SlideShare a Scribd company logo
1 of 3
HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 HYDROSTATIC PRESSURE TESTING INSIDE BUILDINGS
Issued: Rev. Date:
Revision: 0
Page 1 of 3 HSEQ -Rev-01(Jan-2023)
No
Specific Task Step
(In sequence of
works)
Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
L C RR
1 Pressure testing
equipment
 Use at high
pressure;
 Rupture/failure of pump during
testing;
 Valve/connection failure;
 Instrument failure resulting in system
over-pressurization;
3 3
9
MED
i. The supervisor in charge of the test shall ensure that all pressure testing
gauges etc. are in good sound condition, undamaged, correctly dated with
the current valid calibration and that appropriate calibration certificates are
available;
ii. All pumps shall be in sound condition and complete with a valid test
certificate. Any vulnerable items such as manometers and pressure
switches shall be removed or isolated from the system prior to testing if
not required;
iii. The test supervisor shall carry out a thorough inspection of the system
before requesting the permit detailed above to ensure that all isolations,
blanks and other specified safety devices are in place before testing
commences;
No test
documentation
available
Quarantine equipment until
valid documentation provided
Low
2 Permit to work system
 Interaction of
personnel and high
pressure system;
 Injury due to uncontrolled testing;
 Injury due to failure to ensure
adequate pre-checks undertaken;
3 4
12
HIGH
i. All pressure testing operations shall require a Permit to Work to ensure
that no pressure testing will be allowed to commence until all, or
applicable, considerations have been considered;
ii. The Permit shall be completed and distributed at least 2 hours in advance
of the pressure test.
iii. The test area shall be physically walked by the Engineer with all required
checks completed. If any rectifications are required these must be
completed before the test is allowed to commence.
iv. The responsible Permit Holder shall also ensure that the safe work
practices permit and all other requirements outlined on the Work Permit
are strictly adhered to during the task being performed.
v. Hazardous work to be carried out under the Permit to Work must have risk
assessment / JSEA conducted prior to issue and shall be attached with
schematic drawing and the pre-inspection form (if required) to the PTW on
request. Any additional or specific control measures must also be
indicated in the Work Permit.
vi. The Work Permit shall also be available at the Work Area;
vii. Where practicable, implement a Lock out/Tag out procedure to ensure no
lines are pressurized or valves opened/closed until all safety procedures
are in place and relevant parties informed.
Permit not in area
Regular checks during test.
Briefed at TBT’s;
Low
Project Name: xxx
RA Ref No.: xxx
RA compilation
Date:
Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Hydrostatic pressure testing of pipework inside buildings
Relevant Applicable MAS:

Additional Training required: NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be?
What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen
frequently
Often (4)
6 to 12 times a year
Likely (3)
1 to 5 times a year
Possible (2)
Once every 5 years
Rarely (1)
Less than once every 5
years
Can the hazard be Eliminated or removed
from the work place?
Catastrophic (5)
Multiple Fatalities
High 25 High 20 High 15 Medium 10 Medium 5
Can the product or process be substituted for
a less hazardous alternative?
Serious (4)
Class 1 single fatality
High 20 High 16 High 12 Medium 8 Low 4
Can the hazard be engineered away with
guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1
Permanently disabling effects
High 15 High 12 Medium 9 Medium 6 Low 3
Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work
restrictions. MTI
Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment &
Clothing be worn to safe guard against
hazards?
Insignificant (1)
FAI
Medium10 Medium 4 Low 3 Low 2 Low 1
HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 HYDROSTATIC PRESSURE TESTING INSIDE BUILDINGS
Issued: Rev. Date:
Revision: 0
Page 2 of 3 HSEQ -Rev-01(Jan-2023)
No
Specific Task Step
(In sequence of
works)
Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
L C RR
3
Establishing exclusion
zones
 Personnel in area
 Unauthorized access to test area;
 Workers struck by flying materials;
 Worker struck by High pressure water
release;
3 4
12
HIGH
i. The establishment of an exclusion zone(s), (this zone shall be
dependent on the positioning, pressure, test zone and personnel in
adjacent area) from the pressure source, around the test area shall be
undertaken;
ii. Simple barrier tape is not an adequate control of any area where
personnel are present and shall only be used on doorways etc., if a
sentry is to be present at all times to control access;
iii. If practicable, the area may be securely closed off using plywood,
handrail or similar to prevent unauthorized access. The board/rails shall
be securely fixed with suitable signage attached;
iv. Any doors shall, if practicable, be locked with keys retained by the permit
holder;
v. In areas where other contractors are working or other exposed areas,
the use of sentries shall be considered to prevent access, however this
shall be determined by the locality and nature of the test. The sentries
shall be instructed as to emergency contact details etc. and shall remain
in position for the duration of the test;
vi. All flange and valve connections, blank ends or clip connections etc.
shall be zoned off as a matter of general good practice;
vii. All drain or vent points must be fitted with a blanking plug. Any other
areas shall be secured as applicable;
viii. Under no circumstances will any persons be allowed within safety
barriers during pressure testing.
Unable to secure
area during
normal working
hours
Test undertaken out of normal
work shift timings, weekends
etc.
Low
4 Signage to test area  Personnel in area
 Unauthorized access to test area;
 Inadequate signage to test area; 3 4
12
HIGH
i. The exclusion zone shall be clearly marked with suitable signage,
including ‘Warning – Pressure Test’, and emergency contact details;
ii. Signs will be of adequate size and in languages as applicable (minimum
English and Arabic) and shall include the test date;
iii. Simple paper signs are not to be used, as these can blow away or torn
off. Signs shall be fixed onto hard backing and secured to handrails etc.;
iv. On completion of the test all signage shall be removed to prevent
confusion.
Workers not
understanding
signage
Communicated at Induction Low
5 Pressure testing
 High pressure to
pipework;
 Uncontrolled Stored Energy release;
 Rupture/failure in Pipe lines during
testing;
 Valve/connection failure;
 Instrument failure resulting in system
over-pressurization;
 End caps/plugs ejecting under high
pressure;
 Weld/seal/fitting failure, flying objects;
 High pressure water/air injection.
3 4
12
HIGH
i. The initial pressurizing of a system has the potentially highest risk of
failure and sudden release of pressure, possibly resulting in serious
injury;
ii. High pressure testing on systems shall be reached in clearly defined and
controlled stages;
iii. If required as part of the design, on completion of each stage and after a
period of stabilization an inspection of the test area shall be completed
by the responsible person and his team, checking for leaks etc.;
iv. All pressure test details shall be recorded throughout the entire test
schedule;
v. The personnel carrying out the test must be provided with a safe place
from which the progress of the test can be observed and controlled;
Low
6 Emergency procedures  High pressure to
pipework;
 Emergency procedures not briefed
to task workers;
 Poor response in the event of an
emergency;
3 4
12
HIGH
Emergency procedures shall be developed for the pressure test, to be
specific to the area/zone. These shall include:
i. Emergency Contact details;
ii. Persons responsible for shutting down the system;
iii. Actions to be taken in an emergency, escape routes;
iv. Means of communication between parties;
v. First aid response;
Low
HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 HYDROSTATIC PRESSURE TESTING INSIDE BUILDINGS
Issued: Rev. Date:
Revision: 0
Page 3 of 3 HSEQ -Rev-01(Jan-2023)
No
Specific Task Step
(In sequence of
works)
Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
L C RR
These will communicated to all personnel involved in the tests.
7
Re-testing in the event
of failure
 Re-testing with high
pressure
 Injury due to uncontrolled testing;
 Worker injury due to working on
pressurized system;
 Injury due to failure to ensure
adequate pre-checks undertaken;
3 4
12
HIGH
i. If on pressurization any leaks are found in the system, the system shall
be depressurized and leaks repaired as required.
ii. Under no circumstances will personnel work on any pressurized systems
unless the leaking section can be successfully isolated by valves and
can be depressurized safely;
iii. A valve lock out/tag out system shall be adopted in these circumstances
on the closed valves to prevent unauthorized opening;
iv. No unauthorized personnel will be allowed in any test area until
depressurization is complete. Only when leaks have been repaired and
control checks undertaken will the system be re-pressurized following
the same procedure as previous;
v. After full pressure has been achieved another inspection is to be
completed;
vi. If the leak was due to a weld failure or a fixing/valve failure then the
causation must be determined and other welds/fixings/valves with
possible similar defects investigated before a retest is undertaken;
Low

More Related Content

What's hot

31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...Dwarika Bhushan Sharma
 
15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templates6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
20 use of suspended access cradles and platforms (temporary works) risk asses...
20 use of suspended access cradles and platforms (temporary works) risk asses...20 use of suspended access cradles and platforms (temporary works) risk asses...
20 use of suspended access cradles and platforms (temporary works) risk asses...Dwarika Bhushan Sharma
 
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templatesDwarika Bhushan Sharma
 
21 confined space working risk assessment templates
21 confined space working risk assessment templates21 confined space working risk assessment templates
21 confined space working risk assessment templatesDwarika Bhushan Sharma
 
MOBILE ELEVATED WORK PLATFORMS CHECKLIST Form # HSEQ - MEWP Rev 1 - M.docx
MOBILE ELEVATED WORK PLATFORMS CHECKLIST Form # HSEQ - MEWP Rev 1 - M.docxMOBILE ELEVATED WORK PLATFORMS CHECKLIST Form # HSEQ - MEWP Rev 1 - M.docx
MOBILE ELEVATED WORK PLATFORMS CHECKLIST Form # HSEQ - MEWP Rev 1 - M.docxDwarika Bhushan Sharma
 
Hot Work / Welding Fires Training by DBMP
Hot Work / Welding Fires Training by DBMPHot Work / Welding Fires Training by DBMP
Hot Work / Welding Fires Training by DBMPAtlantic Training, LLC.
 
5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
RA- Pressure Testing Of Pipe Works
RA- Pressure Testing Of Pipe WorksRA- Pressure Testing Of Pipe Works
RA- Pressure Testing Of Pipe WorksSajid Ali
 
26 storage of substances under co shh risk assessment templates
26 storage of substances under co shh risk assessment templates26 storage of substances under co shh risk assessment templates
26 storage of substances under co shh risk assessment templatesDwarika Bhushan Sharma
 
18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templates18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templatesDwarika Bhushan Sharma
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templatesDwarika Bhushan Sharma
 
Permit to work system
Permit to work systemPermit to work system
Permit to work systemAsif Khan
 
7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
Work permit system
Work permit systemWork permit system
Work permit systemsmithgeigle
 

What's hot (20)

31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...31 ndrc operations within excavations (temporary works) risk assessment templ...
31 ndrc operations within excavations (temporary works) risk assessment templ...
 
15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates15 formwork (temporary works) risk assessment templates
15 formwork (temporary works) risk assessment templates
 
6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templates6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templates
 
20 use of suspended access cradles and platforms (temporary works) risk asses...
20 use of suspended access cradles and platforms (temporary works) risk asses...20 use of suspended access cradles and platforms (temporary works) risk asses...
20 use of suspended access cradles and platforms (temporary works) risk asses...
 
Excavation
ExcavationExcavation
Excavation
 
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
 
Safety induction-june-11
Safety induction-june-11Safety induction-june-11
Safety induction-june-11
 
9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates
 
21 confined space working risk assessment templates
21 confined space working risk assessment templates21 confined space working risk assessment templates
21 confined space working risk assessment templates
 
MOBILE ELEVATED WORK PLATFORMS CHECKLIST Form # HSEQ - MEWP Rev 1 - M.docx
MOBILE ELEVATED WORK PLATFORMS CHECKLIST Form # HSEQ - MEWP Rev 1 - M.docxMOBILE ELEVATED WORK PLATFORMS CHECKLIST Form # HSEQ - MEWP Rev 1 - M.docx
MOBILE ELEVATED WORK PLATFORMS CHECKLIST Form # HSEQ - MEWP Rev 1 - M.docx
 
Hot Work / Welding Fires Training by DBMP
Hot Work / Welding Fires Training by DBMPHot Work / Welding Fires Training by DBMP
Hot Work / Welding Fires Training by DBMP
 
5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates
 
RA- Pressure Testing Of Pipe Works
RA- Pressure Testing Of Pipe WorksRA- Pressure Testing Of Pipe Works
RA- Pressure Testing Of Pipe Works
 
26 storage of substances under co shh risk assessment templates
26 storage of substances under co shh risk assessment templates26 storage of substances under co shh risk assessment templates
26 storage of substances under co shh risk assessment templates
 
18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templates18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templates
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates
 
Permit to work system
Permit to work systemPermit to work system
Permit to work system
 
Excavation safety
Excavation safetyExcavation safety
Excavation safety
 
7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates
 
Work permit system
Work permit systemWork permit system
Work permit system
 

Similar to 27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx

Generic Hydrotest.doc
Generic Hydrotest.docGeneric Hydrotest.doc
Generic Hydrotest.docamrilalriza
 
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...Dwarika Bhushan Sharma
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
13VesselEntry ppt use in confined space entry
13VesselEntry ppt use in confined space entry13VesselEntry ppt use in confined space entry
13VesselEntry ppt use in confined space entrySumairaKhan268832
 
15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docxDwarika Bhushan Sharma
 
25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templatesDwarika Bhushan Sharma
 
21 Confined Space Working Risk Assessment Templates.docx
21 Confined Space Working Risk Assessment Templates.docx21 Confined Space Working Risk Assessment Templates.docx
21 Confined Space Working Risk Assessment Templates.docxDwarika Bhushan Sharma
 
22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docxDwarika Bhushan Sharma
 
23.plumbing method statement_gn23
23.plumbing method statement_gn2323.plumbing method statement_gn23
23.plumbing method statement_gn23bhattbhai
 
Ma 023 change out butter fly valve for bulk system
Ma 023  change out butter fly valve for bulk systemMa 023  change out butter fly valve for bulk system
Ma 023 change out butter fly valve for bulk systemYousif Fikry
 
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docxDwarika Bhushan Sharma
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templatesDwarika Bhushan Sharma
 
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdfFESTUS RICHARD SIAME
 
AIGA TP 06_06 Work Permit System_reformated Jan 12.ppt
AIGA TP 06_06 Work Permit System_reformated Jan 12.pptAIGA TP 06_06 Work Permit System_reformated Jan 12.ppt
AIGA TP 06_06 Work Permit System_reformated Jan 12.pptAhmadNadzir4
 
Hazard Identification & Control
Hazard Identification & ControlHazard Identification & Control
Hazard Identification & ControlHasnizam Md Saad
 
23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docxDwarika Bhushan Sharma
 
Safe Works In Confined Spaces
Safe Works In Confined SpacesSafe Works In Confined Spaces
Safe Works In Confined SpacesOGDoilandgasdocs
 
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docxDwarika Bhushan Sharma
 

Similar to 27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx (20)

Generic Hydrotest.doc
Generic Hydrotest.docGeneric Hydrotest.doc
Generic Hydrotest.doc
 
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Asses...
 
Pressure testing
Pressure testingPressure testing
Pressure testing
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
 
13VesselEntry ppt use in confined space entry
13VesselEntry ppt use in confined space entry13VesselEntry ppt use in confined space entry
13VesselEntry ppt use in confined space entry
 
15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx15 Formwork (Temporary Works) Risk Assessment Templates.docx
15 Formwork (Temporary Works) Risk Assessment Templates.docx
 
7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx
 
25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates25 demolition of existing concrete structures risk assessment templates
25 demolition of existing concrete structures risk assessment templates
 
21 Confined Space Working Risk Assessment Templates.docx
21 Confined Space Working Risk Assessment Templates.docx21 Confined Space Working Risk Assessment Templates.docx
21 Confined Space Working Risk Assessment Templates.docx
 
22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx
 
23.plumbing method statement_gn23
23.plumbing method statement_gn2323.plumbing method statement_gn23
23.plumbing method statement_gn23
 
Ma 023 change out butter fly valve for bulk system
Ma 023  change out butter fly valve for bulk systemMa 023  change out butter fly valve for bulk system
Ma 023 change out butter fly valve for bulk system
 
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx
19 Use of Mobile Elevated Work Platforms Risk Assessment Templates.docx
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates
 
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
 
AIGA TP 06_06 Work Permit System_reformated Jan 12.ppt
AIGA TP 06_06 Work Permit System_reformated Jan 12.pptAIGA TP 06_06 Work Permit System_reformated Jan 12.ppt
AIGA TP 06_06 Work Permit System_reformated Jan 12.ppt
 
Hazard Identification & Control
Hazard Identification & ControlHazard Identification & Control
Hazard Identification & Control
 
23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx
 
Safe Works In Confined Spaces
Safe Works In Confined SpacesSafe Works In Confined Spaces
Safe Works In Confined Spaces
 
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
 

More from Dwarika Bhushan Sharma

4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdfDwarika Bhushan Sharma
 
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdfDwarika Bhushan Sharma
 
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdfDwarika Bhushan Sharma
 
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdfDwarika Bhushan Sharma
 
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docxDwarika Bhushan Sharma
 
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docxFIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docxDwarika Bhushan Sharma
 
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxSUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxDwarika Bhushan Sharma
 
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxSTORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxDwarika Bhushan Sharma
 
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxPROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxDwarika Bhushan Sharma
 
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docxHSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docxDwarika Bhushan Sharma
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxDwarika Bhushan Sharma
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxDwarika Bhushan Sharma
 
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxMOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxDwarika Bhushan Sharma
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxDwarika Bhushan Sharma
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docxDwarika Bhushan Sharma
 
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docHSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docDwarika Bhushan Sharma
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docDwarika Bhushan Sharma
 
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxOFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxDwarika Bhushan Sharma
 

More from Dwarika Bhushan Sharma (20)

4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
 
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
 
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
 
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
 
1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf
 
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
 
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docxFIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
 
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxSUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
 
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxSTORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
 
WITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docxWITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docx
 
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxPROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
 
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docxHSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
 
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxMOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
 
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docHSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
 
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxOFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
 

Recently uploaded

Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 

Recently uploaded (20)

Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 

27 Hydrostatic Pressure Testing inside buildings Risk Assessment Templates.docx

  • 1. HEALTH SAFETY AND ENVIRONMENT Author: Approved: RISK ASSESSMENT: ACT/HSE/RA 001 HYDROSTATIC PRESSURE TESTING INSIDE BUILDINGS Issued: Rev. Date: Revision: 0 Page 1 of 3 HSEQ -Rev-01(Jan-2023) No Specific Task Step (In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR L C RR 1 Pressure testing equipment  Use at high pressure;  Rupture/failure of pump during testing;  Valve/connection failure;  Instrument failure resulting in system over-pressurization; 3 3 9 MED i. The supervisor in charge of the test shall ensure that all pressure testing gauges etc. are in good sound condition, undamaged, correctly dated with the current valid calibration and that appropriate calibration certificates are available; ii. All pumps shall be in sound condition and complete with a valid test certificate. Any vulnerable items such as manometers and pressure switches shall be removed or isolated from the system prior to testing if not required; iii. The test supervisor shall carry out a thorough inspection of the system before requesting the permit detailed above to ensure that all isolations, blanks and other specified safety devices are in place before testing commences; No test documentation available Quarantine equipment until valid documentation provided Low 2 Permit to work system  Interaction of personnel and high pressure system;  Injury due to uncontrolled testing;  Injury due to failure to ensure adequate pre-checks undertaken; 3 4 12 HIGH i. All pressure testing operations shall require a Permit to Work to ensure that no pressure testing will be allowed to commence until all, or applicable, considerations have been considered; ii. The Permit shall be completed and distributed at least 2 hours in advance of the pressure test. iii. The test area shall be physically walked by the Engineer with all required checks completed. If any rectifications are required these must be completed before the test is allowed to commence. iv. The responsible Permit Holder shall also ensure that the safe work practices permit and all other requirements outlined on the Work Permit are strictly adhered to during the task being performed. v. Hazardous work to be carried out under the Permit to Work must have risk assessment / JSEA conducted prior to issue and shall be attached with schematic drawing and the pre-inspection form (if required) to the PTW on request. Any additional or specific control measures must also be indicated in the Work Permit. vi. The Work Permit shall also be available at the Work Area; vii. Where practicable, implement a Lock out/Tag out procedure to ensure no lines are pressurized or valves opened/closed until all safety procedures are in place and relevant parties informed. Permit not in area Regular checks during test. Briefed at TBT’s; Low Project Name: xxx RA Ref No.: xxx RA compilation Date: Review date: Date: Compiled by: Reviewed by: Approved by: Overall Task Details Hydrostatic pressure testing of pipework inside buildings Relevant Applicable MAS:  Additional Training required: NOC’s Required for task: RISK SCORE CALCULATOR Use the Risk Score Calculator to Determine the Level of Risk of each Hazard What would be the CONSEQUENCE of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls Frequent/Almost certain (5) Continuous or will happen frequently Often (4) 6 to 12 times a year Likely (3) 1 to 5 times a year Possible (2) Once every 5 years Rarely (1) Less than once every 5 years Can the hazard be Eliminated or removed from the work place? Catastrophic (5) Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative? Serious (4) Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers? Moderate (3) Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted I.e. procedures, job rotation etc. Minor (2) Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards? Insignificant (1) FAI Medium10 Medium 4 Low 3 Low 2 Low 1
  • 2. HEALTH SAFETY AND ENVIRONMENT Author: Approved: RISK ASSESSMENT: ACT/HSE/RA 001 HYDROSTATIC PRESSURE TESTING INSIDE BUILDINGS Issued: Rev. Date: Revision: 0 Page 2 of 3 HSEQ -Rev-01(Jan-2023) No Specific Task Step (In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR L C RR 3 Establishing exclusion zones  Personnel in area  Unauthorized access to test area;  Workers struck by flying materials;  Worker struck by High pressure water release; 3 4 12 HIGH i. The establishment of an exclusion zone(s), (this zone shall be dependent on the positioning, pressure, test zone and personnel in adjacent area) from the pressure source, around the test area shall be undertaken; ii. Simple barrier tape is not an adequate control of any area where personnel are present and shall only be used on doorways etc., if a sentry is to be present at all times to control access; iii. If practicable, the area may be securely closed off using plywood, handrail or similar to prevent unauthorized access. The board/rails shall be securely fixed with suitable signage attached; iv. Any doors shall, if practicable, be locked with keys retained by the permit holder; v. In areas where other contractors are working or other exposed areas, the use of sentries shall be considered to prevent access, however this shall be determined by the locality and nature of the test. The sentries shall be instructed as to emergency contact details etc. and shall remain in position for the duration of the test; vi. All flange and valve connections, blank ends or clip connections etc. shall be zoned off as a matter of general good practice; vii. All drain or vent points must be fitted with a blanking plug. Any other areas shall be secured as applicable; viii. Under no circumstances will any persons be allowed within safety barriers during pressure testing. Unable to secure area during normal working hours Test undertaken out of normal work shift timings, weekends etc. Low 4 Signage to test area  Personnel in area  Unauthorized access to test area;  Inadequate signage to test area; 3 4 12 HIGH i. The exclusion zone shall be clearly marked with suitable signage, including ‘Warning – Pressure Test’, and emergency contact details; ii. Signs will be of adequate size and in languages as applicable (minimum English and Arabic) and shall include the test date; iii. Simple paper signs are not to be used, as these can blow away or torn off. Signs shall be fixed onto hard backing and secured to handrails etc.; iv. On completion of the test all signage shall be removed to prevent confusion. Workers not understanding signage Communicated at Induction Low 5 Pressure testing  High pressure to pipework;  Uncontrolled Stored Energy release;  Rupture/failure in Pipe lines during testing;  Valve/connection failure;  Instrument failure resulting in system over-pressurization;  End caps/plugs ejecting under high pressure;  Weld/seal/fitting failure, flying objects;  High pressure water/air injection. 3 4 12 HIGH i. The initial pressurizing of a system has the potentially highest risk of failure and sudden release of pressure, possibly resulting in serious injury; ii. High pressure testing on systems shall be reached in clearly defined and controlled stages; iii. If required as part of the design, on completion of each stage and after a period of stabilization an inspection of the test area shall be completed by the responsible person and his team, checking for leaks etc.; iv. All pressure test details shall be recorded throughout the entire test schedule; v. The personnel carrying out the test must be provided with a safe place from which the progress of the test can be observed and controlled; Low 6 Emergency procedures  High pressure to pipework;  Emergency procedures not briefed to task workers;  Poor response in the event of an emergency; 3 4 12 HIGH Emergency procedures shall be developed for the pressure test, to be specific to the area/zone. These shall include: i. Emergency Contact details; ii. Persons responsible for shutting down the system; iii. Actions to be taken in an emergency, escape routes; iv. Means of communication between parties; v. First aid response; Low
  • 3. HEALTH SAFETY AND ENVIRONMENT Author: Approved: RISK ASSESSMENT: ACT/HSE/RA 001 HYDROSTATIC PRESSURE TESTING INSIDE BUILDINGS Issued: Rev. Date: Revision: 0 Page 3 of 3 HSEQ -Rev-01(Jan-2023) No Specific Task Step (In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR L C RR These will communicated to all personnel involved in the tests. 7 Re-testing in the event of failure  Re-testing with high pressure  Injury due to uncontrolled testing;  Worker injury due to working on pressurized system;  Injury due to failure to ensure adequate pre-checks undertaken; 3 4 12 HIGH i. If on pressurization any leaks are found in the system, the system shall be depressurized and leaks repaired as required. ii. Under no circumstances will personnel work on any pressurized systems unless the leaking section can be successfully isolated by valves and can be depressurized safely; iii. A valve lock out/tag out system shall be adopted in these circumstances on the closed valves to prevent unauthorized opening; iv. No unauthorized personnel will be allowed in any test area until depressurization is complete. Only when leaks have been repaired and control checks undertaken will the system be re-pressurized following the same procedure as previous; v. After full pressure has been achieved another inspection is to be completed; vi. If the leak was due to a weld failure or a fixing/valve failure then the causation must be determined and other welds/fixings/valves with possible similar defects investigated before a retest is undertaken; Low