SlideShare a Scribd company logo
1 of 5
Download to read offline
Testing of bored pile inclination
Joram M. AMIR
Chairman, Piletest.com Ltd. JMAmir@Piletest.com
Erez I. AMIR
President, Piletest.com Ltd. Erezam@piletest.com
Keywords: deep foundations, inclination, testing, raked piles
ABSTRACT:
The allowable deviation from of piles from verticality is mentioned in practically all piling specifications,
with typical values ranging from 1.33 to 2 percent. Similarly, specifications also limit the tolerance of raked
piles from their specified inclination. While this restriction seems critical for piled retaining walls, the
reasoning behind this restriction for piled foundations is not well understood. Finite element simulation we
carried out has shown that exceeding the above limits can introduce large bending moments and shear forces
in piles designed strictly for axial loads and may even lead to structural failure. Still, the above specifications
are seldom enforced due to the lack of convenient testing apparati. In this paper, we describe the BIT
(Borehole Inclination Tester), present its details and calculation method, and show initial field results.
1 INTRODUCTION
Probably all piling specifications prescribe the
tolerances for both centricity and verticality of
piles. The following examples demonstrate
common values for allowable deviation:
“Verticality – the maximum permitted deviation
of the finished pile from the vertical at any level is
1 in 75. Rake – the maximum permitted deviation
of any part of the finished pile from the specified
rake is 1 in 25 for piles raking up to 1 in 6 and 1 in
15 for piles raking more than 1 in 6” (ICE 1996).
“The vertical alignment of a vertical shaft
excavation shall not vary from the plan alignment
by more than 20 mm per meter (1/4 inch per foot)
of depth. The alignment of a battered shaft
excavation shall not vary by more than 40 mm per
meter (1/2 inch per foot) of the distance along the
axis of the shaft from the prescribed batter”
(O’Neill and Reese 1999).
The importance of controlling the verticality of
a contiguous piled retaining wall is clear: piles
protruding excessively into an excavation for a
parking basement, for instance, may cause the loss
of parking spaces and hinder the granting of a
building permit. Strict verticality is even more
important in secant pile walls, where misalignment
can make the wall non-watertight (Fleming et al.
1994). The questions we set out to answer were
twofold.
• Why is verticality important for single
foundation piles?
• How can we quickly check conformance of
bored piles to the specifications regarding
inclination?
In the following, we shall use finite element
simulation to prove the importance of complying
with such specifications. Later on we shall present
a brief overview of existing devices which can
measure pile verticality and then describe the
system which we developed specifically for testing
pile inclination. Initial field results which we have
obtained demonstrate the viability and accuracy of
this technique.
2 TERMINOLOGY
Borehole axis – The trajectory the Kelly bar tip
follows when lowered into the borehole.
Inclination – the angle, in either degrees or
percent, between the vertical and the borehole axis
at any given depth.
Battered pile or raking pile – a pile purposely
constructed at an inclination.
Stop – a depth in the hole at which stabilized
inclination readings are taken.
Depth interval – the mean distance along the
borehole axis between two consecutive stops.
Deviation – the vector, measured in the
horizontal plane, from the planned borehole axis to
the actual one.
3 FINITE ELEMENT SIMULATION
To get a better understanding of the effect of
excessive inclination, we ran a two-dimensional
Plaxis simulation of a diaphragm wall 600 mm
thick and 20 m deep, embedded in soft clay. The
wall inclination was 2.5 percent from the vertical,
a mere 0.5 percent above the typically acceptable
value. We checked two cases: a free wall and a
horizontally-restrained one.
The results show the distribution of normal
force N, shear force Q and bending moment M
down the wall for both a free-headed (Figure 1)
and a fixed-headed (
Figure 2) wall. It shows clearly that even a small
excessive deviation can introduce large,
not-accounted for, shear forces and bending
moments in free walls. In restrained walls, e.g.
those connected by beams, this effect is minimal.
Although this two-dimensional simulation is not
fully-valid for three dimensional piles, the results
are at least qualitatively applicable.
Figure 1: Effect of vertical load on inclined
free-headed wall
Figure 2: Effect of vertical load on inclined restrained wall
4 EXISTING SYSTEMS
Present methods for measuring the inclination of
bored piles are invariably based on the plumb bob
principle: the instrument is hung down from the
planned center of the pile, and the distance to the
sidewalls is measured by ultrasonic sensors (Bruce
et al. 1989, Kort and Kostaschuk 2007). The
sensors are arranged in either of two fashions:
• Four transceivers in two mutually-
perpendicular sets, providing four readings per
every depth
• One rotating transceiver, giving 360º coverage.
Once the hole is completely logged, the
sidewall profile is drawn and, provided it is
relatively regular, the pile axis can be plotted and
compared to the vertical. A bonus of this approach
is that it enables the calculation of the bore
volume, an item of special interest to contractors.
An interesting and simple method, described by
Bruce et al. (1989), is the inverted pendulum in
which a buoy floating on the slurry replaced the
plumb bob.
The above systems have several drawbacks:
• They can be used only in slurry-filled holes
• They cannot be used in slender piles (when the
slenderness ratio L/d exceeds 25, a deviation of
2% or more from the vertical cannot be
measured)
• They cannot be used to measure the inclination
of raked piles
• They cannot be used to measure the inclination
of finished piles
• Some of these systems are cumbersome and
need a dedicated crane to move around the site
and an AC generator to power them.
5 THE PROPOSED SYSTEM
5.1 Description
The system is dual purpose:
• During drilling, it can be mounted on the
drilling bucket that acts as centralizer.
• In the finished pile, it can be lowered inside the
access tubes which are routinely installed for
crosshole ultrasonic testing (ASTM 2008).
The system consists of four main units (Figure
3):
1. The upper unit which contains the electronic
circuitry and is mounted inside a 100 m.
cable-reel
2. The lower unit, containing a bi-axial (X-Y)
Micro Electro-Mechanical System (MEMS)
inclinometer, a MEMS gyro and a
thermometer, all packaged in a compact
waterproof housing. For drilling monitoring,
the lower unit is rigidly mounted on the drilling
bucket crossbar while for finished pile testing it
is mounted on a stabilizer that acts as both a
centralizer and a rotation-suppressor.
3. A wireless depth meter
4. A hand-held computer for recording and
presenting data
Figure 3: Schematic drawing of the system components
The lower unit transmits the data to the upper
one via a cable that runs over the depth meter
wheel and operates it. The upper unit uses wireless
communication to both the depth meter and the
computer.
The actual system components are depicted in
Figure 4.
5.2 Operation - Drilling configuration
After the hole is drilled to the desired depth, the
lower unit is fixed on the bucket cross bar and
inserted into the hole while pointing to the
reference north. The inclination and azimuth are
measured at ground level and then at
predetermined stops until the drilling bucket
reaches the bottom of the hole. The procedure is
then repeated on the way up, with readings taken at
the same stops as before. During the whole
procedure, the rig operator should keep Kelly bar
rotation to a minimum (although some degree of
unavoidable rotation is tolerable). When the bucket
returns to the surface, it is aligned back with the
reference north, and a final reading taken. Typical
test duration is in the order of 10 to 15 minutes.
5.3 Operation - Access tube configuration
The lower unit with the stabilizer is inserted
into the access tube pointing to the reference north.
The inclination and azimuth are measured at pile
head level and then at predetermined stops until
the unit reaches the bottom of the tube. The
procedure is then repeated on the way up, with
readings taken at the same stops as before. When
the unit returns to the surface, it is aligned back
with the reference north, and a final reading taken.
Figure 4: The BIT system
5.4 Calculations (Figure 5)
1. For each stop numbered [n], with sensor
heading hn, the inclinations Xn and Yn in the X
and Y directions, respectively, are transformed
to inclinations in the North and East directions
by the following relationships.
)
sin(h
·
Y
-
)
cos(h
·
X
IncEast n
n
n
n
n +
= (1)
)
cos(h
·
Y
-
)
sin(h
·
X
-
IncNorth n
n
n
n
n = (2)
2. For each stop numbered [n] at depth = Dn, the
deviations of the pile axis in the N-E directions
are calculated as follows.
0
DevEast1 = (3)
0
DevNorth1 = (4)
)
2
tan(
)
(
DevEast
DevEast
1
1
1
-
n
n
−
−
+
⋅
−
+
=
n
n
n
n
IncEast
IncEast
D
D
(5)
)
2
tan(
)
(
DevNorth
DevNorth
1
1
1
-
n
n
−
−
+
⋅
−
+
=
n
n
n
n
IncNorth
IncNorth
D
D
(6)
Figure 5: Inclination and deviation explained
And the combined deviation expressed as a polar
vector is:
n
n
n r
Dev θ
∠
= , (7)
where
2
2
n
n
n DevEast
DevNorth
r +
= (8)








=
n
n
n
DevNorth
DevEast
arctan
θ
(9)
3. Ideally, for the final surface reading N, the
final calculated deviation rf should be zero.
4. If the closure error rf is less than a
pre-determined threshold value (expressed as a
fraction of pile length), it is proportionately
distributed among all stops.
5. If the closure error rn exceeds the threshold
value the operator receives a warning and may
decide to repeat the test.
6. For each stop, the corrected downward and
upward deviations are averaged and
transformed to polar coordinates.
5.5 Calibration
Since the specifications typically allow a deviation
in the order of only 1 to 2 percent, the system
accuracy should be at least one order of magnitude
smaller or better than 0.1%.
MEMS components are generally sensitive to
temperature changes. To achieve the required
accuracy, these components should be carefully
calibrated before the test, as follows:
Inclinometer calibration: The lower unit is
placed on a hard, smooth, horizontal surface and
stabilized inclination readings for both axes taken.
The lower unit is then rotated 1800
and the
procedure repeated. The mean X and Y readings,
respectively, are the level (or zero inclination)
readings.
Gyro calibration: MEMS gyro devices tend to
drift at a fairly constant rate. To compensate for
this drift the lower unit is laid stationary until the
rate of drift is constant, at which time it is
recorded.
Depth meter: A typical distance of 5 to 10 m is
marked on the cable and pulled over the depth
meter wheel.
5.6 Reporting
In addition to project and pile identification, the
report typically includes graphic presentation of
the results in two forms (Figure 6).
1. Top view of the pile axis superimposed on a
number of concentric circles showing the
radii in meters
2. Side view in which the maximum deviations
measured in all stops are connected by straight
lines on the background of a funnel depicting
the allowable deviation.
Figure 6: Typical results
6 CONCLUSIONS
Excessive inclination can be detrimental to piles
which were planned to be vertical, by introducing
large bending moments and shear forces. This
effect is much more prominent when the piles
heads are free to move.
The system presented is a portable instrument
for measuring the deviation of bored piles from the
vertical with accuracy within 0.1%. It may
therefore assist the geotechnical engineer to
enforce the specification for pile verticality. The
system may also serve piling contractors who have
to meet strict verticality tolerances in contiguous
and secant piled walls. In addition, it can help the
contractors to evaluate the suitability of specific
rigs to difficult site conditions, such as the
presence of boulders or rock.
7 REFERENCES
ASTM (2008). "Standard Test Method for Integrity Testing
of Concrete Deep Foundations by Ultrasonic Crosshole
Testing D6760-08", Vol. 04-09 pp. 943-949, West
Conshohocken PA
Bruce, D.A., Paoli, B.D., Mascardi, C. and Mongilardi, E.
(1989). “Monitoring and quality control of a 100 metre
deep diaphragm wall”, Proc. Intl. Conf. on Piling and
Deep Foundations.”, London,Vol 1, pp. 23-32.
O’Neill, M.W. and Reese, L.C. (1999). “Drilled shafts:
construction procedures and design methods”, ADSC,
Dallas, p. 448.
ICE (1996). “Specifications for piling and embedded
retaining walls”, Thomas Telford, London, p. 7.
Fleming, W.G.K., Weltman, A.J., Randolph, M.F. and Elson,
W.K. (1994). “Piling engineering (2nd ed.)” Blackie,
Glasgow, pp. 215-216.
Kort, D.A. and Kostaschuk, R.P. (2007). “Sonar calipering of
slurry constructed bored piles and the impact of pile
shape on measured capacity”, 8th Canadian Geotech.
Conf, Ottawa
O’Neill, M.W. and Reese, L.C. (1999). "Drilled Shafts:
Construction Procedures and Design Methods", US DOT
FHWA, Washington DC, p. 448

More Related Content

What's hot

Profile & Runout CONTROLS in GD&T
Profile & Runout CONTROLS in GD&TProfile & Runout CONTROLS in GD&T
Profile & Runout CONTROLS in GD&TSree Lakshmy
 
Design of flat plate slab and its Punching Shear Reinf.
Design of flat plate slab and its Punching Shear Reinf.Design of flat plate slab and its Punching Shear Reinf.
Design of flat plate slab and its Punching Shear Reinf.MD.MAHBUB UL ALAM
 
Reinforcement detailing
Reinforcement  detailingReinforcement  detailing
Reinforcement detailingAli Ishaqi
 
Seismic Design Of Structures Project
Seismic Design Of Structures ProjectSeismic Design Of Structures Project
Seismic Design Of Structures ProjectGunjan Shetye
 
Guiding Principles of Structural Planning
Guiding Principles of Structural PlanningGuiding Principles of Structural Planning
Guiding Principles of Structural PlanningRaj Shah
 
Design and analysis of RC structures with flat slab
Design and analysis of RC structures with flat slabDesign and analysis of RC structures with flat slab
Design and analysis of RC structures with flat slabDeepak Patil
 
Paper " STRUT-AND-TIE MODEL AND 3-D NONLINEAR FINITE ELEMENT ANALYSIS FOR THE...
Paper " STRUT-AND-TIE MODEL AND 3-D NONLINEAR FINITE ELEMENT ANALYSIS FOR THE...Paper " STRUT-AND-TIE MODEL AND 3-D NONLINEAR FINITE ELEMENT ANALYSIS FOR THE...
Paper " STRUT-AND-TIE MODEL AND 3-D NONLINEAR FINITE ELEMENT ANALYSIS FOR THE...Waleed E. El-Demerdash
 
Lec6-Aircraft structural idealisation 1
Lec6-Aircraft structural idealisation 1Lec6-Aircraft structural idealisation 1
Lec6-Aircraft structural idealisation 1Mahdi Damghani
 
Ahsanullah university ppt 1
Ahsanullah university  ppt 1Ahsanullah university  ppt 1
Ahsanullah university ppt 1Saranireza
 
Shear and diagonal tension in beams
Shear and diagonal tension in beamsShear and diagonal tension in beams
Shear and diagonal tension in beamsmuhammad musaab
 
Analysis and design of flat slabs using various codes
Analysis and design of flat slabs using various codesAnalysis and design of flat slabs using various codes
Analysis and design of flat slabs using various codeseSAT Publishing House
 
COMPARISON OF SEISMIC CODES OF CHINA, INDIA, UK AND USA (STRUCTURAL IRREGULA...
COMPARISON OF SEISMIC CODES OF CHINA, INDIA, UK AND USA  (STRUCTURAL IRREGULA...COMPARISON OF SEISMIC CODES OF CHINA, INDIA, UK AND USA  (STRUCTURAL IRREGULA...
COMPARISON OF SEISMIC CODES OF CHINA, INDIA, UK AND USA (STRUCTURAL IRREGULA...shankar kumar
 
Isolated footing design
Isolated footing designIsolated footing design
Isolated footing designsrinu_anduri
 

What's hot (20)

Profile & Runout CONTROLS in GD&T
Profile & Runout CONTROLS in GD&TProfile & Runout CONTROLS in GD&T
Profile & Runout CONTROLS in GD&T
 
Design of flat plate slab and its Punching Shear Reinf.
Design of flat plate slab and its Punching Shear Reinf.Design of flat plate slab and its Punching Shear Reinf.
Design of flat plate slab and its Punching Shear Reinf.
 
Reinforcement detailing
Reinforcement  detailingReinforcement  detailing
Reinforcement detailing
 
Seismic Design Of Structures Project
Seismic Design Of Structures ProjectSeismic Design Of Structures Project
Seismic Design Of Structures Project
 
Setting out work
Setting out workSetting out work
Setting out work
 
Guiding Principles of Structural Planning
Guiding Principles of Structural PlanningGuiding Principles of Structural Planning
Guiding Principles of Structural Planning
 
Design and analysis of slabs
Design and analysis of slabsDesign and analysis of slabs
Design and analysis of slabs
 
Design and analysis of RC structures with flat slab
Design and analysis of RC structures with flat slabDesign and analysis of RC structures with flat slab
Design and analysis of RC structures with flat slab
 
Paper " STRUT-AND-TIE MODEL AND 3-D NONLINEAR FINITE ELEMENT ANALYSIS FOR THE...
Paper " STRUT-AND-TIE MODEL AND 3-D NONLINEAR FINITE ELEMENT ANALYSIS FOR THE...Paper " STRUT-AND-TIE MODEL AND 3-D NONLINEAR FINITE ELEMENT ANALYSIS FOR THE...
Paper " STRUT-AND-TIE MODEL AND 3-D NONLINEAR FINITE ELEMENT ANALYSIS FOR THE...
 
Lec6-Aircraft structural idealisation 1
Lec6-Aircraft structural idealisation 1Lec6-Aircraft structural idealisation 1
Lec6-Aircraft structural idealisation 1
 
Flat slabs 1
Flat slabs 1Flat slabs 1
Flat slabs 1
 
Deep beams
Deep beams Deep beams
Deep beams
 
DESIGN OF FLAT SLABS
DESIGN OF FLAT SLABSDESIGN OF FLAT SLABS
DESIGN OF FLAT SLABS
 
Dynamics Project
Dynamics ProjectDynamics Project
Dynamics Project
 
Crane
CraneCrane
Crane
 
Ahsanullah university ppt 1
Ahsanullah university  ppt 1Ahsanullah university  ppt 1
Ahsanullah university ppt 1
 
Shear and diagonal tension in beams
Shear and diagonal tension in beamsShear and diagonal tension in beams
Shear and diagonal tension in beams
 
Analysis and design of flat slabs using various codes
Analysis and design of flat slabs using various codesAnalysis and design of flat slabs using various codes
Analysis and design of flat slabs using various codes
 
COMPARISON OF SEISMIC CODES OF CHINA, INDIA, UK AND USA (STRUCTURAL IRREGULA...
COMPARISON OF SEISMIC CODES OF CHINA, INDIA, UK AND USA  (STRUCTURAL IRREGULA...COMPARISON OF SEISMIC CODES OF CHINA, INDIA, UK AND USA  (STRUCTURAL IRREGULA...
COMPARISON OF SEISMIC CODES OF CHINA, INDIA, UK AND USA (STRUCTURAL IRREGULA...
 
Isolated footing design
Isolated footing designIsolated footing design
Isolated footing design
 

Similar to Testing of bored_pile_inclination

surfaceroughnessmetrology-SPU.pptx
surfaceroughnessmetrology-SPU.pptxsurfaceroughnessmetrology-SPU.pptx
surfaceroughnessmetrology-SPU.pptxSheetalUdgave1
 
Research Article - Automation of an excavator boom movement in 3D
Research Article - Automation of an excavator boom movement in 3DResearch Article - Automation of an excavator boom movement in 3D
Research Article - Automation of an excavator boom movement in 3DVan Tien Nguyen
 
Isolation of MIMO Antenna with Electromagnetic Band Gap Structure
Isolation of MIMO Antenna with Electromagnetic Band Gap StructureIsolation of MIMO Antenna with Electromagnetic Band Gap Structure
Isolation of MIMO Antenna with Electromagnetic Band Gap StructureAysu COSKUN
 
Recent changes in underground traversing techniques in western australia
Recent changes in underground traversing techniques in western australiaRecent changes in underground traversing techniques in western australia
Recent changes in underground traversing techniques in western australiabrett_grocock
 
Surface roughness metrology
Surface roughness metrologySurface roughness metrology
Surface roughness metrologyHarshal Varade
 
Seismic response of rc frame structure with soft storey
Seismic response of rc frame structure with soft storeySeismic response of rc frame structure with soft storey
Seismic response of rc frame structure with soft storeyeSAT Publishing House
 
Frank smith final presentation
Frank smith final presentationFrank smith final presentation
Frank smith final presentationbrett_grocock
 
PRESENTATION 3 - Copy.pptx
PRESENTATION 3 - Copy.pptxPRESENTATION 3 - Copy.pptx
PRESENTATION 3 - Copy.pptxkuba9
 
2016 optimisation a rear wing endplate in a rotating domain
2016 optimisation a rear wing endplate in a rotating domain2016 optimisation a rear wing endplate in a rotating domain
2016 optimisation a rear wing endplate in a rotating domainHashan Mendis
 
Earthquake analysis on 2 d rc frames with different aspect ratios of masonry ...
Earthquake analysis on 2 d rc frames with different aspect ratios of masonry ...Earthquake analysis on 2 d rc frames with different aspect ratios of masonry ...
Earthquake analysis on 2 d rc frames with different aspect ratios of masonry ...eSAT Journals
 
Earthquake analysis on 2 d rc frames with different aspect ratios of masonry ...
Earthquake analysis on 2 d rc frames with different aspect ratios of masonry ...Earthquake analysis on 2 d rc frames with different aspect ratios of masonry ...
Earthquake analysis on 2 d rc frames with different aspect ratios of masonry ...eSAT Journals
 
Earthquake analysis on 2 d rc frames with different
Earthquake analysis on 2 d rc frames with differentEarthquake analysis on 2 d rc frames with different
Earthquake analysis on 2 d rc frames with differenteSAT Publishing House
 
STUDIES OF ANALYSIS AND DESIGN FOR MULTI-STORIES STRUCTURES WITH TRANSFER PLA...
STUDIES OF ANALYSIS AND DESIGN FOR MULTI-STORIES STRUCTURES WITH TRANSFER PLA...STUDIES OF ANALYSIS AND DESIGN FOR MULTI-STORIES STRUCTURES WITH TRANSFER PLA...
STUDIES OF ANALYSIS AND DESIGN FOR MULTI-STORIES STRUCTURES WITH TRANSFER PLA...IRJET Journal
 
Bdp shear aci
Bdp shear aciBdp shear aci
Bdp shear aciOscar A
 
Seismic Behaviour of Reinforced Concrete Flat Plate Systems
Seismic Behaviour of Reinforced Concrete Flat Plate SystemsSeismic Behaviour of Reinforced Concrete Flat Plate Systems
Seismic Behaviour of Reinforced Concrete Flat Plate SystemsIRJET Journal
 
Seismic Analysis of Multi-Storeyed Building Having Vertical Irregularities us...
Seismic Analysis of Multi-Storeyed Building Having Vertical Irregularities us...Seismic Analysis of Multi-Storeyed Building Having Vertical Irregularities us...
Seismic Analysis of Multi-Storeyed Building Having Vertical Irregularities us...IRJET Journal
 

Similar to Testing of bored_pile_inclination (20)

surfaceroughnessmetrology-SPU.pptx
surfaceroughnessmetrology-SPU.pptxsurfaceroughnessmetrology-SPU.pptx
surfaceroughnessmetrology-SPU.pptx
 
Research Article - Automation of an excavator boom movement in 3D
Research Article - Automation of an excavator boom movement in 3DResearch Article - Automation of an excavator boom movement in 3D
Research Article - Automation of an excavator boom movement in 3D
 
Isolation of MIMO Antenna with Electromagnetic Band Gap Structure
Isolation of MIMO Antenna with Electromagnetic Band Gap StructureIsolation of MIMO Antenna with Electromagnetic Band Gap Structure
Isolation of MIMO Antenna with Electromagnetic Band Gap Structure
 
Recent changes in underground traversing techniques in western australia
Recent changes in underground traversing techniques in western australiaRecent changes in underground traversing techniques in western australia
Recent changes in underground traversing techniques in western australia
 
Surface roughness metrology
Surface roughness metrologySurface roughness metrology
Surface roughness metrology
 
Surface roughness
Surface roughnessSurface roughness
Surface roughness
 
Seismic response of rc frame structure with soft storey
Seismic response of rc frame structure with soft storeySeismic response of rc frame structure with soft storey
Seismic response of rc frame structure with soft storey
 
Frank smith final presentation
Frank smith final presentationFrank smith final presentation
Frank smith final presentation
 
PRESENTATION 3 - Copy.pptx
PRESENTATION 3 - Copy.pptxPRESENTATION 3 - Copy.pptx
PRESENTATION 3 - Copy.pptx
 
2016 optimisation a rear wing endplate in a rotating domain
2016 optimisation a rear wing endplate in a rotating domain2016 optimisation a rear wing endplate in a rotating domain
2016 optimisation a rear wing endplate in a rotating domain
 
Earthquake analysis on 2 d rc frames with different aspect ratios of masonry ...
Earthquake analysis on 2 d rc frames with different aspect ratios of masonry ...Earthquake analysis on 2 d rc frames with different aspect ratios of masonry ...
Earthquake analysis on 2 d rc frames with different aspect ratios of masonry ...
 
Earthquake analysis on 2 d rc frames with different aspect ratios of masonry ...
Earthquake analysis on 2 d rc frames with different aspect ratios of masonry ...Earthquake analysis on 2 d rc frames with different aspect ratios of masonry ...
Earthquake analysis on 2 d rc frames with different aspect ratios of masonry ...
 
Earthquake analysis on 2 d rc frames with different
Earthquake analysis on 2 d rc frames with differentEarthquake analysis on 2 d rc frames with different
Earthquake analysis on 2 d rc frames with different
 
MEMS CAPACITIVE ACCELEROMETER
MEMS CAPACITIVE ACCELEROMETERMEMS CAPACITIVE ACCELEROMETER
MEMS CAPACITIVE ACCELEROMETER
 
STUDIES OF ANALYSIS AND DESIGN FOR MULTI-STORIES STRUCTURES WITH TRANSFER PLA...
STUDIES OF ANALYSIS AND DESIGN FOR MULTI-STORIES STRUCTURES WITH TRANSFER PLA...STUDIES OF ANALYSIS AND DESIGN FOR MULTI-STORIES STRUCTURES WITH TRANSFER PLA...
STUDIES OF ANALYSIS AND DESIGN FOR MULTI-STORIES STRUCTURES WITH TRANSFER PLA...
 
Nano Indentation Lecture1
Nano Indentation Lecture1Nano Indentation Lecture1
Nano Indentation Lecture1
 
Bdp shear aci
Bdp shear aciBdp shear aci
Bdp shear aci
 
Seismic Behaviour of Reinforced Concrete Flat Plate Systems
Seismic Behaviour of Reinforced Concrete Flat Plate SystemsSeismic Behaviour of Reinforced Concrete Flat Plate Systems
Seismic Behaviour of Reinforced Concrete Flat Plate Systems
 
Seismic Analysis of Multi-Storeyed Building Having Vertical Irregularities us...
Seismic Analysis of Multi-Storeyed Building Having Vertical Irregularities us...Seismic Analysis of Multi-Storeyed Building Having Vertical Irregularities us...
Seismic Analysis of Multi-Storeyed Building Having Vertical Irregularities us...
 
1228808532(2)
1228808532(2)1228808532(2)
1228808532(2)
 

Recently uploaded

Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 

Recently uploaded (20)

Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 

Testing of bored_pile_inclination

  • 1. Testing of bored pile inclination Joram M. AMIR Chairman, Piletest.com Ltd. JMAmir@Piletest.com Erez I. AMIR President, Piletest.com Ltd. Erezam@piletest.com Keywords: deep foundations, inclination, testing, raked piles ABSTRACT: The allowable deviation from of piles from verticality is mentioned in practically all piling specifications, with typical values ranging from 1.33 to 2 percent. Similarly, specifications also limit the tolerance of raked piles from their specified inclination. While this restriction seems critical for piled retaining walls, the reasoning behind this restriction for piled foundations is not well understood. Finite element simulation we carried out has shown that exceeding the above limits can introduce large bending moments and shear forces in piles designed strictly for axial loads and may even lead to structural failure. Still, the above specifications are seldom enforced due to the lack of convenient testing apparati. In this paper, we describe the BIT (Borehole Inclination Tester), present its details and calculation method, and show initial field results. 1 INTRODUCTION Probably all piling specifications prescribe the tolerances for both centricity and verticality of piles. The following examples demonstrate common values for allowable deviation: “Verticality – the maximum permitted deviation of the finished pile from the vertical at any level is 1 in 75. Rake – the maximum permitted deviation of any part of the finished pile from the specified rake is 1 in 25 for piles raking up to 1 in 6 and 1 in 15 for piles raking more than 1 in 6” (ICE 1996). “The vertical alignment of a vertical shaft excavation shall not vary from the plan alignment by more than 20 mm per meter (1/4 inch per foot) of depth. The alignment of a battered shaft excavation shall not vary by more than 40 mm per meter (1/2 inch per foot) of the distance along the axis of the shaft from the prescribed batter” (O’Neill and Reese 1999). The importance of controlling the verticality of a contiguous piled retaining wall is clear: piles protruding excessively into an excavation for a parking basement, for instance, may cause the loss of parking spaces and hinder the granting of a building permit. Strict verticality is even more important in secant pile walls, where misalignment can make the wall non-watertight (Fleming et al. 1994). The questions we set out to answer were twofold. • Why is verticality important for single foundation piles? • How can we quickly check conformance of bored piles to the specifications regarding inclination? In the following, we shall use finite element simulation to prove the importance of complying with such specifications. Later on we shall present a brief overview of existing devices which can measure pile verticality and then describe the system which we developed specifically for testing pile inclination. Initial field results which we have obtained demonstrate the viability and accuracy of this technique. 2 TERMINOLOGY Borehole axis – The trajectory the Kelly bar tip follows when lowered into the borehole. Inclination – the angle, in either degrees or percent, between the vertical and the borehole axis at any given depth.
  • 2. Battered pile or raking pile – a pile purposely constructed at an inclination. Stop – a depth in the hole at which stabilized inclination readings are taken. Depth interval – the mean distance along the borehole axis between two consecutive stops. Deviation – the vector, measured in the horizontal plane, from the planned borehole axis to the actual one. 3 FINITE ELEMENT SIMULATION To get a better understanding of the effect of excessive inclination, we ran a two-dimensional Plaxis simulation of a diaphragm wall 600 mm thick and 20 m deep, embedded in soft clay. The wall inclination was 2.5 percent from the vertical, a mere 0.5 percent above the typically acceptable value. We checked two cases: a free wall and a horizontally-restrained one. The results show the distribution of normal force N, shear force Q and bending moment M down the wall for both a free-headed (Figure 1) and a fixed-headed ( Figure 2) wall. It shows clearly that even a small excessive deviation can introduce large, not-accounted for, shear forces and bending moments in free walls. In restrained walls, e.g. those connected by beams, this effect is minimal. Although this two-dimensional simulation is not fully-valid for three dimensional piles, the results are at least qualitatively applicable. Figure 1: Effect of vertical load on inclined free-headed wall Figure 2: Effect of vertical load on inclined restrained wall 4 EXISTING SYSTEMS Present methods for measuring the inclination of bored piles are invariably based on the plumb bob principle: the instrument is hung down from the planned center of the pile, and the distance to the sidewalls is measured by ultrasonic sensors (Bruce et al. 1989, Kort and Kostaschuk 2007). The sensors are arranged in either of two fashions: • Four transceivers in two mutually- perpendicular sets, providing four readings per every depth • One rotating transceiver, giving 360º coverage. Once the hole is completely logged, the sidewall profile is drawn and, provided it is relatively regular, the pile axis can be plotted and compared to the vertical. A bonus of this approach is that it enables the calculation of the bore volume, an item of special interest to contractors. An interesting and simple method, described by Bruce et al. (1989), is the inverted pendulum in which a buoy floating on the slurry replaced the plumb bob. The above systems have several drawbacks: • They can be used only in slurry-filled holes • They cannot be used in slender piles (when the slenderness ratio L/d exceeds 25, a deviation of 2% or more from the vertical cannot be measured) • They cannot be used to measure the inclination of raked piles • They cannot be used to measure the inclination of finished piles • Some of these systems are cumbersome and need a dedicated crane to move around the site and an AC generator to power them. 5 THE PROPOSED SYSTEM 5.1 Description The system is dual purpose: • During drilling, it can be mounted on the drilling bucket that acts as centralizer. • In the finished pile, it can be lowered inside the access tubes which are routinely installed for crosshole ultrasonic testing (ASTM 2008). The system consists of four main units (Figure 3):
  • 3. 1. The upper unit which contains the electronic circuitry and is mounted inside a 100 m. cable-reel 2. The lower unit, containing a bi-axial (X-Y) Micro Electro-Mechanical System (MEMS) inclinometer, a MEMS gyro and a thermometer, all packaged in a compact waterproof housing. For drilling monitoring, the lower unit is rigidly mounted on the drilling bucket crossbar while for finished pile testing it is mounted on a stabilizer that acts as both a centralizer and a rotation-suppressor. 3. A wireless depth meter 4. A hand-held computer for recording and presenting data Figure 3: Schematic drawing of the system components The lower unit transmits the data to the upper one via a cable that runs over the depth meter wheel and operates it. The upper unit uses wireless communication to both the depth meter and the computer. The actual system components are depicted in Figure 4. 5.2 Operation - Drilling configuration After the hole is drilled to the desired depth, the lower unit is fixed on the bucket cross bar and inserted into the hole while pointing to the reference north. The inclination and azimuth are measured at ground level and then at predetermined stops until the drilling bucket reaches the bottom of the hole. The procedure is then repeated on the way up, with readings taken at the same stops as before. During the whole procedure, the rig operator should keep Kelly bar rotation to a minimum (although some degree of unavoidable rotation is tolerable). When the bucket returns to the surface, it is aligned back with the reference north, and a final reading taken. Typical test duration is in the order of 10 to 15 minutes. 5.3 Operation - Access tube configuration The lower unit with the stabilizer is inserted into the access tube pointing to the reference north. The inclination and azimuth are measured at pile head level and then at predetermined stops until the unit reaches the bottom of the tube. The procedure is then repeated on the way up, with readings taken at the same stops as before. When the unit returns to the surface, it is aligned back with the reference north, and a final reading taken. Figure 4: The BIT system 5.4 Calculations (Figure 5) 1. For each stop numbered [n], with sensor heading hn, the inclinations Xn and Yn in the X and Y directions, respectively, are transformed to inclinations in the North and East directions by the following relationships. ) sin(h · Y - ) cos(h · X IncEast n n n n n + = (1) ) cos(h · Y - ) sin(h · X - IncNorth n n n n n = (2) 2. For each stop numbered [n] at depth = Dn, the deviations of the pile axis in the N-E directions are calculated as follows.
  • 4. 0 DevEast1 = (3) 0 DevNorth1 = (4) ) 2 tan( ) ( DevEast DevEast 1 1 1 - n n − − + ⋅ − + = n n n n IncEast IncEast D D (5) ) 2 tan( ) ( DevNorth DevNorth 1 1 1 - n n − − + ⋅ − + = n n n n IncNorth IncNorth D D (6) Figure 5: Inclination and deviation explained And the combined deviation expressed as a polar vector is: n n n r Dev θ ∠ = , (7) where 2 2 n n n DevEast DevNorth r + = (8)         = n n n DevNorth DevEast arctan θ (9) 3. Ideally, for the final surface reading N, the final calculated deviation rf should be zero. 4. If the closure error rf is less than a pre-determined threshold value (expressed as a fraction of pile length), it is proportionately distributed among all stops. 5. If the closure error rn exceeds the threshold value the operator receives a warning and may decide to repeat the test. 6. For each stop, the corrected downward and upward deviations are averaged and transformed to polar coordinates. 5.5 Calibration Since the specifications typically allow a deviation in the order of only 1 to 2 percent, the system accuracy should be at least one order of magnitude smaller or better than 0.1%. MEMS components are generally sensitive to temperature changes. To achieve the required accuracy, these components should be carefully calibrated before the test, as follows: Inclinometer calibration: The lower unit is placed on a hard, smooth, horizontal surface and stabilized inclination readings for both axes taken. The lower unit is then rotated 1800 and the procedure repeated. The mean X and Y readings, respectively, are the level (or zero inclination) readings. Gyro calibration: MEMS gyro devices tend to drift at a fairly constant rate. To compensate for this drift the lower unit is laid stationary until the rate of drift is constant, at which time it is recorded. Depth meter: A typical distance of 5 to 10 m is marked on the cable and pulled over the depth meter wheel. 5.6 Reporting In addition to project and pile identification, the report typically includes graphic presentation of the results in two forms (Figure 6). 1. Top view of the pile axis superimposed on a number of concentric circles showing the radii in meters 2. Side view in which the maximum deviations measured in all stops are connected by straight lines on the background of a funnel depicting the allowable deviation.
  • 5. Figure 6: Typical results 6 CONCLUSIONS Excessive inclination can be detrimental to piles which were planned to be vertical, by introducing large bending moments and shear forces. This effect is much more prominent when the piles heads are free to move. The system presented is a portable instrument for measuring the deviation of bored piles from the vertical with accuracy within 0.1%. It may therefore assist the geotechnical engineer to enforce the specification for pile verticality. The system may also serve piling contractors who have to meet strict verticality tolerances in contiguous and secant piled walls. In addition, it can help the contractors to evaluate the suitability of specific rigs to difficult site conditions, such as the presence of boulders or rock. 7 REFERENCES ASTM (2008). "Standard Test Method for Integrity Testing of Concrete Deep Foundations by Ultrasonic Crosshole Testing D6760-08", Vol. 04-09 pp. 943-949, West Conshohocken PA Bruce, D.A., Paoli, B.D., Mascardi, C. and Mongilardi, E. (1989). “Monitoring and quality control of a 100 metre deep diaphragm wall”, Proc. Intl. Conf. on Piling and Deep Foundations.”, London,Vol 1, pp. 23-32. O’Neill, M.W. and Reese, L.C. (1999). “Drilled shafts: construction procedures and design methods”, ADSC, Dallas, p. 448. ICE (1996). “Specifications for piling and embedded retaining walls”, Thomas Telford, London, p. 7. Fleming, W.G.K., Weltman, A.J., Randolph, M.F. and Elson, W.K. (1994). “Piling engineering (2nd ed.)” Blackie, Glasgow, pp. 215-216. Kort, D.A. and Kostaschuk, R.P. (2007). “Sonar calipering of slurry constructed bored piles and the impact of pile shape on measured capacity”, 8th Canadian Geotech. Conf, Ottawa O’Neill, M.W. and Reese, L.C. (1999). "Drilled Shafts: Construction Procedures and Design Methods", US DOT FHWA, Washington DC, p. 448