SlideShare a Scribd company logo
1 of 2
HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 WORKPLACE TEMPORARY ELECTRICAL SUPPLY
Issued: Rev. Date:
Revision: 0
Page 1 of 2 HSEQ -Rev-01(Aug-2018)
No
Specific Task Step
(In sequence of
works)
Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
L C RR
1
Installation of
distribution boards to
work areas
 Electricity
 Electrocution;
 Fire;
4 4
16
High
i. All distribution boards (DB) will be within a locked,steel,IP 54 (water and
dustproof) enclosure with mandatorywarning signs;
ii. All openings/holes and penetrations into the DB mustbe closed to IP 54
rating;
iii. All circuits mustbe protected by correct size circuitbreakers and the DB
musthave padlock in addition to the locks alreadyfitted to the DB door;
iv. All 220v/380v supplies mustbe protected by an RCD with a trip current of
not more than 30mA. Every RCD mustbe tested frequently by the
competentperson;
v. Sockets mustonly be mounted on the exterior of the DB enclosure. Timber
framed splitter units are not permitted;
vi. All Steel Wired Armour cables musthave earthing bond cable connected
from gland to earth bar within the DB;
vii. SMDB’s and DB’s shall be subjectto regular inspections,anydamaged
units removed from service;
Rain entering
DB’s;
SMDB’s and DB’s
damaged
Remove from site Low
2
Temporaryelectrics -
offices
 Electrical
connections and
terminations
 Use of untrained electricians for
electrical works;
 Use of substandard electrical fixtures
and fittings;
 Use of substandard connections;
 Non-adherence to colour coding of
wiring;
 Incorrect earthing;
 Tripping hazard; Damage to
unprotected cables;
 Use of incorrectly rated fuses;
4 3
12
High
i. All electricians to be suitablytrained and experienced in the works;
ii. All wiring,connections and terminations inspected prior to connection to
live supply;
iii. All wiring to follow colour coding standards; All fuses shall be to correct
rating for electrical system or equipment;
iv. All junction boxes and sockets fixed securelyto structure; All electrical
junction boxes,sockets and fittings to be of suitable quality;
v. Insulation tape shall not be used for cable connections,correctjunction
boxes to be used;
vi. All earth connections shall be to standards;
vii. No cables shall trail on the floor; all securelyclipped clear of damage or
posing a trip hazard;
viii. Armoured cable used for cables setbelow ground; Armoured cable shall be
correctly fitted and protected at junction boxes; All cables to be fed through
securelyfixed conduit;
Damaged cables
Disconnectsupplyand rectify
or remove. No taped
connections
Low
Project Name: xxx
RA Ref No.: xxx
RA compilation
Date:
Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Temporaryelectrical installation to projects,including generators,DB’s and
temporaryelectrical circuit installation.Use with RA 33 – Temporary Lighting
Relevant Applicable MAS:
 00237 – TemporaryElectrics;
Additional Training required: NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be?
What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen
frequently
Often (4)
6 to 12 times a year
Likely (3)
1 to 5 times a year
Possible (2)
Once every 5 years
Rarely (1)
Less than once every 5
years
Can the hazard be Eliminated or removed
from the w ork place?
Catastrophic (5)
Multiple Fatalities
High 25 High 20 High 15 Medium 10 Medium 5
Can the product or process be substitutedfor
a less hazardous alternative?
Serious (4)
Class 1 single fatality
High 20 High 16 High 12 Medium 8 Low 4
Can the hazard be engineered aw ay w ith
guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1
Permanently disabling effects
High 15 High 12 Medium 9 Medium 6 Low 3
Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work
restrictions. MTI
Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment &
Clothing be w orn to safe guard against
hazards?Insignificant (1)
FAI
Medium10 Medium 4 Low 3 Low 2 Low 1
HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 WORKPLACE TEMPORARY ELECTRICAL SUPPLY
Issued: Rev. Date:
Revision: 0
Page 2 of 2 HSEQ -Rev-01(Aug-2018)
No
Specific Task Step
(In sequence of
works)
Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
L C RR
3
Site generators –
offices and site  Temporarysupply
 Generator fires;
 Incidentdue to incorrectearthing;
 Fuel leakage – environmental risk;
 Fuel storage;
 Noise;
4 3
12
HIGH
i. Generators to be suitable size and capacity for the task, with maintenance
record;
ii. Generators to have suitable earth rod connected at all time;
iii. Fire extinguishers to be located close to generators;
iv. Generators to be fitted with drip trays;
v. Fuel tanks to be bunded to 110% capacity, bunds to be sealed with
delivery hoses retained inside bund;
vi. Generators to be subjectto regular inspection regime;Units monitored for
excessive exhaustfumes;
vii. Generators sited awayfrom combustible storage areas,offices and
welfare areas due to risk of fire and noise;
Fuel leaks
Area bunded and spill area
removed as hazardous waste
Low

More Related Content

What's hot

16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
Fire Risk Assessment.pdf
Fire Risk Assessment.pdfFire Risk Assessment.pdf
Fire Risk Assessment.pdfHSEXINYIPROJECT
 
Risk Assessment Example.pdf
Risk Assessment Example.pdfRisk Assessment Example.pdf
Risk Assessment Example.pdfBalamuruganD26
 
15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templates19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templatesDwarika Bhushan Sharma
 
18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templates18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templatesDwarika Bhushan Sharma
 
25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templatesDwarika Bhushan Sharma
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templatesDwarika Bhushan Sharma
 
Portable tools risk assessment
Portable tools risk assessment Portable tools risk assessment
Portable tools risk assessment Nidhin Sajeevan
 
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templatesDwarika Bhushan Sharma
 
14 use of plant graders and road rollers risk assessment templates
14 use of plant  graders and road rollers risk assessment templates14 use of plant  graders and road rollers risk assessment templates
14 use of plant graders and road rollers risk assessment templatesDwarika Bhushan Sharma
 
2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templatesDwarika Bhushan Sharma
 
13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templatesDwarika Bhushan Sharma
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docxDwarika Bhushan Sharma
 

What's hot (20)

16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates
 
Fire Risk Assessment.pdf
Fire Risk Assessment.pdfFire Risk Assessment.pdf
Fire Risk Assessment.pdf
 
Risk Assessment Example.pdf
Risk Assessment Example.pdfRisk Assessment Example.pdf
Risk Assessment Example.pdf
 
15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates
 
19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templates19 use of mobile elevated work platforms risk assessment templates
19 use of mobile elevated work platforms risk assessment templates
 
18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templates18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templates
 
25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates
 
Portable tools risk assessment
Portable tools risk assessment Portable tools risk assessment
Portable tools risk assessment
 
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
 
9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates
 
14 use of plant graders and road rollers risk assessment templates
14 use of plant  graders and road rollers risk assessment templates14 use of plant  graders and road rollers risk assessment templates
14 use of plant graders and road rollers risk assessment templates
 
Amn safety induction j 175 - staff rev 4 - s 14
Amn safety induction  j 175 - staff rev 4 - s 14Amn safety induction  j 175 - staff rev 4 - s 14
Amn safety induction j 175 - staff rev 4 - s 14
 
2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates2 fire risk assessment template risk assessment templates
2 fire risk assessment template risk assessment templates
 
Internal EHS Audit check sheet
Internal EHS Audit check sheetInternal EHS Audit check sheet
Internal EHS Audit check sheet
 
13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates
 
Hira
HiraHira
Hira
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 

Similar to 30 workplace temporary electrical supply risk assessment templates

29 workplace temporary lighting risk assessment templates
29 workplace temporary lighting risk assessment templates29 workplace temporary lighting risk assessment templates
29 workplace temporary lighting risk assessment templatesDwarika Bhushan Sharma
 
Level 3 ais-manual-12kv
Level 3 ais-manual-12kvLevel 3 ais-manual-12kv
Level 3 ais-manual-12kvHamZer
 
DATASHEET INVERSORES R6 SAJ TRIFASICOS LV
DATASHEET INVERSORES R6 SAJ TRIFASICOS LVDATASHEET INVERSORES R6 SAJ TRIFASICOS LV
DATASHEET INVERSORES R6 SAJ TRIFASICOS LVgrupopridesolar
 
conf-type-test-2007-03.ppt
conf-type-test-2007-03.pptconf-type-test-2007-03.ppt
conf-type-test-2007-03.pptssuser1f60f6
 
29 Workplace Temporary Lighting Risk Assessment Templates.docx
29 Workplace Temporary Lighting Risk Assessment Templates.docx29 Workplace Temporary Lighting Risk Assessment Templates.docx
29 Workplace Temporary Lighting Risk Assessment Templates.docxDwarika Bhushan Sharma
 
WirelessHART Gas Detector for Toxic and Combustible Gas
WirelessHART Gas Detector for Toxic and Combustible GasWirelessHART Gas Detector for Toxic and Combustible Gas
WirelessHART Gas Detector for Toxic and Combustible GasMiller Energy, Inc.
 
Manual osciloscopio GDS-800
Manual osciloscopio GDS-800Manual osciloscopio GDS-800
Manual osciloscopio GDS-800Armando Uribe Jr
 
Grid Event Analysis In Indian Power System
Grid Event Analysis In Indian Power SystemGrid Event Analysis In Indian Power System
Grid Event Analysis In Indian Power SystemChandan Kumar
 
GeoThermLtd-The_Report_Magazine_article_Rig_IR_Window_retrofit_June2020.pdf
GeoThermLtd-The_Report_Magazine_article_Rig_IR_Window_retrofit_June2020.pdfGeoThermLtd-The_Report_Magazine_article_Rig_IR_Window_retrofit_June2020.pdf
GeoThermLtd-The_Report_Magazine_article_Rig_IR_Window_retrofit_June2020.pdfTony Dale
 
RotorK process Controls
RotorK process ControlsRotorK process Controls
RotorK process ControlsSon Nguyen
 
27 hydrostatic pressure testing inside buildings risk assessment templates
27 hydrostatic pressure testing inside buildings risk assessment templates27 hydrostatic pressure testing inside buildings risk assessment templates
27 hydrostatic pressure testing inside buildings risk assessment templatesDwarika Bhushan Sharma
 
Littelfuse PGR-8800 D1000 Arc Flash Unit - DNV Marine Approval
Littelfuse PGR-8800 D1000 Arc Flash Unit - DNV Marine ApprovalLittelfuse PGR-8800 D1000 Arc Flash Unit - DNV Marine Approval
Littelfuse PGR-8800 D1000 Arc Flash Unit - DNV Marine ApprovalThorne & Derrick International
 
Trailblazers (Power) Install Substation Switchgear
Trailblazers (Power) Install Substation SwitchgearTrailblazers (Power) Install Substation Switchgear
Trailblazers (Power) Install Substation SwitchgearMarty Stevenson
 
Trailblazers (Power) Install Substation Circuit Breakers
Trailblazers (Power) Install Substation Circuit BreakersTrailblazers (Power) Install Substation Circuit Breakers
Trailblazers (Power) Install Substation Circuit BreakersMarty Stevenson
 
5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templatesDwarika Bhushan Sharma
 

Similar to 30 workplace temporary electrical supply risk assessment templates (20)

29 workplace temporary lighting risk assessment templates
29 workplace temporary lighting risk assessment templates29 workplace temporary lighting risk assessment templates
29 workplace temporary lighting risk assessment templates
 
Level 3 ais-manual-12kv
Level 3 ais-manual-12kvLevel 3 ais-manual-12kv
Level 3 ais-manual-12kv
 
DATASHEET INVERSORES R6 SAJ TRIFASICOS LV
DATASHEET INVERSORES R6 SAJ TRIFASICOS LVDATASHEET INVERSORES R6 SAJ TRIFASICOS LV
DATASHEET INVERSORES R6 SAJ TRIFASICOS LV
 
Relay testing procedure
Relay testing procedure Relay testing procedure
Relay testing procedure
 
conf-type-test-2007-03.ppt
conf-type-test-2007-03.pptconf-type-test-2007-03.ppt
conf-type-test-2007-03.ppt
 
29 Workplace Temporary Lighting Risk Assessment Templates.docx
29 Workplace Temporary Lighting Risk Assessment Templates.docx29 Workplace Temporary Lighting Risk Assessment Templates.docx
29 Workplace Temporary Lighting Risk Assessment Templates.docx
 
WirelessHART Gas Detector for Toxic and Combustible Gas
WirelessHART Gas Detector for Toxic and Combustible GasWirelessHART Gas Detector for Toxic and Combustible Gas
WirelessHART Gas Detector for Toxic and Combustible Gas
 
Manual osciloscopio GDS-800
Manual osciloscopio GDS-800Manual osciloscopio GDS-800
Manual osciloscopio GDS-800
 
Grid Event Analysis In Indian Power System
Grid Event Analysis In Indian Power SystemGrid Event Analysis In Indian Power System
Grid Event Analysis In Indian Power System
 
GeoThermLtd-The_Report_Magazine_article_Rig_IR_Window_retrofit_June2020.pdf
GeoThermLtd-The_Report_Magazine_article_Rig_IR_Window_retrofit_June2020.pdfGeoThermLtd-The_Report_Magazine_article_Rig_IR_Window_retrofit_June2020.pdf
GeoThermLtd-The_Report_Magazine_article_Rig_IR_Window_retrofit_June2020.pdf
 
RotorK process Controls
RotorK process ControlsRotorK process Controls
RotorK process Controls
 
27 hydrostatic pressure testing inside buildings risk assessment templates
27 hydrostatic pressure testing inside buildings risk assessment templates27 hydrostatic pressure testing inside buildings risk assessment templates
27 hydrostatic pressure testing inside buildings risk assessment templates
 
2015 nfpa 70 e changes
2015 nfpa 70 e changes2015 nfpa 70 e changes
2015 nfpa 70 e changes
 
Littelfuse PGR-8800 D1000 Arc Flash Unit - DNV Marine Approval
Littelfuse PGR-8800 D1000 Arc Flash Unit - DNV Marine ApprovalLittelfuse PGR-8800 D1000 Arc Flash Unit - DNV Marine Approval
Littelfuse PGR-8800 D1000 Arc Flash Unit - DNV Marine Approval
 
BAHAELDIN CV.
BAHAELDIN CV.BAHAELDIN CV.
BAHAELDIN CV.
 
078 switchgear install 1.0
078 switchgear install 1.0078 switchgear install 1.0
078 switchgear install 1.0
 
Trailblazers (Power) Install Substation Switchgear
Trailblazers (Power) Install Substation SwitchgearTrailblazers (Power) Install Substation Switchgear
Trailblazers (Power) Install Substation Switchgear
 
Trailblazers (Power) Install Substation Circuit Breakers
Trailblazers (Power) Install Substation Circuit BreakersTrailblazers (Power) Install Substation Circuit Breakers
Trailblazers (Power) Install Substation Circuit Breakers
 
076 circuit breaker install 1.0
076 circuit breaker install 1.0076 circuit breaker install 1.0
076 circuit breaker install 1.0
 
5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates
 

More from Dwarika Bhushan Sharma

4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdfDwarika Bhushan Sharma
 
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdfDwarika Bhushan Sharma
 
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdfDwarika Bhushan Sharma
 
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdfDwarika Bhushan Sharma
 
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docxDwarika Bhushan Sharma
 
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docxFIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docxDwarika Bhushan Sharma
 
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxSUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxDwarika Bhushan Sharma
 
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxSTORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxDwarika Bhushan Sharma
 
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxPROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxDwarika Bhushan Sharma
 
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docxHSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docxDwarika Bhushan Sharma
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxDwarika Bhushan Sharma
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxDwarika Bhushan Sharma
 
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxMOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxDwarika Bhushan Sharma
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxDwarika Bhushan Sharma
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docxDwarika Bhushan Sharma
 
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docHSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docDwarika Bhushan Sharma
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docDwarika Bhushan Sharma
 
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxOFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxDwarika Bhushan Sharma
 

More from Dwarika Bhushan Sharma (20)

4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
 
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
 
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
 
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
 
1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf
 
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
 
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docxFIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
 
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxSUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
 
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxSTORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
 
WITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docxWITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docx
 
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxPROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
 
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docxHSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
 
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxMOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
 
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docHSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
 
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxOFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
 

Recently uploaded

ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxUnboundStockton
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxJiesonDelaCerna
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentInMediaRes1
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.arsicmarija21
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 

Recently uploaded (20)

ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docx
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media Component
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 

30 workplace temporary electrical supply risk assessment templates

  • 1. HEALTH SAFETY AND ENVIRONMENT Author: Approved: RISK ASSESSMENT: ACT/HSE/RA 001 WORKPLACE TEMPORARY ELECTRICAL SUPPLY Issued: Rev. Date: Revision: 0 Page 1 of 2 HSEQ -Rev-01(Aug-2018) No Specific Task Step (In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR L C RR 1 Installation of distribution boards to work areas  Electricity  Electrocution;  Fire; 4 4 16 High i. All distribution boards (DB) will be within a locked,steel,IP 54 (water and dustproof) enclosure with mandatorywarning signs; ii. All openings/holes and penetrations into the DB mustbe closed to IP 54 rating; iii. All circuits mustbe protected by correct size circuitbreakers and the DB musthave padlock in addition to the locks alreadyfitted to the DB door; iv. All 220v/380v supplies mustbe protected by an RCD with a trip current of not more than 30mA. Every RCD mustbe tested frequently by the competentperson; v. Sockets mustonly be mounted on the exterior of the DB enclosure. Timber framed splitter units are not permitted; vi. All Steel Wired Armour cables musthave earthing bond cable connected from gland to earth bar within the DB; vii. SMDB’s and DB’s shall be subjectto regular inspections,anydamaged units removed from service; Rain entering DB’s; SMDB’s and DB’s damaged Remove from site Low 2 Temporaryelectrics - offices  Electrical connections and terminations  Use of untrained electricians for electrical works;  Use of substandard electrical fixtures and fittings;  Use of substandard connections;  Non-adherence to colour coding of wiring;  Incorrect earthing;  Tripping hazard; Damage to unprotected cables;  Use of incorrectly rated fuses; 4 3 12 High i. All electricians to be suitablytrained and experienced in the works; ii. All wiring,connections and terminations inspected prior to connection to live supply; iii. All wiring to follow colour coding standards; All fuses shall be to correct rating for electrical system or equipment; iv. All junction boxes and sockets fixed securelyto structure; All electrical junction boxes,sockets and fittings to be of suitable quality; v. Insulation tape shall not be used for cable connections,correctjunction boxes to be used; vi. All earth connections shall be to standards; vii. No cables shall trail on the floor; all securelyclipped clear of damage or posing a trip hazard; viii. Armoured cable used for cables setbelow ground; Armoured cable shall be correctly fitted and protected at junction boxes; All cables to be fed through securelyfixed conduit; Damaged cables Disconnectsupplyand rectify or remove. No taped connections Low Project Name: xxx RA Ref No.: xxx RA compilation Date: Review date: Date: Compiled by: Reviewed by: Approved by: Overall Task Details Temporaryelectrical installation to projects,including generators,DB’s and temporaryelectrical circuit installation.Use with RA 33 – Temporary Lighting Relevant Applicable MAS:  00237 – TemporaryElectrics; Additional Training required: NOC’s Required for task: RISK SCORE CALCULATOR Use the Risk Score Calculator to Determine the Level of Risk of each Hazard What would be the CONSEQUENCE of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls Frequent/Almost certain (5) Continuous or will happen frequently Often (4) 6 to 12 times a year Likely (3) 1 to 5 times a year Possible (2) Once every 5 years Rarely (1) Less than once every 5 years Can the hazard be Eliminated or removed from the w ork place? Catastrophic (5) Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substitutedfor a less hazardous alternative? Serious (4) Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered aw ay w ith guards or barriers? Moderate (3) Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted I.e. procedures, job rotation etc. Minor (2) Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be w orn to safe guard against hazards?Insignificant (1) FAI Medium10 Medium 4 Low 3 Low 2 Low 1
  • 2. HEALTH SAFETY AND ENVIRONMENT Author: Approved: RISK ASSESSMENT: ACT/HSE/RA 001 WORKPLACE TEMPORARY ELECTRICAL SUPPLY Issued: Rev. Date: Revision: 0 Page 2 of 2 HSEQ -Rev-01(Aug-2018) No Specific Task Step (In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR L C RR 3 Site generators – offices and site  Temporarysupply  Generator fires;  Incidentdue to incorrectearthing;  Fuel leakage – environmental risk;  Fuel storage;  Noise; 4 3 12 HIGH i. Generators to be suitable size and capacity for the task, with maintenance record; ii. Generators to have suitable earth rod connected at all time; iii. Fire extinguishers to be located close to generators; iv. Generators to be fitted with drip trays; v. Fuel tanks to be bunded to 110% capacity, bunds to be sealed with delivery hoses retained inside bund; vi. Generators to be subjectto regular inspection regime;Units monitored for excessive exhaustfumes; vii. Generators sited awayfrom combustible storage areas,offices and welfare areas due to risk of fire and noise; Fuel leaks Area bunded and spill area removed as hazardous waste Low