2. Whole-life costing and cost management
īThis allows the integrated project
team to propose ways of meeting these
requirements in the most cost-
effective way.
īBy using value management and
engineering techniques approach.
īAlso, to suggest innovative solutions.
3. Whole-life costing and cost management
Determine the baseline against which to
measure the actual performance achieved.
īSet the cost baseline.
ītotal investment needed to complete a
facility.
īsuch as the cost of design.
īconstruction cost.
īland cost estimated.
īrunning cost of the completed facility over
its operational life.
4. Whole-life costing and cost management
īNote that the initial budget estimate and all
subsequent budget estimates should allow for all
costs in connection:
īwith the project in-house costs;
īconsultancy costs;
īland costs;
īlegal costs;
īoperation and maintenance costs;
īdesign and construction costs;
īconcession payments and decommissioning costs;
īIt should also include a risk allowance and
provision for VAT.
5. Whole-life costing and cost management
Benchmark the baseline
īCompare capital and predicted whole-
life costs with the benchmark cost.
īFor a similar facility procured in the
same way (such as Design & Build).
īcalculate the benchmark costs.
6. Whole-life costing and cost management
īRecord data for future benchmarking.
īThis is often difficult in practice as there
may be little available data on actual costs
as opposed to prices of resources.
īThere may also be limited reliable
information about maintenance and energy
costs.
7. Whole-life costing and cost management
īAim for the integrated project team to
deliver better value rather than lower
margins.
īSeek opportunities to further reduce
predicted whole-life costs.
īThis should be achieved without reducing
quality or value by using value engineering
during the design process.
8. Whole-life costing and cost management
īConsider the scope for allowing
higher capital costs to reduce running
costs.
īFor example, investment in more
efficient heating systems.
9. Whole-life costing and cost management
īconsider the scope for sharing any further savings
made during the construction of the facility.
īThe value engineering process works by enhancing
whole-life value.
īIt is not by squeezing profit margins or initial
construction costs.
īEstimating whole-life costs
īAssess the value to the business operations
īCan the cost be justified?
10. Whole-life costing and cost management
īProduce an output-based specification
īConsider the elements that make up whole-life
costs.
īPlanning costs.
īConsultancy fees.
īThe total costs of all consultancy fees incurred for
the project at any stage from inception to disposal
should be included in the model.
11. Whole-life costing and cost management
īConsultancy fees might be incurred
through any of the following:
īprocurement advice and development of
client brief;
īlegal advice;
īfees linked to purchase of site/assets;
īcost consultancy;
īchange management.
12. Whole-life costing and cost management
īFinancing;
īDesign;
īvalue management and risk management;
īproject management;
īeconomic appraisal;
īplanning supervisor role;
īadvice on technical issues.
13. Whole-life costing and cost management
īConstruction costs;
īHealth and safety;
īSecurity;
īOperations;
īCleaning;
14. Whole-life costing and cost management
īMaintenance;
īUtilities;
īAlterations;
īDisposal;
īCarry out a risk analysis.
15. Whole-life costing and cost management
Construction cost elements
īThe construction cost of a project is made
up of many elements, which include:
īin-house costs and expenses (including all
central support services, administration,
overheads, etc);
īconsultancy fees and expenses (such as
financial, technical, legal advice).
16. Whole-life costing and cost management
īland costs;
īway leaves and compensation;
īdemolition and diversion of existing
facilities;
īnew construction or refurbishment
costs;
īInsurance.
17. Whole-life costing and cost management
Cost management
īCost management and reporting;
īoverview Management of the overall cost of the
project is the responsibility of the project manager;
īBy reporting to the project sponsor;
ī Delegations and limits of authority for these two
roles should be agreed at the start of the project;
īSo that everyone knows exactly what they are
empowered to do in managing project costs.
18. Whole-life costing and cost management
The main tasks are:
īto manage the base estimate and risk
allowance;
īto operate change control procedures;
īto produce cost reports, estimates and
forecasts.
19. Whole-life costing and cost management
The project manager is directly
responsible for:
īunderstanding and reporting the cost
consequences of any decisions and for
initiating corrective actions if necessary;
īto maintain an up-to-date estimated
outturn cost and cash flow;
20. Whole-life costing and cost management
īto manage expenditure of the risk
allowance;
īto initiate action to avoid overspend;
īto issue a monthly financial status
report;
īThe objectives of cost management
during construction include:
21. Whole-life costing and cost management
īdelivering the project at the appropriate
capital cost (having considered the
implications of quality;
īprogramme and whole-life objectives;
īusing the value criteria established at the
start of the project);
īensuring that throughout the project, full
and proper accounts are monitored of all
transactions, payments and changes.
22. Whole-life costing and cost management
The principal areas of cost management
are:
īscope â defining what is to be included in
the project and limiting expenditure
accordingly;
īprogramme â defining the project
programme from inception to completion;
īEstimates and cash flow should be
consistent with the programme.
23. Whole-life costing and cost management
Design
īensuring that designs meet the scope
and budget;
īdelivering quality that is appropriate
and conforms to the brief;
īcommitments â ensuring that orders
are properly authorised;
īcontracts and materials;
24. Whole-life costing and cost management
īensuring that the contracts provide full
and proper control;
īall costs are incurred as authorised;
īensuring that materials are properly
specified (in output terms);
īso as to meet the scope and design and
that they can be procured effectively.
25. Whole-life costing and cost management
risk allowance
īensuring all expenditure relating to
risks is appropriately allocated from the
risk allowance;
īmake sure is properly authorised;
īand monitoring use of risk allowance
to assess impact on overall outturn
cost.
26. Whole-life costing and cost management
Cashflow
īplanning and controlling both
commitments and expenditure within
budgets so that unexpected cost over/under
runs do not result;
īensuring that all transactions are properly
recorded and authorised;
īwhere appropriate, decisions are justified.
27. Whole-life costing and cost management
Financial reviews at key decision
points
īThere should be a financial review at
each Gate and other major decision
points.
īThe Gateway process is summarised in
the companion document Achieving
Excellence in Construction: A Manager's
Checklist.
28. Whole-life costing and cost management
Each financial review should ensure
that:
īthe latest estimate is compared
with the previously approved
budget;
īand does not exceed it without
fully reasoned justification;
29. Whole-life costing and cost management
īthe latest estimate of cost is made up
of the base estimate for whole-life
costs and the risk allowance;
īthe risk allowance is for identified
risks only (not an assumed
contingency provision);
īthe project is still affordable;
īfunds are available for planned
expenditure.
30. Whole-life costing and cost management
Management of the risk allowance
īThe project sponsor should manage the risk
allowance;
īwith support and advice from the project manager.
Management of the risk allowance consists
of:
īa procedure to move costs out of the risk allowance
into the base estimate for the project work;
īas risks materialise or actions are taken to manage
the risks.
31. Whole-life costing and cost management
īThere must be formal procedures for
controlling quality, cost, time and changes.
īRisk allowances should only be expended
when the identified risks to which they
relate occur.
īWhen risks occur that have not previously
been identified, they should be treated as
changes to the project.
32. Whole-life costing and cost management
īSimilarly, risks that materialise but have
insufficient risk allowance made for them
will also need to be treated as changes.
īRisks and the risk allowance should be
reviewed on a regular basis.
īParticularly, when formal estimates are
prepared, but also throughout the design,
construction and equipping stages.
33. Whole-life costing and cost management
īAs more firm commitments are
entered into and the work is carried
out, so the risks in future commitments
and work are reduced.
īThe estimate for the risk allowance
should reflect this. (See also AE4:Risk
and value management.)