Critical Path Ppt

Jeff Hilton
Jeff HiltonEducation, consultant, ski instructor
Project Management with Certain
             Time Estimates
• Summary of steps:
  – Determine activities that need to be accomplished
  – Determine precedence relationships and completion
    times
  – Construct network diagram
  – Determine the critical path
  – Determine early start and late start schedules
Project Management: Scheduling
   Projects with Certain Time Estimates
• Create Network Diagram
  – Based on order of precedence
    among activities
Calculation of the Critical Path
• Network approach helps calculate project duration
    – A “path” is a sequence of activities that begins at the start of
      the project and goes to the end of the project
      • 1,2,3,5,6,7,8
      • 1,2,4,6,7,8
    – The “critical path” is the path that takes the longest to
      complete
      • and thus determines the minimum duration of the project

                        3             5
1         2                                        6              7      8

                              4
Calculation of the Critical Path
Calculation of the Critical Path
   • Critical Path
          – The path that
            takes the longest
            to complete




                                2 weeks         3 weeks

4 weeks       10 weeks            3               5       16 weeks   4 weeks   1 week

  1              2                    4 weeks
                                                             6         7         8

                                          4
Calculation of the Critical Path
   • Critical Path
          – The path that
            takes the longest
            to complete




                                2 weeks         3 weeks

4 weeks       10 weeks            3               5       16 weeks   4 weeks   1 week

  1              2                    4 weeks
                                                             6         7           8

                                          4                      C.P. = 40 weeks
Calculation of the Critical Path
 • It is possible for multiple
   Critical Paths to exist
      – New information suggests that
        Activity 4 will take 5 weeks
        instead of 4
                                                                            5
                                                                                 X




                             2 weeks         3 weeks

4 weeks     10 weeks           3               5       16 weeks   4 weeks       1 week

  1             2                  4 weeks
                                                          6         7             8

                                        4
Calculation of the Critical Path
 • It is possible for
   multiple Critical
   Paths to exist
                                                                             5
      – New information                                                           X
        suggests that Activity 4
        will take 5 weeks instead
        of 4


                           2 weeks            3 weeks

4 weeks     10 weeks          3                 5       16 weeks   4 weeks       1 week

  1            2                    5 weeks
                                                           6         7             8

                                      4                        C.P. = 40 weeks
Calculation of the Critical Path
 • Critical Path may also
   shift if non-critical
   activity is lengthened or
   Critical Path activity is                                                  6
   shortened                                                                        X
      – Another update indicates it
        will actually take 6 weeks for
        Activity 4


                             2 weeks           3 weeks

4 weeks     10 weeks            3                5       16 weeks   4 weeks       1 week

  1             2                    4 weeks
                                                            6         7             8

                                         4
Calculation of the Critical Path
• Critical Path may also
  shift if non-critical
  activity is lengthened or
  Critical Path activity is                                                    6
  shortened                                                                         X
   – Another update indicates it
     will actually take 6 weeks for
     Activity 4


                            2 weeks             3 weeks

4 weeks    10 weeks            3                  5       16 weeks   4 weeks       1 week

  1           2                       6 weeks
                                                             6         7             8

                                        4                        C.P. = 41 weeks
Determining Slack
• Slack - The amount of time an activity on a non-critical path
  can be delayed without affecting the duration of the project
  (i.e., without putting it on the critical path)
  – Uses four calculated values
     •   Early start - Earliest an activity can start (based on prerequisites)
     •   Early finish - Earliest it can finish (based on prerequisites & duration)
     •   Late start - Latest an activity can start and not delay the project
     •   Late finish - Latest an activity can finish and not delay the project
Calculating Early Start (ES) and
                   Early Finish (EF)
• Move from left to right in
  network
   – ES for 1st activity usually zero
   – EF equals ES plus activity
     duration
   – ES is latest of the EF times of
     an activity’s predecessors
THIS IS CALLED
THE FORWARD
PASS
Calculating Late Start (LS) and
•   Move from right to left in
                               Late Finish (LF)
    network
    – LF for last activity equals EF
      for last activity
       • Or target date if different
    – LS equals LF minus activity
      duration
    – LF is earliest of the LS times of
      an activity’s followers
    THIS IS CALLED THE
    BACKWARD PASS
Calculating Slack
     • Slack - The amount of time an        • Computed by either:
       activity on a non-critical path        Late Start - Early Start
       can be delayed without affecting            or
       the duration of the project (i.e.,
       putting it on the critical path)       Late Finish - Early Finish




• Activities that have zero slack are, by definition, on the critical path
Project Scheduling with Uncertain
          Time Estimates
• Summary of steps:
  – Determine activities that need to be accomplished
  – Determine precedence relationships and completion times
  – Construct network diagram
  – Determine the critical path
  – Determine early start and late start schedules
  – Calculate the variances for the activity times
  – Calculate the probability of completing by the desired due
    date
Project Scheduling with Time
             Uncertainty
• Take three time estimates
  – Optimistic - What is the (realistic) fastest we can
   get an activity done?
  – Pessimistic - What is the (realistic) worst case
   scenario for delay?
  – Most likely - What is our “most likely” estimate?
Project Scheduling with Time
               Uncertainty
• Calculate the “expected time” for the activity
                       o   4m     p
                 Te
                            6
Where:
 Te   =   Expected Time
 o    =   Optimistic estimate
 m    =   Most likely estimate
 p    =   Worst-case (pessimistic) estimate
Project Scheduling with Time
          Uncertainty
                                       E stim ates
   A ctivity #        O ptim istic     M o st L ikely   P essim istic
        1                  3                  4               5
        2                  8                 10              12
        3                  1                  2               4

                        3    4(4)      5
Activity #1      Te                          4 . 00 weeks
                               6

                        8    4 (10 )    12
Activity #2      Te                            10 . 00 weeks
                                   6

                        1    4(2)      4
Activity #3      Te                          2 . 17 weeks
                               6
Using Variation in Time Estimates to
         Assess Duration Probabilities
How do we interpret this estimate???
   Probability theory (“central limit theorem”) dictates that we assume that
         finish times across entire project are distributed “normally”

                 Probabilistically: 50% chance we will
                      finish faster, 50% chance
                         we will finish slower
                       2.17 weeks       3 weeks

4 weeks   10 weeks         3                5     16.17 weeks   4.17 weeks   1.17 weeks

  1          2                 4.17 weeks
                                                     6            7             8
                                    4
                                                  C.P. = 40.68 weeks
Using Variation in Time Estimates to
     Access Duration Probabilities
           D   Te                  Note that this is , not 2 ,
      Z                       We have to take the square root of the
                             “variance” to get the standard deviation



Where:
Z = Number of standard deviations D is from Te
Te = Expected Time
D = Project duration I am thinking about
Using Variation in Time Estimates to
      Access Duration Probabilities
• We recognize that there is variation around our estimates
  – We are estimating “most likely” or “expected” not “exact”
  – Commonly assume a “Beta” distribution
     • Another asymmetric distribution (because duration is never less than zero)


• Calculating variance of the activity’s duration estimate:

                                                2
                           2        p       o
                                        6
Using Variation in Time Estimates to
   Access Duration Probabilities
                                    E stim ates
  A ctivity #    O ptim istic       M o st L ikely      P essim istic
       1              3                    4                  5
       2              8                   10                 12
       3              1                    2                  4
                                        2
                       2   5        3
   Activity #1                                  0 . 11 weeks
                                6
                                            2
                   2       12       8
   Activity #2                                  0 . 44 weeks
                                6
                                        2
                       2   4        1
   Activity #3                                  0 . 25 weeks
                                6
Using Variation in Time Estimates to
      Assess Duration Probabilities
• Calculate Critical Path using Te
• Accumulate the variances of the individual activities
• Apply formula to estimate project duration probabilities
                            D      Te
                    Z

             Where:
             Z = Number of standard deviations D is from
                Te
             Te = Expected Time
             D = Activity duration I am thinking about
Using Variation in Time Estimates to
   Assess Duration Probabilities
Using Variation in Time Estimates to
         Assess Duration Probabilities
 What is the probability
 of finishing in 39 weeks
 or less?




                     2.17 weeks       3 weeks

4 weeks   10 weeks       3                5     16.17 weeks   4.17 weeks   1.17 weeks

  1          2               4.17 weeks
                                                   6            7             8

                                  4
Using Variation in Time Estimates to
         Assess Duration Probabilities
                                                Exhibit 8.22: Expected Values and Variances of Time Estimates

What is the probability of
finishing in 39 weeks or less?


 Critical Path = 40.68 weeks
 Sum of Variances = 2.56 weeks


                     2.17 weeks           3 weeks

4 weeks   10 weeks       3                  5               16.17 weeks           4.17 weeks          1.17 weeks

  1          2               4.17 weeks
                                                                  6                    7                    8

                                  4
Using Variation in Time Estimates to
       Assess Duration Probabilities
           D      Te     Where:
     Z                   Z = Number of standard deviations D is from Te
                         Te = Expected Time
                         D = Activity duration I am thinking about

      39       40 . 68
Z                          1 . 05 Standard deviation difference between
           1 .6
                                    “most likely” and desired duration
                                      1.6 = the square root of 2.56!!!



• So, I look up the cumulative probability [G(z)] of the activity
    being completed before -1.05 standard deviations from the
    “most likely” estimate…
     – … and find out I have a 85.314% chance of finishing within 39
       weeks!! FROM APPENDIX A PAGE A3
Using Variation in Time Estimates to
      Access Duration Probabilities
• So, what if I want to be 90 percent sure that I hit the
  project duration that I tell my boss I will (or she will fire
  me)?
  – Reconfigure “Z” equation to solve for D
  – Pick the value of “Z” that corresponds to the level of certainty I
                                         Find probability under G(z) in Appendix
    want (90% = +1.30)                    B and translate to number of standard

  – Solve
                                                        deviations
                       D Te         (Z )

                 D     40 . 68    1 .6 * 1 .3   42 . 76 weeks!!!

             What if I can stand to be only 80% sure??
Crashing Projects
• A methodical approach to reducing project duration
  – Focus on the time of activities on the critical path
  – Looking for greatest improvement with least cost
       • Additional labor, machinery
       • Overtime and temporary employees
       • Premiums paid to outside contractors for early delivery
• Steps
  –   Create network
  –   Identify critical path
  –   Identify costs of reducing each activity on path
  –   Reduce most cost effective activity
  –   Look for critical path changes
       • Beware of multiple critical paths
  – Crash next activity
Crashing Projects: Create the
         Network
Crashing Projects: Identify the Critical
                Path
          B                   C
          7                   7
      A             D                   F       H
      8             10                  8       5
                         E                  G
                         12                 9



                    A-B-C-F-H
              Critical Path = 35 days
Crashing Projects: Identify Costs of
      Crashing Each Activity
Crashing Projects: Reduce Most Cost
         Effective Activity
                           6
         B             C
         7             7
                       X
    A        D                 F       H
    8        10                8       5
                  E                G
                  12               9
Crashing Projects: Look for Critical
          Path Changes
                                        6
                B                 C
                7                 7
                                  X
       A                D                   F              H
       8                10                  8              5
                             E                  G
                             12                 9


Old Critical Path Completion = 35 days
Activity C Crashed by 1 day project completion = 34 days
Did that effect the critical path?
Crashing Projects: Look for Critical
          Path Changes
                                          6
                B                     C
                7                     7
                                      X
      A                  D                    F       H
      8                  10                   8       5
                               E                  G
                               12                 9



  Multiple Critical Paths Appear!!!

                        Critical Path = 34 days
Crashing Projects: Crash Next Activity
Exhibit 8.25: Crash Time and Costs




      Both C.P.                      Path 1 Only   Path 2 Only
Crashing Projects: Summary
              Exhibit 8.26: Crashing Summary
Solution
Caveats
•   Time estimates are frequently wrong
•   Early finishes are absorbed
•   Cushions get wasted
•   Resources aren’t always available when
    needed
1 of 38

Recommended

Critical path method(cpm) by
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)chandkec
1.6K views43 slides
Cpm n pert lecture 1 by
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1adeelmunir158
509 views40 slides
Pert & cpm project management by
Pert & cpm   project managementPert & cpm   project management
Pert & cpm project managementRahul Dubey
165.4K views30 slides
6.5 Resource Leveling and Resource Smoothing by
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource SmoothingDavidMcLachlan1
1.7K views7 slides
Network diagram problems by
Network diagram problemsNetwork diagram problems
Network diagram problemsSubhra Mishra
10.6K views5 slides

More Related Content

What's hot

Critical Path Method (CPM) & Network Analysis by
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisAsif Sultan Razu
21K views33 slides
Lecture 1. general introduction to project management by
Lecture 1. general introduction to project management Lecture 1. general introduction to project management
Lecture 1. general introduction to project management Dania Abdel-aziz
11.3K views34 slides
Network Techniques by
Network TechniquesNetwork Techniques
Network Techniquesupendar aavula
19.9K views22 slides
Pert Cpm Nis by
Pert   Cpm NisPert   Cpm Nis
Pert Cpm NisNaveed Salman
8.2K views42 slides
Earned Value Management by
Earned Value ManagementEarned Value Management
Earned Value ManagementAnand Subramaniam
40.3K views37 slides
Project management structures by
Project management structuresProject management structures
Project management structuresAswin prakash i , Xantus Technologies
35.4K views23 slides

What's hot(20)

Critical Path Method (CPM) & Network Analysis by Asif Sultan Razu
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
Asif Sultan Razu21K views
Lecture 1. general introduction to project management by Dania Abdel-aziz
Lecture 1. general introduction to project management Lecture 1. general introduction to project management
Lecture 1. general introduction to project management
Dania Abdel-aziz11.3K views
CPM, Network Analysis A-O-A, A-O-N, Resource management by Amit Kumbar
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
Amit Kumbar4.7K views
PMP Lecture 1: Introduction to Project Management by Benha University
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
Benha University4.9K views
Cpm (critical path method) by El Moro
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
El Moro10K views
Project Time Management by Serdar Temiz
Project Time ManagementProject Time Management
Project Time Management
Serdar Temiz16K views
Project management PPT by Raj Sampat
Project management  PPTProject management  PPT
Project management PPT
Raj Sampat93.4K views
Project Management by ajithsrc
Project ManagementProject Management
Project Management
ajithsrc3.9K views
Critical Path Method: Activities And Events, Float/Slacks by Prasad Thanthratey
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
Prasad Thanthratey1.1K views
00 Introduction of project scheduling by Soe Naing Win
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
Soe Naing Win7.3K views
Project Management Tools and Techniques (PERT- Project Evaluation and Review ... by Zulfiquer Ahmed Amin
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Zulfiquer Ahmed Amin45.4K views
Introduction-to-project-management by Savaş Şakar
Introduction-to-project-managementIntroduction-to-project-management
Introduction-to-project-management
Savaş Şakar21.7K views
Project management tools and techniques by Tata Dinyuy
Project management tools and techniquesProject management tools and techniques
Project management tools and techniques
Tata Dinyuy25.1K views

Viewers also liked

Critical Path Analysis by
Critical Path AnalysisCritical Path Analysis
Critical Path Analysistutor2u
159.6K views23 slides
Heat Exchanger by
Heat ExchangerHeat Exchanger
Heat ExchangerNathan
8.6K views23 slides
Heat exchanger - Training course material by
Heat exchanger - Training course materialHeat exchanger - Training course material
Heat exchanger - Training course materialBassem Eleaba, MEng
10.4K views155 slides
Critical Path Method by
Critical Path MethodCritical Path Method
Critical Path MethodAlecsis Roe Frasco
10.9K views36 slides
Selection of Shell and tube heat exchanger (STHE) by
Selection of Shell and tube heat exchanger (STHE)Selection of Shell and tube heat exchanger (STHE)
Selection of Shell and tube heat exchanger (STHE)Gautham Sankaraselvam
11.1K views36 slides
Power dissipation cmos by
Power dissipation cmosPower dissipation cmos
Power dissipation cmosRajesh Tiwary
22.8K views26 slides

Viewers also liked(16)

Critical Path Analysis by tutor2u
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
tutor2u159.6K views
Heat Exchanger by Nathan
Heat ExchangerHeat Exchanger
Heat Exchanger
Nathan 8.6K views
Power dissipation cmos by Rajesh Tiwary
Power dissipation cmosPower dissipation cmos
Power dissipation cmos
Rajesh Tiwary22.8K views
Power consumption by sdpable
Power consumptionPower consumption
Power consumption
sdpable9.8K views
اسرع طريقة لاحتراف برمجة المايكروكنترولر by messaoudi mohamed
اسرع طريقة لاحتراف برمجة المايكروكنترولراسرع طريقة لاحتراف برمجة المايكروكنترولر
اسرع طريقة لاحتراف برمجة المايكروكنترولر
messaoudi mohamed730 views
Project Scheduling by Ciprian Rusen
Project SchedulingProject Scheduling
Project Scheduling
Ciprian Rusen48.7K views
The Network Diagram and Critical Path by dmdk12
The Network Diagram and Critical PathThe Network Diagram and Critical Path
The Network Diagram and Critical Path
dmdk12116.9K views
Project management planning by Alvin Niere
Project management planningProject management planning
Project management planning
Alvin Niere11.3K views

Recently uploaded

Top 10 Web Development Companies in California by
Top 10 Web Development Companies in CaliforniaTop 10 Web Development Companies in California
Top 10 Web Development Companies in CaliforniaTopCSSGallery
44 views27 slides
Presentation on proposed acquisition of leading European asset manager Aermon... by
Presentation on proposed acquisition of leading European asset manager Aermon...Presentation on proposed acquisition of leading European asset manager Aermon...
Presentation on proposed acquisition of leading European asset manager Aermon...KeppelCorporation
171 views11 slides
Why are KPIs(key performance indicators) important? by
Why are KPIs(key performance indicators) important? Why are KPIs(key performance indicators) important?
Why are KPIs(key performance indicators) important? Epixel MLM Software
11 views17 slides
NYKAA PPT .pptx by
NYKAA PPT .pptxNYKAA PPT .pptx
NYKAA PPT .pptx125071081
13 views9 slides
Leading in A Culture by
Leading in A CultureLeading in A Culture
Leading in A CultureSeta Wicaksana
14 views34 slides
Assignment 4: Reporting to Management.pptx by
Assignment 4: Reporting to Management.pptxAssignment 4: Reporting to Management.pptx
Assignment 4: Reporting to Management.pptxBethanyAline
17 views20 slides

Recently uploaded(20)

Top 10 Web Development Companies in California by TopCSSGallery
Top 10 Web Development Companies in CaliforniaTop 10 Web Development Companies in California
Top 10 Web Development Companies in California
TopCSSGallery44 views
Presentation on proposed acquisition of leading European asset manager Aermon... by KeppelCorporation
Presentation on proposed acquisition of leading European asset manager Aermon...Presentation on proposed acquisition of leading European asset manager Aermon...
Presentation on proposed acquisition of leading European asset manager Aermon...
KeppelCorporation171 views
Why are KPIs(key performance indicators) important? by Epixel MLM Software
Why are KPIs(key performance indicators) important? Why are KPIs(key performance indicators) important?
Why are KPIs(key performance indicators) important?
NYKAA PPT .pptx by 125071081
NYKAA PPT .pptxNYKAA PPT .pptx
NYKAA PPT .pptx
12507108113 views
Assignment 4: Reporting to Management.pptx by BethanyAline
Assignment 4: Reporting to Management.pptxAssignment 4: Reporting to Management.pptx
Assignment 4: Reporting to Management.pptx
BethanyAline17 views
Imports Next Level.pdf by Bloomerang
Imports Next Level.pdfImports Next Level.pdf
Imports Next Level.pdf
Bloomerang80 views
PMU Launch - Guaranteed Slides by pmulaunch
PMU Launch - Guaranteed SlidesPMU Launch - Guaranteed Slides
PMU Launch - Guaranteed Slides
pmulaunch16 views
Businesses to Start in 2024.pdf by Dante St James
Businesses to Start in 2024.pdfBusinesses to Start in 2024.pdf
Businesses to Start in 2024.pdf
Dante St James19 views
voice logger software aegis.pdf by Nirmal Sharma
voice logger software aegis.pdfvoice logger software aegis.pdf
voice logger software aegis.pdf
Nirmal Sharma30 views
Navigating EUDR Compliance within the Coffee Industry by Peter Horsten
Navigating EUDR Compliance within the Coffee IndustryNavigating EUDR Compliance within the Coffee Industry
Navigating EUDR Compliance within the Coffee Industry
Peter Horsten41 views
The Talent Management Navigator Performance Management by Seta Wicaksana
The Talent Management Navigator Performance ManagementThe Talent Management Navigator Performance Management
The Talent Management Navigator Performance Management
Seta Wicaksana21 views
Coomes Consulting Business Profile by Chris Coomes
Coomes Consulting Business ProfileCoomes Consulting Business Profile
Coomes Consulting Business Profile
Chris Coomes46 views

Critical Path Ppt

  • 1. Project Management with Certain Time Estimates • Summary of steps: – Determine activities that need to be accomplished – Determine precedence relationships and completion times – Construct network diagram – Determine the critical path – Determine early start and late start schedules
  • 2. Project Management: Scheduling Projects with Certain Time Estimates • Create Network Diagram – Based on order of precedence among activities
  • 3. Calculation of the Critical Path • Network approach helps calculate project duration – A “path” is a sequence of activities that begins at the start of the project and goes to the end of the project • 1,2,3,5,6,7,8 • 1,2,4,6,7,8 – The “critical path” is the path that takes the longest to complete • and thus determines the minimum duration of the project 3 5 1 2 6 7 8 4
  • 4. Calculation of the Critical Path
  • 5. Calculation of the Critical Path • Critical Path – The path that takes the longest to complete 2 weeks 3 weeks 4 weeks 10 weeks 3 5 16 weeks 4 weeks 1 week 1 2 4 weeks 6 7 8 4
  • 6. Calculation of the Critical Path • Critical Path – The path that takes the longest to complete 2 weeks 3 weeks 4 weeks 10 weeks 3 5 16 weeks 4 weeks 1 week 1 2 4 weeks 6 7 8 4 C.P. = 40 weeks
  • 7. Calculation of the Critical Path • It is possible for multiple Critical Paths to exist – New information suggests that Activity 4 will take 5 weeks instead of 4 5 X 2 weeks 3 weeks 4 weeks 10 weeks 3 5 16 weeks 4 weeks 1 week 1 2 4 weeks 6 7 8 4
  • 8. Calculation of the Critical Path • It is possible for multiple Critical Paths to exist 5 – New information X suggests that Activity 4 will take 5 weeks instead of 4 2 weeks 3 weeks 4 weeks 10 weeks 3 5 16 weeks 4 weeks 1 week 1 2 5 weeks 6 7 8 4 C.P. = 40 weeks
  • 9. Calculation of the Critical Path • Critical Path may also shift if non-critical activity is lengthened or Critical Path activity is 6 shortened X – Another update indicates it will actually take 6 weeks for Activity 4 2 weeks 3 weeks 4 weeks 10 weeks 3 5 16 weeks 4 weeks 1 week 1 2 4 weeks 6 7 8 4
  • 10. Calculation of the Critical Path • Critical Path may also shift if non-critical activity is lengthened or Critical Path activity is 6 shortened X – Another update indicates it will actually take 6 weeks for Activity 4 2 weeks 3 weeks 4 weeks 10 weeks 3 5 16 weeks 4 weeks 1 week 1 2 6 weeks 6 7 8 4 C.P. = 41 weeks
  • 11. Determining Slack • Slack - The amount of time an activity on a non-critical path can be delayed without affecting the duration of the project (i.e., without putting it on the critical path) – Uses four calculated values • Early start - Earliest an activity can start (based on prerequisites) • Early finish - Earliest it can finish (based on prerequisites & duration) • Late start - Latest an activity can start and not delay the project • Late finish - Latest an activity can finish and not delay the project
  • 12. Calculating Early Start (ES) and Early Finish (EF) • Move from left to right in network – ES for 1st activity usually zero – EF equals ES plus activity duration – ES is latest of the EF times of an activity’s predecessors THIS IS CALLED THE FORWARD PASS
  • 13. Calculating Late Start (LS) and • Move from right to left in Late Finish (LF) network – LF for last activity equals EF for last activity • Or target date if different – LS equals LF minus activity duration – LF is earliest of the LS times of an activity’s followers THIS IS CALLED THE BACKWARD PASS
  • 14. Calculating Slack • Slack - The amount of time an • Computed by either: activity on a non-critical path Late Start - Early Start can be delayed without affecting or the duration of the project (i.e., putting it on the critical path) Late Finish - Early Finish • Activities that have zero slack are, by definition, on the critical path
  • 15. Project Scheduling with Uncertain Time Estimates • Summary of steps: – Determine activities that need to be accomplished – Determine precedence relationships and completion times – Construct network diagram – Determine the critical path – Determine early start and late start schedules – Calculate the variances for the activity times – Calculate the probability of completing by the desired due date
  • 16. Project Scheduling with Time Uncertainty • Take three time estimates – Optimistic - What is the (realistic) fastest we can get an activity done? – Pessimistic - What is the (realistic) worst case scenario for delay? – Most likely - What is our “most likely” estimate?
  • 17. Project Scheduling with Time Uncertainty • Calculate the “expected time” for the activity o 4m p Te 6 Where: Te = Expected Time o = Optimistic estimate m = Most likely estimate p = Worst-case (pessimistic) estimate
  • 18. Project Scheduling with Time Uncertainty E stim ates A ctivity # O ptim istic M o st L ikely P essim istic 1 3 4 5 2 8 10 12 3 1 2 4 3 4(4) 5 Activity #1 Te 4 . 00 weeks 6 8 4 (10 ) 12 Activity #2 Te 10 . 00 weeks 6 1 4(2) 4 Activity #3 Te 2 . 17 weeks 6
  • 19. Using Variation in Time Estimates to Assess Duration Probabilities How do we interpret this estimate??? Probability theory (“central limit theorem”) dictates that we assume that finish times across entire project are distributed “normally” Probabilistically: 50% chance we will finish faster, 50% chance we will finish slower 2.17 weeks 3 weeks 4 weeks 10 weeks 3 5 16.17 weeks 4.17 weeks 1.17 weeks 1 2 4.17 weeks 6 7 8 4 C.P. = 40.68 weeks
  • 20. Using Variation in Time Estimates to Access Duration Probabilities D Te Note that this is , not 2 , Z We have to take the square root of the “variance” to get the standard deviation Where: Z = Number of standard deviations D is from Te Te = Expected Time D = Project duration I am thinking about
  • 21. Using Variation in Time Estimates to Access Duration Probabilities • We recognize that there is variation around our estimates – We are estimating “most likely” or “expected” not “exact” – Commonly assume a “Beta” distribution • Another asymmetric distribution (because duration is never less than zero) • Calculating variance of the activity’s duration estimate: 2 2 p o 6
  • 22. Using Variation in Time Estimates to Access Duration Probabilities E stim ates A ctivity # O ptim istic M o st L ikely P essim istic 1 3 4 5 2 8 10 12 3 1 2 4 2 2 5 3 Activity #1 0 . 11 weeks 6 2 2 12 8 Activity #2 0 . 44 weeks 6 2 2 4 1 Activity #3 0 . 25 weeks 6
  • 23. Using Variation in Time Estimates to Assess Duration Probabilities • Calculate Critical Path using Te • Accumulate the variances of the individual activities • Apply formula to estimate project duration probabilities D Te Z Where: Z = Number of standard deviations D is from Te Te = Expected Time D = Activity duration I am thinking about
  • 24. Using Variation in Time Estimates to Assess Duration Probabilities
  • 25. Using Variation in Time Estimates to Assess Duration Probabilities What is the probability of finishing in 39 weeks or less? 2.17 weeks 3 weeks 4 weeks 10 weeks 3 5 16.17 weeks 4.17 weeks 1.17 weeks 1 2 4.17 weeks 6 7 8 4
  • 26. Using Variation in Time Estimates to Assess Duration Probabilities Exhibit 8.22: Expected Values and Variances of Time Estimates What is the probability of finishing in 39 weeks or less? Critical Path = 40.68 weeks Sum of Variances = 2.56 weeks 2.17 weeks 3 weeks 4 weeks 10 weeks 3 5 16.17 weeks 4.17 weeks 1.17 weeks 1 2 4.17 weeks 6 7 8 4
  • 27. Using Variation in Time Estimates to Assess Duration Probabilities D Te Where: Z Z = Number of standard deviations D is from Te Te = Expected Time D = Activity duration I am thinking about 39 40 . 68 Z 1 . 05 Standard deviation difference between 1 .6 “most likely” and desired duration 1.6 = the square root of 2.56!!! • So, I look up the cumulative probability [G(z)] of the activity being completed before -1.05 standard deviations from the “most likely” estimate… – … and find out I have a 85.314% chance of finishing within 39 weeks!! FROM APPENDIX A PAGE A3
  • 28. Using Variation in Time Estimates to Access Duration Probabilities • So, what if I want to be 90 percent sure that I hit the project duration that I tell my boss I will (or she will fire me)? – Reconfigure “Z” equation to solve for D – Pick the value of “Z” that corresponds to the level of certainty I Find probability under G(z) in Appendix want (90% = +1.30) B and translate to number of standard – Solve deviations D Te (Z ) D 40 . 68 1 .6 * 1 .3 42 . 76 weeks!!! What if I can stand to be only 80% sure??
  • 29. Crashing Projects • A methodical approach to reducing project duration – Focus on the time of activities on the critical path – Looking for greatest improvement with least cost • Additional labor, machinery • Overtime and temporary employees • Premiums paid to outside contractors for early delivery • Steps – Create network – Identify critical path – Identify costs of reducing each activity on path – Reduce most cost effective activity – Look for critical path changes • Beware of multiple critical paths – Crash next activity
  • 31. Crashing Projects: Identify the Critical Path B C 7 7 A D F H 8 10 8 5 E G 12 9 A-B-C-F-H Critical Path = 35 days
  • 32. Crashing Projects: Identify Costs of Crashing Each Activity
  • 33. Crashing Projects: Reduce Most Cost Effective Activity 6 B C 7 7 X A D F H 8 10 8 5 E G 12 9
  • 34. Crashing Projects: Look for Critical Path Changes 6 B C 7 7 X A D F H 8 10 8 5 E G 12 9 Old Critical Path Completion = 35 days Activity C Crashed by 1 day project completion = 34 days Did that effect the critical path?
  • 35. Crashing Projects: Look for Critical Path Changes 6 B C 7 7 X A D F H 8 10 8 5 E G 12 9 Multiple Critical Paths Appear!!! Critical Path = 34 days
  • 36. Crashing Projects: Crash Next Activity Exhibit 8.25: Crash Time and Costs Both C.P. Path 1 Only Path 2 Only
  • 37. Crashing Projects: Summary Exhibit 8.26: Crashing Summary Solution
  • 38. Caveats • Time estimates are frequently wrong • Early finishes are absorbed • Cushions get wasted • Resources aren’t always available when needed