SlideShare a Scribd company logo
1 of 26
Download to read offline
6–1
Chapter 6 - Developing a Project Plan
6–2
Developing the Project Plan
• The Project Network
–A flow chart that graphically depicts the sequence,
interdependencies, and start and finish times of the
project job plan of activities that is the critical path
through the network.
• Provides the basis for scheduling labor and equipment.
• Enhances communication among project participants.
• Provides an estimate of the project’s duration.
• Provides a basis for budgeting cash flow.
• Identifies activities that are critical.
• Highlights activities that are “critical” and can not be delayed.
• Help managers get and stay on plan.
6–3
Constructing a Project Network
• Terminology
–Activity: an element of the
project that requires time.
–Merge Activity: an activity that
has two or more preceding
activities on which it depends.
–Parallel (Concurrent) Activities:
Activities that can occur
independently and, if desired,
not at the same time.
A
C
D
B
6–4
Constructing a Project Network (cont’d)
• Terminology
–Path: a sequence of connected, dependent activities.
–Critical path: the longest path through the activity
network that allows for the completion of all project-
related activities; the shortest expected time in which
the entire project can be completed. Delays on the
critical path will delay completion of the entire project.
A B D
(Assumes that minimum of A + B > minimum of C in length of times to complete activities.)
C
6–5
Constructing a Project Network (cont’d)
• Terminology
–Event: a point in time when an activity is started
or completed. It does not consume time.
–Burst Activity: an activity that has more than one
activity immediately following it (more than one
dependency arrow flowing from it).
• Two Approaches
–Activity-on-Node (AON)
• Uses a node to depict an activity.
–Activity-on-Arrow (AOA)
• Uses an arrow to depict an activity.
B
D
A C
6–6
Basic Rules to Follow in Developing
Project Networks
1. Networks typically flow from left to right.
2. An activity cannot begin until all preceding
connected activities are complete.
3. Arrows indicate precedence and flow
and can cross over each other.
4. Each activity must have a unique identify number
that is greater than any of its predecessor activities.
5. Looping is not allowed.
6. Conditional statements are not allowed.
7. Use common start and stop nodes.
6–7
Activity-on-Node Fundamentals
FIGURE 6.2
6–8
Activity-on-Node Fundamentals (cont’d)
FIGURE 6.2 (cont’d)
6–9
Network Information
TABLE 6.1
6–10
Koll Business Center—Partial Network
FIGURE 6.3
6–11
Koll Business Center—Complete Network
FIGURE 6.4
6–12
Network Computation Process
• Forward Pass—Earliest Times
–How soon can the activity start? (early start—ES)
–How soon can the activity finish? (early finish—EF)
–How soon can the project finish? (expected time—ET)
• Backward Pass—Latest Times
–How late can the activity start? (late start—LS)
–How late can the activity finish? (late finish—LF)
–Which activities represent the critical path?
–How long can activity be delayed? (slack or float—SL)
6–13
Network Information
TABLE 6.2
6–14
Activity-on-Node Network
FIGURE 6.5
6–15
Activity-on-Node Network Forward Pass
FIGURE 6.6
6–16
Forward Pass Computation
• Add activity times along each path in the
network (ES + Duration = EF).
• Carry the early finish (EF) to the next activity
where it becomes its early start (ES) unless…
• The next succeeding activity is a merge activity,
in which case the largest EF of all preceding
activities is selected.
6–17
Activity-on-Node Network Backward Pass
FIGURE 6.7
6–18
Backward Pass Computation
• Subtract activity times along each path in the
network (LF - Duration = LS).
• Carry the late start (LS) to the next activity
where it becomes its late finish (LF) unless
• The next succeeding activity is a burst activity, in
which case the smallest LF of all preceding
activities is selected.
6–19
Determining Free Slack (or Float)
• Free Slack (or Float)
–Is the amount of time an activity can be delayed after
the start of a longer parallel activity or activities.
–Is how long an activity can exceed its early finish date
without affecting early start dates of any successor(s).
–Allows flexibility in scheduling scarce resources.
• Sensitivity
–The likelihood the original critical path(s) will change
once the project is initiated.
–The critical path is the network path(s) that has (have)
the least slack in common.
6–20
Activity-on-Node Network with Slack
FIGURE 6.8
6–21
Free Slack Example
FIGURE 6.9
6–22
Illogical Loop
FIGURE 6.10
6–23
Extended Network Techniques
to Come Close to Reality
• Laddering
–Activities are broken into segments so the following
activity can begin sooner and not delay the work.
6–24
Example of Laddering Using
Finish-to-Start Relationship
FIGURE 6.13
6–25
Activity-on-Arrow Network Building Blocks
FIGURE A6.1
6–26
Activity-on-Arrow Network Fundamentals
FIGURE A6.2

More Related Content

What's hot

Chap 6 Developing A Project Plan
Chap 6 Developing A Project PlanChap 6 Developing A Project Plan
Chap 6 Developing A Project Planproject management
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Abhishek Pachisia
 
An introduction to project management: Learning the basics
An introduction to project management:  Learning the basicsAn introduction to project management:  Learning the basics
An introduction to project management: Learning the basicsPaul Di Gangi
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALVismay Shah
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Project Feasibility [DECEMBER 2006]
Project Feasibility [DECEMBER 2006]Project Feasibility [DECEMBER 2006]
Project Feasibility [DECEMBER 2006]Fahad Mahmud Mirza
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control ScheduleAnand Bobade
 
Project management Using Pert
Project management Using PertProject management Using Pert
Project management Using PertVishnu RC Vijayan
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Zulfiquer Ahmed Amin
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 pptahsanrabbani
 

What's hot (20)

Chap 6 Developing A Project Plan
Chap 6 Developing A Project PlanChap 6 Developing A Project Plan
Chap 6 Developing A Project Plan
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 
An introduction to project management: Learning the basics
An introduction to project management:  Learning the basicsAn introduction to project management:  Learning the basics
An introduction to project management: Learning the basics
 
Scheduling
SchedulingScheduling
Scheduling
 
Project Management Tools
Project Management ToolsProject Management Tools
Project Management Tools
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
Assignment project scheduling
Assignment project schedulingAssignment project scheduling
Assignment project scheduling
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
Pert
PertPert
Pert
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIAL
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Project Feasibility [DECEMBER 2006]
Project Feasibility [DECEMBER 2006]Project Feasibility [DECEMBER 2006]
Project Feasibility [DECEMBER 2006]
 
Resource allocation
Resource allocationResource allocation
Resource allocation
 
Chap 6.6 Control Schedule
Chap 6.6 Control ScheduleChap 6.6 Control Schedule
Chap 6.6 Control Schedule
 
Project management Using Pert
Project management Using PertProject management Using Pert
Project management Using Pert
 
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
 
crashing of project
crashing of project crashing of project
crashing of project
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 

Similar to Develop a project plan with critical path analysis

PM Session 5
PM Session 5PM Session 5
PM Session 5dmdk12
 
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptxSession 9 - Project scheduling-PERT-CPM-Network diagram.pptx
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptxAlRashedinKawser2
 
Focus on CPM and Resp Matrix
Focus on CPM and Resp MatrixFocus on CPM and Resp Matrix
Focus on CPM and Resp Matrixdmdk12
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMMubashir Ali
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesSAJID ALI RUK
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management UploadBhuWan Khadka
 
ch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþttttttttttttttch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþttttttttttttttAbdisalamMohamud5
 
module-1 CME NETWORK ANALYSIS.pptx
module-1 CME NETWORK ANALYSIS.pptxmodule-1 CME NETWORK ANALYSIS.pptx
module-1 CME NETWORK ANALYSIS.pptxsurekha1287
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersIIMSE Edu
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptxNaimishKishor
 
المحاضرة السادسة: إعداد جدول المشروع
المحاضرة السادسة: إعداد جدول المشروعالمحاضرة السادسة: إعداد جدول المشروع
المحاضرة السادسة: إعداد جدول المشروعEgypt Scholars Inc.
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdfJerryHung19
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02kongara
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLSiddanna Balapgol
 
12 lecture project scheduling 4
12 lecture project scheduling 412 lecture project scheduling 4
12 lecture project scheduling 4Ahmad Basim Hamza
 

Similar to Develop a project plan with critical path analysis (20)

PM Session 5
PM Session 5PM Session 5
PM Session 5
 
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptxSession 9 - Project scheduling-PERT-CPM-Network diagram.pptx
Session 9 - Project scheduling-PERT-CPM-Network diagram.pptx
 
Focus on CPM and Resp Matrix
Focus on CPM and Resp MatrixFocus on CPM and Resp Matrix
Focus on CPM and Resp Matrix
 
6. Developing Project Plan.pptx
6. Developing Project Plan.pptx6. Developing Project Plan.pptx
6. Developing Project Plan.pptx
 
CHAPTER 6.pptx
CHAPTER 6.pptxCHAPTER 6.pptx
CHAPTER 6.pptx
 
Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPM
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
 
08. Project Time Management Upload
08. Project Time Management Upload08. Project Time Management Upload
08. Project Time Management Upload
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
02-Key Definitions .pdf
02-Key Definitions .pdf02-Key Definitions .pdf
02-Key Definitions .pdf
 
ch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþttttttttttttttch08 (1).pptttttttttttttttþtttttttttttttt
ch08 (1).pptttttttttttttttþtttttttttttttt
 
module-1 CME NETWORK ANALYSIS.pptx
module-1 CME NETWORK ANALYSIS.pptxmodule-1 CME NETWORK ANALYSIS.pptx
module-1 CME NETWORK ANALYSIS.pptx
 
PMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For BeginnersPMP Project Management Basics Tutorial For Beginners
PMP Project Management Basics Tutorial For Beginners
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
المحاضرة السادسة: إعداد جدول المشروع
المحاضرة السادسة: إعداد جدول المشروعالمحاضرة السادسة: إعداد جدول المشروع
المحاضرة السادسة: إعداد جدول المشروع
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
L2_Project_Management.pdf
L2_Project_Management.pdfL2_Project_Management.pdf
L2_Project_Management.pdf
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
 
12 lecture project scheduling 4
12 lecture project scheduling 412 lecture project scheduling 4
12 lecture project scheduling 4
 

Recently uploaded

Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...lizamodels9
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Serviceankitnayak356677
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...lizamodels9
 
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc.../:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...lizamodels9
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedKaiNexus
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creationsnakalysalcedo61
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | DelhiFULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | DelhiMalviyaNagarCallGirl
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 

Recently uploaded (20)

Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.Eni 2024 1Q Results - 24.04.24 business.
Eni 2024 1Q Results - 24.04.24 business.
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In.../:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
/:Call Girls In Indirapuram Ghaziabad ➥9990211544 Independent Best Escorts In...
 
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc.../:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
/:Call Girls In Jaypee Siddharth - 5 Star Hotel New Delhi ➥9990211544 Top Esc...
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
 
Marketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet CreationsMarketing Management Business Plan_My Sweet Creations
Marketing Management Business Plan_My Sweet Creations
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | DelhiFULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
FULL ENJOY - 9953040155 Call Girls in Chhatarpur | Delhi
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 

Develop a project plan with critical path analysis

  • 1. 6–1 Chapter 6 - Developing a Project Plan
  • 2. 6–2 Developing the Project Plan • The Project Network –A flow chart that graphically depicts the sequence, interdependencies, and start and finish times of the project job plan of activities that is the critical path through the network. • Provides the basis for scheduling labor and equipment. • Enhances communication among project participants. • Provides an estimate of the project’s duration. • Provides a basis for budgeting cash flow. • Identifies activities that are critical. • Highlights activities that are “critical” and can not be delayed. • Help managers get and stay on plan.
  • 3. 6–3 Constructing a Project Network • Terminology –Activity: an element of the project that requires time. –Merge Activity: an activity that has two or more preceding activities on which it depends. –Parallel (Concurrent) Activities: Activities that can occur independently and, if desired, not at the same time. A C D B
  • 4. 6–4 Constructing a Project Network (cont’d) • Terminology –Path: a sequence of connected, dependent activities. –Critical path: the longest path through the activity network that allows for the completion of all project- related activities; the shortest expected time in which the entire project can be completed. Delays on the critical path will delay completion of the entire project. A B D (Assumes that minimum of A + B > minimum of C in length of times to complete activities.) C
  • 5. 6–5 Constructing a Project Network (cont’d) • Terminology –Event: a point in time when an activity is started or completed. It does not consume time. –Burst Activity: an activity that has more than one activity immediately following it (more than one dependency arrow flowing from it). • Two Approaches –Activity-on-Node (AON) • Uses a node to depict an activity. –Activity-on-Arrow (AOA) • Uses an arrow to depict an activity. B D A C
  • 6. 6–6 Basic Rules to Follow in Developing Project Networks 1. Networks typically flow from left to right. 2. An activity cannot begin until all preceding connected activities are complete. 3. Arrows indicate precedence and flow and can cross over each other. 4. Each activity must have a unique identify number that is greater than any of its predecessor activities. 5. Looping is not allowed. 6. Conditional statements are not allowed. 7. Use common start and stop nodes.
  • 12. 6–12 Network Computation Process • Forward Pass—Earliest Times –How soon can the activity start? (early start—ES) –How soon can the activity finish? (early finish—EF) –How soon can the project finish? (expected time—ET) • Backward Pass—Latest Times –How late can the activity start? (late start—LS) –How late can the activity finish? (late finish—LF) –Which activities represent the critical path? –How long can activity be delayed? (slack or float—SL)
  • 16. 6–16 Forward Pass Computation • Add activity times along each path in the network (ES + Duration = EF). • Carry the early finish (EF) to the next activity where it becomes its early start (ES) unless… • The next succeeding activity is a merge activity, in which case the largest EF of all preceding activities is selected.
  • 18. 6–18 Backward Pass Computation • Subtract activity times along each path in the network (LF - Duration = LS). • Carry the late start (LS) to the next activity where it becomes its late finish (LF) unless • The next succeeding activity is a burst activity, in which case the smallest LF of all preceding activities is selected.
  • 19. 6–19 Determining Free Slack (or Float) • Free Slack (or Float) –Is the amount of time an activity can be delayed after the start of a longer parallel activity or activities. –Is how long an activity can exceed its early finish date without affecting early start dates of any successor(s). –Allows flexibility in scheduling scarce resources. • Sensitivity –The likelihood the original critical path(s) will change once the project is initiated. –The critical path is the network path(s) that has (have) the least slack in common.
  • 23. 6–23 Extended Network Techniques to Come Close to Reality • Laddering –Activities are broken into segments so the following activity can begin sooner and not delay the work.
  • 24. 6–24 Example of Laddering Using Finish-to-Start Relationship FIGURE 6.13