SlideShare a Scribd company logo
1 of 11
“Management is doing things right,
Leadership is doing the right
things!”

Presentation done by

Peter F. Drucker
PHASES OF
PERT
Project management consists of three
phases
Project Planning Phase

Scheduling Phase

Project Control Phase
Project Planning Phase
In order to visualize the sequencing or precedence
requirements of the activities in a project is helpful to
draw a network diagram. For this the following steps
are adopted: Indentify various activities to be performed in the
project, i.e. develop a breakdown structure(WBS).
 Determine the requirement of resources such as
men, material, machines, money, etc.
 Assign responsibility for each work package.
 Allocate resources to work packages.
 Estimate cost and time at various levels of
project completion.
 Develop work performance criteria.
 Establish control channels for project
personnel.
Scheduling Phase
Once all work packages have been
indentified and given unique names or
identifiers, scheduling the project, i.e.
when each of the activities are required
to be performed, is taken up. It prepares
an analysis/estimate of the likelihood of
the project to be completed on or before
the specified time.
The various steps involved in this phase are:Identify all people who will be responsible for each
task.
Estimate the expected duration(s) of each activity.
Specify the interrelationship.
Develop a network diagram.
Based on these time estimates, calculate the total
project duration, identify critical path; calculate
floats; carry out resources smoothing exercise for
critical resources, taking into account the resource
constraints.
Project Control Phase
Project control refers to the evaluation of the
actual progress against the plan. If significant
differences are observed, then the scheduling
and resource allocation decisions are changed
in order to update revise the uncompleted
part of the project. In other words, remedial
or reallocation of resources measures are
adopted in such cases.
WBS

PRECEDENCE
NETWORK

DEVIATION
FROM
PLAN

ACTUAL
PERFORMANCE
DATA

GANTT
CHART

PERIODIC
COST
REPORTS

SCHEDULE
ALLOCATION

RESOURCE
ALLOCATION
Ask me about the topic if you want.
Thanks

More Related Content

What's hot

The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart
Nicola2903
 
Gantt chart cpm
Gantt chart cpmGantt chart cpm
Gantt chart cpm
Mimin Adam
 

What's hot (20)

Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Mba ii pmom_unit-4.3 scheduling-gantt chart a
Mba ii pmom_unit-4.3 scheduling-gantt chart aMba ii pmom_unit-4.3 scheduling-gantt chart a
Mba ii pmom_unit-4.3 scheduling-gantt chart a
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert Chart
 
PERT & Gantt Chart
PERT & Gantt Chart PERT & Gantt Chart
PERT & Gantt Chart
 
CPM/PERT and Gantt charts
CPM/PERT and Gantt chartsCPM/PERT and Gantt charts
CPM/PERT and Gantt charts
 
Wbs & Bar chart for Civil engg
Wbs & Bar chart for Civil engg Wbs & Bar chart for Civil engg
Wbs & Bar chart for Civil engg
 
Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2
 
Ghant chart
Ghant chartGhant chart
Ghant chart
 
Lecture5---Gantt Chart
Lecture5---Gantt ChartLecture5---Gantt Chart
Lecture5---Gantt Chart
 
Software project management tools
Software project management toolsSoftware project management tools
Software project management tools
 
Apps4.Pro Planner Gantt chart (Chrome extension)
Apps4.Pro Planner Gantt chart (Chrome extension)Apps4.Pro Planner Gantt chart (Chrome extension)
Apps4.Pro Planner Gantt chart (Chrome extension)
 
pert chart guide for dummies
pert chart guide for dummiespert chart guide for dummies
pert chart guide for dummies
 
NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2NCV 4 Project Management Hands-On Support Slide Show - Module 2
NCV 4 Project Management Hands-On Support Slide Show - Module 2
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart
 
Gantt pert
Gantt pertGantt pert
Gantt pert
 
Project Scheduling
Project Scheduling Project Scheduling
Project Scheduling
 
PROJECT SCHEDULING
PROJECT SCHEDULINGPROJECT SCHEDULING
PROJECT SCHEDULING
 
Gantt chart cpm
Gantt chart cpmGantt chart cpm
Gantt chart cpm
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 

Viewers also liked

media pembelajaran tik bab 1 kelas 9
media pembelajaran tik bab 1 kelas 9media pembelajaran tik bab 1 kelas 9
media pembelajaran tik bab 1 kelas 9
nashikhatud
 
Presentation etika
Presentation etikaPresentation etika
Presentation etika
Galih76
 

Viewers also liked (17)

Govt jewellery delhi
Govt jewellery delhiGovt jewellery delhi
Govt jewellery delhi
 
One word Questions
One word QuestionsOne word Questions
One word Questions
 
Group dynamics
Group dynamicsGroup dynamics
Group dynamics
 
Directrices padres al comprar zapatos de fútbol de su hijo
Directrices padres al comprar zapatos de fútbol de su hijoDirectrices padres al comprar zapatos de fútbol de su hijo
Directrices padres al comprar zapatos de fútbol de su hijo
 
Agnee double reduction worm gear box hvd
Agnee double reduction worm gear box hvdAgnee double reduction worm gear box hvd
Agnee double reduction worm gear box hvd
 
Gladiangel fonseca... pdf
Gladiangel fonseca... pdfGladiangel fonseca... pdf
Gladiangel fonseca... pdf
 
media pembelajaran tik bab 1 kelas 9
media pembelajaran tik bab 1 kelas 9media pembelajaran tik bab 1 kelas 9
media pembelajaran tik bab 1 kelas 9
 
Дошкільний заклад №80.Презентація групи "Казкарики"
Дошкільний заклад №80.Презентація групи "Казкарики"Дошкільний заклад №80.Презентація групи "Казкарики"
Дошкільний заклад №80.Презентація групи "Казкарики"
 
Group 4
Group 4Group 4
Group 4
 
Las tic
Las ticLas tic
Las tic
 
Supporting integration and fostering of children with disabilities at schools
Supporting integration and fostering of children with disabilities at schoolsSupporting integration and fostering of children with disabilities at schools
Supporting integration and fostering of children with disabilities at schools
 
Current Affairs
Current Affairs Current Affairs
Current Affairs
 
Non verbal communication
Non verbal communicationNon verbal communication
Non verbal communication
 
Bright light on education - first steps - overview ru
Bright light on education - first steps - overview ruBright light on education - first steps - overview ru
Bright light on education - first steps - overview ru
 
Presentation etika
Presentation etikaPresentation etika
Presentation etika
 
Agnee crane duty helical gear box
Agnee crane duty helical gear boxAgnee crane duty helical gear box
Agnee crane duty helical gear box
 
Softwareu
SoftwareuSoftwareu
Softwareu
 

Similar to Management

Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
AMIT PAYAL
 
Work breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docxWork breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docx
ericbrooks84875
 
MBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docxMBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docx
alfredacavx97
 

Similar to Management (20)

Tools & Techniques.pptx
Tools & Techniques.pptxTools & Techniques.pptx
Tools & Techniques.pptx
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
Planning and Resourcing a Project
Planning and Resourcing a ProjectPlanning and Resourcing a Project
Planning and Resourcing a Project
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
 
1.1c Construction Planning.ppt
1.1c Construction Planning.ppt1.1c Construction Planning.ppt
1.1c Construction Planning.ppt
 
MIS Project management
MIS Project managementMIS Project management
MIS Project management
 
Network Analysis- CPM ppt..pptx
Network Analysis- CPM  ppt..pptxNetwork Analysis- CPM  ppt..pptx
Network Analysis- CPM ppt..pptx
 
Work breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docxWork breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docx
 
Planning and scheduling Techniques.ppt
Planning and scheduling  Techniques.pptPlanning and scheduling  Techniques.ppt
Planning and scheduling Techniques.ppt
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 
9a. SEPM LECTURE # 06 - PERT (1).pptx
9a.    SEPM LECTURE # 06 - PERT (1).pptx9a.    SEPM LECTURE # 06 - PERT (1).pptx
9a. SEPM LECTURE # 06 - PERT (1).pptx
 
SEN-22413 - UNIT - V.pptx
SEN-22413 -  UNIT - V.pptxSEN-22413 -  UNIT - V.pptx
SEN-22413 - UNIT - V.pptx
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life Cycle
 
MBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docxMBA 6941, Managing Project Teams 1 Course Learning Outco.docx
MBA 6941, Managing Project Teams 1 Course Learning Outco.docx
 
Spm unit 3
Spm unit 3Spm unit 3
Spm unit 3
 
Project Preparation and Management
Project Preparation and ManagementProject Preparation and Management
Project Preparation and Management
 
Project planning
Project planningProject planning
Project planning
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Sce vasg os_project_managementprocess_scw2010_05
Sce vasg os_project_managementprocess_scw2010_05Sce vasg os_project_managementprocess_scw2010_05
Sce vasg os_project_managementprocess_scw2010_05
 

More from Jacob John Panicker (17)

Promotion mix
Promotion mixPromotion mix
Promotion mix
 
Environent and its components
Environent  and its componentsEnvironent  and its components
Environent and its components
 
Environmental Management
Environmental Management Environmental Management
Environmental Management
 
Financial Agencies
Financial AgenciesFinancial Agencies
Financial Agencies
 
Scaling technique
Scaling techniqueScaling technique
Scaling technique
 
Chi square
Chi squareChi square
Chi square
 
Retro marketing
Retro marketingRetro marketing
Retro marketing
 
Operation research
Operation researchOperation research
Operation research
 
Leadershp presentation
Leadershp presentationLeadershp presentation
Leadershp presentation
 
Insurance sector
Insurance sectorInsurance sector
Insurance sector
 
The industrial dispute act 1947
The industrial dispute act 1947The industrial dispute act 1947
The industrial dispute act 1947
 
Intervention strategies
Intervention strategiesIntervention strategies
Intervention strategies
 
Identification of training and development needs
Identification of training and development needsIdentification of training and development needs
Identification of training and development needs
 
Executive information
Executive informationExecutive information
Executive information
 
Environmental laws
Environmental lawsEnvironmental laws
Environmental laws
 
Emerging concept
Emerging conceptEmerging concept
Emerging concept
 
Attitude
AttitudeAttitude
Attitude
 

Management

  • 1. “Management is doing things right, Leadership is doing the right things!” Presentation done by Peter F. Drucker
  • 3. Project management consists of three phases Project Planning Phase Scheduling Phase Project Control Phase
  • 4. Project Planning Phase In order to visualize the sequencing or precedence requirements of the activities in a project is helpful to draw a network diagram. For this the following steps are adopted: Indentify various activities to be performed in the project, i.e. develop a breakdown structure(WBS).  Determine the requirement of resources such as men, material, machines, money, etc.
  • 5.  Assign responsibility for each work package.  Allocate resources to work packages.  Estimate cost and time at various levels of project completion.  Develop work performance criteria.  Establish control channels for project personnel.
  • 6. Scheduling Phase Once all work packages have been indentified and given unique names or identifiers, scheduling the project, i.e. when each of the activities are required to be performed, is taken up. It prepares an analysis/estimate of the likelihood of the project to be completed on or before the specified time.
  • 7. The various steps involved in this phase are:Identify all people who will be responsible for each task. Estimate the expected duration(s) of each activity. Specify the interrelationship. Develop a network diagram. Based on these time estimates, calculate the total project duration, identify critical path; calculate floats; carry out resources smoothing exercise for critical resources, taking into account the resource constraints.
  • 8. Project Control Phase Project control refers to the evaluation of the actual progress against the plan. If significant differences are observed, then the scheduling and resource allocation decisions are changed in order to update revise the uncompleted part of the project. In other words, remedial or reallocation of resources measures are adopted in such cases.
  • 10. Ask me about the topic if you want.