SlideShare a Scribd company logo
1 of 10
Download to read offline
Chapter 8 – Construction Surveys (or Setting Out)
Introduction
Setting out is the process of using the surveying instruments and techniques described in
preceding chapters to transfer information from a plan to the ground.
There are three distinct elements to the task:
1. Horizontal control to ensure that the new works are in the correct place
2. Vertical control to ensure that they are at the correct level
3. Vertical alignment to ensure that multi-storey or underground construction is plumb.
In construction surveys, one of the common tasks for the surveyor is to mark on the ground
the locations of the following:
1. Buildings
2. Roads
3. Pipelines
The proposed locations shown on a site plan by the designer are generally by giving
appropriate distance and directions from the site boundary lines or from horizontal and
vertical control monuments.
The surveyor must transfer these given distances from a drawing into the field, with a suitable
degree of accuracy.
Basic Principles and Point Marking
Three orders of points can be defined:
1) Primary stations
• Primary setting-out points are stations on the control traverse or control
triangulation system.
• The station should be permanent for the life of the works.
• The stations should be clearly marked and protected so that they are not
disturbed by construction traffic.
2) Secondary stations
• Secondary setting-out points are established closer to points of detail on the
proposed works, and are referenced by measurement from the primary points.
3) Detail points
• Detail points mark (e.g. 50mm square timber peg with a nail in the top) the
location of features on the works such as the centre of a pile, or the corner of a
building.
Accuracy
Table below shows the expected accuracy for equipment in good working condition and
adjustment as recommended in BS5606:1990 Code of Practice for Accuracy in Building.
* EDM is not recommended for distances less than 30m, where a steel tape used with
precision is more accurate.
Building and Pipeline Stakeout
Stakeout of new buildings and underground pipelines
Traditional procedures: baseline offsets and batter boards
Staking out a building
Property survey must precede the stakeout of any structure on a parcel of land to accurately
locate boundary lines.
Building lines (or building setbacks) specified in the local building code must be located.
A setback is the minimum required distance between a new building and a front or side
property line.
Staking out a building makes use of several perpendicular offsets measured from a
predetermined baseline.
The baseline serves as a reference to control the position of the proposed structure (it may be
a property line).
Batter Boards (or Profile Boards)
A standard method for temporarily referencing the building corners makes use of the batter
board.
A batter board is simply a horizontal wooden plank fastened to two vertical posts.
*The land surveyor may be required only to set offset stakes at each corner of the building
and to set a benchmark.
*The builder is then generally responsible for setting up the batter boards using the land
surveyor’s reference marks.
A pair of batter boards are built offset from each corner so that opposite boards will support a
wire, string, or carpenter’s line.
The string lines are stretched taut between two nails driven into the tops of opposite boards,
which are usually set at the same elevation so that the line will be level.
The string lines then establish both line and grade.
The intersection of two strings marks the position of a corner and this position is easily
transferred vertically with the plumb-bob cord. The string lines can be removed so not to
interfere with the work, and then replaced as necessary to again give line and grade.
Layout Procedure for a simple rectangular structure
1. Set up an instrument at monument P
a. take line on Q
b. set stakes at A and B.
2. Set up an instrument at A
a. back-sight on Q
b. turn 90°
c. set stakes at corners L and M
d. set batter boards and nails at 1 and 2.
3. Set up an instrument at B
a. back-sight on Q
b. turn 90°
c. set stakes at corners N and O
d. set batter boards and nails at 3 and 4.
4. Measure diagonals LO and NM and check with length computed using the
Pythagorean theorem; re-stake if necessary
5. Set up an instrument at L
a. back-sight on N
b. set nail 5
c. plunge scope and set nail 6
6. Set up an instrument at M
a. back-sight on O
b. set nail 7
c. plunge scope and set nail 8
Line and Grade for a Sewer
Flow in a storm sewer or in a sanitary sewer is called open channel gravity flow.
The flow capacity of a given diameter pipe depends primarily on the slope or gradient of the
flow line.
The flow line (or invert) is the bottom inside surface of the pipe or drainage channel.
Whenever the pipeline changes in slope, diameter or direction, a manhole is built to provide
access both for sewage flow measurement and sampling and for pipeline inspection and
maintenance.
Batter boards have traditionally been used to give line and grade for a gravity flow pipeline
(lasers are frequently used in present-day construction).
The pipe is first located by a series of stakes that are usually set at 50ft (15m) intervals and
offset 3 – 6 ft (1 – 2m) from the pipe centerline.
The batter boards are set at a constant elevation (say, 7’0”) above the pipe flow line or invert
and a string line is run between the boards so that it is directly over the pipe centerline.
The string line will have a slope equal to that of the pipeline.
It is then simple for the workers to place the pipe sections into the trench in the proper
position on a bed of sand and gravel, and to adjust the pipe invert while making periodic
measurements from the string line.
Example
Suppose that it is necessary to build a new sewer from a house to an existing manhole. It is
assumed that the flow line must be at least 3ft (1m) below the ground surface, and the
minimum slope should be 0.004. A manhole should be placed at any change in gradient. The
flow line elevation at the house is given as 70.03 on the plans. The invert elevation of the
existing manhole must be determined during the preliminary survey by opening the manhole
cover and observing a rod held on the flow line.
Field steps:
1. Stake out a 4-ft offset line, placing stake 0+0 beside the point in the house where the
house connection is located and a stake every 50 ft thereafter. Carry the measurement
to a point beside the manhole, and determine its plus.
2. Find the elevation of the ground at each 50 ft point along the true line and at all breaks
in ground slope. The rod is held on the ground at an estimated 4 ft from and opposite
to each offset stake. This places the rod at the true position on the construction line.
3. At the same time, determine the elevation of the tops of each of the offset-line stakes.
4. Draw the profile of the ground elevations and determine the grade profile for the flow
line.
Construction Surveys Chapter

More Related Content

What's hot

LEVELING AND CONTOURING
LEVELING AND CONTOURINGLEVELING AND CONTOURING
LEVELING AND CONTOURINGANAND JIBHKATE
 
Setting out construction works 01
Setting out construction works 01Setting out construction works 01
Setting out construction works 01Rajesh Rajguru
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of buildingARUN KUMAR
 
surveying- lecture notes for engineers
surveying- lecture notes for engineerssurveying- lecture notes for engineers
surveying- lecture notes for engineersmusadoto
 
Errorsandmistakesinchaining 170810071200
Errorsandmistakesinchaining 170810071200Errorsandmistakesinchaining 170810071200
Errorsandmistakesinchaining 170810071200Mir Zafarullah
 
Surveying and levelling
Surveying and levellingSurveying and levelling
Surveying and levellingParimal Jha
 
Serviceability of a structure
Serviceability of a structureServiceability of a structure
Serviceability of a structureKhattar Aoun
 
Balancing of traverse
Balancing of traverseBalancing of traverse
Balancing of traverseAditya Mistry
 
Avinesh surveying lab manuals
Avinesh surveying lab manualsAvinesh surveying lab manuals
Avinesh surveying lab manualsavineshgautam
 
1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & RangingRakesh Verma
 
12.1. Horizontal and vertical control (1).pptx
12.1.  Horizontal and vertical control (1).pptx12.1.  Horizontal and vertical control (1).pptx
12.1. Horizontal and vertical control (1).pptxSaddoAjmal
 
Setting out of bridges
Setting out of bridgesSetting out of bridges
Setting out of bridgesWaseem Raja
 
Setting Out Works in Surveying
Setting Out Works in SurveyingSetting Out Works in Surveying
Setting Out Works in SurveyingATUL DONGRE
 

What's hot (20)

LEVELING AND CONTOURING
LEVELING AND CONTOURINGLEVELING AND CONTOURING
LEVELING AND CONTOURING
 
Setting out construction works 01
Setting out construction works 01Setting out construction works 01
Setting out construction works 01
 
Setting out of building
Setting out of buildingSetting out of building
Setting out of building
 
surveying- lecture notes for engineers
surveying- lecture notes for engineerssurveying- lecture notes for engineers
surveying- lecture notes for engineers
 
Errorsandmistakesinchaining 170810071200
Errorsandmistakesinchaining 170810071200Errorsandmistakesinchaining 170810071200
Errorsandmistakesinchaining 170810071200
 
chain surveying
chain surveyingchain surveying
chain surveying
 
Surveying and levelling
Surveying and levellingSurveying and levelling
Surveying and levelling
 
Contouring
ContouringContouring
Contouring
 
ESTIMATING AND COSTING
ESTIMATING AND COSTINGESTIMATING AND COSTING
ESTIMATING AND COSTING
 
Serviceability of a structure
Serviceability of a structureServiceability of a structure
Serviceability of a structure
 
Balancing of traverse
Balancing of traverseBalancing of traverse
Balancing of traverse
 
Avinesh surveying lab manuals
Avinesh surveying lab manualsAvinesh surveying lab manuals
Avinesh surveying lab manuals
 
1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging1.1 Linear measurement original: Chaining & Ranging
1.1 Linear measurement original: Chaining & Ranging
 
12.1. Horizontal and vertical control (1).pptx
12.1.  Horizontal and vertical control (1).pptx12.1.  Horizontal and vertical control (1).pptx
12.1. Horizontal and vertical control (1).pptx
 
Setting out of bridges
Setting out of bridgesSetting out of bridges
Setting out of bridges
 
Setting out work
Setting out workSetting out work
Setting out work
 
Setting Out Works in Surveying
Setting Out Works in SurveyingSetting Out Works in Surveying
Setting Out Works in Surveying
 
Theodolite Traversing
Theodolite TraversingTheodolite Traversing
Theodolite Traversing
 
Site clearance & preparetion
Site clearance & preparetionSite clearance & preparetion
Site clearance & preparetion
 
tacheometry surveying
tacheometry surveyingtacheometry surveying
tacheometry surveying
 

Viewers also liked

Laying of Sewer Line
Laying of Sewer LineLaying of Sewer Line
Laying of Sewer Linesumitvikram
 
sewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenancesewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenanceManish Goyal
 
Excavation & Trenching Safety
Excavation & Trenching Safety Excavation & Trenching Safety
Excavation & Trenching Safety Reliance
 
Basics Of Surveying
Basics Of SurveyingBasics Of Surveying
Basics Of Surveyingstooty s
 
Presentation of surveying
Presentation of surveyingPresentation of surveying
Presentation of surveyingShaker Ullah
 

Viewers also liked (12)

Laying of Sewer Line
Laying of Sewer LineLaying of Sewer Line
Laying of Sewer Line
 
sewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenancesewers and sewer netwrok - design construction and maintenance
sewers and sewer netwrok - design construction and maintenance
 
Drainage
DrainageDrainage
Drainage
 
Topic 4 - Curve
Topic 4 - CurveTopic 4 - Curve
Topic 4 - Curve
 
Sewerage design
Sewerage designSewerage design
Sewerage design
 
Excavation & Trenching Safety
Excavation & Trenching Safety Excavation & Trenching Safety
Excavation & Trenching Safety
 
Basics of surveying
Basics of surveyingBasics of surveying
Basics of surveying
 
OSHA Trenching and Excavation Requirements
OSHA Trenching and Excavation Requirements OSHA Trenching and Excavation Requirements
OSHA Trenching and Excavation Requirements
 
Sewerage System
Sewerage SystemSewerage System
Sewerage System
 
Basics Of Surveying
Basics Of SurveyingBasics Of Surveying
Basics Of Surveying
 
Survey ppt
Survey pptSurvey ppt
Survey ppt
 
Presentation of surveying
Presentation of surveyingPresentation of surveying
Presentation of surveying
 

Similar to Construction Surveys Chapter

Similar to Construction Surveys Chapter (20)

Bridge survey
Bridge surveyBridge survey
Bridge survey
 
Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting out
 
Tutor l1 setting out
Tutor l1 setting outTutor l1 setting out
Tutor l1 setting out
 
7500
75007500
7500
 
Testing of bored_pile_inclination
Testing of bored_pile_inclinationTesting of bored_pile_inclination
Testing of bored_pile_inclination
 
Testing of bored_pile_inclination
Testing of bored_pile_inclinationTesting of bored_pile_inclination
Testing of bored_pile_inclination
 
Levelling
LevellingLevelling
Levelling
 
Chapter 6 Part 2
Chapter 6 Part 2Chapter 6 Part 2
Chapter 6 Part 2
 
levelling and contouring
levelling and contouringlevelling and contouring
levelling and contouring
 
DEFINITIONS, PRINCIPLES AND CHAIN SURVEYING
DEFINITIONS, PRINCIPLES AND CHAIN SURVEYINGDEFINITIONS, PRINCIPLES AND CHAIN SURVEYING
DEFINITIONS, PRINCIPLES AND CHAIN SURVEYING
 
Surveying i
Surveying iSurveying i
Surveying i
 
Profiles (longitudinal section) & cross sections
Profiles (longitudinal section) & cross sectionsProfiles (longitudinal section) & cross sections
Profiles (longitudinal section) & cross sections
 
surveying Work methodology
surveying Work methodologysurveying Work methodology
surveying Work methodology
 
Levelling
LevellingLevelling
Levelling
 
9 pipe structures
9 pipe structures9 pipe structures
9 pipe structures
 
Surveying and levelling
Surveying and levellingSurveying and levelling
Surveying and levelling
 
Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insitu
 
Chain Surveying 2020.ppt
 Chain Surveying 2020.ppt Chain Surveying 2020.ppt
Chain Surveying 2020.ppt
 
Ch 5 levelling
Ch 5 levellingCh 5 levelling
Ch 5 levelling
 
Overhead Electrification
Overhead Electrification Overhead Electrification
Overhead Electrification
 

More from Est

SABD PROGRAMME GUIDE 2017
SABD PROGRAMME GUIDE 2017SABD PROGRAMME GUIDE 2017
SABD PROGRAMME GUIDE 2017Est
 
Sabd undergraduate pg draft v3
Sabd undergraduate pg draft   v3Sabd undergraduate pg draft   v3
Sabd undergraduate pg draft v3Est
 
BS 2 Fire protection 4
BS 2 Fire protection 4BS 2 Fire protection 4
BS 2 Fire protection 4Est
 
CSCM Chapter 11 relationship management cscm
CSCM Chapter 11 relationship management cscmCSCM Chapter 11 relationship management cscm
CSCM Chapter 11 relationship management cscmEst
 
CSCM Partnering
CSCM PartneringCSCM Partnering
CSCM PartneringEst
 
CSCM Communication in construction
CSCM Communication in constructionCSCM Communication in construction
CSCM Communication in constructionEst
 
CSCM Material delivery problems cscm
CSCM Material delivery problems cscmCSCM Material delivery problems cscm
CSCM Material delivery problems cscmEst
 
BS 2 Escalators arrangement
BS 2 Escalators arrangementBS 2 Escalators arrangement
BS 2 Escalators arrangementEst
 
BS 2 Escalators 1of 2
BS 2 Escalators 1of 2BS 2 Escalators 1of 2
BS 2 Escalators 1of 2Est
 
BS 2 Group assignment brief question august 2016
BS 2 Group assignment brief  question august 2016BS 2 Group assignment brief  question august 2016
BS 2 Group assignment brief question august 2016Est
 
BS 2 Variable air volume systems
BS 2 Variable air volume systemsBS 2 Variable air volume systems
BS 2 Variable air volume systemsEst
 
CSCM Supply chain management 312 cscm
CSCM Supply chain management 312 cscmCSCM Supply chain management 312 cscm
CSCM Supply chain management 312 cscmEst
 
CSCM Bim group assignment.docx
CSCM Bim group assignment.docxCSCM Bim group assignment.docx
CSCM Bim group assignment.docxEst
 
CSCM individual assignment
CSCM individual assignmentCSCM individual assignment
CSCM individual assignmentEst
 
Management science group assignment MS
Management science group assignment MSManagement science group assignment MS
Management science group assignment MSEst
 
MS Tutorial 12 hrm
MS Tutorial 12 hrmMS Tutorial 12 hrm
MS Tutorial 12 hrmEst
 
MS Case study development for entrepreneur mark zuckerberg
MS Case study development for entrepreneur mark zuckerbergMS Case study development for entrepreneur mark zuckerberg
MS Case study development for entrepreneur mark zuckerbergEst
 
MS Lecture 7 leadership and motivation
MS Lecture 7 leadership and motivationMS Lecture 7 leadership and motivation
MS Lecture 7 leadership and motivationEst
 
MS Lecture 8 communication
MS Lecture 8 communicationMS Lecture 8 communication
MS Lecture 8 communicationEst
 
MS Qsb 2413 group project 2016
MS Qsb 2413 group project 2016MS Qsb 2413 group project 2016
MS Qsb 2413 group project 2016Est
 

More from Est (20)

SABD PROGRAMME GUIDE 2017
SABD PROGRAMME GUIDE 2017SABD PROGRAMME GUIDE 2017
SABD PROGRAMME GUIDE 2017
 
Sabd undergraduate pg draft v3
Sabd undergraduate pg draft   v3Sabd undergraduate pg draft   v3
Sabd undergraduate pg draft v3
 
BS 2 Fire protection 4
BS 2 Fire protection 4BS 2 Fire protection 4
BS 2 Fire protection 4
 
CSCM Chapter 11 relationship management cscm
CSCM Chapter 11 relationship management cscmCSCM Chapter 11 relationship management cscm
CSCM Chapter 11 relationship management cscm
 
CSCM Partnering
CSCM PartneringCSCM Partnering
CSCM Partnering
 
CSCM Communication in construction
CSCM Communication in constructionCSCM Communication in construction
CSCM Communication in construction
 
CSCM Material delivery problems cscm
CSCM Material delivery problems cscmCSCM Material delivery problems cscm
CSCM Material delivery problems cscm
 
BS 2 Escalators arrangement
BS 2 Escalators arrangementBS 2 Escalators arrangement
BS 2 Escalators arrangement
 
BS 2 Escalators 1of 2
BS 2 Escalators 1of 2BS 2 Escalators 1of 2
BS 2 Escalators 1of 2
 
BS 2 Group assignment brief question august 2016
BS 2 Group assignment brief  question august 2016BS 2 Group assignment brief  question august 2016
BS 2 Group assignment brief question august 2016
 
BS 2 Variable air volume systems
BS 2 Variable air volume systemsBS 2 Variable air volume systems
BS 2 Variable air volume systems
 
CSCM Supply chain management 312 cscm
CSCM Supply chain management 312 cscmCSCM Supply chain management 312 cscm
CSCM Supply chain management 312 cscm
 
CSCM Bim group assignment.docx
CSCM Bim group assignment.docxCSCM Bim group assignment.docx
CSCM Bim group assignment.docx
 
CSCM individual assignment
CSCM individual assignmentCSCM individual assignment
CSCM individual assignment
 
Management science group assignment MS
Management science group assignment MSManagement science group assignment MS
Management science group assignment MS
 
MS Tutorial 12 hrm
MS Tutorial 12 hrmMS Tutorial 12 hrm
MS Tutorial 12 hrm
 
MS Case study development for entrepreneur mark zuckerberg
MS Case study development for entrepreneur mark zuckerbergMS Case study development for entrepreneur mark zuckerberg
MS Case study development for entrepreneur mark zuckerberg
 
MS Lecture 7 leadership and motivation
MS Lecture 7 leadership and motivationMS Lecture 7 leadership and motivation
MS Lecture 7 leadership and motivation
 
MS Lecture 8 communication
MS Lecture 8 communicationMS Lecture 8 communication
MS Lecture 8 communication
 
MS Qsb 2413 group project 2016
MS Qsb 2413 group project 2016MS Qsb 2413 group project 2016
MS Qsb 2413 group project 2016
 

Recently uploaded

exhuma plot and synopsis from the exhuma movie.pptx
exhuma plot and synopsis from the exhuma movie.pptxexhuma plot and synopsis from the exhuma movie.pptx
exhuma plot and synopsis from the exhuma movie.pptxKurikulumPenilaian
 
Authentic # 00971556872006 # Hot Call Girls Service in Dubai By International...
Authentic # 00971556872006 # Hot Call Girls Service in Dubai By International...Authentic # 00971556872006 # Hot Call Girls Service in Dubai By International...
Authentic # 00971556872006 # Hot Call Girls Service in Dubai By International...home
 
Lucknow 💋 Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...
Lucknow 💋 Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...Lucknow 💋 Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...
Lucknow 💋 Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...anilsa9823
 
Gomti Nagar & High Profile Call Girls in Lucknow (Adult Only) 8923113531 Esc...
Gomti Nagar & High Profile Call Girls in Lucknow  (Adult Only) 8923113531 Esc...Gomti Nagar & High Profile Call Girls in Lucknow  (Adult Only) 8923113531 Esc...
Gomti Nagar & High Profile Call Girls in Lucknow (Adult Only) 8923113531 Esc...gurkirankumar98700
 
Lucknow 💋 Call Girls Service Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Call Girls Service Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Call Girls Service Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Call Girls Service Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...anilsa9823
 
Hazratganj / Call Girl in Lucknow - Phone 🫗 8923113531 ☛ Escorts Service at 6...
Hazratganj / Call Girl in Lucknow - Phone 🫗 8923113531 ☛ Escorts Service at 6...Hazratganj / Call Girl in Lucknow - Phone 🫗 8923113531 ☛ Escorts Service at 6...
Hazratganj / Call Girl in Lucknow - Phone 🫗 8923113531 ☛ Escorts Service at 6...akbard9823
 
Lucknow 💋 Call Girls in Lucknow | Service-oriented sexy call girls 8923113531...
Lucknow 💋 Call Girls in Lucknow | Service-oriented sexy call girls 8923113531...Lucknow 💋 Call Girls in Lucknow | Service-oriented sexy call girls 8923113531...
Lucknow 💋 Call Girls in Lucknow | Service-oriented sexy call girls 8923113531...anilsa9823
 
Bobbie goods coloring book 81 pag_240127_163802.pdf
Bobbie goods coloring book 81 pag_240127_163802.pdfBobbie goods coloring book 81 pag_240127_163802.pdf
Bobbie goods coloring book 81 pag_240127_163802.pdfMARIBEL442158
 
RAK Call Girls Service # 971559085003 # Call Girl Service In RAK
RAK Call Girls Service # 971559085003 # Call Girl Service In RAKRAK Call Girls Service # 971559085003 # Call Girl Service In RAK
RAK Call Girls Service # 971559085003 # Call Girl Service In RAKedwardsara83
 
Lucknow 💋 best call girls in Lucknow (Adult Only) 8923113531 Escort Service ...
Lucknow 💋 best call girls in Lucknow  (Adult Only) 8923113531 Escort Service ...Lucknow 💋 best call girls in Lucknow  (Adult Only) 8923113531 Escort Service ...
Lucknow 💋 best call girls in Lucknow (Adult Only) 8923113531 Escort Service ...anilsa9823
 
Lucknow 💋 Call Girl in Lucknow Phone No 8923113531 Elite Escort Service Avail...
Lucknow 💋 Call Girl in Lucknow Phone No 8923113531 Elite Escort Service Avail...Lucknow 💋 Call Girl in Lucknow Phone No 8923113531 Elite Escort Service Avail...
Lucknow 💋 Call Girl in Lucknow Phone No 8923113531 Elite Escort Service Avail...anilsa9823
 
Turn Lock Take Key Storyboard Daniel Johnson
Turn Lock Take Key Storyboard Daniel JohnsonTurn Lock Take Key Storyboard Daniel Johnson
Turn Lock Take Key Storyboard Daniel Johnsonthephillipta
 
Lucknow 💋 Call Girls in Lucknow ₹7.5k Pick Up & Drop With Cash Payment 892311...
Lucknow 💋 Call Girls in Lucknow ₹7.5k Pick Up & Drop With Cash Payment 892311...Lucknow 💋 Call Girls in Lucknow ₹7.5k Pick Up & Drop With Cash Payment 892311...
Lucknow 💋 Call Girls in Lucknow ₹7.5k Pick Up & Drop With Cash Payment 892311...anilsa9823
 
Lucknow 💋 Call Girl in Lucknow 10k @ I'm VIP Independent Escorts Girls 892311...
Lucknow 💋 Call Girl in Lucknow 10k @ I'm VIP Independent Escorts Girls 892311...Lucknow 💋 Call Girl in Lucknow 10k @ I'm VIP Independent Escorts Girls 892311...
Lucknow 💋 Call Girl in Lucknow 10k @ I'm VIP Independent Escorts Girls 892311...anilsa9823
 
Aminabad @ Book Call Girls in Lucknow - 450+ Call Girl Cash Payment 🍵 8923113...
Aminabad @ Book Call Girls in Lucknow - 450+ Call Girl Cash Payment 🍵 8923113...Aminabad @ Book Call Girls in Lucknow - 450+ Call Girl Cash Payment 🍵 8923113...
Aminabad @ Book Call Girls in Lucknow - 450+ Call Girl Cash Payment 🍵 8923113...akbard9823
 
Indira Nagar Lucknow #Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payme...
Indira Nagar Lucknow #Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payme...Indira Nagar Lucknow #Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payme...
Indira Nagar Lucknow #Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payme...akbard9823
 
Young⚡Call Girls in Lajpat Nagar Delhi >༒9667401043 Escort Service
Young⚡Call Girls in Lajpat Nagar Delhi >༒9667401043 Escort ServiceYoung⚡Call Girls in Lajpat Nagar Delhi >༒9667401043 Escort Service
Young⚡Call Girls in Lajpat Nagar Delhi >༒9667401043 Escort Servicesonnydelhi1992
 
Editorial sephora annual report design project
Editorial sephora annual report design projectEditorial sephora annual report design project
Editorial sephora annual report design projecttbatkhuu1
 
Call Girl Service In Dubai #$# O56521286O #$# Dubai Call Girls
Call Girl Service In Dubai #$# O56521286O #$# Dubai Call GirlsCall Girl Service In Dubai #$# O56521286O #$# Dubai Call Girls
Call Girl Service In Dubai #$# O56521286O #$# Dubai Call Girlsparisharma5056
 
(9711106444 )🫦#Sexy Desi Call Girls Noida Sector 4 Escorts Service Delhi 🫶
(9711106444 )🫦#Sexy Desi Call Girls Noida Sector 4 Escorts Service Delhi 🫶(9711106444 )🫦#Sexy Desi Call Girls Noida Sector 4 Escorts Service Delhi 🫶
(9711106444 )🫦#Sexy Desi Call Girls Noida Sector 4 Escorts Service Delhi 🫶delhimunirka444
 

Recently uploaded (20)

exhuma plot and synopsis from the exhuma movie.pptx
exhuma plot and synopsis from the exhuma movie.pptxexhuma plot and synopsis from the exhuma movie.pptx
exhuma plot and synopsis from the exhuma movie.pptx
 
Authentic # 00971556872006 # Hot Call Girls Service in Dubai By International...
Authentic # 00971556872006 # Hot Call Girls Service in Dubai By International...Authentic # 00971556872006 # Hot Call Girls Service in Dubai By International...
Authentic # 00971556872006 # Hot Call Girls Service in Dubai By International...
 
Lucknow 💋 Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...
Lucknow 💋 Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...Lucknow 💋 Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...
Lucknow 💋 Virgin Call Girls Lucknow | Book 8923113531 Extreme Naughty Call Gi...
 
Gomti Nagar & High Profile Call Girls in Lucknow (Adult Only) 8923113531 Esc...
Gomti Nagar & High Profile Call Girls in Lucknow  (Adult Only) 8923113531 Esc...Gomti Nagar & High Profile Call Girls in Lucknow  (Adult Only) 8923113531 Esc...
Gomti Nagar & High Profile Call Girls in Lucknow (Adult Only) 8923113531 Esc...
 
Lucknow 💋 Call Girls Service Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Call Girls Service Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...Lucknow 💋 Call Girls Service Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
Lucknow 💋 Call Girls Service Lucknow ₹7.5k Pick Up & Drop With Cash Payment 8...
 
Hazratganj / Call Girl in Lucknow - Phone 🫗 8923113531 ☛ Escorts Service at 6...
Hazratganj / Call Girl in Lucknow - Phone 🫗 8923113531 ☛ Escorts Service at 6...Hazratganj / Call Girl in Lucknow - Phone 🫗 8923113531 ☛ Escorts Service at 6...
Hazratganj / Call Girl in Lucknow - Phone 🫗 8923113531 ☛ Escorts Service at 6...
 
Lucknow 💋 Call Girls in Lucknow | Service-oriented sexy call girls 8923113531...
Lucknow 💋 Call Girls in Lucknow | Service-oriented sexy call girls 8923113531...Lucknow 💋 Call Girls in Lucknow | Service-oriented sexy call girls 8923113531...
Lucknow 💋 Call Girls in Lucknow | Service-oriented sexy call girls 8923113531...
 
Bobbie goods coloring book 81 pag_240127_163802.pdf
Bobbie goods coloring book 81 pag_240127_163802.pdfBobbie goods coloring book 81 pag_240127_163802.pdf
Bobbie goods coloring book 81 pag_240127_163802.pdf
 
RAK Call Girls Service # 971559085003 # Call Girl Service In RAK
RAK Call Girls Service # 971559085003 # Call Girl Service In RAKRAK Call Girls Service # 971559085003 # Call Girl Service In RAK
RAK Call Girls Service # 971559085003 # Call Girl Service In RAK
 
Lucknow 💋 best call girls in Lucknow (Adult Only) 8923113531 Escort Service ...
Lucknow 💋 best call girls in Lucknow  (Adult Only) 8923113531 Escort Service ...Lucknow 💋 best call girls in Lucknow  (Adult Only) 8923113531 Escort Service ...
Lucknow 💋 best call girls in Lucknow (Adult Only) 8923113531 Escort Service ...
 
Lucknow 💋 Call Girl in Lucknow Phone No 8923113531 Elite Escort Service Avail...
Lucknow 💋 Call Girl in Lucknow Phone No 8923113531 Elite Escort Service Avail...Lucknow 💋 Call Girl in Lucknow Phone No 8923113531 Elite Escort Service Avail...
Lucknow 💋 Call Girl in Lucknow Phone No 8923113531 Elite Escort Service Avail...
 
Turn Lock Take Key Storyboard Daniel Johnson
Turn Lock Take Key Storyboard Daniel JohnsonTurn Lock Take Key Storyboard Daniel Johnson
Turn Lock Take Key Storyboard Daniel Johnson
 
Lucknow 💋 Call Girls in Lucknow ₹7.5k Pick Up & Drop With Cash Payment 892311...
Lucknow 💋 Call Girls in Lucknow ₹7.5k Pick Up & Drop With Cash Payment 892311...Lucknow 💋 Call Girls in Lucknow ₹7.5k Pick Up & Drop With Cash Payment 892311...
Lucknow 💋 Call Girls in Lucknow ₹7.5k Pick Up & Drop With Cash Payment 892311...
 
Lucknow 💋 Call Girl in Lucknow 10k @ I'm VIP Independent Escorts Girls 892311...
Lucknow 💋 Call Girl in Lucknow 10k @ I'm VIP Independent Escorts Girls 892311...Lucknow 💋 Call Girl in Lucknow 10k @ I'm VIP Independent Escorts Girls 892311...
Lucknow 💋 Call Girl in Lucknow 10k @ I'm VIP Independent Escorts Girls 892311...
 
Aminabad @ Book Call Girls in Lucknow - 450+ Call Girl Cash Payment 🍵 8923113...
Aminabad @ Book Call Girls in Lucknow - 450+ Call Girl Cash Payment 🍵 8923113...Aminabad @ Book Call Girls in Lucknow - 450+ Call Girl Cash Payment 🍵 8923113...
Aminabad @ Book Call Girls in Lucknow - 450+ Call Girl Cash Payment 🍵 8923113...
 
Indira Nagar Lucknow #Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payme...
Indira Nagar Lucknow #Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payme...Indira Nagar Lucknow #Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payme...
Indira Nagar Lucknow #Call Girls Lucknow ₹7.5k Pick Up & Drop With Cash Payme...
 
Young⚡Call Girls in Lajpat Nagar Delhi >༒9667401043 Escort Service
Young⚡Call Girls in Lajpat Nagar Delhi >༒9667401043 Escort ServiceYoung⚡Call Girls in Lajpat Nagar Delhi >༒9667401043 Escort Service
Young⚡Call Girls in Lajpat Nagar Delhi >༒9667401043 Escort Service
 
Editorial sephora annual report design project
Editorial sephora annual report design projectEditorial sephora annual report design project
Editorial sephora annual report design project
 
Call Girl Service In Dubai #$# O56521286O #$# Dubai Call Girls
Call Girl Service In Dubai #$# O56521286O #$# Dubai Call GirlsCall Girl Service In Dubai #$# O56521286O #$# Dubai Call Girls
Call Girl Service In Dubai #$# O56521286O #$# Dubai Call Girls
 
(9711106444 )🫦#Sexy Desi Call Girls Noida Sector 4 Escorts Service Delhi 🫶
(9711106444 )🫦#Sexy Desi Call Girls Noida Sector 4 Escorts Service Delhi 🫶(9711106444 )🫦#Sexy Desi Call Girls Noida Sector 4 Escorts Service Delhi 🫶
(9711106444 )🫦#Sexy Desi Call Girls Noida Sector 4 Escorts Service Delhi 🫶
 

Construction Surveys Chapter

  • 1. Chapter 8 – Construction Surveys (or Setting Out) Introduction Setting out is the process of using the surveying instruments and techniques described in preceding chapters to transfer information from a plan to the ground. There are three distinct elements to the task: 1. Horizontal control to ensure that the new works are in the correct place 2. Vertical control to ensure that they are at the correct level 3. Vertical alignment to ensure that multi-storey or underground construction is plumb. In construction surveys, one of the common tasks for the surveyor is to mark on the ground the locations of the following: 1. Buildings 2. Roads 3. Pipelines The proposed locations shown on a site plan by the designer are generally by giving appropriate distance and directions from the site boundary lines or from horizontal and vertical control monuments. The surveyor must transfer these given distances from a drawing into the field, with a suitable degree of accuracy. Basic Principles and Point Marking Three orders of points can be defined: 1) Primary stations • Primary setting-out points are stations on the control traverse or control triangulation system. • The station should be permanent for the life of the works. • The stations should be clearly marked and protected so that they are not disturbed by construction traffic.
  • 2. 2) Secondary stations • Secondary setting-out points are established closer to points of detail on the proposed works, and are referenced by measurement from the primary points. 3) Detail points • Detail points mark (e.g. 50mm square timber peg with a nail in the top) the location of features on the works such as the centre of a pile, or the corner of a building. Accuracy Table below shows the expected accuracy for equipment in good working condition and adjustment as recommended in BS5606:1990 Code of Practice for Accuracy in Building. * EDM is not recommended for distances less than 30m, where a steel tape used with precision is more accurate.
  • 3. Building and Pipeline Stakeout Stakeout of new buildings and underground pipelines Traditional procedures: baseline offsets and batter boards Staking out a building Property survey must precede the stakeout of any structure on a parcel of land to accurately locate boundary lines. Building lines (or building setbacks) specified in the local building code must be located. A setback is the minimum required distance between a new building and a front or side property line. Staking out a building makes use of several perpendicular offsets measured from a predetermined baseline. The baseline serves as a reference to control the position of the proposed structure (it may be a property line).
  • 4. Batter Boards (or Profile Boards) A standard method for temporarily referencing the building corners makes use of the batter board. A batter board is simply a horizontal wooden plank fastened to two vertical posts. *The land surveyor may be required only to set offset stakes at each corner of the building and to set a benchmark. *The builder is then generally responsible for setting up the batter boards using the land surveyor’s reference marks.
  • 5. A pair of batter boards are built offset from each corner so that opposite boards will support a wire, string, or carpenter’s line. The string lines are stretched taut between two nails driven into the tops of opposite boards, which are usually set at the same elevation so that the line will be level. The string lines then establish both line and grade. The intersection of two strings marks the position of a corner and this position is easily transferred vertically with the plumb-bob cord. The string lines can be removed so not to interfere with the work, and then replaced as necessary to again give line and grade. Layout Procedure for a simple rectangular structure
  • 6. 1. Set up an instrument at monument P a. take line on Q b. set stakes at A and B. 2. Set up an instrument at A a. back-sight on Q b. turn 90° c. set stakes at corners L and M d. set batter boards and nails at 1 and 2. 3. Set up an instrument at B a. back-sight on Q b. turn 90° c. set stakes at corners N and O d. set batter boards and nails at 3 and 4. 4. Measure diagonals LO and NM and check with length computed using the Pythagorean theorem; re-stake if necessary 5. Set up an instrument at L a. back-sight on N b. set nail 5 c. plunge scope and set nail 6 6. Set up an instrument at M a. back-sight on O b. set nail 7 c. plunge scope and set nail 8
  • 7. Line and Grade for a Sewer Flow in a storm sewer or in a sanitary sewer is called open channel gravity flow. The flow capacity of a given diameter pipe depends primarily on the slope or gradient of the flow line. The flow line (or invert) is the bottom inside surface of the pipe or drainage channel. Whenever the pipeline changes in slope, diameter or direction, a manhole is built to provide access both for sewage flow measurement and sampling and for pipeline inspection and maintenance. Batter boards have traditionally been used to give line and grade for a gravity flow pipeline (lasers are frequently used in present-day construction). The pipe is first located by a series of stakes that are usually set at 50ft (15m) intervals and offset 3 – 6 ft (1 – 2m) from the pipe centerline. The batter boards are set at a constant elevation (say, 7’0”) above the pipe flow line or invert and a string line is run between the boards so that it is directly over the pipe centerline. The string line will have a slope equal to that of the pipeline.
  • 8. It is then simple for the workers to place the pipe sections into the trench in the proper position on a bed of sand and gravel, and to adjust the pipe invert while making periodic measurements from the string line.
  • 9. Example Suppose that it is necessary to build a new sewer from a house to an existing manhole. It is assumed that the flow line must be at least 3ft (1m) below the ground surface, and the minimum slope should be 0.004. A manhole should be placed at any change in gradient. The flow line elevation at the house is given as 70.03 on the plans. The invert elevation of the existing manhole must be determined during the preliminary survey by opening the manhole cover and observing a rod held on the flow line. Field steps: 1. Stake out a 4-ft offset line, placing stake 0+0 beside the point in the house where the house connection is located and a stake every 50 ft thereafter. Carry the measurement to a point beside the manhole, and determine its plus. 2. Find the elevation of the ground at each 50 ft point along the true line and at all breaks in ground slope. The rod is held on the ground at an estimated 4 ft from and opposite to each offset stake. This places the rod at the true position on the construction line. 3. At the same time, determine the elevation of the tops of each of the offset-line stakes. 4. Draw the profile of the ground elevations and determine the grade profile for the flow line.