SlideShare a Scribd company logo
1 of 41
Download to read offline
Industrial Services, Los Angeles
USC Senior Design Project
December 10, 2003
Rodrigo Del Cid Jr.
Cole Grundstedt
Mr. Ted Mayeshiba
Ms. Priscila Delgado
Ms. Maria Cepeda
Prepared by:
Clarissa Umali
Special thanks to:
Dr. F. Stan Settles
1
Executive Summary
Goodwill Industrial Services, Los Angeles, had a problem—their factory floor could not
accommodate multiple product processes, which they believed resulted in the department
hitting a profit plateau. It was also observed that there was a problem with the hanger
sorting process. It had been done in the department longer than any other product;
however, it took up an enormous area for processing and storage of unsorted, in process,
and sorted hanger boxes. Another perceived issue was a lack of standardization in the
method for approaching new products and services.
To tackle the first problem of the hanger process, profitability was calculated with respect
to the amount of space it required—for both the work itself and storage. This number
was compared to another common product that used far less space—specifically Paul
Mitchell Products. Using historical data and space requirements, it was determined that
the hanger sorting process earns $0.20/day per square foot of floor space while Paul
Mitchell earns nearly four times as much at $0.79/day per square foot. After analysis of
these numbers it was concluded that ideally, the hanger sorting process should be
removed because of the inefficiency inherent to the process. Improving the process itself
was deemed futile because the process would still require a large amount of storage space
regardless of the improvements made within the process.
At present, however, the hanger sorting process cannot be removed from the department
because there are mentally and physically handicapped client-employees that cannot do
anything else except sort and pack hangers. Taking this into account, it was
recommended that it be confined to the back area of the factory floor (see Appendix K).
This way the large amount of boxes needed to complete the process will not interfere
with the other processes of the factory. Different function levels of workers were
separated within the hanger process layout so as to balance the production line and
smooth the flow of product within the different function areas.
In regards to all other product processes, there are two different types of products—one
where only one or two tasks must be done to complete the task (e.g. placing a sticker, or
2
dressing a doll), and one where many tasks must be completed to create a finished
product. Layouts were created for individual groups processing each product type
overseen by one or two team leaders; this is how the factory is presently managed (see
Appendix H & I). Both layouts include ideas and suggestions for line balancing and flow
smoothing.
To help the supervisors better assign client-employees to the tasks required for a process,
the “Hourglass Flow Model” was created (see Appendix D). It breaks down the
fundamental elements of all products received and shows how the difficulty and
complexity of each task relates to its location in the overall flow from raw material to
finished good. This model is applicable to every category of product and layout.
If for some reason, the hanger process is eliminated from the Los Angeles facility, a
factory layout that did not contain hangers was included (see Appendix J). This layout
can accommodate up to four different product processes and has a smooth and logical
flow.
In all layout models, safety was assured by maintaining the preexisting dotted yellow-line
in the factory. This line separates the work areas from the forklift traffic lane and assures
an unobstructed path to the emergency exit and fire extinguisher. The location of pallets
is such that the forklift can easily access them without infringing on the work areas. It
was also suggested that all raw material pallets be deposited after regular work hours and
in a quantity that can be worked through in at least one day for each process in the
factory. This insures that there is little forklift traffic during the busiest hours, which
reduces risk of accidents.
Given the proposed layouts, a list of the materials and equipment that were needed on the
factory floor was made. This list does not account for any equipment already existing. It
should be mentioned that Goodwill Industries, Los Angeles does not currently have the
man power or customer base to employ our layouts fully. They should be considered an
attainable goal that, when reached, should result in increased profits, improved utilization
of the factory floor, and an all-around safer work environment for everyone.
3
Table of Contents
Introduction...................................................................................................Page 4
Employees......................................................................................................Page 4
Hourglass Flow Model................................................................................. Page 6
Problem Statement........................................................................................Page 8
Hanger Profitability......................................................................................Page 9
Disadvantages of hangers.................................................................Page 9
Profitability comparison................................................................... Page 10
Advantages of hangers......................................................................Page 11
Heat Sealing Profitability............................................................................. Page 12
Layout Descriptions and Analyses
Legend............................................................................................... Page 12
Original Layout.................................................................................Page 15
Product Categorization..................................................................... Page 16
Single Task Product..............................................................Page 17
Smoothing Production..............................................Page 18
Multi-task Product................................................................ Page 19
Smoothing Production..............................................Page 20
Proposed Layout (no hangers)......................................................... Page 21
Proposed Layout (with hangers)...................................................... Page 23
Smoothing Production..........................................................Page 26
Conclusions
Equipment requirements.................................................................. Page 27
Final recommendations....................................................................Page 27
Appendices.....................................................................................................Page 29
4
Introduction
Goodwill Industries of Southern California funds programs that train unemployed and
underemployed men and women so that many will be able to transition into a mainstream
work environment with the proper skills and work habits. As shown in its organizational
values, Goodwill is dedicated to helping people help themselves. Goodwill encourages
the workers, called client-employees, to strive to achieve their highest potential, since
their needs are the reason why the organization exists. The Los Angeles facility was the
focus of our project, being the largest of the three facilities in the greater Los Angeles
area, and providing a greater opportunity of improvement. More specifically, we worked
with the Industrial Services division which forms contracts with outside companies to do
the simple tasks for them such as sorting and packaging the goods. Some of these
companies include Paul Mitchell hair products and Auntie-Itch cream products.
Employees
The client-employees who work on the tasks daily include people with physical or mental
disabilities and other vocational disadvantages. There are three levels of client-
employees—low, medium, and high-functioning. They are placed into one of these
categories based on their abilities. An outside work environment is not an option for low-
functioning client-employees, because their disabilities or barriers are too severe to allow
for a successful transition outside of Goodwill. Therefore, Goodwill provides them a
long-term work opportunity that builds in them a sense of accomplishment and pride in
their work.
The low-functioning client-employees can only perform single or simple tasks. Some
examples of the capabilities and responsibilities of low-functioning client-employees
5
include executing a “yes” or “no” decision, wrapping or unwrapping a product, sorting,
packing a single item into a box, and performing checks (such as whether a cap is
tightened or not). The abilities of medium-functioning client-employees are very similar
to the low-functioning client-employees; however, they can perform two tasks
simultaneously. For example, a medium-functioning client-employee can sort and pack,
whereas a low-functioning client-employee can only sort or pack.
For high-functioning client-employees, the work experience that Goodwill provides them
must be “meaningful,” so that the individual can be trained for successful transition into
outside employment such as mail house or assembly environments. Some of the work
skills and work habits that are taught to the client-employees are attendance, hygiene,
inter-personal interactions, communication skills, work place conduct, and following
directions. High-functioning client-employees can perform more complex tasks and
make multiple decisions, some of which include lifting, heat-sealing, labeling, and
packing multiple items. Lifting is usually performed by high-functioning client-
employees because of its physical nature. Client-employees with physical and more
severe mental disabilities would not be able to perform such a task. Heat-sealing is one
of the more dangerous tasks and requires that the client-employee understand the safety
considerations of the task. Labeling is left to the high-functioning client-employees
simply because it requires accuracy of label placement, especially for the smaller
packages and boxes.
6
Material handler is the name given to a high functioning worker; however, he or she is
not classified as a client-employee for several reasons. They are much more able-bodied
to carry out physical tasks such as unloading packages, staging, shrink-wrapping
completed pallets, palletizing and de-palletizing, and distributing materials to the client-
employees. Material handlers are also given an hourly wage, rather than being paid by a
prorated piece-rate based on minimum wage, which is how the client-employees are paid.
Material handlers are classified as high-functioning, not necessarily because of the
complexity of the tasks, but because of the number of concurrent tasks that they are
assigned to do. The material handlers are responsible for many more duties than the
client-employees, especially the tasks at the beginning and at the end of the production
line.
The Hourglass Flow Model
Picture 1
The Hourglass flow model is a representation of
the flow of each product from the beginning
the end of the production process. As seen in
to
Picture 1, the complex tasks are those involving
the raw materials and finished goods. In these
areas, high-functioning workers are needed in
order to accomplish these tasks. After the
material handlers have prepared the raw
materials to be worked upon, the lower-
7
functioning workers can perform the simpler tasks. Then the product returns to the
material handlers who then complete the tasks at the end of the production process. T
Hourglass flow of the work break down sheet can be observed in Chart 1.
Chart 1
Goodwill Industries O
he
5 Shrinkwrap unit box 7.0000 428.571
6 8.0000 375.000
7 Apply address label 3.0000 1000.000
Prevailing Wage
f So Cal Break Down Sheet
COMPANY: Paul Mitchell
DESCRIPTION: Build PM Shines/Dir
ITEM: PM shines/Direct Mail
Assembler=$8.47
Pack unit box with 1 D9Y, 1 D6RV, 1
Processing liquid, check for cap tightened
Pack unit box inside corrugated mailer
along with letter and mini paper swatch
Material Handler = $8.76
ect Mail
STEP
NO. TASK
SEC.
PER/UNIT
STD./UNIT
PER/HR
H 1 Unload material 0.5000 6000.000
H 2 Staging material 0.5000 6000.000
L/M 3 Build unit box 5.0000 600.000
L/M 4 12.0000 250.000
H
H
H
This segment is taken from the Paul Mitchell work break-down sheet. The work break-
down sheets allow the production supervisor and other staff members to see the tasks
flow
e
performed by the client-employees broken down step by step. Also included is the
amount of time it takes to perform each task, the pay rate for performing each task, and
hourly wages. By examining the tasks more closely, one can see that the Hourglass
model is in fact being followed. As noted in Chart 1, the tasks in the beginning and at th
end of the production process are being performed by the high-functioning material
handlers, while the work of the lower and medium-functioning client-employees are
clustered in the center of the process.
8
Chart 2
wn Sheet
COMPANY: Sewing Collection
DESCRIPTION: Sort And Pack Ha
ITEM: Hangers
STEP
NO. TASK
SEC.
PER/UNIT
STD./UNIT
PER/HR
L 1 Sort Hangers 3.0000 1000.000
L 2 Pack Hangers 3.0000 1000.000
M 3 Sort And Pack Hangers 4.5000 666.667
Prevailing Wage
Assembler=$8.47
Material Handler = $8.76
Goodwill Industries Of So Cal Break Do
ngers
Another example supporting the Hourglass flow model, found in Chart 2 above, is for the
hanger process, which Goodwill has been doing for a long time. The material handlers’
jobs are not listed in the tasks, but are being executed. In the beginning of the process
material handlers bring the unsorted boxes of hangers to the warehouse and distribute
them to the client-employees. The low and medium-functioning client-employees then
sort out the different types of hangers, and pack them into separate boxes. Finally, the
material handlers once again perform their duties on the completed hanger boxes.
Having different levels of client-employees exacerbates the difficulty of creating an
efficient flow in the main warehouse.
Problem Statement
The main problem with Goodwill Industrial Services is the inefficient flow in the main
of the inefficient flow, the main warehouse is at capacity for
rial
warehouse. Because
processing multiple products simultaneously. This, in turn, limits the amount of
customers Goodwill Industrial Services can have. With profits leveling off, it was
important to address this problem to be able to expand and grow Goodwill Indust
9
Services’ customer base. With an expanded customer base, revenues can increase a
more jobs can be created.
nd
Hangers
The hanger process is quite simple, yet very time and space consuming. There are about
t types of hangers. The hangers are then sorted using a hanger sorting
fferent
through
out wh r it is, and place it in its corresponding box. This includes having
it is
24 differen
apparatus which facilitates the sorting operation, yet can only be done by a high
functioning client-employee. Currently the unsorted boxes contain about 3 or 4 di
types of hangers which even a low function client-employee can individually sort
and separate. A worker has to pick up each individual hanger and decipher the type, and
place it in the box it belongs to. The hangers are then neatly packaged into individual
boxes, which usually hold at least 100 hangers of one specific type.
Disadvantages
The whole hanger process is very time consuming. Each client-employee has to figure
ich type of hange
to pick it out of a box with many hangers, which are usually tangled in one way or
another, and looking at it carefully because many of the hangers look very similar. If the
client-employee is just sorting, then they put it in another box without worrying that
neatly placed. If the client-employee is sorting and packing, then they have to carefully
place it neatly in the packaging box. Whether the client-employee is only packing, or
sorting and packing, they will be surrounded by at least 4 large boxes, which leads to the
next point.
10
The hanger process is very space consuming, because each client-employee needs at least
still
he hanger process uses too much space on the factory floor and the main building. This
Total Area Used = 9915 sq. ft.
aul Mitchell Product Total Area Used = 420 sq. ft.
he results indicate that a Paul Mitchell product is much more profitable considering the
4 boxes around them to be able to place the hangers in the correct box. This takes up a
lot of useful floor space because many times they might have 6 or 7 boxes around them,
which are not put to use. Also, because of the high turnaround time, the unfinished and
finished boxes take up a lot of space as was discovered during our many visits to
Goodwill Industrial Services. The turnaround time has improved, but hangers are
very much space consuming.
T
includes space for the process itself and for raw and finished materials. Hangers account
for nearly 60% of the revenue, but use over 75% of the whole facility space. One needs
to look at the product profitability in dollars per square foot between hangers and a Paul
Mitchell.
Hangers
Total Profit/Month = $60,000
Profit/sq.ft./day = $0.20
P
Total Profit/Month = $10,000
Profit/sq.ft./day = $0.79
T
amount of floor space it uses. Having mostly Paul Mitchell products would increase
revenues by about 4 times according to the profit per square foot.
11
It is very difficult to provide a flow or an efficient time production with hangers. It is
y
The hanger process provides a productive starting point for new client-employees.
he hanger process also provides jobs to client-employees of different skill levels. A
can
g
angers are always available to be sorted and packaged providing year round jobs. The
hanger process provides jobs during downtime. This is important because when certain
difficult because every worker is working at their pace. Also, the hanger process is ver
time consuming meaning some workers only finish about one box a day. Although the
client-employees are being paid according to their number of completed hanger boxes,
they are taking up a certain amount of space on the factory floor which can otherwise be
used for more profitable products. Furthermore, they are slowing the hanger process,
which can lead to starvation or a high turnaround time.
Advantages
Goodwill Industrial Services many times serves solely as a transition period for the
client-employees. They begin to work and learn at Goodwill Industrial Services, and
when the client-employees reach an adequate skill level, they are transferred to higher
skill demanding employment.
T
low-skilled client-employee can be employed to either sort or package hangers. They
also do both, although most start off by just doing one of the tasks. Here, many low-
skilled client-employees can be used which would otherwise not have any value-addin
tasks. Furthermore, the low-skilled client-employees gain familiarity with the hangers,
increasing their productivity over time.
H
12
products and lines are finished, workers can be placed to work at the hanger process. The
hanger process is always available to be worked on.
The hangers should be eliminated to provide more space for other more profitable
products to come through Goodwill Industrial Services. If the hangers are to be kept,
they are to be kept solely for the advantages listed.
Heat Sealing Process
The heat-sealing machine needs to be removed from the factory floor. The heat-sealing
10% of the floor space, yet generate less than 5% of the revenue.
to
r
machine takes up over
The heat-sealing machine is also used less than 10% of the total time. Furthermore the
heat-sealing machine obstructs the flow on the factory floor. Eliminating it from the
factory floor would greatly improve the floor design and flow. The only reasons for
keeping the heat-sealing machine would be if it brings in more revenue, or if it is vital
receive more customers.
Layouts: Before and Afte
he following is a list of symbols used in our layout drawings:
workers
at are responsible for each client-employee in their group. They make
T
This figure represents a supervisor/team leader. They are wage
th
sure everyone is on task and performing their functions correctly. They
are also responsible for keeping track of the amount of work each client-e
doing so they can be paid piecewise.
mployee is
13
These three figures represent the low (red), medium (yellow),
nd high (green) functioning client-employees. Their job
because of
ey are high functioning workers. They have the mental ability to
lim
ously discussed.
useful to understand where everything comes from and goes to and how it gets there.
t
t pallets of goods. They a distinguished into
o groups—raw material and finished goods. Raw material is the light
y
It is read
re-palletized. It
a
responsibilities and capabilities were previously discussed.
This figure represents the material handlers. They are green
th
handler several different kinds of tasks and have no physical disability to
functions in handling material. Their job responsibilities were previ
This blue arrow represents product flow on the layout drawings. This
it their
is
This helps to produce a product flow that is both organized and efficien
bottlenecks and starvation.
These two symbols represen
with less
tw
colored pallet. It has arrived from a customer as is and has not been
worked through. All material must be de-palletized, sorted, and
distributed by the material handlers before it can be worked-through b
the client-employees. Finished goods is the dark colored pallet.
back to customers. The product has already been worked on, boxed, and
y to be shipped
14
is important to note the location of each type of pallet. These symbols work with the blue
arrow (above) to demonstrate a logical and organized flow.
This symbol represents a pre-existing painted yellow line on the
her
s
his symbol represents a table in the layout. They are labeled by
his symbol represents a roller conveyor. They are in 10-foot
t
his symbol represents a handcart. The factory already has a
sed to
factory floor. It is used to mark the boundary of the work areas w
cross. This keeps all factory workers safe. This line also marks emergency exit paths
and fire extinguisher access and as such all path integrities must be maintained.
Permanent work areas cannot be place outside or on top of these pre-existing area
marked by the dotted yellow line.
e the forklift cannot
T
their lengths which are the dimensions of the pre-existing factory
tables (requirements are discussed later)
T
sections. The factory already has a number of these conveyors
(requirements are discussed later). The conveyor helps to collec
items in one area and reduces the effort and time required to move
another area.
it a short distance to
T
number of these however they are not in use. The handcart is u
transport items a short distance.
15
Original Layout
actory layout as it exists now. It is set up
ed correcting.
being used to store many
nother area of wasted space is the lower-right corner where the
left
this
he entire left side of the warehouse is devoted to hangers. It is clear to see that this area
This is the original f
to do two products—one of them being hangers and the other
being a product requiring a production line.
There are a few items with this layout that ne
First of all there is wasted space—more specifically in the
upper-right corner of the warehouse. This area is currently
items including broken conveyors, unused handcarts and machines, and a number of
tables—some broken.
A
production line is. There is a lot of space on the right of this
production line and since there are pallets being stored on the
taking up that space, there is only room for one production line in
area.
T
is quite cluttered. The nature of task of hanger sorting
requires a large amount of space and a large number of
boxes. This yields a product flow that is both difficult to
understand and visualize. It is this reason that there are no
blue arrows to mark the product flow. The location of the
16
raw material and finished goods pallets in all areas of the warehouse appears to be
arbitrary with no concrete product flow in mind.
The heating tunnel takes up a large portion of
r
roduct Categorization
the upper-left corner. This leaves little room fo
anything else given the constraints of the dotted-
yellow line.
P
dwill receives are broken down into three categories. The first
isjointed
.
t-
it
rials are
consideration from the third product type—the “multi-task” product.
All the products that Goo
is hanger sorting. It was given its own category because it requires much more
workspace than any another product, it has the slowest throughput, and it has a d
product flow. Because of these reasons, it requires its own separate consideration in the
factory layouts. The second type of product Goodwill receives is a “single-task” product
This is a product that, after initial de-palletizing and staging, requires only one or two
tasks before it can be re-boxed and re-palletized. An example of an actual Goodwill
single-task product is the “Scoobie-Doo doll”. After the dolls are staged for the clien
employees, it has to be removed from its bag, dressed and attached to a costume. Then
is placed back in the bag and sent off to be re-boxed. What makes this category
important is that all the tasks required (save the material handlers’ tasks) can be
completed by one person or up to three people in a small sub-group and few mate
required (if any) to complete these intermediate steps. This gives it separate
17
The “multi-task” product has a large number of tasks to be completed after in
and before re-palletizing. An example of an actual Goodwill multi-tas
itial staging
k product is
-line
es their
perations. Each group may have a different category of product to work through so we
“Auntie-itch cream”. After initial staging the individual cream tubes must have a sticker
adhered to them, then be placed in their individual boxes, then have another sticker
placed on the front and back of the box, and finally be placed inside larger boxes which
are then taped and palletized. This product type requires a more traditional assembly
setup and each station requires intermediate materials to complete their tasks in contrast
to the single-task product that requires only what is in the initial palletized box.
The factory layouts are broken down into groups, as this is how Goodwill manag
o
created a layout of each group based on product type.
Single-task Product.
This is a modification of a setup that was in the original layout. Instead of having two
oller conveyor adjacent to one of the rows, a conveyor is placed in
tter
.
rows of tables with a r
the aisle of the two rows leaving adequate room on both sides of the conveyor for a
person to walk back and forth. This solves a few problems. First it allows team leaders
to be closer to the client-
employees and provide be
supervision and guidance
Second it puts the team
leader in control of all goods
18
so as to better keep track of a client-employee’s production. The proposed setup does
allow a product to continue after the client-employee has worked on it until the team
leader marks down their progress and places the item on the conveyor in the center.
From there it simply continues down the conveyor to the material handlers for boxing a
re-palletizing. Another change proposed is the implementation of the use of hand
the material handlers. Note: This proposal is not unique to the single-task produc
line; rather it is an overall factory-wide improvement suggestion. The use of handcarts
allows for more products to be distributed at one time by a material handler improvin
their efficiency. It also improves the overall ergonomic safety of the material handlers
requiring them to lift much less weight at one time. The material handlers with han
will take material from the raw material pallet and distribute the material to the memb
of both lines for work. Since each station does all the tasks required of the product (see
definition of single-task product) excluding staging and re-palletizing, the product goes
directly from each station to the conveyor (see blue product flow arrows). It was
previously said that all tasks are to be completed by one individual or a small sub-group
of no more than three. These sub-groups are displayed by a dotted square around them.
The members of this sub-group break up the tasks and each complete an entire produc
together. This is why there is only one arrow leaving each of these subgroups.
Smoothing Production Flow
It is important to insure that production flow is smooth from to
not
nd
carts by
tion
g
dcarts
ers
t
p to bottom. The material
t workers. The only place where this is a problem ishandlers are assumed to be the fastes
in staging; however they can easily control how much product is distributed to each
client-employee and can pace accordingly. Within the production line of client-
19
employees, each individual or sub-group is seen as the only intermediate step betwee
material handlers’ tasks. Since the client-employees will logically be working sl
than the material handlers, the only place where production flow needs to be analyzed
and controlled is within the sub-groups because they have more than one person affecti
production flow. Our recommendation is that within a particular sub-group, each clien
employee is of the same function level and works at the same pace. This can be seen on
our drawing that each member of a sub-group is of the same function level. By doing
this, it assures that there will be no bottlenecks or starvation within the sub-group and the
product will spend an equal amount of time with each person in the sub-group before
being placed on the conveyor. It should be mentioned that it could occur where the tasks
performed within a sub-group are not the same level of difficultly. In this situation, a
higher functioning worker should do the more complex task and a lower functioning
worker should do the simpler task. Another option would be to have two lower
functioning workers doing a simpler task to feed the higher functioning worker so as n
to starve his supply. In a single-task product, these aforementioned situations wi
occur often so a best guess judgment should be applied using these suggestions and the
layout as a base model.
n the
ower
ng
t-
ot
ll not
Multi-task Product
The layout appears the
sk
at
ed.
same as the single-ta
product layout except th
the conveyor was remov
20
Since there are multiple tasks to complete, a more traditional assembly-line model was
applied. This means that the tables and work surfaces act as the conveyor and the client-
employees will advance the product down the line. The area between the two table lines
allows enough room for two people to comfortably pass one another. It is assumed that
each team leader would be responsible for one table line. They would keep trac
intermediate progress by counting production for the day and totaling unfinished pr
at each station so each client-employee can get paid for their own contribution piecewis
The staging and re-palletizing areas are the same as the single-task product layout. In th
sense the blue product flow arrows are the same except in the client-employees’ areas
which logically advance down the table. The material handlers with handcarts, however
perform a slightly different function. Raw material is deposited at the first station, ei
by the staging crew or the handcart pusher, but at all the other stations, the handcart
pusher delivers intermediate supplies as needed. These supplies are not the main prod
rather they are items that are needed to complete each respective step. The handcart
pusher insures that each station has enough intermediate supplies to complete their tas
Smoothing Production Flow
k of
oduct
e.
is
,
ther
uct
ks.
gray. This is because the layout itself requires no
and
y
Each client-employee in this layout is
logical method of client-employee function distribution. This distribution is dictated by
the product being worked through and the complexity of tasks therein. The client-
employee function distribution must be applied in a way that smoothes production
balances the line. As mentioned earlier, this reduces bottlenecks and starvation at each
station. Before client-employees can be assigned to their respective tasks, the complexit
of each step and type of client-employee that can effectively perform the task must be
21
understood. After this, client-employees should be matched up with the most complex
tasks they can effectively perform. Doing this will normalize the throughput at each
station by having a faster worker perform a harder task and a slower worker perform a
easier task. After this is done, more tweaking may still be necessary. In a situation
where a station is being starved because the previous station is not working fast enou
it is recommended that an extra client-employee is put on the slower station to double the
input into the station that was once starved. In a situation were product is being
bottlenecked at a station because the client-employee is working too slowly for th
previous station, placing an extra worker on this station will speed up its throughput
Before additional workers are placed at a station in an attempt to solve flow problems,
production line and the effect of additional staff on the whole production must be
considered. As mentioned in the single-product layout, the material handlers are th
fastest workers and need not be considered in the smoothing of production flow; they
pace their material distribution as dictated by the client-employee production rate.
n
gh,
e
.
the
e
can
roposed Factory Layout (no hangers)P
yout is that the heating tunnel was removed
all
r-left
placed a line of raw material pallets in the center of the factory. All four production lines
The first thing to notice in the proposed la
from the upper-left corner of the factory. The entire upper-right corner was cleared of
unnecessary equipment, and the handcarts stored there are now being used by the
material handlers at each group. The factory floor has four main sections, the uppe
and right and the lower-right and left corners. There is therefore the potential of four
different product lines being processed simultaneously in each of the four areas. We
22
can
he raw material is delivered by the forklift. This will be done after client-employee
product
y
the
30
easily draw from these pallets to supply their lines (see blue product flow arrows).
T
work hours to assure everyone’s safety. The amount of product delivered to this area
shall be at least one day worth of work per production line. This assures that no
deliveries must be made during regular work hours. Material handlers will move the
pallets (using already available pallet jacks) to their respective staging areas. The
flow through the production lines is dependent on the type of product (single or multi-
task). The production lines shown in the factory layout are just an example of what can
be used, however it should be noted that the single-task production line requires slightl
more space due to the additional width of the conveyor. This adds 2 feet to the
production line width which makes it difficult to put two production lines in an area other
than the lower-left corner since this corner is the widest. The areas at the top of
factory floor can be used either for single or multi-task production. They are oriented
horizontally; this allows for the added width of the single-task production line. The
upper-right corner is a smaller area and restricts the length of any production line from
feet to 22 feet. The
production lines at the
top have material
flowing from out to in.
Raw material is staged
23
on the outside of the factory floor and fed through the production lines to the finished
goods in the center. After a finished goods pallet is created, the material handler (using
the pallet jack) moves the pallet to the yellow-dotted line on the edge of his respecti
work area. From here, the forklift can easily move material out of the factory and prepa
it for shipping. The forklift is not restricted from picking up finished goods pallets
outside of regular client-employee work hours because the location of the finished goods
pallets does not require the forklift to enter the work areas marked by the dotted yellow
line. The production lines in the
lower-left and right of the factory floor
move material from top to bottom—
from the staging area for raw material
at the top of the production line,
through the production line in a
manner governed by the product
classification (single or multi-task)
finished goods pallet is created, the material handler (again, using the pallet jack) moves
the pallet to the yellow-dotted line in the center, on the edge of his respective work area.
The forklift can, again, easily pick up the finished goods for shipping without entering the
work areas and maintaining the safety of the factory floor.
ve
re
, to the finished goods pallets at the bottom. After a
Proposed Factory Layout (with hangers)
The hanger sorting process is placed in the back or upper-right and left corners of the
factory floor. This was done because of the large amount of space and boxes and raw
24
material required of the process—it was placed out of the way of other processes as not to
impede on their flow rates due to
excess boxes. The bottom portion
of the factory is identical to the
previous layout with the exception
that the hanger process took up too much room to have a row of raw materials on both
sides of the floor. This row is now confined to the right side, and this group of raw
materials supplies both non-hanger production lines in the lower portion of the factory.
Raw material for hangers is now stored in the back of the warehouse in the center. The
process is broken up into two areas—one for medium functioning client-employees
(yellow in the upper-left) and one for low functioning client-employees (red in the upper-
right). Each area has its own supply of raw materials which is deposited by the forklift in
the same manner as the previous layout—at least a day’s worth of raw material for each
area.
In the low-functioning area material is deposited to the row of client-employees on the
top by the material handlers. The client-employees take hangers from the unsorted (light-
colored) box and sort them into
their respective boxes below them
(slightly-dark colored). From here
the material handlers take the
sorted hangers from the top row of
client-employees and deposit them
into the bottom row of low-functioning client-employees as needed. These client-
25
employees pack the hangers neatly in boxes (very-dark colored). From here the material
handlers take the packed hangers to the finished goods area in the medium-functioning
area upper-left corner area (follow the blue arrow). Here a material handler weighs,
counts, seals, and re-palletizes the hangers onto pallets at the each of the work area where
the forklift can access them easily. The low-functioning area could not have its own
finished goods area because of space constraints, however, the output of the low-
functioning area is very low so the amount of product that flows across the floor to the
finished goods area is extremely low and will not require much labor.
In the medium-functioning area material is deposited to each of the three rows of
medium-functioning client-employees
by the material handlers (using h
of course) from the raw material pa
Unlike the low-functioning client
employees, there is no intermediate step
between sorting and packing. Medium
function client-employees take the
unsorted hangers from the box where
material handlers originally deposited them (light-colored box) and then sorts and packs
them in the boxes below them (very-dark colored box). From there, the material handlers
take the packed and sorted boxes to the finished goods area where a material handler
again weights, counts, seals, and re-palletizes in same manner as previously mentio
All hangers will end at this one area. Hanger production is a slow process so it is
andcarts
llets.
-
-
ned.
26
unlikely that the material handlers will have too much work to do in these areas. They
could possibly “moonlight” in other production areas.
Smoothing Production Flow
To effectively smooth production flow in the hanger processing area, both the material
handlers and the team leaders need to keep an eye on how fast client-employees are
working. Since client-employees are not working from a table rather from a box, it is
unlikely that starvation will occur. If one low functioning client-employee is starved by
having no hangers to pack, that client-employee can be re-assigned to sorting until
enough sorted hangers are produced to justify a packing client-employee. The ratio
between the sorting and packing client-employees in the low-functioning area (upper-
right) can therefore be tweaked to smooth production. In the medium-functioning area,
the client-employees do both sorting and packing therefore it is infeasible for there to
bottlenecks and starvation within an individuals work area. Smooth production is simply
produced in this area by insuring each medium-functioning client-employee has enough
hangers and that all packed and sorted hanger boxes (very-dark colored) are taken to the
finished goods area in a timely manner. It is therefore ultimately up to the material
handlers and the team leaders to assure smooth production in the hanger processing area.
27
Conclusions
Total equipment needed on hand for increased utilization:
• 130 adjustable stools
- They need to be adjustable to fit each person’s height to provide the correct
working posture. They also need to be rotary, for the client-employees working
on the hangers can easily turn to place hangers in specific boxes.
• 24 low tables for hanger sorting
- The tables need to be low so the client-employees have an easier time reaching
into the boxes to pull out the hangers. It will decrease muscle strains and decrease
sorting and packaging times.
• 32 regular standard height tables
- These tables are needed for other product processes.
• 2 wheelchair height tables
- These need to be available for the client-employees who are wheelchair bound.
• 6 carts
- With these carts material handlers can easily transport raw and finished materials
from the client-employees to the unfinished and finished crates. This will lessen
the physical work material handlers have to do decreasing the chances for injury.
To increase flow through a production line, the hourglass theory was proposed. This
stated that the high functioning client-employees are to be placed at the beginning and
end of processes, while the medium and low functioning client-employees dually
working in the middle of the line, to balance the product flow. To increase overall
factory utilization different layouts with production lines have been proposed. These
layouts augment productivity through the specific placement of raw materials, client-
employees, supervisors, and finished goods. In these layouts it is recommended that the
heat-sealing machine and the hanger process be removed for financial reasons.
28
Removing them would greatly increase the amount of available space for our proposed
layouts as well as increase revenue. If the hangers are to be kept, then a layout is
proposed where the hanger process would not hinder the rest of the factory floor flow.
The use of the layouts will also increase worker and space utilization. With this, profits
will increase while creating a safer working environment which will ultimately lead to
better products.
29
Appendix A
30
Appendix B
31
Appendix C
32
Appendix D
33
Appendix E
34
Appendix F
35
Appendix G
36
Appendix H
37
Appendix I
38
Appendix J
39
Appendix K

More Related Content

What's hot

Lean manufacturing ppt download link: http://www.vpresentationslides.com/lean...
Lean manufacturing ppt download link: http://www.vpresentationslides.com/lean...Lean manufacturing ppt download link: http://www.vpresentationslides.com/lean...
Lean manufacturing ppt download link: http://www.vpresentationslides.com/lean...shreyas desai
 
Organisation study at BILVA MOULDS PVT LTD
Organisation study at BILVA MOULDS PVT LTDOrganisation study at BILVA MOULDS PVT LTD
Organisation study at BILVA MOULDS PVT LTDRahul G
 
Generic Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S DesrocherGeneric Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S DesrocherAlan Desrocher
 
Lean Kanban Systems Training Module
Lean Kanban Systems Training ModuleLean Kanban Systems Training Module
Lean Kanban Systems Training ModuleFrank-G. Adler
 
Operations Research & Methodology project report
Operations Research & Methodology  project reportOperations Research & Methodology  project report
Operations Research & Methodology project reportPankaj Kumar Dwivedi
 
Lean Manufacturing
Lean ManufacturingLean Manufacturing
Lean ManufacturingSocheat Veng
 
Vrundavan Plastic Engg. Works, Ahmedabad, Plastic Machinery
Vrundavan Plastic Engg. Works, Ahmedabad, Plastic MachineryVrundavan Plastic Engg. Works, Ahmedabad, Plastic Machinery
Vrundavan Plastic Engg. Works, Ahmedabad, Plastic MachineryIndiaMART InterMESH Limited
 

What's hot (9)

Lean manufacturing ppt download link: http://www.vpresentationslides.com/lean...
Lean manufacturing ppt download link: http://www.vpresentationslides.com/lean...Lean manufacturing ppt download link: http://www.vpresentationslides.com/lean...
Lean manufacturing ppt download link: http://www.vpresentationslides.com/lean...
 
BASICS OF LEAN MANUFACTURING
BASICS OF LEAN MANUFACTURINGBASICS OF LEAN MANUFACTURING
BASICS OF LEAN MANUFACTURING
 
Organisation study at BILVA MOULDS PVT LTD
Organisation study at BILVA MOULDS PVT LTDOrganisation study at BILVA MOULDS PVT LTD
Organisation study at BILVA MOULDS PVT LTD
 
Generic Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S DesrocherGeneric Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S Desrocher
 
Lean manufacturing principles
Lean manufacturing principlesLean manufacturing principles
Lean manufacturing principles
 
Lean Kanban Systems Training Module
Lean Kanban Systems Training ModuleLean Kanban Systems Training Module
Lean Kanban Systems Training Module
 
Operations Research & Methodology project report
Operations Research & Methodology  project reportOperations Research & Methodology  project report
Operations Research & Methodology project report
 
Lean Manufacturing
Lean ManufacturingLean Manufacturing
Lean Manufacturing
 
Vrundavan Plastic Engg. Works, Ahmedabad, Plastic Machinery
Vrundavan Plastic Engg. Works, Ahmedabad, Plastic MachineryVrundavan Plastic Engg. Works, Ahmedabad, Plastic Machinery
Vrundavan Plastic Engg. Works, Ahmedabad, Plastic Machinery
 

Viewers also liked

MGM Resorts International Eastern Europe Market Entry Proposal
MGM Resorts International Eastern Europe Market Entry ProposalMGM Resorts International Eastern Europe Market Entry Proposal
MGM Resorts International Eastern Europe Market Entry ProposalCole S. Grundstedt MBA, PMP®
 
Market Opportunity Analysis - The International School of Hospitality (TISOH)
Market Opportunity Analysis - The International School of Hospitality (TISOH)Market Opportunity Analysis - The International School of Hospitality (TISOH)
Market Opportunity Analysis - The International School of Hospitality (TISOH)Cole S. Grundstedt MBA, PMP®
 
Strategic Marketing Plan - KONE Product Launch in Germany
Strategic Marketing Plan - KONE Product Launch in GermanyStrategic Marketing Plan - KONE Product Launch in Germany
Strategic Marketing Plan - KONE Product Launch in GermanyCole S. Grundstedt MBA, PMP®
 
What Makes Great Infographics
What Makes Great InfographicsWhat Makes Great Infographics
What Makes Great InfographicsSlideShare
 
Masters of SlideShare
Masters of SlideShareMasters of SlideShare
Masters of SlideShareKapost
 
STOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
STOP! VIEW THIS! 10-Step Checklist When Uploading to SlideshareSTOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
STOP! VIEW THIS! 10-Step Checklist When Uploading to SlideshareEmpowered Presentations
 
10 Ways to Win at SlideShare SEO & Presentation Optimization
10 Ways to Win at SlideShare SEO & Presentation Optimization10 Ways to Win at SlideShare SEO & Presentation Optimization
10 Ways to Win at SlideShare SEO & Presentation OptimizationOneupweb
 
How To Get More From SlideShare - Super-Simple Tips For Content Marketing
How To Get More From SlideShare - Super-Simple Tips For Content MarketingHow To Get More From SlideShare - Super-Simple Tips For Content Marketing
How To Get More From SlideShare - Super-Simple Tips For Content MarketingContent Marketing Institute
 
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...SlideShare
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksSlideShare
 

Viewers also liked (13)

MGM Resorts International Eastern Europe Market Entry Proposal
MGM Resorts International Eastern Europe Market Entry ProposalMGM Resorts International Eastern Europe Market Entry Proposal
MGM Resorts International Eastern Europe Market Entry Proposal
 
Market Opportunity Analysis - The International School of Hospitality (TISOH)
Market Opportunity Analysis - The International School of Hospitality (TISOH)Market Opportunity Analysis - The International School of Hospitality (TISOH)
Market Opportunity Analysis - The International School of Hospitality (TISOH)
 
Strategic Marketing Plan - KONE Product Launch in Germany
Strategic Marketing Plan - KONE Product Launch in GermanyStrategic Marketing Plan - KONE Product Launch in Germany
Strategic Marketing Plan - KONE Product Launch in Germany
 
Industrial Analysis for the LAUSD - Health Fair
Industrial Analysis for the LAUSD - Health Fair Industrial Analysis for the LAUSD - Health Fair
Industrial Analysis for the LAUSD - Health Fair
 
What Makes Great Infographics
What Makes Great InfographicsWhat Makes Great Infographics
What Makes Great Infographics
 
Build Features, Not Apps
Build Features, Not AppsBuild Features, Not Apps
Build Features, Not Apps
 
Masters of SlideShare
Masters of SlideShareMasters of SlideShare
Masters of SlideShare
 
STOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
STOP! VIEW THIS! 10-Step Checklist When Uploading to SlideshareSTOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
STOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
 
You Suck At PowerPoint!
You Suck At PowerPoint!You Suck At PowerPoint!
You Suck At PowerPoint!
 
10 Ways to Win at SlideShare SEO & Presentation Optimization
10 Ways to Win at SlideShare SEO & Presentation Optimization10 Ways to Win at SlideShare SEO & Presentation Optimization
10 Ways to Win at SlideShare SEO & Presentation Optimization
 
How To Get More From SlideShare - Super-Simple Tips For Content Marketing
How To Get More From SlideShare - Super-Simple Tips For Content MarketingHow To Get More From SlideShare - Super-Simple Tips For Content Marketing
How To Get More From SlideShare - Super-Simple Tips For Content Marketing
 
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
A Guide to SlideShare Analytics - Excerpts from Hubspot's Step by Step Guide ...
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & Tricks
 

Similar to Industrial Services Layout Optimization

Production and operations managment notes
Production and operations managment notesProduction and operations managment notes
Production and operations managment notesWasim Arshad
 
Project On Facility Layout
Project On Facility LayoutProject On Facility Layout
Project On Facility LayoutMOHD ARISH
 
Application of lean manufacturing tools in garments production
Application of lean manufacturing tools in garments productionApplication of lean manufacturing tools in garments production
Application of lean manufacturing tools in garments productionRazib Mahmud
 
Chapter 5. Supply Planning Meeting Customer DemandAfter we’ve m.docx
Chapter 5. Supply Planning Meeting Customer DemandAfter we’ve m.docxChapter 5. Supply Planning Meeting Customer DemandAfter we’ve m.docx
Chapter 5. Supply Planning Meeting Customer DemandAfter we’ve m.docxrobert345678
 
Iterature Review Cellular Manufacturing And Group Technology
Iterature Review Cellular Manufacturing And Group TechnologyIterature Review Cellular Manufacturing And Group Technology
Iterature Review Cellular Manufacturing And Group Technologysandeepbags2004
 
Chapter 16. Facility Layout DecisionAfter selecting a facility.docx
Chapter 16. Facility Layout DecisionAfter selecting a facility.docxChapter 16. Facility Layout DecisionAfter selecting a facility.docx
Chapter 16. Facility Layout DecisionAfter selecting a facility.docxrobert345678
 
Chap 3 - Process Design.ppt
Chap 3 - Process Design.pptChap 3 - Process Design.ppt
Chap 3 - Process Design.pptSmartWorld13
 
13.jajajajajajajajjajajajqjajqjajqjajjaajppt
13.jajajajajajajajjajajajqjajqjajqjajjaajppt13.jajajajajajajajjajajajqjajqjajqjajjaajppt
13.jajajajajajajajjajajajqjajqjajqjajjaajpptdoremonlovers365
 
Knitwear industry sri lanka
Knitwear industry sri lankaKnitwear industry sri lanka
Knitwear industry sri lankavinay126me
 
Operation management - Importance & Type of layout
Operation management - Importance & Type of layoutOperation management - Importance & Type of layout
Operation management - Importance & Type of layoutSid Gham
 
3.0 Plant Layout Types.pptx
3.0 Plant Layout Types.pptx3.0 Plant Layout Types.pptx
3.0 Plant Layout Types.pptxsheetalip
 
PREPARE A POWERPOINT PRESENTATION TO THE COO AND
PREPARE A POWERPOINT PRESENTATION TO THE COO ANDPREPARE A POWERPOINT PRESENTATION TO THE COO AND
PREPARE A POWERPOINT PRESENTATION TO THE COO ANDSILAS OLUDARE
 

Similar to Industrial Services Layout Optimization (20)

Production and operations managment notes
Production and operations managment notesProduction and operations managment notes
Production and operations managment notes
 
Project On Facility Layout
Project On Facility LayoutProject On Facility Layout
Project On Facility Layout
 
Application of lean manufacturing tools in garments production
Application of lean manufacturing tools in garments productionApplication of lean manufacturing tools in garments production
Application of lean manufacturing tools in garments production
 
FinalReport
FinalReportFinalReport
FinalReport
 
VALUE CREATION
VALUE CREATIONVALUE CREATION
VALUE CREATION
 
Warehousing Case Study
Warehousing Case StudyWarehousing Case Study
Warehousing Case Study
 
Chapter 5. Supply Planning Meeting Customer DemandAfter we’ve m.docx
Chapter 5. Supply Planning Meeting Customer DemandAfter we’ve m.docxChapter 5. Supply Planning Meeting Customer DemandAfter we’ve m.docx
Chapter 5. Supply Planning Meeting Customer DemandAfter we’ve m.docx
 
Iterature Review Cellular Manufacturing And Group Technology
Iterature Review Cellular Manufacturing And Group TechnologyIterature Review Cellular Manufacturing And Group Technology
Iterature Review Cellular Manufacturing And Group Technology
 
Chapter 16. Facility Layout DecisionAfter selecting a facility.docx
Chapter 16. Facility Layout DecisionAfter selecting a facility.docxChapter 16. Facility Layout DecisionAfter selecting a facility.docx
Chapter 16. Facility Layout DecisionAfter selecting a facility.docx
 
Chap 3 - Process Design.ppt
Chap 3 - Process Design.pptChap 3 - Process Design.ppt
Chap 3 - Process Design.ppt
 
Capacity Management
Capacity ManagementCapacity Management
Capacity Management
 
13.jajajajajajajajjajajajqjajqjajqjajjaajppt
13.jajajajajajajajjajajajqjajqjajqjajjaajppt13.jajajajajajajajjajajajqjajqjajqjajjaajppt
13.jajajajajajajajjajajajqjajqjajqjajjaajppt
 
Layout book
Layout bookLayout book
Layout book
 
Casestudy #3
Casestudy #3Casestudy #3
Casestudy #3
 
Case aircraft assenbly
Case aircraft assenblyCase aircraft assenbly
Case aircraft assenbly
 
Knitwear industry sri lanka
Knitwear industry sri lankaKnitwear industry sri lanka
Knitwear industry sri lanka
 
Operation management - Importance & Type of layout
Operation management - Importance & Type of layoutOperation management - Importance & Type of layout
Operation management - Importance & Type of layout
 
Methods of production
Methods of productionMethods of production
Methods of production
 
3.0 Plant Layout Types.pptx
3.0 Plant Layout Types.pptx3.0 Plant Layout Types.pptx
3.0 Plant Layout Types.pptx
 
PREPARE A POWERPOINT PRESENTATION TO THE COO AND
PREPARE A POWERPOINT PRESENTATION TO THE COO ANDPREPARE A POWERPOINT PRESENTATION TO THE COO AND
PREPARE A POWERPOINT PRESENTATION TO THE COO AND
 

Recently uploaded

IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 

Recently uploaded (20)

IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 

Industrial Services Layout Optimization

  • 1.
  • 2. Industrial Services, Los Angeles USC Senior Design Project December 10, 2003 Rodrigo Del Cid Jr. Cole Grundstedt Mr. Ted Mayeshiba Ms. Priscila Delgado Ms. Maria Cepeda Prepared by: Clarissa Umali Special thanks to: Dr. F. Stan Settles
  • 3. 1 Executive Summary Goodwill Industrial Services, Los Angeles, had a problem—their factory floor could not accommodate multiple product processes, which they believed resulted in the department hitting a profit plateau. It was also observed that there was a problem with the hanger sorting process. It had been done in the department longer than any other product; however, it took up an enormous area for processing and storage of unsorted, in process, and sorted hanger boxes. Another perceived issue was a lack of standardization in the method for approaching new products and services. To tackle the first problem of the hanger process, profitability was calculated with respect to the amount of space it required—for both the work itself and storage. This number was compared to another common product that used far less space—specifically Paul Mitchell Products. Using historical data and space requirements, it was determined that the hanger sorting process earns $0.20/day per square foot of floor space while Paul Mitchell earns nearly four times as much at $0.79/day per square foot. After analysis of these numbers it was concluded that ideally, the hanger sorting process should be removed because of the inefficiency inherent to the process. Improving the process itself was deemed futile because the process would still require a large amount of storage space regardless of the improvements made within the process. At present, however, the hanger sorting process cannot be removed from the department because there are mentally and physically handicapped client-employees that cannot do anything else except sort and pack hangers. Taking this into account, it was recommended that it be confined to the back area of the factory floor (see Appendix K). This way the large amount of boxes needed to complete the process will not interfere with the other processes of the factory. Different function levels of workers were separated within the hanger process layout so as to balance the production line and smooth the flow of product within the different function areas. In regards to all other product processes, there are two different types of products—one where only one or two tasks must be done to complete the task (e.g. placing a sticker, or
  • 4. 2 dressing a doll), and one where many tasks must be completed to create a finished product. Layouts were created for individual groups processing each product type overseen by one or two team leaders; this is how the factory is presently managed (see Appendix H & I). Both layouts include ideas and suggestions for line balancing and flow smoothing. To help the supervisors better assign client-employees to the tasks required for a process, the “Hourglass Flow Model” was created (see Appendix D). It breaks down the fundamental elements of all products received and shows how the difficulty and complexity of each task relates to its location in the overall flow from raw material to finished good. This model is applicable to every category of product and layout. If for some reason, the hanger process is eliminated from the Los Angeles facility, a factory layout that did not contain hangers was included (see Appendix J). This layout can accommodate up to four different product processes and has a smooth and logical flow. In all layout models, safety was assured by maintaining the preexisting dotted yellow-line in the factory. This line separates the work areas from the forklift traffic lane and assures an unobstructed path to the emergency exit and fire extinguisher. The location of pallets is such that the forklift can easily access them without infringing on the work areas. It was also suggested that all raw material pallets be deposited after regular work hours and in a quantity that can be worked through in at least one day for each process in the factory. This insures that there is little forklift traffic during the busiest hours, which reduces risk of accidents. Given the proposed layouts, a list of the materials and equipment that were needed on the factory floor was made. This list does not account for any equipment already existing. It should be mentioned that Goodwill Industries, Los Angeles does not currently have the man power or customer base to employ our layouts fully. They should be considered an attainable goal that, when reached, should result in increased profits, improved utilization of the factory floor, and an all-around safer work environment for everyone.
  • 5. 3 Table of Contents Introduction...................................................................................................Page 4 Employees......................................................................................................Page 4 Hourglass Flow Model................................................................................. Page 6 Problem Statement........................................................................................Page 8 Hanger Profitability......................................................................................Page 9 Disadvantages of hangers.................................................................Page 9 Profitability comparison................................................................... Page 10 Advantages of hangers......................................................................Page 11 Heat Sealing Profitability............................................................................. Page 12 Layout Descriptions and Analyses Legend............................................................................................... Page 12 Original Layout.................................................................................Page 15 Product Categorization..................................................................... Page 16 Single Task Product..............................................................Page 17 Smoothing Production..............................................Page 18 Multi-task Product................................................................ Page 19 Smoothing Production..............................................Page 20 Proposed Layout (no hangers)......................................................... Page 21 Proposed Layout (with hangers)...................................................... Page 23 Smoothing Production..........................................................Page 26 Conclusions Equipment requirements.................................................................. Page 27 Final recommendations....................................................................Page 27 Appendices.....................................................................................................Page 29
  • 6. 4 Introduction Goodwill Industries of Southern California funds programs that train unemployed and underemployed men and women so that many will be able to transition into a mainstream work environment with the proper skills and work habits. As shown in its organizational values, Goodwill is dedicated to helping people help themselves. Goodwill encourages the workers, called client-employees, to strive to achieve their highest potential, since their needs are the reason why the organization exists. The Los Angeles facility was the focus of our project, being the largest of the three facilities in the greater Los Angeles area, and providing a greater opportunity of improvement. More specifically, we worked with the Industrial Services division which forms contracts with outside companies to do the simple tasks for them such as sorting and packaging the goods. Some of these companies include Paul Mitchell hair products and Auntie-Itch cream products. Employees The client-employees who work on the tasks daily include people with physical or mental disabilities and other vocational disadvantages. There are three levels of client- employees—low, medium, and high-functioning. They are placed into one of these categories based on their abilities. An outside work environment is not an option for low- functioning client-employees, because their disabilities or barriers are too severe to allow for a successful transition outside of Goodwill. Therefore, Goodwill provides them a long-term work opportunity that builds in them a sense of accomplishment and pride in their work. The low-functioning client-employees can only perform single or simple tasks. Some examples of the capabilities and responsibilities of low-functioning client-employees
  • 7. 5 include executing a “yes” or “no” decision, wrapping or unwrapping a product, sorting, packing a single item into a box, and performing checks (such as whether a cap is tightened or not). The abilities of medium-functioning client-employees are very similar to the low-functioning client-employees; however, they can perform two tasks simultaneously. For example, a medium-functioning client-employee can sort and pack, whereas a low-functioning client-employee can only sort or pack. For high-functioning client-employees, the work experience that Goodwill provides them must be “meaningful,” so that the individual can be trained for successful transition into outside employment such as mail house or assembly environments. Some of the work skills and work habits that are taught to the client-employees are attendance, hygiene, inter-personal interactions, communication skills, work place conduct, and following directions. High-functioning client-employees can perform more complex tasks and make multiple decisions, some of which include lifting, heat-sealing, labeling, and packing multiple items. Lifting is usually performed by high-functioning client- employees because of its physical nature. Client-employees with physical and more severe mental disabilities would not be able to perform such a task. Heat-sealing is one of the more dangerous tasks and requires that the client-employee understand the safety considerations of the task. Labeling is left to the high-functioning client-employees simply because it requires accuracy of label placement, especially for the smaller packages and boxes.
  • 8. 6 Material handler is the name given to a high functioning worker; however, he or she is not classified as a client-employee for several reasons. They are much more able-bodied to carry out physical tasks such as unloading packages, staging, shrink-wrapping completed pallets, palletizing and de-palletizing, and distributing materials to the client- employees. Material handlers are also given an hourly wage, rather than being paid by a prorated piece-rate based on minimum wage, which is how the client-employees are paid. Material handlers are classified as high-functioning, not necessarily because of the complexity of the tasks, but because of the number of concurrent tasks that they are assigned to do. The material handlers are responsible for many more duties than the client-employees, especially the tasks at the beginning and at the end of the production line. The Hourglass Flow Model Picture 1 The Hourglass flow model is a representation of the flow of each product from the beginning the end of the production process. As seen in to Picture 1, the complex tasks are those involving the raw materials and finished goods. In these areas, high-functioning workers are needed in order to accomplish these tasks. After the material handlers have prepared the raw materials to be worked upon, the lower-
  • 9. 7 functioning workers can perform the simpler tasks. Then the product returns to the material handlers who then complete the tasks at the end of the production process. T Hourglass flow of the work break down sheet can be observed in Chart 1. Chart 1 Goodwill Industries O he 5 Shrinkwrap unit box 7.0000 428.571 6 8.0000 375.000 7 Apply address label 3.0000 1000.000 Prevailing Wage f So Cal Break Down Sheet COMPANY: Paul Mitchell DESCRIPTION: Build PM Shines/Dir ITEM: PM shines/Direct Mail Assembler=$8.47 Pack unit box with 1 D9Y, 1 D6RV, 1 Processing liquid, check for cap tightened Pack unit box inside corrugated mailer along with letter and mini paper swatch Material Handler = $8.76 ect Mail STEP NO. TASK SEC. PER/UNIT STD./UNIT PER/HR H 1 Unload material 0.5000 6000.000 H 2 Staging material 0.5000 6000.000 L/M 3 Build unit box 5.0000 600.000 L/M 4 12.0000 250.000 H H H This segment is taken from the Paul Mitchell work break-down sheet. The work break- down sheets allow the production supervisor and other staff members to see the tasks flow e performed by the client-employees broken down step by step. Also included is the amount of time it takes to perform each task, the pay rate for performing each task, and hourly wages. By examining the tasks more closely, one can see that the Hourglass model is in fact being followed. As noted in Chart 1, the tasks in the beginning and at th end of the production process are being performed by the high-functioning material handlers, while the work of the lower and medium-functioning client-employees are clustered in the center of the process.
  • 10. 8 Chart 2 wn Sheet COMPANY: Sewing Collection DESCRIPTION: Sort And Pack Ha ITEM: Hangers STEP NO. TASK SEC. PER/UNIT STD./UNIT PER/HR L 1 Sort Hangers 3.0000 1000.000 L 2 Pack Hangers 3.0000 1000.000 M 3 Sort And Pack Hangers 4.5000 666.667 Prevailing Wage Assembler=$8.47 Material Handler = $8.76 Goodwill Industries Of So Cal Break Do ngers Another example supporting the Hourglass flow model, found in Chart 2 above, is for the hanger process, which Goodwill has been doing for a long time. The material handlers’ jobs are not listed in the tasks, but are being executed. In the beginning of the process material handlers bring the unsorted boxes of hangers to the warehouse and distribute them to the client-employees. The low and medium-functioning client-employees then sort out the different types of hangers, and pack them into separate boxes. Finally, the material handlers once again perform their duties on the completed hanger boxes. Having different levels of client-employees exacerbates the difficulty of creating an efficient flow in the main warehouse. Problem Statement The main problem with Goodwill Industrial Services is the inefficient flow in the main of the inefficient flow, the main warehouse is at capacity for rial warehouse. Because processing multiple products simultaneously. This, in turn, limits the amount of customers Goodwill Industrial Services can have. With profits leveling off, it was important to address this problem to be able to expand and grow Goodwill Indust
  • 11. 9 Services’ customer base. With an expanded customer base, revenues can increase a more jobs can be created. nd Hangers The hanger process is quite simple, yet very time and space consuming. There are about t types of hangers. The hangers are then sorted using a hanger sorting fferent through out wh r it is, and place it in its corresponding box. This includes having it is 24 differen apparatus which facilitates the sorting operation, yet can only be done by a high functioning client-employee. Currently the unsorted boxes contain about 3 or 4 di types of hangers which even a low function client-employee can individually sort and separate. A worker has to pick up each individual hanger and decipher the type, and place it in the box it belongs to. The hangers are then neatly packaged into individual boxes, which usually hold at least 100 hangers of one specific type. Disadvantages The whole hanger process is very time consuming. Each client-employee has to figure ich type of hange to pick it out of a box with many hangers, which are usually tangled in one way or another, and looking at it carefully because many of the hangers look very similar. If the client-employee is just sorting, then they put it in another box without worrying that neatly placed. If the client-employee is sorting and packing, then they have to carefully place it neatly in the packaging box. Whether the client-employee is only packing, or sorting and packing, they will be surrounded by at least 4 large boxes, which leads to the next point.
  • 12. 10 The hanger process is very space consuming, because each client-employee needs at least still he hanger process uses too much space on the factory floor and the main building. This Total Area Used = 9915 sq. ft. aul Mitchell Product Total Area Used = 420 sq. ft. he results indicate that a Paul Mitchell product is much more profitable considering the 4 boxes around them to be able to place the hangers in the correct box. This takes up a lot of useful floor space because many times they might have 6 or 7 boxes around them, which are not put to use. Also, because of the high turnaround time, the unfinished and finished boxes take up a lot of space as was discovered during our many visits to Goodwill Industrial Services. The turnaround time has improved, but hangers are very much space consuming. T includes space for the process itself and for raw and finished materials. Hangers account for nearly 60% of the revenue, but use over 75% of the whole facility space. One needs to look at the product profitability in dollars per square foot between hangers and a Paul Mitchell. Hangers Total Profit/Month = $60,000 Profit/sq.ft./day = $0.20 P Total Profit/Month = $10,000 Profit/sq.ft./day = $0.79 T amount of floor space it uses. Having mostly Paul Mitchell products would increase revenues by about 4 times according to the profit per square foot.
  • 13. 11 It is very difficult to provide a flow or an efficient time production with hangers. It is y The hanger process provides a productive starting point for new client-employees. he hanger process also provides jobs to client-employees of different skill levels. A can g angers are always available to be sorted and packaged providing year round jobs. The hanger process provides jobs during downtime. This is important because when certain difficult because every worker is working at their pace. Also, the hanger process is ver time consuming meaning some workers only finish about one box a day. Although the client-employees are being paid according to their number of completed hanger boxes, they are taking up a certain amount of space on the factory floor which can otherwise be used for more profitable products. Furthermore, they are slowing the hanger process, which can lead to starvation or a high turnaround time. Advantages Goodwill Industrial Services many times serves solely as a transition period for the client-employees. They begin to work and learn at Goodwill Industrial Services, and when the client-employees reach an adequate skill level, they are transferred to higher skill demanding employment. T low-skilled client-employee can be employed to either sort or package hangers. They also do both, although most start off by just doing one of the tasks. Here, many low- skilled client-employees can be used which would otherwise not have any value-addin tasks. Furthermore, the low-skilled client-employees gain familiarity with the hangers, increasing their productivity over time. H
  • 14. 12 products and lines are finished, workers can be placed to work at the hanger process. The hanger process is always available to be worked on. The hangers should be eliminated to provide more space for other more profitable products to come through Goodwill Industrial Services. If the hangers are to be kept, they are to be kept solely for the advantages listed. Heat Sealing Process The heat-sealing machine needs to be removed from the factory floor. The heat-sealing 10% of the floor space, yet generate less than 5% of the revenue. to r machine takes up over The heat-sealing machine is also used less than 10% of the total time. Furthermore the heat-sealing machine obstructs the flow on the factory floor. Eliminating it from the factory floor would greatly improve the floor design and flow. The only reasons for keeping the heat-sealing machine would be if it brings in more revenue, or if it is vital receive more customers. Layouts: Before and Afte he following is a list of symbols used in our layout drawings: workers at are responsible for each client-employee in their group. They make T This figure represents a supervisor/team leader. They are wage th sure everyone is on task and performing their functions correctly. They are also responsible for keeping track of the amount of work each client-e doing so they can be paid piecewise. mployee is
  • 15. 13 These three figures represent the low (red), medium (yellow), nd high (green) functioning client-employees. Their job because of ey are high functioning workers. They have the mental ability to lim ously discussed. useful to understand where everything comes from and goes to and how it gets there. t t pallets of goods. They a distinguished into o groups—raw material and finished goods. Raw material is the light y It is read re-palletized. It a responsibilities and capabilities were previously discussed. This figure represents the material handlers. They are green th handler several different kinds of tasks and have no physical disability to functions in handling material. Their job responsibilities were previ This blue arrow represents product flow on the layout drawings. This it their is This helps to produce a product flow that is both organized and efficien bottlenecks and starvation. These two symbols represen with less tw colored pallet. It has arrived from a customer as is and has not been worked through. All material must be de-palletized, sorted, and distributed by the material handlers before it can be worked-through b the client-employees. Finished goods is the dark colored pallet. back to customers. The product has already been worked on, boxed, and y to be shipped
  • 16. 14 is important to note the location of each type of pallet. These symbols work with the blue arrow (above) to demonstrate a logical and organized flow. This symbol represents a pre-existing painted yellow line on the her s his symbol represents a table in the layout. They are labeled by his symbol represents a roller conveyor. They are in 10-foot t his symbol represents a handcart. The factory already has a sed to factory floor. It is used to mark the boundary of the work areas w cross. This keeps all factory workers safe. This line also marks emergency exit paths and fire extinguisher access and as such all path integrities must be maintained. Permanent work areas cannot be place outside or on top of these pre-existing area marked by the dotted yellow line. e the forklift cannot T their lengths which are the dimensions of the pre-existing factory tables (requirements are discussed later) T sections. The factory already has a number of these conveyors (requirements are discussed later). The conveyor helps to collec items in one area and reduces the effort and time required to move another area. it a short distance to T number of these however they are not in use. The handcart is u transport items a short distance.
  • 17. 15 Original Layout actory layout as it exists now. It is set up ed correcting. being used to store many nother area of wasted space is the lower-right corner where the left this he entire left side of the warehouse is devoted to hangers. It is clear to see that this area This is the original f to do two products—one of them being hangers and the other being a product requiring a production line. There are a few items with this layout that ne First of all there is wasted space—more specifically in the upper-right corner of the warehouse. This area is currently items including broken conveyors, unused handcarts and machines, and a number of tables—some broken. A production line is. There is a lot of space on the right of this production line and since there are pallets being stored on the taking up that space, there is only room for one production line in area. T is quite cluttered. The nature of task of hanger sorting requires a large amount of space and a large number of boxes. This yields a product flow that is both difficult to understand and visualize. It is this reason that there are no blue arrows to mark the product flow. The location of the
  • 18. 16 raw material and finished goods pallets in all areas of the warehouse appears to be arbitrary with no concrete product flow in mind. The heating tunnel takes up a large portion of r roduct Categorization the upper-left corner. This leaves little room fo anything else given the constraints of the dotted- yellow line. P dwill receives are broken down into three categories. The first isjointed . t- it rials are consideration from the third product type—the “multi-task” product. All the products that Goo is hanger sorting. It was given its own category because it requires much more workspace than any another product, it has the slowest throughput, and it has a d product flow. Because of these reasons, it requires its own separate consideration in the factory layouts. The second type of product Goodwill receives is a “single-task” product This is a product that, after initial de-palletizing and staging, requires only one or two tasks before it can be re-boxed and re-palletized. An example of an actual Goodwill single-task product is the “Scoobie-Doo doll”. After the dolls are staged for the clien employees, it has to be removed from its bag, dressed and attached to a costume. Then is placed back in the bag and sent off to be re-boxed. What makes this category important is that all the tasks required (save the material handlers’ tasks) can be completed by one person or up to three people in a small sub-group and few mate required (if any) to complete these intermediate steps. This gives it separate
  • 19. 17 The “multi-task” product has a large number of tasks to be completed after in and before re-palletizing. An example of an actual Goodwill multi-tas itial staging k product is -line es their perations. Each group may have a different category of product to work through so we “Auntie-itch cream”. After initial staging the individual cream tubes must have a sticker adhered to them, then be placed in their individual boxes, then have another sticker placed on the front and back of the box, and finally be placed inside larger boxes which are then taped and palletized. This product type requires a more traditional assembly setup and each station requires intermediate materials to complete their tasks in contrast to the single-task product that requires only what is in the initial palletized box. The factory layouts are broken down into groups, as this is how Goodwill manag o created a layout of each group based on product type. Single-task Product. This is a modification of a setup that was in the original layout. Instead of having two oller conveyor adjacent to one of the rows, a conveyor is placed in tter . rows of tables with a r the aisle of the two rows leaving adequate room on both sides of the conveyor for a person to walk back and forth. This solves a few problems. First it allows team leaders to be closer to the client- employees and provide be supervision and guidance Second it puts the team leader in control of all goods
  • 20. 18 so as to better keep track of a client-employee’s production. The proposed setup does allow a product to continue after the client-employee has worked on it until the team leader marks down their progress and places the item on the conveyor in the center. From there it simply continues down the conveyor to the material handlers for boxing a re-palletizing. Another change proposed is the implementation of the use of hand the material handlers. Note: This proposal is not unique to the single-task produc line; rather it is an overall factory-wide improvement suggestion. The use of handcarts allows for more products to be distributed at one time by a material handler improvin their efficiency. It also improves the overall ergonomic safety of the material handlers requiring them to lift much less weight at one time. The material handlers with han will take material from the raw material pallet and distribute the material to the memb of both lines for work. Since each station does all the tasks required of the product (see definition of single-task product) excluding staging and re-palletizing, the product goes directly from each station to the conveyor (see blue product flow arrows). It was previously said that all tasks are to be completed by one individual or a small sub-group of no more than three. These sub-groups are displayed by a dotted square around them. The members of this sub-group break up the tasks and each complete an entire produc together. This is why there is only one arrow leaving each of these subgroups. Smoothing Production Flow It is important to insure that production flow is smooth from to not nd carts by tion g dcarts ers t p to bottom. The material t workers. The only place where this is a problem ishandlers are assumed to be the fastes in staging; however they can easily control how much product is distributed to each client-employee and can pace accordingly. Within the production line of client-
  • 21. 19 employees, each individual or sub-group is seen as the only intermediate step betwee material handlers’ tasks. Since the client-employees will logically be working sl than the material handlers, the only place where production flow needs to be analyzed and controlled is within the sub-groups because they have more than one person affecti production flow. Our recommendation is that within a particular sub-group, each clien employee is of the same function level and works at the same pace. This can be seen on our drawing that each member of a sub-group is of the same function level. By doing this, it assures that there will be no bottlenecks or starvation within the sub-group and the product will spend an equal amount of time with each person in the sub-group before being placed on the conveyor. It should be mentioned that it could occur where the tasks performed within a sub-group are not the same level of difficultly. In this situation, a higher functioning worker should do the more complex task and a lower functioning worker should do the simpler task. Another option would be to have two lower functioning workers doing a simpler task to feed the higher functioning worker so as n to starve his supply. In a single-task product, these aforementioned situations wi occur often so a best guess judgment should be applied using these suggestions and the layout as a base model. n the ower ng t- ot ll not Multi-task Product The layout appears the sk at ed. same as the single-ta product layout except th the conveyor was remov
  • 22. 20 Since there are multiple tasks to complete, a more traditional assembly-line model was applied. This means that the tables and work surfaces act as the conveyor and the client- employees will advance the product down the line. The area between the two table lines allows enough room for two people to comfortably pass one another. It is assumed that each team leader would be responsible for one table line. They would keep trac intermediate progress by counting production for the day and totaling unfinished pr at each station so each client-employee can get paid for their own contribution piecewis The staging and re-palletizing areas are the same as the single-task product layout. In th sense the blue product flow arrows are the same except in the client-employees’ areas which logically advance down the table. The material handlers with handcarts, however perform a slightly different function. Raw material is deposited at the first station, ei by the staging crew or the handcart pusher, but at all the other stations, the handcart pusher delivers intermediate supplies as needed. These supplies are not the main prod rather they are items that are needed to complete each respective step. The handcart pusher insures that each station has enough intermediate supplies to complete their tas Smoothing Production Flow k of oduct e. is , ther uct ks. gray. This is because the layout itself requires no and y Each client-employee in this layout is logical method of client-employee function distribution. This distribution is dictated by the product being worked through and the complexity of tasks therein. The client- employee function distribution must be applied in a way that smoothes production balances the line. As mentioned earlier, this reduces bottlenecks and starvation at each station. Before client-employees can be assigned to their respective tasks, the complexit of each step and type of client-employee that can effectively perform the task must be
  • 23. 21 understood. After this, client-employees should be matched up with the most complex tasks they can effectively perform. Doing this will normalize the throughput at each station by having a faster worker perform a harder task and a slower worker perform a easier task. After this is done, more tweaking may still be necessary. In a situation where a station is being starved because the previous station is not working fast enou it is recommended that an extra client-employee is put on the slower station to double the input into the station that was once starved. In a situation were product is being bottlenecked at a station because the client-employee is working too slowly for th previous station, placing an extra worker on this station will speed up its throughput Before additional workers are placed at a station in an attempt to solve flow problems, production line and the effect of additional staff on the whole production must be considered. As mentioned in the single-product layout, the material handlers are th fastest workers and need not be considered in the smoothing of production flow; they pace their material distribution as dictated by the client-employee production rate. n gh, e . the e can roposed Factory Layout (no hangers)P yout is that the heating tunnel was removed all r-left placed a line of raw material pallets in the center of the factory. All four production lines The first thing to notice in the proposed la from the upper-left corner of the factory. The entire upper-right corner was cleared of unnecessary equipment, and the handcarts stored there are now being used by the material handlers at each group. The factory floor has four main sections, the uppe and right and the lower-right and left corners. There is therefore the potential of four different product lines being processed simultaneously in each of the four areas. We
  • 24. 22 can he raw material is delivered by the forklift. This will be done after client-employee product y the 30 easily draw from these pallets to supply their lines (see blue product flow arrows). T work hours to assure everyone’s safety. The amount of product delivered to this area shall be at least one day worth of work per production line. This assures that no deliveries must be made during regular work hours. Material handlers will move the pallets (using already available pallet jacks) to their respective staging areas. The flow through the production lines is dependent on the type of product (single or multi- task). The production lines shown in the factory layout are just an example of what can be used, however it should be noted that the single-task production line requires slightl more space due to the additional width of the conveyor. This adds 2 feet to the production line width which makes it difficult to put two production lines in an area other than the lower-left corner since this corner is the widest. The areas at the top of factory floor can be used either for single or multi-task production. They are oriented horizontally; this allows for the added width of the single-task production line. The upper-right corner is a smaller area and restricts the length of any production line from feet to 22 feet. The production lines at the top have material flowing from out to in. Raw material is staged
  • 25. 23 on the outside of the factory floor and fed through the production lines to the finished goods in the center. After a finished goods pallet is created, the material handler (using the pallet jack) moves the pallet to the yellow-dotted line on the edge of his respecti work area. From here, the forklift can easily move material out of the factory and prepa it for shipping. The forklift is not restricted from picking up finished goods pallets outside of regular client-employee work hours because the location of the finished goods pallets does not require the forklift to enter the work areas marked by the dotted yellow line. The production lines in the lower-left and right of the factory floor move material from top to bottom— from the staging area for raw material at the top of the production line, through the production line in a manner governed by the product classification (single or multi-task) finished goods pallet is created, the material handler (again, using the pallet jack) moves the pallet to the yellow-dotted line in the center, on the edge of his respective work area. The forklift can, again, easily pick up the finished goods for shipping without entering the work areas and maintaining the safety of the factory floor. ve re , to the finished goods pallets at the bottom. After a Proposed Factory Layout (with hangers) The hanger sorting process is placed in the back or upper-right and left corners of the factory floor. This was done because of the large amount of space and boxes and raw
  • 26. 24 material required of the process—it was placed out of the way of other processes as not to impede on their flow rates due to excess boxes. The bottom portion of the factory is identical to the previous layout with the exception that the hanger process took up too much room to have a row of raw materials on both sides of the floor. This row is now confined to the right side, and this group of raw materials supplies both non-hanger production lines in the lower portion of the factory. Raw material for hangers is now stored in the back of the warehouse in the center. The process is broken up into two areas—one for medium functioning client-employees (yellow in the upper-left) and one for low functioning client-employees (red in the upper- right). Each area has its own supply of raw materials which is deposited by the forklift in the same manner as the previous layout—at least a day’s worth of raw material for each area. In the low-functioning area material is deposited to the row of client-employees on the top by the material handlers. The client-employees take hangers from the unsorted (light- colored) box and sort them into their respective boxes below them (slightly-dark colored). From here the material handlers take the sorted hangers from the top row of client-employees and deposit them into the bottom row of low-functioning client-employees as needed. These client-
  • 27. 25 employees pack the hangers neatly in boxes (very-dark colored). From here the material handlers take the packed hangers to the finished goods area in the medium-functioning area upper-left corner area (follow the blue arrow). Here a material handler weighs, counts, seals, and re-palletizes the hangers onto pallets at the each of the work area where the forklift can access them easily. The low-functioning area could not have its own finished goods area because of space constraints, however, the output of the low- functioning area is very low so the amount of product that flows across the floor to the finished goods area is extremely low and will not require much labor. In the medium-functioning area material is deposited to each of the three rows of medium-functioning client-employees by the material handlers (using h of course) from the raw material pa Unlike the low-functioning client employees, there is no intermediate step between sorting and packing. Medium function client-employees take the unsorted hangers from the box where material handlers originally deposited them (light-colored box) and then sorts and packs them in the boxes below them (very-dark colored box). From there, the material handlers take the packed and sorted boxes to the finished goods area where a material handler again weights, counts, seals, and re-palletizes in same manner as previously mentio All hangers will end at this one area. Hanger production is a slow process so it is andcarts llets. - - ned.
  • 28. 26 unlikely that the material handlers will have too much work to do in these areas. They could possibly “moonlight” in other production areas. Smoothing Production Flow To effectively smooth production flow in the hanger processing area, both the material handlers and the team leaders need to keep an eye on how fast client-employees are working. Since client-employees are not working from a table rather from a box, it is unlikely that starvation will occur. If one low functioning client-employee is starved by having no hangers to pack, that client-employee can be re-assigned to sorting until enough sorted hangers are produced to justify a packing client-employee. The ratio between the sorting and packing client-employees in the low-functioning area (upper- right) can therefore be tweaked to smooth production. In the medium-functioning area, the client-employees do both sorting and packing therefore it is infeasible for there to bottlenecks and starvation within an individuals work area. Smooth production is simply produced in this area by insuring each medium-functioning client-employee has enough hangers and that all packed and sorted hanger boxes (very-dark colored) are taken to the finished goods area in a timely manner. It is therefore ultimately up to the material handlers and the team leaders to assure smooth production in the hanger processing area.
  • 29. 27 Conclusions Total equipment needed on hand for increased utilization: • 130 adjustable stools - They need to be adjustable to fit each person’s height to provide the correct working posture. They also need to be rotary, for the client-employees working on the hangers can easily turn to place hangers in specific boxes. • 24 low tables for hanger sorting - The tables need to be low so the client-employees have an easier time reaching into the boxes to pull out the hangers. It will decrease muscle strains and decrease sorting and packaging times. • 32 regular standard height tables - These tables are needed for other product processes. • 2 wheelchair height tables - These need to be available for the client-employees who are wheelchair bound. • 6 carts - With these carts material handlers can easily transport raw and finished materials from the client-employees to the unfinished and finished crates. This will lessen the physical work material handlers have to do decreasing the chances for injury. To increase flow through a production line, the hourglass theory was proposed. This stated that the high functioning client-employees are to be placed at the beginning and end of processes, while the medium and low functioning client-employees dually working in the middle of the line, to balance the product flow. To increase overall factory utilization different layouts with production lines have been proposed. These layouts augment productivity through the specific placement of raw materials, client- employees, supervisors, and finished goods. In these layouts it is recommended that the heat-sealing machine and the hanger process be removed for financial reasons.
  • 30. 28 Removing them would greatly increase the amount of available space for our proposed layouts as well as increase revenue. If the hangers are to be kept, then a layout is proposed where the hanger process would not hinder the rest of the factory floor flow. The use of the layouts will also increase worker and space utilization. With this, profits will increase while creating a safer working environment which will ultimately lead to better products.