SlideShare a Scribd company logo
1 of 10
Download to read offline
Transport Research Arena 2014, Paris
Full scale test on prefabricated slabs for electrical supply by induction
of urban transport systems
Mai-Lan Nguyena*
, Pierre Hornycha
, Jean-Pierre Kerzréhoa
, Sergio Perezb
a
LUNAM Université, IFSTTAR, Materials and Structures Department, Route de Bouaye, 44344 Bouguenais, France
b
Bombardier Transportation, Neustadter Straße 62, 68309 Mannheim, Germany
Abstract
Advanced and innovative technologies are increasingly used in transport infrastructures, especially in urban
transportation. Recently, Bombardier Transport has developed a new system for supply by induction of electrical
public transportation vehicles. The proposed solution consists in integrating the electrical supply cables, for
creating an electromagnetic induction field, in a prefabricated concrete slab implemented in the road. A key
aspect of the project is the design and resistance to heavy traffic of the proposed modular pavement. For this
purpose, it was decided to carry out a full scale test on the accelerated pavement testing facility of IFSTTAR
Nantes. Five different prototype slabs are tested, differing by the width of the slab, and the thickness of the
concrete cover above the supply cables. The experiment consists of subjecting the slabs to one million passes
with a dual wheel load of 65 kN and monitoring the mechanical behaviour of the slabs pavement by measuring
strains and displacements in chosen points. The paper presents the design of the proposed prefabricated slabs
pavement, the installation procedure of these slabs and first results of the current full scale test.
Keywords: prefabricated road slab; full scale test; induction; electric vehicle supply; urban transport system.
Résumé
Les technologies avancées et innovantes sont de plus en plus utilisées dans les infrastructures de transport, en
particulier dans les transports urbains. Bombardier Transport a récemment développé un nouveau système
d'alimentation par induction des véhicules électriques. La solution proposée intègre dans une dalle en béton
préfabriquée installée dans la chaussée, les câbles d'alimentation électrique permettant de créer un champ
d'induction électromagnétique. Un aspect clé du projet est le concept et la résistance au trafic lourd du module
proposé. A cet effet, il a été décidé de réaliser un essai en vraie grandeur avec le simulateur de trafic routier
lourd, le manège de fatigue de l'IFSTTAR à Nantes. Cinq dalles prototypes ont été testées, différenciées par leur
largeur et par l'épaisseur de la couverture en béton au-dessus des câbles. L’expérience consiste à soumettre ces
dalles à un million de passages du jumelage de 65 kN et à suivre le comportement mécanique de la chaussée des
dalles en mesurant les déformations et les déplacements en des points choisis. Cet article présente le concept de
la chaussée expérimentale en dalles préfabriquées, la solution de mise en place et le suivi du comportement de
ces dalles dans l’essai manège en cours.
Mots-clé: dalle chaussée préfabriquée ; essai en vraie grandeur ; induction ; alimentation de véhicule électrique ;
système de transport urban
*
Tel.: +33-2-4084-5715; fax: +33-2-4084-5994.
E-mail address: mai-lan.nguyen@ifsttar.fr.
Nguyen Mai-Lan / Transport Research Arena 2014, Paris 2
1. Introduction
Electric road becomes more realistic. Among the technologies under development, inductive charging represents
a promising technique and is being experimented in Germany and Belgium (Beeldens, 2013). In addition to the
advantages of clean solutions (no use of ordinary fuels, such as petrol or diesel, no local emissions), inductive
charging technology is practical to use and may contribute to minimizing different types of urban pollution (air,
visibility and noise pollutions). It also solves the problem of autonomy of electric vehicles (EV) and reduces
their weight by reducing the battery size, in particular for public transport vehicles.The development of this new
technology for transport infrastructures matches the ideas of current projects in France and Europe: the 5th
Generation Road, the European project Forever Open Road, and the Infravation programme.
Recently, Bombardier Transportation has developed a new system for supply by inductive charging of electric
buses. The idea is to implement the inductive charging system in the road at bus stops for recharging while
passengers get on and off. This implementation is based on the principle of modular construction consisting of
prefabricated elements ready to be installed simply and quickly. In particular, the component responsible for the
inductive power transfer is integrated in a prefabricated concrete slab which is implemented in the road. The slab
contains electrical supply cables, for creating a magnetic field. A power receiver system installed underneath the
EV, when the last one parks on the induction segment, turns this magnetic field into an electric current that feeds
the vehicle traction system.
A key aspect of the project is the design and resistance to heavy traffic of the proposed modular pavement. For
this purpose, it was decided to carry out a full scale test on the accelerated pavement testing (APT) facility of
IFSTTAR Nantes (fig. 1). It is a heavy road traffic simulator, dedicated to full-scale pavement experiments.
Since 2000s, the APT facility has demonstrated its capacity for testing of urban infrastructure solutions (de
Larrard et al., 2013; Fort, 2013).
Fig. 1. The IFSTTAR’s APT facility
Five different slab prototypes are tested, differing by the width of the slab, and the thickness of the concrete
cover above the supply cables. The slabs are instrumented using strain gages, displacement transducers, and
geophones, to verify their strains and displacements under loading. Electrical measurements are also made to
verify the performance of the cables throughout the experiment. The experiment consists of subjecting the slabs
to one million passes with a dual wheel load of 65 kN (corresponding to half of the French standard axle load of
130 kN, which is the highest in the world). From February 1st to April 4th 2013, a first period of loading was
performed with approximately 260 000 traffic passages. The paper presents the design and construction of the
proposed prefabricated slab pavement, results of the first period of the current full scale test, and their
perspectives, in terms of deployment of this technology.
2. Design of the full scale test
The proposed solution, to ensure the implementation of the inductive charging system in the road, consists of
prefabricated concrete slabs, containing the electrical supply cables. These slabs, reinforced with glass fibre
reinforced polymer (GFRP) rebars, have a length of 5 m, a thickness of 0.25 m, and are intended to be
incorporated into a pavement structure. The power supply of each slab is independent and is activated only by
passing of an applicable EV when it is detected by an antenna system.
Nguyen Mai-Lan / Transport Research Arena 2014, Paris
IFSTTAR has been asked to work on the design of the pavement structure to receive these prefabricated slabs
and then test them on the APT facility. The solution that has been proposed is to provide a bituminous
foundation layer of 8 cm thickness, then place on it the prefabricated slabs using aluminium supports of
adjustable height, placed at the corners of the slabs to control precisely the final level of the slabs. A high
performance, non-shrinking, cement slurry is placed in the space remaining below the slab (about 2 cm) to
ensure a good contact between the slab and the foundation support. After the placement of the slabs, the space
around the slabs was filled with cement concrete. Dowels made of glass fibres are used to connect the slabs with
the surrounding concrete pavement in the longitudinal direction. A pre-cracking in the transverse direction,
extending the joints between the slabs and the concrete fill, was made in the concrete fill. For that purpose, the
concrete has been sawn, one day after its casting, to a third of its depth, to avoid the appearance of uncontrolled
cracks. A transverse profile of the pavement structure, without concrete fill around the slab, is shown on fig. 2.
8 cm bituminous base
Platform 150 ÷ 200 MPa
2 cm cement
slurry
25 cm
aluminium
supports
Prefab.
slab
Component responsible for
inductive power transfer
Fig. 2. Transverse profile of the tested pavement.
The experimentation of inductive charging system integrated on prefabricated slabs is performed on a half-ring
of the circular test track (fig. 3). A classical bituminous pavement is placed on the other half-ring for proper
rotation of the traffic simulator. Five slab prototypes, including three standard slabs of 5 m  2.4 m and two
narrow slabs of 5 m  1.25 m, are being tested. The narrow size is intended for optimizing precast and transport
processes. These two narrow slabs have eight GFRP rebars coming out of the slabs on the longitudinal sides.
Pre-cracking was created, in the longitudinal direction on both sides of the narrow slabs at the end of these
rebars. Both standard and narrow slabs include the same module containing the electrical supply cables, which is
positioned in the central part of the slab. On the test track, the wheel loads run at a fixed radius, of 19 m. The
slabs have been placed at different transversal positions on the test track in order to apply the loads either on the
centre or on the edge of the slab. The thickness of the concrete cover above the supply cables is also an
important parameter, for the resistance of the slabs. On the standard slabs, two levels of thickness have been
tested: 4 cm on the two first slabs, and 5 cm on the third one. On the two narrow slabs, the thickness of the top
concrete layer is 3.5 cm and 4 cm respectively. Table 1 summarises the testing configuration of these slabs.
Direction ofrotation
Pre-cracking
Concretepavement
Slab A
Slab E
Slab D Slab C
Slab B
Old concrete
slab pavement
Bituminous
pavement
Other
components
R 19 m
Fig. 3. Plan of the circular test track
Nguyen Mai-Lan / Transport Research Arena 2014, Paris 4
Table 1. Testing configuration of slab prototypes
Slab Slab dimensions
(m)
Lateral position of traffic
along the slab
Thickness of the concrete
cover (cm)
Slab A 52.40.25 middle 5.0
Slab B 52.40.25 edge 5.0
Slab C 52.40.25 middle 4.0
Slab D 51.250.25 middle 3.5
Slab E 51.250.25 edge 4.0
3. Construction of the full scale test and solution for installation of the prefabricated slabs
The construction of the test track required several phases. After removing the existing pavement to the level of
the subgrade platform, it has been adjusted at the right level for installation of the prefabricated slabs. The
bearing capacity of the existing platform was then measured at different positions by means of the dynamic plate
test, which gave values between 150 and 200 MPa.
To test the mechanical behaviour and resistance of the prefabricated slabs under heavy traffic, stabilization of
these slabs is very important. For the construction of the proposed structure (fig. 1), the following procedure was
applied for the first four slabs (A, B, C and D). For slab E, in order to simulate better actual conditions on
construction sites in urban areas, i.e. limited space and time, a slightly different procedure was tested.
3.1. Procedure for installation of the slabs A, B, C and D
 Realization of an 8 cm thick bituminous subbase layer. This step was needed on the APT site. However, on an
actual site, it could be another support, e.g. milling of the existing pavement.
 Fine milling of this base layer to obtain a first calibration of the final level of the prefabricated slab.
 Positioning of aluminium supports at the four corners of each slab. At each corner, several support plates of
different thicknesses were used, firstly a thick plate of 15 mm, then thinner plates (of 1 mm minimum). The
level of these supports was verified (taking into account the slab thickness) by leveling measurements, in
order to reach precisely the final level of the slab.
 Placement of the slab on the aluminium supports using a crane to ensure the final level of the slab.
 Construction of a formwork around the slab for receiving the cement slurry.
 Lifting of the slab and filling of the formwork with the cement slurry; before replacing the slab on top of the
cement slurry.
To ensure proper filling of the cement slurry, several blowholes have been created in the slabs in the
prefabrication, to allow entrapped air to escape and the cement slurry to be well distributed during installation of
the slabs. These blowholes were clogged at the end of the process.
To validate this procedure and check the stability of the slab under moving of a heavy vehicle, a feasibility test
was performed on slab A (fig. 4). The test was carried out 18 days after placement of the slab. It consisted of
moving slowly the half axle of a heavy vehicle of about 20 tons on the slab and measuring deflection of the slab
at different positions: at the four corners and in the middle of each lateral edge. Three load levels of the half axle
were applied: 66 kN, 76 kN and 96 kN. The measured maximum deflections, which increased proportionally
with the load level, were 0.10 mm, 0.11 mm and 0.16 mm respectively. These deflection levels remained small
and were consistent with estimations made using the pavement design software Alizé-Lcpc.
After installation of the slabs, the remaining space around the slabs was filled using a cement concrete of high
performance to form a continuous pavement.
Nguyen Mai-Lan / Transport Research Arena 2014, Paris
Fig. 4. Feasibility test with a truck.
3.2. Procedure for installation of slab E
The same principle of slab stabilization using cement slurry was used, but two main points were modified:
 To approach the actual conditions of insertion of the prefabricated slab into an existing pavement with limited
space, the concrete fill, next to the upstream end of the slab, was placed before installation of the slab. Several
grooves were made in the concrete fill to allow insertion of the dowels.
 In order to accelerate the installation of the slab, a faster procedure of stabilization of the slabs was applied.
The slab E was placed on supports, the level of which could be adjusted using three screws. The cement slurry
was then injected under pressure (fig. 5) directly under the slab. This procedure avoided lifting the slab again
before filling of the cement slurry, which reduces the use of the crane on the construction site.
After installation of the slabs, the remaining space around the slab was filled using a high performance cement
concrete as realized previously.
Fig. 5. Installation of prefabricated slab with injection of cement slurry.
4. Test conditions and parameters measured during the test
4.1. Test conditions
The test program consists in applying one million loads, with dual wheels, loaded at 50 kN for the first 100 000
passages and 65 kN for the remaining of the test. This represents a traffic of about 150 buses per day for 20
years, and corresponds to 250 000 rotations of the four arms carousel. Loading is applied at the radius of 19 m
and thus the total perimeter of the test track circuit is approximately 120 m. A reduced lateral wandering of 0.8
m wide of the load is applied in order to simulate the channelized traffic of buses.
The speed of rotation of the carousel applied under normal conditions is 5 rounds/minute, which corresponds to a
tangential velocity of about 35.8 km/h at a radius of 19 m. Lower speeds have also been applied for specific
Displacement
transducer
Nguyen Mai-Lan / Transport Research Arena 2014, Paris 6
measurements. However, it was decided not to run at higher speeds, in order to avoid dynamic effects in the
loading modules of the traffic simulator, which could occur due to the less even surface of the concrete slab
pavement compared to a conventional bituminous pavement.
4.2. Parameters measured during the test
The instrumentation of the test comprises mainly surface measurements close to the joints between the slabs and
the concrete fill. These measurements monitor the movements of the slabs under moving loads. Three
measurement systems are used:
 A Benkelman beam with two LVDTs (Linear Variable Differential Transducer) measures the deflection on
both sides of each joint, compared to fixed supports located about 2 m away from the measured points. This
system can make measurements only at slow speed (1 round/minute). It can be moved to follow in turn the
deflections at different joints.
 A LVDT, installed next to each joint, measures the relative movement, i.e. the faulting effect, between the
slab and the concrete fill. This equipment can operate regardless of the speed of the traffic simulator.
 To measure the deflections at high speeds, four geophones were installed on slab C. These geophones, fixed
on both sides of each joint of the slab C, measure the speed of the vertical displacement of the measured
points under moving loads, which allows determining, by integration, the deflections at these points.
Periodic FWD (Falling Weight Deflectometer) measurements will be performed to evaluate the response of the
prefabricated slabs at different stages of the experiment.
Due to the difficulty of instrumenting on site, only two strain gauges were glued on the lower surface of the slab
A, near the middle of each lateral edge, in the longitudinal direction. These gauges allow measuring the
deformation of the slab at these positions.
Regarding the subgrade, three strain gauges were installed vertically at the top of the subgrade layer, under each
of the three slabs B, C and D, to follow the evolution of vertical deformations of the subgrade.
Two temperature profiles, one in slab B and the other one in the concrete fill located between slabs B and C, are
being recorded using thermocouple sensors placed at different depth levels, i.e. 0, - 12, - 24, - 29, - 34 and - 44
cm. Two other thermocouples are used to measure the air temperature in sunlight and in the shade.
The functioning of the integrated electric cables is also controlled at different stages of the test.
At the end of the test, it is planned to carry out detailed investigations, to core specimens to check different
aspects such as: contact conditions under the slabs or in the areas containing electric cables, possible
deterioration or cracking of the slabs, mechanical properties of concrete material and cement slurry.
5. First results and interpretation
Results presented in this paper concern the first period of the test with approximately 260 000 loads.
Measurements by different sensors were recorded at 10 000, 50 000, 100 000 and 260 000 loads. During this first
period of investigation, temperatures measured on the surface of the concrete slabs ranged between -3 °C and 22
°C. This period was also marked by a high rainfall level. Visual surveys were carried out regularly. Up to now,
no degradation has been observed on the surface of the slabs.
Evolution of deflections and vertical strains measured respectively on the upper surface of the slabs and in the
platform under the slabs, as well as an example of horizontal strain of a slab measured on its lower surface are
shown below.
5.1. Deflections of concrete slabs pavement measured at joints
Deflections measured with the double LVDT beam on both sides of the joints between the slabs and the concrete
fill, at 100 000 loads (the beginning of application of the standard load of 65 kN) and then at 260 000 loads are
Nguyen Mai-Lan / Transport Research Arena 2014, Paris
summarised in fig.6. These measurements were carried out successively at all joints, by moving the beam on
each joint, over a period of about two hours.
At 100 000 loads, it is observed that:
 Deflection signals are very similar at all joints, and there is very little difference between the measurements
on the concrete fill side and on the prefabricated slab side, indicating good continuity of the pavement.
 Deflection levels are small, between 0.06 and 0.12 mm. These values are in agreement with calculations using
the Alizé-LCPC pavement design software (which assumes a continuous, jointless pavement), which gives a
deflection of 0.11 mm.
 However, we can note slightly higher deflections at the upstream joints of slabs B and D (in the direction of
rotation of the loads).
At 260 000 loads, measured deflections increase clearly, indicating possibly a decrease of rigidity of the support
at the joints:
 At most joints, deflections vary between 0.10 and 0.16 mm, and have the same level on both sides of the joint.
 However, on the upstream joints of slabs B and D, the differences between the measurements on the concrete
fill and on the slabs increase significantly. This indicates higher slab faulting, confirming the observations
done at 100 000 loads. Deflections measured on the slab side reach 0.25 mm for slab B and 0.20 mm for slab
D. It can be seen that the faulting increases only at the upstream joints (of slabs B and D for the moment).
This phenomenon can be explained by the fact that when the load reaches the upstream joint of the slab, it
will create an impact (dynamic overload) due to the unevenness of the joint. The subgrade under the upstream
part of the slab thus deteriorates more rapidly, with increasing number of loads. When the load leaves the
slab, the load variation is more gradual, and therefore, there is no dynamic impact on the downstream part of
the slab.
-0.3
-0.25
-0.2
-0.15
-0.1
-0.05
0
0.05
0.1
0 5 10 15 20 25 30 35 40 45 50
Deflection(mm)
Distance (m)
Measurement on the concrete fill boder
Measurement on the slab border
A B C D E
Measurement 14/03/2013,100 000 loads
65 kN; 7.2 km/h; T(surface) = 4.5 oC
Direction of rotation
-0.3
-0.25
-0.2
-0.15
-0.1
-0.05
0
0.05
0.1
0 5 10 15 20 25 30 35 40 45 50
Deflection(mm)
Distance (m)
Measurement on the concrete fill boder
Measurement on the slab border
A B C D E
Measurement 04/04/2013,260 000 loads
65 kN; 7.2 km/h; T(surface) = 8.5 oC
Fig. 6. Deflection measured by means of two LVDTs mounted on a Benkelman beam, on both sides of each slab joint: (a) at
100 000 loads; (b) at 260 000 loads
Nguyen Mai-Lan / Transport Research Arena 2014, Paris 8
5.2. Vertical subgrade strains under the prefabricated slabs
Fig. 7 presents vertical strains of the subgrade under the three slabs B, C and D, respectively at 100 000 loads
and then at 260 000 loads. These measurements were recorded during only one rotation of the load.
At 100 000 loads:
 At this stage, the vertical strains under each slab are still more or less similar.
 Vertical strains under slab B (where the loads pass near the edge) are larger than the ones under slab C (where
the loads pass in the middle). This result indicates that passing of traffic near the edge of the prefabricated
modular slab, which will be the normal condition of bus operation, leads to higher strains (and settlements) of
the subgrade beneath the slab.
 Even though the narrow slab D (with loads passing the middle) has eight GFRP rebars used to transfer the
load to the surrounding concrete fill, vertical strains under this slab are more visible than under the slab C.
At 260 000 loads:
 Vertical strains under each slab increase mostly at both ends of the slab (indicating that the faulting of the
slabs increases).
 However, under the upstream end of slabs B and D, the maximum vertical strain is significantly higher than
under the downstream end of the slabs. This confirms the results obtained for the deflection measurements,
which indicate a more pronounced loss of stiffness of the subgrade near the upstream end of the slabs.
-500
-400
-300
-200
-100
0
100
10 15 20 25 30 35
Verticalstrain(mm/m)
Distance (m)
ZB1
ZB2
ZB3
ZC4
ZC5
ZC6
ZD7
ZD8
ZD9
Measurement 14/03/2013, 100 000 loads
65 kN; 7.2 km/h; T(surface) = 4.5 oC
B C D
-500
-400
-300
-200
-100
0
100
10 15 20 25 30 35
Verticalstrain(mm/m)
Distance (m)
ZB1
ZB2
ZB3
ZC4
ZC5
ZC6
ZD7
ZD8
ZD9
Measurement 04/04/2013, 260 000 loads
65 kN; 7.2 km/h; T(surface) = 8.5 oC
B C D
Fig. 7. Vertical strain measurements by means of strain gauges installed in the subgrade under each slab: (a) at 100 000 loads;
(b) at 260 000 loads
5.3. Horizontal strains at bottom of the prefabricated slab
An example of typical signals measured by means of a strain gauge glued on the lower surface of slab A is
plotted in fig. 8. In this measurement, the four load modules (all loaded at 65 kN) of the traffic simulator passed
at four different lateral positions of the slab (corresponding to radii of 18.5, 18.7, 18.9 and 19.1 m), and rotated at
a speed of 5 rounds/minute. The strain gauge was placed close to the inner lateral edge of the slab, which
corresponds to a radius of 17.85 m. Thus, the closer the load approaches the position of the gauge, the higher the
Nguyen Mai-Lan / Transport Research Arena 2014, Paris
strain level. However, the strain levels are very small (the maximum value is 9 μm/m when the load passed at the
radius of 18.5 m). These low strain levels indicate no fatigue due to tensile strains at the bottom of the slabs.
-4
-2
0
2
4
6
8
10
20 40 60 80 100 120 140
Horizontalstrain(mm/m)
Distance (m)
R=19.1 m
R=18.9 m
R=18.7 m
R=18.5 m
Fig. 8. Horizontal strain measured on the lower surface of the slab A when the four loads (65 kN each) passed at four
different lateral positions of the slab at 260 000 loads.
The results of these different measurements give a good idea of the mechanical response of the slabs. This will
enable comparisons with finite element calculations, using the Cesar-Lcpc software (Humbert et al., 2005) to
accurately reproduce the behavior of the prefabricated concrete slabs, the key element of the inductive charging
solution for EVs in urban areas, and to evaluate their durability.
6. Conclusions and perspectives
This experiment confirms the interest of the IFSTTAR's APT facility for testing an innovative solution of
electrified road, which represents a very promising solution for power supply of EVs in urban areas. A solution
of pavement support to receive the prefabricated slabs containing the charging system for electric vehicles by
induction was designed and tested on the heavy traffic simulator. A practical procedure for the implementation
of these slabs in urban areas has also been studied and validated by a feasibility test.
The full scale experiment, which aims to test these prefabricated slabs with a traffic of one million dual wheel
half axles loaded at 65 kN, started in February 2013. At this stage, 260 000 loads have been realized.
Measurements taken during this first period show satisfactory results:
 The deflection of the slabs and the faulting level at joints remain small and consistent with simulations. Only
a slight increase of faulting of two slab ends with the evolution of traffic is observed.
 The power supply systems of the five tested slabs continue to function properly, without any damage, after
260 000 loads.
 At this stage, no deterioration was observed on the surface of the slabs.
The test will be continued up to one million loads. From 500 000 loads, it is planned to install on the test track a
new precast slab with a different design. A detailed assessment of the slabs behaviour will be conducted at the
end of the experiment, and will allow validation and improvement of this particular Bombardier’s solution for
inductive EVs recharging system integrated on a specific designed prefabricated slab.
Under development since 2008, the inductive charging technology is firstly in passenger operation in 2013 in
Braunschweig (Germany). This next generation of electric mobility solutions will be provided for all forms of
electric vehicles, including trams, buses, commercial vehicles, taxis and cars operating in urban areas.
References
Beeldens A. (2013). Inductive Charging: projet de charge par induction de véhicules électriques. Revue Générale
des Routes et des Aménagements, n°910.
de Larrard F., Sedran T., Balay J.M. (2012). Removable Urban Pavements: An innovative, sustainable
technology. International Journal of Pavement Engineering, Vol. 14, Issue 1, 1 - 11.
Nguyen Mai-Lan / Transport Research Arena 2014, Paris 10
Fort T. (2013). Evaluation sous trafic lourds des systèmes d’alimentation des tramways par le sol – Essai
Alstom, Revue Générale des Routes et des Aménagements, n°914.
Humbert, P., Dubouchet, A., Fezans, G., & Remaud, D. (2005). CESAR-LCPC, un progiciel de calcul dédié au
génie civil. Bulletin de liaison des Laboratoires des Ponts et Chaussées, Numéro spécial CESAR-LCPC, (256-
257), 7-37.
The IFSTTAR’s Alizé-LCPC software for the thickness design of pavement according to the French rational
method: http://www.lcpc.fr/english/products/lcpc-products-alize-lcpc-routes/

More Related Content

What's hot

Lect 6 pavement design
Lect 6 pavement designLect 6 pavement design
Lect 6 pavement designM Firdaus
 
Intelligent infrastructure and maintenance on the railway network - Andy Doherty
Intelligent infrastructure and maintenance on the railway network - Andy DohertyIntelligent infrastructure and maintenance on the railway network - Andy Doherty
Intelligent infrastructure and maintenance on the railway network - Andy DohertyKTN
 
Tunnel Stability Factor Michalis_Konstantis
Tunnel Stability Factor Michalis_KonstantisTunnel Stability Factor Michalis_Konstantis
Tunnel Stability Factor Michalis_KonstantisILIAS MICHALIS
 
Modern Trends In Pavement Design
Modern Trends In Pavement DesignModern Trends In Pavement Design
Modern Trends In Pavement DesignLatif Hyder Wadho
 
Urban track singapore
Urban track singaporeUrban track singapore
Urban track singaporeIrwan Joe
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
Strain characteristicts in a unique platform integrated with truck chassis un...
Strain characteristicts in a unique platform integrated with truck chassis un...Strain characteristicts in a unique platform integrated with truck chassis un...
Strain characteristicts in a unique platform integrated with truck chassis un...Dr.Vikas Deulgaonkar
 
Effect of l b ratio of stone column on bearing capacity and relative settleme...
Effect of l b ratio of stone column on bearing capacity and relative settleme...Effect of l b ratio of stone column on bearing capacity and relative settleme...
Effect of l b ratio of stone column on bearing capacity and relative settleme...IAEME Publication
 
10-Traffic Characterization ( Highway Engineering Dr. Sherif El-Badawy )
10-Traffic Characterization ( Highway Engineering Dr. Sherif El-Badawy )10-Traffic Characterization ( Highway Engineering Dr. Sherif El-Badawy )
10-Traffic Characterization ( Highway Engineering Dr. Sherif El-Badawy )Hossam Shafiq I
 
Critical Appraisal of Pavement Design of Ohio Department of Transportation (O...
Critical Appraisal of Pavement Design of Ohio Department of Transportation (O...Critical Appraisal of Pavement Design of Ohio Department of Transportation (O...
Critical Appraisal of Pavement Design of Ohio Department of Transportation (O...Pranamesh Chakraborty
 
Pavement thickness design
Pavement thickness designPavement thickness design
Pavement thickness designSohail Khan
 
Teaser ogres v 150307.2
Teaser ogres v 150307.2Teaser ogres v 150307.2
Teaser ogres v 150307.2Fabian Huguet
 
Improved magnetic behavior of hemicycle PM motor via stator modification
Improved magnetic behavior of hemicycle PM motor  via stator modification Improved magnetic behavior of hemicycle PM motor  via stator modification
Improved magnetic behavior of hemicycle PM motor via stator modification IJECEIAES
 
Heavy Duty Pavement Design
Heavy Duty Pavement DesignHeavy Duty Pavement Design
Heavy Duty Pavement Designguestdbd9fccc
 

What's hot (19)

64 bus rollover simulation
64 bus rollover simulation64 bus rollover simulation
64 bus rollover simulation
 
Lect 6 pavement design
Lect 6 pavement designLect 6 pavement design
Lect 6 pavement design
 
Intelligent infrastructure and maintenance on the railway network - Andy Doherty
Intelligent infrastructure and maintenance on the railway network - Andy DohertyIntelligent infrastructure and maintenance on the railway network - Andy Doherty
Intelligent infrastructure and maintenance on the railway network - Andy Doherty
 
Tunnel Stability Factor Michalis_Konstantis
Tunnel Stability Factor Michalis_KonstantisTunnel Stability Factor Michalis_Konstantis
Tunnel Stability Factor Michalis_Konstantis
 
Modern Trends In Pavement Design
Modern Trends In Pavement DesignModern Trends In Pavement Design
Modern Trends In Pavement Design
 
Urban track singapore
Urban track singaporeUrban track singapore
Urban track singapore
 
LIAN_D_NRC
LIAN_D_NRCLIAN_D_NRC
LIAN_D_NRC
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
Strain characteristicts in a unique platform integrated with truck chassis un...
Strain characteristicts in a unique platform integrated with truck chassis un...Strain characteristicts in a unique platform integrated with truck chassis un...
Strain characteristicts in a unique platform integrated with truck chassis un...
 
Effect of l b ratio of stone column on bearing capacity and relative settleme...
Effect of l b ratio of stone column on bearing capacity and relative settleme...Effect of l b ratio of stone column on bearing capacity and relative settleme...
Effect of l b ratio of stone column on bearing capacity and relative settleme...
 
Flexible Pavement Design
Flexible Pavement DesignFlexible Pavement Design
Flexible Pavement Design
 
10-Traffic Characterization ( Highway Engineering Dr. Sherif El-Badawy )
10-Traffic Characterization ( Highway Engineering Dr. Sherif El-Badawy )10-Traffic Characterization ( Highway Engineering Dr. Sherif El-Badawy )
10-Traffic Characterization ( Highway Engineering Dr. Sherif El-Badawy )
 
Critical Appraisal of Pavement Design of Ohio Department of Transportation (O...
Critical Appraisal of Pavement Design of Ohio Department of Transportation (O...Critical Appraisal of Pavement Design of Ohio Department of Transportation (O...
Critical Appraisal of Pavement Design of Ohio Department of Transportation (O...
 
Pavement thickness design
Pavement thickness designPavement thickness design
Pavement thickness design
 
Sma 17
Sma 17Sma 17
Sma 17
 
Pavement design
Pavement designPavement design
Pavement design
 
Teaser ogres v 150307.2
Teaser ogres v 150307.2Teaser ogres v 150307.2
Teaser ogres v 150307.2
 
Improved magnetic behavior of hemicycle PM motor via stator modification
Improved magnetic behavior of hemicycle PM motor  via stator modification Improved magnetic behavior of hemicycle PM motor  via stator modification
Improved magnetic behavior of hemicycle PM motor via stator modification
 
Heavy Duty Pavement Design
Heavy Duty Pavement DesignHeavy Duty Pavement Design
Heavy Duty Pavement Design
 

Similar to Full-scale testing of prefabricated slabs for inductive electric vehicle charging

PARAMETRIC STUDY ON SLAB DECK BRIDGES USING RESPONSE SURFACE METHOD
PARAMETRIC STUDY ON SLAB DECK BRIDGES USING RESPONSE SURFACE METHODPARAMETRIC STUDY ON SLAB DECK BRIDGES USING RESPONSE SURFACE METHOD
PARAMETRIC STUDY ON SLAB DECK BRIDGES USING RESPONSE SURFACE METHODIRJET Journal
 
IRJET- Comparative Study of Effect of Varying Span Length on Major Elemen...
IRJET-  	  Comparative Study of Effect of Varying Span Length on Major Elemen...IRJET-  	  Comparative Study of Effect of Varying Span Length on Major Elemen...
IRJET- Comparative Study of Effect of Varying Span Length on Major Elemen...IRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
Seminar report on Vactrain
Seminar report on VactrainSeminar report on Vactrain
Seminar report on VactrainPunit Chainwal
 
A Review of Dynamic Wireless Power Transfer for In-Motion Electric Vehicles
A Review of Dynamic Wireless Power Transfer for In-Motion Electric VehiclesA Review of Dynamic Wireless Power Transfer for In-Motion Electric Vehicles
A Review of Dynamic Wireless Power Transfer for In-Motion Electric VehiclesRoger Atkins
 
Three Dimensional Non-Linear Seismic Analysis of a Cable Stayed Bridge using ...
Three Dimensional Non-Linear Seismic Analysis of a Cable Stayed Bridge using ...Three Dimensional Non-Linear Seismic Analysis of a Cable Stayed Bridge using ...
Three Dimensional Non-Linear Seismic Analysis of a Cable Stayed Bridge using ...IRJET Journal
 
Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...IRJET Journal
 
Advanced Cable Stayed Bridge Construction Process Analysis with ANSYS
Advanced Cable Stayed Bridge Construction Process Analysis  with ANSYS Advanced Cable Stayed Bridge Construction Process Analysis  with ANSYS
Advanced Cable Stayed Bridge Construction Process Analysis with ANSYS IJMER
 
2 sec 004_cygas_et_al_research
2 sec 004_cygas_et_al_research2 sec 004_cygas_et_al_research
2 sec 004_cygas_et_al_researchugrasenchy
 
Innovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yardInnovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yardRajesh Prasad
 
Design of cell transmission tower with different bracing patterns
Design of cell transmission tower with different bracing patternsDesign of cell transmission tower with different bracing patterns
Design of cell transmission tower with different bracing patternsIRJET Journal
 
Analytical study of abutment and pile behaviour of iab with soil interaction
Analytical study of abutment and pile behaviour of iab with soil interactionAnalytical study of abutment and pile behaviour of iab with soil interaction
Analytical study of abutment and pile behaviour of iab with soil interactioneSAT Publishing House
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
 

Similar to Full-scale testing of prefabricated slabs for inductive electric vehicle charging (20)

PARAMETRIC STUDY ON SLAB DECK BRIDGES USING RESPONSE SURFACE METHOD
PARAMETRIC STUDY ON SLAB DECK BRIDGES USING RESPONSE SURFACE METHODPARAMETRIC STUDY ON SLAB DECK BRIDGES USING RESPONSE SURFACE METHOD
PARAMETRIC STUDY ON SLAB DECK BRIDGES USING RESPONSE SURFACE METHOD
 
IRJET- Comparative Study of Effect of Varying Span Length on Major Elemen...
IRJET-  	  Comparative Study of Effect of Varying Span Length on Major Elemen...IRJET-  	  Comparative Study of Effect of Varying Span Length on Major Elemen...
IRJET- Comparative Study of Effect of Varying Span Length on Major Elemen...
 
Mumbai-Nagpur.pdf
Mumbai-Nagpur.pdfMumbai-Nagpur.pdf
Mumbai-Nagpur.pdf
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
Seminar report on Vactrain
Seminar report on VactrainSeminar report on Vactrain
Seminar report on Vactrain
 
A Review of Dynamic Wireless Power Transfer for In-Motion Electric Vehicles
A Review of Dynamic Wireless Power Transfer for In-Motion Electric VehiclesA Review of Dynamic Wireless Power Transfer for In-Motion Electric Vehicles
A Review of Dynamic Wireless Power Transfer for In-Motion Electric Vehicles
 
Jcemi 2018 14
Jcemi 2018 14Jcemi 2018 14
Jcemi 2018 14
 
Three Dimensional Non-Linear Seismic Analysis of a Cable Stayed Bridge using ...
Three Dimensional Non-Linear Seismic Analysis of a Cable Stayed Bridge using ...Three Dimensional Non-Linear Seismic Analysis of a Cable Stayed Bridge using ...
Three Dimensional Non-Linear Seismic Analysis of a Cable Stayed Bridge using ...
 
Solar roadways
Solar roadwaysSolar roadways
Solar roadways
 
Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...Analysis of stability of rock column between cut & cover Metro Station and NA...
Analysis of stability of rock column between cut & cover Metro Station and NA...
 
training report LMRC
training report LMRCtraining report LMRC
training report LMRC
 
Advanced Cable Stayed Bridge Construction Process Analysis with ANSYS
Advanced Cable Stayed Bridge Construction Process Analysis  with ANSYS Advanced Cable Stayed Bridge Construction Process Analysis  with ANSYS
Advanced Cable Stayed Bridge Construction Process Analysis with ANSYS
 
Ijciet 10 01_167-2-3
Ijciet 10 01_167-2-3Ijciet 10 01_167-2-3
Ijciet 10 01_167-2-3
 
2 sec 004_cygas_et_al_research
2 sec 004_cygas_et_al_research2 sec 004_cygas_et_al_research
2 sec 004_cygas_et_al_research
 
PPP
PPPPPP
PPP
 
Innovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yardInnovative solution for crossing larger spaces like railway yard
Innovative solution for crossing larger spaces like railway yard
 
EXPLINER
EXPLINEREXPLINER
EXPLINER
 
Design of cell transmission tower with different bracing patterns
Design of cell transmission tower with different bracing patternsDesign of cell transmission tower with different bracing patterns
Design of cell transmission tower with different bracing patterns
 
Analytical study of abutment and pile behaviour of iab with soil interaction
Analytical study of abutment and pile behaviour of iab with soil interactionAnalytical study of abutment and pile behaviour of iab with soil interaction
Analytical study of abutment and pile behaviour of iab with soil interaction
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 

More from l’Institut français des sciences et technologies des transports, de l’aménagement et des réseaux

More from l’Institut français des sciences et technologies des transports, de l’aménagement et des réseaux (20)

Trajectoire le magazine n°16 - décembre 2018
Trajectoire le magazine n°16 - décembre 2018Trajectoire le magazine n°16 - décembre 2018
Trajectoire le magazine n°16 - décembre 2018
 
2018 avec l'Ifsttar
2018 avec l'Ifsttar2018 avec l'Ifsttar
2018 avec l'Ifsttar
 
Trajectoire, le magazine n°15 - juin 2018
Trajectoire, le magazine n°15 - juin 2018Trajectoire, le magazine n°15 - juin 2018
Trajectoire, le magazine n°15 - juin 2018
 
Activity report 2017
Activity report 2017Activity report 2017
Activity report 2017
 
Electric road - revue de presse
Electric road - revue de presseElectric road - revue de presse
Electric road - revue de presse
 
Rapport d'activité 2017
Rapport d'activité 2017Rapport d'activité 2017
Rapport d'activité 2017
 
Dossier de presse - Sense-City
Dossier de presse - Sense-City Dossier de presse - Sense-City
Dossier de presse - Sense-City
 
Projet INDIRA_B
Projet INDIRA_B Projet INDIRA_B
Projet INDIRA_B
 
2017 avec l'Ifsttar - Twitter
2017 avec l'Ifsttar - Twitter2017 avec l'Ifsttar - Twitter
2017 avec l'Ifsttar - Twitter
 
Dossier de presse - Janvier 2018
Dossier de presse - Janvier 2018Dossier de presse - Janvier 2018
Dossier de presse - Janvier 2018
 
Trajectoire le magazine n°14 - décembre 2017
Trajectoire le magazine n°14 - décembre 2017Trajectoire le magazine n°14 - décembre 2017
Trajectoire le magazine n°14 - décembre 2017
 
Rapport d'activité 2016
Rapport d'activité 2016Rapport d'activité 2016
Rapport d'activité 2016
 
Trajectoire le magazine n°13 - Juin 2017
Trajectoire le magazine n°13 - Juin 2017Trajectoire le magazine n°13 - Juin 2017
Trajectoire le magazine n°13 - Juin 2017
 
Le programme de recherche et de développement de l'Ifsttar 2017
Le programme de recherche et de développement de l'Ifsttar 2017Le programme de recherche et de développement de l'Ifsttar 2017
Le programme de recherche et de développement de l'Ifsttar 2017
 
La Stratégie scientifique « précisée » de l'Ifsttar à 10 ans
La Stratégie scientifique « précisée » de l'Ifsttar à 10 ansLa Stratégie scientifique « précisée » de l'Ifsttar à 10 ans
La Stratégie scientifique « précisée » de l'Ifsttar à 10 ans
 
JTR 2017
JTR 2017JTR 2017
JTR 2017
 
2016 avec l'Ifsttar
2016 avec l'Ifsttar2016 avec l'Ifsttar
2016 avec l'Ifsttar
 
Les BFUP : 20 ans de croissance accompagnés par l’IFSTTAR
Les BFUP : 20 ans de croissance accompagnés par l’IFSTTARLes BFUP : 20 ans de croissance accompagnés par l’IFSTTAR
Les BFUP : 20 ans de croissance accompagnés par l’IFSTTAR
 
Comment étudier les comportements : présentation du simulateur vélo
Comment étudier les comportements : présentation du simulateur véloComment étudier les comportements : présentation du simulateur vélo
Comment étudier les comportements : présentation du simulateur vélo
 
Intermodalité vélo transport collectif - Le projet VERT
Intermodalité vélo transport collectif - Le projet VERTIntermodalité vélo transport collectif - Le projet VERT
Intermodalité vélo transport collectif - Le projet VERT
 

Recently uploaded

CALL ON ➥8923113531 🔝Call Girls Kesar Bagh Lucknow best Night Fun service 🪡
CALL ON ➥8923113531 🔝Call Girls Kesar Bagh Lucknow best Night Fun service  🪡CALL ON ➥8923113531 🔝Call Girls Kesar Bagh Lucknow best Night Fun service  🪡
CALL ON ➥8923113531 🔝Call Girls Kesar Bagh Lucknow best Night Fun service 🪡anilsa9823
 
Biopesticide (2).pptx .This slides helps to know the different types of biop...
Biopesticide (2).pptx  .This slides helps to know the different types of biop...Biopesticide (2).pptx  .This slides helps to know the different types of biop...
Biopesticide (2).pptx .This slides helps to know the different types of biop...RohitNehra6
 
Formation of low mass protostars and their circumstellar disks
Formation of low mass protostars and their circumstellar disksFormation of low mass protostars and their circumstellar disks
Formation of low mass protostars and their circumstellar disksSérgio Sacani
 
Chromatin Structure | EUCHROMATIN | HETEROCHROMATIN
Chromatin Structure | EUCHROMATIN | HETEROCHROMATINChromatin Structure | EUCHROMATIN | HETEROCHROMATIN
Chromatin Structure | EUCHROMATIN | HETEROCHROMATINsankalpkumarsahoo174
 
Animal Communication- Auditory and Visual.pptx
Animal Communication- Auditory and Visual.pptxAnimal Communication- Auditory and Visual.pptx
Animal Communication- Auditory and Visual.pptxUmerFayaz5
 
Nightside clouds and disequilibrium chemistry on the hot Jupiter WASP-43b
Nightside clouds and disequilibrium chemistry on the hot Jupiter WASP-43bNightside clouds and disequilibrium chemistry on the hot Jupiter WASP-43b
Nightside clouds and disequilibrium chemistry on the hot Jupiter WASP-43bSérgio Sacani
 
Spermiogenesis or Spermateleosis or metamorphosis of spermatid
Spermiogenesis or Spermateleosis or metamorphosis of spermatidSpermiogenesis or Spermateleosis or metamorphosis of spermatid
Spermiogenesis or Spermateleosis or metamorphosis of spermatidSarthak Sekhar Mondal
 
GBSN - Biochemistry (Unit 1)
GBSN - Biochemistry (Unit 1)GBSN - Biochemistry (Unit 1)
GBSN - Biochemistry (Unit 1)Areesha Ahmad
 
Biological Classification BioHack (3).pdf
Biological Classification BioHack (3).pdfBiological Classification BioHack (3).pdf
Biological Classification BioHack (3).pdfmuntazimhurra
 
TEST BANK For Radiologic Science for Technologists, 12th Edition by Stewart C...
TEST BANK For Radiologic Science for Technologists, 12th Edition by Stewart C...TEST BANK For Radiologic Science for Technologists, 12th Edition by Stewart C...
TEST BANK For Radiologic Science for Technologists, 12th Edition by Stewart C...ssifa0344
 
Isotopic evidence of long-lived volcanism on Io
Isotopic evidence of long-lived volcanism on IoIsotopic evidence of long-lived volcanism on Io
Isotopic evidence of long-lived volcanism on IoSérgio Sacani
 
Forensic Biology & Its biological significance.pdf
Forensic Biology & Its biological significance.pdfForensic Biology & Its biological significance.pdf
Forensic Biology & Its biological significance.pdfrohankumarsinghrore1
 
Lucknow 💋 Russian Call Girls Lucknow Finest Escorts Service 8923113531 Availa...
Lucknow 💋 Russian Call Girls Lucknow Finest Escorts Service 8923113531 Availa...Lucknow 💋 Russian Call Girls Lucknow Finest Escorts Service 8923113531 Availa...
Lucknow 💋 Russian Call Girls Lucknow Finest Escorts Service 8923113531 Availa...anilsa9823
 
Pests of cotton_Borer_Pests_Binomics_Dr.UPR.pdf
Pests of cotton_Borer_Pests_Binomics_Dr.UPR.pdfPests of cotton_Borer_Pests_Binomics_Dr.UPR.pdf
Pests of cotton_Borer_Pests_Binomics_Dr.UPR.pdfPirithiRaju
 
Raman spectroscopy.pptx M Pharm, M Sc, Advanced Spectral Analysis
Raman spectroscopy.pptx M Pharm, M Sc, Advanced Spectral AnalysisRaman spectroscopy.pptx M Pharm, M Sc, Advanced Spectral Analysis
Raman spectroscopy.pptx M Pharm, M Sc, Advanced Spectral AnalysisDiwakar Mishra
 
DIFFERENCE IN BACK CROSS AND TEST CROSS
DIFFERENCE IN  BACK CROSS AND TEST CROSSDIFFERENCE IN  BACK CROSS AND TEST CROSS
DIFFERENCE IN BACK CROSS AND TEST CROSSLeenakshiTyagi
 
Hire 💕 9907093804 Hooghly Call Girls Service Call Girls Agency
Hire 💕 9907093804 Hooghly Call Girls Service Call Girls AgencyHire 💕 9907093804 Hooghly Call Girls Service Call Girls Agency
Hire 💕 9907093804 Hooghly Call Girls Service Call Girls AgencySheetal Arora
 
GBSN - Microbiology (Unit 1)
GBSN - Microbiology (Unit 1)GBSN - Microbiology (Unit 1)
GBSN - Microbiology (Unit 1)Areesha Ahmad
 

Recently uploaded (20)

CALL ON ➥8923113531 🔝Call Girls Kesar Bagh Lucknow best Night Fun service 🪡
CALL ON ➥8923113531 🔝Call Girls Kesar Bagh Lucknow best Night Fun service  🪡CALL ON ➥8923113531 🔝Call Girls Kesar Bagh Lucknow best Night Fun service  🪡
CALL ON ➥8923113531 🔝Call Girls Kesar Bagh Lucknow best Night Fun service 🪡
 
Biopesticide (2).pptx .This slides helps to know the different types of biop...
Biopesticide (2).pptx  .This slides helps to know the different types of biop...Biopesticide (2).pptx  .This slides helps to know the different types of biop...
Biopesticide (2).pptx .This slides helps to know the different types of biop...
 
Formation of low mass protostars and their circumstellar disks
Formation of low mass protostars and their circumstellar disksFormation of low mass protostars and their circumstellar disks
Formation of low mass protostars and their circumstellar disks
 
Chromatin Structure | EUCHROMATIN | HETEROCHROMATIN
Chromatin Structure | EUCHROMATIN | HETEROCHROMATINChromatin Structure | EUCHROMATIN | HETEROCHROMATIN
Chromatin Structure | EUCHROMATIN | HETEROCHROMATIN
 
Animal Communication- Auditory and Visual.pptx
Animal Communication- Auditory and Visual.pptxAnimal Communication- Auditory and Visual.pptx
Animal Communication- Auditory and Visual.pptx
 
CELL -Structural and Functional unit of life.pdf
CELL -Structural and Functional unit of life.pdfCELL -Structural and Functional unit of life.pdf
CELL -Structural and Functional unit of life.pdf
 
Nightside clouds and disequilibrium chemistry on the hot Jupiter WASP-43b
Nightside clouds and disequilibrium chemistry on the hot Jupiter WASP-43bNightside clouds and disequilibrium chemistry on the hot Jupiter WASP-43b
Nightside clouds and disequilibrium chemistry on the hot Jupiter WASP-43b
 
The Philosophy of Science
The Philosophy of ScienceThe Philosophy of Science
The Philosophy of Science
 
Spermiogenesis or Spermateleosis or metamorphosis of spermatid
Spermiogenesis or Spermateleosis or metamorphosis of spermatidSpermiogenesis or Spermateleosis or metamorphosis of spermatid
Spermiogenesis or Spermateleosis or metamorphosis of spermatid
 
GBSN - Biochemistry (Unit 1)
GBSN - Biochemistry (Unit 1)GBSN - Biochemistry (Unit 1)
GBSN - Biochemistry (Unit 1)
 
Biological Classification BioHack (3).pdf
Biological Classification BioHack (3).pdfBiological Classification BioHack (3).pdf
Biological Classification BioHack (3).pdf
 
TEST BANK For Radiologic Science for Technologists, 12th Edition by Stewart C...
TEST BANK For Radiologic Science for Technologists, 12th Edition by Stewart C...TEST BANK For Radiologic Science for Technologists, 12th Edition by Stewart C...
TEST BANK For Radiologic Science for Technologists, 12th Edition by Stewart C...
 
Isotopic evidence of long-lived volcanism on Io
Isotopic evidence of long-lived volcanism on IoIsotopic evidence of long-lived volcanism on Io
Isotopic evidence of long-lived volcanism on Io
 
Forensic Biology & Its biological significance.pdf
Forensic Biology & Its biological significance.pdfForensic Biology & Its biological significance.pdf
Forensic Biology & Its biological significance.pdf
 
Lucknow 💋 Russian Call Girls Lucknow Finest Escorts Service 8923113531 Availa...
Lucknow 💋 Russian Call Girls Lucknow Finest Escorts Service 8923113531 Availa...Lucknow 💋 Russian Call Girls Lucknow Finest Escorts Service 8923113531 Availa...
Lucknow 💋 Russian Call Girls Lucknow Finest Escorts Service 8923113531 Availa...
 
Pests of cotton_Borer_Pests_Binomics_Dr.UPR.pdf
Pests of cotton_Borer_Pests_Binomics_Dr.UPR.pdfPests of cotton_Borer_Pests_Binomics_Dr.UPR.pdf
Pests of cotton_Borer_Pests_Binomics_Dr.UPR.pdf
 
Raman spectroscopy.pptx M Pharm, M Sc, Advanced Spectral Analysis
Raman spectroscopy.pptx M Pharm, M Sc, Advanced Spectral AnalysisRaman spectroscopy.pptx M Pharm, M Sc, Advanced Spectral Analysis
Raman spectroscopy.pptx M Pharm, M Sc, Advanced Spectral Analysis
 
DIFFERENCE IN BACK CROSS AND TEST CROSS
DIFFERENCE IN  BACK CROSS AND TEST CROSSDIFFERENCE IN  BACK CROSS AND TEST CROSS
DIFFERENCE IN BACK CROSS AND TEST CROSS
 
Hire 💕 9907093804 Hooghly Call Girls Service Call Girls Agency
Hire 💕 9907093804 Hooghly Call Girls Service Call Girls AgencyHire 💕 9907093804 Hooghly Call Girls Service Call Girls Agency
Hire 💕 9907093804 Hooghly Call Girls Service Call Girls Agency
 
GBSN - Microbiology (Unit 1)
GBSN - Microbiology (Unit 1)GBSN - Microbiology (Unit 1)
GBSN - Microbiology (Unit 1)
 

Full-scale testing of prefabricated slabs for inductive electric vehicle charging

  • 1. Transport Research Arena 2014, Paris Full scale test on prefabricated slabs for electrical supply by induction of urban transport systems Mai-Lan Nguyena* , Pierre Hornycha , Jean-Pierre Kerzréhoa , Sergio Perezb a LUNAM Université, IFSTTAR, Materials and Structures Department, Route de Bouaye, 44344 Bouguenais, France b Bombardier Transportation, Neustadter Straße 62, 68309 Mannheim, Germany Abstract Advanced and innovative technologies are increasingly used in transport infrastructures, especially in urban transportation. Recently, Bombardier Transport has developed a new system for supply by induction of electrical public transportation vehicles. The proposed solution consists in integrating the electrical supply cables, for creating an electromagnetic induction field, in a prefabricated concrete slab implemented in the road. A key aspect of the project is the design and resistance to heavy traffic of the proposed modular pavement. For this purpose, it was decided to carry out a full scale test on the accelerated pavement testing facility of IFSTTAR Nantes. Five different prototype slabs are tested, differing by the width of the slab, and the thickness of the concrete cover above the supply cables. The experiment consists of subjecting the slabs to one million passes with a dual wheel load of 65 kN and monitoring the mechanical behaviour of the slabs pavement by measuring strains and displacements in chosen points. The paper presents the design of the proposed prefabricated slabs pavement, the installation procedure of these slabs and first results of the current full scale test. Keywords: prefabricated road slab; full scale test; induction; electric vehicle supply; urban transport system. Résumé Les technologies avancées et innovantes sont de plus en plus utilisées dans les infrastructures de transport, en particulier dans les transports urbains. Bombardier Transport a récemment développé un nouveau système d'alimentation par induction des véhicules électriques. La solution proposée intègre dans une dalle en béton préfabriquée installée dans la chaussée, les câbles d'alimentation électrique permettant de créer un champ d'induction électromagnétique. Un aspect clé du projet est le concept et la résistance au trafic lourd du module proposé. A cet effet, il a été décidé de réaliser un essai en vraie grandeur avec le simulateur de trafic routier lourd, le manège de fatigue de l'IFSTTAR à Nantes. Cinq dalles prototypes ont été testées, différenciées par leur largeur et par l'épaisseur de la couverture en béton au-dessus des câbles. L’expérience consiste à soumettre ces dalles à un million de passages du jumelage de 65 kN et à suivre le comportement mécanique de la chaussée des dalles en mesurant les déformations et les déplacements en des points choisis. Cet article présente le concept de la chaussée expérimentale en dalles préfabriquées, la solution de mise en place et le suivi du comportement de ces dalles dans l’essai manège en cours. Mots-clé: dalle chaussée préfabriquée ; essai en vraie grandeur ; induction ; alimentation de véhicule électrique ; système de transport urban * Tel.: +33-2-4084-5715; fax: +33-2-4084-5994. E-mail address: mai-lan.nguyen@ifsttar.fr.
  • 2. Nguyen Mai-Lan / Transport Research Arena 2014, Paris 2 1. Introduction Electric road becomes more realistic. Among the technologies under development, inductive charging represents a promising technique and is being experimented in Germany and Belgium (Beeldens, 2013). In addition to the advantages of clean solutions (no use of ordinary fuels, such as petrol or diesel, no local emissions), inductive charging technology is practical to use and may contribute to minimizing different types of urban pollution (air, visibility and noise pollutions). It also solves the problem of autonomy of electric vehicles (EV) and reduces their weight by reducing the battery size, in particular for public transport vehicles.The development of this new technology for transport infrastructures matches the ideas of current projects in France and Europe: the 5th Generation Road, the European project Forever Open Road, and the Infravation programme. Recently, Bombardier Transportation has developed a new system for supply by inductive charging of electric buses. The idea is to implement the inductive charging system in the road at bus stops for recharging while passengers get on and off. This implementation is based on the principle of modular construction consisting of prefabricated elements ready to be installed simply and quickly. In particular, the component responsible for the inductive power transfer is integrated in a prefabricated concrete slab which is implemented in the road. The slab contains electrical supply cables, for creating a magnetic field. A power receiver system installed underneath the EV, when the last one parks on the induction segment, turns this magnetic field into an electric current that feeds the vehicle traction system. A key aspect of the project is the design and resistance to heavy traffic of the proposed modular pavement. For this purpose, it was decided to carry out a full scale test on the accelerated pavement testing (APT) facility of IFSTTAR Nantes (fig. 1). It is a heavy road traffic simulator, dedicated to full-scale pavement experiments. Since 2000s, the APT facility has demonstrated its capacity for testing of urban infrastructure solutions (de Larrard et al., 2013; Fort, 2013). Fig. 1. The IFSTTAR’s APT facility Five different slab prototypes are tested, differing by the width of the slab, and the thickness of the concrete cover above the supply cables. The slabs are instrumented using strain gages, displacement transducers, and geophones, to verify their strains and displacements under loading. Electrical measurements are also made to verify the performance of the cables throughout the experiment. The experiment consists of subjecting the slabs to one million passes with a dual wheel load of 65 kN (corresponding to half of the French standard axle load of 130 kN, which is the highest in the world). From February 1st to April 4th 2013, a first period of loading was performed with approximately 260 000 traffic passages. The paper presents the design and construction of the proposed prefabricated slab pavement, results of the first period of the current full scale test, and their perspectives, in terms of deployment of this technology. 2. Design of the full scale test The proposed solution, to ensure the implementation of the inductive charging system in the road, consists of prefabricated concrete slabs, containing the electrical supply cables. These slabs, reinforced with glass fibre reinforced polymer (GFRP) rebars, have a length of 5 m, a thickness of 0.25 m, and are intended to be incorporated into a pavement structure. The power supply of each slab is independent and is activated only by passing of an applicable EV when it is detected by an antenna system.
  • 3. Nguyen Mai-Lan / Transport Research Arena 2014, Paris IFSTTAR has been asked to work on the design of the pavement structure to receive these prefabricated slabs and then test them on the APT facility. The solution that has been proposed is to provide a bituminous foundation layer of 8 cm thickness, then place on it the prefabricated slabs using aluminium supports of adjustable height, placed at the corners of the slabs to control precisely the final level of the slabs. A high performance, non-shrinking, cement slurry is placed in the space remaining below the slab (about 2 cm) to ensure a good contact between the slab and the foundation support. After the placement of the slabs, the space around the slabs was filled with cement concrete. Dowels made of glass fibres are used to connect the slabs with the surrounding concrete pavement in the longitudinal direction. A pre-cracking in the transverse direction, extending the joints between the slabs and the concrete fill, was made in the concrete fill. For that purpose, the concrete has been sawn, one day after its casting, to a third of its depth, to avoid the appearance of uncontrolled cracks. A transverse profile of the pavement structure, without concrete fill around the slab, is shown on fig. 2. 8 cm bituminous base Platform 150 ÷ 200 MPa 2 cm cement slurry 25 cm aluminium supports Prefab. slab Component responsible for inductive power transfer Fig. 2. Transverse profile of the tested pavement. The experimentation of inductive charging system integrated on prefabricated slabs is performed on a half-ring of the circular test track (fig. 3). A classical bituminous pavement is placed on the other half-ring for proper rotation of the traffic simulator. Five slab prototypes, including three standard slabs of 5 m  2.4 m and two narrow slabs of 5 m  1.25 m, are being tested. The narrow size is intended for optimizing precast and transport processes. These two narrow slabs have eight GFRP rebars coming out of the slabs on the longitudinal sides. Pre-cracking was created, in the longitudinal direction on both sides of the narrow slabs at the end of these rebars. Both standard and narrow slabs include the same module containing the electrical supply cables, which is positioned in the central part of the slab. On the test track, the wheel loads run at a fixed radius, of 19 m. The slabs have been placed at different transversal positions on the test track in order to apply the loads either on the centre or on the edge of the slab. The thickness of the concrete cover above the supply cables is also an important parameter, for the resistance of the slabs. On the standard slabs, two levels of thickness have been tested: 4 cm on the two first slabs, and 5 cm on the third one. On the two narrow slabs, the thickness of the top concrete layer is 3.5 cm and 4 cm respectively. Table 1 summarises the testing configuration of these slabs. Direction ofrotation Pre-cracking Concretepavement Slab A Slab E Slab D Slab C Slab B Old concrete slab pavement Bituminous pavement Other components R 19 m Fig. 3. Plan of the circular test track
  • 4. Nguyen Mai-Lan / Transport Research Arena 2014, Paris 4 Table 1. Testing configuration of slab prototypes Slab Slab dimensions (m) Lateral position of traffic along the slab Thickness of the concrete cover (cm) Slab A 52.40.25 middle 5.0 Slab B 52.40.25 edge 5.0 Slab C 52.40.25 middle 4.0 Slab D 51.250.25 middle 3.5 Slab E 51.250.25 edge 4.0 3. Construction of the full scale test and solution for installation of the prefabricated slabs The construction of the test track required several phases. After removing the existing pavement to the level of the subgrade platform, it has been adjusted at the right level for installation of the prefabricated slabs. The bearing capacity of the existing platform was then measured at different positions by means of the dynamic plate test, which gave values between 150 and 200 MPa. To test the mechanical behaviour and resistance of the prefabricated slabs under heavy traffic, stabilization of these slabs is very important. For the construction of the proposed structure (fig. 1), the following procedure was applied for the first four slabs (A, B, C and D). For slab E, in order to simulate better actual conditions on construction sites in urban areas, i.e. limited space and time, a slightly different procedure was tested. 3.1. Procedure for installation of the slabs A, B, C and D  Realization of an 8 cm thick bituminous subbase layer. This step was needed on the APT site. However, on an actual site, it could be another support, e.g. milling of the existing pavement.  Fine milling of this base layer to obtain a first calibration of the final level of the prefabricated slab.  Positioning of aluminium supports at the four corners of each slab. At each corner, several support plates of different thicknesses were used, firstly a thick plate of 15 mm, then thinner plates (of 1 mm minimum). The level of these supports was verified (taking into account the slab thickness) by leveling measurements, in order to reach precisely the final level of the slab.  Placement of the slab on the aluminium supports using a crane to ensure the final level of the slab.  Construction of a formwork around the slab for receiving the cement slurry.  Lifting of the slab and filling of the formwork with the cement slurry; before replacing the slab on top of the cement slurry. To ensure proper filling of the cement slurry, several blowholes have been created in the slabs in the prefabrication, to allow entrapped air to escape and the cement slurry to be well distributed during installation of the slabs. These blowholes were clogged at the end of the process. To validate this procedure and check the stability of the slab under moving of a heavy vehicle, a feasibility test was performed on slab A (fig. 4). The test was carried out 18 days after placement of the slab. It consisted of moving slowly the half axle of a heavy vehicle of about 20 tons on the slab and measuring deflection of the slab at different positions: at the four corners and in the middle of each lateral edge. Three load levels of the half axle were applied: 66 kN, 76 kN and 96 kN. The measured maximum deflections, which increased proportionally with the load level, were 0.10 mm, 0.11 mm and 0.16 mm respectively. These deflection levels remained small and were consistent with estimations made using the pavement design software Alizé-Lcpc. After installation of the slabs, the remaining space around the slabs was filled using a cement concrete of high performance to form a continuous pavement.
  • 5. Nguyen Mai-Lan / Transport Research Arena 2014, Paris Fig. 4. Feasibility test with a truck. 3.2. Procedure for installation of slab E The same principle of slab stabilization using cement slurry was used, but two main points were modified:  To approach the actual conditions of insertion of the prefabricated slab into an existing pavement with limited space, the concrete fill, next to the upstream end of the slab, was placed before installation of the slab. Several grooves were made in the concrete fill to allow insertion of the dowels.  In order to accelerate the installation of the slab, a faster procedure of stabilization of the slabs was applied. The slab E was placed on supports, the level of which could be adjusted using three screws. The cement slurry was then injected under pressure (fig. 5) directly under the slab. This procedure avoided lifting the slab again before filling of the cement slurry, which reduces the use of the crane on the construction site. After installation of the slabs, the remaining space around the slab was filled using a high performance cement concrete as realized previously. Fig. 5. Installation of prefabricated slab with injection of cement slurry. 4. Test conditions and parameters measured during the test 4.1. Test conditions The test program consists in applying one million loads, with dual wheels, loaded at 50 kN for the first 100 000 passages and 65 kN for the remaining of the test. This represents a traffic of about 150 buses per day for 20 years, and corresponds to 250 000 rotations of the four arms carousel. Loading is applied at the radius of 19 m and thus the total perimeter of the test track circuit is approximately 120 m. A reduced lateral wandering of 0.8 m wide of the load is applied in order to simulate the channelized traffic of buses. The speed of rotation of the carousel applied under normal conditions is 5 rounds/minute, which corresponds to a tangential velocity of about 35.8 km/h at a radius of 19 m. Lower speeds have also been applied for specific Displacement transducer
  • 6. Nguyen Mai-Lan / Transport Research Arena 2014, Paris 6 measurements. However, it was decided not to run at higher speeds, in order to avoid dynamic effects in the loading modules of the traffic simulator, which could occur due to the less even surface of the concrete slab pavement compared to a conventional bituminous pavement. 4.2. Parameters measured during the test The instrumentation of the test comprises mainly surface measurements close to the joints between the slabs and the concrete fill. These measurements monitor the movements of the slabs under moving loads. Three measurement systems are used:  A Benkelman beam with two LVDTs (Linear Variable Differential Transducer) measures the deflection on both sides of each joint, compared to fixed supports located about 2 m away from the measured points. This system can make measurements only at slow speed (1 round/minute). It can be moved to follow in turn the deflections at different joints.  A LVDT, installed next to each joint, measures the relative movement, i.e. the faulting effect, between the slab and the concrete fill. This equipment can operate regardless of the speed of the traffic simulator.  To measure the deflections at high speeds, four geophones were installed on slab C. These geophones, fixed on both sides of each joint of the slab C, measure the speed of the vertical displacement of the measured points under moving loads, which allows determining, by integration, the deflections at these points. Periodic FWD (Falling Weight Deflectometer) measurements will be performed to evaluate the response of the prefabricated slabs at different stages of the experiment. Due to the difficulty of instrumenting on site, only two strain gauges were glued on the lower surface of the slab A, near the middle of each lateral edge, in the longitudinal direction. These gauges allow measuring the deformation of the slab at these positions. Regarding the subgrade, three strain gauges were installed vertically at the top of the subgrade layer, under each of the three slabs B, C and D, to follow the evolution of vertical deformations of the subgrade. Two temperature profiles, one in slab B and the other one in the concrete fill located between slabs B and C, are being recorded using thermocouple sensors placed at different depth levels, i.e. 0, - 12, - 24, - 29, - 34 and - 44 cm. Two other thermocouples are used to measure the air temperature in sunlight and in the shade. The functioning of the integrated electric cables is also controlled at different stages of the test. At the end of the test, it is planned to carry out detailed investigations, to core specimens to check different aspects such as: contact conditions under the slabs or in the areas containing electric cables, possible deterioration or cracking of the slabs, mechanical properties of concrete material and cement slurry. 5. First results and interpretation Results presented in this paper concern the first period of the test with approximately 260 000 loads. Measurements by different sensors were recorded at 10 000, 50 000, 100 000 and 260 000 loads. During this first period of investigation, temperatures measured on the surface of the concrete slabs ranged between -3 °C and 22 °C. This period was also marked by a high rainfall level. Visual surveys were carried out regularly. Up to now, no degradation has been observed on the surface of the slabs. Evolution of deflections and vertical strains measured respectively on the upper surface of the slabs and in the platform under the slabs, as well as an example of horizontal strain of a slab measured on its lower surface are shown below. 5.1. Deflections of concrete slabs pavement measured at joints Deflections measured with the double LVDT beam on both sides of the joints between the slabs and the concrete fill, at 100 000 loads (the beginning of application of the standard load of 65 kN) and then at 260 000 loads are
  • 7. Nguyen Mai-Lan / Transport Research Arena 2014, Paris summarised in fig.6. These measurements were carried out successively at all joints, by moving the beam on each joint, over a period of about two hours. At 100 000 loads, it is observed that:  Deflection signals are very similar at all joints, and there is very little difference between the measurements on the concrete fill side and on the prefabricated slab side, indicating good continuity of the pavement.  Deflection levels are small, between 0.06 and 0.12 mm. These values are in agreement with calculations using the Alizé-LCPC pavement design software (which assumes a continuous, jointless pavement), which gives a deflection of 0.11 mm.  However, we can note slightly higher deflections at the upstream joints of slabs B and D (in the direction of rotation of the loads). At 260 000 loads, measured deflections increase clearly, indicating possibly a decrease of rigidity of the support at the joints:  At most joints, deflections vary between 0.10 and 0.16 mm, and have the same level on both sides of the joint.  However, on the upstream joints of slabs B and D, the differences between the measurements on the concrete fill and on the slabs increase significantly. This indicates higher slab faulting, confirming the observations done at 100 000 loads. Deflections measured on the slab side reach 0.25 mm for slab B and 0.20 mm for slab D. It can be seen that the faulting increases only at the upstream joints (of slabs B and D for the moment). This phenomenon can be explained by the fact that when the load reaches the upstream joint of the slab, it will create an impact (dynamic overload) due to the unevenness of the joint. The subgrade under the upstream part of the slab thus deteriorates more rapidly, with increasing number of loads. When the load leaves the slab, the load variation is more gradual, and therefore, there is no dynamic impact on the downstream part of the slab. -0.3 -0.25 -0.2 -0.15 -0.1 -0.05 0 0.05 0.1 0 5 10 15 20 25 30 35 40 45 50 Deflection(mm) Distance (m) Measurement on the concrete fill boder Measurement on the slab border A B C D E Measurement 14/03/2013,100 000 loads 65 kN; 7.2 km/h; T(surface) = 4.5 oC Direction of rotation -0.3 -0.25 -0.2 -0.15 -0.1 -0.05 0 0.05 0.1 0 5 10 15 20 25 30 35 40 45 50 Deflection(mm) Distance (m) Measurement on the concrete fill boder Measurement on the slab border A B C D E Measurement 04/04/2013,260 000 loads 65 kN; 7.2 km/h; T(surface) = 8.5 oC Fig. 6. Deflection measured by means of two LVDTs mounted on a Benkelman beam, on both sides of each slab joint: (a) at 100 000 loads; (b) at 260 000 loads
  • 8. Nguyen Mai-Lan / Transport Research Arena 2014, Paris 8 5.2. Vertical subgrade strains under the prefabricated slabs Fig. 7 presents vertical strains of the subgrade under the three slabs B, C and D, respectively at 100 000 loads and then at 260 000 loads. These measurements were recorded during only one rotation of the load. At 100 000 loads:  At this stage, the vertical strains under each slab are still more or less similar.  Vertical strains under slab B (where the loads pass near the edge) are larger than the ones under slab C (where the loads pass in the middle). This result indicates that passing of traffic near the edge of the prefabricated modular slab, which will be the normal condition of bus operation, leads to higher strains (and settlements) of the subgrade beneath the slab.  Even though the narrow slab D (with loads passing the middle) has eight GFRP rebars used to transfer the load to the surrounding concrete fill, vertical strains under this slab are more visible than under the slab C. At 260 000 loads:  Vertical strains under each slab increase mostly at both ends of the slab (indicating that the faulting of the slabs increases).  However, under the upstream end of slabs B and D, the maximum vertical strain is significantly higher than under the downstream end of the slabs. This confirms the results obtained for the deflection measurements, which indicate a more pronounced loss of stiffness of the subgrade near the upstream end of the slabs. -500 -400 -300 -200 -100 0 100 10 15 20 25 30 35 Verticalstrain(mm/m) Distance (m) ZB1 ZB2 ZB3 ZC4 ZC5 ZC6 ZD7 ZD8 ZD9 Measurement 14/03/2013, 100 000 loads 65 kN; 7.2 km/h; T(surface) = 4.5 oC B C D -500 -400 -300 -200 -100 0 100 10 15 20 25 30 35 Verticalstrain(mm/m) Distance (m) ZB1 ZB2 ZB3 ZC4 ZC5 ZC6 ZD7 ZD8 ZD9 Measurement 04/04/2013, 260 000 loads 65 kN; 7.2 km/h; T(surface) = 8.5 oC B C D Fig. 7. Vertical strain measurements by means of strain gauges installed in the subgrade under each slab: (a) at 100 000 loads; (b) at 260 000 loads 5.3. Horizontal strains at bottom of the prefabricated slab An example of typical signals measured by means of a strain gauge glued on the lower surface of slab A is plotted in fig. 8. In this measurement, the four load modules (all loaded at 65 kN) of the traffic simulator passed at four different lateral positions of the slab (corresponding to radii of 18.5, 18.7, 18.9 and 19.1 m), and rotated at a speed of 5 rounds/minute. The strain gauge was placed close to the inner lateral edge of the slab, which corresponds to a radius of 17.85 m. Thus, the closer the load approaches the position of the gauge, the higher the
  • 9. Nguyen Mai-Lan / Transport Research Arena 2014, Paris strain level. However, the strain levels are very small (the maximum value is 9 μm/m when the load passed at the radius of 18.5 m). These low strain levels indicate no fatigue due to tensile strains at the bottom of the slabs. -4 -2 0 2 4 6 8 10 20 40 60 80 100 120 140 Horizontalstrain(mm/m) Distance (m) R=19.1 m R=18.9 m R=18.7 m R=18.5 m Fig. 8. Horizontal strain measured on the lower surface of the slab A when the four loads (65 kN each) passed at four different lateral positions of the slab at 260 000 loads. The results of these different measurements give a good idea of the mechanical response of the slabs. This will enable comparisons with finite element calculations, using the Cesar-Lcpc software (Humbert et al., 2005) to accurately reproduce the behavior of the prefabricated concrete slabs, the key element of the inductive charging solution for EVs in urban areas, and to evaluate their durability. 6. Conclusions and perspectives This experiment confirms the interest of the IFSTTAR's APT facility for testing an innovative solution of electrified road, which represents a very promising solution for power supply of EVs in urban areas. A solution of pavement support to receive the prefabricated slabs containing the charging system for electric vehicles by induction was designed and tested on the heavy traffic simulator. A practical procedure for the implementation of these slabs in urban areas has also been studied and validated by a feasibility test. The full scale experiment, which aims to test these prefabricated slabs with a traffic of one million dual wheel half axles loaded at 65 kN, started in February 2013. At this stage, 260 000 loads have been realized. Measurements taken during this first period show satisfactory results:  The deflection of the slabs and the faulting level at joints remain small and consistent with simulations. Only a slight increase of faulting of two slab ends with the evolution of traffic is observed.  The power supply systems of the five tested slabs continue to function properly, without any damage, after 260 000 loads.  At this stage, no deterioration was observed on the surface of the slabs. The test will be continued up to one million loads. From 500 000 loads, it is planned to install on the test track a new precast slab with a different design. A detailed assessment of the slabs behaviour will be conducted at the end of the experiment, and will allow validation and improvement of this particular Bombardier’s solution for inductive EVs recharging system integrated on a specific designed prefabricated slab. Under development since 2008, the inductive charging technology is firstly in passenger operation in 2013 in Braunschweig (Germany). This next generation of electric mobility solutions will be provided for all forms of electric vehicles, including trams, buses, commercial vehicles, taxis and cars operating in urban areas. References Beeldens A. (2013). Inductive Charging: projet de charge par induction de véhicules électriques. Revue Générale des Routes et des Aménagements, n°910. de Larrard F., Sedran T., Balay J.M. (2012). Removable Urban Pavements: An innovative, sustainable technology. International Journal of Pavement Engineering, Vol. 14, Issue 1, 1 - 11.
  • 10. Nguyen Mai-Lan / Transport Research Arena 2014, Paris 10 Fort T. (2013). Evaluation sous trafic lourds des systèmes d’alimentation des tramways par le sol – Essai Alstom, Revue Générale des Routes et des Aménagements, n°914. Humbert, P., Dubouchet, A., Fezans, G., & Remaud, D. (2005). CESAR-LCPC, un progiciel de calcul dédié au génie civil. Bulletin de liaison des Laboratoires des Ponts et Chaussées, Numéro spécial CESAR-LCPC, (256- 257), 7-37. The IFSTTAR’s Alizé-LCPC software for the thickness design of pavement according to the French rational method: http://www.lcpc.fr/english/products/lcpc-products-alize-lcpc-routes/