EEA 2013 AUFLS P3 Ready Widescreen Presentation Ver 4
1. AUFLS Load Control for HVDC Pole 3
Commissioning
Challenges and Findings
Load Control for HVDC Pole 3
Commissioning
VDC Pole 3 Commissioning
By Lekshmi Mohan
Justin Blass
2. PURPOSE
The AUFLS Pole 3 Ready project was initiated
To improve the performance of the current
AUFLS scheme prior to the commissioning of
Pole 3.
To increase consumer confidence in the security
provided by the AUFLS system during
commissioning.
3. 50 -
49 -
48 -
47 -
51 -
52 -
46 -
45 -
53 -
54 -
55 -FREQUENCY(Hz)
INTERRUPTIBLE LOAD
AUFLS RANGE
BLACK START
OVER FREQUENCY RANGE
GENERATORS
OPERATE SAFELY
14. DESIGN QUESTIONS
• How big of AUFLS blocks can system handle?
• What size AUFLS blocks do we expect?
• How much AUFLS load could we control?
• How will we coordinate and control the reduction
process?
15. METHODOLOGY
• Bipole tripping event
• Worst case load profiles for month.
• 3 different stages of study
– Existing scheme (2 x 16%)
– Increment in block size (+1%) until 52 Hz is
reached
– Over frequency arming (OFA)
18. AUFLS REDUCTION PRINCIPLES
• Reduce AUFLS load when possible
• Limit disarming to once a day
• Observe a safety margin with RMT (17%)
• Spread reduction geographically when possible
19. INDUSTRY PARTICIPATION
• Urgent Code Amendment enabled obligation
modification
• Network companies volunteered to participate
• Various GXP and Vector relays were organised into
controllable groups
• Special thanks to Vector, Counties Power, Powerco,
Unison, Scanpower, Waipa, and WEL Networks for
participating
22. CONCLUSION
• Corrective action was needed during the commissioning of Pole 3.
• The control process improved reliability during commissioning.
• The control process will be carried out for the commissioning of the
new Pole 2 controls.
• The SO is continuing a long term initiative to improve the scheme
design and compliance requirements. To be proposed in 2013.