SlideShare a Scribd company logo
1 of 4
Organic Soil and Water Management at the Arlington
             Agricultural Research Station
                                              Project Background
            Introduction                                                                                    Design Standards / Constraints
                                                                           Badger Lane
                                                                                               N

In recent years multiple environmental                                                                     Standards
concerns have arisen in the organic                                                                        •Erosion must be limited to the
                                                                                               S
area at the Arlington Agriculture                                                                          designated tolerable soil loss (T) for
Research Station (AARS) . This area                                                                        the soil type (NR 151.02)
can be seen in Figure 1 on the right.
The two primary areas of concern are                                                                       •Gully erosion must be eliminated




                                                            Hopkins Road
soil erosion and the need for evaluation
of the capacity and stability of a                                                                         •Waterway needs to convey flow
waterway draining a large watershed                                                                        without over topping or eroding
north of the organic area.
                                                                                                            Constraints
                                                                                                           •Area needs to remain under organic
       Problem Description                                                          Ramsey Road            management

Erosion Control                                                                                            •Flexibility in field boundaries for
•Significant erosion taking place in              Area of concern for
                                                                                     Organic area          research projects
                                                                                     boundary.
                                                  erosion
organic fields due to steep slopes and
the high level of tillage                         Location of waterway              Arlington Research     •Limit Costs to $10,000 over three
                                                  being evaluated                   Station Headquarters
                                                                                                           years
                                           Figure 1: Aerial Photograph of Organic Area
•Also, gullies are forming in spots due
                                            at Arlington Agriculture Research Station                                      Approach
to natural topography and erosion of
old diversions                                                                                             NRCS Design Process:
Waterway Design
•Waterway designed and constructed                                                                         1.Determine client objectives
                                                                                                           2.Conduct a resource inventory
without proper watershed delineation                                                                       3.Analyze resource data to identify problems
                                                                                                           and opportunities
•Waterway conveys runoff from a                                                                            4.Formulate and evaluate resource
nearly 200 acre watershed that includes                                                                    alternatives
both research station and private                                                                          5.Document the client’s planning decisions
farmland
                                           Figure 2: Photograph of Existing Waterway

Team Members: Josh Gable,Tyler Hastings,
               Lis Nimani, Ryan Stenjem                                                                    Advisors: John Panuska, Anita Thompson
Organic Soil and Water Management at the Arlington
             Agricultural Research Station
                                                                  Waterway Analysis
                         Purpose                                   The Design Storm: SCS Type II                                                                                                                            HydroCAD
In 2008, a grassed waterway was constructed                            10–year, 24–hour storm                                                                                                  The Stormwater Modeling Software, HydroCAD, uses hydrology
                                                                                                                                                                                               principles that were developed by the NRCS as well as various
to transport flows from an upstream                                                                                                                                                            hydraulic calculations. It uses the TR-55 method for calculating Time
watershed, through the AARS Organic Corner                                                                                                                                                     of Concentration (tc) values and gives unique hydrographs through
                                                                                                                                                                                               waterways, ponds, culverts and various other hydraulic components.
(denoted with blue arrows in Figure 3).
Because of the immediate need for the
channel, a proper engineering design was not
carried out. In order to verify that this
waterway was adequately built, HydroCAD
was used to model the watershed and
waterway.
                                                             Figure 4 Design Storm Unit Hydrograph, exported from HydroCAD




  Figure 1 Main Waterway, in Organic Corner, AARS

                                                                                                                                                                                                             Figure 6 HydroCAD Layout Map
                                                                                                                                                                                               Results
                                                             Figure 5 Design Storm Depth vs. Time Graph, exported from HydroCAD
      Figure 2 Cross-Section of Main Waterway
                                                                                    Watershed Parameters
     The Contributing Watershed                                                  Table 1 Contributing Watershed Characteristics
                                                                                   Sub -                                                          Time of Concentration, Tc
                                                                                                    Area (acres)        Curve Number, CN
                                                                                 Watershed                                                                  (min)
                                                                                      1                   8.2                  76                           15.6
                                                                                      2                   13.4                 77                           23.2
                                                                                      3                   34.4                 70                            37                                      Figure 7 Final Hydrograph for Main Waterway
                                                                                      4                   42.5                 76                           32.1
                                                                                      5                  127.2                 76                           78.4
                                                                                                                                                                                                           Table 4 10-year, 24-hr Storm Results
                                                                                      6                   9.2                  76                           13.1
                                                                                                                                                                                                             Reach   Channel Capacity (cfs)   Peak Flow (cfs)   Max Velocity (ft/s)
                                                                                      7                   6.9                  76                           19.7
                                                                                                                                                                                                              1              63.23                 17.2                2.2
                                                                                      8                   12.2                 76                           20.2
                                                                                                                                                                                                              2              44.84                 38.52               1.25
                                                                                       Table 2 Outlet Characteristics                                                                                        Main            316.5                141.34                5
                                                                                          Culvert             Diameter (in)         Length (ft)          Slope (%)
                                                                                             1                     24                  50.3                2.25                                            Table 5 25-year, 24-hr Storm Results
                                                                                             2                     18                   38                 1.37
                                                                                                                                                                                                             Reach   Channel Capacity (cfs)   Peak Flow (cfs)   Max Velocity (ft/s)
                                                                                             3                     18                   38                 0.66
                                                                                                                                                                                                              1              63.23                 19.3                2.27
                                                                                             4                     24                   36                 1.78
                                                                                                                                                                                                              2              44.84                49.85                1.33
                                                                                             5                     36                  28.6                2.24
                                                                                             6                     36                  28.6                0.98                                              Main            316.5                208.5                5.57

                                                                                             7                     18                  24.3                3.29
                                                                                                                                                                                                          Table 6 100-year, 24-hr Storm Results
                                                                 Table 3 Sub-Watershed Characteristics                                                                                                       Reach   Channel Capacity (cfs)   Peak Flow (cfs)   Max Velocity (ft/s)
                                                                                             Trapezoidal Cross-Section                            Channel Length Channel Slope
                                                                 Reach                                                                                                         Manning’s No.                  1              63.23                 20.71               2.32
                                                                         bottom width (ft)       depth (ft)      side-slope (horizontal/vertical)      (ft)          (%)
                                                                                                                                                                                                              2              44.84                 72.86               1.44
                                                                   1            10                   1                        10                         1400            0.85     0.033
                                                                                                                                                                                                             Main            316.5                257.95               5.9
                                                                   2            8                   1.5                       10                         1400            0.43      0.07
                                                                  Main          12                   2                        6.7                        1050            0.84     0.026
                                                                                                                                                                                                                            Conclusion
                                                            In modeling the upstream watershed, culverts                                                                                       After completing the HydroCAD model
                                                            were modeled as outlets to ponds with storage                                                                                      analyzing the waterway in the Organic Corner
                                                            behind. Where water had the potential to flow                                                                                      and its upstream watershed, we have
     Figure 3 Contour Map of Watershed with 4 ft Contours
                                                            over a roadway upon a culvert reaching capacity,                                                                                   determined that the current waterway is more
                           Waterway – Organic Corner        the roadway way was treated as a broad-crested                                                                                     than adequate for handling flows from the
                           Watershed Boundary
                                                            weir as an outlet to a pond.
                           4 ft Contour Lines                                                                                                                                                  design storm.
Organic Soil and Water Management at the Arlington
             Agricultural Research Station
                                           Erosion Management
       Problem Description                                    Field     Soil Slope Slope                      Design Options
                                                                                     (%)
                                                                        Loss Length
                                                                       (ton/ac/yr)   (ft)
•Steep Slopes and intensive tillage                                                               •Option 1 – Implement strip cropping
operations have lead to erosion.                              401        4.3         140    3.7   and make three fields of equal width
                                                              402        2.9         160    2.5   out of fields 447 A and B, and also for
•The DNR requires that erosion be                            403 A       2.4         160    2.0   fields 404 and 403C-S and N.
less than the designated tolerable soil                      403 B       3.4         155    3.0                 Field      Soil Loss
loss (T) for the soil type. (NR                             403 C-N      6.5         180    4.9                             (ton/ac/yr)

151.02).                                                    403 C-S      5.5         180    4.5                 401            4.3
                                                              404        7.4         175    5.6                 402            2.9
•The tolerable soil loss for the                              446        3.3         150    2.3                403 A           2.4
Organic Fields are 5 ton/acre/year.                          447 A       4.9         175    4.1                403 B           3.4
(Web Soil Survey).                                           447 B       4.5         175    3.5               403 C-N
                                          Figure 1: Current field boundaries with respective                  403 C-S          4.8
•Fields 403 C-N, 403 C-S, and 404                     soil loss and LS Inputs.                                  404
are currently above T, and fields 447           Universal Soil Loss Equation                                    446            2.6
A and B are near T (Figure 1), so they                  A=RKLSCP                                               447 A
                                                                                                                               4.1
require best management practices,        R          Rainfall Erosivity Factor                                 447 B
                                                                                                      Figure 4: Soil loss after strip cropping
such as strip cropping, terracing, or     K           Soil Erodibility Factor
contouring, in order to reduce soil       LS   Topographic Factor (Slope Length and
loss.                                                         Slope)                              •Option 2 – Design a terrace system to
                                          CP      Cropping Management Factors
                                                                                                  break up the slope length along the
                                                                                                  steepest slopes
                                                  Figure 2: USLE Equation
              RUSLE2                                                                                            Field      Soil Loss
                                                                                                                            (ton/ac/yr)

                                                                                                                401            4.3
•Is a computer program that utilizes
                                                                                                                402            2.9
the Universal Soil Loss Equation
                                                                                                               403 A           2.4
(USLE) to model rill and interrill
                                                                                                               403 B           3.4
erosion. See Figure 2.
                                                                                                                404
                                                                                                              403 C-N          4.3
•Used a crop rotation of Winter
                                                                                                              403 C-S
wheat, 3 years alfalfa, Corn grain,
                                                                                                                 446           2.6
soybeans.
                                                                                                                447 A
                                                                                                                               3.9
                                                 Figure 3: Screen shot of RUSLE2                                447 B
•Tillage operations of chisel plow and
                                                                                                         Figure 5: Soil loss after terraced
disk before planting and 2-3
cultivations during spring.
Organic Soil and Water Management at the Arlington
             Agricultural Research Station
                                              Designs and Recommendations
   Designs and Recommendations                                                                      Final Terrace Design
                                                                                                    Q = 2.0 ft3/s (determined from HydroCAD)
Waterway                                                                                            Vpermissible = 1.5 - 5 ft/s
In evaluating the waterway it was determined                                                        A = 3.5 ft2
that the current channel will be sufficient to                                                      S=2%
handle the peak flow from a 10 yr – 24 hour
storm event. This determination was made
primarily using the results from the
HydroCAD model.

Erosion Control
After Conversations with the Arlington
Research Station staff a modified plan was
devised. The impact of this proposed plan on
erosion rates can be seen in Table 1.                                                                   Figure 2: Proposed Terrace Cross
                                                                                                                     Section
•Terraces will be implemented in fields 404
and 403C (See Figure1 and Figure 2)
                                                                                                       Table 1: Proposal Impact on Erosion
•A diversion will be cut along the top of field                                                                       Rates
447 A to reduce the occurrence of gulley                                                                  Field     Current       Expected
erosion. (See Figure 1)                                                                                            Soil Loss      Soil Loss
                                                  Figure 1: Location for Proposed Construction                      (ton/ac/yr)    (ton/ac/yr)
•Strip Cropping is also recommended in the                                                                401         4.3            4.3
area of fields 447 A and 447 B.
                                                   Terrace Spacing Calculation                            402         2.9            2.9
                                                   H.I. = (xs + y) (100/s)                               403 A        2.4            2.4
•Impact of proposal can be seen in Table 1
                                                                                                         403 B        3.4            3.4
                                                   H.I. = horizontal interval in feet                   403 C-N       6.5            4.3
Channel Capacity Calculation                       x = constant determined by geographic location       403 C-S       5.5            4.3
Q = V*A                                            s = land slope in percent
                                                                                                          404         7.4            4.3
V = (1.49/n) * R(2/3)*S(1/2)                       y = constant determined by cropping and soil
                                                   erodibility                                            446         3.3            3.3
                                                                                                         447 A        4.9            4.1
Q = Peak flow rate in Channel (ft3/s)
V = Flow velocity (ft/s)                           H.I .= (0.5 * 6 + 4) (100/6)                          447 B        4.5            4.1
A = Cross sectional area of channel
n = Manning’s Roughness Coefficient (varies        H.I. = 140
depending on vegetation growth from 0.035          *raised to 150 feet due to farming equipment
to 0.075)                                          restrictions                                           Special Thanks to:
R = Hydraulic radius of channel (ft)                                                                      Jeff Breuer, Darwin Frye, Scott
S = Channel slope (ft/ft)                                                                                 Mueller, Matt Repking, Anita
                                                                                                          Thompson, and John Panuska

More Related Content

What's hot

Design build strategies to optimize cost effectiveness in aml v2
Design build strategies to optimize cost effectiveness in aml v2Design build strategies to optimize cost effectiveness in aml v2
Design build strategies to optimize cost effectiveness in aml v2
Angelshoot
 
Max KroschelResume061715
Max KroschelResume061715Max KroschelResume061715
Max KroschelResume061715
Max Kroschel
 
robert mcgregor 006865u 25Apr2016
robert mcgregor 006865u 25Apr2016robert mcgregor 006865u 25Apr2016
robert mcgregor 006865u 25Apr2016
Robert Mcgregor
 
Group 03 Development Presentation
Group 03 Development PresentationGroup 03 Development Presentation
Group 03 Development Presentation
GP Design PS
 
Marengo lid symposium_2011-09-25
Marengo lid symposium_2011-09-25Marengo lid symposium_2011-09-25
Marengo lid symposium_2011-09-25
retzcanter
 

What's hot (19)

Mining Impacts and Wetlands_Crandon_Experience
Mining Impacts and Wetlands_Crandon_ExperienceMining Impacts and Wetlands_Crandon_Experience
Mining Impacts and Wetlands_Crandon_Experience
 
Design build strategies to optimize cost effectiveness in aml v2
Design build strategies to optimize cost effectiveness in aml v2Design build strategies to optimize cost effectiveness in aml v2
Design build strategies to optimize cost effectiveness in aml v2
 
Civil Works Transformation
Civil Works TransformationCivil Works Transformation
Civil Works Transformation
 
Duke Study: Methane contamination of drinking water accompanying gas-well dri...
Duke Study: Methane contamination of drinking water accompanying gas-well dri...Duke Study: Methane contamination of drinking water accompanying gas-well dri...
Duke Study: Methane contamination of drinking water accompanying gas-well dri...
 
Dead Run Stream Restoration Project Meeting: Feb. 18, 2015
Dead Run Stream Restoration Project Meeting: Feb. 18, 2015Dead Run Stream Restoration Project Meeting: Feb. 18, 2015
Dead Run Stream Restoration Project Meeting: Feb. 18, 2015
 
Max KroschelResume061715
Max KroschelResume061715Max KroschelResume061715
Max KroschelResume061715
 
robert mcgregor 006865u 25Apr2016
robert mcgregor 006865u 25Apr2016robert mcgregor 006865u 25Apr2016
robert mcgregor 006865u 25Apr2016
 
Gopal K - UEI Day 1 - Kochi Jan18
Gopal K - UEI Day 1 - Kochi Jan18Gopal K - UEI Day 1 - Kochi Jan18
Gopal K - UEI Day 1 - Kochi Jan18
 
Group 03 Development Presentation
Group 03 Development PresentationGroup 03 Development Presentation
Group 03 Development Presentation
 
Permitting potable water from rainwater- AIA Houston- September 2014
Permitting potable water from rainwater- AIA Houston- September 2014Permitting potable water from rainwater- AIA Houston- September 2014
Permitting potable water from rainwater- AIA Houston- September 2014
 
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
Urban Planning Design Considerations for Better Water Quality, Bill Hunt NC S...
 
Hangar One Update to the Moffett RAB
Hangar One Update to the Moffett RABHangar One Update to the Moffett RAB
Hangar One Update to the Moffett RAB
 
Independent Review of Hydrological Issues: Deloro Mine Site
Independent Review of Hydrological Issues: Deloro Mine SiteIndependent Review of Hydrological Issues: Deloro Mine Site
Independent Review of Hydrological Issues: Deloro Mine Site
 
Marengo lid symposium_2011-09-25
Marengo lid symposium_2011-09-25Marengo lid symposium_2011-09-25
Marengo lid symposium_2011-09-25
 
Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]
Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]
Lake Manzala Engineered Wetland, Port Said, Egypt [IWC4 Presentation]
 
Low impact development_coupled_with_floodplain_mitigation
Low impact development_coupled_with_floodplain_mitigationLow impact development_coupled_with_floodplain_mitigation
Low impact development_coupled_with_floodplain_mitigation
 
Viod Mitigation with the BCCP
Viod Mitigation with the BCCPViod Mitigation with the BCCP
Viod Mitigation with the BCCP
 
Swim Drink Fish Canada submission for relicensing written hearing for the Del...
Swim Drink Fish Canada submission for relicensing written hearing for the Del...Swim Drink Fish Canada submission for relicensing written hearing for the Del...
Swim Drink Fish Canada submission for relicensing written hearing for the Del...
 
Texas
TexasTexas
Texas
 

Similar to Organic Soil and Water Management at the Arlington Agricultural Research Station

SOQ (Sample)
SOQ (Sample)SOQ (Sample)
SOQ (Sample)
jcirone
 
Additions And Alterations
Additions And AlterationsAdditions And Alterations
Additions And Alterations
sarath2008
 
State & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
State & Federal Regulation of Hydraulic Fracturing: A Comparative AnalysisState & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
State & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
Dan Arthur
 

Similar to Organic Soil and Water Management at the Arlington Agricultural Research Station (20)

Landform-based Erosion Control for Stormwater Management
Landform-based Erosion Control for Stormwater ManagementLandform-based Erosion Control for Stormwater Management
Landform-based Erosion Control for Stormwater Management
 
SOQ (Sample)
SOQ (Sample)SOQ (Sample)
SOQ (Sample)
 
MEW Update to Moffett RAB
MEW Update to Moffett RABMEW Update to Moffett RAB
MEW Update to Moffett RAB
 
Wastewater Treatment Trends in the 21st Century - George Tchobanoglous, Unive...
Wastewater Treatment Trends in the 21st Century - George Tchobanoglous, Unive...Wastewater Treatment Trends in the 21st Century - George Tchobanoglous, Unive...
Wastewater Treatment Trends in the 21st Century - George Tchobanoglous, Unive...
 
Resource Recovery Panel
Resource Recovery PanelResource Recovery Panel
Resource Recovery Panel
 
Artificial recharge guide
Artificial recharge guideArtificial recharge guide
Artificial recharge guide
 
ACOE Coastal Storm Management Alternative for Jamaica Bay Communities
ACOE Coastal Storm Management Alternative for Jamaica Bay CommunitiesACOE Coastal Storm Management Alternative for Jamaica Bay Communities
ACOE Coastal Storm Management Alternative for Jamaica Bay Communities
 
B.Sc. Summary
B.Sc. SummaryB.Sc. Summary
B.Sc. Summary
 
Environmental Issues Related to Construction Projects
Environmental Issues Related to Construction ProjectsEnvironmental Issues Related to Construction Projects
Environmental Issues Related to Construction Projects
 
Aerial Recon in Bakken, ND
Aerial Recon in Bakken, NDAerial Recon in Bakken, ND
Aerial Recon in Bakken, ND
 
Lecture 1-CVS 445.ppt
Lecture 1-CVS 445.pptLecture 1-CVS 445.ppt
Lecture 1-CVS 445.ppt
 
Lecture 1-CVS 445.ppt
Lecture 1-CVS 445.pptLecture 1-CVS 445.ppt
Lecture 1-CVS 445.ppt
 
2012 Recent US Work Relating to Munitions in the Underwater Environment
2012 Recent US Work Relating to Munitions in the Underwater Environment2012 Recent US Work Relating to Munitions in the Underwater Environment
2012 Recent US Work Relating to Munitions in the Underwater Environment
 
Case Study Of A Successful Sesc Plan
Case Study Of A Successful Sesc PlanCase Study Of A Successful Sesc Plan
Case Study Of A Successful Sesc Plan
 
Mp ground water
Mp ground waterMp ground water
Mp ground water
 
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
A Methodology to Assess the Potential Impacts of Longwall Mining on Streams i...
 
"Green Infrastructure to Manage Combined Sewer Overflows and Flooding" by Emi...
"Green Infrastructure to Manage Combined Sewer Overflows and Flooding" by Emi..."Green Infrastructure to Manage Combined Sewer Overflows and Flooding" by Emi...
"Green Infrastructure to Manage Combined Sewer Overflows and Flooding" by Emi...
 
19 22
19 2219 22
19 22
 
Additions And Alterations
Additions And AlterationsAdditions And Alterations
Additions And Alterations
 
State & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
State & Federal Regulation of Hydraulic Fracturing: A Comparative AnalysisState & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
State & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
 

Recently uploaded

The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
heathfieldcps1
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
SoniaTolstoy
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 

Recently uploaded (20)

Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 

Organic Soil and Water Management at the Arlington Agricultural Research Station

  • 1. Organic Soil and Water Management at the Arlington Agricultural Research Station Project Background Introduction Design Standards / Constraints Badger Lane N In recent years multiple environmental Standards concerns have arisen in the organic •Erosion must be limited to the S area at the Arlington Agriculture designated tolerable soil loss (T) for Research Station (AARS) . This area the soil type (NR 151.02) can be seen in Figure 1 on the right. The two primary areas of concern are •Gully erosion must be eliminated Hopkins Road soil erosion and the need for evaluation of the capacity and stability of a •Waterway needs to convey flow waterway draining a large watershed without over topping or eroding north of the organic area. Constraints •Area needs to remain under organic Problem Description Ramsey Road management Erosion Control •Flexibility in field boundaries for •Significant erosion taking place in Area of concern for Organic area research projects boundary. erosion organic fields due to steep slopes and the high level of tillage Location of waterway Arlington Research •Limit Costs to $10,000 over three being evaluated Station Headquarters years Figure 1: Aerial Photograph of Organic Area •Also, gullies are forming in spots due at Arlington Agriculture Research Station Approach to natural topography and erosion of old diversions NRCS Design Process: Waterway Design •Waterway designed and constructed 1.Determine client objectives 2.Conduct a resource inventory without proper watershed delineation 3.Analyze resource data to identify problems and opportunities •Waterway conveys runoff from a 4.Formulate and evaluate resource nearly 200 acre watershed that includes alternatives both research station and private 5.Document the client’s planning decisions farmland Figure 2: Photograph of Existing Waterway Team Members: Josh Gable,Tyler Hastings, Lis Nimani, Ryan Stenjem Advisors: John Panuska, Anita Thompson
  • 2. Organic Soil and Water Management at the Arlington Agricultural Research Station Waterway Analysis Purpose The Design Storm: SCS Type II HydroCAD In 2008, a grassed waterway was constructed 10–year, 24–hour storm The Stormwater Modeling Software, HydroCAD, uses hydrology principles that were developed by the NRCS as well as various to transport flows from an upstream hydraulic calculations. It uses the TR-55 method for calculating Time watershed, through the AARS Organic Corner of Concentration (tc) values and gives unique hydrographs through waterways, ponds, culverts and various other hydraulic components. (denoted with blue arrows in Figure 3). Because of the immediate need for the channel, a proper engineering design was not carried out. In order to verify that this waterway was adequately built, HydroCAD was used to model the watershed and waterway. Figure 4 Design Storm Unit Hydrograph, exported from HydroCAD Figure 1 Main Waterway, in Organic Corner, AARS Figure 6 HydroCAD Layout Map Results Figure 5 Design Storm Depth vs. Time Graph, exported from HydroCAD Figure 2 Cross-Section of Main Waterway Watershed Parameters The Contributing Watershed Table 1 Contributing Watershed Characteristics Sub - Time of Concentration, Tc Area (acres) Curve Number, CN Watershed (min) 1 8.2 76 15.6 2 13.4 77 23.2 3 34.4 70 37 Figure 7 Final Hydrograph for Main Waterway 4 42.5 76 32.1 5 127.2 76 78.4 Table 4 10-year, 24-hr Storm Results 6 9.2 76 13.1 Reach Channel Capacity (cfs) Peak Flow (cfs) Max Velocity (ft/s) 7 6.9 76 19.7 1 63.23 17.2 2.2 8 12.2 76 20.2 2 44.84 38.52 1.25 Table 2 Outlet Characteristics Main 316.5 141.34 5 Culvert Diameter (in) Length (ft) Slope (%) 1 24 50.3 2.25 Table 5 25-year, 24-hr Storm Results 2 18 38 1.37 Reach Channel Capacity (cfs) Peak Flow (cfs) Max Velocity (ft/s) 3 18 38 0.66 1 63.23 19.3 2.27 4 24 36 1.78 2 44.84 49.85 1.33 5 36 28.6 2.24 6 36 28.6 0.98 Main 316.5 208.5 5.57 7 18 24.3 3.29 Table 6 100-year, 24-hr Storm Results Table 3 Sub-Watershed Characteristics Reach Channel Capacity (cfs) Peak Flow (cfs) Max Velocity (ft/s) Trapezoidal Cross-Section Channel Length Channel Slope Reach Manning’s No. 1 63.23 20.71 2.32 bottom width (ft) depth (ft) side-slope (horizontal/vertical) (ft) (%) 2 44.84 72.86 1.44 1 10 1 10 1400 0.85 0.033 Main 316.5 257.95 5.9 2 8 1.5 10 1400 0.43 0.07 Main 12 2 6.7 1050 0.84 0.026 Conclusion In modeling the upstream watershed, culverts After completing the HydroCAD model were modeled as outlets to ponds with storage analyzing the waterway in the Organic Corner behind. Where water had the potential to flow and its upstream watershed, we have Figure 3 Contour Map of Watershed with 4 ft Contours over a roadway upon a culvert reaching capacity, determined that the current waterway is more Waterway – Organic Corner the roadway way was treated as a broad-crested than adequate for handling flows from the Watershed Boundary weir as an outlet to a pond. 4 ft Contour Lines design storm.
  • 3. Organic Soil and Water Management at the Arlington Agricultural Research Station Erosion Management Problem Description Field Soil Slope Slope Design Options (%) Loss Length (ton/ac/yr) (ft) •Steep Slopes and intensive tillage •Option 1 – Implement strip cropping operations have lead to erosion. 401 4.3 140 3.7 and make three fields of equal width 402 2.9 160 2.5 out of fields 447 A and B, and also for •The DNR requires that erosion be 403 A 2.4 160 2.0 fields 404 and 403C-S and N. less than the designated tolerable soil 403 B 3.4 155 3.0 Field Soil Loss loss (T) for the soil type. (NR 403 C-N 6.5 180 4.9 (ton/ac/yr) 151.02). 403 C-S 5.5 180 4.5 401 4.3 404 7.4 175 5.6 402 2.9 •The tolerable soil loss for the 446 3.3 150 2.3 403 A 2.4 Organic Fields are 5 ton/acre/year. 447 A 4.9 175 4.1 403 B 3.4 (Web Soil Survey). 447 B 4.5 175 3.5 403 C-N Figure 1: Current field boundaries with respective 403 C-S 4.8 •Fields 403 C-N, 403 C-S, and 404 soil loss and LS Inputs. 404 are currently above T, and fields 447 Universal Soil Loss Equation 446 2.6 A and B are near T (Figure 1), so they A=RKLSCP 447 A 4.1 require best management practices, R Rainfall Erosivity Factor 447 B Figure 4: Soil loss after strip cropping such as strip cropping, terracing, or K Soil Erodibility Factor contouring, in order to reduce soil LS Topographic Factor (Slope Length and loss. Slope) •Option 2 – Design a terrace system to CP Cropping Management Factors break up the slope length along the steepest slopes Figure 2: USLE Equation RUSLE2 Field Soil Loss (ton/ac/yr) 401 4.3 •Is a computer program that utilizes 402 2.9 the Universal Soil Loss Equation 403 A 2.4 (USLE) to model rill and interrill 403 B 3.4 erosion. See Figure 2. 404 403 C-N 4.3 •Used a crop rotation of Winter 403 C-S wheat, 3 years alfalfa, Corn grain, 446 2.6 soybeans. 447 A 3.9 Figure 3: Screen shot of RUSLE2 447 B •Tillage operations of chisel plow and Figure 5: Soil loss after terraced disk before planting and 2-3 cultivations during spring.
  • 4. Organic Soil and Water Management at the Arlington Agricultural Research Station Designs and Recommendations Designs and Recommendations Final Terrace Design Q = 2.0 ft3/s (determined from HydroCAD) Waterway Vpermissible = 1.5 - 5 ft/s In evaluating the waterway it was determined A = 3.5 ft2 that the current channel will be sufficient to S=2% handle the peak flow from a 10 yr – 24 hour storm event. This determination was made primarily using the results from the HydroCAD model. Erosion Control After Conversations with the Arlington Research Station staff a modified plan was devised. The impact of this proposed plan on erosion rates can be seen in Table 1. Figure 2: Proposed Terrace Cross Section •Terraces will be implemented in fields 404 and 403C (See Figure1 and Figure 2) Table 1: Proposal Impact on Erosion •A diversion will be cut along the top of field Rates 447 A to reduce the occurrence of gulley Field Current Expected erosion. (See Figure 1) Soil Loss Soil Loss Figure 1: Location for Proposed Construction (ton/ac/yr) (ton/ac/yr) •Strip Cropping is also recommended in the 401 4.3 4.3 area of fields 447 A and 447 B. Terrace Spacing Calculation 402 2.9 2.9 H.I. = (xs + y) (100/s) 403 A 2.4 2.4 •Impact of proposal can be seen in Table 1 403 B 3.4 3.4 H.I. = horizontal interval in feet 403 C-N 6.5 4.3 Channel Capacity Calculation x = constant determined by geographic location 403 C-S 5.5 4.3 Q = V*A s = land slope in percent 404 7.4 4.3 V = (1.49/n) * R(2/3)*S(1/2) y = constant determined by cropping and soil erodibility 446 3.3 3.3 447 A 4.9 4.1 Q = Peak flow rate in Channel (ft3/s) V = Flow velocity (ft/s) H.I .= (0.5 * 6 + 4) (100/6) 447 B 4.5 4.1 A = Cross sectional area of channel n = Manning’s Roughness Coefficient (varies H.I. = 140 depending on vegetation growth from 0.035 *raised to 150 feet due to farming equipment to 0.075) restrictions Special Thanks to: R = Hydraulic radius of channel (ft) Jeff Breuer, Darwin Frye, Scott S = Channel slope (ft/ft) Mueller, Matt Repking, Anita Thompson, and John Panuska