SlideShare a Scribd company logo
1 of 32
Download to read offline
Phoenix Convention Center • Phoenix, Arizona
Goal Setting and Performance Based Contracting
Track 7: Building
Performance
Session 5:
Constructing High Performance New Buildings
Shanti Pless
National Renewable Energy Laboratory
August 12, 2015
Energy Exchange: Federal Sustainability for the Next Decade
Goal Setting and Performance Based Contracting
Presenter: Paul Torcellini, NREL
Description: Learn to set goals in constructing high performance new
buildings and how to maximize the use of performance based
contracts to achieve those goals
Implementation Lessons and Results
Presenter: Shanti Pless, NREL
Description: Review lessons learned and results in implementation of
practices to best help guarantee building performance.
A View from a Contractor
Presenter: Phil Macey, JE Dunn Construction
Description: Develop an understanding from the contractor’s
perspective in understanding the process in designing and constructing
high performance new buildings.
2
Session Overview
NREL: 2006
3
Energy Exchange: Federal Sustainability for the Next Decade
Historical Context
Pre-2007
– Design-bid-build
– Specifications of “exactly”
what we wanted
– Always struggling to balance
the budget with program and
architecture and energy
4
NREL: Today
2012 aerial, Photo by Sincere/Duncan Studios courtesy of JE Dunn Construction
NREL Campus Growth with Design-Build
• Procurement process attributes post-2007:
– Design-build project delivery with firm fixed price for >$400 Million of new
facilities
– Specific energy performance requirements in the Request for Proposal (RFP, also
referred to as the contract)
• RSF I, office example: 25 kBtu/ft2/yr
• SEB, guard house example: net zero energy
• PUE for datacenter of 1.06
– Energy modeling required to substantiate goals
– Energy end-use metering requirement
– Voluntary incentive ($) program to ensure measurement and verification
outcome has a chance to meet predicted performance
6
Research Support Facility Vision
• A showcase for sustainable, high-performance design
o Incorporates the best in energy efficiency, environmental
performance, and advanced controls using a “whole-building”
integrated design process
• Serves as a model for cost-competitive, high-performance
commercial buildings for the nation’s design construction,
operation, and financing communities
Credit: RNL
7
Energy Exchange: Federal Sustainability for the Next Decade
Owner Defines Desires
Mission Critical:
Project cannot succeed without
this element
Highly Desirable:
What the owner wants
If Possible:
The wish list
8
Problem Definition: RFP Objectives
HIGHLY
DESIRABLE
MISSION
CRITICAL
IF
POSSIBLE
9
Problem Definition: RFP Objectives
• Attain safe work performance/
Safe Design Practices
• LEED Platinum
• ENERGY STAR “Plus”
MISSION
CRITICAL
10
Problem Definition: RFP Objectives
• 800 staff capacity
• 25kBTU/sf/year
• Architectural integrity
• Honor future staff needs
• Measurable ASHRAE 90.1
• Support culture and amenities
• Expandable building
• Ergonomics
• Flexible workspace
• Support future technologies
• Documentation to
produce
a “How to” manual
• “PR” campaign
implemented in real-
time
• Allow secure
collaboration
with outsiders
• Building information
modeling
• Substantial completion
by 2010
HIGHLY
DESIRABLE
11
Problem Definition: RFP Objectives
• Net Zero/design approach
• Most energy efficient building in the world
• LEED Platinum Plus
• ASHRAE 90.1 + 50%
• Visual displays of current energy efficiency
• Support public tours
• Achieve national and global recognition and
awards
• Support personnel turnover
IF
POSSIBLE
12
Details of 25 kBtu/ft2 in a Contract
1. Set energy goal based on past measured office building research
2. Need to provide normalization for space efficiency
3. Need to provide adjustment for energy use for large external users – data
center
4. Calculation method for delivered campus utilities
- Didn’t want to let design team “assume” unknown delivered efficiency
5. Benchmark current plug loads and operational schedules
6. Thermal comfort requirements
7. Energy monitoring requirements
8. Unique substantiation requirements
9. Provide ZEB definitions and classification system
13
EUI Design Requirements
• 25 kBtu/ft2/yr for standard office space occupant
density and datacenter loads
• Normalized up to 35.1 kBtu/ft2/yr for better space
efficiency and to account for full data center load
14
Performance-based design-build with absolute energy use requirements
• These are NOT bridging documents
– Owner has significant input into the preliminary design
– Some overlap of A/E costs
• These ARE performance specifications
– What something must do, not what it must be
– Subcontractor must substantiate that the design meets requirements
– Owner must not give the subcontractor technical direction
No drawings/plans in RFP!
• Don’t change your mind
Energy Performance Based Design-Build Process
15
A value engineering process that adds
value
16
A value engineering process that adds
value
17
The Results
18
Acquisition Strategy Results
• Created Value Beyond the Budget at Lower Cost and Risk to All
Parties
• No Claims or Controversy
• No Contractor Change Orders
• Virtually No Contingency Use for Unknowns or Omissions
• Sixteen Months from Shovel to Move-In
• Over a year of delivery time saved!
• Large Scale Net Zero Energy without increase in first cost
• Defined a New National Building Energy Standard
• Replicable Acquisition Strategy for Use by Others to Create
Their Own Successes!
19
How Much Did It Cost?
• $259/ft2 construction costs for site work,
infrastructure, and building
o Includes interiors, furniture, and cabling
o Does not include PV, land, or design costs
• Third-party-owned power purchase
agreement for PV
o $29/ft2 or 11% additional cost if NREL had purchased all
PV without tax breaks or subsidies (at $5/Watt)
20
• Firm fixed price with required energy goals in design-build
contract
• Integrated architecture and envelope as efficiency measures
• Simple and commercially viable
• No unique technologies required
• Modular precast wall panels with minimal finishes
• Optimized glazing area
• Repeatable office floorplate
• Takes a coordinated effort with the owner (and all user
groups), architect, builder, and engineers
Replicable – Cost Control Review
21
DOE/NREL Research Support Facility
RFP Design/Build Requirements:
• 50% energy cost savings over
ASHRAE 90.1
• 35.1 kBtu/ft2/yr
• Net zero energy use
• Performance assurance plan
with incentives
Design/Build Results:
• Net zero energy use
• 36.4 kBtu/ft2/yr
• $259/sqft construction costs
22
DOE/NREL RSF 3rd Wing
RFP Design/Build Requirements:
• 27 kBtu/ft2/yr
• 50% Energy Cost Savings
• Performance assurance plan
with incentives
Design/Build Results:
• 20 kBtu/ft2/yr measured
• Demonstration of additional
cost savings, energy efficiency,
and schedule gains over phase
1
• 17% more efficient than the RSF
• Cost savings of 5% ($14/ft2
cheaper)
23
DOE/NREL 1800 Car Staff Parking
Garage
Design/Build Requirements:
• 0.5 kBtu/ft2
• 175 kBtu/stall
• Net-zero energy Site
Entrance Building
Design/Build Results:
• 90% Energy savings
• 138 kBtu/parking stall
• $14,172 per parking space
• $15,500 to $24,500 for
typical parking space in
Denver area
DOE/NREL Cafeteria
RFP Design/Build Requirements:
• 35% energy cost savings over
ASHRAE 90.1
• Best in class commercial
kitchen equipment
• Performance assurance plan
with incentives
• LEED Gold
Design/Build Results:
• 36% energy savings and
Platinum
• Demonstration of max efficiency
in a commercial kitchen using
energy performance based
design/build delivery and
procurement methods
• Continuous improvement
requirements in vendor contract
to ensure performance
assurance
DOE/NREL Energy Systems Integration Facility
Design/Build Requirements:
• 27 kBtu/ft2 Office wing
• 1.06 PUE Super computer
• No mechanical cooling
• Waste heat reuse
• 30% savings for all labs
• LEED Gold
Design/Build Results:
• 26 kBtu/ft2 Office wing
• World class efficient super
computer
• 1.05 PUE
• 36% savings in labs
• LEED Platinum
26
Replication Success
27
World Class Efficiency is Possible
Within Our Construction Budgets!
• Include absolute EUI requirements
– Set up acquisition process to “force”
integrated design
– Subsystem measureable performance
requirements when needed
• Energy modeling guides conceptual design decisions
• Architecture and envelope are also efficiency
measures
– Unwavering commitment to problem statement
• Unleash power of design/build team of experts to
meet your needs – true value engineering
Spend the
time to get
the RFP
right
28
How-to Guides for Cost Control
Guide:
– https://buildingdata.energy.gov/cbrd/resource/1655
– Discusses the recommended strategies
– Pairs strategies with industry examples of success in ZEBs and
other high-performance buildings where possible
– Describes how to balance key decision-making factors
– Provides quick reference tables to help building owners and
project teams apply the recommended strategies to their
projects.
• Fact sheet:
– https://buildingdata.energy.gov/cbrd/resource/1654
– Highlights key ideas from the guide
– Directs readers to the guide for more details.
Energy Exchange: Federal Sustainability for the Next Decade
https://buildingdata.energy.gov/cbrd/energy_based_acquisition/
Scale performance-
based procurement
100 buildings
three years
This material is based upon work supported by the Department of Energy, Office of Energy Efficiency and Renewable Energy
(EERE), under Award Number DE-EE0007068.
Extended partnerships and stakeholder group forming now
TEAM
Seventhwave
National Renewable Energy
Laboratory
Institute for Sustainable Energy
UTILITY PARTNERS
ComEd
Eversource
United Illuminating
OWNER PARTNERS
University of Chicago
Lend Lease
Photos courtesy of University of Chicago

More Related Content

What's hot

Combined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWCombined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWmelanie_bissonnette
 
IES Faculty - Closing the Performance Gap
IES Faculty - Closing the Performance GapIES Faculty - Closing the Performance Gap
IES Faculty - Closing the Performance GapIES VE
 
Controlling capital costs using a performance based design build process
Controlling capital costs using a performance based design build processControlling capital costs using a performance based design build process
Controlling capital costs using a performance based design build processShanti Pless
 
NREL Commercial Buildings Research Group, ASHRAE June 2013 Research Keynote
NREL Commercial Buildings Research Group, ASHRAE June 2013 Research Keynote NREL Commercial Buildings Research Group, ASHRAE June 2013 Research Keynote
NREL Commercial Buildings Research Group, ASHRAE June 2013 Research Keynote Shanti Pless
 
COH Permitting Center
COH Permitting CenterCOH Permitting Center
COH Permitting Centeraiahouston
 
NZEB Interm Specification by Sean Armstrong
NZEB Interm Specification by Sean ArmstrongNZEB Interm Specification by Sean Armstrong
NZEB Interm Specification by Sean ArmstrongSustainableEnergyAut
 
Modeling, It's Not Just For Calendars and Energy
Modeling, It's Not Just For Calendars and EnergyModeling, It's Not Just For Calendars and Energy
Modeling, It's Not Just For Calendars and EnergyIllinois ASHRAE
 
Deep Retrofit: Irish Housing Building Standards
Deep Retrofit: Irish Housing Building StandardsDeep Retrofit: Irish Housing Building Standards
Deep Retrofit: Irish Housing Building StandardsSustainableEnergyAut
 
Delivering an Energy Model for BREEAM and LEED – Exposing What Really Matters...
Delivering an Energy Model for BREEAM and LEED – Exposing What Really Matters...Delivering an Energy Model for BREEAM and LEED – Exposing What Really Matters...
Delivering an Energy Model for BREEAM and LEED – Exposing What Really Matters...IES VE
 
Delivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & DataDelivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & Dataconstructingexcellence
 
Green buildings matter
Green buildings matterGreen buildings matter
Green buildings matterGRIHA India
 
IES Faculty – Part L, EPC’s & the VE (Part 1)
IES Faculty – Part L, EPC’s & the VE (Part 1)IES Faculty – Part L, EPC’s & the VE (Part 1)
IES Faculty – Part L, EPC’s & the VE (Part 1)IES VE
 
Study and analysis of energy rating of real
Study and analysis of energy rating of realStudy and analysis of energy rating of real
Study and analysis of energy rating of realAditya Ghumare
 
Health Business Services, HSE NZEB approach by Brendan Reddington
Health Business Services, HSE NZEB approach by Brendan ReddingtonHealth Business Services, HSE NZEB approach by Brendan Reddington
Health Business Services, HSE NZEB approach by Brendan ReddingtonSustainableEnergyAut
 
Deep Retrofit: Deep Retrofits across Europe,Passive House Institute
Deep Retrofit: Deep Retrofits across Europe,Passive House InstituteDeep Retrofit: Deep Retrofits across Europe,Passive House Institute
Deep Retrofit: Deep Retrofits across Europe,Passive House InstituteSustainableEnergyAut
 
MANIKANDAN_ENERGY ENGINEER_Detailed Resume
MANIKANDAN_ENERGY ENGINEER_Detailed ResumeMANIKANDAN_ENERGY ENGINEER_Detailed Resume
MANIKANDAN_ENERGY ENGINEER_Detailed ResumeManikandan Sudalaimani
 

What's hot (20)

Combined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NWCombined Heat and Power Engineering and Installation in the Pacific NW
Combined Heat and Power Engineering and Installation in the Pacific NW
 
IES Faculty - Closing the Performance Gap
IES Faculty - Closing the Performance GapIES Faculty - Closing the Performance Gap
IES Faculty - Closing the Performance Gap
 
Controlling capital costs using a performance based design build process
Controlling capital costs using a performance based design build processControlling capital costs using a performance based design build process
Controlling capital costs using a performance based design build process
 
NREL Commercial Buildings Research Group, ASHRAE June 2013 Research Keynote
NREL Commercial Buildings Research Group, ASHRAE June 2013 Research Keynote NREL Commercial Buildings Research Group, ASHRAE June 2013 Research Keynote
NREL Commercial Buildings Research Group, ASHRAE June 2013 Research Keynote
 
COH Permitting Center
COH Permitting CenterCOH Permitting Center
COH Permitting Center
 
NZEB Interm Specification by Sean Armstrong
NZEB Interm Specification by Sean ArmstrongNZEB Interm Specification by Sean Armstrong
NZEB Interm Specification by Sean Armstrong
 
Modeling, It's Not Just For Calendars and Energy
Modeling, It's Not Just For Calendars and EnergyModeling, It's Not Just For Calendars and Energy
Modeling, It's Not Just For Calendars and Energy
 
Deep Retrofit: Irish Housing Building Standards
Deep Retrofit: Irish Housing Building StandardsDeep Retrofit: Irish Housing Building Standards
Deep Retrofit: Irish Housing Building Standards
 
Manikandan Energy Engineer
Manikandan Energy EngineerManikandan Energy Engineer
Manikandan Energy Engineer
 
final
finalfinal
final
 
Delivering an Energy Model for BREEAM and LEED – Exposing What Really Matters...
Delivering an Energy Model for BREEAM and LEED – Exposing What Really Matters...Delivering an Energy Model for BREEAM and LEED – Exposing What Really Matters...
Delivering an Energy Model for BREEAM and LEED – Exposing What Really Matters...
 
Delivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & DataDelivering Sustainability Digitally - BREEAM & Data
Delivering Sustainability Digitally - BREEAM & Data
 
IGBC RATING SYSTEM
IGBC RATING SYSTEMIGBC RATING SYSTEM
IGBC RATING SYSTEM
 
Green buildings matter
Green buildings matterGreen buildings matter
Green buildings matter
 
IES Faculty – Part L, EPC’s & the VE (Part 1)
IES Faculty – Part L, EPC’s & the VE (Part 1)IES Faculty – Part L, EPC’s & the VE (Part 1)
IES Faculty – Part L, EPC’s & the VE (Part 1)
 
Study and analysis of energy rating of real
Study and analysis of energy rating of realStudy and analysis of energy rating of real
Study and analysis of energy rating of real
 
Health Business Services, HSE NZEB approach by Brendan Reddington
Health Business Services, HSE NZEB approach by Brendan ReddingtonHealth Business Services, HSE NZEB approach by Brendan Reddington
Health Business Services, HSE NZEB approach by Brendan Reddington
 
BEA deck 2.22.13
BEA deck   2.22.13BEA deck   2.22.13
BEA deck 2.22.13
 
Deep Retrofit: Deep Retrofits across Europe,Passive House Institute
Deep Retrofit: Deep Retrofits across Europe,Passive House InstituteDeep Retrofit: Deep Retrofits across Europe,Passive House Institute
Deep Retrofit: Deep Retrofits across Europe,Passive House Institute
 
MANIKANDAN_ENERGY ENGINEER_Detailed Resume
MANIKANDAN_ENERGY ENGINEER_Detailed ResumeMANIKANDAN_ENERGY ENGINEER_Detailed Resume
MANIKANDAN_ENERGY ENGINEER_Detailed Resume
 

Similar to Energy Exchange 2015: Track 7 session 5: Energy Performance Based Design Build Delivery at NREL

Mainstreaming Zero: Large Scale Commercial Net Zero Energy Buildings, AGC 2013
Mainstreaming Zero: Large Scale Commercial Net Zero Energy Buildings, AGC 2013Mainstreaming Zero: Large Scale Commercial Net Zero Energy Buildings, AGC 2013
Mainstreaming Zero: Large Scale Commercial Net Zero Energy Buildings, AGC 2013Shanti Pless
 
High Performance Building Design Workshop
High Performance Building Design WorkshopHigh Performance Building Design Workshop
High Performance Building Design WorkshopJerry Yudelson
 
American Institute of Architects Committee on the Envrinment
American Institute of Architects Committee on the EnvrinmentAmerican Institute of Architects Committee on the Envrinment
American Institute of Architects Committee on the EnvrinmentCenter for Energy and Environment
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxLisa Cooley, LEED AP
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxssuser5fc1e7
 
GTC_Energy Services_Mexico City
GTC_Energy Services_Mexico CityGTC_Energy Services_Mexico City
GTC_Energy Services_Mexico CityDiana Nash
 
Existing Buildings: Energy Efficiency
Existing Buildings: Energy EfficiencyExisting Buildings: Energy Efficiency
Existing Buildings: Energy Efficiencyjwalleisa
 
1-fmm-11-9-16-jcc-ppt-jw-final-11-8-16.pptx
1-fmm-11-9-16-jcc-ppt-jw-final-11-8-16.pptx1-fmm-11-9-16-jcc-ppt-jw-final-11-8-16.pptx
1-fmm-11-9-16-jcc-ppt-jw-final-11-8-16.pptxSayeedHvac
 
NZC - Olgyay Scaling
NZC - Olgyay ScalingNZC - Olgyay Scaling
NZC - Olgyay ScalingWRONG PERSON
 
Why the EUI in the RFP?
Why the EUI in the RFP?Why the EUI in the RFP?
Why the EUI in the RFP?AdamMcMillen2
 
Advanced Energy Design and Retrofit Guides Summary from the 2013 DOE BTO Peer...
Advanced Energy Design and Retrofit Guides Summary from the 2013 DOE BTO Peer...Advanced Energy Design and Retrofit Guides Summary from the 2013 DOE BTO Peer...
Advanced Energy Design and Retrofit Guides Summary from the 2013 DOE BTO Peer...Shanti Pless
 
Research Support Facility: Three years of net zero operations, occupants, and...
Research Support Facility: Three years of net zero operations, occupants, and...Research Support Facility: Three years of net zero operations, occupants, and...
Research Support Facility: Three years of net zero operations, occupants, and...Shanti Pless
 
Energy Show 2022 - EXEED Outline and Sample Projects
Energy Show 2022 - EXEED Outline and Sample ProjectsEnergy Show 2022 - EXEED Outline and Sample Projects
Energy Show 2022 - EXEED Outline and Sample ProjectsSustainableEnergyAut
 
Green building rating system on des innovations
Green building rating system on des innovationsGreen building rating system on des innovations
Green building rating system on des innovationssaif hasan
 

Similar to Energy Exchange 2015: Track 7 session 5: Energy Performance Based Design Build Delivery at NREL (20)

Mainstreaming Zero: Large Scale Commercial Net Zero Energy Buildings, AGC 2013
Mainstreaming Zero: Large Scale Commercial Net Zero Energy Buildings, AGC 2013Mainstreaming Zero: Large Scale Commercial Net Zero Energy Buildings, AGC 2013
Mainstreaming Zero: Large Scale Commercial Net Zero Energy Buildings, AGC 2013
 
High Performance Building Design Workshop
High Performance Building Design WorkshopHigh Performance Building Design Workshop
High Performance Building Design Workshop
 
American Institute of Architects Committee on the Envrinment
American Institute of Architects Committee on the EnvrinmentAmerican Institute of Architects Committee on the Envrinment
American Institute of Architects Committee on the Envrinment
 
federal reserve.
federal reserve.federal reserve.
federal reserve.
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptx
 
project-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptxproject-delivery-methods-final-for-presentation.pptx
project-delivery-methods-final-for-presentation.pptx
 
GTC_Energy Services_Mexico City
GTC_Energy Services_Mexico CityGTC_Energy Services_Mexico City
GTC_Energy Services_Mexico City
 
Cold-Climate Research Round-Up
Cold-Climate Research Round-UpCold-Climate Research Round-Up
Cold-Climate Research Round-Up
 
Existing Buildings: Energy Efficiency
Existing Buildings: Energy EfficiencyExisting Buildings: Energy Efficiency
Existing Buildings: Energy Efficiency
 
REEP[1]
REEP[1]REEP[1]
REEP[1]
 
Besf building renewal_021815
Besf building renewal_021815Besf building renewal_021815
Besf building renewal_021815
 
1-fmm-11-9-16-jcc-ppt-jw-final-11-8-16.pptx
1-fmm-11-9-16-jcc-ppt-jw-final-11-8-16.pptx1-fmm-11-9-16-jcc-ppt-jw-final-11-8-16.pptx
1-fmm-11-9-16-jcc-ppt-jw-final-11-8-16.pptx
 
NZC - Olgyay Scaling
NZC - Olgyay ScalingNZC - Olgyay Scaling
NZC - Olgyay Scaling
 
Why the EUI in the RFP?
Why the EUI in the RFP?Why the EUI in the RFP?
Why the EUI in the RFP?
 
Advanced Energy Design and Retrofit Guides Summary from the 2013 DOE BTO Peer...
Advanced Energy Design and Retrofit Guides Summary from the 2013 DOE BTO Peer...Advanced Energy Design and Retrofit Guides Summary from the 2013 DOE BTO Peer...
Advanced Energy Design and Retrofit Guides Summary from the 2013 DOE BTO Peer...
 
Cli Grp
Cli GrpCli Grp
Cli Grp
 
Research Support Facility: Three years of net zero operations, occupants, and...
Research Support Facility: Three years of net zero operations, occupants, and...Research Support Facility: Three years of net zero operations, occupants, and...
Research Support Facility: Three years of net zero operations, occupants, and...
 
Energy Show 2022 - EXEED Outline and Sample Projects
Energy Show 2022 - EXEED Outline and Sample ProjectsEnergy Show 2022 - EXEED Outline and Sample Projects
Energy Show 2022 - EXEED Outline and Sample Projects
 
Green building rating system on des innovations
Green building rating system on des innovationsGreen building rating system on des innovations
Green building rating system on des innovations
 
O2ne draft white
O2ne draft whiteO2ne draft white
O2ne draft white
 

More from Shanti Pless

Integrating Energy Efficiency into Advanced Manufacturing of Buildings
Integrating Energy Efficiency into Advanced Manufacturing of BuildingsIntegrating Energy Efficiency into Advanced Manufacturing of Buildings
Integrating Energy Efficiency into Advanced Manufacturing of BuildingsShanti Pless
 
Zero Energy Commercial Buildings: Research For the Next Generation
Zero Energy Commercial Buildings: Research For the Next GenerationZero Energy Commercial Buildings: Research For the Next Generation
Zero Energy Commercial Buildings: Research For the Next GenerationShanti Pless
 
NREL’s Research Support Facility: Making Plug Loads Count
NREL’s Research Support Facility:  Making Plug Loads CountNREL’s Research Support Facility:  Making Plug Loads Count
NREL’s Research Support Facility: Making Plug Loads CountShanti Pless
 
Energy Exchange 2015 Track 3 session 3: High Performance Buildings Operations
Energy Exchange 2015 Track 3 session 3: High Performance Buildings OperationsEnergy Exchange 2015 Track 3 session 3: High Performance Buildings Operations
Energy Exchange 2015 Track 3 session 3: High Performance Buildings OperationsShanti Pless
 
Building Agent Dashboard Development and Use - Presented at haystack connect ...
Building Agent Dashboard Development and Use - Presented at haystack connect ...Building Agent Dashboard Development and Use - Presented at haystack connect ...
Building Agent Dashboard Development and Use - Presented at haystack connect ...Shanti Pless
 
Plug Load Efficiency for Zero Energy Buildings Webinar 1 29 2013
Plug Load Efficiency for Zero Energy Buildings Webinar 1 29 2013Plug Load Efficiency for Zero Energy Buildings Webinar 1 29 2013
Plug Load Efficiency for Zero Energy Buildings Webinar 1 29 2013Shanti Pless
 
Human Side Of Net Zero - Rocky Mountain Green
Human Side Of Net Zero - Rocky Mountain GreenHuman Side Of Net Zero - Rocky Mountain Green
Human Side Of Net Zero - Rocky Mountain GreenShanti Pless
 
Occupant Engaged - A ZEB control concept for engaging occupants
Occupant Engaged -  A ZEB control concept for engaging occupantsOccupant Engaged -  A ZEB control concept for engaging occupants
Occupant Engaged - A ZEB control concept for engaging occupantsShanti Pless
 
50% Savings Advanced Energy Design Guides, ACEEE Summer Study, 2012
50% Savings Advanced Energy Design Guides, ACEEE Summer Study, 201250% Savings Advanced Energy Design Guides, ACEEE Summer Study, 2012
50% Savings Advanced Energy Design Guides, ACEEE Summer Study, 2012Shanti Pless
 
Rebuilding Greensburg to be a Zero Energy City
Rebuilding Greensburg to be a Zero Energy CityRebuilding Greensburg to be a Zero Energy City
Rebuilding Greensburg to be a Zero Energy CityShanti Pless
 
AIA 2013: Facts on the Ground: Testing the Performance of Ft. Carson's Green ...
AIA 2013: Facts on the Ground: Testing the Performance of Ft. Carson's Green ...AIA 2013: Facts on the Ground: Testing the Performance of Ft. Carson's Green ...
AIA 2013: Facts on the Ground: Testing the Performance of Ft. Carson's Green ...Shanti Pless
 

More from Shanti Pless (11)

Integrating Energy Efficiency into Advanced Manufacturing of Buildings
Integrating Energy Efficiency into Advanced Manufacturing of BuildingsIntegrating Energy Efficiency into Advanced Manufacturing of Buildings
Integrating Energy Efficiency into Advanced Manufacturing of Buildings
 
Zero Energy Commercial Buildings: Research For the Next Generation
Zero Energy Commercial Buildings: Research For the Next GenerationZero Energy Commercial Buildings: Research For the Next Generation
Zero Energy Commercial Buildings: Research For the Next Generation
 
NREL’s Research Support Facility: Making Plug Loads Count
NREL’s Research Support Facility:  Making Plug Loads CountNREL’s Research Support Facility:  Making Plug Loads Count
NREL’s Research Support Facility: Making Plug Loads Count
 
Energy Exchange 2015 Track 3 session 3: High Performance Buildings Operations
Energy Exchange 2015 Track 3 session 3: High Performance Buildings OperationsEnergy Exchange 2015 Track 3 session 3: High Performance Buildings Operations
Energy Exchange 2015 Track 3 session 3: High Performance Buildings Operations
 
Building Agent Dashboard Development and Use - Presented at haystack connect ...
Building Agent Dashboard Development and Use - Presented at haystack connect ...Building Agent Dashboard Development and Use - Presented at haystack connect ...
Building Agent Dashboard Development and Use - Presented at haystack connect ...
 
Plug Load Efficiency for Zero Energy Buildings Webinar 1 29 2013
Plug Load Efficiency for Zero Energy Buildings Webinar 1 29 2013Plug Load Efficiency for Zero Energy Buildings Webinar 1 29 2013
Plug Load Efficiency for Zero Energy Buildings Webinar 1 29 2013
 
Human Side Of Net Zero - Rocky Mountain Green
Human Side Of Net Zero - Rocky Mountain GreenHuman Side Of Net Zero - Rocky Mountain Green
Human Side Of Net Zero - Rocky Mountain Green
 
Occupant Engaged - A ZEB control concept for engaging occupants
Occupant Engaged -  A ZEB control concept for engaging occupantsOccupant Engaged -  A ZEB control concept for engaging occupants
Occupant Engaged - A ZEB control concept for engaging occupants
 
50% Savings Advanced Energy Design Guides, ACEEE Summer Study, 2012
50% Savings Advanced Energy Design Guides, ACEEE Summer Study, 201250% Savings Advanced Energy Design Guides, ACEEE Summer Study, 2012
50% Savings Advanced Energy Design Guides, ACEEE Summer Study, 2012
 
Rebuilding Greensburg to be a Zero Energy City
Rebuilding Greensburg to be a Zero Energy CityRebuilding Greensburg to be a Zero Energy City
Rebuilding Greensburg to be a Zero Energy City
 
AIA 2013: Facts on the Ground: Testing the Performance of Ft. Carson's Green ...
AIA 2013: Facts on the Ground: Testing the Performance of Ft. Carson's Green ...AIA 2013: Facts on the Ground: Testing the Performance of Ft. Carson's Green ...
AIA 2013: Facts on the Ground: Testing the Performance of Ft. Carson's Green ...
 

Recently uploaded

Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 

Recently uploaded (20)

Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 

Energy Exchange 2015: Track 7 session 5: Energy Performance Based Design Build Delivery at NREL

  • 1. Phoenix Convention Center • Phoenix, Arizona Goal Setting and Performance Based Contracting Track 7: Building Performance Session 5: Constructing High Performance New Buildings Shanti Pless National Renewable Energy Laboratory August 12, 2015
  • 2. Energy Exchange: Federal Sustainability for the Next Decade Goal Setting and Performance Based Contracting Presenter: Paul Torcellini, NREL Description: Learn to set goals in constructing high performance new buildings and how to maximize the use of performance based contracts to achieve those goals Implementation Lessons and Results Presenter: Shanti Pless, NREL Description: Review lessons learned and results in implementation of practices to best help guarantee building performance. A View from a Contractor Presenter: Phil Macey, JE Dunn Construction Description: Develop an understanding from the contractor’s perspective in understanding the process in designing and constructing high performance new buildings. 2 Session Overview
  • 4. Energy Exchange: Federal Sustainability for the Next Decade Historical Context Pre-2007 – Design-bid-build – Specifications of “exactly” what we wanted – Always struggling to balance the budget with program and architecture and energy 4
  • 5. NREL: Today 2012 aerial, Photo by Sincere/Duncan Studios courtesy of JE Dunn Construction
  • 6. NREL Campus Growth with Design-Build • Procurement process attributes post-2007: – Design-build project delivery with firm fixed price for >$400 Million of new facilities – Specific energy performance requirements in the Request for Proposal (RFP, also referred to as the contract) • RSF I, office example: 25 kBtu/ft2/yr • SEB, guard house example: net zero energy • PUE for datacenter of 1.06 – Energy modeling required to substantiate goals – Energy end-use metering requirement – Voluntary incentive ($) program to ensure measurement and verification outcome has a chance to meet predicted performance 6
  • 7. Research Support Facility Vision • A showcase for sustainable, high-performance design o Incorporates the best in energy efficiency, environmental performance, and advanced controls using a “whole-building” integrated design process • Serves as a model for cost-competitive, high-performance commercial buildings for the nation’s design construction, operation, and financing communities Credit: RNL 7
  • 8. Energy Exchange: Federal Sustainability for the Next Decade Owner Defines Desires Mission Critical: Project cannot succeed without this element Highly Desirable: What the owner wants If Possible: The wish list 8
  • 9. Problem Definition: RFP Objectives HIGHLY DESIRABLE MISSION CRITICAL IF POSSIBLE 9
  • 10. Problem Definition: RFP Objectives • Attain safe work performance/ Safe Design Practices • LEED Platinum • ENERGY STAR “Plus” MISSION CRITICAL 10
  • 11. Problem Definition: RFP Objectives • 800 staff capacity • 25kBTU/sf/year • Architectural integrity • Honor future staff needs • Measurable ASHRAE 90.1 • Support culture and amenities • Expandable building • Ergonomics • Flexible workspace • Support future technologies • Documentation to produce a “How to” manual • “PR” campaign implemented in real- time • Allow secure collaboration with outsiders • Building information modeling • Substantial completion by 2010 HIGHLY DESIRABLE 11
  • 12. Problem Definition: RFP Objectives • Net Zero/design approach • Most energy efficient building in the world • LEED Platinum Plus • ASHRAE 90.1 + 50% • Visual displays of current energy efficiency • Support public tours • Achieve national and global recognition and awards • Support personnel turnover IF POSSIBLE 12
  • 13. Details of 25 kBtu/ft2 in a Contract 1. Set energy goal based on past measured office building research 2. Need to provide normalization for space efficiency 3. Need to provide adjustment for energy use for large external users – data center 4. Calculation method for delivered campus utilities - Didn’t want to let design team “assume” unknown delivered efficiency 5. Benchmark current plug loads and operational schedules 6. Thermal comfort requirements 7. Energy monitoring requirements 8. Unique substantiation requirements 9. Provide ZEB definitions and classification system 13
  • 14. EUI Design Requirements • 25 kBtu/ft2/yr for standard office space occupant density and datacenter loads • Normalized up to 35.1 kBtu/ft2/yr for better space efficiency and to account for full data center load 14
  • 15. Performance-based design-build with absolute energy use requirements • These are NOT bridging documents – Owner has significant input into the preliminary design – Some overlap of A/E costs • These ARE performance specifications – What something must do, not what it must be – Subcontractor must substantiate that the design meets requirements – Owner must not give the subcontractor technical direction No drawings/plans in RFP! • Don’t change your mind Energy Performance Based Design-Build Process 15
  • 16. A value engineering process that adds value 16
  • 17. A value engineering process that adds value 17
  • 19. Acquisition Strategy Results • Created Value Beyond the Budget at Lower Cost and Risk to All Parties • No Claims or Controversy • No Contractor Change Orders • Virtually No Contingency Use for Unknowns or Omissions • Sixteen Months from Shovel to Move-In • Over a year of delivery time saved! • Large Scale Net Zero Energy without increase in first cost • Defined a New National Building Energy Standard • Replicable Acquisition Strategy for Use by Others to Create Their Own Successes! 19
  • 20. How Much Did It Cost? • $259/ft2 construction costs for site work, infrastructure, and building o Includes interiors, furniture, and cabling o Does not include PV, land, or design costs • Third-party-owned power purchase agreement for PV o $29/ft2 or 11% additional cost if NREL had purchased all PV without tax breaks or subsidies (at $5/Watt) 20
  • 21. • Firm fixed price with required energy goals in design-build contract • Integrated architecture and envelope as efficiency measures • Simple and commercially viable • No unique technologies required • Modular precast wall panels with minimal finishes • Optimized glazing area • Repeatable office floorplate • Takes a coordinated effort with the owner (and all user groups), architect, builder, and engineers Replicable – Cost Control Review 21
  • 22. DOE/NREL Research Support Facility RFP Design/Build Requirements: • 50% energy cost savings over ASHRAE 90.1 • 35.1 kBtu/ft2/yr • Net zero energy use • Performance assurance plan with incentives Design/Build Results: • Net zero energy use • 36.4 kBtu/ft2/yr • $259/sqft construction costs 22
  • 23. DOE/NREL RSF 3rd Wing RFP Design/Build Requirements: • 27 kBtu/ft2/yr • 50% Energy Cost Savings • Performance assurance plan with incentives Design/Build Results: • 20 kBtu/ft2/yr measured • Demonstration of additional cost savings, energy efficiency, and schedule gains over phase 1 • 17% more efficient than the RSF • Cost savings of 5% ($14/ft2 cheaper) 23
  • 24. DOE/NREL 1800 Car Staff Parking Garage Design/Build Requirements: • 0.5 kBtu/ft2 • 175 kBtu/stall • Net-zero energy Site Entrance Building Design/Build Results: • 90% Energy savings • 138 kBtu/parking stall • $14,172 per parking space • $15,500 to $24,500 for typical parking space in Denver area
  • 25. DOE/NREL Cafeteria RFP Design/Build Requirements: • 35% energy cost savings over ASHRAE 90.1 • Best in class commercial kitchen equipment • Performance assurance plan with incentives • LEED Gold Design/Build Results: • 36% energy savings and Platinum • Demonstration of max efficiency in a commercial kitchen using energy performance based design/build delivery and procurement methods • Continuous improvement requirements in vendor contract to ensure performance assurance
  • 26. DOE/NREL Energy Systems Integration Facility Design/Build Requirements: • 27 kBtu/ft2 Office wing • 1.06 PUE Super computer • No mechanical cooling • Waste heat reuse • 30% savings for all labs • LEED Gold Design/Build Results: • 26 kBtu/ft2 Office wing • World class efficient super computer • 1.05 PUE • 36% savings in labs • LEED Platinum 26
  • 28. World Class Efficiency is Possible Within Our Construction Budgets! • Include absolute EUI requirements – Set up acquisition process to “force” integrated design – Subsystem measureable performance requirements when needed • Energy modeling guides conceptual design decisions • Architecture and envelope are also efficiency measures – Unwavering commitment to problem statement • Unleash power of design/build team of experts to meet your needs – true value engineering Spend the time to get the RFP right 28
  • 29. How-to Guides for Cost Control Guide: – https://buildingdata.energy.gov/cbrd/resource/1655 – Discusses the recommended strategies – Pairs strategies with industry examples of success in ZEBs and other high-performance buildings where possible – Describes how to balance key decision-making factors – Provides quick reference tables to help building owners and project teams apply the recommended strategies to their projects. • Fact sheet: – https://buildingdata.energy.gov/cbrd/resource/1654 – Highlights key ideas from the guide – Directs readers to the guide for more details.
  • 30. Energy Exchange: Federal Sustainability for the Next Decade https://buildingdata.energy.gov/cbrd/energy_based_acquisition/
  • 31. Scale performance- based procurement 100 buildings three years This material is based upon work supported by the Department of Energy, Office of Energy Efficiency and Renewable Energy (EERE), under Award Number DE-EE0007068.
  • 32. Extended partnerships and stakeholder group forming now TEAM Seventhwave National Renewable Energy Laboratory Institute for Sustainable Energy UTILITY PARTNERS ComEd Eversource United Illuminating OWNER PARTNERS University of Chicago Lend Lease Photos courtesy of University of Chicago