SlideShare a Scribd company logo
1 of 23
AUFLS Load Control for HVDC Pole 3
Commissioning
Challenges and Findings
Load Control for HVDC Pole 3
Commissioning
VDC Pole 3 Commissioning
By Lekshmi Mohan
Justin Blass
PURPOSE
The AUFLS Pole 3 Ready project was initiated
 To improve the performance of the current
AUFLS scheme prior to the commissioning of
Pole 3.
 To increase consumer confidence in the security
provided by the AUFLS system during
commissioning.
50 -
49 -
48 -
47 -
51 -
52 -
46 -
45 -
53 -
54 -
55 -FREQUENCY(Hz)
INTERRUPTIBLE LOAD
AUFLS RANGE
BLACK START
OVER FREQUENCY RANGE
GENERATORS
OPERATE SAFELY
DEMAND GENERATION
16%
16%
AUFLS BLOCKS
50 -
49 -
48 -
47 -
51 -
52 -
46 -
45 -
53 -
54 -
55 -
FREQUENCY(Hz)
BACKGROUND
50 -
49 -
48 -
47 -
51 -
52 -
46 -
45 -
53 -
54 -
55 -
FREQUENCY(Hz)
DEMAND GENERATION
50 -
49 -
48 -
47 -
51 -
52 -
46 -
45 -
53 -
54 -
55 -
FREQUENCY(Hz)
50 -
49 -
48 -
47 -
51 -
52 -
46 -
45 -
53 -
54 -
55 -
FREQUENCY(Hz)
50 -
49 -
48 -
47 -
51 -
52 -
46 -
45 -
53 -
54 -
55 -
FREQUENCY(Hz)
CCGT PLANT
50 -
49 -
48 -
47 -
51 -
52 -
46 -
45 -
53 -
54 -
55 -
FREQUENCY(Hz)
50 -
49 -
48 -
47 -
51 -
52 -
46 -
45 -
53 -
54 -
55 -FREQUENCY(Hz)
OVER FREQUENCY RANGE
AUFLS RANGE
BLACK START
• Compliance and provision behaviour
• Variations in AUFLS percentage
• Large amount of AUFLS armed during peak and
weekends
PROBLEMS IDENTIFIED
Commissioning risk
Discrimination between blocks
Problem
Number and size of AUFLS
blocks
Quantity of AUFLS load armed
PROBLEM ANALYSIS
Limitations
CONTROLTIME
LIMITING FACTORS
ACCURACYVISIBILITY
DESIGN QUESTIONS
• How big of AUFLS blocks can system handle?
• What size AUFLS blocks do we expect?
• How much AUFLS load could we control?
• How will we coordinate and control the reduction
process?
METHODOLOGY
• Bipole tripping event
• Worst case load profiles for month.
• 3 different stages of study
– Existing scheme (2 x 16%)
– Increment in block size (+1%) until 52 Hz is
reached
– Over frequency arming (OFA)
RESULTS
AUFLS REDUCTION PRINCIPLES
• Reduce AUFLS load when possible
• Limit disarming to once a day
• Observe a safety margin with RMT (17%)
• Spread reduction geographically when possible
INDUSTRY PARTICIPATION
• Urgent Code Amendment enabled obligation
modification
• Network companies volunteered to participate
• Various GXP and Vector relays were organised into
controllable groups
• Special thanks to Vector, Counties Power, Powerco,
Unison, Scanpower, Waipa, and WEL Networks for
participating
CONTROL PROCESS
TRANSPOWER
OPERATOR
VECTOR
OPERATOR
OVER
FREQUENCY
RESERVE
PROVIDER
VECTOR
RELAYGXP
RELAY
CONCLUSION
• Corrective action was needed during the commissioning of Pole 3.
• The control process improved reliability during commissioning.
• The control process will be carried out for the commissioning of the
new Pole 2 controls.
• The SO is continuing a long term initiative to improve the scheme
design and compliance requirements. To be proposed in 2013.
THE AUFLS JOURNEY

More Related Content

Viewers also liked (7)

MaintreamingGenderinWaterResources_WorldVision Process
MaintreamingGenderinWaterResources_WorldVision ProcessMaintreamingGenderinWaterResources_WorldVision Process
MaintreamingGenderinWaterResources_WorldVision Process
 
entirepersuasuve
entirepersuasuveentirepersuasuve
entirepersuasuve
 
50 anni
50 anni50 anni
50 anni
 
Revanth CV.doc exp.
Revanth CV.doc exp.Revanth CV.doc exp.
Revanth CV.doc exp.
 
cas_Knowledge_Network
cas_Knowledge_Networkcas_Knowledge_Network
cas_Knowledge_Network
 
Lekshmi_Mohan
Lekshmi_MohanLekshmi_Mohan
Lekshmi_Mohan
 
Sistema eduativo de corea
Sistema eduativo de coreaSistema eduativo de corea
Sistema eduativo de corea
 

Similar to EEA 2013 AUFLS P3 Ready Widescreen Presentation Ver 4

Show and Tell - Flexibility & Hydrogen Integration.pdf
Show and Tell - Flexibility & Hydrogen Integration.pdfShow and Tell - Flexibility & Hydrogen Integration.pdf
Show and Tell - Flexibility & Hydrogen Integration.pdf
SIFOfgem
 
EEE_4822_Topic_16_T&D.pdfunjnnmnmimiojijimim
EEE_4822_Topic_16_T&D.pdfunjnnmnmimiojijimimEEE_4822_Topic_16_T&D.pdfunjnnmnmimiojijimim
EEE_4822_Topic_16_T&D.pdfunjnnmnmimiojijimim
gffddffv vfdfvfvf
 
Congestion_Control09.ppt
Congestion_Control09.pptCongestion_Control09.ppt
Congestion_Control09.ppt
tahaniali27
 
SwRI_Mitchem_2NMC_09122014
SwRI_Mitchem_2NMC_09122014SwRI_Mitchem_2NMC_09122014
SwRI_Mitchem_2NMC_09122014
Sean Mitchem
 

Similar to EEA 2013 AUFLS P3 Ready Widescreen Presentation Ver 4 (20)

Power system transmission issues and effects
Power system transmission issues and effectsPower system transmission issues and effects
Power system transmission issues and effects
 
Power system interconnection presentation
Power system interconnection presentationPower system interconnection presentation
Power system interconnection presentation
 
Intra-vehicular Wireless Sensor Networks
Intra-vehicular Wireless Sensor NetworksIntra-vehicular Wireless Sensor Networks
Intra-vehicular Wireless Sensor Networks
 
Show and Tell - Flexibility & Hydrogen Integration.pdf
Show and Tell - Flexibility & Hydrogen Integration.pdfShow and Tell - Flexibility & Hydrogen Integration.pdf
Show and Tell - Flexibility & Hydrogen Integration.pdf
 
Inter-controller Traffic in ONOS Clusters for SDN Networks
Inter-controller Traffic in ONOS Clusters for SDN Networks Inter-controller Traffic in ONOS Clusters for SDN Networks
Inter-controller Traffic in ONOS Clusters for SDN Networks
 
RACH Procedures
RACH ProceduresRACH Procedures
RACH Procedures
 
Power System Stability Issues
Power System Stability IssuesPower System Stability Issues
Power System Stability Issues
 
OPTICAL BURST SWITCHING
OPTICAL BURST SWITCHINGOPTICAL BURST SWITCHING
OPTICAL BURST SWITCHING
 
EEE_4822_Topic_16_T&D.pdfunjnnmnmimiojijimim
EEE_4822_Topic_16_T&D.pdfunjnnmnmimiojijimimEEE_4822_Topic_16_T&D.pdfunjnnmnmimiojijimim
EEE_4822_Topic_16_T&D.pdfunjnnmnmimiojijimim
 
ULTRA WIDE BAND TECHNOLOGY
ULTRA WIDE BAND TECHNOLOGYULTRA WIDE BAND TECHNOLOGY
ULTRA WIDE BAND TECHNOLOGY
 
WAMS Applications , Wide Area Monitoring Systems WAMS
WAMS Applications , Wide Area Monitoring Systems WAMSWAMS Applications , Wide Area Monitoring Systems WAMS
WAMS Applications , Wide Area Monitoring Systems WAMS
 
WSN_energy.pptx
WSN_energy.pptxWSN_energy.pptx
WSN_energy.pptx
 
CONTROLLING FREQUENCY DEVIATIONS IN INTERCONNECTED POWER SYSTEM USING SMART ...
CONTROLLING FREQUENCY DEVIATIONS IN INTERCONNECTED POWER SYSTEM USING SMART ...CONTROLLING FREQUENCY DEVIATIONS IN INTERCONNECTED POWER SYSTEM USING SMART ...
CONTROLLING FREQUENCY DEVIATIONS IN INTERCONNECTED POWER SYSTEM USING SMART ...
 
IEEE 848 Standard Procedure For The Determination Of Tthe Ampacity Derating o...
IEEE 848 Standard Procedure For The Determination Of Tthe Ampacity Derating o...IEEE 848 Standard Procedure For The Determination Of Tthe Ampacity Derating o...
IEEE 848 Standard Procedure For The Determination Of Tthe Ampacity Derating o...
 
Class 16 load shedding
Class 16 load sheddingClass 16 load shedding
Class 16 load shedding
 
Energy Management by Adaptive Neuro-Fuzzy For Under Frequency Load Shedding/C...
Energy Management by Adaptive Neuro-Fuzzy For Under Frequency Load Shedding/C...Energy Management by Adaptive Neuro-Fuzzy For Under Frequency Load Shedding/C...
Energy Management by Adaptive Neuro-Fuzzy For Under Frequency Load Shedding/C...
 
Congestion control
Congestion controlCongestion control
Congestion control
 
Congestion_Control09.ppt
Congestion_Control09.pptCongestion_Control09.ppt
Congestion_Control09.ppt
 
14 berdner hawaiian adv inverters
14 berdner   hawaiian adv inverters14 berdner   hawaiian adv inverters
14 berdner hawaiian adv inverters
 
SwRI_Mitchem_2NMC_09122014
SwRI_Mitchem_2NMC_09122014SwRI_Mitchem_2NMC_09122014
SwRI_Mitchem_2NMC_09122014
 

EEA 2013 AUFLS P3 Ready Widescreen Presentation Ver 4

  • 1. AUFLS Load Control for HVDC Pole 3 Commissioning Challenges and Findings Load Control for HVDC Pole 3 Commissioning VDC Pole 3 Commissioning By Lekshmi Mohan Justin Blass
  • 2. PURPOSE The AUFLS Pole 3 Ready project was initiated  To improve the performance of the current AUFLS scheme prior to the commissioning of Pole 3.  To increase consumer confidence in the security provided by the AUFLS system during commissioning.
  • 3. 50 - 49 - 48 - 47 - 51 - 52 - 46 - 45 - 53 - 54 - 55 -FREQUENCY(Hz) INTERRUPTIBLE LOAD AUFLS RANGE BLACK START OVER FREQUENCY RANGE GENERATORS OPERATE SAFELY
  • 4. DEMAND GENERATION 16% 16% AUFLS BLOCKS 50 - 49 - 48 - 47 - 51 - 52 - 46 - 45 - 53 - 54 - 55 - FREQUENCY(Hz) BACKGROUND
  • 5. 50 - 49 - 48 - 47 - 51 - 52 - 46 - 45 - 53 - 54 - 55 - FREQUENCY(Hz) DEMAND GENERATION
  • 6. 50 - 49 - 48 - 47 - 51 - 52 - 46 - 45 - 53 - 54 - 55 - FREQUENCY(Hz)
  • 7. 50 - 49 - 48 - 47 - 51 - 52 - 46 - 45 - 53 - 54 - 55 - FREQUENCY(Hz)
  • 8. 50 - 49 - 48 - 47 - 51 - 52 - 46 - 45 - 53 - 54 - 55 - FREQUENCY(Hz) CCGT PLANT
  • 9. 50 - 49 - 48 - 47 - 51 - 52 - 46 - 45 - 53 - 54 - 55 - FREQUENCY(Hz)
  • 10. 50 - 49 - 48 - 47 - 51 - 52 - 46 - 45 - 53 - 54 - 55 -FREQUENCY(Hz) OVER FREQUENCY RANGE AUFLS RANGE BLACK START
  • 11. • Compliance and provision behaviour • Variations in AUFLS percentage • Large amount of AUFLS armed during peak and weekends PROBLEMS IDENTIFIED
  • 12. Commissioning risk Discrimination between blocks Problem Number and size of AUFLS blocks Quantity of AUFLS load armed PROBLEM ANALYSIS
  • 14. DESIGN QUESTIONS • How big of AUFLS blocks can system handle? • What size AUFLS blocks do we expect? • How much AUFLS load could we control? • How will we coordinate and control the reduction process?
  • 15. METHODOLOGY • Bipole tripping event • Worst case load profiles for month. • 3 different stages of study – Existing scheme (2 x 16%) – Increment in block size (+1%) until 52 Hz is reached – Over frequency arming (OFA)
  • 17.
  • 18. AUFLS REDUCTION PRINCIPLES • Reduce AUFLS load when possible • Limit disarming to once a day • Observe a safety margin with RMT (17%) • Spread reduction geographically when possible
  • 19. INDUSTRY PARTICIPATION • Urgent Code Amendment enabled obligation modification • Network companies volunteered to participate • Various GXP and Vector relays were organised into controllable groups • Special thanks to Vector, Counties Power, Powerco, Unison, Scanpower, Waipa, and WEL Networks for participating
  • 20.
  • 22. CONCLUSION • Corrective action was needed during the commissioning of Pole 3. • The control process improved reliability during commissioning. • The control process will be carried out for the commissioning of the new Pole 2 controls. • The SO is continuing a long term initiative to improve the scheme design and compliance requirements. To be proposed in 2013.