SlideShare a Scribd company logo
1 of 5
Download to read offline
April 2020
Outline
Overall Equipment Effectiveness or OEE is a method of looking at a
manufacturing process to determine how well it is operating. It
combines three metrics to provide a single measure that encompasses
the utilisation of an asset, if it is being run at its optimum speed, and
what proportion of scrap to good products are being produced.
OEE (%) = Availability (%) x Performance (%) x Quality (%)
10000
Savings
Unless you have a site that is already extremely efficient, in virtually all
cases that I have come across it is possible to get a payback for a
system in just a few weeks. After that you are saving money and
improving your bottom line.
Generally there are also benefits realised that were not apparent
initially. For example, with one timber mill, it was presumed that the
operator on one of their stackers was stood waiting for about 1½ hours
in an 8 hour shift. After an automatic OEE system was installed it
became clear that it was actually 4½ hours. As a result their process
was adjusted to build up a buffer and the operator redeployed on
other tasks during their ‘newly available’ time.
When not to implement
Implementing an OEE system will not inherently make you more
efficient or save you money. The only way to make it work is if you
actively use the data it generates.
Ideally more than one member of staff should champion the process.
Otherwise if that person is busy or if they leave, you are left without
appropriate knowledge and the system is unlikely to be successful.
You also need buy-in from the top management all the way down to
the shop floor. Fundamentally you need to be committed to it, or you
will just be wasting your time and money.
Why OEE?
by Ashley Tizard
Summary
This article highlights both
the pros and cons of
implementing OEE in a
manufacturing
environment.
I have tried to include
both the positive and
negative elements to give
a balanced view, and have
also included some of the
best practices that I have
seen over the last 29
years that I have been
working in the industry.
Although my background
is as a software developer
and in particular using the
PlantRun and Prodigy
software platforms, the
concepts described here
are universally applicable.
OEE  Machine Downtime  Manufacturing Information Systems
The pros and cons of implementing an OEE system
April 2020
1
April 2020
OEE  Machine Downtime  Manufacturing Information Systems
2 Available or not…
The availability metric immediately brings up some interesting
differences in possible approach. From the production plan point of
view, operators are expected to be running their assets according to a
defined shift pattern with allowances for breaks, clean up times etc.
This gives an amount of available time for running on each asset. It
can, however, make it complicated when, for example, operators are
off sick, the production plan needs to change on the fly, or an
impromptu meeting is held. Ultimately this leads to an increased
administration requirement which, in my experience can result in the
system falling out of favour as the overhead is too onerous.
I think in most cases it is better to handle the planned not to run
periods by using simple concepts such as identifying when an operator
is not logged on to an asset. Then there is no additional administration
and logging on can be enforced through the use of machine interlocks.
What is the target speed?
Takt or cycle times for machines can be well defined but that is only
the start of the story. Production planning systems will calculate how
many products of a particular type can be manufactured in a given
amount of time. They take into account changeover and clean down
times, and include timings for bringing raw materials to an asset and
taking finished goods away. This gives most sites their performance
targets. However, I have seen many cases where the data in the
ERP/MES is based on historic hearsay and is not particularly accurate.
A little while ago, I was stood with a production manager at a site
looking at a machine with a speed measurement above it of about 200
m/hr. I questioned how they knew if it was running at the correct
speed and what the target speed was. The discussion progressed to
the fact that when the machine was installed the manufacturer said it
could run at 800 m/hr, as the machine was now quite old they had
recently said that they thought that it would probably be capable of
400 m/hr. “Ok” I said, “but why is it running at 200?”. “That’s a good
question” was the response…
The target speed for each product should be reviewed and if there is
uncertainty about them then data needs to be collected initially to
allow an accurate figure to be determined and then fixed.
Availability
is an indication of the
time that an asset is
running.
It is calculated as the
operating time as a
percentage of the planned
production time
(otherwise known as
available time).
Performance
is an indication of how
close the asset is running
to its target production
rate for the product being
made.
It is calculated as the
number of products
produced as a proportion
of the possible number of
products that could have
been made in the running
time.
April 2020
OEE  Machine Downtime  Manufacturing Information Systems
3 Quality products
OEE accounts for the quality metric with exactly the same weight as
availability and performance, however, in most instances the early wins
at a site do not initially come from targeting quality issues. That is not
to say that it should be ignored though. If you speed up production to
improve performance, you may inadvertently reduce the quality.
Ideally if the quality metric is not going to be targeted initially, I would
suggest using a nominal value, for example, defining a percentage of all
products manufactured to be scrap.
World class performance?
World class performance is often quoted at 85% but the reality is that
it is wholly dependent on the manufacturing process for a particular
type of product. In some cases a 50% OEE may be exceptional.
Ultimately, OEE is a benchmark that should be used to determine
whether a site is making improvements or not. It doesn’t matter if the
actual value is 85% or 25%.
Paper based data collection
Manual, paper based systems allow users to become familiar with the
concepts of OEE and are, therefore, a good starting point. However,
they have two key issues:
1. It can require a significant amount of time to interpret handwriting
and transcribe it into a tool that can be used to analyse the data.
2. Human nature would inherently mean that the data is not accurate.
If I was running an asset, my focus would be manufacturing
products, not filling in a form. If I reached the end of an 8 hour
shift and realised that I had made 500 products instead of 1000, I
would assume that it would be because I had 4 hours of
breakdown. I would be unlikely to remember how long any period
of stoppage was for and every reason that the asset stopped.
An automatic system will accurately timestamp each stoppage event
and can be used to force reasons to be entered at the time they occur.
This leads to better data that can be automatically analysed.
Quality
is an indication of how
well the products are
being made.
It is calculated as the
number of good products
as a proportion of the
total number that were
started.
OEE
OEE is a widely used
analysis and
benchmarking metric.
World class sites are
regarded as an 85% or
above OEE, and the
average OEE is around
65%.
April 2020
OEE  Machine Downtime  Manufacturing Information Systems
4 What about manual assembly?
Although tracking OEE for a manual assembly process is inherently
dependent on an operator entering accurate information, there is no
reason why it cannot be monitored so that data is collated
electronically and automatically processed, meaning that there is only
minimal administration required.
If you also look at minimising operator interactions using barcode
scanners, RFID readers, and the integration of the OEE system with
production planning to get works orders / jobs automatically, then
there are some significant additional benefits to be realised.
Response times
In order to improve, one of the key areas to address is response times.
This may be simply highlighting to management when an asset has
been stopped for an extended period of time, or improving the
notification / call out mechanisms available for maintenance staff.
For longer stoppages there is often a disagreement between
production and maintenance about how long a breakdown took to
repair. Recording call out and response times allows these period to be
analysed in more detail to determine, for example, if there are
sufficient maintenance staff on a night shift.
In addition, allowing operators to request raw materials or their team
leader, direct from their asset can also result in shorter stoppages.
What about the detail?
In order to make improvements you will need to go from the 3 key
metrics into the data that they are made up of. For example,
• If the availability measure is low then you need to understand what
stoppages have occurred and why?
• If the performance metric is low, you need to be able to review the
data to determine what is happening and potentially see the
reasons for slow speed running.
• If the quality measure is low, what are the reasons for scrap?
April 2020
OEE  Machine Downtime  Manufacturing Information Systems
5 Why OEE?
OEE is not a panacea but it is a great tool for identifying where issues
are and providing a means of seeing that improvements have been
made.
Implementing an OEE system that can be easily expanded over time to
cover more assets and include additional functional areas is a way of
instilling continuous improvement throughout the workforce.
After all, your competitors are improving and unless you continue to
become more efficient, you will get left behind.
About the
Author
Ashley Tizard is the
Managing Director of
Tascomp Ltd. He has
implemented machine
downtime systems for
almost 30 years, looking
at the reasons for
stoppages, OEE, and
improving response times
to issues.
He has worked in virtually
all manufacturing industry
sectors, including:
• Food & Drink
• Chemicals and
Pharmaceuticals
• Metals
• Forestry Products
• Automotive
• Aerospace
• Print
• Textiles

More Related Content

What's hot

Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)Brian Thomas
 
Oee on hana overall equipment effectiveness overview aug 2012 (2)
Oee on hana   overall equipment effectiveness overview aug 2012 (2)Oee on hana   overall equipment effectiveness overview aug 2012 (2)
Oee on hana overall equipment effectiveness overview aug 2012 (2)Marco Bueno
 
OEE System - Overall Equipment Effectiveness
OEE System - Overall Equipment EffectivenessOEE System - Overall Equipment Effectiveness
OEE System - Overall Equipment EffectivenessSatish Nande
 
Oee (overall equipment effectifness)
Oee (overall equipment effectifness)Oee (overall equipment effectifness)
Oee (overall equipment effectifness)Anang Tristianto
 
Using OEE to Improve Production - Interphex 2012
Using OEE to Improve Production - Interphex 2012Using OEE to Improve Production - Interphex 2012
Using OEE to Improve Production - Interphex 2012Adrian Pask
 
The visual machine_infographic 1.11.26 pm
The visual machine_infographic 1.11.26 pmThe visual machine_infographic 1.11.26 pm
The visual machine_infographic 1.11.26 pmBrady North America
 
OEE & MES - Help Food & Beverage Manufacturers 4-2011
OEE & MES - Help Food & Beverage Manufacturers 4-2011OEE & MES - Help Food & Beverage Manufacturers 4-2011
OEE & MES - Help Food & Beverage Manufacturers 4-2011Paul Dengler, BSME, CEA, EIT
 
OPS 571 Effective Communication - snaptutorial.com
OPS 571 Effective Communication - snaptutorial.comOPS 571 Effective Communication - snaptutorial.com
OPS 571 Effective Communication - snaptutorial.comdonaldzs34
 
Proefficient 1.0 - – AN HOLISTIC TOOL TO CALCULATE AND INTERPRET OVERALL EQU...
Proefficient 1.0 -  – AN HOLISTIC TOOL TO CALCULATE AND INTERPRET OVERALL EQU...Proefficient 1.0 -  – AN HOLISTIC TOOL TO CALCULATE AND INTERPRET OVERALL EQU...
Proefficient 1.0 - – AN HOLISTIC TOOL TO CALCULATE AND INTERPRET OVERALL EQU...Ruchir Gupta
 
OPS 571 HELP Inspiring Innovation--ops571help.com
OPS 571 HELP Inspiring Innovation--ops571help.comOPS 571 HELP Inspiring Innovation--ops571help.com
OPS 571 HELP Inspiring Innovation--ops571help.comclaric77
 
Plant Productivity Measurement, Analysis & Improvement: Business Case
Plant Productivity Measurement, Analysis & Improvement: Business CasePlant Productivity Measurement, Analysis & Improvement: Business Case
Plant Productivity Measurement, Analysis & Improvement: Business CaseMohammed Hamed Ahmed Soliman
 
Building a next generation facility fit tool
Building a next generation facility fit toolBuilding a next generation facility fit tool
Building a next generation facility fit toolGBX Summits
 
GregorySusa-Portfolio
GregorySusa-PortfolioGregorySusa-Portfolio
GregorySusa-PortfolioGregory Susa
 
5 Compelling Reasons To Embrace ERP Automation Technology
5 Compelling Reasons To Embrace ERP Automation Technology5 Compelling Reasons To Embrace ERP Automation Technology
5 Compelling Reasons To Embrace ERP Automation Technologyenvertisindia
 

What's hot (20)

How To Track OEE
How To Track OEEHow To Track OEE
How To Track OEE
 
Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)
 
Oee Explained
Oee ExplainedOee Explained
Oee Explained
 
Oee on hana overall equipment effectiveness overview aug 2012 (2)
Oee on hana   overall equipment effectiveness overview aug 2012 (2)Oee on hana   overall equipment effectiveness overview aug 2012 (2)
Oee on hana overall equipment effectiveness overview aug 2012 (2)
 
OEE System - Overall Equipment Effectiveness
OEE System - Overall Equipment EffectivenessOEE System - Overall Equipment Effectiveness
OEE System - Overall Equipment Effectiveness
 
Oee (overall equipment effectifness)
Oee (overall equipment effectifness)Oee (overall equipment effectifness)
Oee (overall equipment effectifness)
 
Using OEE to Improve Production - Interphex 2012
Using OEE to Improve Production - Interphex 2012Using OEE to Improve Production - Interphex 2012
Using OEE to Improve Production - Interphex 2012
 
Role Of OEE in Lean Manufacturing
Role Of OEE in Lean ManufacturingRole Of OEE in Lean Manufacturing
Role Of OEE in Lean Manufacturing
 
The visual machine_infographic 1.11.26 pm
The visual machine_infographic 1.11.26 pmThe visual machine_infographic 1.11.26 pm
The visual machine_infographic 1.11.26 pm
 
OEE IMPLEMENTATION part 1
OEE IMPLEMENTATION part 1OEE IMPLEMENTATION part 1
OEE IMPLEMENTATION part 1
 
OEE & MES - Help Food & Beverage Manufacturers 4-2011
OEE & MES - Help Food & Beverage Manufacturers 4-2011OEE & MES - Help Food & Beverage Manufacturers 4-2011
OEE & MES - Help Food & Beverage Manufacturers 4-2011
 
Oee part 2
Oee part  2 Oee part  2
Oee part 2
 
OPS 571 Effective Communication - snaptutorial.com
OPS 571 Effective Communication - snaptutorial.comOPS 571 Effective Communication - snaptutorial.com
OPS 571 Effective Communication - snaptutorial.com
 
Proefficient 1.0 - – AN HOLISTIC TOOL TO CALCULATE AND INTERPRET OVERALL EQU...
Proefficient 1.0 -  – AN HOLISTIC TOOL TO CALCULATE AND INTERPRET OVERALL EQU...Proefficient 1.0 -  – AN HOLISTIC TOOL TO CALCULATE AND INTERPRET OVERALL EQU...
Proefficient 1.0 - – AN HOLISTIC TOOL TO CALCULATE AND INTERPRET OVERALL EQU...
 
OPS 571 HELP Inspiring Innovation--ops571help.com
OPS 571 HELP Inspiring Innovation--ops571help.comOPS 571 HELP Inspiring Innovation--ops571help.com
OPS 571 HELP Inspiring Innovation--ops571help.com
 
Casestudy #3
Casestudy #3Casestudy #3
Casestudy #3
 
Plant Productivity Measurement, Analysis & Improvement: Business Case
Plant Productivity Measurement, Analysis & Improvement: Business CasePlant Productivity Measurement, Analysis & Improvement: Business Case
Plant Productivity Measurement, Analysis & Improvement: Business Case
 
Building a next generation facility fit tool
Building a next generation facility fit toolBuilding a next generation facility fit tool
Building a next generation facility fit tool
 
GregorySusa-Portfolio
GregorySusa-PortfolioGregorySusa-Portfolio
GregorySusa-Portfolio
 
5 Compelling Reasons To Embrace ERP Automation Technology
5 Compelling Reasons To Embrace ERP Automation Technology5 Compelling Reasons To Embrace ERP Automation Technology
5 Compelling Reasons To Embrace ERP Automation Technology
 

Similar to Why OEE?

The Critical KPI to drive Manufacturing Productivity
The Critical KPI to drive Manufacturing ProductivityThe Critical KPI to drive Manufacturing Productivity
The Critical KPI to drive Manufacturing ProductivityJason Corder
 
OEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing ProductivityOEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing ProductivityParsec_Automation_Corp
 
The Critical KPI to Drive Manufacturing Productivity
The Critical KPI to Drive Manufacturing ProductivityThe Critical KPI to Drive Manufacturing Productivity
The Critical KPI to Drive Manufacturing ProductivityCorey Vodvarka
 
The 7 deadly sins of Overall Equipment Effectiveness (OEE)
The 7 deadly sins of Overall Equipment Effectiveness (OEE)The 7 deadly sins of Overall Equipment Effectiveness (OEE)
The 7 deadly sins of Overall Equipment Effectiveness (OEE)Claire Healey
 
Design and Analysis of Chute System to obtain World Class OEE
Design and Analysis of Chute System to obtain World Class OEEDesign and Analysis of Chute System to obtain World Class OEE
Design and Analysis of Chute System to obtain World Class OEEijsrd.com
 
Managing OEE o optimize factory performance
Managing OEE o optimize factory performanceManaging OEE o optimize factory performance
Managing OEE o optimize factory performanceYasmin AbdelAziz
 
A Manager's Guide to OEE (Overall Equipment Effectiveness)
A Manager's Guide to OEE (Overall Equipment Effectiveness)A Manager's Guide to OEE (Overall Equipment Effectiveness)
A Manager's Guide to OEE (Overall Equipment Effectiveness)OEEsystems International
 
Mellor Consulting Group approach toward a BKM OEE deployment
Mellor Consulting Group approach toward a BKM OEE deployment Mellor Consulting Group approach toward a BKM OEE deployment
Mellor Consulting Group approach toward a BKM OEE deployment Mellor Consulting Group
 
Performance Analysis using OEE
Performance Analysis using OEEPerformance Analysis using OEE
Performance Analysis using OEEijsrd.com
 
Executive Guide to Leveraging OEE
Executive Guide to Leveraging OEEExecutive Guide to Leveraging OEE
Executive Guide to Leveraging OEEJason Corder
 
Whitepaper: How to perform better test on SAP PI/PO
Whitepaper: How to perform better test on SAP PI/POWhitepaper: How to perform better test on SAP PI/PO
Whitepaper: How to perform better test on SAP PI/PODaniel Graversen
 
6 OEE overview
6 OEE overview6 OEE overview
6 OEE overviewWebseology
 
Maintenance metrics in oee
Maintenance metrics in oeeMaintenance metrics in oee
Maintenance metrics in oeejohnsqms
 
Inventory plus oracle inventory zero_issues
Inventory plus oracle inventory zero_issuesInventory plus oracle inventory zero_issues
Inventory plus oracle inventory zero_issuesGeorge Faur
 
Meeting the challenges to adopt visual production management systems hms-whit...
Meeting the challenges to adopt visual production management systems hms-whit...Meeting the challenges to adopt visual production management systems hms-whit...
Meeting the challenges to adopt visual production management systems hms-whit...Ariel Lerer
 

Similar to Why OEE? (20)

OEE article
OEE articleOEE article
OEE article
 
OEE
OEEOEE
OEE
 
lean & agile
lean & agilelean & agile
lean & agile
 
The Critical KPI to drive Manufacturing Productivity
The Critical KPI to drive Manufacturing ProductivityThe Critical KPI to drive Manufacturing Productivity
The Critical KPI to drive Manufacturing Productivity
 
OEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing ProductivityOEE - The Critical KPI to Drive Manufacturing Productivity
OEE - The Critical KPI to Drive Manufacturing Productivity
 
The Critical KPI to Drive Manufacturing Productivity
The Critical KPI to Drive Manufacturing ProductivityThe Critical KPI to Drive Manufacturing Productivity
The Critical KPI to Drive Manufacturing Productivity
 
The 7 deadly sins of Overall Equipment Effectiveness (OEE)
The 7 deadly sins of Overall Equipment Effectiveness (OEE)The 7 deadly sins of Overall Equipment Effectiveness (OEE)
The 7 deadly sins of Overall Equipment Effectiveness (OEE)
 
Design and Analysis of Chute System to obtain World Class OEE
Design and Analysis of Chute System to obtain World Class OEEDesign and Analysis of Chute System to obtain World Class OEE
Design and Analysis of Chute System to obtain World Class OEE
 
Managing OEE o optimize factory performance
Managing OEE o optimize factory performanceManaging OEE o optimize factory performance
Managing OEE o optimize factory performance
 
A Manager's Guide to OEE (Overall Equipment Effectiveness)
A Manager's Guide to OEE (Overall Equipment Effectiveness)A Manager's Guide to OEE (Overall Equipment Effectiveness)
A Manager's Guide to OEE (Overall Equipment Effectiveness)
 
Mellor Consulting Group approach toward a BKM OEE deployment
Mellor Consulting Group approach toward a BKM OEE deployment Mellor Consulting Group approach toward a BKM OEE deployment
Mellor Consulting Group approach toward a BKM OEE deployment
 
Wcm4
Wcm4Wcm4
Wcm4
 
Performance Analysis using OEE
Performance Analysis using OEEPerformance Analysis using OEE
Performance Analysis using OEE
 
Executive Guide to Leveraging OEE
Executive Guide to Leveraging OEEExecutive Guide to Leveraging OEE
Executive Guide to Leveraging OEE
 
Whitepaper: How to perform better test on SAP PI/PO
Whitepaper: How to perform better test on SAP PI/POWhitepaper: How to perform better test on SAP PI/PO
Whitepaper: How to perform better test on SAP PI/PO
 
OEE Fact sheet
OEE Fact sheetOEE Fact sheet
OEE Fact sheet
 
6 OEE overview
6 OEE overview6 OEE overview
6 OEE overview
 
Maintenance metrics in oee
Maintenance metrics in oeeMaintenance metrics in oee
Maintenance metrics in oee
 
Inventory plus oracle inventory zero_issues
Inventory plus oracle inventory zero_issuesInventory plus oracle inventory zero_issues
Inventory plus oracle inventory zero_issues
 
Meeting the challenges to adopt visual production management systems hms-whit...
Meeting the challenges to adopt visual production management systems hms-whit...Meeting the challenges to adopt visual production management systems hms-whit...
Meeting the challenges to adopt visual production management systems hms-whit...
 

Recently uploaded

Bios of leading Astrologers & Researchers
Bios of leading Astrologers & ResearchersBios of leading Astrologers & Researchers
Bios of leading Astrologers & Researchersdarmandersingh4580
 
社内勉強会資料_Object Recognition as Next Token Prediction
社内勉強会資料_Object Recognition as Next Token Prediction社内勉強会資料_Object Recognition as Next Token Prediction
社内勉強会資料_Object Recognition as Next Token PredictionNABLAS株式会社
 
Las implicancias del memorándum de entendimiento entre Codelco y SQM según la...
Las implicancias del memorándum de entendimiento entre Codelco y SQM según la...Las implicancias del memorándum de entendimiento entre Codelco y SQM según la...
Las implicancias del memorándum de entendimiento entre Codelco y SQM según la...Voces Mineras
 
Ranking and Scoring Exercises for Research
Ranking and Scoring Exercises for ResearchRanking and Scoring Exercises for Research
Ranking and Scoring Exercises for ResearchRajesh Mondal
 
jll-asia-pacific-capital-tracker-1q24.pdf
jll-asia-pacific-capital-tracker-1q24.pdfjll-asia-pacific-capital-tracker-1q24.pdf
jll-asia-pacific-capital-tracker-1q24.pdfjaytendertech
 
如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样
如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样
如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样jk0tkvfv
 
一比一原版(曼大毕业证书)曼尼托巴大学毕业证成绩单留信学历认证一手价格
一比一原版(曼大毕业证书)曼尼托巴大学毕业证成绩单留信学历认证一手价格一比一原版(曼大毕业证书)曼尼托巴大学毕业证成绩单留信学历认证一手价格
一比一原版(曼大毕业证书)曼尼托巴大学毕业证成绩单留信学历认证一手价格q6pzkpark
 
原件一样(UWO毕业证书)西安大略大学毕业证成绩单留信学历认证
原件一样(UWO毕业证书)西安大略大学毕业证成绩单留信学历认证原件一样(UWO毕业证书)西安大略大学毕业证成绩单留信学历认证
原件一样(UWO毕业证书)西安大略大学毕业证成绩单留信学历认证pwgnohujw
 
obat aborsi Tarakan wa 081336238223 jual obat aborsi cytotec asli di Tarakan9...
obat aborsi Tarakan wa 081336238223 jual obat aborsi cytotec asli di Tarakan9...obat aborsi Tarakan wa 081336238223 jual obat aborsi cytotec asli di Tarakan9...
obat aborsi Tarakan wa 081336238223 jual obat aborsi cytotec asli di Tarakan9...yulianti213969
 
Identify Rules that Predict Patient’s Heart Disease - An Application of Decis...
Identify Rules that Predict Patient’s Heart Disease - An Application of Decis...Identify Rules that Predict Patient’s Heart Disease - An Application of Decis...
Identify Rules that Predict Patient’s Heart Disease - An Application of Decis...ThinkInnovation
 
Simplify hybrid data integration at an enterprise scale. Integrate all your d...
Simplify hybrid data integration at an enterprise scale. Integrate all your d...Simplify hybrid data integration at an enterprise scale. Integrate all your d...
Simplify hybrid data integration at an enterprise scale. Integrate all your d...varanasisatyanvesh
 
Northern New England Tableau User Group (TUG) May 2024
Northern New England Tableau User Group (TUG) May 2024Northern New England Tableau User Group (TUG) May 2024
Northern New England Tableau User Group (TUG) May 2024patrickdtherriault
 
Credit Card Fraud Detection: Safeguarding Transactions in the Digital Age
Credit Card Fraud Detection: Safeguarding Transactions in the Digital AgeCredit Card Fraud Detection: Safeguarding Transactions in the Digital Age
Credit Card Fraud Detection: Safeguarding Transactions in the Digital AgeBoston Institute of Analytics
 
Case Study 4 Where the cry of rebellion happen?
Case Study 4 Where the cry of rebellion happen?Case Study 4 Where the cry of rebellion happen?
Case Study 4 Where the cry of rebellion happen?RemarkSemacio
 
SCI8-Q4-MOD11.pdfwrwujrrjfaajerjrajrrarj
SCI8-Q4-MOD11.pdfwrwujrrjfaajerjrajrrarjSCI8-Q4-MOD11.pdfwrwujrrjfaajerjrajrrarj
SCI8-Q4-MOD11.pdfwrwujrrjfaajerjrajrrarjadimosmejiaslendon
 
如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证
如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证
如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证zifhagzkk
 
Huawei Ransomware Protection Storage Solution Technical Overview Presentation...
Huawei Ransomware Protection Storage Solution Technical Overview Presentation...Huawei Ransomware Protection Storage Solution Technical Overview Presentation...
Huawei Ransomware Protection Storage Solution Technical Overview Presentation...LuisMiguelPaz5
 
sourabh vyas1222222222222222222244444444
sourabh vyas1222222222222222222244444444sourabh vyas1222222222222222222244444444
sourabh vyas1222222222222222222244444444saurabvyas476
 

Recently uploaded (20)

Abortion pills in Riyadh Saudi Arabia| +966572737505 | Get Cytotec, Unwanted Kit
Abortion pills in Riyadh Saudi Arabia| +966572737505 | Get Cytotec, Unwanted KitAbortion pills in Riyadh Saudi Arabia| +966572737505 | Get Cytotec, Unwanted Kit
Abortion pills in Riyadh Saudi Arabia| +966572737505 | Get Cytotec, Unwanted Kit
 
Bios of leading Astrologers & Researchers
Bios of leading Astrologers & ResearchersBios of leading Astrologers & Researchers
Bios of leading Astrologers & Researchers
 
社内勉強会資料_Object Recognition as Next Token Prediction
社内勉強会資料_Object Recognition as Next Token Prediction社内勉強会資料_Object Recognition as Next Token Prediction
社内勉強会資料_Object Recognition as Next Token Prediction
 
Las implicancias del memorándum de entendimiento entre Codelco y SQM según la...
Las implicancias del memorándum de entendimiento entre Codelco y SQM según la...Las implicancias del memorándum de entendimiento entre Codelco y SQM según la...
Las implicancias del memorándum de entendimiento entre Codelco y SQM según la...
 
Ranking and Scoring Exercises for Research
Ranking and Scoring Exercises for ResearchRanking and Scoring Exercises for Research
Ranking and Scoring Exercises for Research
 
jll-asia-pacific-capital-tracker-1q24.pdf
jll-asia-pacific-capital-tracker-1q24.pdfjll-asia-pacific-capital-tracker-1q24.pdf
jll-asia-pacific-capital-tracker-1q24.pdf
 
如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样
如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样
如何办理(UCLA毕业证书)加州大学洛杉矶分校毕业证成绩单学位证留信学历认证原件一样
 
一比一原版(曼大毕业证书)曼尼托巴大学毕业证成绩单留信学历认证一手价格
一比一原版(曼大毕业证书)曼尼托巴大学毕业证成绩单留信学历认证一手价格一比一原版(曼大毕业证书)曼尼托巴大学毕业证成绩单留信学历认证一手价格
一比一原版(曼大毕业证书)曼尼托巴大学毕业证成绩单留信学历认证一手价格
 
原件一样(UWO毕业证书)西安大略大学毕业证成绩单留信学历认证
原件一样(UWO毕业证书)西安大略大学毕业证成绩单留信学历认证原件一样(UWO毕业证书)西安大略大学毕业证成绩单留信学历认证
原件一样(UWO毕业证书)西安大略大学毕业证成绩单留信学历认证
 
obat aborsi Tarakan wa 081336238223 jual obat aborsi cytotec asli di Tarakan9...
obat aborsi Tarakan wa 081336238223 jual obat aborsi cytotec asli di Tarakan9...obat aborsi Tarakan wa 081336238223 jual obat aborsi cytotec asli di Tarakan9...
obat aborsi Tarakan wa 081336238223 jual obat aborsi cytotec asli di Tarakan9...
 
Identify Rules that Predict Patient’s Heart Disease - An Application of Decis...
Identify Rules that Predict Patient’s Heart Disease - An Application of Decis...Identify Rules that Predict Patient’s Heart Disease - An Application of Decis...
Identify Rules that Predict Patient’s Heart Disease - An Application of Decis...
 
Simplify hybrid data integration at an enterprise scale. Integrate all your d...
Simplify hybrid data integration at an enterprise scale. Integrate all your d...Simplify hybrid data integration at an enterprise scale. Integrate all your d...
Simplify hybrid data integration at an enterprise scale. Integrate all your d...
 
Northern New England Tableau User Group (TUG) May 2024
Northern New England Tableau User Group (TUG) May 2024Northern New England Tableau User Group (TUG) May 2024
Northern New England Tableau User Group (TUG) May 2024
 
Credit Card Fraud Detection: Safeguarding Transactions in the Digital Age
Credit Card Fraud Detection: Safeguarding Transactions in the Digital AgeCredit Card Fraud Detection: Safeguarding Transactions in the Digital Age
Credit Card Fraud Detection: Safeguarding Transactions in the Digital Age
 
Case Study 4 Where the cry of rebellion happen?
Case Study 4 Where the cry of rebellion happen?Case Study 4 Where the cry of rebellion happen?
Case Study 4 Where the cry of rebellion happen?
 
Abortion pills in Jeddah | +966572737505 | Get Cytotec
Abortion pills in Jeddah | +966572737505 | Get CytotecAbortion pills in Jeddah | +966572737505 | Get Cytotec
Abortion pills in Jeddah | +966572737505 | Get Cytotec
 
SCI8-Q4-MOD11.pdfwrwujrrjfaajerjrajrrarj
SCI8-Q4-MOD11.pdfwrwujrrjfaajerjrajrrarjSCI8-Q4-MOD11.pdfwrwujrrjfaajerjrajrrarj
SCI8-Q4-MOD11.pdfwrwujrrjfaajerjrajrrarj
 
如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证
如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证
如何办理(Dalhousie毕业证书)达尔豪斯大学毕业证成绩单留信学历认证
 
Huawei Ransomware Protection Storage Solution Technical Overview Presentation...
Huawei Ransomware Protection Storage Solution Technical Overview Presentation...Huawei Ransomware Protection Storage Solution Technical Overview Presentation...
Huawei Ransomware Protection Storage Solution Technical Overview Presentation...
 
sourabh vyas1222222222222222222244444444
sourabh vyas1222222222222222222244444444sourabh vyas1222222222222222222244444444
sourabh vyas1222222222222222222244444444
 

Why OEE?

  • 1. April 2020 Outline Overall Equipment Effectiveness or OEE is a method of looking at a manufacturing process to determine how well it is operating. It combines three metrics to provide a single measure that encompasses the utilisation of an asset, if it is being run at its optimum speed, and what proportion of scrap to good products are being produced. OEE (%) = Availability (%) x Performance (%) x Quality (%) 10000 Savings Unless you have a site that is already extremely efficient, in virtually all cases that I have come across it is possible to get a payback for a system in just a few weeks. After that you are saving money and improving your bottom line. Generally there are also benefits realised that were not apparent initially. For example, with one timber mill, it was presumed that the operator on one of their stackers was stood waiting for about 1½ hours in an 8 hour shift. After an automatic OEE system was installed it became clear that it was actually 4½ hours. As a result their process was adjusted to build up a buffer and the operator redeployed on other tasks during their ‘newly available’ time. When not to implement Implementing an OEE system will not inherently make you more efficient or save you money. The only way to make it work is if you actively use the data it generates. Ideally more than one member of staff should champion the process. Otherwise if that person is busy or if they leave, you are left without appropriate knowledge and the system is unlikely to be successful. You also need buy-in from the top management all the way down to the shop floor. Fundamentally you need to be committed to it, or you will just be wasting your time and money. Why OEE? by Ashley Tizard Summary This article highlights both the pros and cons of implementing OEE in a manufacturing environment. I have tried to include both the positive and negative elements to give a balanced view, and have also included some of the best practices that I have seen over the last 29 years that I have been working in the industry. Although my background is as a software developer and in particular using the PlantRun and Prodigy software platforms, the concepts described here are universally applicable. OEE  Machine Downtime  Manufacturing Information Systems The pros and cons of implementing an OEE system April 2020 1
  • 2. April 2020 OEE  Machine Downtime  Manufacturing Information Systems 2 Available or not… The availability metric immediately brings up some interesting differences in possible approach. From the production plan point of view, operators are expected to be running their assets according to a defined shift pattern with allowances for breaks, clean up times etc. This gives an amount of available time for running on each asset. It can, however, make it complicated when, for example, operators are off sick, the production plan needs to change on the fly, or an impromptu meeting is held. Ultimately this leads to an increased administration requirement which, in my experience can result in the system falling out of favour as the overhead is too onerous. I think in most cases it is better to handle the planned not to run periods by using simple concepts such as identifying when an operator is not logged on to an asset. Then there is no additional administration and logging on can be enforced through the use of machine interlocks. What is the target speed? Takt or cycle times for machines can be well defined but that is only the start of the story. Production planning systems will calculate how many products of a particular type can be manufactured in a given amount of time. They take into account changeover and clean down times, and include timings for bringing raw materials to an asset and taking finished goods away. This gives most sites their performance targets. However, I have seen many cases where the data in the ERP/MES is based on historic hearsay and is not particularly accurate. A little while ago, I was stood with a production manager at a site looking at a machine with a speed measurement above it of about 200 m/hr. I questioned how they knew if it was running at the correct speed and what the target speed was. The discussion progressed to the fact that when the machine was installed the manufacturer said it could run at 800 m/hr, as the machine was now quite old they had recently said that they thought that it would probably be capable of 400 m/hr. “Ok” I said, “but why is it running at 200?”. “That’s a good question” was the response… The target speed for each product should be reviewed and if there is uncertainty about them then data needs to be collected initially to allow an accurate figure to be determined and then fixed. Availability is an indication of the time that an asset is running. It is calculated as the operating time as a percentage of the planned production time (otherwise known as available time). Performance is an indication of how close the asset is running to its target production rate for the product being made. It is calculated as the number of products produced as a proportion of the possible number of products that could have been made in the running time.
  • 3. April 2020 OEE  Machine Downtime  Manufacturing Information Systems 3 Quality products OEE accounts for the quality metric with exactly the same weight as availability and performance, however, in most instances the early wins at a site do not initially come from targeting quality issues. That is not to say that it should be ignored though. If you speed up production to improve performance, you may inadvertently reduce the quality. Ideally if the quality metric is not going to be targeted initially, I would suggest using a nominal value, for example, defining a percentage of all products manufactured to be scrap. World class performance? World class performance is often quoted at 85% but the reality is that it is wholly dependent on the manufacturing process for a particular type of product. In some cases a 50% OEE may be exceptional. Ultimately, OEE is a benchmark that should be used to determine whether a site is making improvements or not. It doesn’t matter if the actual value is 85% or 25%. Paper based data collection Manual, paper based systems allow users to become familiar with the concepts of OEE and are, therefore, a good starting point. However, they have two key issues: 1. It can require a significant amount of time to interpret handwriting and transcribe it into a tool that can be used to analyse the data. 2. Human nature would inherently mean that the data is not accurate. If I was running an asset, my focus would be manufacturing products, not filling in a form. If I reached the end of an 8 hour shift and realised that I had made 500 products instead of 1000, I would assume that it would be because I had 4 hours of breakdown. I would be unlikely to remember how long any period of stoppage was for and every reason that the asset stopped. An automatic system will accurately timestamp each stoppage event and can be used to force reasons to be entered at the time they occur. This leads to better data that can be automatically analysed. Quality is an indication of how well the products are being made. It is calculated as the number of good products as a proportion of the total number that were started. OEE OEE is a widely used analysis and benchmarking metric. World class sites are regarded as an 85% or above OEE, and the average OEE is around 65%.
  • 4. April 2020 OEE  Machine Downtime  Manufacturing Information Systems 4 What about manual assembly? Although tracking OEE for a manual assembly process is inherently dependent on an operator entering accurate information, there is no reason why it cannot be monitored so that data is collated electronically and automatically processed, meaning that there is only minimal administration required. If you also look at minimising operator interactions using barcode scanners, RFID readers, and the integration of the OEE system with production planning to get works orders / jobs automatically, then there are some significant additional benefits to be realised. Response times In order to improve, one of the key areas to address is response times. This may be simply highlighting to management when an asset has been stopped for an extended period of time, or improving the notification / call out mechanisms available for maintenance staff. For longer stoppages there is often a disagreement between production and maintenance about how long a breakdown took to repair. Recording call out and response times allows these period to be analysed in more detail to determine, for example, if there are sufficient maintenance staff on a night shift. In addition, allowing operators to request raw materials or their team leader, direct from their asset can also result in shorter stoppages. What about the detail? In order to make improvements you will need to go from the 3 key metrics into the data that they are made up of. For example, • If the availability measure is low then you need to understand what stoppages have occurred and why? • If the performance metric is low, you need to be able to review the data to determine what is happening and potentially see the reasons for slow speed running. • If the quality measure is low, what are the reasons for scrap?
  • 5. April 2020 OEE  Machine Downtime  Manufacturing Information Systems 5 Why OEE? OEE is not a panacea but it is a great tool for identifying where issues are and providing a means of seeing that improvements have been made. Implementing an OEE system that can be easily expanded over time to cover more assets and include additional functional areas is a way of instilling continuous improvement throughout the workforce. After all, your competitors are improving and unless you continue to become more efficient, you will get left behind. About the Author Ashley Tizard is the Managing Director of Tascomp Ltd. He has implemented machine downtime systems for almost 30 years, looking at the reasons for stoppages, OEE, and improving response times to issues. He has worked in virtually all manufacturing industry sectors, including: • Food & Drink • Chemicals and Pharmaceuticals • Metals • Forestry Products • Automotive • Aerospace • Print • Textiles