SlideShare a Scribd company logo
1 of 31
GSC MENEAT
Tanzania Factory
David Nderimo
Regional GSC meeting, March 12-16, 2012
Engineering –
Project Management
© Copyright JTI 2012
Engineering – Project management
Engineering - Project Management
Organization chart
Martin MARIKI
Project Engineer
Shabani WAZIRI
Draftman
David NDERIMO
Project Manager
Martin PORTZ
Project Engineer
STA
Recently completed projects
3Engineering - Project Management
© Copyright JTI 2012
Factory water network
• Replacement of worn out 50 years old water
network
• Connecting of 3rd
borehole to water network
• Installation of water softener
• Implementation of water flow meter for
monitoring
4
Completed in February 2012
Engineering - Project Management
© Copyright JTI 2012
Partial upgrade of new site warehouse
• Upgrade of part of semi finished warehouse
(Mezzanine) with a total area of 1,800m² out
of 10,000m²
• Operation with automatic exhaust heat fans
• Using natural light (Transparent sheets)
• Hygienic condition surface floor
• The warehouse is now used for tobacco
storage
5
Completed in January 2012
Engineering - Project Management
© Copyright JTI 2012
Extension of fire detection system to
• Parts of newly installed Primary (Flash dryer)
• TP filter room
• Upgraded warehouse
• Fire pump area
Fire detection system extension
Completed in January 2012
6Engineering - Project Management
Projects in progress
7Engineering - Project Management
© Copyright JTI 2012
2nd
gas engine
• Description
• Installation of additional 1MW electricity generating capacity to meet increased energy demand due to
new Primary and additional Make/Pack machines
• Goal
• Ensure stable and sufficient power supply to support volume growth
• Status
• Preparation works in progress
• Engine delivered; Synchronization panel in transit
• Key equipment installation start: 04/12
• Commissioning: 05/12
Marketing budget
8Engineering - Project Management
© Copyright JTI 2012
Make/Pack and Cutfiller Storage HVAC
• Description
• Extension of existing HVAC system in Make/Pack due to increased area and heat load
• Replacement of existing Cutfiller AHU due to increased storage area
• Goal
• Improve machine performance
• Improve product quality
• Be in line with policies and procedures
• Status
• Preparation works in progress
• Key equipment partially delivered; rest expected to be cleared by mid of March 2012
• Installation start: 04/12
• Commissioning: 06/12
ASP 2011-2012
9Engineering - Project Management
© Copyright JTI 2012 10
New cutfiller AHU New Make/Pack AHU
Exisiting Make/Pack AHU Engineering - Project Management
© Copyright JTI 2012
Boiler Replacement and Co-generation
• Description
• Replacement of one old boiler and making use of waste heat of gas engine #1
• Waste heat recovery of engine #2 not in scope
• Goal
• Reliable and cost efficient steam supply
• Possible funding by Belgium government (subsidy directly paid to supplier) up to 50% of the equipment
with a maximum of 247.500 Euro
• Status:
• Application for subsidy: 01/12
• Feedback for subsidy: expected in 03/12
• PO: 04/12 (after feedback for subsidy)
• Installation: 10/12
• Commissioning: 11/12
ASP 2011-2012
11Engineering - Project Management
© Copyright JTI 2012 12Engineering - Project Management
© Copyright JTI 2012 13
New boiler house
Existing boiler house
Engineering - Project Management
© Copyright JTI 2012
KDF line
• Description
• The current situation with JTI Tanzania is having two Filter makers (Rebuild KDF 2ER and KDF 2
overhauled by HAUNI)
• While the volume growth in make/pack has made an increase of the filter demand, it is necessary to
increase the capacity in the filter production to avoid the risk of having insufficient filter supply to the
makers and lowering the loading level to below 95%.
• Goal
• Avoid overtime
• Meet volume demand
• Status:
• Future Make/Pack layout to be finalized and agreed with production
• Machine in transit; expected to be cleared by mid of March 2012
• Installation start: 05/12
• Commissioning: 06/12
ASP 2012
14Engineering - Project Management
© Copyright JTI 2012
Printers for export product
• Description
• Democratic Republic of Congo (DRC) requires printing of three lines on each pack
(Date of Manufacturing, Date of Expiration and Lot number of the product)
• Current domino ink jet printers do not have the capability of meeting this requirements
• Therefore two X500 packing lines need to be equipped with new printer
• Goal
• Meet regulatory requirements for DRC market
• Status:
• Original delivery time 04/12
• New delivery time 07/12 (Delay of 2 month)
• Commissioning: 08/12
ASP 2011-2012
15Engineering - Project Management
© Copyright JTI 2012
4th GD 121/X 500 line
• Description
• Installation of additional soft pack line (GD 121-AF 12, GD B 21, GD X 500, GD C800 and Taurus filter
mass flow) to provide sufficient capacity to cope with the increasing volume demand - driven by both the
Tanzania domestic and East African markets
• Goal
• Reduce loading level of soft pack lines
• Increase flexibility in production
• Meet market volume demand as per ASP
• Status:
• Future Make/Pack layout to be finalized and agreed with production
• FAT / pre-inspection: 07/12
• Installation start: 11/12
• Commissioning: 12/12
ASP 2011-2012
16Engineering - Project Management
Planned projects
17Engineering - Project Management
© Copyright JTI 2012
GD X2 electronics update
• Description
• Replacement of obsolete Micro I plc control
• Goal
• Ensure availability of machine
• Status:
• Quotation from GD on hand
• BAP prepared and on internal circulation  expected to be submitted by end of March 2012
• BAP approval: 04/12
• PO: 05/12
• Installation: 04/13
• Commissioning: 05/13
ASP 2012-2013
18Engineering - Project Management
© Copyright JTI 2012
Rejects and Shorts buffering
• Description
• Installation of rack system in production area to generate space for Rejects and Shorts to avoid outside
buffering
• Goal
• Reduce material handling
• Optimize work flow
• Status:
• Layout change of QC lab extension
• Installation: 04/12
TP Upgrade
19Engineering - Project Management
© Copyright JTI 2012 20
Shorts tipper
Shorts buffering
QC extension
Engineering - Project Management
Outlook / focus areas
21Engineering - Project Management
© Copyright JTI 2012
Primary
• Utilities
• Steam pipe
• Waste water drainage
• Segregating Primary from outside
• Emergency exits / doors
• Roller shutters
• Roof insulation
• Windows
• Ventilation system
Pending issues
22Engineering - Project Management
© Copyright JTI 2012
Reduction of idle times in Primary
• Description
• Lamina and CRES line are in direct connection via two old silos, but of non-matching capacities
• High idle times on Lamina line waiting for CRES
• Goal
• Reduce idle times ( reduction of working hours and energy need)
• Optimize operation
• Status:
• Alternative 1: CRES buffering in C-48 and adding back via tipper
• Alternative 2: Replace existing two old silos by two new double layer silos (in total 4 silos)
• Next steps
• Conduct feasibility study to investigate different alternatives in detail
• Share results: 04/12
Study
23Engineering - Project Management
© Copyright JTI 2012 24
CRES box off CRES silos
Addback tipper
Engineering - Project Management
© Copyright JTI 2012
New concept for batch preparation
• Description
• Due to limited space inside Primary tobacco batches are prepared and stored outside
• This causes a lot of fork lift traffic as well as limited overview
• Goal
• Reduce handling
• Optimize operation
• Increase safety on site
• Status:
• Alternative 1: Convert old boiler house
• Alternative 2: Convert former heavy fuel oil storage
• Next steps
• Conduct feasibility study to investigate different alternatives in detail
• Share results: 04/12
Study
25Engineering - Project Management
© Copyright JTI 2012 26
Former heavy fuel
oil storage
Boiler house
Engineering - Project Management
© Copyright JTI 2012
Finalizing semi-finished warehouse on new site
• Description
• Due to limited storage capacity Tanzania factory is renting outside storage
• Required space: 20,350 m2
• Available space: 11,819 m2
• Deficit: 8,531 m2
• Goal
• Provide sufficient storage capacity for NTM, FG and tobacco on site
• Status:
• Available space to be completed is 8,400 m2
• Estimated cost of work to complete is $ 2,132,750 (at the cost 250$/m²)
• Next steps
• Conduct feasibility study to investigate in detail
• Share results: 04/12
Study
27Engineering - Project Management
The future of Project
Management section
28Engineering - Project Management
© Copyright JTI 2012
The future of Project Management section
The department will merge as per ‘JTIs best practice’
Draftsman
Maintenance ENGINEER
Engineering MANAGER
Utility ENGINEER Project ENGINEER
Engineering - Project Management
© Copyright JTI 2012
David Nderimo
The department will merge as per ‘JTIs best practice’
Engineering - Project Management
Enterprising
Open
Challenging

More Related Content

What's hot

Marcel Zeestraten - Concept Engineer
Marcel Zeestraten - Concept EngineerMarcel Zeestraten - Concept Engineer
Marcel Zeestraten - Concept EngineerMarcel Zeestraten
 
Fuel Flexibility - a techno-economic review
Fuel Flexibility - a techno-economic reviewFuel Flexibility - a techno-economic review
Fuel Flexibility - a techno-economic reviewShaun West
 
Europe User Conference: KBC Visual MESA energy real-time optimizer at TOTAL A...
Europe User Conference: KBC Visual MESA energy real-time optimizer at TOTAL A...Europe User Conference: KBC Visual MESA energy real-time optimizer at TOTAL A...
Europe User Conference: KBC Visual MESA energy real-time optimizer at TOTAL A...KBC (A Yokogawa Company)
 
CBI-electric Renewable Cabins Presentation
CBI-electric Renewable Cabins PresentationCBI-electric Renewable Cabins Presentation
CBI-electric Renewable Cabins PresentationDamian Coetzee
 
Case study FCC model with integrated energy and yield
Case study FCC model with integrated energy and yieldCase study FCC model with integrated energy and yield
Case study FCC model with integrated energy and yieldKBC (A Yokogawa Company)
 
Europe User Conference: Galp refinery wide model - a real work example
Europe User Conference: Galp refinery wide model - a real work exampleEurope User Conference: Galp refinery wide model - a real work example
Europe User Conference: Galp refinery wide model - a real work exampleKBC (A Yokogawa Company)
 
Europe User Conference: KBC Engineering Suite v7
Europe User Conference: KBC Engineering Suite v7Europe User Conference: KBC Engineering Suite v7
Europe User Conference: KBC Engineering Suite v7KBC (A Yokogawa Company)
 
DBIA 2016 Presentation on Progressive Design Build Aqua Marion WTP Project
DBIA 2016 Presentation on Progressive Design Build Aqua Marion WTP Project DBIA 2016 Presentation on Progressive Design Build Aqua Marion WTP Project
DBIA 2016 Presentation on Progressive Design Build Aqua Marion WTP Project Bowen
 
Mega air separation risk management
Mega air separation risk managementMega air separation risk management
Mega air separation risk managementaob
 
Johnson & johnson project
Johnson & johnson projectJohnson & johnson project
Johnson & johnson projectRadivoj Jovanov
 
Delivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & DataDelivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & Dataconstructingexcellence
 
2017 Multifamily Green Building Primer Webinar
2017 Multifamily Green Building Primer Webinar2017 Multifamily Green Building Primer Webinar
2017 Multifamily Green Building Primer WebinarDominic Butler
 
Operational analysis of biogas based cold storage
Operational analysis of biogas based cold storageOperational analysis of biogas based cold storage
Operational analysis of biogas based cold storagePrem Kumar
 
Supply Chain Opportunities in the Bioenergy Sector Workshop - Hilary Kinney
Supply Chain Opportunities in the Bioenergy Sector Workshop  - Hilary KinneySupply Chain Opportunities in the Bioenergy Sector Workshop  - Hilary Kinney
Supply Chain Opportunities in the Bioenergy Sector Workshop - Hilary KinneyInvest Northern Ireland
 
ASHRAE Virtual Design and Construction Conference March 2021- Development of ...
ASHRAE Virtual Design and Construction Conference March 2021- Development of ...ASHRAE Virtual Design and Construction Conference March 2021- Development of ...
ASHRAE Virtual Design and Construction Conference March 2021- Development of ...Shanti Pless
 
Combined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWCombined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWmelanie_bissonnette
 
Coventry university CASE STUDY
Coventry university CASE STUDYCoventry university CASE STUDY
Coventry university CASE STUDYPaul Harrison
 

What's hot (20)

Marcel Zeestraten - Concept Engineer
Marcel Zeestraten - Concept EngineerMarcel Zeestraten - Concept Engineer
Marcel Zeestraten - Concept Engineer
 
Fuel Flexibility - a techno-economic review
Fuel Flexibility - a techno-economic reviewFuel Flexibility - a techno-economic review
Fuel Flexibility - a techno-economic review
 
Europe User Conference: KBC Visual MESA energy real-time optimizer at TOTAL A...
Europe User Conference: KBC Visual MESA energy real-time optimizer at TOTAL A...Europe User Conference: KBC Visual MESA energy real-time optimizer at TOTAL A...
Europe User Conference: KBC Visual MESA energy real-time optimizer at TOTAL A...
 
CBI-electric Renewable Cabins Presentation
CBI-electric Renewable Cabins PresentationCBI-electric Renewable Cabins Presentation
CBI-electric Renewable Cabins Presentation
 
Case study FCC model with integrated energy and yield
Case study FCC model with integrated energy and yieldCase study FCC model with integrated energy and yield
Case study FCC model with integrated energy and yield
 
Europe User Conference: Galp refinery wide model - a real work example
Europe User Conference: Galp refinery wide model - a real work exampleEurope User Conference: Galp refinery wide model - a real work example
Europe User Conference: Galp refinery wide model - a real work example
 
Europe User Conference: KBC Engineering Suite v7
Europe User Conference: KBC Engineering Suite v7Europe User Conference: KBC Engineering Suite v7
Europe User Conference: KBC Engineering Suite v7
 
Arcelormittal Italie
Arcelormittal ItalieArcelormittal Italie
Arcelormittal Italie
 
DBIA 2016 Presentation on Progressive Design Build Aqua Marion WTP Project
DBIA 2016 Presentation on Progressive Design Build Aqua Marion WTP Project DBIA 2016 Presentation on Progressive Design Build Aqua Marion WTP Project
DBIA 2016 Presentation on Progressive Design Build Aqua Marion WTP Project
 
Mega air separation risk management
Mega air separation risk managementMega air separation risk management
Mega air separation risk management
 
Johnson & johnson project
Johnson & johnson projectJohnson & johnson project
Johnson & johnson project
 
Delivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & DataDelivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & Data
 
GE Hitachi. Nuclear Innovation
GE Hitachi. Nuclear InnovationGE Hitachi. Nuclear Innovation
GE Hitachi. Nuclear Innovation
 
2017 Multifamily Green Building Primer Webinar
2017 Multifamily Green Building Primer Webinar2017 Multifamily Green Building Primer Webinar
2017 Multifamily Green Building Primer Webinar
 
Operational analysis of biogas based cold storage
Operational analysis of biogas based cold storageOperational analysis of biogas based cold storage
Operational analysis of biogas based cold storage
 
Supply Chain Opportunities in the Bioenergy Sector Workshop - Hilary Kinney
Supply Chain Opportunities in the Bioenergy Sector Workshop  - Hilary KinneySupply Chain Opportunities in the Bioenergy Sector Workshop  - Hilary Kinney
Supply Chain Opportunities in the Bioenergy Sector Workshop - Hilary Kinney
 
ASHRAE Virtual Design and Construction Conference March 2021- Development of ...
ASHRAE Virtual Design and Construction Conference March 2021- Development of ...ASHRAE Virtual Design and Construction Conference March 2021- Development of ...
ASHRAE Virtual Design and Construction Conference March 2021- Development of ...
 
Combined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWCombined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NW
 
Earliest days SIM reactor suite models
Earliest days SIM reactor suite modelsEarliest days SIM reactor suite models
Earliest days SIM reactor suite models
 
Coventry university CASE STUDY
Coventry university CASE STUDYCoventry university CASE STUDY
Coventry university CASE STUDY
 

Viewers also liked

Viewers also liked (14)

EEA 2014 Risk analysis for World Cups pdf
EEA 2014 Risk analysis for World Cups pdfEEA 2014 Risk analysis for World Cups pdf
EEA 2014 Risk analysis for World Cups pdf
 
entirepersuasuve
entirepersuasuveentirepersuasuve
entirepersuasuve
 
50 anni
50 anni50 anni
50 anni
 
Family Matter Expat to Local Hire
Family Matter Expat to Local HireFamily Matter Expat to Local Hire
Family Matter Expat to Local Hire
 
η χρυσομαλλούσα
η χρυσομαλλούσαη χρυσομαλλούσα
η χρυσομαλλούσα
 
EEA 2013 AUFLS P3 Ready Widescreen Presentation Ver 4
EEA 2013 AUFLS P3 Ready Widescreen Presentation Ver 4EEA 2013 AUFLS P3 Ready Widescreen Presentation Ver 4
EEA 2013 AUFLS P3 Ready Widescreen Presentation Ver 4
 
Revanth CV.doc exp.
Revanth CV.doc exp.Revanth CV.doc exp.
Revanth CV.doc exp.
 
profile-mvp
profile-mvpprofile-mvp
profile-mvp
 
Lekshmi_Mohan
Lekshmi_MohanLekshmi_Mohan
Lekshmi_Mohan
 
MaintreamingGenderinWaterResources_WorldVision Process
MaintreamingGenderinWaterResources_WorldVision ProcessMaintreamingGenderinWaterResources_WorldVision Process
MaintreamingGenderinWaterResources_WorldVision Process
 
Published Marketing Research Article
Published Marketing Research ArticlePublished Marketing Research Article
Published Marketing Research Article
 
cas_Knowledge_Network
cas_Knowledge_Networkcas_Knowledge_Network
cas_Knowledge_Network
 
amaqhawe (2015)
amaqhawe (2015)amaqhawe (2015)
amaqhawe (2015)
 
Sistema eduativo de corea
Sistema eduativo de coreaSistema eduativo de corea
Sistema eduativo de corea
 

Similar to GSC meeting PM - Final

RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARSAQIB MANIAR
 
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage ProjectPaul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage ProjectGlobal CCS Institute
 
Ppt5 exp lonodn - kevin cope & alex yakimov ( imperial college ) data cent...
Ppt5   exp lonodn - kevin cope & alex yakimov ( imperial college )  data cent...Ppt5   exp lonodn - kevin cope & alex yakimov ( imperial college )  data cent...
Ppt5 exp lonodn - kevin cope & alex yakimov ( imperial college ) data cent...JISC's Green ICT Programme
 
Ramy Emad C.V Project Engineer
Ramy Emad C.V Project EngineerRamy Emad C.V Project Engineer
Ramy Emad C.V Project EngineerRamy Emad
 
RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARSAQIB MANIAR
 
Slides Transcription.docx
Slides Transcription.docxSlides Transcription.docx
Slides Transcription.docxbrian157854
 
Simon Coles, Dounreay: Strategic Challenges in a Decommissioning Context
Simon Coles, Dounreay: Strategic Challenges in a Decommissioning ContextSimon Coles, Dounreay: Strategic Challenges in a Decommissioning Context
Simon Coles, Dounreay: Strategic Challenges in a Decommissioning ContextAssociation for Project Management
 
Energy Efficient Server Rooms at the University of Cambridge
Energy Efficient Server Rooms at the University of CambridgeEnergy Efficient Server Rooms at the University of Cambridge
Energy Efficient Server Rooms at the University of CambridgeJISC's Green ICT Programme
 
MAN presentation
MAN presentationMAN presentation
MAN presentationhansbeyer
 
Esteem Projects Pvt Ltd - The Fired Heater Company
Esteem Projects Pvt Ltd - The Fired Heater CompanyEsteem Projects Pvt Ltd - The Fired Heater Company
Esteem Projects Pvt Ltd - The Fired Heater CompanyTanveer Singh
 
RV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaRV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaMichaelUberti
 
Presentaciones taeca kom 영문
Presentaciones taeca kom 영문Presentaciones taeca kom 영문
Presentaciones taeca kom 영문qooji
 
Circular Economy in Transformer Service.pptx
Circular Economy in Transformer Service.pptxCircular Economy in Transformer Service.pptx
Circular Economy in Transformer Service.pptxMircea Gingu
 
Complexity - Advanced Engineering Project Management
Complexity - Advanced Engineering Project ManagementComplexity - Advanced Engineering Project Management
Complexity - Advanced Engineering Project ManagementMDCSystems
 

Similar to GSC meeting PM - Final (20)

RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIAR
 
Perth metro
Perth metroPerth metro
Perth metro
 
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage ProjectPaul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
Paul Crooks - Abu Dhabi Carbon Capture, Usage and Storage Project
 
Ppt5 exp lonodn - kevin cope & alex yakimov ( imperial college ) data cent...
Ppt5   exp lonodn - kevin cope & alex yakimov ( imperial college )  data cent...Ppt5   exp lonodn - kevin cope & alex yakimov ( imperial college )  data cent...
Ppt5 exp lonodn - kevin cope & alex yakimov ( imperial college ) data cent...
 
Ramy Emad C.V Project Engineer
Ramy Emad C.V Project EngineerRamy Emad C.V Project Engineer
Ramy Emad C.V Project Engineer
 
RESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIARRESUME - NAJMUL SAQIB MANIAR
RESUME - NAJMUL SAQIB MANIAR
 
slides
slidesslides
slides
 
New alan kiff
New alan kiffNew alan kiff
New alan kiff
 
Slides Transcription.docx
Slides Transcription.docxSlides Transcription.docx
Slides Transcription.docx
 
Simon Coles, Dounreay: Strategic Challenges in a Decommissioning Context
Simon Coles, Dounreay: Strategic Challenges in a Decommissioning ContextSimon Coles, Dounreay: Strategic Challenges in a Decommissioning Context
Simon Coles, Dounreay: Strategic Challenges in a Decommissioning Context
 
Energy Efficient Server Rooms at the University of Cambridge
Energy Efficient Server Rooms at the University of CambridgeEnergy Efficient Server Rooms at the University of Cambridge
Energy Efficient Server Rooms at the University of Cambridge
 
MAN presentation
MAN presentationMAN presentation
MAN presentation
 
Esteem Projects Pvt Ltd - The Fired Heater Company
Esteem Projects Pvt Ltd - The Fired Heater CompanyEsteem Projects Pvt Ltd - The Fired Heater Company
Esteem Projects Pvt Ltd - The Fired Heater Company
 
PerthMetro case study
PerthMetro case studyPerthMetro case study
PerthMetro case study
 
Upload
UploadUpload
Upload
 
PerthMetro Case Study
PerthMetro Case StudyPerthMetro Case Study
PerthMetro Case Study
 
RV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaRV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey Australia
 
Presentaciones taeca kom 영문
Presentaciones taeca kom 영문Presentaciones taeca kom 영문
Presentaciones taeca kom 영문
 
Circular Economy in Transformer Service.pptx
Circular Economy in Transformer Service.pptxCircular Economy in Transformer Service.pptx
Circular Economy in Transformer Service.pptx
 
Complexity - Advanced Engineering Project Management
Complexity - Advanced Engineering Project ManagementComplexity - Advanced Engineering Project Management
Complexity - Advanced Engineering Project Management
 

GSC meeting PM - Final

  • 1. GSC MENEAT Tanzania Factory David Nderimo Regional GSC meeting, March 12-16, 2012 Engineering – Project Management
  • 2. © Copyright JTI 2012 Engineering – Project management Engineering - Project Management Organization chart Martin MARIKI Project Engineer Shabani WAZIRI Draftman David NDERIMO Project Manager Martin PORTZ Project Engineer STA
  • 4. © Copyright JTI 2012 Factory water network • Replacement of worn out 50 years old water network • Connecting of 3rd borehole to water network • Installation of water softener • Implementation of water flow meter for monitoring 4 Completed in February 2012 Engineering - Project Management
  • 5. © Copyright JTI 2012 Partial upgrade of new site warehouse • Upgrade of part of semi finished warehouse (Mezzanine) with a total area of 1,800m² out of 10,000m² • Operation with automatic exhaust heat fans • Using natural light (Transparent sheets) • Hygienic condition surface floor • The warehouse is now used for tobacco storage 5 Completed in January 2012 Engineering - Project Management
  • 6. © Copyright JTI 2012 Extension of fire detection system to • Parts of newly installed Primary (Flash dryer) • TP filter room • Upgraded warehouse • Fire pump area Fire detection system extension Completed in January 2012 6Engineering - Project Management
  • 7. Projects in progress 7Engineering - Project Management
  • 8. © Copyright JTI 2012 2nd gas engine • Description • Installation of additional 1MW electricity generating capacity to meet increased energy demand due to new Primary and additional Make/Pack machines • Goal • Ensure stable and sufficient power supply to support volume growth • Status • Preparation works in progress • Engine delivered; Synchronization panel in transit • Key equipment installation start: 04/12 • Commissioning: 05/12 Marketing budget 8Engineering - Project Management
  • 9. © Copyright JTI 2012 Make/Pack and Cutfiller Storage HVAC • Description • Extension of existing HVAC system in Make/Pack due to increased area and heat load • Replacement of existing Cutfiller AHU due to increased storage area • Goal • Improve machine performance • Improve product quality • Be in line with policies and procedures • Status • Preparation works in progress • Key equipment partially delivered; rest expected to be cleared by mid of March 2012 • Installation start: 04/12 • Commissioning: 06/12 ASP 2011-2012 9Engineering - Project Management
  • 10. © Copyright JTI 2012 10 New cutfiller AHU New Make/Pack AHU Exisiting Make/Pack AHU Engineering - Project Management
  • 11. © Copyright JTI 2012 Boiler Replacement and Co-generation • Description • Replacement of one old boiler and making use of waste heat of gas engine #1 • Waste heat recovery of engine #2 not in scope • Goal • Reliable and cost efficient steam supply • Possible funding by Belgium government (subsidy directly paid to supplier) up to 50% of the equipment with a maximum of 247.500 Euro • Status: • Application for subsidy: 01/12 • Feedback for subsidy: expected in 03/12 • PO: 04/12 (after feedback for subsidy) • Installation: 10/12 • Commissioning: 11/12 ASP 2011-2012 11Engineering - Project Management
  • 12. © Copyright JTI 2012 12Engineering - Project Management
  • 13. © Copyright JTI 2012 13 New boiler house Existing boiler house Engineering - Project Management
  • 14. © Copyright JTI 2012 KDF line • Description • The current situation with JTI Tanzania is having two Filter makers (Rebuild KDF 2ER and KDF 2 overhauled by HAUNI) • While the volume growth in make/pack has made an increase of the filter demand, it is necessary to increase the capacity in the filter production to avoid the risk of having insufficient filter supply to the makers and lowering the loading level to below 95%. • Goal • Avoid overtime • Meet volume demand • Status: • Future Make/Pack layout to be finalized and agreed with production • Machine in transit; expected to be cleared by mid of March 2012 • Installation start: 05/12 • Commissioning: 06/12 ASP 2012 14Engineering - Project Management
  • 15. © Copyright JTI 2012 Printers for export product • Description • Democratic Republic of Congo (DRC) requires printing of three lines on each pack (Date of Manufacturing, Date of Expiration and Lot number of the product) • Current domino ink jet printers do not have the capability of meeting this requirements • Therefore two X500 packing lines need to be equipped with new printer • Goal • Meet regulatory requirements for DRC market • Status: • Original delivery time 04/12 • New delivery time 07/12 (Delay of 2 month) • Commissioning: 08/12 ASP 2011-2012 15Engineering - Project Management
  • 16. © Copyright JTI 2012 4th GD 121/X 500 line • Description • Installation of additional soft pack line (GD 121-AF 12, GD B 21, GD X 500, GD C800 and Taurus filter mass flow) to provide sufficient capacity to cope with the increasing volume demand - driven by both the Tanzania domestic and East African markets • Goal • Reduce loading level of soft pack lines • Increase flexibility in production • Meet market volume demand as per ASP • Status: • Future Make/Pack layout to be finalized and agreed with production • FAT / pre-inspection: 07/12 • Installation start: 11/12 • Commissioning: 12/12 ASP 2011-2012 16Engineering - Project Management
  • 17. Planned projects 17Engineering - Project Management
  • 18. © Copyright JTI 2012 GD X2 electronics update • Description • Replacement of obsolete Micro I plc control • Goal • Ensure availability of machine • Status: • Quotation from GD on hand • BAP prepared and on internal circulation  expected to be submitted by end of March 2012 • BAP approval: 04/12 • PO: 05/12 • Installation: 04/13 • Commissioning: 05/13 ASP 2012-2013 18Engineering - Project Management
  • 19. © Copyright JTI 2012 Rejects and Shorts buffering • Description • Installation of rack system in production area to generate space for Rejects and Shorts to avoid outside buffering • Goal • Reduce material handling • Optimize work flow • Status: • Layout change of QC lab extension • Installation: 04/12 TP Upgrade 19Engineering - Project Management
  • 20. © Copyright JTI 2012 20 Shorts tipper Shorts buffering QC extension Engineering - Project Management
  • 21. Outlook / focus areas 21Engineering - Project Management
  • 22. © Copyright JTI 2012 Primary • Utilities • Steam pipe • Waste water drainage • Segregating Primary from outside • Emergency exits / doors • Roller shutters • Roof insulation • Windows • Ventilation system Pending issues 22Engineering - Project Management
  • 23. © Copyright JTI 2012 Reduction of idle times in Primary • Description • Lamina and CRES line are in direct connection via two old silos, but of non-matching capacities • High idle times on Lamina line waiting for CRES • Goal • Reduce idle times ( reduction of working hours and energy need) • Optimize operation • Status: • Alternative 1: CRES buffering in C-48 and adding back via tipper • Alternative 2: Replace existing two old silos by two new double layer silos (in total 4 silos) • Next steps • Conduct feasibility study to investigate different alternatives in detail • Share results: 04/12 Study 23Engineering - Project Management
  • 24. © Copyright JTI 2012 24 CRES box off CRES silos Addback tipper Engineering - Project Management
  • 25. © Copyright JTI 2012 New concept for batch preparation • Description • Due to limited space inside Primary tobacco batches are prepared and stored outside • This causes a lot of fork lift traffic as well as limited overview • Goal • Reduce handling • Optimize operation • Increase safety on site • Status: • Alternative 1: Convert old boiler house • Alternative 2: Convert former heavy fuel oil storage • Next steps • Conduct feasibility study to investigate different alternatives in detail • Share results: 04/12 Study 25Engineering - Project Management
  • 26. © Copyright JTI 2012 26 Former heavy fuel oil storage Boiler house Engineering - Project Management
  • 27. © Copyright JTI 2012 Finalizing semi-finished warehouse on new site • Description • Due to limited storage capacity Tanzania factory is renting outside storage • Required space: 20,350 m2 • Available space: 11,819 m2 • Deficit: 8,531 m2 • Goal • Provide sufficient storage capacity for NTM, FG and tobacco on site • Status: • Available space to be completed is 8,400 m2 • Estimated cost of work to complete is $ 2,132,750 (at the cost 250$/m²) • Next steps • Conduct feasibility study to investigate in detail • Share results: 04/12 Study 27Engineering - Project Management
  • 28. The future of Project Management section 28Engineering - Project Management
  • 29. © Copyright JTI 2012 The future of Project Management section The department will merge as per ‘JTIs best practice’ Draftsman Maintenance ENGINEER Engineering MANAGER Utility ENGINEER Project ENGINEER Engineering - Project Management
  • 30. © Copyright JTI 2012 David Nderimo The department will merge as per ‘JTIs best practice’ Engineering - Project Management