SlideShare a Scribd company logo
1 of 3
Download to read offline
I N T E R N A T I O N A L E R O S I O N C O N T R O L A S S O C I A T I O N
JANUARY 2013 | VOLUME 7 • ISSUE 1 | www.ieca.org
ENVIRONMENTAL
CONNECTION 2013
PRE-CONFERENCE
PLANNING GUIDE
STARTS ON PAGE 17
POLYMER SYSTEM
ENSURES CLEANWATER
FOR HYDROELECTRIC
PROJECT
AMENDMENTSTO
PREVENT SOIL EROSION
EROSION CONTROL
& SPANISH OLIVES:
A FIELDTOUR
AWARD-WINNING MINE
RECLAMATION PROJECT
LETSTHE LAND GIVE BACK
WOOD-BASED MULCH:
AREYOU COVERED?
INSIDE
NONPROFIT
ORG
USPOSTAGE
PAID
CPCMAIL
InternationalErosionControlAssociation
3401QuebecSt.Ste.3500
Denver,CO80207
E N V I R O N M E N T A L
PlanyourEnvironmentalConnection2013
tripwithourPre-ConferencePlanning
Guide,startingonpage17.
28 • ENVIRONMENTAL CONNECTION
Award-Winning Mine Reclamation
Project Lets the Land Give Back:
Part One of Two
814 Solutions, LLC was responsible for the
following on the reclamation project: creation,
implementation and maintenance of the SWPPP;
harvesting all plant and plug material; transporta-
tion and care of all plant material throughout the
project; soil analysis; amendment application and
incorporation; seed bed preparation; seeding and
mulching. Construction on the project began in
March 2012, and most items were completed in
October 2012. Cottonwood poles will be planted
in early Spring 2013.
The project was performed as a “time and
materials project” with budgets set for each line
item, so that production rates, material costs, labor
hours and total project costs could be tracked
throughout the project. To lower the environmen-
tal footprint of the project and to stretch the fund-
ing dollars, all material that could be repurposed
from onsite materials was considered for use.
Site Challenges
To accommodate the dramatically different
changes in soil composition on the site, soil analy-
sis was performed on small areas to accurately
determine the need for soil amendments, com-
post material size variations and engineered wood
strand material application rates, depending on the
slope of finished areas. Since the project is located
inside a narrow canyon, there was limited space for
construction activities and material stockpiling.
In addition to limited space, there are a number
of archeological sites in the area that had to be
considered when planning construction, material
harvesting and movement. 814 Solutions, LLC
partnered with Kiewit Construction on areas to
be harvested, areas to be amended and areas to be
seeded, and the successful partnership was a sig-
nificant factor in accomplishing the project in such
a short time frame.
The grading and drainage for the site used
a geomorphic reclamation design with the goal of
returning the area to its natural state before any
mining began. The access road in the area was
removed during construction and moved out of
the way of Dillon Creek, replacing the creek to its
natural state. Having limited access to most areas
of the site was managed with careful transition
onto a new access road that was constructed so
that it would not interfere with the creek.
Letting the Land Give Back
Over the past decade, wood material had
been pulled from the Vermejo Park Ranch and
stockpiled at Western Wood Products to sell as fin-
ished lumber products. The process of creating fin-
ished lumber creates waste wood material, which
814 Solutions planned to use as compost material
for the seeding. After the project was awarded, 814
Solutions worked with Western Wood Products to
use a small area on their facility to have the mate-
rial composted to meet site specifications for each
area to be composted. In order to account for the
unique soil composition from each area, the com-
post material size was modified to include small
to large material, based on the desired timeframes
and speed at which the material would compost.
review
PEER
Salem (Sam) Stribling is the
Chief Executive Officer of 814
Solutions, LLC, headquartered
out of Albuquerque New Mexi-
co. 814 Solutions, LLC provides
seeding, slope stabilization, dust
control and environmental com-
pliance as some of their services
to their clients throughout the
Southwest and Rocky Moun-
tains. Mr. Stribling graduated
from the Anderson School of
BusinessattheUniversityofNew
Mexico with Bachelor’s degrees
in Marketing, Production and
Operations Management, and
Entrepreneurial Studies. 814
Solutions,LLC can be reachedat
505-872-0846 or by email at:
Sam@814solutions.com.
Plantings ready for transport after being
harvested onsite.
The Swastika Mine and Dutchman Canyon project is located in Raton, New Mexico on a portion of the Vermejo Park Ranch. The scope of the
project’s contract involved reclaiming two abandoned mine areas - one called Brilliant Number Two (previously known as the Swastika Mine, but
renamed after World War II) and the Dutchman Canyon Mine. The name “Brilliant” is said to have been inspired by the unusually lustrous sheen of
coal in the area. The project was administered by the Abandoned Mine Land Program, which is part of the Energy Minerals and Natural Resources
Department of the U.S. Department of Interior. As part of the reclamation project, 400,000 cubic yards of soil and mine waste material were used to
create stable landforms to restore pre-mining meanders in the Dillon Canyon Creek which were removed during the mines’ construction.
Volume 7• Issue1 • 29
The smaller pieces would compost faster, and the larger pieces would
compost much slower and provide material for many years.
In addition to using the wood waste material as compost, 814
Solutions used the material as media for the erosion control logs that
were placed onsite as BMPs.
The repurposing of the wood waste material made sense for
814 Solutions, placing all compost and erosion control logs needed
within ten miles of the site. The repurposing also made sense for the
project administrator, since the material already was acclimated to
site conditions, was relatively free from non-native plant material
and was being pro-
vided at a sig-
nificantly reduced
cost. In addition
to the above-men-
tioned benefits,
the Vermejo Park
Ranch liked the
idea as well, since
they knew that the
land was giving
back what it was
able to use from the
last ten years. The material that was chipped and composted was
placed less than ten miles from the location where it orginally had
grown.
Since the site soil composition was so different at each area,
there was a strong need to modify the fertilizers used for each area.
To meet this challenge, large quantities of lime, gypsum, sulphur
and nitrogen were ordered to be placed at each area, as indicated by
the soil analysis results. Negotiations were made with each supplier
for the return of any unused material, which lowered the project cost
and ensured that each area received exactly what it needed. For areas
that needed material, the gob located onsite was used as a fill material
and then capped with two feet of clean fill as topsoil. The final cap
was tested to make sure that any amendments needed for optimal
growing conditions were met.
Harvesting Onsite
To eliminate
the need to pur-
chase plant material,
shrubs, poles and/
or wetland plugs, all
material was har-
vested onsite from
areas that were over-
grown or areas that
needed to undergo
modifications, such as
the access road and old stream bed. All material was collected prior
to the onset of other construction activities and stockpiled in areas
that were out of the way for planting at later dates. A shade struc-
ture was created to provide shade for all of the transplants, and a
watering system was installed. All material successfully was planted
once the areas were finished. The total cost per plant was less than
$200.00 a plant, a figure that takes into consideration harvesting,
transportation, nursery
(shade structures, wire
baskets, planting pots,
soils, amendments
and fertilizers), water-
ing and planting - a
tremendous cost sav-
ings to the project. The
plan and process pro-
vided was excellent and
resulted in less than
four percent mortality of the plants.
The Mining and Minerals Division of the New Mexico Energy,
MineralsandNaturalResourcesDepartment(EMNRD)presentedthe
2012 Excellence in Reclamation
Award to 814 Solutions, LLC
for this project on September 6,
2012 at the New Mexico Mining
Association Convention held in
Las Cruces, New Mexico. Part
Two of this article will be fea-
tured in the next issue and will
highlight updated results of the
plantings.
Volume 7• Issue 1 • 29
Kiewit Construction and 814 Solutions, LLC
crews shaping the Dillon channel realignment.
Note the large pile of gob in the background,
which gives a good perspective on the scale of the
814 Solutions, LLC’s talented crew
and specialized equipment.
Crews installing wetland plugs, shaping the
channel and prepping for turf reinforcement
mat and engineered wood strand material.
Aged wood material processing area. All
material used was repurposed from wood that
was harvested from the Vermejo Park Ranch
over the course of several years.
STORMWATER
STORAGE MODULES
• Easy to Install & Clean
• 97% Void Space
• High Strength
• Stackable
• 18, 24, 30 or
36" Heights
Phone: 610-236-1100
Email: stormwater@brentw.com
Web: www.brentwoodprocess.com
As a follow up to this project, there is an interactive online
community board located at www.814solutions.com/commu-
nityshare. Get involved, ask questions, make recommendations
and see additional photos of the site as it matures!

More Related Content

What's hot

Pumice Products and LEED Certification
Pumice Products and LEED CertificationPumice Products and LEED Certification
Pumice Products and LEED CertificationHess Pumice Products
 
EMIN SG - Geoceldas Envirogrid Caso Rio Guayabo Panama (ingles)
EMIN SG - Geoceldas Envirogrid Caso Rio Guayabo Panama (ingles)EMIN SG - Geoceldas Envirogrid Caso Rio Guayabo Panama (ingles)
EMIN SG - Geoceldas Envirogrid Caso Rio Guayabo Panama (ingles)EMIN Sistemas Geotecnicos
 
EarthBalance Projects
EarthBalance ProjectsEarthBalance Projects
EarthBalance Projectsmitch2372
 
EMIN SG - Geoceldas Envirogrid Caso El Valle del Anton (ingles)
EMIN SG - Geoceldas Envirogrid Caso El Valle del Anton (ingles)EMIN SG - Geoceldas Envirogrid Caso El Valle del Anton (ingles)
EMIN SG - Geoceldas Envirogrid Caso El Valle del Anton (ingles)EMIN Sistemas Geotecnicos
 
Andrew Davies Portfolio 2019
Andrew Davies Portfolio 2019Andrew Davies Portfolio 2019
Andrew Davies Portfolio 2019Andrew Davies
 
CA: Bay-Friendly Rating Manual for Civic and Commerical Landscapes
CA: Bay-Friendly Rating Manual for Civic and Commerical LandscapesCA: Bay-Friendly Rating Manual for Civic and Commerical Landscapes
CA: Bay-Friendly Rating Manual for Civic and Commerical LandscapesSotirakou964
 
Orf superfund site leed certified
Orf superfund site leed certifiedOrf superfund site leed certified
Orf superfund site leed certifiedJimmy Carchietta
 
Opus Sustainable
Opus SustainableOpus Sustainable
Opus Sustainablewinstonh
 
CA: Bay-Friendly Rating Manual for New Homes Landscapes
CA: Bay-Friendly Rating Manual for New Homes LandscapesCA: Bay-Friendly Rating Manual for New Homes Landscapes
CA: Bay-Friendly Rating Manual for New Homes LandscapesSotirakou964
 
IN: Green Infrastructure and Low Impact Development
IN: Green Infrastructure and Low Impact DevelopmentIN: Green Infrastructure and Low Impact Development
IN: Green Infrastructure and Low Impact DevelopmentSotirakou964
 
Stephen O'Connor - Curriculum Vitae - July 2016
Stephen O'Connor - Curriculum Vitae - July 2016Stephen O'Connor - Curriculum Vitae - July 2016
Stephen O'Connor - Curriculum Vitae - July 2016Steve OConnor
 
Parking Forest Questions from the City of Gresham
Parking Forest Questions from the City of GreshamParking Forest Questions from the City of Gresham
Parking Forest Questions from the City of GreshamMaria Cahill
 
GreenLight Completes 43-101 on Heavy REE, Base Metal Property
GreenLight Completes 43-101 on Heavy REE, Base Metal PropertyGreenLight Completes 43-101 on Heavy REE, Base Metal Property
GreenLight Completes 43-101 on Heavy REE, Base Metal PropertyChristopher R Anderson
 
Organic Soil and Water Management at the Arlington Agricultural Research Station
Organic Soil and Water Management at the Arlington Agricultural Research StationOrganic Soil and Water Management at the Arlington Agricultural Research Station
Organic Soil and Water Management at the Arlington Agricultural Research StationUniversity of Wisconsin-Madison
 
Empire landfill drainage_channel[1]
Empire landfill drainage_channel[1]Empire landfill drainage_channel[1]
Empire landfill drainage_channel[1]rsturgpe
 
BBarton resume
BBarton resumeBBarton resume
BBarton resumeBen Barton
 
Mini projects for_civil_engineering_(3)_(1) (1) (1)
Mini projects for_civil_engineering_(3)_(1) (1) (1)Mini projects for_civil_engineering_(3)_(1) (1) (1)
Mini projects for_civil_engineering_(3)_(1) (1) (1)arun naga sai
 
Ecological Enhancement of Coastal and Marine Infrastructures
Ecological Enhancement of Coastal and Marine InfrastructuresEcological Enhancement of Coastal and Marine Infrastructures
Ecological Enhancement of Coastal and Marine InfrastructuresStephanie Camay
 
CA: Bay-Friendly Landscapes Case Studies - Ohlone College Newark Center for H...
CA: Bay-Friendly Landscapes Case Studies - Ohlone College Newark Center for H...CA: Bay-Friendly Landscapes Case Studies - Ohlone College Newark Center for H...
CA: Bay-Friendly Landscapes Case Studies - Ohlone College Newark Center for H...Sotirakou964
 

What's hot (20)

Pumice Products and LEED Certification
Pumice Products and LEED CertificationPumice Products and LEED Certification
Pumice Products and LEED Certification
 
EMIN SG - Geoceldas Envirogrid Caso Rio Guayabo Panama (ingles)
EMIN SG - Geoceldas Envirogrid Caso Rio Guayabo Panama (ingles)EMIN SG - Geoceldas Envirogrid Caso Rio Guayabo Panama (ingles)
EMIN SG - Geoceldas Envirogrid Caso Rio Guayabo Panama (ingles)
 
EarthBalance Projects
EarthBalance ProjectsEarthBalance Projects
EarthBalance Projects
 
EMIN SG - Geoceldas Envirogrid Caso El Valle del Anton (ingles)
EMIN SG - Geoceldas Envirogrid Caso El Valle del Anton (ingles)EMIN SG - Geoceldas Envirogrid Caso El Valle del Anton (ingles)
EMIN SG - Geoceldas Envirogrid Caso El Valle del Anton (ingles)
 
Andrew Davies Portfolio 2019
Andrew Davies Portfolio 2019Andrew Davies Portfolio 2019
Andrew Davies Portfolio 2019
 
CA: Bay-Friendly Rating Manual for Civic and Commerical Landscapes
CA: Bay-Friendly Rating Manual for Civic and Commerical LandscapesCA: Bay-Friendly Rating Manual for Civic and Commerical Landscapes
CA: Bay-Friendly Rating Manual for Civic and Commerical Landscapes
 
Orf superfund site leed certified
Orf superfund site leed certifiedOrf superfund site leed certified
Orf superfund site leed certified
 
Opus Sustainable
Opus SustainableOpus Sustainable
Opus Sustainable
 
CA: Bay-Friendly Rating Manual for New Homes Landscapes
CA: Bay-Friendly Rating Manual for New Homes LandscapesCA: Bay-Friendly Rating Manual for New Homes Landscapes
CA: Bay-Friendly Rating Manual for New Homes Landscapes
 
IN: Green Infrastructure and Low Impact Development
IN: Green Infrastructure and Low Impact DevelopmentIN: Green Infrastructure and Low Impact Development
IN: Green Infrastructure and Low Impact Development
 
Stephen O'Connor - Curriculum Vitae - July 2016
Stephen O'Connor - Curriculum Vitae - July 2016Stephen O'Connor - Curriculum Vitae - July 2016
Stephen O'Connor - Curriculum Vitae - July 2016
 
Parking Forest Questions from the City of Gresham
Parking Forest Questions from the City of GreshamParking Forest Questions from the City of Gresham
Parking Forest Questions from the City of Gresham
 
GreenLight Completes 43-101 on Heavy REE, Base Metal Property
GreenLight Completes 43-101 on Heavy REE, Base Metal PropertyGreenLight Completes 43-101 on Heavy REE, Base Metal Property
GreenLight Completes 43-101 on Heavy REE, Base Metal Property
 
Organic Soil and Water Management at the Arlington Agricultural Research Station
Organic Soil and Water Management at the Arlington Agricultural Research StationOrganic Soil and Water Management at the Arlington Agricultural Research Station
Organic Soil and Water Management at the Arlington Agricultural Research Station
 
Empire landfill drainage_channel[1]
Empire landfill drainage_channel[1]Empire landfill drainage_channel[1]
Empire landfill drainage_channel[1]
 
BBarton resume
BBarton resumeBBarton resume
BBarton resume
 
SFPR-Project-Profile_0
SFPR-Project-Profile_0SFPR-Project-Profile_0
SFPR-Project-Profile_0
 
Mini projects for_civil_engineering_(3)_(1) (1) (1)
Mini projects for_civil_engineering_(3)_(1) (1) (1)Mini projects for_civil_engineering_(3)_(1) (1) (1)
Mini projects for_civil_engineering_(3)_(1) (1) (1)
 
Ecological Enhancement of Coastal and Marine Infrastructures
Ecological Enhancement of Coastal and Marine InfrastructuresEcological Enhancement of Coastal and Marine Infrastructures
Ecological Enhancement of Coastal and Marine Infrastructures
 
CA: Bay-Friendly Landscapes Case Studies - Ohlone College Newark Center for H...
CA: Bay-Friendly Landscapes Case Studies - Ohlone College Newark Center for H...CA: Bay-Friendly Landscapes Case Studies - Ohlone College Newark Center for H...
CA: Bay-Friendly Landscapes Case Studies - Ohlone College Newark Center for H...
 

Viewers also liked

BOSTON MARATHON 2016
BOSTON MARATHON 2016BOSTON MARATHON 2016
BOSTON MARATHON 2016McKensy Vogt
 
Ohio Supreme Court Decision: Lutz v. Chesapeake Appalachia
Ohio Supreme Court Decision: Lutz v. Chesapeake AppalachiaOhio Supreme Court Decision: Lutz v. Chesapeake Appalachia
Ohio Supreme Court Decision: Lutz v. Chesapeake AppalachiaMarcellus Drilling News
 
профессия – устный переводчик коломийцева
профессия – устный переводчик коломийцевапрофессия – устный переводчик коломийцева
профессия – устный переводчик коломийцеваAnna Kolomiitseva
 
NEA Focus - September 2016 (print final)
NEA Focus - September 2016 (print final)NEA Focus - September 2016 (print final)
NEA Focus - September 2016 (print final)Laura McVeigh
 
Good Night in French - Easy French Lessons
Good Night in French - Easy French LessonsGood Night in French - Easy French Lessons
Good Night in French - Easy French LessonsDavid Teamara
 
Carotenoids retention in leafy vegetables based on cooking methods
Carotenoids retention in leafy vegetables based on cooking methodsCarotenoids retention in leafy vegetables based on cooking methods
Carotenoids retention in leafy vegetables based on cooking methodsRuna La-Ela
 
متسلسلة تايلور وماكلورين ملخص
 متسلسلة تايلور وماكلورين ملخص متسلسلة تايلور وماكلورين ملخص
متسلسلة تايلور وماكلورين ملخصyaser karam
 

Viewers also liked (14)

Composicion cony
Composicion conyComposicion cony
Composicion cony
 
BOSTON MARATHON 2016
BOSTON MARATHON 2016BOSTON MARATHON 2016
BOSTON MARATHON 2016
 
Idioms
Idioms Idioms
Idioms
 
Erdoitzako andramariak mañarian
Erdoitzako andramariak mañarianErdoitzako andramariak mañarian
Erdoitzako andramariak mañarian
 
Ohio Supreme Court Decision: Lutz v. Chesapeake Appalachia
Ohio Supreme Court Decision: Lutz v. Chesapeake AppalachiaOhio Supreme Court Decision: Lutz v. Chesapeake Appalachia
Ohio Supreme Court Decision: Lutz v. Chesapeake Appalachia
 
профессия – устный переводчик коломийцева
профессия – устный переводчик коломийцевапрофессия – устный переводчик коломийцева
профессия – устный переводчик коломийцева
 
NEA Focus - September 2016 (print final)
NEA Focus - September 2016 (print final)NEA Focus - September 2016 (print final)
NEA Focus - September 2016 (print final)
 
1. intro economía 2do parcial
1. intro economía     2do parcial1. intro economía     2do parcial
1. intro economía 2do parcial
 
Good Night in French - Easy French Lessons
Good Night in French - Easy French LessonsGood Night in French - Easy French Lessons
Good Night in French - Easy French Lessons
 
Idioms
Idioms Idioms
Idioms
 
Enhanging bifacial PV modeling with ray-tracing
Enhanging bifacial PV modeling with ray-tracingEnhanging bifacial PV modeling with ray-tracing
Enhanging bifacial PV modeling with ray-tracing
 
Carotenoids retention in leafy vegetables based on cooking methods
Carotenoids retention in leafy vegetables based on cooking methodsCarotenoids retention in leafy vegetables based on cooking methods
Carotenoids retention in leafy vegetables based on cooking methods
 
متسلسلة تايلور وماكلورين ملخص
 متسلسلة تايلور وماكلورين ملخص متسلسلة تايلور وماكلورين ملخص
متسلسلة تايلور وماكلورين ملخص
 
Hoja de vida beimar sanchez
Hoja de vida beimar sanchezHoja de vida beimar sanchez
Hoja de vida beimar sanchez
 

Similar to Environmental Connection - January 2013 - Vol. 7 - Issue 1 - cover plus pages 28-29

AAEE E3Competition-Winners-2002
AAEE E3Competition-Winners-2002AAEE E3Competition-Winners-2002
AAEE E3Competition-Winners-2002Dennis Palalay
 
TerraCure Chosen for Oil Site Remediation in Louisiana - International Dredgi...
TerraCure Chosen for Oil Site Remediation in Louisiana - International Dredgi...TerraCure Chosen for Oil Site Remediation in Louisiana - International Dredgi...
TerraCure Chosen for Oil Site Remediation in Louisiana - International Dredgi...mbehan
 
Kaitlyn_Fulton_Portfolio
Kaitlyn_Fulton_PortfolioKaitlyn_Fulton_Portfolio
Kaitlyn_Fulton_PortfolioKaitlyn Fulton
 
Land, Water, People: New Parks in Practice
Land, Water, People: New Parks in PracticeLand, Water, People: New Parks in Practice
Land, Water, People: New Parks in PracticeRiverFirst Initiative
 
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012Erin Vieira
 
WS_May_News Q1 2015 Final
WS_May_News Q1 2015 FinalWS_May_News Q1 2015 Final
WS_May_News Q1 2015 FinalJim Jones
 
Drill Bit Manufacturer Cuts Water Use by 88 Percent
Drill Bit Manufacturer Cuts Water Use by 88 PercentDrill Bit Manufacturer Cuts Water Use by 88 Percent
Drill Bit Manufacturer Cuts Water Use by 88 PercentEric851q
 
Port lavaca desalination study
Port lavaca desalination studyPort lavaca desalination study
Port lavaca desalination studyJeffrey Pickett
 
OR: Portland: Multnomah Building Green Roof
OR: Portland: Multnomah Building Green RoofOR: Portland: Multnomah Building Green Roof
OR: Portland: Multnomah Building Green RoofSotirakou964
 
Jamaica bay resiliency
Jamaica bay resiliencyJamaica bay resiliency
Jamaica bay resiliencyecowatchers
 
GreenSquareProjectPresentation_optimized
GreenSquareProjectPresentation_optimizedGreenSquareProjectPresentation_optimized
GreenSquareProjectPresentation_optimizedJose Calderon Garcia
 
Project profile brownfield
Project profile brownfieldProject profile brownfield
Project profile brownfieldShannonCrook
 
Coastal Landscapes and How they Must Adapt to Climate Change
Coastal Landscapes and How they Must Adapt to Climate ChangeCoastal Landscapes and How they Must Adapt to Climate Change
Coastal Landscapes and How they Must Adapt to Climate ChangeCarter Craft
 
Swim Drink Fish Canada submission for relicensing written hearing for the Del...
Swim Drink Fish Canada submission for relicensing written hearing for the Del...Swim Drink Fish Canada submission for relicensing written hearing for the Del...
Swim Drink Fish Canada submission for relicensing written hearing for the Del...LOWaterkeeper
 
2014: Designing Dredge - Reconsidering the Toledo Riverfront
2014: Designing Dredge - Reconsidering the Toledo Riverfront2014: Designing Dredge - Reconsidering the Toledo Riverfront
2014: Designing Dredge - Reconsidering the Toledo Riverfrontnorthcoastdesigncompetition
 

Similar to Environmental Connection - January 2013 - Vol. 7 - Issue 1 - cover plus pages 28-29 (20)

AAEE E3Competition-Winners-2002
AAEE E3Competition-Winners-2002AAEE E3Competition-Winners-2002
AAEE E3Competition-Winners-2002
 
TerraCure Chosen for Oil Site Remediation in Louisiana - International Dredgi...
TerraCure Chosen for Oil Site Remediation in Louisiana - International Dredgi...TerraCure Chosen for Oil Site Remediation in Louisiana - International Dredgi...
TerraCure Chosen for Oil Site Remediation in Louisiana - International Dredgi...
 
Kaitlyn_Fulton_Portfolio
Kaitlyn_Fulton_PortfolioKaitlyn_Fulton_Portfolio
Kaitlyn_Fulton_Portfolio
 
Land, Water, People: New Parks in Practice
Land, Water, People: New Parks in PracticeLand, Water, People: New Parks in Practice
Land, Water, People: New Parks in Practice
 
Emc²
Emc²Emc²
Emc²
 
BSantelik_resume
BSantelik_resumeBSantelik_resume
BSantelik_resume
 
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
 
WS_May_News Q1 2015 Final
WS_May_News Q1 2015 FinalWS_May_News Q1 2015 Final
WS_May_News Q1 2015 Final
 
Drill Bit Manufacturer Cuts Water Use by 88 Percent
Drill Bit Manufacturer Cuts Water Use by 88 PercentDrill Bit Manufacturer Cuts Water Use by 88 Percent
Drill Bit Manufacturer Cuts Water Use by 88 Percent
 
Port lavaca desalination study
Port lavaca desalination studyPort lavaca desalination study
Port lavaca desalination study
 
OR: Portland: Multnomah Building Green Roof
OR: Portland: Multnomah Building Green RoofOR: Portland: Multnomah Building Green Roof
OR: Portland: Multnomah Building Green Roof
 
Jamaica bay resiliency
Jamaica bay resiliencyJamaica bay resiliency
Jamaica bay resiliency
 
GreenSquareProjectPresentation_optimized
GreenSquareProjectPresentation_optimizedGreenSquareProjectPresentation_optimized
GreenSquareProjectPresentation_optimized
 
Orlando 2015
Orlando 2015Orlando 2015
Orlando 2015
 
Project profile brownfield
Project profile brownfieldProject profile brownfield
Project profile brownfield
 
Maintaining Rain Gardens: Lessons Learned from Kansas State University
Maintaining Rain Gardens: Lessons Learned from Kansas State UniversityMaintaining Rain Gardens: Lessons Learned from Kansas State University
Maintaining Rain Gardens: Lessons Learned from Kansas State University
 
Coastal Landscapes and How they Must Adapt to Climate Change
Coastal Landscapes and How they Must Adapt to Climate ChangeCoastal Landscapes and How they Must Adapt to Climate Change
Coastal Landscapes and How they Must Adapt to Climate Change
 
Drainage Salvation-JRiopelle
Drainage Salvation-JRiopelleDrainage Salvation-JRiopelle
Drainage Salvation-JRiopelle
 
Swim Drink Fish Canada submission for relicensing written hearing for the Del...
Swim Drink Fish Canada submission for relicensing written hearing for the Del...Swim Drink Fish Canada submission for relicensing written hearing for the Del...
Swim Drink Fish Canada submission for relicensing written hearing for the Del...
 
2014: Designing Dredge - Reconsidering the Toledo Riverfront
2014: Designing Dredge - Reconsidering the Toledo Riverfront2014: Designing Dredge - Reconsidering the Toledo Riverfront
2014: Designing Dredge - Reconsidering the Toledo Riverfront
 

Environmental Connection - January 2013 - Vol. 7 - Issue 1 - cover plus pages 28-29

  • 1. I N T E R N A T I O N A L E R O S I O N C O N T R O L A S S O C I A T I O N JANUARY 2013 | VOLUME 7 • ISSUE 1 | www.ieca.org ENVIRONMENTAL CONNECTION 2013 PRE-CONFERENCE PLANNING GUIDE STARTS ON PAGE 17 POLYMER SYSTEM ENSURES CLEANWATER FOR HYDROELECTRIC PROJECT AMENDMENTSTO PREVENT SOIL EROSION EROSION CONTROL & SPANISH OLIVES: A FIELDTOUR AWARD-WINNING MINE RECLAMATION PROJECT LETSTHE LAND GIVE BACK WOOD-BASED MULCH: AREYOU COVERED? INSIDE NONPROFIT ORG USPOSTAGE PAID CPCMAIL InternationalErosionControlAssociation 3401QuebecSt.Ste.3500 Denver,CO80207 E N V I R O N M E N T A L PlanyourEnvironmentalConnection2013 tripwithourPre-ConferencePlanning Guide,startingonpage17.
  • 2. 28 • ENVIRONMENTAL CONNECTION Award-Winning Mine Reclamation Project Lets the Land Give Back: Part One of Two 814 Solutions, LLC was responsible for the following on the reclamation project: creation, implementation and maintenance of the SWPPP; harvesting all plant and plug material; transporta- tion and care of all plant material throughout the project; soil analysis; amendment application and incorporation; seed bed preparation; seeding and mulching. Construction on the project began in March 2012, and most items were completed in October 2012. Cottonwood poles will be planted in early Spring 2013. The project was performed as a “time and materials project” with budgets set for each line item, so that production rates, material costs, labor hours and total project costs could be tracked throughout the project. To lower the environmen- tal footprint of the project and to stretch the fund- ing dollars, all material that could be repurposed from onsite materials was considered for use. Site Challenges To accommodate the dramatically different changes in soil composition on the site, soil analy- sis was performed on small areas to accurately determine the need for soil amendments, com- post material size variations and engineered wood strand material application rates, depending on the slope of finished areas. Since the project is located inside a narrow canyon, there was limited space for construction activities and material stockpiling. In addition to limited space, there are a number of archeological sites in the area that had to be considered when planning construction, material harvesting and movement. 814 Solutions, LLC partnered with Kiewit Construction on areas to be harvested, areas to be amended and areas to be seeded, and the successful partnership was a sig- nificant factor in accomplishing the project in such a short time frame. The grading and drainage for the site used a geomorphic reclamation design with the goal of returning the area to its natural state before any mining began. The access road in the area was removed during construction and moved out of the way of Dillon Creek, replacing the creek to its natural state. Having limited access to most areas of the site was managed with careful transition onto a new access road that was constructed so that it would not interfere with the creek. Letting the Land Give Back Over the past decade, wood material had been pulled from the Vermejo Park Ranch and stockpiled at Western Wood Products to sell as fin- ished lumber products. The process of creating fin- ished lumber creates waste wood material, which 814 Solutions planned to use as compost material for the seeding. After the project was awarded, 814 Solutions worked with Western Wood Products to use a small area on their facility to have the mate- rial composted to meet site specifications for each area to be composted. In order to account for the unique soil composition from each area, the com- post material size was modified to include small to large material, based on the desired timeframes and speed at which the material would compost. review PEER Salem (Sam) Stribling is the Chief Executive Officer of 814 Solutions, LLC, headquartered out of Albuquerque New Mexi- co. 814 Solutions, LLC provides seeding, slope stabilization, dust control and environmental com- pliance as some of their services to their clients throughout the Southwest and Rocky Moun- tains. Mr. Stribling graduated from the Anderson School of BusinessattheUniversityofNew Mexico with Bachelor’s degrees in Marketing, Production and Operations Management, and Entrepreneurial Studies. 814 Solutions,LLC can be reachedat 505-872-0846 or by email at: Sam@814solutions.com. Plantings ready for transport after being harvested onsite. The Swastika Mine and Dutchman Canyon project is located in Raton, New Mexico on a portion of the Vermejo Park Ranch. The scope of the project’s contract involved reclaiming two abandoned mine areas - one called Brilliant Number Two (previously known as the Swastika Mine, but renamed after World War II) and the Dutchman Canyon Mine. The name “Brilliant” is said to have been inspired by the unusually lustrous sheen of coal in the area. The project was administered by the Abandoned Mine Land Program, which is part of the Energy Minerals and Natural Resources Department of the U.S. Department of Interior. As part of the reclamation project, 400,000 cubic yards of soil and mine waste material were used to create stable landforms to restore pre-mining meanders in the Dillon Canyon Creek which were removed during the mines’ construction.
  • 3. Volume 7• Issue1 • 29 The smaller pieces would compost faster, and the larger pieces would compost much slower and provide material for many years. In addition to using the wood waste material as compost, 814 Solutions used the material as media for the erosion control logs that were placed onsite as BMPs. The repurposing of the wood waste material made sense for 814 Solutions, placing all compost and erosion control logs needed within ten miles of the site. The repurposing also made sense for the project administrator, since the material already was acclimated to site conditions, was relatively free from non-native plant material and was being pro- vided at a sig- nificantly reduced cost. In addition to the above-men- tioned benefits, the Vermejo Park Ranch liked the idea as well, since they knew that the land was giving back what it was able to use from the last ten years. The material that was chipped and composted was placed less than ten miles from the location where it orginally had grown. Since the site soil composition was so different at each area, there was a strong need to modify the fertilizers used for each area. To meet this challenge, large quantities of lime, gypsum, sulphur and nitrogen were ordered to be placed at each area, as indicated by the soil analysis results. Negotiations were made with each supplier for the return of any unused material, which lowered the project cost and ensured that each area received exactly what it needed. For areas that needed material, the gob located onsite was used as a fill material and then capped with two feet of clean fill as topsoil. The final cap was tested to make sure that any amendments needed for optimal growing conditions were met. Harvesting Onsite To eliminate the need to pur- chase plant material, shrubs, poles and/ or wetland plugs, all material was har- vested onsite from areas that were over- grown or areas that needed to undergo modifications, such as the access road and old stream bed. All material was collected prior to the onset of other construction activities and stockpiled in areas that were out of the way for planting at later dates. A shade struc- ture was created to provide shade for all of the transplants, and a watering system was installed. All material successfully was planted once the areas were finished. The total cost per plant was less than $200.00 a plant, a figure that takes into consideration harvesting, transportation, nursery (shade structures, wire baskets, planting pots, soils, amendments and fertilizers), water- ing and planting - a tremendous cost sav- ings to the project. The plan and process pro- vided was excellent and resulted in less than four percent mortality of the plants. The Mining and Minerals Division of the New Mexico Energy, MineralsandNaturalResourcesDepartment(EMNRD)presentedthe 2012 Excellence in Reclamation Award to 814 Solutions, LLC for this project on September 6, 2012 at the New Mexico Mining Association Convention held in Las Cruces, New Mexico. Part Two of this article will be fea- tured in the next issue and will highlight updated results of the plantings. Volume 7• Issue 1 • 29 Kiewit Construction and 814 Solutions, LLC crews shaping the Dillon channel realignment. Note the large pile of gob in the background, which gives a good perspective on the scale of the 814 Solutions, LLC’s talented crew and specialized equipment. Crews installing wetland plugs, shaping the channel and prepping for turf reinforcement mat and engineered wood strand material. Aged wood material processing area. All material used was repurposed from wood that was harvested from the Vermejo Park Ranch over the course of several years. STORMWATER STORAGE MODULES • Easy to Install & Clean • 97% Void Space • High Strength • Stackable • 18, 24, 30 or 36" Heights Phone: 610-236-1100 Email: stormwater@brentw.com Web: www.brentwoodprocess.com As a follow up to this project, there is an interactive online community board located at www.814solutions.com/commu- nityshare. Get involved, ask questions, make recommendations and see additional photos of the site as it matures!