HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 USE OF SUSPENDED ACCESS CRADLES AND PLATFORMS (TEMPORARY WORKS)
Issued: Rev. Date:
Revision: 0
Page 1 of 2 HSEQ -Rev-01(Jan-2023)
No
Specific Task Step
(In sequence of
works)
Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
P S RR
1
Cradle checks on
arrival to site
PRIOR TO USE
 Use of Access
equipment
 Failure due to use of un-certificated
plant; 3 4
12
HIGH
i. All plant to be Third Party Certificated by a DM approved inspector,
documentation available on arrival to site (6 monthly check);
ii. Visual inspection of MEWP undertaken by competent person;
Documentation
unavailable for
review
Plant quarantined until
evidence provided
Low
2
Pre-use checks of
suspended access
cradle or platform
 Work at Height;
 Collapse of cradle through damage
or failure of equipment;
 Falling materials; 4 5
20
HIGH
i. Method statements and risk assessments to be submitted and adhered to;
ii. The safe working load must be clearly marked on the cradle and shall not
be exceeded;
iii. It is erected and installed by a competent person, following the
manufacturer’s instructions;
iv. An independent life line rope/wire and rope grabbing device installed;
v. All safety devices and controls are operating correctly;
vi. There are no visible signs of damage to the cradle and corresponding
supports, tracks/runways;
vii. The ropes are free from damage and are correctly weaved through the
drum and pulleys;
viii.Floors and guard rails are rigid and free from defects;
ix. All landing wheels must be attached and intact;
x. All Cradles are to be fitted with a fit for purpose fire extinguisher;
Damage
discovered
Machine isolated and
quarantined until repaired.
Low
5 Cradle operation ;
 Work at Height;
 Fall from height;
 Material fall from height;
 Machine malfunction at height;
 Workers trapped at height;
3 5
15
High
i. Supervision to ensure visual inspection of all plant and equipment daily;
ii. Cradles can only be entered/exited from ground floor or purpose built
landing platforms;
iii. Climbing outside the Cradle is strictly prohibited;
iv. Supervision to control workers in working area drop zone;
v. A high level of housekeeping must be maintained at all times. All
materials, equipment, tools, rubbish, etc. to be removed at the end of
shift;
vi. Cradle to be shut down and locked out at the end of shift or at any time
that the cradle is not in use (break times, collecting materials/equipment);
vii. All person/s operating in Cradles must be trained in the use of the
emergency lowering device;
viii. If malfunction occurs, work is stopped immediately and the malfunction
reported;
ix. An appropriate rescue from heights plan must be in place;
Machine
breakdown
Machine isolated and
quarantined until repaired.
Low
Project Name: xxx
RA Ref No.: xxx
RA compilation
Date:
Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Use of Suspended access cradles and platforms
Relevant Applicable MAS:
 0242 – Suspended access cradles and platforms
Additional Training required: NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be?
What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen
frequently
Often (4)
6 to 12 times a year
Likely (3)
1 to 5 times a year
Possible (2)
Once every 5 years
Rarely (1)
Less than once every 5
years
Can the hazard be Eliminated or removed
from the work place?
Catastrophic (5)
Multiple Fatalities
High 25 High 20 High 15 Medium 10 Medium 5
Can the product or process be substituted for
a less hazardous alternative?
Serious (4)
Class 1 single fatality
High 20 High 16 High 12 Medium 8 Low 4
Can the hazard be engineered away with
guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1
Permanently disabling effects
High 15 High 12 Medium 9 Medium 6 Low 3
Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work
restrictions. MTI
Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment &
Clothing be worn to safe guard against
hazards?
Insignificant (1)
FAI
Medium10 Medium 4 Low 3 Low 2 Low 1
HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 USE OF SUSPENDED ACCESS CRADLES AND PLATFORMS (TEMPORARY WORKS)
Issued: Rev. Date:
Revision: 0
Page 2 of 2 HSEQ -Rev-01(Jan-2023)
No
Specific Task Step
(In sequence of
works)
Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
P S RR
x. When weather conditions deteriorate, wind, rain etc. worked is stopped
immediately;
xi. Access to the area below where Cradles are working must be properly
barricaded and sign posted to prevent entry of unauthorized personnel;
xii. All person/s in the Cradle must wear a harness, with the lanyard
attached to the independent safety line at all times;
xiii. The equipment shall only be altered or dismantled by a competent
person. Every time the equipment is altered/dismantled/relocated it must
be 3rd party certified;
xiv. The safe working load is not exceeded;
xv. Tools and equipment are secured appropriately. Tool lanyards must be
utilized;

More Related Content

Similar to 20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Assessment Templates.docx

12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
10 Use of Mobile Concrete Pump Risk Assessment Templates.docx
10 Use of Mobile Concrete Pump Risk Assessment Templates.docx10 Use of Mobile Concrete Pump Risk Assessment Templates.docx
10 Use of Mobile Concrete Pump Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 

Similar to 20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Assessment Templates.docx (20)

12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
 
14 use of plant graders and road rollers risk assessment templates
14 use of plant  graders and road rollers risk assessment templates14 use of plant  graders and road rollers risk assessment templates
14 use of plant graders and road rollers risk assessment templates
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates
 
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
14 Use of Plant- Graders and road rollers Risk Assessment Templates.docx
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates
 
7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates
 
7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx7 Falsework (Temporary Works) Risk Assessment Templates.docx
7 Falsework (Temporary Works) Risk Assessment Templates.docx
 
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx
 
22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx22 Casting of concrete columns Risk Assessment Templates.docx
22 Casting of concrete columns Risk Assessment Templates.docx
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates
 
22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templates22 casting of concrete columns risk assessment templates
22 casting of concrete columns risk assessment templates
 
10 Use of Mobile Concrete Pump Risk Assessment Templates.docx
10 Use of Mobile Concrete Pump Risk Assessment Templates.docx10 Use of Mobile Concrete Pump Risk Assessment Templates.docx
10 Use of Mobile Concrete Pump Risk Assessment Templates.docx
 
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates
 
23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx23 Casting of concrete slabs Risk Assessment Templates.docx
23 Casting of concrete slabs Risk Assessment Templates.docx
 
5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates5 trial trenches (temporary works) risk assessment templates
5 trial trenches (temporary works) risk assessment templates
 
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
5 Trial Trenches (Temporary Works) Risk Assessment Templates.docx
 

More from Dwarika Bhushan Sharma

PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
Dwarika Bhushan Sharma
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
Dwarika Bhushan Sharma
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
Dwarika Bhushan Sharma
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
Dwarika Bhushan Sharma
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
Dwarika Bhushan Sharma
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
Dwarika Bhushan Sharma
 

More from Dwarika Bhushan Sharma (20)

4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
 
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
 
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
 
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
 
1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf
 
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
 
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docxFIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
 
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxSUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
 
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxSTORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
 
WITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docxWITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docx
 
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxPROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
 
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docxHSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
 
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxMOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
 
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docHSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
 
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxOFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
 

Recently uploaded

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Christo Ananth
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
Tonystark477637
 

Recently uploaded (20)

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 

20 Use of Suspended Access cradles and Platforms (Temporary Works) Risk Assessment Templates.docx

  • 1. HEALTH SAFETY AND ENVIRONMENT Author: Approved: RISK ASSESSMENT: ACT/HSE/RA 001 USE OF SUSPENDED ACCESS CRADLES AND PLATFORMS (TEMPORARY WORKS) Issued: Rev. Date: Revision: 0 Page 1 of 2 HSEQ -Rev-01(Jan-2023) No Specific Task Step (In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR P S RR 1 Cradle checks on arrival to site PRIOR TO USE  Use of Access equipment  Failure due to use of un-certificated plant; 3 4 12 HIGH i. All plant to be Third Party Certificated by a DM approved inspector, documentation available on arrival to site (6 monthly check); ii. Visual inspection of MEWP undertaken by competent person; Documentation unavailable for review Plant quarantined until evidence provided Low 2 Pre-use checks of suspended access cradle or platform  Work at Height;  Collapse of cradle through damage or failure of equipment;  Falling materials; 4 5 20 HIGH i. Method statements and risk assessments to be submitted and adhered to; ii. The safe working load must be clearly marked on the cradle and shall not be exceeded; iii. It is erected and installed by a competent person, following the manufacturer’s instructions; iv. An independent life line rope/wire and rope grabbing device installed; v. All safety devices and controls are operating correctly; vi. There are no visible signs of damage to the cradle and corresponding supports, tracks/runways; vii. The ropes are free from damage and are correctly weaved through the drum and pulleys; viii.Floors and guard rails are rigid and free from defects; ix. All landing wheels must be attached and intact; x. All Cradles are to be fitted with a fit for purpose fire extinguisher; Damage discovered Machine isolated and quarantined until repaired. Low 5 Cradle operation ;  Work at Height;  Fall from height;  Material fall from height;  Machine malfunction at height;  Workers trapped at height; 3 5 15 High i. Supervision to ensure visual inspection of all plant and equipment daily; ii. Cradles can only be entered/exited from ground floor or purpose built landing platforms; iii. Climbing outside the Cradle is strictly prohibited; iv. Supervision to control workers in working area drop zone; v. A high level of housekeeping must be maintained at all times. All materials, equipment, tools, rubbish, etc. to be removed at the end of shift; vi. Cradle to be shut down and locked out at the end of shift or at any time that the cradle is not in use (break times, collecting materials/equipment); vii. All person/s operating in Cradles must be trained in the use of the emergency lowering device; viii. If malfunction occurs, work is stopped immediately and the malfunction reported; ix. An appropriate rescue from heights plan must be in place; Machine breakdown Machine isolated and quarantined until repaired. Low Project Name: xxx RA Ref No.: xxx RA compilation Date: Review date: Date: Compiled by: Reviewed by: Approved by: Overall Task Details Use of Suspended access cradles and platforms Relevant Applicable MAS:  0242 – Suspended access cradles and platforms Additional Training required: NOC’s Required for task: RISK SCORE CALCULATOR Use the Risk Score Calculator to Determine the Level of Risk of each Hazard What would be the CONSEQUENCE of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls Frequent/Almost certain (5) Continuous or will happen frequently Often (4) 6 to 12 times a year Likely (3) 1 to 5 times a year Possible (2) Once every 5 years Rarely (1) Less than once every 5 years Can the hazard be Eliminated or removed from the work place? Catastrophic (5) Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative? Serious (4) Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers? Moderate (3) Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted I.e. procedures, job rotation etc. Minor (2) Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards? Insignificant (1) FAI Medium10 Medium 4 Low 3 Low 2 Low 1
  • 2. HEALTH SAFETY AND ENVIRONMENT Author: Approved: RISK ASSESSMENT: ACT/HSE/RA 001 USE OF SUSPENDED ACCESS CRADLES AND PLATFORMS (TEMPORARY WORKS) Issued: Rev. Date: Revision: 0 Page 2 of 2 HSEQ -Rev-01(Jan-2023) No Specific Task Step (In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR P S RR x. When weather conditions deteriorate, wind, rain etc. worked is stopped immediately; xi. Access to the area below where Cradles are working must be properly barricaded and sign posted to prevent entry of unauthorized personnel; xii. All person/s in the Cradle must wear a harness, with the lanyard attached to the independent safety line at all times; xiii. The equipment shall only be altered or dismantled by a competent person. Every time the equipment is altered/dismantled/relocated it must be 3rd party certified; xiv. The safe working load is not exceeded; xv. Tools and equipment are secured appropriately. Tool lanyards must be utilized;