SlideShare a Scribd company logo
1 of 5
Download to read offline
Abstract--- In this paper, we have addressed a Multi
Objective Problem (MOP) which covers-minimize the
makespan, tardiness, load variation, flow time and secondary
resources constraints for unrelated parallel machine
scheduling problem with consideration of inherent uncertainty
in processing times and due dates. To resolve the above
computationally challenge problem in a reasonable time and
to find a good approximation of Pareto frontier, we have
proposed a Multi-Objective Evolutionary Algorithm (MOEA)
based Fuzzy-Non-dominated Sorting Genetic Algorithm
(FNSGA-II). Over randomly generated test problems, the
performance of the proposed algorithm is validated and the
results are analyzed for the benefit of the manufacturer.
Finally, statistical analysis has been conducted and found that
the proposed algorithm performs reasonably well in terms of
quality, computational time, diversity and spacing metrics.
Keywordsā€“ Load Variation, MOEA, Makespan,
Tardiness, Unrelated Parallel Machine
I. INTRODUCTION
HE parallel machine scheduling problem (PMSP) is a very
common production environment that can be found in
several manufacturing situations, in which the allocation of a
set of jobs are assigned to a number of parallel machines in
order to meet customerā€™s requirement. In general, from the
literature it is found that PMSP is categorized as identical,
uniform and unrelated parallel machine scheduling
problem[1]. Among the above mentioned classifications, it is
found that for unrelated PMSP (UPMSP) the processing time
of each job depends on machines with different processing
capabilities it is assigned to, where workstations are supposed
to be non-identical. However, handling of UPMSPā€™s with real
life cases is a challenge for researchers and Practitioners due
V.K.Manupati, Assistant professor, Department of Mechanical
Engineering, KL University, Andhra Pradesh, India. E-mail:
manupativijay@gmail.com
R. Sridharan, Professor, Department of mechanical Engineering, NIT
Calicut, Kerala, India. E-mail: sreedhar@nitc.ac.in
N. Arudhra, Student, Department of Mechanical Engineering, KL
University, Andhra Pradesh, India. E-mail: arudhra19@gmail.com
P.Bharadwaj, Student, Department of Mechanical Engineering, KL
University, Andhra Pradesh, India. E-mail:bharadwaj.popuri9@gmail.com
D.Trinath, Student, Department of Mechanical Engineering, KL
University, Andhra Pradesh, India. E-mail:trinathh@outlook.com
M.V.B.T.Santhi, Assistant professor, Department of Computer Science
and Engineering, KL University, Andhra Pradesh, India. E-mail:
santhi_ist@kluniversity.in
to the fact that they are mostly NP-hard in nature and their
special characteristics/requirements in practice [2].
The unrelated parallel machine system has been solved
with many methods and techniques and it has been widely
addressed in the literature from past few years. Leeet al. [6]
addressed the UPMSP to minimize the objective function i.e.,
with dedicated machines and common deadlines kim et al.[4]
and arnaout et al.[5] presented a simulated Annealing and ant
colony algorithm optimization approach for the UPMSP with
sequence dependent setup times.
In real world scheduling problems many factors are often
uncertain. This research deals with scheduling of number of
jobs on an unrelated parallel machine system with secondary
resource constraints. Where, each job can only be processed if
its required machine and other secondary resources are
available
The remainder of this paper is organized as follows. In
section 2, we give a detailed description of the problem with
the basic assumptions and developed a mathematical model
along with the constraints. Section 3 explains the mapping of
NSGA-II, MPSO algorithms for solving the MOP. The
experimentation with an illustrative example having different
complex scenarios is illustrated in Section 4. In Section 5, the
results and their discussions are detailed. The paper concludes
with Section 6 suggesting the directions of the future work.
II. PROBLEM DESCRIPTION
In this paper, we propose a multi-objective UPMSP with
non-zero ready times, job-sequence-and machine-dependent
setup times, and the auxiliary resource constraints in a fuzzy
based environment for improving the performance measures
such as makespan, flow time, tardiness and machine load
variation. Here we consider a set of jobs with j = {1,2.., n} of
n that have to be processed on exactly one machine out of a set
M= {1,2.., m} of m parallel machines. The jobs are processed
on machines that are available continuously to process at most
one job J at a time. When jobs are processing on the machines
we have consider that pre-emption is not allowed and jobs are
processing on machines k with their processing times,
tardiness, makespan and load variation. In this problem, we
consider a sequence dependent and machine dependent which
deals with processing times, and setup times, when a machine
switches its production from job i to job j on the same
machine. We do not consider setup times before processing
the first job on a machine. In this problem the occurrence of
machine idle time is allowed. Idle time on a machine may be
A fuzzy Multi-Objective Based Un-Related Parallel
Machines Scheduling Problem with Sequence and
Machine Dependent Setup Times
V.K.Manupati, R. Sridharan, N. Arudhra, P. Bharadwaj, D.Trinath and M.V.B.T. Santhi
T
International Conference on Advances in Design and Manufacturing (ICAD&M'14) 1275
ISBN 978-93-84743-12-3 Ā© 2014 Bonfring
required to complete a job on its due date, avoiding earliness.
However, to meet the requirements from real-world
production, we have considered more than two objectives
corresponding to constraints for Multi objective problem. The
above mentioned problem makes several assumptions that are
worth highlighting.
2.1 Assumptions
1. Each job requires an operation that can be done on all
machines,
2. Jobā€™s setup times are sequence and machine
dependent,
3. Jobs may have different arrival (ready) times,
4. Assignment of a job to a machine is permitted if the
required secondary resource(s) (e.g., tool, die) is (are)
available,
5. Processing times of jobs are machine dependent,
6. Preemption and machine breakdown are not allowed,
7. Processing times and due dates of jobs due to possible
fluctuations in real world are subject toepistemic
uncertainty (i.e. lack of knowledge in estimating these
parameters precisely).
The indices, parameters and variables used to formulate
the problem mathematically are described below.
1
0
1
0
1 sin
Decision varibles :
if job i precedes job j on machine k
otherwise
if job i is assigned to machine k
otherwise
if proces g of job i is finished before
X
ijk
Yjk
Zij
ļ£±ļ£“
= ļ£²
ļ£“ļ£³
ļ£±
= ļ£²
ļ£³
= sin
0
proces g of job j starts
otherwise
ļ£±
ļ£“
ļ£²
ļ£“
ļ£³
2.2 Mathematical Model
By allocating the above mentioned assumptions and
notations, the problem is being formulated as the following
fuzzy mixedā€“integer nonā€“linear programming (FMINLP)
model.
International Conference on Advances in Design and Manufacturing (ICAD&M'14) 1276
ISBN 978-93-84743-12-3 Ā© 2014 Bonfring
Objectives :
N
= w c (1)i i
i=1
N
= w (c -c )(D) (2)i i+1 i
MinZ1
Min Z2
M
i=1
= w (cin -s )i i
i
Z3 i
āˆ‘
āˆ‘
N
(3)
=1
M k= (D)(c -c ) (4)max max
k=1
Subjected to constraints :
1 ;
1 1
MinZ4
Ā Ā 
N m
Xijk j
i k
i j
āˆ‘
āˆ‘
= āˆ€āˆ‘ āˆ‘
= =
ā‰ 
;
Ā  (5)Ā 
(6)
1, , Ā Ā 
,
1
;
1
1
N
X Yijk jk j k
i
i j
N
X Yijk ik
j
i N
j
= āˆ€āˆ‘
=
ā‰ 
ā‰¤āˆ‘
=
= ā€¦
ā‰ 
(7)
, , Ā Ā  (8)
,Ā  ) (9)Ā Ā Ā Ā Ā 
,
(1 ) Max{c } ;,
(1 ) (c , ) ; (
1
1; Ā 
c A Xijk s s pj N i ijk j jk
M
c A z Max s p Yj N ij i j jk jk
k
i j k
i
z zij ji
jƎS i jr
i jƎ
+ āˆ’ ā‰„ + +
+ āˆ’ ā‰„ + āˆ‘
=
+ =
ā‰ 
( )
(10),Ā 
,Ā  Ā  (11),Ā 
; Ā Ā 
;
1
S i jr
i jƎS i jr
T C di
M
X zijk ij
i
k
i i
ā‰ 
ā‰ ā‰¤āˆ‘
=
ā‰„ āˆ€ā”€
{ } ( )
(12)
0; 0; , 0,1 ;Ā  , , .Ā Ā Ā Ā Ā  13 Ā 
, ,
C T I X Y Z Ǝ i j k
i i ijk ik ij
ā‰„ ā‰„
The above mentioned objectives, i.e. minimization of total
weighted makespan(Z1), total weighted flow time(Z2)total
weighted tardiness(Z3), machine load variation(Z4) are given
by Eqs. (1) ā€“ (4), respectively. Eq (5)assures that each job is
only assigned to one position on a machine. Eq(6) suggests
that if job jis allotted to machine k, then it is adopted by
another job indicating dummy job 0. Constraint (7)specify that
at most one job can immediately adopt the previously allotted
job i on machine k. Constraint (8)computes the completion
time of job when it is processed instantly after job i on
machine . Constraint (9 and 10)ensures that if job I and j
needs same tool, one must be finished earlier before starting
the other. Constraint (11)gives the relation between Xijk and
Zij.Eq(12)computes tardiness of job i.Eventually Eq(13)points
the non-negativity and integrality constraints.
III. MULTI-OBJECTIVE BASED EVOLUTIONARY
ALGORITHM
Most of the UPMSPs are NP-hard in nature and due to its
characteristic it is necessary to solve more than two objectives
simultaneously to find out the optimal solutions that are very
close to reality. In general, it is very difficult to solve the
multiple objectives simultaneously thus we adopted multi-
objective based evolutionary algorithms for solving the above
mentioned complex problem.[7] In this paper, we apply a
NSGA-II which includes parito ranking and crowding system
mechanism for selection of the individuals
3.1.Nondominated sorting Genetic Algorithm
Goldberg was the first who suggested the concept of non-
dominated sorting genetic algorithm (NSGA) and Srinivas and
Deb were the first to implement it. Where NSGA differs from
well known simple genetic algorithm is only in the way the
selection operator works. Although NSGA has been used to
solve a variety of MOPs, its main drawbacks include: (i)high
computational complexity of non-dominated sorting, (ii) lack
of elitism, and (iii) the need for specifying the tunable
parameter. With the advent of NSGA-II, the above mentioned
drawbacks have been resolved.
3.1.1. Initial population generation
Fig.1: Initial Population Generation.
We randomly generate the initial population for a given
population size. According to the characteristics of the
proposed problem, encoding schema and its representation is
designed. An example of the encoding scheme for the problem
is illustrated in Fig 1. Here, we have considered the number of
jobs(1 to 6) as chromosome which is having length seven,
where jobs should process on machines (1 to 4) in such a way
that the secondary resources ( 1 to 3 ) must available. In the
second set of the chromosome representation the machines
and their secondary resources and the encoding scheme of this
layer is shown in Fig 2b. In this layer, zeroes indicate, no job
assign on the machine. One more advantage of indicating
zeroes is for maintaining the chromosome length as uniform.
3.1.2. Evolutionary operators
Cross over
Crossover chooses genes from parent chromosomes and
produce a new offspring. Crossover is done by swapping
portions between two parent chromosomes. It is based on
basic parameter called crossover probability. Specific
crossover built for a particular problem can improve
performance of the genetic algorithm.
Mutation
International Conference on Advances in Design and Manufacturing (ICAD&M'14) 1277
ISBN 978-93-84743-12-3 Ā© 2014 Bonfring
Mutation randomly used for alternating the values of
particular genes to prevent diminishing all solutions in
population into a local optimum of solved problem.
Non dominated sorting
Non dominating sorting is done by choosing the best
pareto front which is spread throughout the space by
tournament selection based on Pareto domination.
Fig.2: Schematic Procedure for Processing NSGA-II.
OP ā€“Offspring population
PP - Parent population
Fig 2, describes the schematic algorithm throughout the
processing of NSGA-II (Deb et al. 2000)
crowding distance
Crowding distance can be calculated for all chromosomes
of same pareto front, then individual having large crowding
distance is selected to obtain uniform distribution.
Stopping rule
If the maximum generation is reached then stop.
IV. EXPERIMENTATION
Here, Card (g) describes the cardinality of test sample, and
Ī±, Ī² represents the control of job arrival and control of
tightness respectively.
Table 1: Test Sample (TS) Form Machine Shop
Table 1 represents a raw data of random test sample (TS)
taken from a cable and manufacturing company that is
incorporated as unrelated parallel machine which have
sequence dependent and machine dependent setup times
.
V. RESULTS AND DISCUSSION
Figure 3: Pareto Optimal Front for Sets Considering
Makespan vs. Flow Time.
Figure 4: Pareto Optimal Front for Sets Considering
Makespan vs. Tardiness.
Figure 5: Pareto Optimal Front for Sets Considering
Makespan vs. Machine Load Variation.
Pareto optimal front is obtained using the evolutionary
operators based on concerned performance measures(Fig:3,
Fig:4, Fig: 5) such as minimization of makespan, flowtime,
tardiness, and machine load variation, for randomly selected
test samples. The make span is the total completion time of
jobs, flow time is the time taken by the required job to
complete, tardiness is lateness or slow processing i.e., more
than due date, machine load variation is the time to setup or
calibration of machine during processing of jobs on the
machines. Results show better solutions and achieved Pareto
optimal solutions
VI. CONCLUSION AND FUTURE WORK
This paper proposes a fuzzy multi objective UPMSP with
non zero ready times, sequence and machine dependent setup
times. Moreover, we have considered secondary resource
0
200
400
45.542.940.931.123.120.916.614.2 7.3
flowtime
Makespan
Makespan vs Flowtime
Set 1
Set 2
0.00
100.00
200.00
45.5
42.9
40.9
32.3
31.9
23.8
20.9
16.6
14.2
7.3
Tardiness
Makespan
Makespan vs Tardiness
Set
3
0.00
200.00
25.8
33.9
18.7
45.9
9.3
24.9
46.8
48.3
13.4
35.6
MachineLoad
variation
Makespan
Makespan vs Machine load
variation Set 1
Set 2
Set 3
International Conference on Advances in Design and Manufacturing (ICAD&M'14) 1278
ISBN 978-93-84743-12-3 Ā© 2014 Bonfring
constraints to simultaneously solving different performance
measures to obtain pareto optimal solutions. Here, we have
considered different performance measures as minimization of
makespan, total weighted tardiness, total weighted flow time,
machine load variation. To solve the above mentioned
complex NP hard problem it is necessary to adopt a multi-
objective based evolutionary algorithm i.e., NSGA-II. With
different problem sets by varying its cardinality starting time
and due date the performance of the algorithm is examined.
Experimental results show that the proposed approach is
performing better and obtained optimal solutions in the future
work, one can compare with different multi-objective
evolutionary algorithms and also on large data sets that can
bring the experimentation close to reality.
REFERENCES
[1] T. Cheng, C. Sin, A state-of-the-art review of parallel-machine
schedulingresearch, European Journal of Operational Research 47
(1990) 271ā€“292.
[2] S.A. TORABI, N.Sahebjamnia, S.A.Mansouri,M. Aramon bajestani, ā€œA
particle swarm optimization for fuzzy multi-objective unrelated parallel
machines scheduling problemā€,Applied Soft Computing, 13(2013)4750-
4762.
[3] J.-Y. Bang, Y.-D. Kim, Scheduling algorithms for a semiconductor
probing facil-ity, Computers and Operations Research 38 (2011) 666ā€“
673.
[4] J.-P. Arnaout, G. Rabadi, R. Musa, A two-stage ant colony
optimizationalgorithm to minimize the makespan on unrelated parallel
machines withsequence-dependent setup times, Journal of Intelligent
Manufacturing 21(2010) 693ā€“701.
[5] F.A. Cappadonna,A. Costa,S. Fichera, ā€œMake span minimization of
unrelated parallel machines with limited human resourcesā€,Procedia
CIRP 12(2013)450-455.
[6] Lee, Cheng-Hsiung, Ching-Jong Liao, and Chien-Wen Chao. "Unrelated
parallel machine scheduling with dedicated machines and common
deadline." Computers & Industrial Engineering (2014).
[7] Deb, Kalyanmoy. "Multi-objective optimization." Search
methodologies. Springer US, 2014. 403-449.
Dr. Vijay Kumar Manupati received the B-Tech
degree in Department of mechanical engineering from
Siddhardha Engineering College, and M-Tech in
Department of Mechanical engineering with Industrial
Engineering and Management as a specialization from
National Institute of Technology Calicut. He received
his PhD in Department of Industrial and Systems
Engineering from Indian Institute of Technology
Kharagpur. His current research interests belong include
Intelligent manufacturing systems, agent/multi-agent/mobile-agent systems
for distributed control, simulation, integration of process planning and
scheduling in manufacturing. He has published papers inInternational Journal
of Production Research, Computers and Industrial Engineering, and
International Journal of Advanced Manufacturing Technology.
Dr.R.Sridhran completed his B. E. Honours in
Mechanical engineering from madras University, M-
Tech in Department of Industrial Engineering and
Operation Research specialization from IIT Kharagpur,
and Ph. D. in department of Industrial Engineering from
IIT Bombay. He had published many publications and
technical reports in reputed journals. His areas of
research are Operation Management, Supply Chain
Management, Decision Modelling, Simulation Modelling and Analysis
Arudhra Nerella pursuing his Bachelor degree in
Mechanical Engineering from KLUniversity
(Vijayawada, Andhra Pradesh, India). He worked on
several projects like ā€œControlling the Defects in
Centrifugal Castingā€, ā€œDeveloped a Flexible
Manufacturing System using Cellular Manufacturing
Techniquesā€. He is a Member of American Society of
Mechanical Engineers. His research interest includes manufacturing,
production, and Supply chain management
TRINATH DESIBOYINA, was born on June 12th
1992 and perusing B .Tech in mechanical engineering
at KLUniversity(2011-2015).He has done internship at
GENTING LANCO Power(India) Private Limited,
Kondapalli,and done an automobile oriented project on
ā€˜Aero carā€™s, an environmental oriented project on
ā€˜Solar cellā€™, and a technical project on ā€˜Conditional
monitoring on rotating machines using vibrational
analysisā€™ these were done as a part of curriculum
BHARADWAJ POPURI: was born on July 30th
1993
and pursuing B.Tech in mechanical engineering at
KLUniversity (2011-2015),he has done internship on
Quality control charts for variables and attributes at
ā€œModel Dairy Private Limitedā€, and done his projectā€™s
on ā€˜ wire electric discharge machiningā€™ and ā€˜lean
manufacturing in processing industryā€™ as a part of
curriculum.
M.V.B.T.Santhi received the M-Tech degree in
Computer Science and Engineering from AN
University, in 2010 & B-Tech degree in Computer
Science and Engineering from Jawaharlal Nehru
Technology University, Hyderabad, in 2003 .She is
currently working as an Assistant Professor in
Department of Computer Science & Engineering,
Koneru Lakshmaiah University, Vaddeswaram, Guntur
Dist.A.P
International Conference on Advances in Design and Manufacturing (ICAD&M'14) 1279
ISBN 978-93-84743-12-3 Ā© 2014 Bonfring

More Related Content

What's hot

11.bicriteria in n x 0003www.iiste.org call for paper flow shop scheduling un...
11.bicriteria in n x 0003www.iiste.org call for paper flow shop scheduling un...11.bicriteria in n x 0003www.iiste.org call for paper flow shop scheduling un...
11.bicriteria in n x 0003www.iiste.org call for paper flow shop scheduling un...Alexander Decker
Ā 
Bicriteria in n x 3 flow shop scheduling under specified rental policy (2)
Bicriteria in n x 3 flow shop scheduling under specified rental policy (2)Bicriteria in n x 3 flow shop scheduling under specified rental policy (2)
Bicriteria in n x 3 flow shop scheduling under specified rental policy (2)Alexander Decker
Ā 
AN ANT COLONY OPTIMIZATION ALGORITHM FOR JOB SHOP SCHEDULING PROBLEM
AN ANT COLONY OPTIMIZATION ALGORITHM FOR JOB SHOP SCHEDULING PROBLEMAN ANT COLONY OPTIMIZATION ALGORITHM FOR JOB SHOP SCHEDULING PROBLEM
AN ANT COLONY OPTIMIZATION ALGORITHM FOR JOB SHOP SCHEDULING PROBLEMijaia
Ā 
14 sameer sharma final_paper
14 sameer sharma final_paper14 sameer sharma final_paper
14 sameer sharma final_paperAlexander Decker
Ā 
IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...
IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...
IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...IJCSEA Journal
Ā 
Heuristic approach for bicriteria in constrained three stage flow shop schedu...
Heuristic approach for bicriteria in constrained three stage flow shop schedu...Heuristic approach for bicriteria in constrained three stage flow shop schedu...
Heuristic approach for bicriteria in constrained three stage flow shop schedu...Alexander Decker
Ā 
Heuristic approach for bicriteria in constrained three stage flow shop schedu...
Heuristic approach for bicriteria in constrained three stage flow shop schedu...Heuristic approach for bicriteria in constrained three stage flow shop schedu...
Heuristic approach for bicriteria in constrained three stage flow shop schedu...Alexander Decker
Ā 
11.flow shop scheduling problem, processing time associated with probabilitie...
11.flow shop scheduling problem, processing time associated with probabilitie...11.flow shop scheduling problem, processing time associated with probabilitie...
11.flow shop scheduling problem, processing time associated with probabilitie...Alexander Decker
Ā 
A M ULTI -O BJECTIVE B ASED E VOLUTIONARY A LGORITHM AND S OCIAL N ETWOR...
A M ULTI -O BJECTIVE  B ASED  E VOLUTIONARY  A LGORITHM AND  S OCIAL  N ETWOR...A M ULTI -O BJECTIVE  B ASED  E VOLUTIONARY  A LGORITHM AND  S OCIAL  N ETWOR...
A M ULTI -O BJECTIVE B ASED E VOLUTIONARY A LGORITHM AND S OCIAL N ETWOR...IJCI JOURNAL
Ā 
A tricky task scheduling technique to optimize time cost and reliability in m...
A tricky task scheduling technique to optimize time cost and reliability in m...A tricky task scheduling technique to optimize time cost and reliability in m...
A tricky task scheduling technique to optimize time cost and reliability in m...eSAT Publishing House
Ā 
Modified heuristic time deviation Technique for job sequencing and Computatio...
Modified heuristic time deviation Technique for job sequencing and Computatio...Modified heuristic time deviation Technique for job sequencing and Computatio...
Modified heuristic time deviation Technique for job sequencing and Computatio...ijcsit
Ā 
An efficient simulated annealing algorithm for a No-Wait Two Stage Flexible F...
An efficient simulated annealing algorithm for a No-Wait Two Stage Flexible F...An efficient simulated annealing algorithm for a No-Wait Two Stage Flexible F...
An efficient simulated annealing algorithm for a No-Wait Two Stage Flexible F...ijait
Ā 
International Refereed Journal of Engineering and Science (IRJES)
International Refereed Journal of Engineering and Science (IRJES)International Refereed Journal of Engineering and Science (IRJES)
International Refereed Journal of Engineering and Science (IRJES)irjes
Ā 
IRJET- Two-Class Priority Queueing System with Restricted Number of Priority ...
IRJET- Two-Class Priority Queueing System with Restricted Number of Priority ...IRJET- Two-Class Priority Queueing System with Restricted Number of Priority ...
IRJET- Two-Class Priority Queueing System with Restricted Number of Priority ...IRJET Journal
Ā 
8.yongching lim 89-100
8.yongching lim 89-1008.yongching lim 89-100
8.yongching lim 89-100Alexander Decker
Ā 
Job Shop Scheduling Using Mixed Integer Programming
Job Shop Scheduling Using Mixed Integer ProgrammingJob Shop Scheduling Using Mixed Integer Programming
Job Shop Scheduling Using Mixed Integer ProgrammingIJMERJOURNAL
Ā 

What's hot (18)

11.bicriteria in n x 0003www.iiste.org call for paper flow shop scheduling un...
11.bicriteria in n x 0003www.iiste.org call for paper flow shop scheduling un...11.bicriteria in n x 0003www.iiste.org call for paper flow shop scheduling un...
11.bicriteria in n x 0003www.iiste.org call for paper flow shop scheduling un...
Ā 
Bicriteria in n x 3 flow shop scheduling under specified rental policy (2)
Bicriteria in n x 3 flow shop scheduling under specified rental policy (2)Bicriteria in n x 3 flow shop scheduling under specified rental policy (2)
Bicriteria in n x 3 flow shop scheduling under specified rental policy (2)
Ā 
AN ANT COLONY OPTIMIZATION ALGORITHM FOR JOB SHOP SCHEDULING PROBLEM
AN ANT COLONY OPTIMIZATION ALGORITHM FOR JOB SHOP SCHEDULING PROBLEMAN ANT COLONY OPTIMIZATION ALGORITHM FOR JOB SHOP SCHEDULING PROBLEM
AN ANT COLONY OPTIMIZATION ALGORITHM FOR JOB SHOP SCHEDULING PROBLEM
Ā 
14 sameer sharma final_paper
14 sameer sharma final_paper14 sameer sharma final_paper
14 sameer sharma final_paper
Ā 
K017446974
K017446974K017446974
K017446974
Ā 
IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...
IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...
IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...
Ā 
Heuristic approach for bicriteria in constrained three stage flow shop schedu...
Heuristic approach for bicriteria in constrained three stage flow shop schedu...Heuristic approach for bicriteria in constrained three stage flow shop schedu...
Heuristic approach for bicriteria in constrained three stage flow shop schedu...
Ā 
Heuristic approach for bicriteria in constrained three stage flow shop schedu...
Heuristic approach for bicriteria in constrained three stage flow shop schedu...Heuristic approach for bicriteria in constrained three stage flow shop schedu...
Heuristic approach for bicriteria in constrained three stage flow shop schedu...
Ā 
11.flow shop scheduling problem, processing time associated with probabilitie...
11.flow shop scheduling problem, processing time associated with probabilitie...11.flow shop scheduling problem, processing time associated with probabilitie...
11.flow shop scheduling problem, processing time associated with probabilitie...
Ā 
A M ULTI -O BJECTIVE B ASED E VOLUTIONARY A LGORITHM AND S OCIAL N ETWOR...
A M ULTI -O BJECTIVE  B ASED  E VOLUTIONARY  A LGORITHM AND  S OCIAL  N ETWOR...A M ULTI -O BJECTIVE  B ASED  E VOLUTIONARY  A LGORITHM AND  S OCIAL  N ETWOR...
A M ULTI -O BJECTIVE B ASED E VOLUTIONARY A LGORITHM AND S OCIAL N ETWOR...
Ā 
A tricky task scheduling technique to optimize time cost and reliability in m...
A tricky task scheduling technique to optimize time cost and reliability in m...A tricky task scheduling technique to optimize time cost and reliability in m...
A tricky task scheduling technique to optimize time cost and reliability in m...
Ā 
Modified heuristic time deviation Technique for job sequencing and Computatio...
Modified heuristic time deviation Technique for job sequencing and Computatio...Modified heuristic time deviation Technique for job sequencing and Computatio...
Modified heuristic time deviation Technique for job sequencing and Computatio...
Ā 
Job shop scheduling problem using genetic algorithm
Job shop scheduling problem using genetic algorithmJob shop scheduling problem using genetic algorithm
Job shop scheduling problem using genetic algorithm
Ā 
An efficient simulated annealing algorithm for a No-Wait Two Stage Flexible F...
An efficient simulated annealing algorithm for a No-Wait Two Stage Flexible F...An efficient simulated annealing algorithm for a No-Wait Two Stage Flexible F...
An efficient simulated annealing algorithm for a No-Wait Two Stage Flexible F...
Ā 
International Refereed Journal of Engineering and Science (IRJES)
International Refereed Journal of Engineering and Science (IRJES)International Refereed Journal of Engineering and Science (IRJES)
International Refereed Journal of Engineering and Science (IRJES)
Ā 
IRJET- Two-Class Priority Queueing System with Restricted Number of Priority ...
IRJET- Two-Class Priority Queueing System with Restricted Number of Priority ...IRJET- Two-Class Priority Queueing System with Restricted Number of Priority ...
IRJET- Two-Class Priority Queueing System with Restricted Number of Priority ...
Ā 
8.yongching lim 89-100
8.yongching lim 89-1008.yongching lim 89-100
8.yongching lim 89-100
Ā 
Job Shop Scheduling Using Mixed Integer Programming
Job Shop Scheduling Using Mixed Integer ProgrammingJob Shop Scheduling Using Mixed Integer Programming
Job Shop Scheduling Using Mixed Integer Programming
Ā 

Viewers also liked

Reynard Arlow Final Year Project
Reynard Arlow Final Year ProjectReynard Arlow Final Year Project
Reynard Arlow Final Year ProjectReynard Arlow
Ā 
Apache Hadoop India Summit 2011 talk "Scheduling in MapReduce using Machine L...
Apache Hadoop India Summit 2011 talk "Scheduling in MapReduce using Machine L...Apache Hadoop India Summit 2011 talk "Scheduling in MapReduce using Machine L...
Apache Hadoop India Summit 2011 talk "Scheduling in MapReduce using Machine L...Yahoo Developer Network
Ā 
Tardiness
TardinessTardiness
TardinessJessicaSon
Ā 
Tardiness among uitm puncak alam students (presentation)
Tardiness among uitm puncak alam students   (presentation)Tardiness among uitm puncak alam students   (presentation)
Tardiness among uitm puncak alam students (presentation)342016
Ā 
Research paper (pre ed 2)
Research paper (pre ed 2)Research paper (pre ed 2)
Research paper (pre ed 2)Ysa Garcera
Ā 
A STUDY ON THE FACTOR OF STUDENT ABSENTEEISM AT FACULTY OF BUSINESS, UNISEL S...
A STUDY ON THE FACTOR OF STUDENT ABSENTEEISM AT FACULTY OF BUSINESS, UNISEL S...A STUDY ON THE FACTOR OF STUDENT ABSENTEEISM AT FACULTY OF BUSINESS, UNISEL S...
A STUDY ON THE FACTOR OF STUDENT ABSENTEEISM AT FACULTY OF BUSINESS, UNISEL S...Nisha Ambalan
Ā 

Viewers also liked (6)

Reynard Arlow Final Year Project
Reynard Arlow Final Year ProjectReynard Arlow Final Year Project
Reynard Arlow Final Year Project
Ā 
Apache Hadoop India Summit 2011 talk "Scheduling in MapReduce using Machine L...
Apache Hadoop India Summit 2011 talk "Scheduling in MapReduce using Machine L...Apache Hadoop India Summit 2011 talk "Scheduling in MapReduce using Machine L...
Apache Hadoop India Summit 2011 talk "Scheduling in MapReduce using Machine L...
Ā 
Tardiness
TardinessTardiness
Tardiness
Ā 
Tardiness among uitm puncak alam students (presentation)
Tardiness among uitm puncak alam students   (presentation)Tardiness among uitm puncak alam students   (presentation)
Tardiness among uitm puncak alam students (presentation)
Ā 
Research paper (pre ed 2)
Research paper (pre ed 2)Research paper (pre ed 2)
Research paper (pre ed 2)
Ā 
A STUDY ON THE FACTOR OF STUDENT ABSENTEEISM AT FACULTY OF BUSINESS, UNISEL S...
A STUDY ON THE FACTOR OF STUDENT ABSENTEEISM AT FACULTY OF BUSINESS, UNISEL S...A STUDY ON THE FACTOR OF STUDENT ABSENTEEISM AT FACULTY OF BUSINESS, UNISEL S...
A STUDY ON THE FACTOR OF STUDENT ABSENTEEISM AT FACULTY OF BUSINESS, UNISEL S...
Ā 

Similar to Nitt paper A fuzzy multi-objective based un-related parallel Machine Scheduling

Hybridizing guided genetic algorithm and single-based metaheuristics to solve...
Hybridizing guided genetic algorithm and single-based metaheuristics to solve...Hybridizing guided genetic algorithm and single-based metaheuristics to solve...
Hybridizing guided genetic algorithm and single-based metaheuristics to solve...IAESIJAI
Ā 
SWARM INTELLIGENCE SCHEDULING OF SOFT REAL-TIME TASKS IN HETEROGENEOUS MULTIP...
SWARM INTELLIGENCE SCHEDULING OF SOFT REAL-TIME TASKS IN HETEROGENEOUS MULTIP...SWARM INTELLIGENCE SCHEDULING OF SOFT REAL-TIME TASKS IN HETEROGENEOUS MULTIP...
SWARM INTELLIGENCE SCHEDULING OF SOFT REAL-TIME TASKS IN HETEROGENEOUS MULTIP...ecij
Ā 
Multiprocessor scheduling of dependent tasks to minimize makespan and reliabi...
Multiprocessor scheduling of dependent tasks to minimize makespan and reliabi...Multiprocessor scheduling of dependent tasks to minimize makespan and reliabi...
Multiprocessor scheduling of dependent tasks to minimize makespan and reliabi...ijfcstjournal
Ā 
Design and Implementation of a Multi-Agent System for the Job Shop Scheduling...
Design and Implementation of a Multi-Agent System for the Job Shop Scheduling...Design and Implementation of a Multi-Agent System for the Job Shop Scheduling...
Design and Implementation of a Multi-Agent System for the Job Shop Scheduling...CSCJournals
Ā 
AN EFFICIENT HEURISTIC ALGORITHM FOR FLEXIBLE JOB SHOP SCHEDULING WITH MAINTE...
AN EFFICIENT HEURISTIC ALGORITHM FOR FLEXIBLE JOB SHOP SCHEDULING WITH MAINTE...AN EFFICIENT HEURISTIC ALGORITHM FOR FLEXIBLE JOB SHOP SCHEDULING WITH MAINTE...
AN EFFICIENT HEURISTIC ALGORITHM FOR FLEXIBLE JOB SHOP SCHEDULING WITH MAINTE...mathsjournal
Ā 
An Efficient Heuristic Algorithm for Flexible Job Shop Scheduling with Mainte...
An Efficient Heuristic Algorithm for Flexible Job Shop Scheduling with Mainte...An Efficient Heuristic Algorithm for Flexible Job Shop Scheduling with Mainte...
An Efficient Heuristic Algorithm for Flexible Job Shop Scheduling with Mainte...mathsjournal
Ā 
Planning and Scheduling of a Corrugated Cardboard Manufacturing Process in IoT
Planning and Scheduling of a Corrugated Cardboard Manufacturing Process in IoTPlanning and Scheduling of a Corrugated Cardboard Manufacturing Process in IoT
Planning and Scheduling of a Corrugated Cardboard Manufacturing Process in IoTijtsrd
Ā 
PREDICTION OF AVERAGE TOTAL PROJECT DURATION USING ARTIFICIAL NEURAL NETWORKS...
PREDICTION OF AVERAGE TOTAL PROJECT DURATION USING ARTIFICIAL NEURAL NETWORKS...PREDICTION OF AVERAGE TOTAL PROJECT DURATION USING ARTIFICIAL NEURAL NETWORKS...
PREDICTION OF AVERAGE TOTAL PROJECT DURATION USING ARTIFICIAL NEURAL NETWORKS...IAEME Publication
Ā 
Artificial Neural Network Based Graphical User Interface for Estimation of Fa...
Artificial Neural Network Based Graphical User Interface for Estimation of Fa...Artificial Neural Network Based Graphical User Interface for Estimation of Fa...
Artificial Neural Network Based Graphical User Interface for Estimation of Fa...ijsrd.com
Ā 
Artificial Neural Network Based Graphical User Interface for Estimation of Fa...
Artificial Neural Network Based Graphical User Interface for Estimation of Fa...Artificial Neural Network Based Graphical User Interface for Estimation of Fa...
Artificial Neural Network Based Graphical User Interface for Estimation of Fa...ijsrd.com
Ā 
IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...
IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...
IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...IJCSEA Journal
Ā 
IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...
IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...
IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...IJCSEA Journal
Ā 
Effective Hybrid Algorithms for No-Wait Flowshop Scheduling Problem
Effective Hybrid Algorithms for No-Wait Flowshop Scheduling ProblemEffective Hybrid Algorithms for No-Wait Flowshop Scheduling Problem
Effective Hybrid Algorithms for No-Wait Flowshop Scheduling ProblemIRJET Journal
Ā 
MULTIPROCESSOR SCHEDULING AND PERFORMANCE EVALUATION USING ELITIST NON DOMINA...
MULTIPROCESSOR SCHEDULING AND PERFORMANCE EVALUATION USING ELITIST NON DOMINA...MULTIPROCESSOR SCHEDULING AND PERFORMANCE EVALUATION USING ELITIST NON DOMINA...
MULTIPROCESSOR SCHEDULING AND PERFORMANCE EVALUATION USING ELITIST NON DOMINA...ijcsa
Ā 
A Discrete Firefly Algorithm for the Multi-Objective Hybrid Flowshop Scheduli...
A Discrete Firefly Algorithm for the Multi-Objective Hybrid Flowshop Scheduli...A Discrete Firefly Algorithm for the Multi-Objective Hybrid Flowshop Scheduli...
A Discrete Firefly Algorithm for the Multi-Objective Hybrid Flowshop Scheduli...Xin-She Yang
Ā 
A case study on Machine scheduling and sequencing using Meta heuristics
A case study on Machine scheduling and sequencing using Meta heuristicsA case study on Machine scheduling and sequencing using Meta heuristics
A case study on Machine scheduling and sequencing using Meta heuristicsIJERA Editor
Ā 
A case study on Machine scheduling and sequencing using Meta heuristics
A case study on Machine scheduling and sequencing using Meta heuristicsA case study on Machine scheduling and sequencing using Meta heuristics
A case study on Machine scheduling and sequencing using Meta heuristicsIJERA Editor
Ā 

Similar to Nitt paper A fuzzy multi-objective based un-related parallel Machine Scheduling (20)

Hybridizing guided genetic algorithm and single-based metaheuristics to solve...
Hybridizing guided genetic algorithm and single-based metaheuristics to solve...Hybridizing guided genetic algorithm and single-based metaheuristics to solve...
Hybridizing guided genetic algorithm and single-based metaheuristics to solve...
Ā 
F012113746
F012113746F012113746
F012113746
Ā 
SWARM INTELLIGENCE SCHEDULING OF SOFT REAL-TIME TASKS IN HETEROGENEOUS MULTIP...
SWARM INTELLIGENCE SCHEDULING OF SOFT REAL-TIME TASKS IN HETEROGENEOUS MULTIP...SWARM INTELLIGENCE SCHEDULING OF SOFT REAL-TIME TASKS IN HETEROGENEOUS MULTIP...
SWARM INTELLIGENCE SCHEDULING OF SOFT REAL-TIME TASKS IN HETEROGENEOUS MULTIP...
Ā 
Multiprocessor scheduling of dependent tasks to minimize makespan and reliabi...
Multiprocessor scheduling of dependent tasks to minimize makespan and reliabi...Multiprocessor scheduling of dependent tasks to minimize makespan and reliabi...
Multiprocessor scheduling of dependent tasks to minimize makespan and reliabi...
Ā 
30420140503003
3042014050300330420140503003
30420140503003
Ā 
Design and Implementation of a Multi-Agent System for the Job Shop Scheduling...
Design and Implementation of a Multi-Agent System for the Job Shop Scheduling...Design and Implementation of a Multi-Agent System for the Job Shop Scheduling...
Design and Implementation of a Multi-Agent System for the Job Shop Scheduling...
Ā 
AN EFFICIENT HEURISTIC ALGORITHM FOR FLEXIBLE JOB SHOP SCHEDULING WITH MAINTE...
AN EFFICIENT HEURISTIC ALGORITHM FOR FLEXIBLE JOB SHOP SCHEDULING WITH MAINTE...AN EFFICIENT HEURISTIC ALGORITHM FOR FLEXIBLE JOB SHOP SCHEDULING WITH MAINTE...
AN EFFICIENT HEURISTIC ALGORITHM FOR FLEXIBLE JOB SHOP SCHEDULING WITH MAINTE...
Ā 
An Efficient Heuristic Algorithm for Flexible Job Shop Scheduling with Mainte...
An Efficient Heuristic Algorithm for Flexible Job Shop Scheduling with Mainte...An Efficient Heuristic Algorithm for Flexible Job Shop Scheduling with Mainte...
An Efficient Heuristic Algorithm for Flexible Job Shop Scheduling with Mainte...
Ā 
Planning and Scheduling of a Corrugated Cardboard Manufacturing Process in IoT
Planning and Scheduling of a Corrugated Cardboard Manufacturing Process in IoTPlanning and Scheduling of a Corrugated Cardboard Manufacturing Process in IoT
Planning and Scheduling of a Corrugated Cardboard Manufacturing Process in IoT
Ā 
PREDICTION OF AVERAGE TOTAL PROJECT DURATION USING ARTIFICIAL NEURAL NETWORKS...
PREDICTION OF AVERAGE TOTAL PROJECT DURATION USING ARTIFICIAL NEURAL NETWORKS...PREDICTION OF AVERAGE TOTAL PROJECT DURATION USING ARTIFICIAL NEURAL NETWORKS...
PREDICTION OF AVERAGE TOTAL PROJECT DURATION USING ARTIFICIAL NEURAL NETWORKS...
Ā 
220 229
220 229220 229
220 229
Ā 
Artificial Neural Network Based Graphical User Interface for Estimation of Fa...
Artificial Neural Network Based Graphical User Interface for Estimation of Fa...Artificial Neural Network Based Graphical User Interface for Estimation of Fa...
Artificial Neural Network Based Graphical User Interface for Estimation of Fa...
Ā 
Artificial Neural Network Based Graphical User Interface for Estimation of Fa...
Artificial Neural Network Based Graphical User Interface for Estimation of Fa...Artificial Neural Network Based Graphical User Interface for Estimation of Fa...
Artificial Neural Network Based Graphical User Interface for Estimation of Fa...
Ā 
IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...
IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...
IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...
Ā 
IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...
IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...
IMPROVED WORKLOAD BALANCING OF THE SCHEDULING JOBS WITH THE RELEASE DATES IN ...
Ā 
Effective Hybrid Algorithms for No-Wait Flowshop Scheduling Problem
Effective Hybrid Algorithms for No-Wait Flowshop Scheduling ProblemEffective Hybrid Algorithms for No-Wait Flowshop Scheduling Problem
Effective Hybrid Algorithms for No-Wait Flowshop Scheduling Problem
Ā 
MULTIPROCESSOR SCHEDULING AND PERFORMANCE EVALUATION USING ELITIST NON DOMINA...
MULTIPROCESSOR SCHEDULING AND PERFORMANCE EVALUATION USING ELITIST NON DOMINA...MULTIPROCESSOR SCHEDULING AND PERFORMANCE EVALUATION USING ELITIST NON DOMINA...
MULTIPROCESSOR SCHEDULING AND PERFORMANCE EVALUATION USING ELITIST NON DOMINA...
Ā 
A Discrete Firefly Algorithm for the Multi-Objective Hybrid Flowshop Scheduli...
A Discrete Firefly Algorithm for the Multi-Objective Hybrid Flowshop Scheduli...A Discrete Firefly Algorithm for the Multi-Objective Hybrid Flowshop Scheduli...
A Discrete Firefly Algorithm for the Multi-Objective Hybrid Flowshop Scheduli...
Ā 
A case study on Machine scheduling and sequencing using Meta heuristics
A case study on Machine scheduling and sequencing using Meta heuristicsA case study on Machine scheduling and sequencing using Meta heuristics
A case study on Machine scheduling and sequencing using Meta heuristics
Ā 
A case study on Machine scheduling and sequencing using Meta heuristics
A case study on Machine scheduling and sequencing using Meta heuristicsA case study on Machine scheduling and sequencing using Meta heuristics
A case study on Machine scheduling and sequencing using Meta heuristics
Ā 

Recently uploaded

Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
Ā 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
Ā 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
Ā 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
Ā 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoĆ£o Esperancinha
Ā 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
Ā 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
Ā 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
Ā 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
Ā 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
Ā 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
Ā 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
Ā 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
Ā 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
Ā 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
Ā 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
Ā 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
Ā 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
Ā 

Recently uploaded (20)

Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
Ā 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
Ā 
young call girls in Rajiv ChowkšŸ” 9953056974 šŸ” Delhi escort Service
young call girls in Rajiv ChowkšŸ” 9953056974 šŸ” Delhi escort Serviceyoung call girls in Rajiv ChowkšŸ” 9953056974 šŸ” Delhi escort Service
young call girls in Rajiv ChowkšŸ” 9953056974 šŸ” Delhi escort Service
Ā 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Ā 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
Ā 
ā˜… CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
ā˜… CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCRā˜… CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
ā˜… CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
Ā 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Ā 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
Ā 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
Ā 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
Ā 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
Ā 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
Ā 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
Ā 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
Ā 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
Ā 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
Ā 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
Ā 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
Ā 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
Ā 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
Ā 

Nitt paper A fuzzy multi-objective based un-related parallel Machine Scheduling

  • 1. Abstract--- In this paper, we have addressed a Multi Objective Problem (MOP) which covers-minimize the makespan, tardiness, load variation, flow time and secondary resources constraints for unrelated parallel machine scheduling problem with consideration of inherent uncertainty in processing times and due dates. To resolve the above computationally challenge problem in a reasonable time and to find a good approximation of Pareto frontier, we have proposed a Multi-Objective Evolutionary Algorithm (MOEA) based Fuzzy-Non-dominated Sorting Genetic Algorithm (FNSGA-II). Over randomly generated test problems, the performance of the proposed algorithm is validated and the results are analyzed for the benefit of the manufacturer. Finally, statistical analysis has been conducted and found that the proposed algorithm performs reasonably well in terms of quality, computational time, diversity and spacing metrics. Keywordsā€“ Load Variation, MOEA, Makespan, Tardiness, Unrelated Parallel Machine I. INTRODUCTION HE parallel machine scheduling problem (PMSP) is a very common production environment that can be found in several manufacturing situations, in which the allocation of a set of jobs are assigned to a number of parallel machines in order to meet customerā€™s requirement. In general, from the literature it is found that PMSP is categorized as identical, uniform and unrelated parallel machine scheduling problem[1]. Among the above mentioned classifications, it is found that for unrelated PMSP (UPMSP) the processing time of each job depends on machines with different processing capabilities it is assigned to, where workstations are supposed to be non-identical. However, handling of UPMSPā€™s with real life cases is a challenge for researchers and Practitioners due V.K.Manupati, Assistant professor, Department of Mechanical Engineering, KL University, Andhra Pradesh, India. E-mail: manupativijay@gmail.com R. Sridharan, Professor, Department of mechanical Engineering, NIT Calicut, Kerala, India. E-mail: sreedhar@nitc.ac.in N. Arudhra, Student, Department of Mechanical Engineering, KL University, Andhra Pradesh, India. E-mail: arudhra19@gmail.com P.Bharadwaj, Student, Department of Mechanical Engineering, KL University, Andhra Pradesh, India. E-mail:bharadwaj.popuri9@gmail.com D.Trinath, Student, Department of Mechanical Engineering, KL University, Andhra Pradesh, India. E-mail:trinathh@outlook.com M.V.B.T.Santhi, Assistant professor, Department of Computer Science and Engineering, KL University, Andhra Pradesh, India. E-mail: santhi_ist@kluniversity.in to the fact that they are mostly NP-hard in nature and their special characteristics/requirements in practice [2]. The unrelated parallel machine system has been solved with many methods and techniques and it has been widely addressed in the literature from past few years. Leeet al. [6] addressed the UPMSP to minimize the objective function i.e., with dedicated machines and common deadlines kim et al.[4] and arnaout et al.[5] presented a simulated Annealing and ant colony algorithm optimization approach for the UPMSP with sequence dependent setup times. In real world scheduling problems many factors are often uncertain. This research deals with scheduling of number of jobs on an unrelated parallel machine system with secondary resource constraints. Where, each job can only be processed if its required machine and other secondary resources are available The remainder of this paper is organized as follows. In section 2, we give a detailed description of the problem with the basic assumptions and developed a mathematical model along with the constraints. Section 3 explains the mapping of NSGA-II, MPSO algorithms for solving the MOP. The experimentation with an illustrative example having different complex scenarios is illustrated in Section 4. In Section 5, the results and their discussions are detailed. The paper concludes with Section 6 suggesting the directions of the future work. II. PROBLEM DESCRIPTION In this paper, we propose a multi-objective UPMSP with non-zero ready times, job-sequence-and machine-dependent setup times, and the auxiliary resource constraints in a fuzzy based environment for improving the performance measures such as makespan, flow time, tardiness and machine load variation. Here we consider a set of jobs with j = {1,2.., n} of n that have to be processed on exactly one machine out of a set M= {1,2.., m} of m parallel machines. The jobs are processed on machines that are available continuously to process at most one job J at a time. When jobs are processing on the machines we have consider that pre-emption is not allowed and jobs are processing on machines k with their processing times, tardiness, makespan and load variation. In this problem, we consider a sequence dependent and machine dependent which deals with processing times, and setup times, when a machine switches its production from job i to job j on the same machine. We do not consider setup times before processing the first job on a machine. In this problem the occurrence of machine idle time is allowed. Idle time on a machine may be A fuzzy Multi-Objective Based Un-Related Parallel Machines Scheduling Problem with Sequence and Machine Dependent Setup Times V.K.Manupati, R. Sridharan, N. Arudhra, P. Bharadwaj, D.Trinath and M.V.B.T. Santhi T International Conference on Advances in Design and Manufacturing (ICAD&M'14) 1275 ISBN 978-93-84743-12-3 Ā© 2014 Bonfring
  • 2. required to complete a job on its due date, avoiding earliness. However, to meet the requirements from real-world production, we have considered more than two objectives corresponding to constraints for Multi objective problem. The above mentioned problem makes several assumptions that are worth highlighting. 2.1 Assumptions 1. Each job requires an operation that can be done on all machines, 2. Jobā€™s setup times are sequence and machine dependent, 3. Jobs may have different arrival (ready) times, 4. Assignment of a job to a machine is permitted if the required secondary resource(s) (e.g., tool, die) is (are) available, 5. Processing times of jobs are machine dependent, 6. Preemption and machine breakdown are not allowed, 7. Processing times and due dates of jobs due to possible fluctuations in real world are subject toepistemic uncertainty (i.e. lack of knowledge in estimating these parameters precisely). The indices, parameters and variables used to formulate the problem mathematically are described below. 1 0 1 0 1 sin Decision varibles : if job i precedes job j on machine k otherwise if job i is assigned to machine k otherwise if proces g of job i is finished before X ijk Yjk Zij ļ£±ļ£“ = ļ£² ļ£“ļ£³ ļ£± = ļ£² ļ£³ = sin 0 proces g of job j starts otherwise ļ£± ļ£“ ļ£² ļ£“ ļ£³ 2.2 Mathematical Model By allocating the above mentioned assumptions and notations, the problem is being formulated as the following fuzzy mixedā€“integer nonā€“linear programming (FMINLP) model. International Conference on Advances in Design and Manufacturing (ICAD&M'14) 1276 ISBN 978-93-84743-12-3 Ā© 2014 Bonfring
  • 3. Objectives : N = w c (1)i i i=1 N = w (c -c )(D) (2)i i+1 i MinZ1 Min Z2 M i=1 = w (cin -s )i i i Z3 i āˆ‘ āˆ‘ N (3) =1 M k= (D)(c -c ) (4)max max k=1 Subjected to constraints : 1 ; 1 1 MinZ4 Ā Ā  N m Xijk j i k i j āˆ‘ āˆ‘ = āˆ€āˆ‘ āˆ‘ = = ā‰  ; Ā  (5)Ā  (6) 1, , Ā Ā  , 1 ; 1 1 N X Yijk jk j k i i j N X Yijk ik j i N j = āˆ€āˆ‘ = ā‰  ā‰¤āˆ‘ = = ā€¦ ā‰  (7) , , Ā Ā  (8) ,Ā  ) (9)Ā Ā Ā Ā Ā  , (1 ) Max{c } ;, (1 ) (c , ) ; ( 1 1; Ā  c A Xijk s s pj N i ijk j jk M c A z Max s p Yj N ij i j jk jk k i j k i z zij ji jƎS i jr i jƎ + āˆ’ ā‰„ + + + āˆ’ ā‰„ + āˆ‘ = + = ā‰  ( ) (10),Ā  ,Ā  Ā  (11),Ā  ; Ā Ā  ; 1 S i jr i jƎS i jr T C di M X zijk ij i k i i ā‰  ā‰ ā‰¤āˆ‘ = ā‰„ āˆ€ā”€ { } ( ) (12) 0; 0; , 0,1 ;Ā  , , .Ā Ā Ā Ā Ā  13 Ā  , , C T I X Y Z Ǝ i j k i i ijk ik ij ā‰„ ā‰„ The above mentioned objectives, i.e. minimization of total weighted makespan(Z1), total weighted flow time(Z2)total weighted tardiness(Z3), machine load variation(Z4) are given by Eqs. (1) ā€“ (4), respectively. Eq (5)assures that each job is only assigned to one position on a machine. Eq(6) suggests that if job jis allotted to machine k, then it is adopted by another job indicating dummy job 0. Constraint (7)specify that at most one job can immediately adopt the previously allotted job i on machine k. Constraint (8)computes the completion time of job when it is processed instantly after job i on machine . Constraint (9 and 10)ensures that if job I and j needs same tool, one must be finished earlier before starting the other. Constraint (11)gives the relation between Xijk and Zij.Eq(12)computes tardiness of job i.Eventually Eq(13)points the non-negativity and integrality constraints. III. MULTI-OBJECTIVE BASED EVOLUTIONARY ALGORITHM Most of the UPMSPs are NP-hard in nature and due to its characteristic it is necessary to solve more than two objectives simultaneously to find out the optimal solutions that are very close to reality. In general, it is very difficult to solve the multiple objectives simultaneously thus we adopted multi- objective based evolutionary algorithms for solving the above mentioned complex problem.[7] In this paper, we apply a NSGA-II which includes parito ranking and crowding system mechanism for selection of the individuals 3.1.Nondominated sorting Genetic Algorithm Goldberg was the first who suggested the concept of non- dominated sorting genetic algorithm (NSGA) and Srinivas and Deb were the first to implement it. Where NSGA differs from well known simple genetic algorithm is only in the way the selection operator works. Although NSGA has been used to solve a variety of MOPs, its main drawbacks include: (i)high computational complexity of non-dominated sorting, (ii) lack of elitism, and (iii) the need for specifying the tunable parameter. With the advent of NSGA-II, the above mentioned drawbacks have been resolved. 3.1.1. Initial population generation Fig.1: Initial Population Generation. We randomly generate the initial population for a given population size. According to the characteristics of the proposed problem, encoding schema and its representation is designed. An example of the encoding scheme for the problem is illustrated in Fig 1. Here, we have considered the number of jobs(1 to 6) as chromosome which is having length seven, where jobs should process on machines (1 to 4) in such a way that the secondary resources ( 1 to 3 ) must available. In the second set of the chromosome representation the machines and their secondary resources and the encoding scheme of this layer is shown in Fig 2b. In this layer, zeroes indicate, no job assign on the machine. One more advantage of indicating zeroes is for maintaining the chromosome length as uniform. 3.1.2. Evolutionary operators Cross over Crossover chooses genes from parent chromosomes and produce a new offspring. Crossover is done by swapping portions between two parent chromosomes. It is based on basic parameter called crossover probability. Specific crossover built for a particular problem can improve performance of the genetic algorithm. Mutation International Conference on Advances in Design and Manufacturing (ICAD&M'14) 1277 ISBN 978-93-84743-12-3 Ā© 2014 Bonfring
  • 4. Mutation randomly used for alternating the values of particular genes to prevent diminishing all solutions in population into a local optimum of solved problem. Non dominated sorting Non dominating sorting is done by choosing the best pareto front which is spread throughout the space by tournament selection based on Pareto domination. Fig.2: Schematic Procedure for Processing NSGA-II. OP ā€“Offspring population PP - Parent population Fig 2, describes the schematic algorithm throughout the processing of NSGA-II (Deb et al. 2000) crowding distance Crowding distance can be calculated for all chromosomes of same pareto front, then individual having large crowding distance is selected to obtain uniform distribution. Stopping rule If the maximum generation is reached then stop. IV. EXPERIMENTATION Here, Card (g) describes the cardinality of test sample, and Ī±, Ī² represents the control of job arrival and control of tightness respectively. Table 1: Test Sample (TS) Form Machine Shop Table 1 represents a raw data of random test sample (TS) taken from a cable and manufacturing company that is incorporated as unrelated parallel machine which have sequence dependent and machine dependent setup times . V. RESULTS AND DISCUSSION Figure 3: Pareto Optimal Front for Sets Considering Makespan vs. Flow Time. Figure 4: Pareto Optimal Front for Sets Considering Makespan vs. Tardiness. Figure 5: Pareto Optimal Front for Sets Considering Makespan vs. Machine Load Variation. Pareto optimal front is obtained using the evolutionary operators based on concerned performance measures(Fig:3, Fig:4, Fig: 5) such as minimization of makespan, flowtime, tardiness, and machine load variation, for randomly selected test samples. The make span is the total completion time of jobs, flow time is the time taken by the required job to complete, tardiness is lateness or slow processing i.e., more than due date, machine load variation is the time to setup or calibration of machine during processing of jobs on the machines. Results show better solutions and achieved Pareto optimal solutions VI. CONCLUSION AND FUTURE WORK This paper proposes a fuzzy multi objective UPMSP with non zero ready times, sequence and machine dependent setup times. Moreover, we have considered secondary resource 0 200 400 45.542.940.931.123.120.916.614.2 7.3 flowtime Makespan Makespan vs Flowtime Set 1 Set 2 0.00 100.00 200.00 45.5 42.9 40.9 32.3 31.9 23.8 20.9 16.6 14.2 7.3 Tardiness Makespan Makespan vs Tardiness Set 3 0.00 200.00 25.8 33.9 18.7 45.9 9.3 24.9 46.8 48.3 13.4 35.6 MachineLoad variation Makespan Makespan vs Machine load variation Set 1 Set 2 Set 3 International Conference on Advances in Design and Manufacturing (ICAD&M'14) 1278 ISBN 978-93-84743-12-3 Ā© 2014 Bonfring
  • 5. constraints to simultaneously solving different performance measures to obtain pareto optimal solutions. Here, we have considered different performance measures as minimization of makespan, total weighted tardiness, total weighted flow time, machine load variation. To solve the above mentioned complex NP hard problem it is necessary to adopt a multi- objective based evolutionary algorithm i.e., NSGA-II. With different problem sets by varying its cardinality starting time and due date the performance of the algorithm is examined. Experimental results show that the proposed approach is performing better and obtained optimal solutions in the future work, one can compare with different multi-objective evolutionary algorithms and also on large data sets that can bring the experimentation close to reality. REFERENCES [1] T. Cheng, C. Sin, A state-of-the-art review of parallel-machine schedulingresearch, European Journal of Operational Research 47 (1990) 271ā€“292. [2] S.A. TORABI, N.Sahebjamnia, S.A.Mansouri,M. Aramon bajestani, ā€œA particle swarm optimization for fuzzy multi-objective unrelated parallel machines scheduling problemā€,Applied Soft Computing, 13(2013)4750- 4762. [3] J.-Y. Bang, Y.-D. Kim, Scheduling algorithms for a semiconductor probing facil-ity, Computers and Operations Research 38 (2011) 666ā€“ 673. [4] J.-P. Arnaout, G. Rabadi, R. Musa, A two-stage ant colony optimizationalgorithm to minimize the makespan on unrelated parallel machines withsequence-dependent setup times, Journal of Intelligent Manufacturing 21(2010) 693ā€“701. [5] F.A. Cappadonna,A. Costa,S. Fichera, ā€œMake span minimization of unrelated parallel machines with limited human resourcesā€,Procedia CIRP 12(2013)450-455. [6] Lee, Cheng-Hsiung, Ching-Jong Liao, and Chien-Wen Chao. "Unrelated parallel machine scheduling with dedicated machines and common deadline." Computers & Industrial Engineering (2014). [7] Deb, Kalyanmoy. "Multi-objective optimization." Search methodologies. Springer US, 2014. 403-449. Dr. Vijay Kumar Manupati received the B-Tech degree in Department of mechanical engineering from Siddhardha Engineering College, and M-Tech in Department of Mechanical engineering with Industrial Engineering and Management as a specialization from National Institute of Technology Calicut. He received his PhD in Department of Industrial and Systems Engineering from Indian Institute of Technology Kharagpur. His current research interests belong include Intelligent manufacturing systems, agent/multi-agent/mobile-agent systems for distributed control, simulation, integration of process planning and scheduling in manufacturing. He has published papers inInternational Journal of Production Research, Computers and Industrial Engineering, and International Journal of Advanced Manufacturing Technology. Dr.R.Sridhran completed his B. E. Honours in Mechanical engineering from madras University, M- Tech in Department of Industrial Engineering and Operation Research specialization from IIT Kharagpur, and Ph. D. in department of Industrial Engineering from IIT Bombay. He had published many publications and technical reports in reputed journals. His areas of research are Operation Management, Supply Chain Management, Decision Modelling, Simulation Modelling and Analysis Arudhra Nerella pursuing his Bachelor degree in Mechanical Engineering from KLUniversity (Vijayawada, Andhra Pradesh, India). He worked on several projects like ā€œControlling the Defects in Centrifugal Castingā€, ā€œDeveloped a Flexible Manufacturing System using Cellular Manufacturing Techniquesā€. He is a Member of American Society of Mechanical Engineers. His research interest includes manufacturing, production, and Supply chain management TRINATH DESIBOYINA, was born on June 12th 1992 and perusing B .Tech in mechanical engineering at KLUniversity(2011-2015).He has done internship at GENTING LANCO Power(India) Private Limited, Kondapalli,and done an automobile oriented project on ā€˜Aero carā€™s, an environmental oriented project on ā€˜Solar cellā€™, and a technical project on ā€˜Conditional monitoring on rotating machines using vibrational analysisā€™ these were done as a part of curriculum BHARADWAJ POPURI: was born on July 30th 1993 and pursuing B.Tech in mechanical engineering at KLUniversity (2011-2015),he has done internship on Quality control charts for variables and attributes at ā€œModel Dairy Private Limitedā€, and done his projectā€™s on ā€˜ wire electric discharge machiningā€™ and ā€˜lean manufacturing in processing industryā€™ as a part of curriculum. M.V.B.T.Santhi received the M-Tech degree in Computer Science and Engineering from AN University, in 2010 & B-Tech degree in Computer Science and Engineering from Jawaharlal Nehru Technology University, Hyderabad, in 2003 .She is currently working as an Assistant Professor in Department of Computer Science & Engineering, Koneru Lakshmaiah University, Vaddeswaram, Guntur Dist.A.P International Conference on Advances in Design and Manufacturing (ICAD&M'14) 1279 ISBN 978-93-84743-12-3 Ā© 2014 Bonfring