Mehta
This document provides a practical training report submitted by Sagar Mehta to Rajasthan Technical University in partial fulfillment of the requirements for a Bachelor of Technology degree. The report details Mehta's summer training at the Nashik Thermal Power Station in Maharashtra, India. It includes sections on the history of the power sector and thermal power generation in India, an overview of the Nashik Thermal Power Station, descriptions of the various systems and processes within a thermal power plant including the steam power plant, coal handling plant, water treatment plant, boilers, turbines, generators, condensers and ash handling plant. The report concludes with discussions on energy conservation, auditing, and suggestions.
This document provides an overview of maintenance of equipment at a 33/11kV substation. It discusses key components like transformers, busbars, insulators, circuit breakers, metering equipment, relays, miscellaneous equipment, and protection systems. It also covers substation design considerations like earthing methodology and materials. The document aims to give an understanding of maintenance needs for high voltage substation equipment.
A seminar report on stps by ashok khojaASHOK KHOJA
The document provides details about Suratgarh Super Thermal Power Station in Rajasthan, India. It discusses the introduction and installed capacity of the power plant. Suratgarh STPS is the first super thermal plant in Rajasthan, located 25km from Suratgarh town. It has a total generation capacity of 1500MW through 6 units of 250MW each. The power plant uses coal from MP fields and water from the Indira Gandhi Canal. Future expansion plans include adding 2 units of 660MW each.
Abdelrahman Mokhtar is an electrical engineer seeking a challenging career in engineering. He has over 5 years of experience in testing and commissioning high, medium, and low voltage substations in Saudi Arabia. He also has 1 year of experience as a sales engineer in Egypt. He holds a Bachelor's degree in Power and Electrical Machines from Ain Shams University in Egypt.
Similar to Shri akash bhai sundarkand wale thermal report (20)
Exploiting Artificial Intelligence for Empowering Researchers and Faculty, In...Dr. Vinod Kumar Kanvaria
Exploiting Artificial Intelligence for Empowering Researchers and Faculty,
International FDP on Fundamentals of Research in Social Sciences
at Integral University, Lucknow, 06.06.2024
By Dr. Vinod Kumar Kanvaria
This presentation was provided by Steph Pollock of The American Psychological Association’s Journals Program, and Damita Snow, of The American Society of Civil Engineers (ASCE), for the initial session of NISO's 2024 Training Series "DEIA in the Scholarly Landscape." Session One: 'Setting Expectations: a DEIA Primer,' was held June 6, 2024.
The simplified electron and muon model, Oscillating Spacetime: The Foundation...RitikBhardwaj56
Discover the Simplified Electron and Muon Model: A New Wave-Based Approach to Understanding Particles delves into a groundbreaking theory that presents electrons and muons as rotating soliton waves within oscillating spacetime. Geared towards students, researchers, and science buffs, this book breaks down complex ideas into simple explanations. It covers topics such as electron waves, temporal dynamics, and the implications of this model on particle physics. With clear illustrations and easy-to-follow explanations, readers will gain a new outlook on the universe's fundamental nature.
This presentation includes basic of PCOS their pathology and treatment and also Ayurveda correlation of PCOS and Ayurvedic line of treatment mentioned in classics.
it describes the bony anatomy including the femoral head , acetabulum, labrum . also discusses the capsule , ligaments . muscle that act on the hip joint and the range of motion are outlined. factors affecting hip joint stability and weight transmission through the joint are summarized.
This slide is special for master students (MIBS & MIFB) in UUM. Also useful for readers who are interested in the topic of contemporary Islamic banking.
Main Java[All of the Base Concepts}.docxadhitya5119
This is part 1 of my Java Learning Journey. This Contains Custom methods, classes, constructors, packages, multithreading , try- catch block, finally block and more.
Macroeconomics- Movie Location
This will be used as part of your Personal Professional Portfolio once graded.
Objective:
Prepare a presentation or a paper using research, basic comparative analysis, data organization and application of economic information. You will make an informed assessment of an economic climate outside of the United States to accomplish an entertainment industry objective.
Executive Directors Chat Leveraging AI for Diversity, Equity, and InclusionTechSoup
Let’s explore the intersection of technology and equity in the final session of our DEI series. Discover how AI tools, like ChatGPT, can be used to support and enhance your nonprofit's DEI initiatives. Participants will gain insights into practical AI applications and get tips for leveraging technology to advance their DEI goals.
Executive Directors Chat Leveraging AI for Diversity, Equity, and Inclusion
Shri akash bhai sundarkand wale thermal report
1. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
A
PROJECT REPORT
ON
KOTA SUPER THERMAL POWER STATION
Submitted
in
partial fulfillment for the award of the Degree of
Bachelor of Technology
In
Department of Electrical & Electronics Engineering
Guided By: Submitted By:
Rajendra Dhakad SHRI AKASH BHAI
(Lect. Of EEE) SUNDARKAND WALE
1
(10EVNEX001)
Vedant College of Engineering and Technology
Rajasthan Technical University, Kota
2010-2014
2. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
ACKNOWLEDGEMENT
It is a matter of great pleasure and privilege for me to present this report of 30
days on the basis of practical knowledge gained by me during practical training at
KOTA SUPER THERMAL POWER STATION (K.S.T.P.S.), KOTA (Rajasthan)
during session 2013-2014.
I am grateful to Mr. S.C. Madan for their persistent help and for providing some
of the technical data in form of computer print outs.
Last but not the least I am equally obliged to all those engineers’ technical
personnel and operators at K.S.T.P.S. who gave me their valuable time and rendered
practical knowledge in my training period.
And at last I want to thank my colleagues. Without their help guidance and
suggestions it was not possible to produce this training report.
2
3. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
S.NO CONTENT Page No
1 Introduction 9
1.1 K.S.T.P.S is designed in following stage 10
1.2 Location 10
1.3 Land 11
1.4 Coal 11
1.5 Water 11
1.6 Design Features 11-12
2 GENRAL LAYOUT & BASIC IDEA 13
2.1 Fuel & Ash Circuit 14
2.2 Air & Gas Circuit 14
2.3 Feed Water & Steam Circuit 14
2.4 Cooling Water Circuit 15
2.5 Coal Handling Plant 15
2.5.1 Introduction 15
2.6 Wagon Unloading System 15-16
2.6.1 Wagon Tripler 16
2.7 Crushing System 17
2.7.1 Crusher House 17
2.7.2 Primary Crusher 17
2.7.3 Roll Crusher 17
2.7.4 Rotary Breaker 17-18
3
4. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
2.7.5 Secondary Crusher 18
2.8 Construction & Operation 18
2.9 Conveying system 19
2.9.1 Stacker Recamier 19
2.9.2 Conveyor Specification of Stacker Rellaimer 19
2.9.3 Conveyor Specification 19-20
2.10 Feeders 20
2.11 ASH Handling Plant 21
2.11.1 Puel & Ash Plant 21
2.11.2 Air & Gas Plant 21
2.11.3 Ash Disposal & Dust Collection Plant 22
2.11.4 Utilization 22
2.12 Electro-static Precipitator 23
2.12.1 Scope & Principal operation 23
2.13 Controller 23
2.14 H.V.R.T 23-24
2.15 E.S.P Field 25
3.1. BOILERS ARE CLASSIFIED AS 26
3.1.1. FIRE TUBEBOILER 26
3.1.2. WATER TUBE BOILER 26-27
3.2. FURNACE 27
3.3. PULVERISED FUEL SYSTEM 28
3.4. FUEL OIL SYSTEM 28-29
4
5. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
3.5 BOILER DRUM 29-30
3.6. DRAFT SYSTEM 30
3.7. DRAUGHT FANS 31-32
3.8. ECONOMIZER 32-33
3.9. AIR PREHEATERS 33-34
3.10 SUPERHEATER 34-35
3.11 REHEATER 35
3.12 CIRCULATION SYSTEM 35
3.13 SOOT BLOWER 35-36
3.14 TECHNICAL SPECIFICATION OF BOILER 36-37
3.15 FUEL 37
3.16 GENERAL DESCRIPTION 37-38
STEAM TURBINE 39
4.1. INTRODUCTION 39
4.2. PRINCIPAL OF OPERATION OF STEAM TURBINE 39-40
4.3. TECHNICAL DATA OF TURBINES 41-42
4.4. DESCRIPTION OF STEAM TURBINES 42-44
4.5. ELECTRICITY GENERATOR 44-45
4.6. TURBO GENERATOR 46-50
4.7. HYDROGEN COOLERS 50
4.8. ROTOR 50-53
4.9. TECHNICAL DATA 53-54
5
6. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
4.10. COOLING SYSTEM 54-55
EXCITATION SYSTEM 56
5.1. FUNCTION OF EXCITATION SYSTEM 56
5.2. TYPE OF EXCITATION SYSTEM 56
5.3. STATIC EXCITATION SYSTEM 56-57
5.4. GENERAL ARRANGEMENT 57-58
5.5. OPERATION 58
5.6. WATER TREATMENT PLANT 58-60
TRANSFORMER 61
6.1. INTRODUCTION 61-62
6.2GENRATOR TRANSFORMER 62-63
6.3 STATION TRANSFORMER 63
6.4 UNIT AUXILIARY TRANSFORMER 64
6.5. UNIT STATIC TRANSFORMER 64
6.6. UNIT SERVICE TRANSFORMER 64
6.7. SWITCH YARD 64
6.8. CIRCUIT BREAKERS 65
6.9. ISOLATOR 65
6.10. CURRENT TRANSFORMER 65-66
6.11. POTENTIAL TRANSFORMER 66
6.12. LIGHTENING ARRESTOR 66
6
7. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
6.13. 220 KV MOCB 66
6.14. 220 KV ISOLATORS 67
6.15. 220 KV CURRENT TRANSFORMER 67
6.16. CIRCUIT BREAKER 67-68
6.17. POWER CAPACITOR 68
6.18. 220 KV LIGNTENING ARRESTOR 68
PROTECTION 69
7.1. INTRODUCTION 69
7.2. GENERAL PROTECTION 69
7.3. SALIENT FEATURE OF K.S.T.P.S. 69-70
7.4. Fuel 71
CONCLUSION 72
REFFERENCES 73
OTHER 47
7
8. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
FIGURE LIST
Figure No Page
Figure 1: Layout of thermal power plant 13
Figure 2: Wagon Tripler 16
Figure 3: Layout of coal mill AB 20
Figure 4: High Voltage Rectifier Transformer 24
Figure 5: Water Cooled Furnance 27
Figure 6: Tangential Firing 28
Figure 7: Steam Drum Internals 29
Figure 8: Force Drought Fan 31
Figure 9: Induced Drought Fan 32
Figure 10: Economizer 33
Figure 11: Air Preheater 34
Figure 12: Steam Turbine 39
Figure 13: Stator Assembly 47
Figure 14: Rotor of Generator 51
8
9. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
Figure 15: Hydrogen Cooled Alternator 55
9
INTRODUCTION
For the power generation with 2x110MW, 3x210MW & 2x195 of K.S.T.P.S. authorities
are required to be operative to active full operation. The auxiliaries are basically
operation either on L.T. System i.e. 415 V 3-Ø power supply is made available to the
system after providing the station transformer of 3x50 MVA capacity with voltage 220
KV/ 7.2/7.2 KV & different service transformers of capacity 1.0 MVA, 1.5 MVA, 2.0
MVA, which are located near the load centre as the transformer having the voltage of 6.6
KV /415 V. The 6.6 KV power is distributed through 6.6 KV interconnected Bus System
for all the five units with a control through DC of 220 V.
The 415 V power supply is done through a L.T. SWGR (Switchgear) which are located
nearby the distribution transformer as well as the load centers. The all incomers, which
are breaker controlled , are having the control the L.T. SWGR are having the control
system on 110 / 220 V AC. The 6.6 KV power supply which are either MOCB
(Minimum Oil Circuit Breaker) of JYOTI make or Air Circuit Breakers.
The 6.6 KV power supply to various draining equipment’s i.e. more is made through
breakers which are either MOCB of Jyoti make air circuit breaker which are either of
voltage makers as well as SF 6 of NGEF make. The LT supply is also controlled through
air break circuit breaker which are either L&T make or English Electric Company of
India. The various H.T. motors are switched on started through on direct ON line (DOL)
in order to inverse the availability of equipment at full efficiency without time gap.
10. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
Further, the 6.6 KV system which is normally in delta configuration and terms as an
unearthed system so also to keep the running motor complete in operating condition in
case of anyone .phase of motor winding is earthed due to any one reason. Earthling is
detected by an protection system with alarm facility to take remedial measures
immediately and at the same time to maintain the generation level in the same condition,
prior to occurring the earth fault the single phase earth fault is detected in due course till
the motor is not earthed to other or another phase. “PUBLIC ADDRESS SYSTEM” is
available through in area of each unit which helps in fast communication for prompt
remedial measure. Soot Blowers are there in the boiler area on the furnace side or Zone
which helps in blowing the soot / ash deposition regularly of the furnace wall /
economizer tubes to keep heat transfer at the required parameter.
In April 1973, Central Electricity Authority prepared a Project Report for power station
comprising of the two units of each of capacity 110 MW for RSEB subsequently in
September. 1975 this was revised by the Consultant Thermal Design Organization ,
Central Electricity Authority for invention of 2x110 MW units being manufactured by
BHEL, Hyderabad in 1st Stage. The planning commission cleared the project report in
Sept., 1976 for installation of two units each of 110 MW in first estimated cost of Rs. 143
Corers.
The KSTPS has four stage & six unit power station. In first stage there is 2 unit of 110
MW, in second stage 2 unit of 210 MW. In third & fourth stage, there each having
210MW &195 MW units respectively. The construction of fifth stage Of 195 MW is
under construction and may be possibly completed up to Sept. 2008. The total power
generated in KSTPS is 1045 MW.
1.1. K.S.T.P.S. ISDESIGNED IN FOLLOWING STAGES
STAGE I - 2x110 MW
STAGE II - 2X210 MW
10
11. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
STAGE III - 1X210 MW
STAGE IV - 1X195 MW
STAGE V - 1X195MW
11
1.2. LOCATION
The Kota Thermal Power Station is ideally on the left bank of Chambal River at Up
Stream of Kota Barrage. The large expanse of water reached by the barrage provides an
efficient direct circulation of cooling system for the power station. The 220 KV GSS is
within ½ Kms. from the power station.
1.3. LAND
Land measuring approx. 250 hectares was required for the project in 1976, For
disposal of ash tank very near to power station is acquired which the ash in slurry
form is disposed off through ash and slurry disposal plants.
1.4. COAL
Coal India limited owns and operates all the major coal fields in India through its
coal producing subsidiary companies viz. Eastern Coal Fields Limited, Western
Coal Fields Limited/Coal India limited is supply coal from its coal mines of coal
producing subsidiaries BCCL, SECL & ECL to Kota Thermal Power Station
through railway wagons. The average distances of SECL, ECL & BCCL are 800,
950 and 1350 Kms. respectively.
1.5. WATER
The source of water for power station is reservoir formed by Kota Barrage on the
Chambal River. In case of large capacity plants huge quantities of coal and water
is required. The cost of transporting coal and water is particularly high.
Therefore, as far as possible, the plant must be located near the pit rather than at
12. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
load Centre for load above 200 MW and 375 MW. The transportation of electrical
energy is more economical as compared to the transportation of coal.
12
1.6. DESIGN FEATURES
The satisfactory design consists of the flowing steps.
Estimation of cost.
Selection of site.
Capacity of Power Station.
Selection of Boiler & Turbine.
Selection of Condensing Unit.
Selection of Electrical Generator.
Selection of Cooling System.
Design of Control and instrumentation system.
The design of steam power station requires wide experience as the subsequent
operation and maintenance are greatly affected by its design. The most efficient
design consists of properly sized component designed to operate safely and
conveniently along with its auxiliaries and installation.
13. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
GENERAL LAYOUT & BASIC IDEA
A control system of station basically works on Rankin Cycle. Steam is produced in
Boiler is exported in prime mover and is condensed in condenser to be fed into the boiler
again. In practice of good number of modifications are affected so as to have heat
economy and to increase the thermal efficiency of plant.
13
14. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
Fig.2.1 Layout of Thermal Power Plant
The Kota Thermal Power Station is divided into four main circuits.
14
Fuel and Ash Circuit.
Air and Gas Circuit.
Feed water and Steam Circuit.
Cooling Water Circuit.
2.1. FUEL & ASH CIRCUIT
Fuel from the storage is fed to the boiler through fuel handling device. The fuel used in
KSTPS is coal, which on combustion in the boiler produced the ash. The quantity of ash
produced is approximately 35-40% of coal used. This ash is collected at the back of the
boiler and removed to ash storage tank through ash disposal equipment.
15. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
15
2.2. AIR AND GAS CIRCUIT
Air from the atmosphere is supplied to the combustion chamber of Boiler through the
action of forced draft fan and induced draft fan. The flue gas gases are first pass around
the boiler tubes and super-heated tubes in the furnace, next through dust collector (ESP)
& then economizer. Finally, they are exhausted to the atmosphere through fans.
2.3. FEED WATER AND STEAM CIRCUIT
The condensate leaving the condenser is first heated in low pressure (LP) heaters through
extracted steam from the lower pressure extraction of the turbine. Then its goes to
dearator where extra air and non-condensable gases are removed from the hot water to
avoid pitting / oxidation. From dearator it goes to boiler feed pump which increases the
pressure of the water. From the BFP it passes through the high pressure heaters. A small
part of water and steam is lost while passing through different components therefore
water is added in hot well. This water is called the makeup water. Thereafter, feed water
enters into the boiler drum through economizer. In boiler tubes water circulates because
of density difference in lower and higher temperature section of the boiler. The wet steam
passes through superheated. From superheated it goes into the HP turbine after expanding
in the HP turbine. The low pressure steam called the cold reheat steam (CRH) goes to the
reheater (boiler). From reheater it goes to IP turbine and then to the LP turbine and then
exhausted through the condenser into hot well.
2.4. COOLING WATER CIRCUIT
A large quantity of cooling water is required to condense the steam in condenser and
marinating low pressure in it. The water is drawn from reservoir and after use it is
drained into the river.
16. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
16
2.5. COAL HANDLING PLANT
2.5.1. INTRODUCTION
It can be called the heart of thermal power plant because it provided the fuel for
combustion in boiler. The coal is brought to the KSTPS through rails there are fourteen
tracks in all for transportation of coal through rails. The main coal sources for KSTPS are
SECL (South Eastern Coalfields Limited), ECL (Eastern Coalfield Limited) and BCCL
(Bharat Coking Coal Limited). Everyday 3 to 4 trains of coal are unloaded at KSTPS.
Each train consists of 58 wagons and each wagon consists of 50 tons of coal. The
approximate per day consumption at KSTPS is about 1400 metric tons. It costs
approximate 2 corers of rupees per day including transportation expenses. The coal is
firstly unloaded from wagon by wagon trippers then crushed by crushers and magnetic
pulley and pulverized to be transformed to the boiler. The whole transportation of coal is
through conveyor belt operated by 3-Ø Induction motor.
The coal handling plant can broadly be divided into three sections:
1) Wagon Unloading System.
2) Crushing System.
3) Conveying System.
2.6. WAGON UNLOADING SYSTEM
2.6.1. WAGON TRIPLER
It unloads the coal from wagon to hopper. The hopper, which is made of Iron is in the
form of net so that coal pieces of only equal to and less than 200 mm. size pass through
it. The bigger ones are broken by the workers with the help of hammers. From the
hopper coal pieces fall on the vibrator. It is a mechanical system having two rollers each
at its ends.
17. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
The rollers roll with the help of a rope moving on pulley operated by a slip ring induction
motor with specification:
Fig. 2.2 Wagon Tripler
Rated Output : 71 KW.
Rated Voltage : 415 V.
Rated Current : 14.22 Amp.
Rated Speed : 975 rpm.
No. of phases : 3
Frequency : 50 Hz.
The four rollers place themselves respectively behind the first and the last pair of wheels
of the wagon. When the motor operates the rollers roll in forward direction moving the
wagon towards the “Wagon Table”. On the Wagon table a limit is specified in which
wagon to be has kept otherwise the triple would not be achieved.
17
18. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
18
2.7.CRUSHING SYSTEM
2.7.1. CRUSHER HOUSE
It consists of crushers which are used to crush the coal to 20 mm. size. There are mainly
two types of crushers working in KSTPS
Primary Crushers i.e. i) Rail crushers or ii) Rotary breaker.
Secondary Crushers. i.e. Ring granulators.
2.7.2. PRIMARY CRUSHERS
Primary crushers are provided in only CHP stage 3 system, which breaking of coal in
CHO Stage 1 & Stage 2 system is done at wagon Tripler hopper jail up to the size (-)
250 mm.
2.7.3. ROLL CRUSHER
Type : 80” 5 A breakers.
Capacity : 1350 TPH Rates/ 1500 TPH Design.
Feed material : Rom Coal.
Feed size : (-) 1200 mm. (approx.)
End Product size : (-) 500 mm.
Motor rating : 2 Nos. 125 KW, 100 rpm.
Crushers : 225.
2.7.4. ROTARY BREAKER
Type : 12’ x 21o Rotary Breaker.
Capacity : 800 TPH Rated/ 1000 TPH Design.
Feed Material : Coal with rejects.
19. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
19
Feed size : (-) 0-500 mm.
End product size : (-) 0-200 mm.
Motor rating : 125 HP, 1500 rpm.
2.7.5. SECONDARY CRUSHER
Basically there are four ways to reduce material size impact attrition, Shearing and
Compression. Most of the crushers employ a combination of three crushing methods.
Ring granulators crush by compressing accompanied by impact and shearing. The unique
feature of this granulator is the minimum power required for tone for this type of material
to be crushed compared to that of other type of crushers.
2.8. CONSTRUCTION & OPERATION
Secondary crushers are ring type granulators crushing at the rate of 550 TPH / 750 TPH
for input size of 250 mm. and output size of 20 mm. The crusher is coupled with motor
and gearbox by fluid coupling.
Main parts of granulator like break plates, cages, crushing rings and other internal parts
are made of tough manganese (MN) steel.
The rotor consists of four rows of crushing rings each set having 20 Nos. of toothed rings
and 18 Nos. of plain rings. In CHP Stage 1 & 2 having 64 Nos. of ring hammers. These
rows are hung on a pair of suspension shaft mounted on rotor discs. Crushers of this
type employ the centrifugal force of swinging rings stroking the coal to produce the
crushing action. The coal is admitted at the top and the ring strokes the coal downward.
The coal discharges through grating at the bottom.
20. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
20
2.9. CONVEYING SYSTEM
2.9.1. STACKER RECAMIER
The stacker re-claimer unit can stack the material on to the pipe or reclaim the stack filed
material and fed on to the main line conveyor. While stacking material is being fed from
the main line conveyor via Tripler unit and vibrating feeder on the intermediate conveyor
which feds the boom conveyor of the stacker cum reclaimed. During reclaiming the
material discharged on to the boom conveyor by the bucket fitted to the bucket wheel
body and boom conveyor feeds the material on the main line conveyor running in the
reverse direction.
2.9.2. CONVEYOR BELT SPECIFICATION OF STACKER / RECLAIMER
Belt width : 1400 mm.
Speed : 2.2 m/second.
Schedule of motor : All 3-Ø induction motors.
Bucket wheel motor : 90 KW.
Boom Conveyor motor : 70 KW.
Intermediate Conveyor Motor : 90 KW.
Boom Housing Motor : 22 KW.
Slewing assembly : 10 KW.
Travel Motor : 7.5 KW.
Vibrating Feeder : 2x6 KW.
Total installed power : 360 KW.
2.9.3. CONVEYOR SPECIFICATION
Capacity : 1) 1350 tons per hour.
2) 750 tons per hour.
21. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
No. of conveyor : 38
Horizontal length : 28 meters.
Lift(M) (approx.) : Variable to suit the system.
Belt width : 1400 mm. specification of conveyor
motor
21
2.10. FEEDERS
This structure is erected to serve the purpose of storage. Underground machines are
installed known as plow feeder machines.
These machines collect the coal from conveyor and drop it to the other from one
conveyor with the help of jaws and this coal is taken to huge erected structure from where
the coal falls to the ground Jali chutes are used to prevent dust.
Fig. 2.3 Layout of Coal Mill AB
22. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
22
2.11. ASH HANDLING PLANT
This plant can be divided into 3 sub plants as follows:-
1) Fuel and Ash Plant.
2) Air and Gas Plant.
3) Ash Disposal and & Dust Collection Plant.
2.11.1. FUEL AND ASH PLANT
Coal is used as combustion material in KTPS, In order to get an efficient utilization of
coal mills. The Pulverization also increases the overall efficiency and flexibility of
boilers. However for light up and with stand static load, oil burners are also used. Ash
produced as the result of combustion of coal is connected and removed by ash handling
plant. Ash Handling Plant at KTPS consists of specially designed bottom ash and fly ash
in electro static precipitator economizer and air pre-heaters hoppers.
2.11.2. AIR & GAS PLANT
Air from atmosphere is supplied to combustion chamber of boiler through the action of
forced draft fan. In KTPS there are two FD fans and three ID fans available for draft
system per unit. The air before being supplied to the boiler passes through pre-heater
where the flue gases heat it. The pre heating of primary air causes improved and
intensified combustion of coal.
The flue gases formed due to combustion of coal first passes round the boiler tubes and
then it passes through the super heater and then through economizer. In re-heater the
temperature of the steam (CRH) coming from the HP turbines heated with increasing the
number of steps of re-heater the efficiency of cycle also increases. In economizer the heat
of flue gases raises the temperature of feed water. Finally the flue gases after passing
through the Electro-Static Precipitator is exhausted through chimney.
23. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
2.11.3. ASH DISPOSAL & DUST COLLECTION PLANT
KSTPS has dry bottom furnace. Ash Handling Plant consists of especially designed
bottom and fly ash system for two path boiler. The system for both units is identical and
following description is applied to both the units the water compounded bottom ash
hopper receives the bottom ash from the furnace from where it is stores and discharged
through the clinker grinder. Two slurry pumps are provided which is common to both
units & used to make slurry and further transportation to ash dyke through pipe line.
Dry free fly ash is collected in two number of 31 fly ash hoppers which are handled by
two independent fly ash system. The ash is removed from fly ash hoppers in dry state are
carried to the collecting equipment where it is mixed with water and resulting slurry
sump is discharged.
23
2.11.4. UTILIZATION
Utilization of coal-ash is always practice than its disposal. There are various methods of
utilization of coal-ash along with established engineering technologies some of them are
mentioned below:
1. Manufacturing of building materials.
2. Making of concrete.
3. Manufacturing of pozzuolana cement.
4. Road construction etc.
In all the above cases financial constraint discourages the entrepreneurs to take up the
work. In view of the environmental impact of disposal, Government may give attractive
subsidy and create marketing facility so that entrepreneurs may come forward to use as
their raw material.
24. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
2.12. ELECTRO-STATIC PRECIPITATOR
2.12.1. SCOPE& PRINCIPLE OF OPERATION
For general mankind, today an Eco friendly industry is must. As far as air pollution is
concerned now a days various flue gases filter are there in service. The choice depends on
the size of suspended particle matter. These filters are E.S.P. Fabric filter high efficiency
cyclone separations and sideling room. Fop fly ash, where the particle size vary from
0.75 microns to 100 micron use gradually use E.S.P. to purify the flue gases due to its
higher efficiency & low running cost etc. In an ESP the dust ladder gas is passed through
an intense electric field, which causes ionization of the gases & they changed into ion
while traveling towards opposite charged electrode get deposited as particles and thus
dust is electric deposited an electrode creating the field. It is continuous process.
24
2.13. CONTROLLER
Now a day micro-processor based intelligent controllers are used to regulate the power
fed to the HVR. The controls the firing / ignition angle of the thyristor connected in
parallel mode. Input out waves of the controller and HVR are also shown above, which
clearly indicates that average power fed to ESP field can be controlled by variation of the
firing angle of thyristor.
The output of controller with respect to time is also controlled by microprocessor, so that
ESP operation is smooth and efficient. The char is as shown As can be seen in the event
of spark between electrodes the output of controller is reduced to zero for few
milliseconds for quenching the spark. Controller also takes place care of fault in KVR
and gives a trapping and non-trapping alarm as per the nature of fault.
2.14. HIGH VOLTAGE RECTIFIER TRANSFORMER
25. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
HVR receives the regulated supply from controller. It steps up to high voltage rectifier.
The D.C. supply is fed to E.S.P. field through its negative bushing. The positive bushing
so connected to earth through small resistance which forms a current feedback circuit. A
very high resistance column is also connected with negative bushing. It forms the voltage
feedback circuit. These two feedbacks are used in the controller for indication and control
purpose.
Fig.2.4 High Voltage Rectifier Transformer
25
26. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
26
2.15. E.S.P. FIELD
The field consists of emitting and collecting electrodes structure which are totally isolated
from each other and hanging with the top roof of field. The emitting is also isolated from
the roof through the support insulators which are supporting the emitting electrode frame
works and also the supply to these electrodes is fed through support insulators. The
collecting electrodes are of the shape of flat plates. By several similar plates which the
emitting electrodes are of the shape of spring. Strong on the emitting frame work with the
help of hooks in both the ends.
The ash depositing on these electrode is rapped down by separate wrapping mechanism
happens at the bottom of the field. From these hoppers ash is evacuated by ash handling
system and dispose to the disposal area. The wrapping system is automatically controlled
with the help of the programmable metal controller, located in the ESP auxiliaries control
panels.
27. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
27
BOILER
A boiler (or steam generator) is a closed vessel in which water, under pressure is
converted into steam. It is one of the major components of a thermal power plant. A
boiler is always designed to absorb maximum amount of heat released in process of
combustion. This is transferred to the boiler by all the three modes of heat transfer i.e.
conduction, convection and radiation.
3.1. BOILERS ARE CLASSIFIED AS
3.1.1. FIRE TUBEBOILER
In this type the products of combustion pass through the tubes which are surrounded by
water. These are economical for low pressure only.
3.1.2. WATER TUBE BOILER
In this type of boiler water flows inside the tubes and hot gases flow outside the tubes.
These tubes are interconnected to common water channels and to steam outlet.
The water tube boilers have many advantages over the fire tube boilers
High evaporation capacity due to availability of large heating surface.
Better heat transfer to the mass of water.
Better efficiency of plant owing to rapid and uniform circulation of water in tubes.
Better overall control.
Easy removal of scale from inside the tubes.
In KSTPS, Natural circulation, tangentially fired, over hanged type, Water tube boilers
are used. Oil burners are provided between coal burners for initial startup and flame
28. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
stabilization. Firstly, light oil (diesel oil) is sprayed for initialization then heavy oil (high
speed diesel oil) is used for stabilization of flame. Pulverized coal is directly fed from
the coal mills to the burners at the four corners of the furnace through coal pipes with the
help of heated air coming from PA fan. Four nos. of ball mills of 34MT/hr. capacity each
have been installed for each boiler. The pressure inside boiler is -ive so as to minimized
the pollution and looses & to prevent the accidents outside the boiler.
For ensuring safe operation of boilers, furnace safe guard supervisory system (FSSS) of
combustion engineering USA designed has been installed. This equipment systematically
feed fuel to furnace as per load requirement. The UV flame scanners installed in each of
the four corners of the furnace, scan the flame conditions and in case of unsafe working
conditions trip the boiler and consequently the turbine. Turbine - boiler interlocks safe
guarding the boiler against possibility furnace explosion owing to flame failure.
28
3.2. FURNACE
Furnace is primary part of the boiler where the chemical energy available in the fuel is
converted into thermal energy by combustion. Furnace is designed for efficient and
complete combustion. Major factors that assist for efficient combustion are the
temperature inside the furnace and turbulence, which causes rapid mixing of fuel and air.
In modern boilers, water-cooled furnaces are used.
29. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
Fig. 3.1 Water Cooled Furnace
3.3. PULVERISED FUEL SYSTEM
The boiler fuel firing system is tangentially firing system in which the fuel is introduced
from wind nozzle located in the four corners inside the boiler.
The crushed coal from the coal crusher is transferred into the unit coalbunkers where the
coal is stored for feeding into pulverizing mill through rotary feed the rotary feeders feed
the coal to pulverize mill at a definite rate. Then coal burners are employed to fire the
pulverized coal along with primary air into furnace. These burners are placed in the
corners of the furnace and they send horizontal streams of air and fuel tangent to an
imaginary circle in the center of the furnace.
Fig. 3.2TangentialFiring
29
3.4. FUEL OIL SYSTEM
The functional requirement of the fuel burning system is to supply a controllable and
uninterrupted flammable furnace input of fuel and air and to continuously ignite and burn
30. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
the fuel as rapidly as it is introduced into the furnace. This system provides efficient
conversion of chemical energy of fuel into heat energy. The fuel burning system should
function such that fuel and air input is ignited continuously and immediately upon its
entry into furnace.
The Fuel air (secondary air) provided FD fan, surrounds the fuel nozzles. Since this air
provides covering for the fuel nozzles so it is called as mantle air. Dampers are provided
so that quantity of air can be modulated. Coal burners distribute the fuel and air evenly in
the furnace.
Ignition takes place when the flammable furnace input is heated above the ignition
temperature. No flammable mixture should be allowed to accumulate in the furnace.
Ignition energy is usually supplied in the form of heat. This ignition energy is provided
by oil guns and by igniters.
30
3.5. BOILER DRUM
The drum is a pressure vessel. Its function is to separate water and steam from mixture
(of steam & water) generated in the furnace walls. It provides water storage for
preventing the saturation of tubes. It also houses the equipment needed for purification of
steam. The steam purification primarily depends on the extent of moisture removal, since
solids in steam are carried by the moisture associated with it. The drum internals reduce
the dissolved solids content of the steam to below the acceptable limitdrum is made up of
two halves of carbon steel plates having thickness of 133 mm.
31. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
Fig. 3.3 Steam Drum Internals
The top half and bottom half are heated in a plate heating furnace at a very high
temperature and are pressured to form a semi cylindrical shape. The top and bottom semi
cylinders with hemispherical dished ends are fusion welded to form the boiler drum. The
drum is provided with stubs for welding all the connecting tubes i.e. down comer stubs,
riser tubes stubs and super heater outlet tube stubs.
Boiler drum is located at a height of 53m from ground. The drum is provided with
manholes and manhole covers. Manhole is used for facilitating the maintenance person to
go inside the drum for maintenance.
The drum form the part of boiler circulating system i.e. movement of fluid from the drum
to the combustion zone and back to boiler drum. Feed water is supplied to the drum from
the economizer through feed nozzles. Water from the drum goes to water walls through
six down comers.
31
Main parts of boiler drum are:
Feed pipe
Riser tube
Down comer
Baffle plate
Chemical dosing pipe
Turbo separation
Screen dryer
32. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
32
Drum level gauge
3.6. DRAFT SYSTEM
The combustion process in a furnace can take place only when it receives a steady flow
of air and has the combustion gases continuously removed. Theoretically balanced draft
means keeping furnace pressure equal to atmospheric pressure, but in practice the furnace
is kept slightly below atmospheric pressure. It ensures that there is no egress of air or hot
gas and ash into boiler house.
3.7. DRAUGHT FANS
A fan can be defined as volumetric machine which like pumps moves quantities of air or
gas from one place to another. In doing this it overcomes resistance to flow by supplying
the fluid with the energy necessary for contained motion. The following fans are used in
boiler house.
3.7.1. PRIMARYAIR FAN (P.A. FAN) OR EXHAUSTER FAN
Pulverized coal is directly fed from coal mills to the burners at the four corners of the
furnace through coal pipes with the help of heated air coming from PA fan. Secondly,
this fan also dries the coal. It usually sized for 1500 RPM due to high pressure.
3.7.2. FORCED DRAUGHT FAN (F.D. FAN)
The combustion process in the furnace can take place only when it receives a steady flow
of air. This air is supplied by FD fan. Thus FD fan takes air from atmosphere at ambient
temperature & so provides additional draught. Its speed varies from 600-1500 RPM.
SPECIFICATION OF FORCE
DRAUGHT FAN
33. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
3,6.6KV,700KW Rated.current-74A
RPM-1500 Discharge- 408 T/Hr
33
Fig. 3.4 Force Draught Fan
3.7.3. INDUCED DRAUGHT FAN (I.D. FAN)
The flue gases coming out of the boiler are passed to the ESP & then dust free gases are
discharged up by the chimney to the atmosphere through the ID fan.
SPECIFICATION OF ID FAN
3,6.6KV,1750KW
Rated.current-192.1A
Discharge- 720 T/Hr
RPM- 750
Fig. 3.5 Induced Draught Fan
3.7.4. IGNITER AIR FAN
It is used to provide necessary combustion air to igniter. Two fans are usually provided.
One will run and 2nd will remain as stand by. A control damper is provided on the
34. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
discharge which modulates to maintain a constant differential pressure across igniter
when any igniter is in service. Typical speed is 1460 RPM.
34
3.7.5. SCANNER AIR FAN
Used to provide necessary cooling air to the flame scanners. Two air fans are usually
provided. One will run and other will remain as stand by. When F.D. fans trip the scanner
air fan will draw air from atmosphere through emergency damper. Typical speed 3000
RPM.
3.8. ECONOMIZER
The flue gases coming out of the boiler carry lot of heat. An economizer extracts a part of
this heat from the flue gases and uses it for heating the feed water before it enters into the
steam drum. The use of economizer results in saving fuel consumption and higher boiler
efficiency but needs extra investment. In an economizer, a large number of small
diameter thin walled tubes are placed between two headers. Feed water enters the tubes
through the other. The flue gases flow outside the tubes.
Fig. 3.6 Economiser
35. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
35
3.9. AIR PREHEATERS
Air preheaters are employed to recover the heat from the flue gases leaving the
economiser and are used to heat the incoming air for combustion. This raises the
temperature of the furnace gases, improves combustion rates and efficiency and lowers
the stack (chimney) temperature, thus improving the overall efficiency of the boiler.
Cooling of flue gases by 20% raises the plant efficiency by 1%.
In KSTPS regenerative type of preheater is used. They use a cylindrical rotor made of
corrugated steel plate. The rotor is placed in a drum which is divided into two
compartments, i.e. air compartment (primary air coming from primary air fan and
secondary air for air coming from FD fan with +ive pressure) and flue gases (from
economizer with –ive pressure) compartments. To avoid leakage from one compartment
to other seals are provided.
The rotor is fixed on an electrical shaft rotating at a speed of 2 to 4 rpm. As the rotor
rotates the flue gases, are pass through alternatively gas and air zone. The rotor elements
are heated by flue gases in their zone and transfer the heat to air when they are in air
zone. The air temperature required for drying in the case of coal-fired boiler decided the
size of the air heaters.
36. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
Fig. 3.7 Air Preheater
36
3.10. SUPERHEATER
Superheated steam is that steam, which contains more heat than the saturated steam at the
same pressure i.e. it, has been heated above the temperature corresponding to its pressure.
This additional heat provides more energy to the turbine and thus the electrical power
output is more.
A super heater is a device which removes the last traces of moisture from the saturated
steam leaving the boiler tubes and also increases its temperature above the saturation
temperature.
The steam is superheated to the highest economical temperature not only to increase the
efficiency but also to have following advantages:
Reduction in requirement of steam quantity for a given output of energy owing to
its high internal energy reduces the turbine size.
Superheated steam being dry, turbine blades remain dry so the mechanical
resistance to the flow of steam over them is small resulting in high efficiency.
No corrosion and pitting at the turbine blades occur owing to dryness of steam.
3.11. REHEATER
Reheaters are provided to raise the temperature of the steam from which part of energy
has already been extracted by HP turbine. This is done so that the steam remains dry as
far as possible through the last stage of the turbine. A reheater can also be convection,
radiation or combination of both.
3.12. CIRCULATION SYSTEM
37. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
In natural circulation system, water delivered to steam generator from header, which are
at a temperature well below the saturation value corresponding to that pressure. After
header, it is delivered to economizer, which heated to above the saturation temperature.
From economizer the water enters the drum and thus joins the circulation system through
down covering water wall tubes. In water wall tubes a part of the water is converted to
steam due to boiler and the mixture flows back to the drum. In the drum, the steam is
separated out through the steam separators and passed to the super heater. After the super
heater when the steam temperature becomes high and pressure upto 150 Kg./cm3 steam is
allowed to enter the turbine to convert potential energy to kinetic energy.
37
3.13. SOOT BLOWER
The boiler tubes are cleaned with the help of steam by the process called soot blowing.
We are well known that a greater no. of tubes are presented inside the boiler. Slowly and
slowly the fine ash particles are collected on the tube surface and from a layer this is
called soot. Soot is a thermal insulating material.
There are mainly three types of soot blower are used in KSTPS:
Water wall soot blower
Super heater soot blower
Air pre heater soot blower
3.14. TECHNICAL SPECIFICATION OF BOILER
1. Type : Direct fired, natural circulation
balance draft water tube boiler.
38. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
2. No. of Units. : Two.
3. Make : BHEL.
4. Capacity : 375 tons per hour.
5. Steam Pressure : 139 Kg./Cm2
6. Efficiency : 86.6 %.
38
7. No. of fans in service
a) ID fans. : 2 Nos.
b) FD fans. : 2 Nos.
c) PA fans. : 2 Nos.
d) Seal Air fan. : 1 No.
e) Scanner Air fan. : 1 No.
f) Igniter fan. : 1 No.
8. Steam Temperature : 540oC.
9. No. of coal mills in : 3 Nos.service.
10. No. of soot blowers : 70 Nos.
3.15. FUEL
a) COAL:
Type : Slack Coal.
Quantity consumed : 3074 tons per day.
Type of handing : Conveyor.
Ash disposal : Wet system.
39. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
39
b) OIL:
Type : HSD and fuel oil.
Quantity : a) HSD – 5520 KL per year. *
b) Furnace Oil: 28800 KL per year.
No. of chimney / stack : 1 / 2.
Height of Chimney : 180 Meters.
Volume of flue Gas : 198 M3/ Sec.Air emitted.
Temp. Of flue gas : 140oC.
ESP : One for each unit.
3.16. GENERAL DESCRIPTION
Boilers are tangentially fired, balance draft, natural circulation, radiant type, and dry
bottom with direct fired pulverized coal from bowl mills. They are designed for burning
low grade coal with high ash content. Oil burners are located between coal burners for
flame stabilization. Pulverized coal is directly fed from the coal mills to the burners at
the four corners of the furnace through coal pipes. The pulverized fuel pipes from the
mills to the bunkers are provided with basalt lined bends to reduce erosion and to
improve the life of these pipes owing to poor grade of coal there is a high percentage of
mill rejects. The mill rejects are conveyed in a sluice way to an under-ground tank. From
this tank the mixture is taken to an overhead hydro-bin where water is decanted and the
mill reject are disposed of by trucking. ESP with collection efficiency of 99.8% have
been provided to reduce environmental pollution and to minimize induce draft fan wear.
A multi- flue reinforced concrete stack with two internal flues has been provided.
Two boiler feed pumps each of 100 % capacity are driven by AC motor through hyd.
coupling with scoop tube arrangement for regulating feed water pressure for each unit.
40. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
The air required for combustion is supplied bytwoforced draft fans.
Due to anticipated high abrasion of ID fans impellers. Three ID fans each of 60%
capacity have been provided one ID fan to serve as standby.
For ensuring safe operation of boilers, furnace safe guard supervisory system (FSSS) of
combustion engineering USA designed has been installed. This equipment systematically
feed fuel to furnace as per load requirement.
The UV flame scanners installed at two elevation in each of the four corners of the
furnace, scan the flame conditions and in case of unsafe working conditions but out fuel
and trip the boiler and consequently the turbine. Turbine – boiler interlocks safe
guarding the boiler against possibility furnace explosion owing to flame failure. Facilities
have been provided to simultaneously unload and transfer 10 light oil and 40 heavy oil
tankers to the designated tanks. Oil preheating arrangement is provided on the tanks
floors for the heavy oil tanks. Superheated steam temperature is controlled by
attemperation.
Re-heater steam temperature is primarily by tilting fuel burners through + 30o and further
control if necessary is done by attemperation.
40
STEAM TURBINE
4.1. INTRODUCTION
Turbine is a machine in which a shaft is rotated steadily by impact or reaction of current
or stream of working substance (steam, air, water, gases etc.) upon blades of a wheel. It
converts the potential or kinetic energy of the working substance into mechanical power
by virtue of dynamic action of working substance. When the working substance is steam
it is called the steam turbine.
41. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
Fig. 4.1 Steam Turbine
4.2. PRINCIPAL OF OPERATION OF STEAM TURBINE
Working of the steam turbine depends wholly upon the dynamic action of Steam. The
steam is caused to fall in pressure in a passage of nozzle: doe to this fall in pressure a
certain amount of heat energy is converted into mechanical kinetic energy and the steam
is set moving with a greater velocity. The rapidly moving particles of steam, enter the
moving part of the turbine and here suffer a change in direction of motion which gives
rose to change of momentum and therefore to a force. This constitutes the driving force
of the machine. The processor of expansion and direction changing may occur once or a
number of times in succession and may be carried out with difference of detail. The
passage of steam through moving part of the commonly called the blade, may take place
in such a manner that the pressure at the outlet side of the blade is equal to that at the inlet
inside. Such a turbine is broadly termed as impulse turbine. On the other hand the
pressure of the steam at outlet from the moving blade may be less than that at the inlet
side of the blades; the drop in pressure suffered by the steam during its flow through the
moving causes a further generation of kinetic energy within the blades and adds to the
propelling force which is applied to the turbine rotor. Such a turbine is broadly termed as
impulse reaction turbine. The majority of the steam turbine have, therefore two important
41
42. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
elements, or Sets of such elements. These are (1) the nozzle in which the system expands
from high pressure end a state of comparative rest to a lower pressure end a status of
comparatively rapid motion.
(2) The blade or deflector, in which the steam particles changes its directions and hence
its momentum changes. The blades are attach to the rotating elements are attached to the
stationary part of the turbine which is usually termed the stator, casing or cylinder.
Although the fundamental principles on which all steam turbine operate the same, yet the
methods where by these principles carried into effect very end as a result, certain types of
turbine have come into existence.
42
1. Simple impulse steam turbine.
2. The pressure compounded impulse turbine.
3. Simple velocity compounded impulse turbine.
4. Pressure-velocity compounded turbine.
5. Pure reaction turbine.
6. Impulse reaction turbine.
4.3. TECHNICAL DATA OF TURBINES
The main technical data of 110 MW turbines is given below:
Rated output : 110 MW.
Economic output : 95 MW.
Rated speed3000 rpm
43. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
Direction of rotation viewing from : Clockwise
43
the front bearing pedestal
Rated steam pressure before : 130 ata
Stop valve.
Maximum steam pressure before : 146 ata
Stop valve
Rated temperature of steam before : 535oC
the stop valve
Maximum temperature of steam before : 545oC
the stop valve
Rated pressure of steam : 31.6 ata
MP Casing
Rated pressure of steam before : 35 ata
MP Casing:
Rated Temp. of steam before : 535oC.
MP Casing.
Maximum Temp. Of steam before : 545oC.
MP Casing.
Informative heat flow at the economic o/p : 2135 K cal/Kwh
Informative heat rate at the rated output : 2152.5KCal/Kwh.
HP Cylinder : 2 row carts wheel
+ 8moving wheels
44. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
MP Cylinder : 12 moving wheels
LP cylinder : 4 moving wheels
Quantity of oil for first filling1800ltr.for the turbine
Single flow HP turbine with 25 reaction stages.
Double flow IP turbine with 20 reaction stages per flow.
Double flow LP turbine with 8 reaction stages per flow.
2 main stop & control valves &2 steam check valve in CRH.
2 reheat stop & control valves &2 bypass stop & control valve.
At KSTPS there are 2x110 MW turbines installed for unit 1 & 2 and 210 MW turbines
installed for units 3, 4 & 5 & one 195 MW turbine installed for unit 6 &7 (which one is
under final stage of construction & generation of power is expected in Sept, 2008).
4.4. DESCRIPTION OF STEAM TURBINES
44
4.4.1. STEAM FLOW
210 MW steam turbine is a tandem compound machine with HP, IP & LP parts. The HP
part is single flow cylinder and HP & LP parts are double flow cylinders. The individual
turbine rotors and generator rotor are rigidly coupled. The HP cylinder has a throttle
control. Main steam is admitted before blending by two combined main stop and control
valves. The HP turbine exhaust (CRH) leading to reheated have tow swing check valves
that prevent back flow of hot steam from reheated, into HP turbine. The steam coming
from reheated called HRH is passed to turbine via two combined stop and control valves.
The IP turbine exhausts directly goes to LP turbine by cross ground pipes.
4.4.2. HP TURBINE
45. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
The HP casing is a barrel type casing without axial joint. Because of its rotation
symmetry the barrel type casing remain constant in shape and leak proof during quick
change in temperature. The inner casing too is cylinder in shape as horizontal joint flange
are relieved by higher pressure arising outside and this can kept small. Due to this reason
barrel type casing are especially suitable for quick start up and loading. The HP turbine
consists of 25 reaction stages. The moving and stationary blades are inserted into
appropriately shapes into inner casing and the shaft to reduce leakage losses at blade tips.
45
4.4.3. IP TURBINE
The IP part of turbine is of double flow construction. The casing of IP turbine is split
horizontally and is of double shell construction. The double flow inner casing is
supported kinematically in the outer casing. The steam from HP turbine after reheating
enters the inner casing from above and below through two inlet nozzles. The centre
flows compensates the axial thrust and prevent steam inlet temperature affecting brackets,
bearing etc. The arrangements of inner casing confines high steam inlet condition to
admission branch of casing, while the joints of outer casing is subjected only to lower
pressure and temperature at the exhaust of inner casing. The pressure in outer casing
relieves the joint of inner casing so that this joint is to be sealed only against resulting
differential pressure.
The IP turbine consists of 20 reaction stages per flow. The moving and stationary blades
are inserted in appropriately shaped grooves in shaft and inner casing.
4.4.4. LP TURBINE
The casing of double flow type LP turbine is of three shell design. The shells are axially
split and have rigidly welded construction. The outer casing consists of the front and rear
walls, the lateral longitudinal support bearing and upper part.
46. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
The outer casing is supported by the ends of longitudinal beams on the base plates of
foundation. The double flow inner casing consists of outer shell and inner shell. The inner
shell is attached to outer shell with provision of free thermal movement.
Steam admitted to LP turbine from IP turbine flows into the inner casing from both sides
through steam inlet nozzles.
4.5. ELECTRICITY GENERATOR
Thermal power station burns the fuel and use the resultant heat to raise the steam which
drives the turbo-generator. The fuel may be “Fossil” (Coal, Oil and Natural Gas)
whichever fuel is used the object is same to convert the heat into mechanical energy to
electrical energy by rotating a magnet inside the set of winding. In a coal fired thermal
power station other raw materials are air and water. The coal is brought to station by train
or other means travels from the coal handling system.
i) By conveyer belts to coal bunkers from where it is fed to pulverizing mills.
ii) Mills grind it fine as face powder.
iii) Then this powdered coal mixed with preheated air is blow into boiler by a Fan
known as primary air fan (PA fan).
iv) When it burns more like a gas as solid in conventional domestic or
industrial grate with additional amount of air called secondary air supplied by
“Forced Draft Fan”. As the coal has been grinded so resultant ash is also as
fine as powder. Some of its fine particles blinds together to form a lump
which falls into the ash pit at the bottom of furnace.
v) The water quenched ash from the bottom of furnace is carried out boiler to pit
46
for subsequent disposal.
vi) Now after passing through ESP few gases are discharged up to chimney
47. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
Meanwhile the heat reloaded from the coal has been absorbed by kilometers a long tube
which lies in boiler walls inside the tubes “Boiler Feed Water” which is transferred into
turbine blades and makes them rotate. To the end of the turbine rotor of generator is
coupled, so that when turbine rotates the rotor turns with it. The rotor is housed inside the
stator having coil of copper bars in which electric is produced through the movement of
magnetic field created by rotor The electricity passes from the stator winding to the
transformer which steps up the voltage so that it can be transmitted effectively over the
power line of grid.
The steam which has given up its heat energy in changed back into a condenser so that it
is ready for reuse. The cold water continuously pumped in condenser. The steam passing
around the tubes loose heat and rapidly change into water. But these two types of water
(boiler feed water and cooling water) must never mix together. The cooling water is
drawn from the river but the Boiler Feed Water must be pure than potable water (DM
Water).
47
4.6. TURBO GENERATOR
4.6.1. THEORY
TURBO GENERATOR manufactured by B.H.E.L. and incorporated with most modern
design concepts and constructional features, which ensures reliability, with constructional
& operational economy. The generator stator is a tight construction, supporting &
enclosing the stator windings, core and hydrogen coolers. Cooling medium hydrogen is
contained within frame & circulated by fans mounted at either ends of rotor. The
generator is driven by directly coupled steam turbine at a speed of 3000 r.p.m. the
Generator is designed for continuous operation at the rated output. Temperature
detectors and other devices installed or connected within then machine, permit the
windings, teeth core & hydrogen temperature, pressure & purity in machine under the
conditions. The source of excitation of rotor windings is thyristor controlled D.C. supply.
48. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
The auxiliary equipment’s supplied with the machine suppresses and enables the control
of hydrogen pressure and purity, shaft sealing lubricating oils. There is a provision for
cooling water in order to maintain a constant temperature of coolant (hydrogen) which
controls the temperature of windings
48
4.6.2. MAIN PARTS OF GENERATOR
(a) STATOR FRAME
The stator frame of welded steel frame construction, which gives sufficient & necessary
rigidity to minimize the vibrations and to withstand the thermal gas pressure. Heavy end
shields enclose the ends of frame and form mounting of generator bearings and radial
shaft seals. Ribs subdivide the frame and axial members to form duct from which the
cooling gas to & fro radial ducts in the core and is re-circulated through internally
mounted coolers. All the gas ducts are designed so as to secure the balanced flow of
hydrogen to all parts of the core. The stator constructed in a single piece houses the core
and windings. The horizontally mounted water cooled gas coolers being so arranged that
it may be cleaned on the water side without opening the machine to atmosphere. All
welded joints exposed to hydrogen are specially made to prevent leakage. The complete
frame is subjected to hydraulic test at a pressure of 7 ATA.
49. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
Fig. 4.2 Stator Assembly
49
(b) STATOR CORE
It is built up of special sheet laminations and whose assembly is supported by a special
guide bass. The method of construction ensures that the core is firmly supported at a large
number of points on its periphery. The laminations of high quality silicon steel which
combines high permeability with low hysterias and eddy current losses. After stamping
each lamination is varnished on both sides with two coats. The segment of insulating
material is inserted at frequent intervals to provide additional insulation. The laminations
are stamped out with accurately fine combination of ties. Laminations are assembled on
guide bass of group separated by radial ducts to provide ventilation passage. The
ventilation ducts are disposed so as to distribute the gas evenly over the core & in
particularly to give adequate supports to the teeth. At frequent intervals during stacking
the assembled laminations are passed together in powerful hydraulic press to ensure tight
core which is finally kept between heavy clamping plates which are non-magnetic steel.
Use of non-magnetic steel reduces considerably by heating of end iron clamping. The
50. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
footed region of the core is provided by pressing figures of non-magnetic steel, which are
welded to the inner periphery of the clamping plates. In order to reduce the losses in the
ends packets special dampers are provided at either ends of core. Mostly dampers are
provided to prevent hunting in ac machines.
50
(c) STATOR BARS
Stator bars are manufactured as half bars. Each stator half coil is composed of double
glass cover and bars of copper transposed in straight portion of “Robill Method” so that
each strip occupies every radial portion in the bar. For an equal length along the bar.
They are made in strips to reduce skin effect. The winding overhead is in volute shape.
The overhung portion of the bar is divided into four quadrants & insulated. The
arrangement reduces additional losses due to damping currents which otherwise be
present due to self-induced non-uniform flux distribution in the coil slots. The main
distribution for the bar consists of resin rich mica loosed thermosetting epoxy. This has
excellent mechanical and electrical properties & does not require any impregnation. Its
moisture absorbing tendency is very low and behavior of mica is for superior than any
other conventional tape insulation system. Semi-conductor coating is also applied to a
part of overhung with a straight overlap of conductive coil in the sides to reduce eddy
currents to minimum. Conductor material is electrolytic copper connections brazed with
free coating silver alloy to obtain joints, which are both electrically & mechanically
sound.
(d) STATOR WINDINGS
Stator windings are double star layers, lap wound, three phase, and short pitch type. The
top & bottom are brazed and insulated at either end to form turns. Several such turns
form a phase. Phases are connected to form a double star winding. The arrangement of
complete stator winding electrical circuit is viewed from turbine end of generator & rotor
windings. Slot numbering is clockwise from turbine end. A thick line identifies the top
bar in slot No.1. End windings will be sealed against movement of short circuit by both
axial & peripheral bracing. The later consists of hardened glass laminated blocks inserted
51. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
between adjacent coil sides in coil overhangs, so that with the coils, they form a
continuous rigid ring. Glass cord or top is used lashing the packing of blocks. The
complete assembly is secured by high tensile brass blots. The winding is designed to
withstand short circuit stresses. The exposed portion of windings is finally coated.
Insulation of individual bars & stator windings at various stresses is tested with applied
high voltages of AC of Hz.
51
(e) TERMINAL BUSHINGS
Six output leads (3 long, 3 short) have been brought out of the coming on the exciter side.
External connections are to be made to the three shorter terminals, which are phase
terminals. The large terminals are of neutral & current transformer is inserted. The
conductor of Generator terminal bushing having hollow copper tubes with Copper brazed
at the ends to avoid leakage of hydrogen. Hollow portions enable bushings to be
hydrogen cooled. Ends of bushings are Silver-plated: middle portion of the bushing is
adequately insulated & has a circular flange for bolting the stator casing. Gaskets are
provided between the Flange of terminal bushings and castings to make it absolutely gas
tight.
(f) BEARINGS
Generator bearings have electrical seats of consists of steel bodies with removable steel
pads. The bearings are formed for forced lubrication of oil at a pressure of 2-3 ATM/
from the same pump that supplies oils to the turbine, bearings & governing gears. There
is a provision to ensure & measure the rotor bearing temperature by inserting a resistance
thermometer in the oil pockets.
(g) VENTILATION SYSTEM
The machine is designed with ventilation system having 2 atm rated hydrogen pressure.
Two axial fans mounted on either side of the rotor to ensure circulation of hydrogen. The
stator is designed for radial ventilation by stem. The end stator core packets & core
clamping & plates are intensively cooled by Hydrogen through special ventilation
52. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
system. Design of special ventilation is so as to ensure almost uniform temperature of
rotor windings and stator core. Rated load operating temperature is well within the limits
corresponding to the Class B operation. Embedded Resistance Temperature Detectors do
continuous monitoring of Hydrogen temperature at active parts of Generator.
52
4.7. HYDROGEN COOLERS
Three Hydrogen Coolers each comprising of two individual units are mounted inside the
stator frame, the inlet and outlet of cooling water from both of machine i.e. from non-driving
side as well as turbine side. The Clearing of the individual cooler element can be
carried out from both ends of the Generator even during operation. The assembly of
individual cooler elements in stator frame is however carried out only from the non-driving
side.
4.8. ROTOR
Rotor shaft consists of single piece alloy steel forging of high mechanical and magnetic
properties performance test includes:
1. Tensile test on specimen piece.
2. Surface examination.
3. Sulfur prist tests.
4. Magnetic crack detection.
5. Visual examination of bore.
6. Ultrasonic examination.
Slots are milled on the rotor gorging to receive the rotor winding. Transverse slots
machined in the pole faces of the rotor to equalize the moment of inertia in direct and
quadrilateral axis of rotor with a view minimizing the double frequency.
53. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
53
4.8.1. VIBRATION OF ROTOR
The fully brazed rotor is dynamically balanced and subject to 120 % over speed test at the
work balancing tunnel so as to ensure reliable operation.
Fig. 4.3. Rotor of Generator
4.8.2. ROTOR WINDINGS
Rotor winding is of direct coil type and consists of parallel strips of very high
conductivity Silver Bearing Copper, bent on edge to form coil. The coils are placed in
impregnated glass, laminated short shells; using glass strips inter turn insulation and will
be brazed at the end to form continuous winding. The complete winging will be packed
at high temperature and pressed to size by heavy steel damping rings. When the windings
have cooled, heavy dove tail wedges of non-magnetic materials will seal the insulation at
the top of slot portion. The cooling medium hydrogen gas will be brought in direct
contact with copper by means of radial slots in embedded portion. Treated glass spacers
inserted between the coils and solid ring prevent lateral movement of coil overhang. The
formation and description of glass spacer is such as to leave ample space for ventilation.
4.8.3. BEARINGS
The bearings are self-aligned & consist of slip steel shells linked with special bearing
metal having very low coefficient of friction. The bore is machined on an elliptical shape
54. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
so as to increase the mechanical stability of the rotor. The bearing are pressure lubricated
from the turbine oil supply. Special precautions are taken to prevent oil & oil vapor from
shaft seals and bearing along the shaft. The circulation of shaft current is liable to
damage. The bearing surface is protected by insulation so placed that the bearings, seals
& necessary pipes are inclined from the frame.
54
4.8.4. SLIP RINGS
The slip rings are made of forged steel. They are located at either side of Generator Shaft.
The slip ring towards the exciter side is given +ve polarity initially. They have helical
grooves and skewed holes in the body for cooling purpose by air. Calibrated mica is first
built up to required thickness on the shaft where slip rings are located. The slip rings are
insulated from the rotor shaft. Excitation current is supplied to the rotor winding.
Through the slip rings, which are connected to the winding.
On one end and to the slip ring on the other end with insulated (terminal) studs passing
‘though’ the radial holes in the rotor shaft. The terminal studs at both the ends of
excitation leads are fitted gas cat seals to prevent leakage.
4.8.5. BUSH GEAR ASSEMBLY
Generator bushes are made from the various compositions of natural graphite and binding
material. They have a low coefficient of friction and are self-lubricating. The brushes are
provided with a double flexible copper or pigtails. A helical spring is mounted rapidly
over each bush so that pressure is applied on the centerline of bush. A metal cap is
riveted to the brass bead and is provided with a hole to maintain the position of the spring
plug. Several brush holders, each carrying on brush in radial position are fixed to silver
plated copper studs mounted on the collecting arm concentric with each slip rings. The
collecting arm is made out of a copper strip.
4.8.6. DRYING OF WINDING
55. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
Generator stator bars are insulated with mica insulation, which is homogeneous in nature
and practically impervious to moisture, and reduce time required to draught. The
insulation resistance of the stator phase winging against earth and with reference to other
phases under hot condition shall not be less than the value obtained automatically.
55
Rin = μ/(s/100+1000) m 52
U = rated winding Voltage under test.
Rin = insulation resistance under hot conditions Rated o/p of turbo generator.
The insulation resistance of entire excitation system circuit, in hot condition must not fall
below 0.5 m 52. The insulation resistance in calculated as per the formula
Rin = Rv (U1 +U2) / (U-1)
Rin = Insulation resistance of exciter
Rv = Internal resistance of voltmeter
U1 = Voltage measured btw, Slip ring & shaft/ earth (volts).
4.9. TECHNICAL DATA
(A) GENERATOR (110 MW)
Type : t.g.p. 2,34,602
Continuous apparent power : 1,37,500 KVA.
Active power : 7,10,000 KW.
Power factor : 0.8 (lagging).
Rated voltage : 1000 + 5% rated.
Current : 7,220 A
Critical speed : 3000 r.p.m. at
Frequency : 50 Hz.
Phase connection : double star
56. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
No. of terminals : 6.
Main diameter of slip rings : 420 mm.
Voltage regulation : 39%.
Reactance : Informative.
56
(B) HYDROGEN COOLER
Nos. of elements : 6
Cooling medium : Water, H2at 2 atm
Discharge losses : 1500 KW.
Quantity of H2 : 30 M3/ sec.
Quantity of water Temp : 34oC,
Cooling cold H2 Temp : 400C
How resistance (H2 side) : 12 mm. of peak.
Inherent voltage regulation : 39%
Short circuit ratio : 0.5%.
Type : HC-WLL-BS/C46.
4.10. COOLING SYSTEM
4.10.1. GENERAL
In KSTPS hydrogen cooling system is employed for generator cooling. Hydrogen is used
for cooling medium primarily because of its superior cooling properties & low density.
Thermal conductivity of hydrogen is 7.3 times of air. It also has higher transfer co-efficient.
Its ability to transfer heat through forced convection is about 75% better than
air. Density of hydrogen is approx. 7/14 of the air at a given temperature and pressure.
57. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
This reduces the wind age losses in high speed machine like turbo-generator. Increasing
the hydrogen pressure the machine improves its capacity to absorb & remote heat.
Relative cooling properties of air and hydrogen are given below:
1) Elimination of fire risk because hydrogen will not support combustion.
2) Corona discharge is not harmful to insula. Since oxidation is not possible.
3) Smooth operation of machine in view of vertical elimination of wind age noise &
the use of heavy gas light enclosure and dirty probe casing.
At pressure 0.035 atm. of hydrogen heat carrying capacity is 1.But at 2atm. of hydrogen
heat carrying capacity is 1.95 to overcome the serious possibility of hydrogen explosion
within the machine and to ensure the safety of operation purity of hydrogen on the
generator. Casing must be maintained as high as possible. The purity of hydrogen should
be 98% above but should not be less than 98%. In case of hydrogen purity drops below
98% an alarm is provided.
57
4.10.2. HYDROGEN DRYERS
Two nos. of dryers are provided to absorb the hydrogen in the Generator. Moisture in this
gas is absorbed by silica gel in the dryer as the absorbed gas passes through it. The
natural of silica gel is indicated by change in its color from blue to pink. The silica gel is
reactivated by heating. By suitable change over from drier to the other on uninterrupted
drying achieve.
58. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
Fig. 4.4 Hydrogen Cooled Alternato
58
EXCITATION SYSTEM
The electric power Generators requires direct current excited magnets for its field system.
The excitation system must be reliable, stable in operation and must response quickly to
excitation current requirements. When excitation system response is controlled by fast
acting regulators, it is chiefly dependent on exciter. Exciter supply is given from
transformer and then rectified.
5.1. FUNCTION OF EXCITATION SYSTEM
The main function of excitation system is to supply required excitation current at rated
load condition of turbo Generator. It should be able to adjust the field current of the
Generator, either by normal controller automatic control so that for all operation &
between no load and rated load. The terminal voltage of the system machine is
maintained at its value. The excitation system makes contribution improving power
system stability steady state condition. The excitation system that are commonly termed
quick response system and have following principal feature:- Exciter of quick response &
high voltage of not less than 1.4 times the rated filed voltage and nominal exciter
response of minimum 0.5.
59. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
5.2. TYPE OF EXCITATION SYSTEM
There have been many developments in excitation system design. There has been
continuing reach among the design and the use alike from improving the excitation
system performance. The ultimate is to achieve stability; accuracy etc. the modern
excitation system adopted presently on BHEL makes turbo-generator I. Conventional DC
excitation system Brushes excitation system.
5.3. STATIC EXCITATION SYSTEM
In KSTPS static excitation system is provided it mainly consists of the following:
59
1) Rectifier transformer.
2)
2) Nos. of thyristor converters.
3) An automatic voltage regulator (AVR).
4) Field suppression equipment.
5) Field flashing equipment.
5.4. GENERAL ARRANGEMENT
In the excitation system the power required for excitation of Generation are tapped from
11 KV bus ducts through a step down rectifier transformer. After rectification in
thermistor, converter, the DC power is fed to the Generator field winding through a field
breaker. The AVR control the o/p from thyristor converter by adjusting the firing angle
depending upon Generator voltages. The field flashing system facilitates initial built up
of the Generator voltage from the static AC or DC supply.
5.4.1. RECTIFIER TRANSFORMER
60. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
This transformer steps down the bus voltage 11 KV to 640 V and has a rating of 1360
KVA. It is dry type, it is however provided with current relays and two temperature
sensors.
60
5.4.2. A THYRISTOR CONVERTOR
The thyristor panel and are intended for controlled rectification of AC Input power. 6.
Thyristor converter are connected in parallel each rates for continuous current o/p of 20
% of the rated capacity i.e. 20 % reserve. Each thyristor converter consists of 6 thyristor
connected in 3-3, full wave, 6-pulse Bridge from and they are cooled by fans provided
with a fuse for protection against short circuit.
5.4.3. AUTOMATIC VOLTAGE CONTROLS
The AVR is transistorized thyristor controlled equipment with very fast response. The
AVR is also having provision of stator and rotor currents limits and load angle limits for
optimum utilization of lagging and leading reactive capacities of generator.
5.4.4. FIELD SUPRESSION EQUIPMENT
The field equipment consists of a field breaker with discharge resistors. The field
breakers have 4 main breaking contacts and two discharge contacts, which close before
main contact break.
(a) A very fast response.
(b) Extremely reliable in view of static components.
(c) Low maintenance cost.
(d) High efficiency.
(e) Fast field suppression through field and discharge resistance as well as through
Thyristor Bridge, feeding the Generator field.
5.5. OPERATION
61. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
After bringing the speed to operation speed say 3000 r.p.m., the voltage is slowly built up
with the help of excitation system. This action is taken for synchronizing the Generator.
61
5.5.1. SYNCHRONIZING
For synchronizing the Generator to the grid system 5 condition of equality have to be
satisfied. These are (I) Voltage (II) Frequency (III) Phase displacement (IV) Phase
sequence (V) Wave form. Wave form and phase sequence of the Generator are
determined at the design of each connection SYNCHRONIZING of the generator.
5.6. WATER TREATMENT PLANT
The principle problem in high pressure boiler is to control corrosion and steam quality.
Internal corrosion costs power station corers of rupees in repair without strict control
impurities in steam also form deposit over turbine blades and nozzles. The impurities
present in water are as follows:
1) Un-dissolved and suspended solid materials.
2) Dissolved slats and minerals.
3) Dissolved gases
4) Other minerals (oil, acid etc.).
5) a) Turbidity & Sediment.
b) Silica.
c) Micro Biological.
d) Sodium & Potassium Salt.
e) Dissolved Sales Minerals.
6) a) O2gas.
b) CO2 gas.
62. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
62
5.6.1. D.M. PLANT
In this plant process water is fed from all these dissolved salts. Equipment for
demineralization cum softening plant is supplied and erected by M/s. Wanson (India) Ld.,
Pune. This plant consists of two streams each stream with activated carbon filter, weak
acid, cation exchanger and mixed bed exchanger. The filter water to DM plant through
250 dia. header from where a heater top off has been taken to softening plant. Two
filtered water booster pumps are provided on filtered water line for meeting the pressure
requirement in DM Plant.
Sodium Sulphate solution of required strength is dosed into different filtered water by
mean of dosing pump to neutralize chlorine prior to activated carbon filter. When water
passed an activated carbon filter will remove residual chlorine from water. Provision is
made for back washing the activated carbon filter. When pressure drop across filter
exceeds a prescribed limit from the activated carbon filter provides acid cation unit. The
deception water the weak base anion exchanger unit water then enters de-gasified unit
where free CO2 is scrubbed out of water by upward counter flow of low pr. air flow
through degasified lower and degassed water is pumped to strong base exchanger (anion
exchanger).
Arrangement for dosing ammonia solution into de-mineralized water after mixed bed
unit has been provided p+1 correction before water is taken in de-condensate transfer
pump the DM water to unit condenser as make up.
5.6.2. C.W. PLANT
Circulating water pump house has pumps for condensing the steam for condenser. Five
pumps are used for condensing Unit No.1 & 2 and after condensing this water is
discharged back into the river. Each pump has capacity of 8275 M3/Hr, and develop
pressure about 1.94 Kg./Cm2.Three seal water pump are used for sealing circulating
water pump shaft at pr. 4.5 kg./cm2.
63. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
Two pump for unit 1 & 2 with one standby is used for supplying raw water to chlorified
chemical dosing is tone between and chlorified water is taken through main line. From
main line water passes through filter bed to filter the water. Chlorified water is pumped to
42 m elevation by two pumps of capacity 270 M3/Inch at discharge pressure of 6.9
Kg./Cm2. At 42 M elevation the water is stored in tank and used for cooling the oil
coolers and returned back to river. Oil coolers are situated on ground and there is no. of
tress for each unit.
63
5.6.3. B.C.W. PUMP HOUSE
Filter water after demineralization is used for bearing cooling from BCW pump house
after passing through strainer and heat exchanger it enters at 30-32oC and leave
exchanger at 38oC. The raw water used in ash handling plant and remaining quantity is
stored in sumps of BCW Pump House. From here the water is pumped to CW Pump by
TWS (Traveling water screens) pumps are run by motors of 90 KW and has a capacity of
240 Cum/hr/pump at pressure of 5 kg/cm2.
BCW here stand for water used for cooling oil used for cooling the bearing. In CW pump
house water is discharged from nozzle and impinged for traveling water screens for
cleaning it.
TRANSFORMER
6.1. INTRODUCTION
Transformer is a static device which is used to change the voltage level keeping the
power and frequency same. In the plant transformer is one of the most important
equipment. In the whole plant, there are about 83 transformer installed at various places
to operate the auxiliaries.
Main transformers, which are necessary:
64. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
64
1. To step up the generated voltage.
2. To supply power to the auxiliaries from the generator.
3. To start the plant by taking the supply from the grid.
These are installed in a transformer yard. It is located in between the main plant and the
switchyard. The main transformers installed in the transformer yard are:
1. GENERATOR TRANSFORMER (GT – A)
It steps up the voltage from 16.5 KV to 220 KV. It connects the plant with the 220 KV
switchyard.
2. GENERATOR TRANSFORMER (GT – B)
It steps up the voltage from 16.5 KV to 400 KV. It connects the plant with the 400 KV
switchyard.
3. STATION TRANSFORMER (ST)
It is a step down transformer with 50 MVA capacities. It is used to step down 220 KV
from the grid to 6.9 KV.
4. UNIT AUXILIARY TRANSFORMER (UAT)
It is a step down transformer with 20 MVA capacities. It steps down the voltage from
16.5 KV to 6.9 KV.
5. STATION SERVICE TRANSFORMER (SST)
It is a step down transformer with 2MVA capacity. It is used to step down from 6.6 KV
to 0.4333 KV.
6. UNIT SERVICE TRANSFORMER (UST)
It is a step down transformer with 2 MVA capacities. It is used to step down from 6.6 kV
to 0.4333 KV.
65. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
6.2. GENERATOR TRANSFORMER
Type of cooling ONAN ONAF OFAF
65
Rating HV (in MVA)
Rating LV (in MVA)
160
160
240
240
315
315
Line Current HV 219.9 329.9 433.0
Line Current LV 5598.5 8397.8 11022
Temperature rise in oil (C) 45 45 45
Temperature rise in wdg (C) 50 50 50
No load voltage HV (KV) - 420KV
No Load voltage LV (KV) - 16.5 KV
Connection symbol – Ynd11
Oil - 65300 Liters
There are 5 generator transformers in the plant, one for each unit. The output from the
generator is fed to the generator transformer, which step up the voltage from 16.5 KV to
400 KV and supplies power to grid. Generator transformer winding connected in
stardelta with a phase displacement of 30 degrees. Three – phase supply from the
generator is connected to the low voltage side bushings and the output is taken from the
opposite side. Neutral point on the H.V. side is provided at the side of the tank. Neutral is
solidly grounded. In case neutral is solidly connected to the earth a very small current
flowing through the neutral causes the tripling of the transformer. So in this case more
care is to be taken.
66. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
66
6.3. STATION TRANSFORMER
When the unit is to be started, power supplied to the auxiliaries is taken from the station
transformer. The rating of the station transformer is 50 MVA. It takes power from the
grid at 220 kV and steps it down to 6.6 kV. At the time of starting all the auxiliaries are
supplied from the station transformer. When the generator is synchronized and starts
producing power, about 80% of the load is shifted on to the unit auxiliary transformer.
The load that requires uninterrupted supply is left connected on the station transformer.
There are 5 S.T’s in the plant, one for each stage.
Type of cooling ONAN ONAF
MVA rating
H.V.
L.V.
40
26
50
31.05
Current (line)
H.V.
L.V.
105
3351
131
4189
Voltage (line):-
H.V. L.V.
220 Kv 6.9 Kv
67. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
6.4. UNIT AUXILIARY TRANSFORMER
Each unit has two unit auxiliary transformers. When the unit starts generating electricity
these transformers are energized and then supplies power to the auxiliaries. Before
starting of the unit, UAT bus is connected to the station bus. Auxiliaries of one unit take
about 20MW of power. UAT is connected between the generator and the GT. A tapping
is taken from the power coming from the generator to the GT. UAT relieves GT from
extra load of about 20 MW which is to be supplied to the auxiliaries via GT and ST thus
increasing the efficiency. It is a step down transformer, which steps down the voltage
from 16.5 kV to 6.9kV. The rating of UAT is 20 MVA. UAT bus supplies only those
auxiliaries, which are not necessary to be energized in case of sudden tripping of
generator.
6.5. UNIT STATIC TRANSFORMER
It is a step down transformer, which is connected to the station bus. It steps down the
voltage from 6.6 kV to 0.433 kV it is used to supply the low voltage auxiliaries.
6.6. UNIT SERVICE TRANSFORMER
It is also a 66-kV/ 415 V transformers which is used to supply the auxiliaries connected
to the unit secondary switchgear bus.
67
6.7. SWITCH YARD
6.7.1. 220 KV SYSTEM
Two 220 KV bus bars have been provided in switch yard and are inter-connected through
a bus coupler. Each of the two 110 MW generator is connected to this system through a
step up of 125 MVA 240/ 11 KV yard generator transformer. There are two step down
transformer each feeding 6.6 KV system (Station Switchyard) viz. BS-IS & SB-IB. Each
68. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
station transformer has two windings one secondary side and is rated for 50/25/25 mva,
270/7/7.2 kva four feeders take off from 220 switch yard, two to SKATPURA GSS and
other to HEERAPURA, Jaipur GSS. Each of four feeders are provided with bypass
isolators which is connected across line breaker and breaker isolator. By closing bus
coupler between 220 KV buses and putting line feeders whose breaker required
maintenance of any one bus through by pass isolators and all other line feeders whose
breaker is by passed is then transformed to bus coupler breaker. A brief description of
equipments of 220 KV systems is as follows.
68
6.8. CIRCUIT BREAKERS
Each of generator transformer, station transformer, line feeder and bus coupler is
provided with minimum oil circuit breaker of BHEL make. It is rated for 245 KW, 2500
A and 13400 MVA circuit breaker is used to break the circuit either in load condition or
in no load condition.
6.9. ISOLATOR
All the isolators are provided in 220KV switchyard and are motor operated. Triple pole
double breaker type and power switch yard L&T make these and are rates for 245 KV
and 1250 A. The four isolators are provided with earth switch.
6.10. CURRENT TRANSFORMER
All the 220 KV current transformers are provided for measuring and protection. They are
BHEL make, single phase, oil filled nitrogen sealed outdoor type. All the E.T.S. is multi-cored
with each core having specification upon duty it is to perform. Feeder circuits have
5 cores.
1) Bus bar protection core I 1250/250/IA.
69. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
2) Distance protection core II 600-300/IA.
3) O/C and E/F protection core 600-300 /IA.
4) For metering and measuring 600-300/ IA.
6.11. POTENTIAL TRANSFORMER
Each of 220 KV buses is provided with three P.T.’S are core for each phase of BHEL
make. There are single phase, oil filled outdoor. N2sealed, elicitor magnetic type P.T. has
two secondary windings on secondary side and selected for 220/53 KV, 10/53 KV.
69
6.12. LIGHTENING ARRESTOR
For protection against lightening each of line feeders, generator transformer, station
transformer has been provided with three L.A. (one for each phase). All the L.A. are 2 Ø
outdoor type and are rated for 198 KV these are manufactured by W.S. insulator. The
L.A. of generator transformer and station transformer are located near them.
It has larger value of capacitance and will change up to line voltage. If we have to do
some work on line, first earth line through earthing isolator for discharging the line
capacitance and then work.
6.13. 220 KV MOCB
Manufacturer : BHEL, Hyderabad.
Total No’s : 9
Type : HLR 245/2503 B-I.
Rated Frequency : 50 Hz.
Nominal Current : 2240 Amp.
Type of operating mechanism : Motor charging Spring Closed.
6.14. 220 KV ISOLATORS
70. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
Manufacturer : A&S Power SWGR LTD
Number : 36
Type : Double break operated.
Rated Current : 1250 Amp.
No. of Phase : 3 Ø
Rated Voltage. : 245 KV.
6.15. 220 KV CURRENT TRANSFORMER
Manufacturer : BHEL, Trichy.
Type : Outdoor, Oil filled.
Rated Voltage : 220 KV.
Nominal : 220 KV.
Max. : 245 KV.
Rated Frequency : 50 Hz.
No. of Phase : 1-Ø
Class of Insulation : A.
Rated Primary Voltage : 2220/ 53 V.
Secondary Voltage Wdg.I : 110/53 V.
Wdg.II : 110/53 V.
70
6.16. CIRCUIT BREAKER
Make : L&T Circuit Breaker Ltd.
Type : Air Circuit Breaker.
Maximum Continuous Voltage : 500 V for circuit breaker operation.
71. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
No. of Phase : 3-Ø
Rated Voltage : 415 V.
71
6.17. POWER CAPACITOR
Make : L&T Limited.
Type : ML1, ML2, ML3, ML4, ML8, ML12,.
No. of Poles : 3.
Rated Voltage for main Contacts : 500 V.
6.18. 220 KV LIGNTENING ARRESTOR
Manufacturer : W-S Isolators India Ltd. Chennai.
Type : Heavy Duty CPL II.
No. of Phases : 3-Ø
Rated Voltage : 198 KV.
Nominal Discharge Current : 10 KA.
High Current Impulse : 100 KA.
Long Duration Rating : 500 KA.
PROTECTION
72. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
72
7.1. INTRODUCTION
1. Field Protection.
2. Pole Slipping.
3. Plane Overload Protection.
4. Inter-turn Fault
5. Negative Phase Sequence Protection.
6. Reverse Power Protection.
7. Forward Power Protection.
8. Under Frequency & Over Frequency Protection.
9. Generator Voltage Protection.
10. Rotor Earth Fault Protection.
7.2. GENERAL PROTECTION
It is most important electrical equipment of many generating station. Tripping of even a
generating unit may cause overloading of associated machines and even to system un-stability.
The basis function of protection applied to generator is to reduce voltage to
minimum by rapid discrimination clearance of faults. Unlike other apparatus the opening
of C.B. to isolate faulty generator is not sufficient to prevent future damage.
7.3. SALIENT FEATURE OF K.S.T.P.S.
1. Location Sakatpura, Kota.
2. Capacity
A) 1ST Stage. 2x110 MW.
B) 2nd Stage. 2x210 MW.
C) 3rd Stage. 1x210 MW.
73. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
D) 4th Stage. 1x195 MW.
E) 5th Stage 1x195 MW (to be commissioned in
73
September 2008).
3. Source of water Chambal River.
4. Boiler
a) Type tangentially fired natural circulation,
balance direct fired radiant reheat, water
tube boiler.
b) No. of units. 6
c) Max. Efficiency BHEL (86.6 + 1) %
d) Capacity 375 tones 1 Hr.
e) Steam Pressure 139 Kg./cm2
f) Steam Temp. 540oC,
g) No. of draft fans in i) FD fans 2 Unit (Each boiler)
services ii) ID fan 2 Unit (Each boiler ).
h) No. of Air fans in Service
i) Primary 2 Unit.
ii) Seal Air fan 1 Unit.
iii) Scanner 1 Unit.
i) No. of coal mills in service 3 Unit.
j) No. of Soot blower in service 68
k) No. of oil burners 8
74. VEDANT COLLEGE OF ENGINEERING & TECHNOLOGY BUMDI
NAME-SHRI AKASH BHAI BRANCH-EEE BATCH-EEE(A)
SUNDARKAND WALE
ROLL NO-10EVNEX0001 YEAR-FINAL YEAR/7 SEM
74
7.4. Fuel
A) COAL
i) Type Stack Coal.
ii) Calorific Value 4450 K.Cal./Kg.
iii) Qty. Used 3074 tons per day.
iv) Ash contents 40%
v) Sulphur contents 0.5%
vi) Type of Handling Belt Conveyor