SlideShare a Scribd company logo
1 of 16
Download to read offline
Solar Power Policy for J&K
JAKEDA
JAMMU AND KASHMIR ENERGY DEVELOPMENT AGENCY
Government of Jammu and Kashmir
Solar Power Policy for J&K
Jammu and Kashmir Energy Development Agency Page 2
Table of contents
1. INTRODUCTION……………………………………………………………………….3
2. NEED FOR SOLAR POWER PROJECTS……………………………………............4
3. OBJECTIVES……………………………….……………………………..…………….5
4. OPERATIVE PERIOD ………………………………………………………….……..5
5. CAPACITY CAP……………………………………………….…………………….…5
6. ELIGIBLE UNIT…………………………………………….……………………….…6
7. PROCEDURE FOR ALLOTMENT OF SITES FOR DEVELOPMENT
OF SOLAR POWER PLANTS……………………….………………………………..6
8. EVALUATION / PRE-QUALIFICATION CRITERIA ……………………………..7
9. SELF IDENTIFICATION OF PROJECTS……………………………..……….……8
10. INCENTIVES TO THE POWER DEVELOPERS ……………………….…………8
11. SCHEDULE OF IMPLEMENTATION……………………………………..…….…10
12. WHEELING CHARGES………………………………………………………..……..11
13. SALE OF ENERGY…………………………………………………………….….…..11
14. PLANT AND MACHINERY………………………………………………….….…...11
15. METERING OF ELECTRICITY ……………………………………………….…..12
16. GRID CONNECTIVITY AND EVACUATION FACILITY UPTO
PDD SUB-SUBSTATION………………………………………………………....…..12
17. OPEN ACCESS FOR THIRD PARTY SALE ………………………………….…..12
18. RENEWABLE PURCHASE OBLIGATION …………………………..…………..13
19. REACTIVE POWER CHARGES……………………………………………………13
20. PENALTY FOR NON FULFILLING POWER PURCHASE OBLIGATION…..13
21. SHARING OF CLEAN DEVELOPMENT MECHANISM (CDM) BENEFIT ….13
22. STATE GOVT FACILITATION AGENCY………………………………………..14
23. MID TERM REVIEW…………………………………………………………….…..14
24. POWER TO REMOVE DIFFICULTIES…………………………………………...15
25. REGULATORY OVERSIGHT……………………………………………………...15
26. ROLE OF NODAL AGENCY ……………………………………………………….15
27. PROJECT APPROVAL COMMITTEE…………………………………………...16
28. DEFINITIONS………………………………………………………………………...16
Solar Power Policy for J&K
Jammu and Kashmir Energy Development Agency Page 3
1. INTRODUCTION
1.1 The challenges of climate change and global warming continuously threaten the
world community. The Government of Jammu & Kashmir has taken note of the growing
recognition of impact of climate change at the local, national and global levels. The
Government recognizes the urgent need to tackle challenges that arise on account of these
impacts through integrated policy prescriptions and programmes aimed at mitigation of
impacts and adaptation to reduce vulnerability of systems. The Government is also
cognizant of the cross-cutting nature of impacts with enormous cost implications for
tackling them and that these costs could escalate if preventive action is not taken
immediately. Besides this MNRE has launched Jawaharlal Nehru National Solar Mission
(JNNSM) under the brand 'Solar India' with the objective to establish India as a global
leader in solar energy, by creating the policy conditions for its diffusion across the country
as quickly as possible. The Mission has set a target of 20,000MWand stipulates
implementation and achievement of the target in 3 phases (first phase upto 2012-13,
second phase from 2013 to 2017 and the third phase from 2017 to 2022) for various
components, including grid connected solar power.
1.2 The successful implementation of the JNNSM requires the identification of
resources to overcome the financial, investment, technology, institutional and other related
barriers which confront solar power development in India. The penetration of solar power,
therefore, requires substantial support. The policy framework of the Mission will facilitate
the process of achieving grid parity by 2022.
1.3 To ramp up capacity of grid-connected solar power generation to 1000 MW
within three years – by 2013; an additional 3000 MW by 2017 through the mandatory use
of the renewable purchase obligation by utilities backed with a preferential tariff. This
capacity can be more than doubled – reaching 10,000MW installed power by 2017 and
20,000 MW or more by 2022 in the country. The transition could be appropriately up
scaled, based on availability of international finance and technology.
Solar Power Policy for J&K
Jammu and Kashmir Energy Development Agency Page 4
2. NEED FOR SOLAR POWER PROJECTS
2.1 Solar energy is environmentally friendly as it has zero emissions while generating
electricity or heat. The exhaustible reserves of fossil fuels and their volatile market prices
further contribute towards energy insecurity. Government recognizes the central role of
energy and the need to have a policy to promote efficient use of conventional energy
together with proactive establishment and promotion of sustained use of new and non-
conventional energy sources and applications to reduce emissions and other impacts of
climate change. Based on this “climate efficient initiative” the state has decided to promote
energy efficiency measures, adopt preventive management techniques and build capacities
for all the concerned stakeholders to contribute and sustain successful transitions to a more
energy efficient future duly emphasizing the local relevance of alternatives.
2.2 From an energy security perspective, solar is the most secure of all sources, since
it is abundantly available. Theoretically, a small fraction of the total incident solar energy
(if captured effectively) can meet the entire country’s power requirements. It is also clear
that given the large proportion of poor and energy un-served population in the country,
every effort needs to be made to exploit the relatively abundant sources of energy
available to the country. While, today, domestic coal based power generation is the
cheapest electricity source, future scenarios suggest that this could well change. Already,
faced with crippling electricity shortages, price of electricity traded internally, touched Rs
7 per unit for base loads and around Rs 8.50 per unit during peak periods. The situation
will also change, as the country moves towards imported coal to meet its energy demand.
The price of power will have to factor in the availability of coal in international markets
and the cost of developing import infrastructure. It is also evident that as the cost of
environmental degradation is factored into the mining of coal, as it must, the price of this
raw material will increase. In the situation of energy shortages, the country is increasing
the use of diesel-based electricity, which is both expensive – costs as high as Rs 15 per unit
- and polluting. It is in this situation the solar imperative is both urgent and feasible to
enable the country to meet long-term energy needs.
Solar Power Policy for J&K
Jammu and Kashmir Energy Development Agency Page 5
3. OBJECTIVES
3.1 The State Government introduces the Solar Power Policy with the following
objectives :
i) Promoting generation of green and clean power in the State using Solar Energy
ii) To meet the targets to be achieved countrywide under JNNSM.
iii) To put in place an appropriate investment climate, that could leverage the Clean
Development Mechanism (CDM).
iv) Productive use of the wastelands, thereby fostering a socio-economic transformation.
v) Employment generation and skill enhancement of local youth.
vi) Promotion of R&D and facilitation of technology transfer
vii)Establish core technical competence in professionals in the state to initiate and sustain
use and effective management of newer energy applications.
viii) Creation of environmental consciousness among citizens
4. OPERATIVE PERIOD
4.1 The Policy will come into operation with effect from its publication in the State
Gazette and will remain in force until superseded or modified by another Policy.
5. CAPACITY CAP
5.1 The minimum project capacity shall be 1 MW. However, if MNRE launches any
scheme for lower capacity power plant then that shall also be considered.
Solar Power Policy for J&K
Jammu and Kashmir Energy Development Agency Page 6
6. ELIGIBLE UNIT
6.1 Any company or body corporate or association or body of individuals or project
proponents as per MNRE Schemes/ guidelines launched/issued from time to time will be
eligible for setting up of Solar Power Plants (SPPs), for the purpose of captive use and / or
for selling of electricity as per MNRE / JKSERC norms.
7. PROCEDURE FOR ALLOTMENT OF SITES FOR
DEVELOPMENT OF SOLAR POWER PLANTS
7.1 The Nodal Agency shall prepare a Land Bank containing list of potential sites for
development of Solar Power Plants and such sites shall be allotted as per following
procedure..
(i) The available sites shall be advertized to seek bids.
(ii) All the applications received in response to the advertisement shall be subject to
pre-qualification as per evaluation criteria. The applications shall be accompanied
with a non-refundable Demand Draft of Rs.10,000/- as processing fees or as
applicable under the MNRE scheme.
(iii) Bids shall be invited on the basis of upfront premium payable to GoJK and shall
quote this premium up to 100 of Rupees.
(iv) The bids shall be subject to two-stage scrutiny. In the first stage the pre
qualification of bids will be conducted on the basis of financial and technical
capacity in the manner as specified in the bid document or MNRE guidelines as per
the scheme.
(v) The bidders which are found technically responsive shall be asked to submit their
price bids based on upfront premium per MW payable to the GoJK.
(vi) The minimum threshold premium will be Rs.2.00 lakhs per MW. Bids received
beneath this threshold shall be rejected.
Solar Power Policy for J&K
Jammu and Kashmir Energy Development Agency Page 7
(vii) The project shall be allotted to the bidder making the highest bid.
(viii) In case two or more bidders bid identical premium for a site then the bidder
securing the highest technical score during pre-qualification shall be awarded the
project.
(ix) If after advertisement of the project site, only one tender is received, fresh
advertisement would be issued. If a single bid is again received in response to the
second advertisement, the said bid shall be considered on the basis of technical and
commercial capacity with minimum threshold premium or premium quoted by him
whichever is higher.
7.2 In case the Project Proponent arranges land of his own then all the Financial/
Technical/ other conditions laid down by the MNRE under the particular scheme shall be
applicable.
8. EVALUATION / PRE-QUALIFICATION CRITERIA
8.1 Pre qualification of bidders will be based on financial and technical
capacity to mobilize the required resources. Applications will be graded on the
basis of balance sheets, annual reports and other supported evidence of financial and
technical capabilities.
8.2 The weightage to be given to financial capacity, technical capability, past
experience and other relevant attributes of the applicants, the sub-categories of these
attributes to be evaluated and their inter-se weightage, the guidelines for evaluation
and the passing score on attributes /in aggregate required for pre-qualification shall
be specified in the bid documents inviting bids for pre-qualification.
8.3 Any entity in order to technically qualify shall be required to have an
agreement with proven technology supplier of Solar Power Projects for supply of
equipments for the plant.
Solar Power Policy for J&K
Jammu and Kashmir Energy Development Agency Page 8
9. SELF IDENTIFICATION OF PROJECTS
9.1 Self identification of sites shall be fully permissible. Whenever such a proposal is
received from an entity in respect of a particular project site (Govt. land) which has not yet
been advertised, the Nodal Agency shall proceed to examine the feasibility of the site for
setting up a Solar Power Plant and also determining the optimum power potential that can
be harnessed.
9.2 In case the project site is found feasible, it will be advertized to seek bids. Two-
stage bid process as mentioned in paras 7.1 shall be followed.
9.3 While evaluating a price bid, 10% price preference on the highest bid will be
given to the entity which has identified the project site. However, he will have to pay the
upfront premium at the level of the highest bid.
9.4 In case a proposal is received from an entity in respect of a project site ( private/
personal land), the Nodal Agency shall examine the feasibility of the site for setting up a
Solar Power Plant and also determine the optimum power potential that can be harnessed
and accordingly shall recommend the application of the Project Proponent to MNRE for
development of the site as per the guidelines of the scheme in vogue.
10. INCENTIVES TO THE POWER DEVELOPERS
10.1 Solar Power Plants (SPPs) installed and commissioned during the operative
period shall be eligible for the incentives declared under this policy, for a period of twenty
five years from the date of commissioning or as approved by MNRE or for the life span of
the Solar Power Plants (SPPs) which ever is earlier.
10.2 No entry tax will be levied by the state Govt. on Power generation/transmission
equipment and building material used for Solar Power Plants.
Solar Power Policy for J&K
Jammu and Kashmir Energy Development Agency Page 9
10.3 The Govt. land if required, for Power Projects shall be allotted on lease for 25
years at a premium of Rs. 1 per Kanal per annum.
10.4 In case of non availability of Govt. land, the land required shall be arranged by
the entity.
10.5 Wherever required, the state will acquire the land for the project under the
provisions of the J&K Land Acquisition Act and lease out the same to the entity for 25
years at a premium of Rs 1 per Kanal per annum plus an amount equal to the
compensation of land.
10.6 Wherever forest land is involved, the state will facilitate permission for use of
forest land for non forest purposes under the provisions of the J&K Forest Conservation
Act. However, the compensation required to be paid for the purpose including the amount
required for net present value, compensatory afforestation etc. will be paid by the entity.
10.7 Mortgage deed in favour of the financing institutions required to be signed by the
promoters shall be exempted from payment of stamp duty. The State Government has
already enabled equitable mortgage in the state.
10.8 Exemption from court fee for registration of documents relating to lease of land
will be granted to the entities.
10.9 No royalty in the shape of free power has to be paid for the Solar Power Projects.
However in case such provision is incorporated by the MNRE in the guidelines the same
shall be applicable.
10.10 Entities will be eligible for central financial assistance as per the guidelines of
MNRE, GoI as may be applicable besides other incentives given by the state or centre.
Solar Power Policy for J&K
Jammu and Kashmir Energy Development Agency Page 10
10.11 Electricity generated from the SPPs and used for self consumption / sale to third
party / sale to licensees shall be exempted from payment of Electricity Duty or shall be as
per the MNRE Guidelines.
10.12 Exemption from demand cut to the extent of 50% of the installed capacity of
SPPs, assigned for captive use purpose, shall be allowed.
11. SCHEDULE OF IMPLEMENTATION
11.1 Entity shall prepare and submit the DPR / Company Profile and other
information and make necessary applications for obtaining statutory clearances and
approvals from state Govt. and regulatory authority (as applicable) after carrying out
required confirmatory surveys and investigations as per prevailing regulations/norms. The
entity shall be responsible for providing all documents and submissions of documents to
concerned authorities within 12 months from the date of allotment. The state will facilitate
the process of seeking statutory and non-statuary clearances on best effort basis.
11.2 The entity shall achieve the financial closure within three months from the date of
receipt of all statutory approvals and clearances given by the state and Central
Governments. Financial closure would imply firm commitments for financing the entire
Project, with all pre-disbursement conditions having been fulfilled.
11.3 The Project shall be completed and made operational within a period of 24
months after receiving all statutory clearances.
11.4 The failure to fulfill any of the commitments/conditions will result in automatic
cancellation of the allotment of site and forfeiture of upfront premium amount. No
compensation would be payable to the entity in such instance.
11.5 The entity shall deposit upfront premium to the Nodal Agency within one month
from the date of allotment of the site.
Solar Power Policy for J&K
Jammu and Kashmir Energy Development Agency Page 11
12. WHEELING CHARGES
12.1 Wherever feasible, the infrastructure and transmission/distribution network of
PDD shall be available to entities for transmission of the power generated from the SPP.
However, the point of interface between the network of PDD and SPP shall be specified in
the agreement executed between PDD and the entity.
12.2 For sale of Power within or outside the state, wheeling charges shall be applicable
as determined under norms by the state regulator viz J&K SERC.
12.3 Facility for banking shall be for captive use only and not for third party sales.
13. SALE OF ENERGY
13.1 The energy generated from a Solar Power Plant, shall be sold to the PDD or any
third party in or outside the state.
13.2 In case of sale of Energy to PDD, the tariff shall be determined by the J&K
SERC.
13.3 Projects allotted under this policy will also be entitled to avail the
benefit/incentive as may be allowed by the MNRE, GoI from time to time.
14. PLANT AND MACHINERY
14.1 Only new plant and machinery shall be eligible for installation under this policy.
Solar Power Policy for J&K
Jammu and Kashmir Energy Development Agency Page 12
15. METERING OF ELECTRICITY
15.1 The Electricity Generated from the SPP shall be metered at the interconnection
point with the SEMs Conforming to the specification as laid down under Grid Code. These
meters shall be scaled jointly by the utility and the transmission company (PDD) and shall
be recorded on monthly basis at 00Hrs of the last day of the month and conveyed to SLDC
for energy accounting.
16. GRID CONNECTIVITY AND EVACUATION
FACILITY UPTO PDD SUB-SUBSTATION
16.1 The evacuation facility from the Solar Substation/Switch yard to the
Interconnection point shall be approved by PDD after carrying out the system study. The
power by the SPP can be injected at LT 11 KV & 33KV or above. Further, the
interconnection should be at the nearest distribution transformer/substation. In this regard,
the Project Proponent shall submit a letter from the concerned Distribution Utility
confirming technical feasibility of connecting the plant to the distribution
transformer/substation.
16.2 The transmission line from the Switch yard of the Solar Substation to the
Interconnection point shall be developed by the entity. They should be provided with the
communication facility for scheduling and monitoring on real time basis.
17. OPEN ACCESS FOR THIRD PARTY SALE
17.1 The developer shall have to apply for the Open Access and be subjected to Open
Access charges and losses as per regulations by JKSERC from time to time.
Solar Power Policy for J&K
Jammu and Kashmir Energy Development Agency Page 13
18. RENEWABLE PURCHASE OBLIGATION
18.1 The quantum of power that can be injected in the grid from Solar Power House
shall be governed by RPO as per JKSERC regulations in this regard.
19. REACTIVE POWER CHARGES
19.1 The drawl of reactive power shall be charged as per the JKSERC regulations, as
amended from time to time.
20. PENALTY FOR NON FULFILLING POWER
PURCHASE OBLIGATION
20.1 Distribution licensees in the state of J&K are mandated to purchase solar power
specified by JKSERC from time to time.
20.2 Distribution licensee failing to meet the minimum solar power purchase /
obligation specified by J&KSERC shall be liable to pay penalty at a rate of Rs. 12/KWh to
JAKEDA which will be passed on to the developer. Penalty shall not be levied on
distribution licensee in case of non-availability of adequate power from power project. This
will, however, be subject to the regulations of J&KSERC, if any, in this regard.
21. SHARING OF CLEAN DEVELOPMENT
MECHANISM (CDM) BENEFIT
21.1 The solar power project developer will pass on the gross benefits of CDM to the
distribution licensee with whom PPA is signed, as per the J&K SERC norms.
Solar Power Policy for J&K
Jammu and Kashmir Energy Development Agency Page 14
22. STATE GOVT FACILITATION AGENCY
22.1 JAKEDA and J&K PDC shall be the State Government facilitation Agencies for
facilitation and implementation of the solar power policy. These facilitation agencies will
facilitate and assist the project developers and undertake the following activities to achieve
the objects of the Policy:
a) Identification of suitable locations for solar projects, preparing a land bank and
creation / upgradation of connected infrastructure to the project site i.e roads etc.
b) Facilitation in arranging Right of Way, Water Supply and in obtaining clearances
and approvals which are in the purview of the State Government.
c) Recommending the project (subject to qualification) to avail benefits under any
policy declared or to be declared by Government of India
d) Promote Research and Development activities for cost effective sustainable and
environment friendly technologies in collaboration with internationally and nationally
reputed institutions.
e) Engage the services of national/global experts/consultants for Research and
Development of solar and other renewable technologies
f) Carry out awareness campaign on energy conservation and use of renewable
sources of energy at all levels ( i.e village, tehsil, district etc. through schools, colleges,
educational institutions, community centers and civil society organizations).
g) Along with project developers, develop appropriate manpower skills by tying up
with training or educational institutions through Public Private Partnership (PPP).
23. MID TERM REVIEW
23.1 State Government may undertake a mid term review of this policy after a period
of 5 years or as and when the need arises in view of any technological breakthrough or to
remove any inconsistencies with JKSERC Regulations made or any Govt. of India policy.
Solar Power Policy for J&K
Jammu and Kashmir Energy Development Agency Page 15
24. POWER TO REMOVE DIFFICULTIES
24.1 If any difficulty arises in giving effect to this policy, the project approval
committee is authorized to issue clarification as well as interpretation to such provisions, as
may appear to be necessary for removing the difficulty either on its own motion or after
hearing those parties who have sought clarifications for the provisions contained in the
policy.
25. REGULATORY OVERSIGHT
25.1 Aspects of this policy that require regulatory approvals from any concerned
Regulator would be subject to such approvals being given and would apply in the manner
approved by the regulator.
26. ROLE OF NODALAGENCY
26.1 JAKEDA will be the Nodal Agency in Jammu and Kashmir Divisions of the
State and LREDA & KREDA will be Nodal Agencies in respect of Leh and Kargil
Districts respectively. The Agencies will be responsible for :
i. Invitation of Bid.
ii. Evaluation of the bids received.
iii. Allotment of the SPP sites.
iv. Forwarding the project proposals to MNRE, GoI for grant of CFA applicable for
development of SPPs.
v. Monitoring the progress of the Project and project appraisals.
vi. Whenever MNRE invites applications under JNNSM for setting up of Solar Power
Plants, the Agency shall evaluate the bids as per the standing norms laid by the
MNRE for smooth implementation of the programme.
vii. In case any other Govt Department launches scheme for promotion of Solar Power
Plants (Off-grid or grid connected of any capacity) and are to be allotted on bidding
basis then the allotment shall be made by following the procedure laid down in this
policy subject to the condition they will not contradict the norms laid down in that
particular scheme.
Solar Power Policy for J&K
Jammu and Kashmir Energy Development Agency Page 16
27. PROJECT APPROVAL COMMITTEE
27.1 The Project approval Committee consisting of following members shall approve
the Solar Power Projects based on the financial & Technical criteria:
1. Administrative Head
Science & Technology Department
Chairman
2. Managing Director, J&K PDC Member
3. District Development Commissioner
(Concerned district)
Member
4. Representative of Finance Department Member
5. Representative of Power Dev. Deptt Member
6. Chief Executive Officer, JAKEDA Member-Secretary
28. DEFINITIONS
28.1 Following expressions used in the Policy would have meanings assigned to
them as defined here under:
i. ABT : Availability Based Tariff
ii. CFA : Central Financial Assistance
iii. CDM : Clean Development Mechanism
iv. Developer : A person who develops electricity and transfers it to
consumer
v. DPR : Detailed Project Report
vi. ENTITY : Independent Power Producer
vii. GoJK : Government of Jammu and Kashmir
viii. J&K : Jammu & Kashmir
ix. JAKEDA : Jammu & Kashmir Energy Development Agency
x. JKSERC : Jammu & Kashmir State Electricity Regulatory
Commission
xi. JNNSM : Jawaharlal Nehru National Solar Mission
xii. KREDA : Kargil Renewable Energy Development Agency
xiii. LREDA : Ladakh Renewable Energy Development Agency
xiv. MNRE : Ministry of New and Renewable Energy
xv. PDC : Power Development Corporation
xvi. PDD : Power Development Department
xvii. PPA : Power Purchase Agreement
xviii. Power producer: Entity or the Agency Developing MHP
xix. PRC : Permanent Resident Certificate
xx. R&D : Research & Development
xxi. RTU : Remote Terminal Unit
xxii. SPPs : Solar Power Plants

More Related Content

What's hot

Green Corner l2010
Green Corner l2010Green Corner l2010
Green Corner l2010Amit Bharti
 
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...Harish Sharma
 
China Clean Energy Industry Report, 2009 2010
China Clean Energy Industry Report, 2009 2010China Clean Energy Industry Report, 2009 2010
China Clean Energy Industry Report, 2009 2010ResearchInChina
 
A PROJECT REPORT ON ANALYSIS OF FINANCIAL STATEMENTS OF NATIONAL THERMAL PO...
A PROJECT REPORT ON ANALYSIS OF FINANCIAL STATEMENTS  OF  NATIONAL THERMAL PO...A PROJECT REPORT ON ANALYSIS OF FINANCIAL STATEMENTS  OF  NATIONAL THERMAL PO...
A PROJECT REPORT ON ANALYSIS OF FINANCIAL STATEMENTS OF NATIONAL THERMAL PO...Rohit Kumar
 
Ministry electric power_myanmar_2_27_13
Ministry electric power_myanmar_2_27_13Ministry electric power_myanmar_2_27_13
Ministry electric power_myanmar_2_27_13Seokho Shin
 
Power sector ,devlopment
Power sector ,devlopmentPower sector ,devlopment
Power sector ,devlopmentBhakti Parida
 
Final Report Biomass
Final Report BiomassFinal Report Biomass
Final Report BiomassNeel Patel
 
The Republic of the Union of Myanmar Ministry of Electricity and Energy Hydro...
The Republic of the Union of Myanmar Ministry of Electricity and Energy Hydro...The Republic of the Union of Myanmar Ministry of Electricity and Energy Hydro...
The Republic of the Union of Myanmar Ministry of Electricity and Energy Hydro...MYO AUNG Myanmar
 
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - DraftIndia's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - DraftHeadway Solar
 
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.Harish Sharma
 
New base energy news 04 may 2020 issue no. 1335 senior editor eng. khale...
New base energy news  04 may  2020   issue no. 1335  senior editor eng. khale...New base energy news  04 may  2020   issue no. 1335  senior editor eng. khale...
New base energy news 04 may 2020 issue no. 1335 senior editor eng. khale...Khaled Al Awadi
 
India power transmission & distribution sector opportunity outlook 2025
India power transmission & distribution sector opportunity outlook 2025India power transmission & distribution sector opportunity outlook 2025
India power transmission & distribution sector opportunity outlook 2025Rajesh Sarma
 
Manipur solar policy 2014
Manipur solar policy 2014Manipur solar policy 2014
Manipur solar policy 2014Headway Solar
 
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...Harish Sharma
 
Feasibility Study of Low Carbon Energy Investments in Jordan. By Bashar Zagha
Feasibility Study of Low Carbon Energy Investments in Jordan. By Bashar ZaghaFeasibility Study of Low Carbon Energy Investments in Jordan. By Bashar Zagha
Feasibility Study of Low Carbon Energy Investments in Jordan. By Bashar Zaghabasharzagha
 
ICF ppt India Infrastructure - The road ahead for Power sector 16th May 2016
ICF ppt India Infrastructure - The road ahead for Power sector 16th May 2016ICF ppt India Infrastructure - The road ahead for Power sector 16th May 2016
ICF ppt India Infrastructure - The road ahead for Power sector 16th May 2016Ashish Singla
 
Electricity.2013.slides
Electricity.2013.slidesElectricity.2013.slides
Electricity.2013.slidesZaw Aung
 

What's hot (19)

Green Corner l2010
Green Corner l2010Green Corner l2010
Green Corner l2010
 
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
250 MW GRID CONNECTED SOLAR PV POWER PROJECTS UNDER JNNSM PHASE II BATCH-III ...
 
China Clean Energy Industry Report, 2009 2010
China Clean Energy Industry Report, 2009 2010China Clean Energy Industry Report, 2009 2010
China Clean Energy Industry Report, 2009 2010
 
A PROJECT REPORT ON ANALYSIS OF FINANCIAL STATEMENTS OF NATIONAL THERMAL PO...
A PROJECT REPORT ON ANALYSIS OF FINANCIAL STATEMENTS  OF  NATIONAL THERMAL PO...A PROJECT REPORT ON ANALYSIS OF FINANCIAL STATEMENTS  OF  NATIONAL THERMAL PO...
A PROJECT REPORT ON ANALYSIS OF FINANCIAL STATEMENTS OF NATIONAL THERMAL PO...
 
9-Energy
9-Energy9-Energy
9-Energy
 
Ministry electric power_myanmar_2_27_13
Ministry electric power_myanmar_2_27_13Ministry electric power_myanmar_2_27_13
Ministry electric power_myanmar_2_27_13
 
Power sector ,devlopment
Power sector ,devlopmentPower sector ,devlopment
Power sector ,devlopment
 
Final Report Biomass
Final Report BiomassFinal Report Biomass
Final Report Biomass
 
The Republic of the Union of Myanmar Ministry of Electricity and Energy Hydro...
The Republic of the Union of Myanmar Ministry of Electricity and Energy Hydro...The Republic of the Union of Myanmar Ministry of Electricity and Energy Hydro...
The Republic of the Union of Myanmar Ministry of Electricity and Energy Hydro...
 
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - DraftIndia's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
 
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
Solar Power Scheme for Unemployed Youth and Farmers in Himachal Pradesh.
 
New base energy news 04 may 2020 issue no. 1335 senior editor eng. khale...
New base energy news  04 may  2020   issue no. 1335  senior editor eng. khale...New base energy news  04 may  2020   issue no. 1335  senior editor eng. khale...
New base energy news 04 may 2020 issue no. 1335 senior editor eng. khale...
 
India power transmission & distribution sector opportunity outlook 2025
India power transmission & distribution sector opportunity outlook 2025India power transmission & distribution sector opportunity outlook 2025
India power transmission & distribution sector opportunity outlook 2025
 
Manipur solar policy 2014
Manipur solar policy 2014Manipur solar policy 2014
Manipur solar policy 2014
 
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
RfS for Selection of “500 MW Grid Connected Solar Power Projects in Maharasht...
 
Feasibility Study of Low Carbon Energy Investments in Jordan. By Bashar Zagha
Feasibility Study of Low Carbon Energy Investments in Jordan. By Bashar ZaghaFeasibility Study of Low Carbon Energy Investments in Jordan. By Bashar Zagha
Feasibility Study of Low Carbon Energy Investments in Jordan. By Bashar Zagha
 
ICF ppt India Infrastructure - The road ahead for Power sector 16th May 2016
ICF ppt India Infrastructure - The road ahead for Power sector 16th May 2016ICF ppt India Infrastructure - The road ahead for Power sector 16th May 2016
ICF ppt India Infrastructure - The road ahead for Power sector 16th May 2016
 
Electricity.2013.slides
Electricity.2013.slidesElectricity.2013.slides
Electricity.2013.slides
 
Indian Power Sector
Indian Power SectorIndian Power Sector
Indian Power Sector
 

Viewers also liked

Tracxn Wind Energy Landscape Report July 2016
Tracxn Wind Energy Landscape Report July 2016Tracxn Wind Energy Landscape Report July 2016
Tracxn Wind Energy Landscape Report July 2016Tracxn
 
Financing the Next Generation of Solar Workers
Financing the Next Generation of Solar WorkersFinancing the Next Generation of Solar Workers
Financing the Next Generation of Solar WorkersThe Solar Foundation
 
Solar Schools: Potential Savings by District
Solar Schools: Potential Savings by DistrictSolar Schools: Potential Savings by District
Solar Schools: Potential Savings by DistrictThe Solar Foundation
 
National Solar Jobs Census 2010 Executive Summary
National Solar Jobs Census 2010 Executive SummaryNational Solar Jobs Census 2010 Executive Summary
National Solar Jobs Census 2010 Executive SummaryThe Solar Foundation
 
Agenda - GW Solar Symposium 2012
Agenda - GW Solar Symposium 2012 Agenda - GW Solar Symposium 2012
Agenda - GW Solar Symposium 2012 GW Solar Institute
 
Specification No. 119440: RFP for New 311 System for the Municipal Government...
Specification No. 119440: RFP for New 311 System for the Municipal Government...Specification No. 119440: RFP for New 311 System for the Municipal Government...
Specification No. 119440: RFP for New 311 System for the Municipal Government...Smart Chicago Collaborative
 
Tamilnadu solar energy policy 2012
Tamilnadu solar energy policy 2012Tamilnadu solar energy policy 2012
Tamilnadu solar energy policy 2012Headway Solar
 
National Solar Jobs Census 2013 Teleconference Transcript
National Solar Jobs Census 2013 Teleconference TranscriptNational Solar Jobs Census 2013 Teleconference Transcript
National Solar Jobs Census 2013 Teleconference TranscriptThe Solar Foundation
 
National Solar Jobs Census 2012 Fact Sheet
National Solar Jobs Census 2012 Fact SheetNational Solar Jobs Census 2012 Fact Sheet
National Solar Jobs Census 2012 Fact SheetThe Solar Foundation
 
Softer Solar Landings: Options to Avoid the Investment Tax Credit Cliff
Softer Solar Landings: Options to Avoid the Investment Tax Credit CliffSofter Solar Landings: Options to Avoid the Investment Tax Credit Cliff
Softer Solar Landings: Options to Avoid the Investment Tax Credit CliffGW Solar Institute
 
Haryana solar power policy 2014
Haryana solar power policy 2014Haryana solar power policy 2014
Haryana solar power policy 2014Headway Solar
 
Tender Document for 3 MW solar plant at Diu
Tender Document for 3 MW solar plant at DiuTender Document for 3 MW solar plant at Diu
Tender Document for 3 MW solar plant at DiuHeadway Solar
 
National Solar Jobs Census 2013
National Solar Jobs Census 2013National Solar Jobs Census 2013
National Solar Jobs Census 2013GW Solar Institute
 

Viewers also liked (20)

Tracxn Wind Energy Landscape Report July 2016
Tracxn Wind Energy Landscape Report July 2016Tracxn Wind Energy Landscape Report July 2016
Tracxn Wind Energy Landscape Report July 2016
 
Wind energy(Pakistan)
Wind energy(Pakistan)Wind energy(Pakistan)
Wind energy(Pakistan)
 
Financing the Next Generation of Solar Workers
Financing the Next Generation of Solar WorkersFinancing the Next Generation of Solar Workers
Financing the Next Generation of Solar Workers
 
Minnesota Solar Jobs Census 2013
Minnesota Solar Jobs Census 2013Minnesota Solar Jobs Census 2013
Minnesota Solar Jobs Census 2013
 
Solar Schools: Potential Savings by District
Solar Schools: Potential Savings by DistrictSolar Schools: Potential Savings by District
Solar Schools: Potential Savings by District
 
National Solar Jobs Census 2010 Executive Summary
National Solar Jobs Census 2010 Executive SummaryNational Solar Jobs Census 2010 Executive Summary
National Solar Jobs Census 2010 Executive Summary
 
Agenda - GW Solar Symposium 2012
Agenda - GW Solar Symposium 2012 Agenda - GW Solar Symposium 2012
Agenda - GW Solar Symposium 2012
 
Specification No. 119440: RFP for New 311 System for the Municipal Government...
Specification No. 119440: RFP for New 311 System for the Municipal Government...Specification No. 119440: RFP for New 311 System for the Municipal Government...
Specification No. 119440: RFP for New 311 System for the Municipal Government...
 
Top 5 States Sector Breakdowns
Top 5 States Sector BreakdownsTop 5 States Sector Breakdowns
Top 5 States Sector Breakdowns
 
Tamilnadu solar energy policy 2012
Tamilnadu solar energy policy 2012Tamilnadu solar energy policy 2012
Tamilnadu solar energy policy 2012
 
National Solar Jobs Census 2013 Teleconference Transcript
National Solar Jobs Census 2013 Teleconference TranscriptNational Solar Jobs Census 2013 Teleconference Transcript
National Solar Jobs Census 2013 Teleconference Transcript
 
Arizona Solar Jobs Census 2013
Arizona Solar Jobs Census 2013Arizona Solar Jobs Census 2013
Arizona Solar Jobs Census 2013
 
National Solar Jobs Census 2012 Fact Sheet
National Solar Jobs Census 2012 Fact SheetNational Solar Jobs Census 2012 Fact Sheet
National Solar Jobs Census 2012 Fact Sheet
 
California Solar Jobs Census 2013
California Solar Jobs Census 2013California Solar Jobs Census 2013
California Solar Jobs Census 2013
 
Softer Solar Landings: Options to Avoid the Investment Tax Credit Cliff
Softer Solar Landings: Options to Avoid the Investment Tax Credit CliffSofter Solar Landings: Options to Avoid the Investment Tax Credit Cliff
Softer Solar Landings: Options to Avoid the Investment Tax Credit Cliff
 
Advantages of Solar Energy
Advantages of Solar EnergyAdvantages of Solar Energy
Advantages of Solar Energy
 
Haryana solar power policy 2014
Haryana solar power policy 2014Haryana solar power policy 2014
Haryana solar power policy 2014
 
Get started with solar
Get started with solarGet started with solar
Get started with solar
 
Tender Document for 3 MW solar plant at Diu
Tender Document for 3 MW solar plant at DiuTender Document for 3 MW solar plant at Diu
Tender Document for 3 MW solar plant at Diu
 
National Solar Jobs Census 2013
National Solar Jobs Census 2013National Solar Jobs Census 2013
National Solar Jobs Census 2013
 

Similar to J&K Solar policy 2010

Andhra pradesh solar policy 2015
Andhra pradesh solar policy 2015Andhra pradesh solar policy 2015
Andhra pradesh solar policy 2015Headway Solar
 
UP Solar Power Policy 2013
UP Solar Power Policy 2013UP Solar Power Policy 2013
UP Solar Power Policy 2013Headway Solar
 
Jharkhand solar power policy 2013
Jharkhand solar power policy 2013Jharkhand solar power policy 2013
Jharkhand solar power policy 2013Headway Solar
 
Ap solar policy 2012.
Ap solar policy 2012.Ap solar policy 2012.
Ap solar policy 2012.antastoya
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeSanman Rajput
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeSanman Rajput
 
India solar-policy-element-casting-shadow-on-harnessing-the-potential
India solar-policy-element-casting-shadow-on-harnessing-the-potentialIndia solar-policy-element-casting-shadow-on-harnessing-the-potential
India solar-policy-element-casting-shadow-on-harnessing-the-potentialRajapandiS
 
Kerala solar energy policy 2013
Kerala solar energy policy 2013Kerala solar energy policy 2013
Kerala solar energy policy 2013Headway Solar
 
Deployment of micro grids in india
Deployment of micro grids in indiaDeployment of micro grids in india
Deployment of micro grids in indiaAjeet1364
 
India's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - DraftIndia's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - DraftHeadway Solar
 
Odisha solar policy 2013 draft
Odisha solar policy 2013 draftOdisha solar policy 2013 draft
Odisha solar policy 2013 draftHeadway Solar
 
Odisha solar-power-policy
Odisha solar-power-policyOdisha solar-power-policy
Odisha solar-power-policyJay Ranvir
 
Draft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projectsDraft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projectsSanman Rajput
 
Solar India - Sun Power is Solution to India's Energy Crisis
Solar India - Sun Power is Solution to India's Energy CrisisSolar India - Sun Power is Solution to India's Energy Crisis
Solar India - Sun Power is Solution to India's Energy Crisissolarindia
 
India’s solar policies
India’s solar policiesIndia’s solar policies
India’s solar policiesNaresh Goud
 

Similar to J&K Solar policy 2010 (20)

Andhra pradesh solar policy 2015
Andhra pradesh solar policy 2015Andhra pradesh solar policy 2015
Andhra pradesh solar policy 2015
 
UP Solar Power Policy 2013
UP Solar Power Policy 2013UP Solar Power Policy 2013
UP Solar Power Policy 2013
 
Jharkhand solar power policy 2013
Jharkhand solar power policy 2013Jharkhand solar power policy 2013
Jharkhand solar power policy 2013
 
Solar power - A developer prespective
Solar power - A developer prespectiveSolar power - A developer prespective
Solar power - A developer prespective
 
Ap solar policy 2012.
Ap solar policy 2012.Ap solar policy 2012.
Ap solar policy 2012.
 
Solar power plant Opportunity and Costing
Solar power plant Opportunity and CostingSolar power plant Opportunity and Costing
Solar power plant Opportunity and Costing
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-scheme
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-scheme
 
India solar-policy-element-casting-shadow-on-harnessing-the-potential
India solar-policy-element-casting-shadow-on-harnessing-the-potentialIndia solar-policy-element-casting-shadow-on-harnessing-the-potential
India solar-policy-element-casting-shadow-on-harnessing-the-potential
 
Kerala solar energy policy 2013
Kerala solar energy policy 2013Kerala solar energy policy 2013
Kerala solar energy policy 2013
 
Deployment of micro grids in india
Deployment of micro grids in indiaDeployment of micro grids in india
Deployment of micro grids in india
 
India's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - DraftIndia's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - Draft
 
Odisha solar policy 2013 draft
Odisha solar policy 2013 draftOdisha solar policy 2013 draft
Odisha solar policy 2013 draft
 
Odisha solar-power-policy
Odisha solar-power-policyOdisha solar-power-policy
Odisha solar-power-policy
 
Draft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projectsDraft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projects
 
Success Story of Solar Parks in India
Success Story of Solar Parks in IndiaSuccess Story of Solar Parks in India
Success Story of Solar Parks in India
 
Solar India - Sun Power is Solution to India's Energy Crisis
Solar India - Sun Power is Solution to India's Energy CrisisSolar India - Sun Power is Solution to India's Energy Crisis
Solar India - Sun Power is Solution to India's Energy Crisis
 
India’s solar policies
India’s solar policiesIndia’s solar policies
India’s solar policies
 
SOLAR MISSION
SOLAR MISSION SOLAR MISSION
SOLAR MISSION
 
Grid Connected Roof Top Solar Power Generation: A Review
Grid Connected Roof Top Solar Power Generation: A ReviewGrid Connected Roof Top Solar Power Generation: A Review
Grid Connected Roof Top Solar Power Generation: A Review
 

More from Headway Solar

Tender Document for Procurement of 150MW of Solar Power from Grid Connected S...
Tender Document for Procurement of 150MW of Solar Power from Grid Connected S...Tender Document for Procurement of 150MW of Solar Power from Grid Connected S...
Tender Document for Procurement of 150MW of Solar Power from Grid Connected S...Headway Solar
 
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Headway Solar
 
RERC Net metering Regulations 2015
RERC Net metering Regulations 2015RERC Net metering Regulations 2015
RERC Net metering Regulations 2015Headway Solar
 
Draft MERC Net Metering for Solar Rooftop Regulations,2015
Draft MERC Net Metering for Solar Rooftop Regulations,2015Draft MERC Net Metering for Solar Rooftop Regulations,2015
Draft MERC Net Metering for Solar Rooftop Regulations,2015Headway Solar
 
DERC Renewable energy Net Metering Regulations 2014
DERC Renewable energy Net Metering Regulations 2014DERC Renewable energy Net Metering Regulations 2014
DERC Renewable energy Net Metering Regulations 2014Headway Solar
 
Solar Power - Grid Connected Ground Mounted and Solar Rooftop and Metering Re...
Solar Power - Grid Connected Ground Mounted and Solar Rooftop and Metering Re...Solar Power - Grid Connected Ground Mounted and Solar Rooftop and Metering Re...
Solar Power - Grid Connected Ground Mounted and Solar Rooftop and Metering Re...Headway Solar
 
Final draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft Guidelines
Final draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft GuidelinesFinal draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft Guidelines
Final draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft GuidelinesHeadway Solar
 
Renewable policy 2012 of West Bengal
Renewable policy 2012 of West BengalRenewable policy 2012 of West Bengal
Renewable policy 2012 of West BengalHeadway Solar
 
Tender document for solar in Dehradun, Uttarakhand
Tender document for solar in Dehradun, UttarakhandTender document for solar in Dehradun, Uttarakhand
Tender document for solar in Dehradun, UttarakhandHeadway Solar
 
Uttarakhand solar power policy 2013
Uttarakhand solar power policy 2013Uttarakhand solar power policy 2013
Uttarakhand solar power policy 2013Headway Solar
 
RFP Documents for Solar Plant in Uttar Pradesh
RFP Documents for Solar Plant in Uttar PradeshRFP Documents for Solar Plant in Uttar Pradesh
RFP Documents for Solar Plant in Uttar PradeshHeadway Solar
 
Telangana solar RFS Document 2014
Telangana solar RFS Document 2014Telangana solar RFS Document 2014
Telangana solar RFS Document 2014Headway Solar
 
Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...
Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...
Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...Headway Solar
 
RFP Document for solar PV Project Rajasthan
RFP Document for solar PV Project RajasthanRFP Document for solar PV Project Rajasthan
RFP Document for solar PV Project RajasthanHeadway Solar
 
Rajasthan Solar Roof Top tender 2014-2015
Rajasthan Solar Roof Top tender 2014-2015Rajasthan Solar Roof Top tender 2014-2015
Rajasthan Solar Roof Top tender 2014-2015Headway Solar
 
Rajasthan solar policy of 2014
Rajasthan solar policy of 2014Rajasthan solar policy of 2014
Rajasthan solar policy of 2014Headway Solar
 
RFP for Solar Power Plant in Punjab
RFP for Solar Power Plant in PunjabRFP for Solar Power Plant in Punjab
RFP for Solar Power Plant in PunjabHeadway Solar
 
New and renewable sources of energy (NRSE) policy – 2012
New and renewable sources of energy (NRSE) policy – 2012New and renewable sources of energy (NRSE) policy – 2012
New and renewable sources of energy (NRSE) policy – 2012Headway Solar
 
RFP Document of Solar Power Project in Karnataka
RFP Document of Solar Power Project in KarnatakaRFP Document of Solar Power Project in Karnataka
RFP Document of Solar Power Project in KarnatakaHeadway Solar
 
Karnataka solar policy 2014-2021
Karnataka solar policy 2014-2021Karnataka solar policy 2014-2021
Karnataka solar policy 2014-2021Headway Solar
 

More from Headway Solar (20)

Tender Document for Procurement of 150MW of Solar Power from Grid Connected S...
Tender Document for Procurement of 150MW of Solar Power from Grid Connected S...Tender Document for Procurement of 150MW of Solar Power from Grid Connected S...
Tender Document for Procurement of 150MW of Solar Power from Grid Connected S...
 
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
 
RERC Net metering Regulations 2015
RERC Net metering Regulations 2015RERC Net metering Regulations 2015
RERC Net metering Regulations 2015
 
Draft MERC Net Metering for Solar Rooftop Regulations,2015
Draft MERC Net Metering for Solar Rooftop Regulations,2015Draft MERC Net Metering for Solar Rooftop Regulations,2015
Draft MERC Net Metering for Solar Rooftop Regulations,2015
 
DERC Renewable energy Net Metering Regulations 2014
DERC Renewable energy Net Metering Regulations 2014DERC Renewable energy Net Metering Regulations 2014
DERC Renewable energy Net Metering Regulations 2014
 
Solar Power - Grid Connected Ground Mounted and Solar Rooftop and Metering Re...
Solar Power - Grid Connected Ground Mounted and Solar Rooftop and Metering Re...Solar Power - Grid Connected Ground Mounted and Solar Rooftop and Metering Re...
Solar Power - Grid Connected Ground Mounted and Solar Rooftop and Metering Re...
 
Final draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft Guidelines
Final draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft GuidelinesFinal draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft Guidelines
Final draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft Guidelines
 
Renewable policy 2012 of West Bengal
Renewable policy 2012 of West BengalRenewable policy 2012 of West Bengal
Renewable policy 2012 of West Bengal
 
Tender document for solar in Dehradun, Uttarakhand
Tender document for solar in Dehradun, UttarakhandTender document for solar in Dehradun, Uttarakhand
Tender document for solar in Dehradun, Uttarakhand
 
Uttarakhand solar power policy 2013
Uttarakhand solar power policy 2013Uttarakhand solar power policy 2013
Uttarakhand solar power policy 2013
 
RFP Documents for Solar Plant in Uttar Pradesh
RFP Documents for Solar Plant in Uttar PradeshRFP Documents for Solar Plant in Uttar Pradesh
RFP Documents for Solar Plant in Uttar Pradesh
 
Telangana solar RFS Document 2014
Telangana solar RFS Document 2014Telangana solar RFS Document 2014
Telangana solar RFS Document 2014
 
Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...
Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...
Guidelines for Grid-connected Small Scale (Rooftop) Solar PV Systems for Tami...
 
RFP Document for solar PV Project Rajasthan
RFP Document for solar PV Project RajasthanRFP Document for solar PV Project Rajasthan
RFP Document for solar PV Project Rajasthan
 
Rajasthan Solar Roof Top tender 2014-2015
Rajasthan Solar Roof Top tender 2014-2015Rajasthan Solar Roof Top tender 2014-2015
Rajasthan Solar Roof Top tender 2014-2015
 
Rajasthan solar policy of 2014
Rajasthan solar policy of 2014Rajasthan solar policy of 2014
Rajasthan solar policy of 2014
 
RFP for Solar Power Plant in Punjab
RFP for Solar Power Plant in PunjabRFP for Solar Power Plant in Punjab
RFP for Solar Power Plant in Punjab
 
New and renewable sources of energy (NRSE) policy – 2012
New and renewable sources of energy (NRSE) policy – 2012New and renewable sources of energy (NRSE) policy – 2012
New and renewable sources of energy (NRSE) policy – 2012
 
RFP Document of Solar Power Project in Karnataka
RFP Document of Solar Power Project in KarnatakaRFP Document of Solar Power Project in Karnataka
RFP Document of Solar Power Project in Karnataka
 
Karnataka solar policy 2014-2021
Karnataka solar policy 2014-2021Karnataka solar policy 2014-2021
Karnataka solar policy 2014-2021
 

Recently uploaded

PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORSPPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORSgovindsharma81649
 
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Call Girls in Nagpur High Profile
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxPeter Miles
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)NAP Global Network
 
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...tanu pandey
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learningNAP Global Network
 
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...tanu pandey
 
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...robinsonayot
 
2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos WebinarLinda Reinstein
 
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...MOHANI PANDEY
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)ahcitycouncil
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxSwastiRanjanNayak
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Dipal Arora
 
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginningsinfo695895
 
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...SUHANI PANDEY
 
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...SUHANI PANDEY
 
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...SUHANI PANDEY
 
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
An Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCAn Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCNAP Global Network
 

Recently uploaded (20)

PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORSPPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
 
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari ⟟ 6297143586 ⟟ Call Me For Genuine Sex Ser...
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)
 
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learning
 
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
 
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...
TEST BANK For Essentials of Negotiation, 7th Edition by Roy Lewicki, Bruce Ba...
 
2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar
 
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Budhwar Peth Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
 
PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)PPT Item # 4 - 231 Encino Ave (Significance Only)
PPT Item # 4 - 231 Encino Ave (Significance Only)
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptx
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation -  Humble BeginningsZechariah Boodey Farmstead Collaborative presentation -  Humble Beginnings
Zechariah Boodey Farmstead Collaborative presentation - Humble Beginnings
 
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
 
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
 
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
VIP Model Call Girls Shikrapur ( Pune ) Call ON 8005736733 Starting From 5K t...
 
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
 
An Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCAn Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCC
 

J&K Solar policy 2010

  • 1. Solar Power Policy for J&K JAKEDA JAMMU AND KASHMIR ENERGY DEVELOPMENT AGENCY Government of Jammu and Kashmir
  • 2. Solar Power Policy for J&K Jammu and Kashmir Energy Development Agency Page 2 Table of contents 1. INTRODUCTION……………………………………………………………………….3 2. NEED FOR SOLAR POWER PROJECTS……………………………………............4 3. OBJECTIVES……………………………….……………………………..…………….5 4. OPERATIVE PERIOD ………………………………………………………….……..5 5. CAPACITY CAP……………………………………………….…………………….…5 6. ELIGIBLE UNIT…………………………………………….……………………….…6 7. PROCEDURE FOR ALLOTMENT OF SITES FOR DEVELOPMENT OF SOLAR POWER PLANTS……………………….………………………………..6 8. EVALUATION / PRE-QUALIFICATION CRITERIA ……………………………..7 9. SELF IDENTIFICATION OF PROJECTS……………………………..……….……8 10. INCENTIVES TO THE POWER DEVELOPERS ……………………….…………8 11. SCHEDULE OF IMPLEMENTATION……………………………………..…….…10 12. WHEELING CHARGES………………………………………………………..……..11 13. SALE OF ENERGY…………………………………………………………….….…..11 14. PLANT AND MACHINERY………………………………………………….….…...11 15. METERING OF ELECTRICITY ……………………………………………….…..12 16. GRID CONNECTIVITY AND EVACUATION FACILITY UPTO PDD SUB-SUBSTATION………………………………………………………....…..12 17. OPEN ACCESS FOR THIRD PARTY SALE ………………………………….…..12 18. RENEWABLE PURCHASE OBLIGATION …………………………..…………..13 19. REACTIVE POWER CHARGES……………………………………………………13 20. PENALTY FOR NON FULFILLING POWER PURCHASE OBLIGATION…..13 21. SHARING OF CLEAN DEVELOPMENT MECHANISM (CDM) BENEFIT ….13 22. STATE GOVT FACILITATION AGENCY………………………………………..14 23. MID TERM REVIEW…………………………………………………………….…..14 24. POWER TO REMOVE DIFFICULTIES…………………………………………...15 25. REGULATORY OVERSIGHT……………………………………………………...15 26. ROLE OF NODAL AGENCY ……………………………………………………….15 27. PROJECT APPROVAL COMMITTEE…………………………………………...16 28. DEFINITIONS………………………………………………………………………...16
  • 3. Solar Power Policy for J&K Jammu and Kashmir Energy Development Agency Page 3 1. INTRODUCTION 1.1 The challenges of climate change and global warming continuously threaten the world community. The Government of Jammu & Kashmir has taken note of the growing recognition of impact of climate change at the local, national and global levels. The Government recognizes the urgent need to tackle challenges that arise on account of these impacts through integrated policy prescriptions and programmes aimed at mitigation of impacts and adaptation to reduce vulnerability of systems. The Government is also cognizant of the cross-cutting nature of impacts with enormous cost implications for tackling them and that these costs could escalate if preventive action is not taken immediately. Besides this MNRE has launched Jawaharlal Nehru National Solar Mission (JNNSM) under the brand 'Solar India' with the objective to establish India as a global leader in solar energy, by creating the policy conditions for its diffusion across the country as quickly as possible. The Mission has set a target of 20,000MWand stipulates implementation and achievement of the target in 3 phases (first phase upto 2012-13, second phase from 2013 to 2017 and the third phase from 2017 to 2022) for various components, including grid connected solar power. 1.2 The successful implementation of the JNNSM requires the identification of resources to overcome the financial, investment, technology, institutional and other related barriers which confront solar power development in India. The penetration of solar power, therefore, requires substantial support. The policy framework of the Mission will facilitate the process of achieving grid parity by 2022. 1.3 To ramp up capacity of grid-connected solar power generation to 1000 MW within three years – by 2013; an additional 3000 MW by 2017 through the mandatory use of the renewable purchase obligation by utilities backed with a preferential tariff. This capacity can be more than doubled – reaching 10,000MW installed power by 2017 and 20,000 MW or more by 2022 in the country. The transition could be appropriately up scaled, based on availability of international finance and technology.
  • 4. Solar Power Policy for J&K Jammu and Kashmir Energy Development Agency Page 4 2. NEED FOR SOLAR POWER PROJECTS 2.1 Solar energy is environmentally friendly as it has zero emissions while generating electricity or heat. The exhaustible reserves of fossil fuels and their volatile market prices further contribute towards energy insecurity. Government recognizes the central role of energy and the need to have a policy to promote efficient use of conventional energy together with proactive establishment and promotion of sustained use of new and non- conventional energy sources and applications to reduce emissions and other impacts of climate change. Based on this “climate efficient initiative” the state has decided to promote energy efficiency measures, adopt preventive management techniques and build capacities for all the concerned stakeholders to contribute and sustain successful transitions to a more energy efficient future duly emphasizing the local relevance of alternatives. 2.2 From an energy security perspective, solar is the most secure of all sources, since it is abundantly available. Theoretically, a small fraction of the total incident solar energy (if captured effectively) can meet the entire country’s power requirements. It is also clear that given the large proportion of poor and energy un-served population in the country, every effort needs to be made to exploit the relatively abundant sources of energy available to the country. While, today, domestic coal based power generation is the cheapest electricity source, future scenarios suggest that this could well change. Already, faced with crippling electricity shortages, price of electricity traded internally, touched Rs 7 per unit for base loads and around Rs 8.50 per unit during peak periods. The situation will also change, as the country moves towards imported coal to meet its energy demand. The price of power will have to factor in the availability of coal in international markets and the cost of developing import infrastructure. It is also evident that as the cost of environmental degradation is factored into the mining of coal, as it must, the price of this raw material will increase. In the situation of energy shortages, the country is increasing the use of diesel-based electricity, which is both expensive – costs as high as Rs 15 per unit - and polluting. It is in this situation the solar imperative is both urgent and feasible to enable the country to meet long-term energy needs.
  • 5. Solar Power Policy for J&K Jammu and Kashmir Energy Development Agency Page 5 3. OBJECTIVES 3.1 The State Government introduces the Solar Power Policy with the following objectives : i) Promoting generation of green and clean power in the State using Solar Energy ii) To meet the targets to be achieved countrywide under JNNSM. iii) To put in place an appropriate investment climate, that could leverage the Clean Development Mechanism (CDM). iv) Productive use of the wastelands, thereby fostering a socio-economic transformation. v) Employment generation and skill enhancement of local youth. vi) Promotion of R&D and facilitation of technology transfer vii)Establish core technical competence in professionals in the state to initiate and sustain use and effective management of newer energy applications. viii) Creation of environmental consciousness among citizens 4. OPERATIVE PERIOD 4.1 The Policy will come into operation with effect from its publication in the State Gazette and will remain in force until superseded or modified by another Policy. 5. CAPACITY CAP 5.1 The minimum project capacity shall be 1 MW. However, if MNRE launches any scheme for lower capacity power plant then that shall also be considered.
  • 6. Solar Power Policy for J&K Jammu and Kashmir Energy Development Agency Page 6 6. ELIGIBLE UNIT 6.1 Any company or body corporate or association or body of individuals or project proponents as per MNRE Schemes/ guidelines launched/issued from time to time will be eligible for setting up of Solar Power Plants (SPPs), for the purpose of captive use and / or for selling of electricity as per MNRE / JKSERC norms. 7. PROCEDURE FOR ALLOTMENT OF SITES FOR DEVELOPMENT OF SOLAR POWER PLANTS 7.1 The Nodal Agency shall prepare a Land Bank containing list of potential sites for development of Solar Power Plants and such sites shall be allotted as per following procedure.. (i) The available sites shall be advertized to seek bids. (ii) All the applications received in response to the advertisement shall be subject to pre-qualification as per evaluation criteria. The applications shall be accompanied with a non-refundable Demand Draft of Rs.10,000/- as processing fees or as applicable under the MNRE scheme. (iii) Bids shall be invited on the basis of upfront premium payable to GoJK and shall quote this premium up to 100 of Rupees. (iv) The bids shall be subject to two-stage scrutiny. In the first stage the pre qualification of bids will be conducted on the basis of financial and technical capacity in the manner as specified in the bid document or MNRE guidelines as per the scheme. (v) The bidders which are found technically responsive shall be asked to submit their price bids based on upfront premium per MW payable to the GoJK. (vi) The minimum threshold premium will be Rs.2.00 lakhs per MW. Bids received beneath this threshold shall be rejected.
  • 7. Solar Power Policy for J&K Jammu and Kashmir Energy Development Agency Page 7 (vii) The project shall be allotted to the bidder making the highest bid. (viii) In case two or more bidders bid identical premium for a site then the bidder securing the highest technical score during pre-qualification shall be awarded the project. (ix) If after advertisement of the project site, only one tender is received, fresh advertisement would be issued. If a single bid is again received in response to the second advertisement, the said bid shall be considered on the basis of technical and commercial capacity with minimum threshold premium or premium quoted by him whichever is higher. 7.2 In case the Project Proponent arranges land of his own then all the Financial/ Technical/ other conditions laid down by the MNRE under the particular scheme shall be applicable. 8. EVALUATION / PRE-QUALIFICATION CRITERIA 8.1 Pre qualification of bidders will be based on financial and technical capacity to mobilize the required resources. Applications will be graded on the basis of balance sheets, annual reports and other supported evidence of financial and technical capabilities. 8.2 The weightage to be given to financial capacity, technical capability, past experience and other relevant attributes of the applicants, the sub-categories of these attributes to be evaluated and their inter-se weightage, the guidelines for evaluation and the passing score on attributes /in aggregate required for pre-qualification shall be specified in the bid documents inviting bids for pre-qualification. 8.3 Any entity in order to technically qualify shall be required to have an agreement with proven technology supplier of Solar Power Projects for supply of equipments for the plant.
  • 8. Solar Power Policy for J&K Jammu and Kashmir Energy Development Agency Page 8 9. SELF IDENTIFICATION OF PROJECTS 9.1 Self identification of sites shall be fully permissible. Whenever such a proposal is received from an entity in respect of a particular project site (Govt. land) which has not yet been advertised, the Nodal Agency shall proceed to examine the feasibility of the site for setting up a Solar Power Plant and also determining the optimum power potential that can be harnessed. 9.2 In case the project site is found feasible, it will be advertized to seek bids. Two- stage bid process as mentioned in paras 7.1 shall be followed. 9.3 While evaluating a price bid, 10% price preference on the highest bid will be given to the entity which has identified the project site. However, he will have to pay the upfront premium at the level of the highest bid. 9.4 In case a proposal is received from an entity in respect of a project site ( private/ personal land), the Nodal Agency shall examine the feasibility of the site for setting up a Solar Power Plant and also determine the optimum power potential that can be harnessed and accordingly shall recommend the application of the Project Proponent to MNRE for development of the site as per the guidelines of the scheme in vogue. 10. INCENTIVES TO THE POWER DEVELOPERS 10.1 Solar Power Plants (SPPs) installed and commissioned during the operative period shall be eligible for the incentives declared under this policy, for a period of twenty five years from the date of commissioning or as approved by MNRE or for the life span of the Solar Power Plants (SPPs) which ever is earlier. 10.2 No entry tax will be levied by the state Govt. on Power generation/transmission equipment and building material used for Solar Power Plants.
  • 9. Solar Power Policy for J&K Jammu and Kashmir Energy Development Agency Page 9 10.3 The Govt. land if required, for Power Projects shall be allotted on lease for 25 years at a premium of Rs. 1 per Kanal per annum. 10.4 In case of non availability of Govt. land, the land required shall be arranged by the entity. 10.5 Wherever required, the state will acquire the land for the project under the provisions of the J&K Land Acquisition Act and lease out the same to the entity for 25 years at a premium of Rs 1 per Kanal per annum plus an amount equal to the compensation of land. 10.6 Wherever forest land is involved, the state will facilitate permission for use of forest land for non forest purposes under the provisions of the J&K Forest Conservation Act. However, the compensation required to be paid for the purpose including the amount required for net present value, compensatory afforestation etc. will be paid by the entity. 10.7 Mortgage deed in favour of the financing institutions required to be signed by the promoters shall be exempted from payment of stamp duty. The State Government has already enabled equitable mortgage in the state. 10.8 Exemption from court fee for registration of documents relating to lease of land will be granted to the entities. 10.9 No royalty in the shape of free power has to be paid for the Solar Power Projects. However in case such provision is incorporated by the MNRE in the guidelines the same shall be applicable. 10.10 Entities will be eligible for central financial assistance as per the guidelines of MNRE, GoI as may be applicable besides other incentives given by the state or centre.
  • 10. Solar Power Policy for J&K Jammu and Kashmir Energy Development Agency Page 10 10.11 Electricity generated from the SPPs and used for self consumption / sale to third party / sale to licensees shall be exempted from payment of Electricity Duty or shall be as per the MNRE Guidelines. 10.12 Exemption from demand cut to the extent of 50% of the installed capacity of SPPs, assigned for captive use purpose, shall be allowed. 11. SCHEDULE OF IMPLEMENTATION 11.1 Entity shall prepare and submit the DPR / Company Profile and other information and make necessary applications for obtaining statutory clearances and approvals from state Govt. and regulatory authority (as applicable) after carrying out required confirmatory surveys and investigations as per prevailing regulations/norms. The entity shall be responsible for providing all documents and submissions of documents to concerned authorities within 12 months from the date of allotment. The state will facilitate the process of seeking statutory and non-statuary clearances on best effort basis. 11.2 The entity shall achieve the financial closure within three months from the date of receipt of all statutory approvals and clearances given by the state and Central Governments. Financial closure would imply firm commitments for financing the entire Project, with all pre-disbursement conditions having been fulfilled. 11.3 The Project shall be completed and made operational within a period of 24 months after receiving all statutory clearances. 11.4 The failure to fulfill any of the commitments/conditions will result in automatic cancellation of the allotment of site and forfeiture of upfront premium amount. No compensation would be payable to the entity in such instance. 11.5 The entity shall deposit upfront premium to the Nodal Agency within one month from the date of allotment of the site.
  • 11. Solar Power Policy for J&K Jammu and Kashmir Energy Development Agency Page 11 12. WHEELING CHARGES 12.1 Wherever feasible, the infrastructure and transmission/distribution network of PDD shall be available to entities for transmission of the power generated from the SPP. However, the point of interface between the network of PDD and SPP shall be specified in the agreement executed between PDD and the entity. 12.2 For sale of Power within or outside the state, wheeling charges shall be applicable as determined under norms by the state regulator viz J&K SERC. 12.3 Facility for banking shall be for captive use only and not for third party sales. 13. SALE OF ENERGY 13.1 The energy generated from a Solar Power Plant, shall be sold to the PDD or any third party in or outside the state. 13.2 In case of sale of Energy to PDD, the tariff shall be determined by the J&K SERC. 13.3 Projects allotted under this policy will also be entitled to avail the benefit/incentive as may be allowed by the MNRE, GoI from time to time. 14. PLANT AND MACHINERY 14.1 Only new plant and machinery shall be eligible for installation under this policy.
  • 12. Solar Power Policy for J&K Jammu and Kashmir Energy Development Agency Page 12 15. METERING OF ELECTRICITY 15.1 The Electricity Generated from the SPP shall be metered at the interconnection point with the SEMs Conforming to the specification as laid down under Grid Code. These meters shall be scaled jointly by the utility and the transmission company (PDD) and shall be recorded on monthly basis at 00Hrs of the last day of the month and conveyed to SLDC for energy accounting. 16. GRID CONNECTIVITY AND EVACUATION FACILITY UPTO PDD SUB-SUBSTATION 16.1 The evacuation facility from the Solar Substation/Switch yard to the Interconnection point shall be approved by PDD after carrying out the system study. The power by the SPP can be injected at LT 11 KV & 33KV or above. Further, the interconnection should be at the nearest distribution transformer/substation. In this regard, the Project Proponent shall submit a letter from the concerned Distribution Utility confirming technical feasibility of connecting the plant to the distribution transformer/substation. 16.2 The transmission line from the Switch yard of the Solar Substation to the Interconnection point shall be developed by the entity. They should be provided with the communication facility for scheduling and monitoring on real time basis. 17. OPEN ACCESS FOR THIRD PARTY SALE 17.1 The developer shall have to apply for the Open Access and be subjected to Open Access charges and losses as per regulations by JKSERC from time to time.
  • 13. Solar Power Policy for J&K Jammu and Kashmir Energy Development Agency Page 13 18. RENEWABLE PURCHASE OBLIGATION 18.1 The quantum of power that can be injected in the grid from Solar Power House shall be governed by RPO as per JKSERC regulations in this regard. 19. REACTIVE POWER CHARGES 19.1 The drawl of reactive power shall be charged as per the JKSERC regulations, as amended from time to time. 20. PENALTY FOR NON FULFILLING POWER PURCHASE OBLIGATION 20.1 Distribution licensees in the state of J&K are mandated to purchase solar power specified by JKSERC from time to time. 20.2 Distribution licensee failing to meet the minimum solar power purchase / obligation specified by J&KSERC shall be liable to pay penalty at a rate of Rs. 12/KWh to JAKEDA which will be passed on to the developer. Penalty shall not be levied on distribution licensee in case of non-availability of adequate power from power project. This will, however, be subject to the regulations of J&KSERC, if any, in this regard. 21. SHARING OF CLEAN DEVELOPMENT MECHANISM (CDM) BENEFIT 21.1 The solar power project developer will pass on the gross benefits of CDM to the distribution licensee with whom PPA is signed, as per the J&K SERC norms.
  • 14. Solar Power Policy for J&K Jammu and Kashmir Energy Development Agency Page 14 22. STATE GOVT FACILITATION AGENCY 22.1 JAKEDA and J&K PDC shall be the State Government facilitation Agencies for facilitation and implementation of the solar power policy. These facilitation agencies will facilitate and assist the project developers and undertake the following activities to achieve the objects of the Policy: a) Identification of suitable locations for solar projects, preparing a land bank and creation / upgradation of connected infrastructure to the project site i.e roads etc. b) Facilitation in arranging Right of Way, Water Supply and in obtaining clearances and approvals which are in the purview of the State Government. c) Recommending the project (subject to qualification) to avail benefits under any policy declared or to be declared by Government of India d) Promote Research and Development activities for cost effective sustainable and environment friendly technologies in collaboration with internationally and nationally reputed institutions. e) Engage the services of national/global experts/consultants for Research and Development of solar and other renewable technologies f) Carry out awareness campaign on energy conservation and use of renewable sources of energy at all levels ( i.e village, tehsil, district etc. through schools, colleges, educational institutions, community centers and civil society organizations). g) Along with project developers, develop appropriate manpower skills by tying up with training or educational institutions through Public Private Partnership (PPP). 23. MID TERM REVIEW 23.1 State Government may undertake a mid term review of this policy after a period of 5 years or as and when the need arises in view of any technological breakthrough or to remove any inconsistencies with JKSERC Regulations made or any Govt. of India policy.
  • 15. Solar Power Policy for J&K Jammu and Kashmir Energy Development Agency Page 15 24. POWER TO REMOVE DIFFICULTIES 24.1 If any difficulty arises in giving effect to this policy, the project approval committee is authorized to issue clarification as well as interpretation to such provisions, as may appear to be necessary for removing the difficulty either on its own motion or after hearing those parties who have sought clarifications for the provisions contained in the policy. 25. REGULATORY OVERSIGHT 25.1 Aspects of this policy that require regulatory approvals from any concerned Regulator would be subject to such approvals being given and would apply in the manner approved by the regulator. 26. ROLE OF NODALAGENCY 26.1 JAKEDA will be the Nodal Agency in Jammu and Kashmir Divisions of the State and LREDA & KREDA will be Nodal Agencies in respect of Leh and Kargil Districts respectively. The Agencies will be responsible for : i. Invitation of Bid. ii. Evaluation of the bids received. iii. Allotment of the SPP sites. iv. Forwarding the project proposals to MNRE, GoI for grant of CFA applicable for development of SPPs. v. Monitoring the progress of the Project and project appraisals. vi. Whenever MNRE invites applications under JNNSM for setting up of Solar Power Plants, the Agency shall evaluate the bids as per the standing norms laid by the MNRE for smooth implementation of the programme. vii. In case any other Govt Department launches scheme for promotion of Solar Power Plants (Off-grid or grid connected of any capacity) and are to be allotted on bidding basis then the allotment shall be made by following the procedure laid down in this policy subject to the condition they will not contradict the norms laid down in that particular scheme.
  • 16. Solar Power Policy for J&K Jammu and Kashmir Energy Development Agency Page 16 27. PROJECT APPROVAL COMMITTEE 27.1 The Project approval Committee consisting of following members shall approve the Solar Power Projects based on the financial & Technical criteria: 1. Administrative Head Science & Technology Department Chairman 2. Managing Director, J&K PDC Member 3. District Development Commissioner (Concerned district) Member 4. Representative of Finance Department Member 5. Representative of Power Dev. Deptt Member 6. Chief Executive Officer, JAKEDA Member-Secretary 28. DEFINITIONS 28.1 Following expressions used in the Policy would have meanings assigned to them as defined here under: i. ABT : Availability Based Tariff ii. CFA : Central Financial Assistance iii. CDM : Clean Development Mechanism iv. Developer : A person who develops electricity and transfers it to consumer v. DPR : Detailed Project Report vi. ENTITY : Independent Power Producer vii. GoJK : Government of Jammu and Kashmir viii. J&K : Jammu & Kashmir ix. JAKEDA : Jammu & Kashmir Energy Development Agency x. JKSERC : Jammu & Kashmir State Electricity Regulatory Commission xi. JNNSM : Jawaharlal Nehru National Solar Mission xii. KREDA : Kargil Renewable Energy Development Agency xiii. LREDA : Ladakh Renewable Energy Development Agency xiv. MNRE : Ministry of New and Renewable Energy xv. PDC : Power Development Corporation xvi. PDD : Power Development Department xvii. PPA : Power Purchase Agreement xviii. Power producer: Entity or the Agency Developing MHP xix. PRC : Permanent Resident Certificate xx. R&D : Research & Development xxi. RTU : Remote Terminal Unit xxii. SPPs : Solar Power Plants