SlideShare a Scribd company logo
1 of 18
Download to read offline
The Avenue Former Coking Works Remediation and
Regeneration Project (1999-2018)
Project Verification
Martin Westwood
Environmental Scientist BSc (Hons) CEnv
Stage 3 NEC Contract Supervisor/ designer
8 March 2018 IES Land Condition Symposium
Scope of Presentation
1. Project Overview
2. Remediation Techniques
3. Verification Procedures
4. Final Site Conditions
5. Verification Reporting
History and Works Stages
Year Activity
1890 Avenue Colliery and Lime & Iron Works operational on site
1930 Avenue Colliery and Lime & Iron Works become disused
1952 Construction of The Avenue Coking Works commenced
1956 Works is operational
1992 Works are closed
1999 EMDA take ownership of the site and become responsible for delivering its reclamation
1999 –2005 Stage 1: Plant area drain-down and demolition, site surveys, ground investigations, H&S
and environmental improvement works, desk studies, PRA, DQRA, remediation trials,
development of outline remediation strategy
2005-2006 Stage 2: Pre-qualification exercise and tender for detailed design of remediation strategy
/ Appointment of VSD for detailed design of remediation strategy
2006 –2009 Stage 2: Detailed design of earthworks and remediation strategy, value engineering,
economic appraisal. Early Contractor Involvement / OJEU Procurement / NEC:EEC
Option C Target Contract with Activity Schedule
2009 Stage3: Appointment of VSD for remediation of The Avenue site
2009 - 2016 Stage 3: Remediation and landscaping works
2017-2018 Defects Period and Verification Reporting Site Opens/Development commences
 1991 and 2007: 22 Phases of GI :
415 Boreholes/750 Trial Pits
 Environmental Monitoring
Programmes (Ground gas, Vapour, Air
Quality, Surface Water, Groundwater,
leachate)
 Source characterisation: Identified
Contaminants of Concern : PAHs
(Poly Aromatic Hydrocarbons),
Phenols, DROs (Diesel Range
Organics), PROs (Petrol Range
Organics), BTEX (Benzene, Toluene,
Ethylene, Xylene), Cyanide,
Thiocyanate, Ammonia, Heavy Metals
(Arsenic, Nickel, Cadmium,
Chromium), Asbestos
 Geological / Geotechnical /
Hydrogeological Characterisation
Project Overview
Remediation objectives
 Discharge legal obligations: avoid regulatory action under Part IIA of the EPA-Voluntary remediation
 Protect human health (future site users)
 Protect Controlled waters, specifically the River Rother
 28 hectare development platform (residential housing / garden) and public open space (65 hectares)
 Incorporate flood protection measures and SUDs
 Minimise material import / export and maximise material re-use on site (24 material types)
Remediation strategy
 Excavation and treatment of material that had the greatest potential to adversely impact receptors to
a design base of excavation (generally the top of the coal measure lithology)
 Shallow groundwater remediation: limited to shallow groundwater encountered in open excavations,
 Removal of all below ground structures and hazards
 No treatment of the deeper groundwater in the Coal Measures / Aquitard Reinstatement
 Reinstate material to achieve formation levels and adhere to geotechnical specification
Site Zones
Pre-Remediation Conceptual Site Model
Remediation Techniques
Technique Designs
Volume
Final /
Forecast
Treatment (m3)
Thermal desorption 270,300 257,266
Soil screening /sorting 237,600 203,485
Bioremediation 74,000 181,206
Total 581,900 641,497
Off-Site Disposal (Tonnes)
Asbestos 2352 913
Metal 3000 550
Other waste 4600 2470
Recovered Timber 1450 10,000
Tar 0 19,000
Total 11, 402 32,020
All Earthworks (m3)
Total Material volume (cut) 1,883,377 2,244,989
Total Material volume (Fill) 1,934,896 2,178,20
Total 3,818,273 4,423,189
Material Import to Create Landform 0 80,000
Groundwater and Surface Water Treated ?? 650,000+
Verification
Minimum Soil 1 per 250 m3 / m2
 Re-use SSAC (6000 samples)
 In situ / delineation testing (5,000 samples)
 Base of excavation testing (3,000 samples)
 Treatment Suitability and Operational Testing (>10,000 samples)
 Treatment Performance Verification (2,500 samples)
Groundwater and Surface Water
 Operational Surface and Groundwater Analytical Testing
 Compliance Surface and Foul Water Discharge Consents
 Treatment Suitability and Operational Testing
 Treatment Performance Verification
Other
 Geotechnical specifications
 Noise/Air /Waste notes/licenses /permits/MMP
Post Completion
 Preliminary Surface and Groundwater Monitoring Programme
 Ground Gas Monitoring Programme and GI
 Long term Surface and Groundwater Monitoring Programme
 Reed Bed Verification
Final Site Conditions (Base Chemical / Lithology)
Final Site Conditions (Fill Thickness / Unforeseen Excavations)
Material Excavated for
Treatment and to Create
Landform
1 High Geotechnical Quality (Reworked Natural Ground): Burnt Red shale.
2 High Geotechnical Quality (Reworked Natural Ground): Cohesive Colliery Spoil /Red Shale
3 Low Geotechnical Quality (Made Ground): Granular Iron Work Waste and Granular Colliery Spoil
4 High Geotechnical Quality (Reworked Natural Ground): Cohesive Colliery Spoil
5 Low Geotechnical Quality: Granular Made Ground
6 Granular Made Ground: Railway ballast / sub-base material
7 Waste Tip Material Upon
8 Lagoon Sediment / Tar /Free product
Material Excavated for
Disposal
9a Lagoon Tar
9b Waste tip material impacted natural ground
9c Inert Waste such as wood, plastic, metal, rags
9d Asbestos Containing Material (ACM)
Natural Ground / Reworked
Natural Ground Excavated
for Treatment / Landform
10 Alluvial Deposits / River Terrace deposits and River Sediments
11 Totally Weathered Mudstone Bedrock (Natural Ground): Mottled Brown Clay
12 Partially Weathered /Weakly Interbedded Undisturbed Mudstone (Natural Ground): Grey Mudstone
13 Weathered / Reworked sandstone (Natural Ground)
Material Output that has
been Subject to
Remediation/Treatment
14 TDU Output Material
15 WTPP Output Material Sorted Gravels, boulders, cobbles (30 mm - 75 mm)
16 Biologically Treated Material: Waste Tip Fines (0-30 mm fraction)
17 Biologically Treated Material: Made Ground
18 Biologically Treated Material: Natural Ground
Manufactured /Reclaimed
Materials Placed as Fill
Material
19 Crushed Demolition Materials (Manufactured Material from on-site material recovery).
20 Timber: (Manufactured Material from on-site material recovery)
21 Horticultural soils: (Manufactured Material from on-site material recovery)
22 Site won Low Quality topsoil/subsoil
Imported Material 23 Imported Material: Crushed Limestone Aggregate (6F5)
24 Imported Material: Horticultural Topsoil
Final Site Conditions (Material Types)
Final Site Conditions
(Material Types)
Final Site Conditions (Sub Surface / Surface Backfill Chemical)
Final Site Conditions (Ground / Surface Water)
Reporting
Post Completion DQRA Model
 Upward flow from coal measures (artesian /rising groundwater) excluded as aquitard reinstated
 Conceptual agreement that COCs above the Coal Measures will migrate to river / no GW water + COC loss to the aquifer
 Base of excavation derived to excavate and treat all contaminated material above coal measures
 River Rother = Receptor
 In-situ biodegradation not included
 Retardation allowed for (KOC)
 Plume concentration diluted by a factor of 175 (low flow river DF) + 1/10th EQS
 Limited suite of COCs given TDU/cost + COCs co-exist i.e. destroy one, destroy them all
Numerous iterations to reach final RTs
 COC physical/chemical properties: retained in all DQRA
 Source: Material volumes, placement zones, depth, composition - varies as scheme evolves
 Pathway: Hydrogeological Parameterisation - constant review as scheme evolves
 Receptor : River final location - varies as scheme evolves
 Forward mode to check predicted impacts at river (in final alignment)
 As-built data (soil chemistry and properties after treatment / placement)
 As built hydrogeology/ geology /geometry / parametrisation
 3 source areas
 Predicted “Raw Concentration” from 3 models combined and diluted by DF for river concentration
 Model run for 1000 years
 New as built parameters reviewed against design parameters (sensitivity analysis)
Measured Surface and Groundwater Verses
Predicted Surface Water Results
Parameter Units Maximum Measured
Groundwater
Concentration: Coal
Measures
Maximum Measured
Perched Groundwater
Concentration: Fill
Material
Maximum Measured
up gradient river
concentration
Maximum Measured
down gradient river
concentration
Predicted River Diluted
Concentration Based on Variable
Leachate SSAC
Sulphate mg/l 5,720 16,000 170 174 -
BAP µg/l - 0.27 0.2 0.13 -
Ammoniacal nitrogen mg/l - 5.23 0.93 0.90 0.0044
Naphthalene µg/l 20,000 237 0.12 0.13 0.1
COD mg/l - 1,950 30.7 35.2 -
pH (range) No unit 4.82 – 8.1 6.54 – 10.3 7.7 – 7.9 7.7 – 8.1 -
Iron (diss.filt) mg/l 1,170 20 0.24 0.22 -
Total PAH µg/l >13,000 480 2.58 2.24 -
Carbon, Organic mg/l - 91.7 7.47 7.47 -
Conductivity mS/cm 9.79 30.8 0.817 0.823 -
Benzene µg/l 69,500 40 <7 <7 1.5
Phenol µg/l <2 <2 <2 <2 2.1
DRO µg/l 113,000 1,420 <10 <10 0.6
GRO µg/l 940,000 79 <50 <50 -
Cyanide mg/l - 154 <0.05 <0.05 0.002
Thiocyanate mg/l 218 50.1 <0.05 <0.05 0.03
Thank You. Any Questions

More Related Content

What's hot

chapter 7 Health and Safety in Construction Industry lecture 8.ppt
chapter 7 Health and Safety in Construction Industry lecture 8.pptchapter 7 Health and Safety in Construction Industry lecture 8.ppt
chapter 7 Health and Safety in Construction Industry lecture 8.pptssuserb4074f
 
Green building vs conventional building
Green building vs conventional buildingGreen building vs conventional building
Green building vs conventional buildingRaj Singh
 
Contracts and their types
Contracts and their typesContracts and their types
Contracts and their typesTouqeer1
 
Case study on burj khalifa FOUNDATION
Case study on burj khalifa FOUNDATIONCase study on burj khalifa FOUNDATION
Case study on burj khalifa FOUNDATIONShagun mahajan
 
ITGS Project - Criterion C - Project Schedule
ITGS Project - Criterion C - Project ScheduleITGS Project - Criterion C - Project Schedule
ITGS Project - Criterion C - Project Scheduleitgstextbook
 
Burj al arab (Cofferdam&Rigging)
Burj al arab (Cofferdam&Rigging)Burj al arab (Cofferdam&Rigging)
Burj al arab (Cofferdam&Rigging)Sunny Mahajan
 
demolition of building
demolition of buildingdemolition of building
demolition of buildingtushar garg
 
Bill of Quantity Tabulation
Bill of Quantity TabulationBill of Quantity Tabulation
Bill of Quantity TabulationLamaJassim1
 
Method painting works emulsion paint
Method painting works   emulsion paintMethod painting works   emulsion paint
Method painting works emulsion paintMinh Bui Si
 
Vico Office - 5D BIM
Vico Office - 5D BIMVico Office - 5D BIM
Vico Office - 5D BIMclivejordan
 
Deep Retrofit: Irish Housing Building Standards
Deep Retrofit: Irish Housing Building StandardsDeep Retrofit: Irish Housing Building Standards
Deep Retrofit: Irish Housing Building StandardsSustainableEnergyAut
 
Green buildings matter
Green buildings matterGreen buildings matter
Green buildings matterGRIHA India
 
2018 03 Embodied Energy in Buildings
2018 03 Embodied Energy in Buildings2018 03 Embodied Energy in Buildings
2018 03 Embodied Energy in BuildingsJennifer Fox
 
Building construction
Building constructionBuilding construction
Building constructionnhmurad
 
ISG Pit to Ship Bulk Container Brochure 2015
ISG Pit to Ship Bulk Container Brochure 2015ISG Pit to Ship Bulk Container Brochure 2015
ISG Pit to Ship Bulk Container Brochure 2015ISG Pit to Ship Solutions
 
detailed specification for cement concrete
detailed specification for cement concretedetailed specification for cement concrete
detailed specification for cement concretevivek gami
 
Seminar artificial island.pptx
Seminar  artificial island.pptxSeminar  artificial island.pptx
Seminar artificial island.pptxVismayaChandran3
 
Bldg 6561 Feasibility Study Presentation Group#8
Bldg 6561   Feasibility Study Presentation   Group#8Bldg 6561   Feasibility Study Presentation   Group#8
Bldg 6561 Feasibility Study Presentation Group#8Sherif Hafez
 

What's hot (20)

chapter 7 Health and Safety in Construction Industry lecture 8.ppt
chapter 7 Health and Safety in Construction Industry lecture 8.pptchapter 7 Health and Safety in Construction Industry lecture 8.ppt
chapter 7 Health and Safety in Construction Industry lecture 8.ppt
 
Introduction to Building Information Modeling
Introduction to Building Information Modeling Introduction to Building Information Modeling
Introduction to Building Information Modeling
 
Green building vs conventional building
Green building vs conventional buildingGreen building vs conventional building
Green building vs conventional building
 
Contracts and their types
Contracts and their typesContracts and their types
Contracts and their types
 
Case study on burj khalifa FOUNDATION
Case study on burj khalifa FOUNDATIONCase study on burj khalifa FOUNDATION
Case study on burj khalifa FOUNDATION
 
ITGS Project - Criterion C - Project Schedule
ITGS Project - Criterion C - Project ScheduleITGS Project - Criterion C - Project Schedule
ITGS Project - Criterion C - Project Schedule
 
BIM case study
BIM case studyBIM case study
BIM case study
 
Burj al arab (Cofferdam&Rigging)
Burj al arab (Cofferdam&Rigging)Burj al arab (Cofferdam&Rigging)
Burj al arab (Cofferdam&Rigging)
 
demolition of building
demolition of buildingdemolition of building
demolition of building
 
Bill of Quantity Tabulation
Bill of Quantity TabulationBill of Quantity Tabulation
Bill of Quantity Tabulation
 
Method painting works emulsion paint
Method painting works   emulsion paintMethod painting works   emulsion paint
Method painting works emulsion paint
 
Vico Office - 5D BIM
Vico Office - 5D BIMVico Office - 5D BIM
Vico Office - 5D BIM
 
Deep Retrofit: Irish Housing Building Standards
Deep Retrofit: Irish Housing Building StandardsDeep Retrofit: Irish Housing Building Standards
Deep Retrofit: Irish Housing Building Standards
 
Green buildings matter
Green buildings matterGreen buildings matter
Green buildings matter
 
2018 03 Embodied Energy in Buildings
2018 03 Embodied Energy in Buildings2018 03 Embodied Energy in Buildings
2018 03 Embodied Energy in Buildings
 
Building construction
Building constructionBuilding construction
Building construction
 
ISG Pit to Ship Bulk Container Brochure 2015
ISG Pit to Ship Bulk Container Brochure 2015ISG Pit to Ship Bulk Container Brochure 2015
ISG Pit to Ship Bulk Container Brochure 2015
 
detailed specification for cement concrete
detailed specification for cement concretedetailed specification for cement concrete
detailed specification for cement concrete
 
Seminar artificial island.pptx
Seminar  artificial island.pptxSeminar  artificial island.pptx
Seminar artificial island.pptx
 
Bldg 6561 Feasibility Study Presentation Group#8
Bldg 6561   Feasibility Study Presentation   Group#8Bldg 6561   Feasibility Study Presentation   Group#8
Bldg 6561 Feasibility Study Presentation Group#8
 

Similar to The Avenue Former Coking Works Remediation Project Verification (1999-2018

Introduction to disposal part 2 engineering barriers in landfill
Introduction to disposal part 2 engineering barriers in landfillIntroduction to disposal part 2 engineering barriers in landfill
Introduction to disposal part 2 engineering barriers in landfillRehab O. Abdel Rahman
 
NAPL Site Remediation (HMVT)
NAPL Site Remediation (HMVT)NAPL Site Remediation (HMVT)
NAPL Site Remediation (HMVT)Frank Pels
 
NAPL Site Remediation (HMVT)
NAPL Site Remediation (HMVT)NAPL Site Remediation (HMVT)
NAPL Site Remediation (HMVT)Frank Pels
 
Case Study: Closure of an Earthen Lagoon
Case Study: Closure of an Earthen LagoonCase Study: Closure of an Earthen Lagoon
Case Study: Closure of an Earthen LagoonLPE Learning Center
 
Remediation
RemediationRemediation
RemediationVladimir
 
Measuring and monitoring soil carbon stocks from point to continental scale i...
Measuring and monitoring soil carbon stocks from point to continental scale i...Measuring and monitoring soil carbon stocks from point to continental scale i...
Measuring and monitoring soil carbon stocks from point to continental scale i...ExternalEvents
 
GI For Tunnel Projects
GI For Tunnel ProjectsGI For Tunnel Projects
GI For Tunnel ProjectsKeith Kong
 
Building Soil Carbon: Benefits, Possibilities, and Modeling
Building Soil Carbon: Benefits, Possibilities, and ModelingBuilding Soil Carbon: Benefits, Possibilities, and Modeling
Building Soil Carbon: Benefits, Possibilities, and ModelingCarbon Coalition
 
Zipporah Musyimi CLIFF Workshop
Zipporah Musyimi CLIFF WorkshopZipporah Musyimi CLIFF Workshop
Zipporah Musyimi CLIFF WorkshopMerylRichards
 
The significance of Surface Logging For The Formation Evaluation Advance Surf...
The significance of Surface Logging For The Formation Evaluation Advance Surf...The significance of Surface Logging For The Formation Evaluation Advance Surf...
The significance of Surface Logging For The Formation Evaluation Advance Surf...Evangelos Siskos
 
Moffett RAB Site 25 Update
Moffett RAB Site 25 UpdateMoffett RAB Site 25 Update
Moffett RAB Site 25 UpdateSteve Williams
 
Mine propcessdisposal
Mine propcessdisposalMine propcessdisposal
Mine propcessdisposalDC Graphics
 
Introduction to Accelerated Carbonation - Robert Williams (Carbon8 Systems Ltd)
Introduction to Accelerated Carbonation - Robert Williams (Carbon8 Systems Ltd)Introduction to Accelerated Carbonation - Robert Williams (Carbon8 Systems Ltd)
Introduction to Accelerated Carbonation - Robert Williams (Carbon8 Systems Ltd)ecoconnect
 
Stormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste FacilityStormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste FacilityFairfax County
 
Planning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptxPlanning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptxssuser0a41e6
 

Similar to The Avenue Former Coking Works Remediation Project Verification (1999-2018 (20)

Introduction to disposal part 2 engineering barriers in landfill
Introduction to disposal part 2 engineering barriers in landfillIntroduction to disposal part 2 engineering barriers in landfill
Introduction to disposal part 2 engineering barriers in landfill
 
NAPL Site Remediation (HMVT)
NAPL Site Remediation (HMVT)NAPL Site Remediation (HMVT)
NAPL Site Remediation (HMVT)
 
NAPL Site Remediation (HMVT)
NAPL Site Remediation (HMVT)NAPL Site Remediation (HMVT)
NAPL Site Remediation (HMVT)
 
Case Study: Closure of an Earthen Lagoon
Case Study: Closure of an Earthen LagoonCase Study: Closure of an Earthen Lagoon
Case Study: Closure of an Earthen Lagoon
 
Remediation
RemediationRemediation
Remediation
 
Measuring and monitoring soil carbon stocks from point to continental scale i...
Measuring and monitoring soil carbon stocks from point to continental scale i...Measuring and monitoring soil carbon stocks from point to continental scale i...
Measuring and monitoring soil carbon stocks from point to continental scale i...
 
GI For Tunnel Projects
GI For Tunnel ProjectsGI For Tunnel Projects
GI For Tunnel Projects
 
Landfilling
Landfilling Landfilling
Landfilling
 
Construction of an ash pond with wrp,
Construction of an ash pond with wrp,Construction of an ash pond with wrp,
Construction of an ash pond with wrp,
 
Landfill - Basics
Landfill - BasicsLandfill - Basics
Landfill - Basics
 
Building Soil Carbon: Benefits, Possibilities, and Modeling
Building Soil Carbon: Benefits, Possibilities, and ModelingBuilding Soil Carbon: Benefits, Possibilities, and Modeling
Building Soil Carbon: Benefits, Possibilities, and Modeling
 
Zipporah Musyimi CLIFF Workshop
Zipporah Musyimi CLIFF WorkshopZipporah Musyimi CLIFF Workshop
Zipporah Musyimi CLIFF Workshop
 
Pastoral Land Management Options in the Sahel: The Consequent Climate Forcings
Pastoral Land Management Options in the Sahel: The Consequent Climate ForcingsPastoral Land Management Options in the Sahel: The Consequent Climate Forcings
Pastoral Land Management Options in the Sahel: The Consequent Climate Forcings
 
Marks Sess13 102309
Marks Sess13 102309Marks Sess13 102309
Marks Sess13 102309
 
The significance of Surface Logging For The Formation Evaluation Advance Surf...
The significance of Surface Logging For The Formation Evaluation Advance Surf...The significance of Surface Logging For The Formation Evaluation Advance Surf...
The significance of Surface Logging For The Formation Evaluation Advance Surf...
 
Moffett RAB Site 25 Update
Moffett RAB Site 25 UpdateMoffett RAB Site 25 Update
Moffett RAB Site 25 Update
 
Mine propcessdisposal
Mine propcessdisposalMine propcessdisposal
Mine propcessdisposal
 
Introduction to Accelerated Carbonation - Robert Williams (Carbon8 Systems Ltd)
Introduction to Accelerated Carbonation - Robert Williams (Carbon8 Systems Ltd)Introduction to Accelerated Carbonation - Robert Williams (Carbon8 Systems Ltd)
Introduction to Accelerated Carbonation - Robert Williams (Carbon8 Systems Ltd)
 
Stormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste FacilityStormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste Facility
 
Planning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptxPlanning_and_design_of_assured_potable_water.pptx
Planning_and_design_of_assured_potable_water.pptx
 

More from IES / IAQM

Concept for sustainable remediation of an airfield
Concept for sustainable remediation of an airfieldConcept for sustainable remediation of an airfield
Concept for sustainable remediation of an airfieldIES / IAQM
 
Implementation of CE principles in the remediation of a former paper mill site
Implementation of CE principles in the remediation of a former paper mill siteImplementation of CE principles in the remediation of a former paper mill site
Implementation of CE principles in the remediation of a former paper mill siteIES / IAQM
 
Land remediation and conservation - the interaction of regulatory regimes
Land remediation and conservation - the interaction of regulatory regimesLand remediation and conservation - the interaction of regulatory regimes
Land remediation and conservation - the interaction of regulatory regimesIES / IAQM
 
Brownfield sites in N Ireland, case study on Belfast Ship yards development
Brownfield sites in N Ireland, case study on Belfast Ship yards developmentBrownfield sites in N Ireland, case study on Belfast Ship yards development
Brownfield sites in N Ireland, case study on Belfast Ship yards developmentIES / IAQM
 
A Contractor’s Perspective on Redeveloping Historical Landfills
A Contractor’s Perspective on Redeveloping Historical LandfillsA Contractor’s Perspective on Redeveloping Historical Landfills
A Contractor’s Perspective on Redeveloping Historical LandfillsIES / IAQM
 
Sharing is Caring – Can cross industry collaboration be achieved on key envir...
Sharing is Caring – Can cross industry collaboration be achieved on key envir...Sharing is Caring – Can cross industry collaboration be achieved on key envir...
Sharing is Caring – Can cross industry collaboration be achieved on key envir...IES / IAQM
 
The problem with waste soil: Are soil banks the answer?
The problem with waste soil: Are soil banks the answer?The problem with waste soil: Are soil banks the answer?
The problem with waste soil: Are soil banks the answer?IES / IAQM
 
Are we in a sustainable world?
Are we in a sustainable world?Are we in a sustainable world?
Are we in a sustainable world?IES / IAQM
 
16.00 Updates to CURED and CREAM Emissions Models.pdf
16.00 Updates to CURED and CREAM Emissions Models.pdf16.00 Updates to CURED and CREAM Emissions Models.pdf
16.00 Updates to CURED and CREAM Emissions Models.pdfIES / IAQM
 
15.30 Reducing Construction Emissions.pdf
15.30 Reducing Construction Emissions.pdf15.30 Reducing Construction Emissions.pdf
15.30 Reducing Construction Emissions.pdfIES / IAQM
 
15.30 Ethical considerations when determining air quality policies.pdf
15.30 Ethical considerations when determining air quality policies.pdf15.30 Ethical considerations when determining air quality policies.pdf
15.30 Ethical considerations when determining air quality policies.pdfIES / IAQM
 
14.50 The Impact of the Clean Air Zone on Air Quality in Birmingham.pdf
14.50 The Impact of the Clean Air Zone on Air Quality in Birmingham.pdf14.50 The Impact of the Clean Air Zone on Air Quality in Birmingham.pdf
14.50 The Impact of the Clean Air Zone on Air Quality in Birmingham.pdfIES / IAQM
 
14.40 The role of clean air zones in achieving the UK’s net-zero emissions ta...
14.40 The role of clean air zones in achieving the UK’s net-zero emissions ta...14.40 The role of clean air zones in achieving the UK’s net-zero emissions ta...
14.40 The role of clean air zones in achieving the UK’s net-zero emissions ta...IES / IAQM
 
14.30 The discord between limit value compliance and the LAQM objective regim...
14.30 The discord between limit value compliance and the LAQM objective regim...14.30 The discord between limit value compliance and the LAQM objective regim...
14.30 The discord between limit value compliance and the LAQM objective regim...IES / IAQM
 
14.00 Developments in occupational hygiene and air quality.pdf
14.00 Developments in occupational hygiene and air quality.pdf14.00 Developments in occupational hygiene and air quality.pdf
14.00 Developments in occupational hygiene and air quality.pdfIES / IAQM
 
12.15 Insights from the Clean Air Networks Conference.pdf
12.15 Insights from the Clean Air Networks Conference.pdf12.15 Insights from the Clean Air Networks Conference.pdf
12.15 Insights from the Clean Air Networks Conference.pdfIES / IAQM
 
12.00 Applied Source Apportionment using Low Cost Sensors.pdf
12.00 Applied Source Apportionment  using Low Cost Sensors.pdf12.00 Applied Source Apportionment  using Low Cost Sensors.pdf
12.00 Applied Source Apportionment using Low Cost Sensors.pdfIES / IAQM
 
11.15 Addressing emissions from NRMM.pdf
11.15 Addressing emissions from NRMM.pdf11.15 Addressing emissions from NRMM.pdf
11.15 Addressing emissions from NRMM.pdfIES / IAQM
 
09.45 Dispersion modelling considerations for Net Zero and air quality.pdf
09.45 Dispersion modelling considerations for Net Zero and air quality.pdf09.45 Dispersion modelling considerations for Net Zero and air quality.pdf
09.45 Dispersion modelling considerations for Net Zero and air quality.pdfIES / IAQM
 
09.15Measuring air pollutant emissions using novel techniques.pdf
09.15Measuring air pollutant emissions using novel techniques.pdf09.15Measuring air pollutant emissions using novel techniques.pdf
09.15Measuring air pollutant emissions using novel techniques.pdfIES / IAQM
 

More from IES / IAQM (20)

Concept for sustainable remediation of an airfield
Concept for sustainable remediation of an airfieldConcept for sustainable remediation of an airfield
Concept for sustainable remediation of an airfield
 
Implementation of CE principles in the remediation of a former paper mill site
Implementation of CE principles in the remediation of a former paper mill siteImplementation of CE principles in the remediation of a former paper mill site
Implementation of CE principles in the remediation of a former paper mill site
 
Land remediation and conservation - the interaction of regulatory regimes
Land remediation and conservation - the interaction of regulatory regimesLand remediation and conservation - the interaction of regulatory regimes
Land remediation and conservation - the interaction of regulatory regimes
 
Brownfield sites in N Ireland, case study on Belfast Ship yards development
Brownfield sites in N Ireland, case study on Belfast Ship yards developmentBrownfield sites in N Ireland, case study on Belfast Ship yards development
Brownfield sites in N Ireland, case study on Belfast Ship yards development
 
A Contractor’s Perspective on Redeveloping Historical Landfills
A Contractor’s Perspective on Redeveloping Historical LandfillsA Contractor’s Perspective on Redeveloping Historical Landfills
A Contractor’s Perspective on Redeveloping Historical Landfills
 
Sharing is Caring – Can cross industry collaboration be achieved on key envir...
Sharing is Caring – Can cross industry collaboration be achieved on key envir...Sharing is Caring – Can cross industry collaboration be achieved on key envir...
Sharing is Caring – Can cross industry collaboration be achieved on key envir...
 
The problem with waste soil: Are soil banks the answer?
The problem with waste soil: Are soil banks the answer?The problem with waste soil: Are soil banks the answer?
The problem with waste soil: Are soil banks the answer?
 
Are we in a sustainable world?
Are we in a sustainable world?Are we in a sustainable world?
Are we in a sustainable world?
 
16.00 Updates to CURED and CREAM Emissions Models.pdf
16.00 Updates to CURED and CREAM Emissions Models.pdf16.00 Updates to CURED and CREAM Emissions Models.pdf
16.00 Updates to CURED and CREAM Emissions Models.pdf
 
15.30 Reducing Construction Emissions.pdf
15.30 Reducing Construction Emissions.pdf15.30 Reducing Construction Emissions.pdf
15.30 Reducing Construction Emissions.pdf
 
15.30 Ethical considerations when determining air quality policies.pdf
15.30 Ethical considerations when determining air quality policies.pdf15.30 Ethical considerations when determining air quality policies.pdf
15.30 Ethical considerations when determining air quality policies.pdf
 
14.50 The Impact of the Clean Air Zone on Air Quality in Birmingham.pdf
14.50 The Impact of the Clean Air Zone on Air Quality in Birmingham.pdf14.50 The Impact of the Clean Air Zone on Air Quality in Birmingham.pdf
14.50 The Impact of the Clean Air Zone on Air Quality in Birmingham.pdf
 
14.40 The role of clean air zones in achieving the UK’s net-zero emissions ta...
14.40 The role of clean air zones in achieving the UK’s net-zero emissions ta...14.40 The role of clean air zones in achieving the UK’s net-zero emissions ta...
14.40 The role of clean air zones in achieving the UK’s net-zero emissions ta...
 
14.30 The discord between limit value compliance and the LAQM objective regim...
14.30 The discord between limit value compliance and the LAQM objective regim...14.30 The discord between limit value compliance and the LAQM objective regim...
14.30 The discord between limit value compliance and the LAQM objective regim...
 
14.00 Developments in occupational hygiene and air quality.pdf
14.00 Developments in occupational hygiene and air quality.pdf14.00 Developments in occupational hygiene and air quality.pdf
14.00 Developments in occupational hygiene and air quality.pdf
 
12.15 Insights from the Clean Air Networks Conference.pdf
12.15 Insights from the Clean Air Networks Conference.pdf12.15 Insights from the Clean Air Networks Conference.pdf
12.15 Insights from the Clean Air Networks Conference.pdf
 
12.00 Applied Source Apportionment using Low Cost Sensors.pdf
12.00 Applied Source Apportionment  using Low Cost Sensors.pdf12.00 Applied Source Apportionment  using Low Cost Sensors.pdf
12.00 Applied Source Apportionment using Low Cost Sensors.pdf
 
11.15 Addressing emissions from NRMM.pdf
11.15 Addressing emissions from NRMM.pdf11.15 Addressing emissions from NRMM.pdf
11.15 Addressing emissions from NRMM.pdf
 
09.45 Dispersion modelling considerations for Net Zero and air quality.pdf
09.45 Dispersion modelling considerations for Net Zero and air quality.pdf09.45 Dispersion modelling considerations for Net Zero and air quality.pdf
09.45 Dispersion modelling considerations for Net Zero and air quality.pdf
 
09.15Measuring air pollutant emissions using novel techniques.pdf
09.15Measuring air pollutant emissions using novel techniques.pdf09.15Measuring air pollutant emissions using novel techniques.pdf
09.15Measuring air pollutant emissions using novel techniques.pdf
 

Recently uploaded

Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur EscortsCall Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Contact Number Call Girls Service In Goa 9316020077 Goa Call Girls Service
Contact Number Call Girls Service In Goa  9316020077 Goa  Call Girls ServiceContact Number Call Girls Service In Goa  9316020077 Goa  Call Girls Service
Contact Number Call Girls Service In Goa 9316020077 Goa Call Girls Servicesexy call girls service in goa
 
Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)RaviPrajapat11
 
Freegle User Survey as visual display - BH
Freegle User Survey as visual display - BHFreegle User Survey as visual display - BH
Freegle User Survey as visual display - BHbill846304
 
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...ranjana rawat
 
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...Suhani Kapoor
 
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...Suhani Kapoor
 
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...ranjana rawat
 
Horizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben AbrahamHorizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben Abrahamssuserbb03ff
 
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...ranjana rawat
 
DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024itadmin50
 
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Bookingtanu pandey
 
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service BikanerLow Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service BikanerSuhani Kapoor
 
Russian Call Girls Nashik Anjali 7001305949 Independent Escort Service Nashik
Russian Call Girls Nashik Anjali 7001305949 Independent Escort Service NashikRussian Call Girls Nashik Anjali 7001305949 Independent Escort Service Nashik
Russian Call Girls Nashik Anjali 7001305949 Independent Escort Service Nashikranjana rawat
 

Recently uploaded (20)

Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur EscortsCall Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
Call Girl Nagpur Roshni Call 7001035870 Meet With Nagpur Escorts
 
Contact Number Call Girls Service In Goa 9316020077 Goa Call Girls Service
Contact Number Call Girls Service In Goa  9316020077 Goa  Call Girls ServiceContact Number Call Girls Service In Goa  9316020077 Goa  Call Girls Service
Contact Number Call Girls Service In Goa 9316020077 Goa Call Girls Service
 
Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)
 
Escort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCR
Escort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCREscort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCR
Escort Service Call Girls In Shakti Nagar, 99530°56974 Delhi NCR
 
Freegle User Survey as visual display - BH
Freegle User Survey as visual display - BHFreegle User Survey as visual display - BH
Freegle User Survey as visual display - BH
 
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
 
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
VIP Call Girls Mahadevpur Colony ( Hyderabad ) Phone 8250192130 | ₹5k To 25k ...
 
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
 
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(NANDITA) Hadapsar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
 
Gandhi Nagar (Delhi) 9953330565 Escorts, Call Girls Services
Gandhi Nagar (Delhi) 9953330565 Escorts, Call Girls ServicesGandhi Nagar (Delhi) 9953330565 Escorts, Call Girls Services
Gandhi Nagar (Delhi) 9953330565 Escorts, Call Girls Services
 
Horizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben AbrahamHorizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben Abraham
 
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
 
DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024DENR EPR Law Compliance Updates April 2024
DENR EPR Law Compliance Updates April 2024
 
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Pune Airport Call Me 7737669865 Budget Friendly No Advance Booking
 
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Sustainable Packaging
Sustainable PackagingSustainable Packaging
Sustainable Packaging
 
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service BikanerLow Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
Low Rate Call Girls Bikaner Anika 8250192130 Independent Escort Service Bikaner
 
Russian Call Girls Nashik Anjali 7001305949 Independent Escort Service Nashik
Russian Call Girls Nashik Anjali 7001305949 Independent Escort Service NashikRussian Call Girls Nashik Anjali 7001305949 Independent Escort Service Nashik
Russian Call Girls Nashik Anjali 7001305949 Independent Escort Service Nashik
 
Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Rajiv Chowk Delhi reach out to us at 🔝9953056974🔝
 

The Avenue Former Coking Works Remediation Project Verification (1999-2018

  • 1. The Avenue Former Coking Works Remediation and Regeneration Project (1999-2018) Project Verification Martin Westwood Environmental Scientist BSc (Hons) CEnv Stage 3 NEC Contract Supervisor/ designer 8 March 2018 IES Land Condition Symposium
  • 2. Scope of Presentation 1. Project Overview 2. Remediation Techniques 3. Verification Procedures 4. Final Site Conditions 5. Verification Reporting
  • 3. History and Works Stages Year Activity 1890 Avenue Colliery and Lime & Iron Works operational on site 1930 Avenue Colliery and Lime & Iron Works become disused 1952 Construction of The Avenue Coking Works commenced 1956 Works is operational 1992 Works are closed 1999 EMDA take ownership of the site and become responsible for delivering its reclamation 1999 –2005 Stage 1: Plant area drain-down and demolition, site surveys, ground investigations, H&S and environmental improvement works, desk studies, PRA, DQRA, remediation trials, development of outline remediation strategy 2005-2006 Stage 2: Pre-qualification exercise and tender for detailed design of remediation strategy / Appointment of VSD for detailed design of remediation strategy 2006 –2009 Stage 2: Detailed design of earthworks and remediation strategy, value engineering, economic appraisal. Early Contractor Involvement / OJEU Procurement / NEC:EEC Option C Target Contract with Activity Schedule 2009 Stage3: Appointment of VSD for remediation of The Avenue site 2009 - 2016 Stage 3: Remediation and landscaping works 2017-2018 Defects Period and Verification Reporting Site Opens/Development commences  1991 and 2007: 22 Phases of GI : 415 Boreholes/750 Trial Pits  Environmental Monitoring Programmes (Ground gas, Vapour, Air Quality, Surface Water, Groundwater, leachate)  Source characterisation: Identified Contaminants of Concern : PAHs (Poly Aromatic Hydrocarbons), Phenols, DROs (Diesel Range Organics), PROs (Petrol Range Organics), BTEX (Benzene, Toluene, Ethylene, Xylene), Cyanide, Thiocyanate, Ammonia, Heavy Metals (Arsenic, Nickel, Cadmium, Chromium), Asbestos  Geological / Geotechnical / Hydrogeological Characterisation
  • 4. Project Overview Remediation objectives  Discharge legal obligations: avoid regulatory action under Part IIA of the EPA-Voluntary remediation  Protect human health (future site users)  Protect Controlled waters, specifically the River Rother  28 hectare development platform (residential housing / garden) and public open space (65 hectares)  Incorporate flood protection measures and SUDs  Minimise material import / export and maximise material re-use on site (24 material types) Remediation strategy  Excavation and treatment of material that had the greatest potential to adversely impact receptors to a design base of excavation (generally the top of the coal measure lithology)  Shallow groundwater remediation: limited to shallow groundwater encountered in open excavations,  Removal of all below ground structures and hazards  No treatment of the deeper groundwater in the Coal Measures / Aquitard Reinstatement  Reinstate material to achieve formation levels and adhere to geotechnical specification
  • 7. Remediation Techniques Technique Designs Volume Final / Forecast Treatment (m3) Thermal desorption 270,300 257,266 Soil screening /sorting 237,600 203,485 Bioremediation 74,000 181,206 Total 581,900 641,497 Off-Site Disposal (Tonnes) Asbestos 2352 913 Metal 3000 550 Other waste 4600 2470 Recovered Timber 1450 10,000 Tar 0 19,000 Total 11, 402 32,020 All Earthworks (m3) Total Material volume (cut) 1,883,377 2,244,989 Total Material volume (Fill) 1,934,896 2,178,20 Total 3,818,273 4,423,189 Material Import to Create Landform 0 80,000 Groundwater and Surface Water Treated ?? 650,000+
  • 8. Verification Minimum Soil 1 per 250 m3 / m2  Re-use SSAC (6000 samples)  In situ / delineation testing (5,000 samples)  Base of excavation testing (3,000 samples)  Treatment Suitability and Operational Testing (>10,000 samples)  Treatment Performance Verification (2,500 samples) Groundwater and Surface Water  Operational Surface and Groundwater Analytical Testing  Compliance Surface and Foul Water Discharge Consents  Treatment Suitability and Operational Testing  Treatment Performance Verification Other  Geotechnical specifications  Noise/Air /Waste notes/licenses /permits/MMP Post Completion  Preliminary Surface and Groundwater Monitoring Programme  Ground Gas Monitoring Programme and GI  Long term Surface and Groundwater Monitoring Programme  Reed Bed Verification
  • 9. Final Site Conditions (Base Chemical / Lithology)
  • 10. Final Site Conditions (Fill Thickness / Unforeseen Excavations)
  • 11. Material Excavated for Treatment and to Create Landform 1 High Geotechnical Quality (Reworked Natural Ground): Burnt Red shale. 2 High Geotechnical Quality (Reworked Natural Ground): Cohesive Colliery Spoil /Red Shale 3 Low Geotechnical Quality (Made Ground): Granular Iron Work Waste and Granular Colliery Spoil 4 High Geotechnical Quality (Reworked Natural Ground): Cohesive Colliery Spoil 5 Low Geotechnical Quality: Granular Made Ground 6 Granular Made Ground: Railway ballast / sub-base material 7 Waste Tip Material Upon 8 Lagoon Sediment / Tar /Free product Material Excavated for Disposal 9a Lagoon Tar 9b Waste tip material impacted natural ground 9c Inert Waste such as wood, plastic, metal, rags 9d Asbestos Containing Material (ACM) Natural Ground / Reworked Natural Ground Excavated for Treatment / Landform 10 Alluvial Deposits / River Terrace deposits and River Sediments 11 Totally Weathered Mudstone Bedrock (Natural Ground): Mottled Brown Clay 12 Partially Weathered /Weakly Interbedded Undisturbed Mudstone (Natural Ground): Grey Mudstone 13 Weathered / Reworked sandstone (Natural Ground) Material Output that has been Subject to Remediation/Treatment 14 TDU Output Material 15 WTPP Output Material Sorted Gravels, boulders, cobbles (30 mm - 75 mm) 16 Biologically Treated Material: Waste Tip Fines (0-30 mm fraction) 17 Biologically Treated Material: Made Ground 18 Biologically Treated Material: Natural Ground Manufactured /Reclaimed Materials Placed as Fill Material 19 Crushed Demolition Materials (Manufactured Material from on-site material recovery). 20 Timber: (Manufactured Material from on-site material recovery) 21 Horticultural soils: (Manufactured Material from on-site material recovery) 22 Site won Low Quality topsoil/subsoil Imported Material 23 Imported Material: Crushed Limestone Aggregate (6F5) 24 Imported Material: Horticultural Topsoil Final Site Conditions (Material Types)
  • 13. Final Site Conditions (Sub Surface / Surface Backfill Chemical)
  • 14. Final Site Conditions (Ground / Surface Water)
  • 16. Post Completion DQRA Model  Upward flow from coal measures (artesian /rising groundwater) excluded as aquitard reinstated  Conceptual agreement that COCs above the Coal Measures will migrate to river / no GW water + COC loss to the aquifer  Base of excavation derived to excavate and treat all contaminated material above coal measures  River Rother = Receptor  In-situ biodegradation not included  Retardation allowed for (KOC)  Plume concentration diluted by a factor of 175 (low flow river DF) + 1/10th EQS  Limited suite of COCs given TDU/cost + COCs co-exist i.e. destroy one, destroy them all Numerous iterations to reach final RTs  COC physical/chemical properties: retained in all DQRA  Source: Material volumes, placement zones, depth, composition - varies as scheme evolves  Pathway: Hydrogeological Parameterisation - constant review as scheme evolves  Receptor : River final location - varies as scheme evolves  Forward mode to check predicted impacts at river (in final alignment)  As-built data (soil chemistry and properties after treatment / placement)  As built hydrogeology/ geology /geometry / parametrisation  3 source areas  Predicted “Raw Concentration” from 3 models combined and diluted by DF for river concentration  Model run for 1000 years  New as built parameters reviewed against design parameters (sensitivity analysis)
  • 17. Measured Surface and Groundwater Verses Predicted Surface Water Results Parameter Units Maximum Measured Groundwater Concentration: Coal Measures Maximum Measured Perched Groundwater Concentration: Fill Material Maximum Measured up gradient river concentration Maximum Measured down gradient river concentration Predicted River Diluted Concentration Based on Variable Leachate SSAC Sulphate mg/l 5,720 16,000 170 174 - BAP µg/l - 0.27 0.2 0.13 - Ammoniacal nitrogen mg/l - 5.23 0.93 0.90 0.0044 Naphthalene µg/l 20,000 237 0.12 0.13 0.1 COD mg/l - 1,950 30.7 35.2 - pH (range) No unit 4.82 – 8.1 6.54 – 10.3 7.7 – 7.9 7.7 – 8.1 - Iron (diss.filt) mg/l 1,170 20 0.24 0.22 - Total PAH µg/l >13,000 480 2.58 2.24 - Carbon, Organic mg/l - 91.7 7.47 7.47 - Conductivity mS/cm 9.79 30.8 0.817 0.823 - Benzene µg/l 69,500 40 <7 <7 1.5 Phenol µg/l <2 <2 <2 <2 2.1 DRO µg/l 113,000 1,420 <10 <10 0.6 GRO µg/l 940,000 79 <50 <50 - Cyanide mg/l - 154 <0.05 <0.05 0.002 Thiocyanate mg/l 218 50.1 <0.05 <0.05 0.03
  • 18. Thank You. Any Questions