It is situated in Kafen, Muzaffarpur
and is 50km away from Patna,
capital of Bihar
It was inaugurated on 26 august
2006, and has a total
transformation capacity of 1115
MVA
It has been constructed by PGCIL,
as a part of east-north
interconnector
Breaker and a half scheme has
been used in 400kv switchyard
while 220kv switchyard has double
main and Transfer Bus scheme
3. Associated transmission Lines
400kv Purnea-Muzaffarpur Line (Double circuit, 239kms)
400kv Gorakhpur-Muzaffarpur Line (Double circuit,
261kms)
400kv Biharsarif-Muzaffarpur Line (Double circuit, 131kms)
400kv Darbhanga-Muzaffarpur Line (Double circuit, 64kms)
220kv kanti MTPS-Muzaffarpur Line (Double circuit,
24kms)
220kv Hazipur-Muzaffarpur Line (Double circuit, 55kms)
220kv Dhalkebar-Muzaffarpur Line (Double circuit,
128kms)
4. Equipments used in Substation
Busbar
Lightning Arrestors
Capacitive Voltage Transformer
Circuit Breaker
Isolators
Current Transformers
Wave Trap
Interconnected Transformers
Shunt Reactor
5. Busbars
It is a thick stripe of
copper or aluminium that
conducts electricity
within a switch board or
substation
In Muzaffarpur substation
flexible ACSR bus is used
with Quad conductors
Rated voltage= 400kv
Rated current=3150A
6. Lightning Arrestor
It is used to ground the high
voltages surges falling on line
due to lightning
Core of LA is made of ZnO2,
which acts as Non linear
resistance
ZnO2 offers high resistance
during normal conditions and
Low resistance during high
surge voltages
A ring type structure is
provided on top to reduce
corona effect
7. Capacitive voltage Transformer
It is used to step down
extra high voltages to low
values for metering and
protection purposes
It has 3 secondary cores in
which two are used for
protection and one is used
for metering
It is always connected in
parallel
8. Circuit Breakers
It is an automatically
operated electrical switch
designed to protect an
electric circuit from
damage caused by short
circuit or overload
SF6 circuit breakers are
widely used in substations
these days because of its
excellent arc
extinguishing ability
9. Isolators
It is a switch used to
completely de-energize an
electrical circuit
It operates under no load
conditions
It provides isolation of
apparatus such as circuit
breakers, transformers
and transmission lines
during maintenance
10. Current Transformers
It is used for protection
and metering
It has primary coil of one
or more turns of thick
wire connected in series
with the line whose
current is to be measured
Secondary consists of
large number of turns of
fine wires and is
connected across
ammeter terminals
11. Wave Trap
A wave trap is used on those
transmission lines which are
equipped with PLCC (Power
Line Carrier Communication).
As the communication signal
frequency is much different
from line frequency, it is quite
necessary to separate the
power signal and
communication signal.
This task is performed by a
wave trap which simply consists
of L-C series and parallel
filters.
12. Interconnected transformers
It is the costliest equipment of
substations
It is used to step up or step down
voltages in substations without
change in frequency
In Muzaffarpur substation two
transformers of 315MVA and one
transformer of 500MVA is used
Secondary winding provides 220kV
voltages
There is tertiary winding also
which provides 33kv and can be
used as auxiliary power purpose
13. Shunt Reactor
It is a thyristor controlled
high impedance
transformer
It is used to absorb excess
of reactive power in
transmission line
It compensates the
capacitive VAR generated
in line
14. Control Room
The control room has various control panels which shows
the information like incoming power, outgoing power,
frequency, time common to all substations, status of
various lines (healthy, faulted, under outage or
maintenance), status of various protective instruments
like isolators, circuit breakers; temperatures of various
instruments, working tap of transformers etc.
16. Relay Room
It has Relay Panels for protection purposes
The protection system is so fast that it can
detect a fault within 30 ms and hence the
circuit breaker can be operated within as
less as 80 ms.
All relays used here are numerical and are
either from Siemens OR ABB .
18. Conclusion
During these four weeks of work there I
developed my team work, analytical thinking
and various important information about
electric power system. The main objective of
this whole training program is to provide an
opportunity to identify, observe and practice
how engineering is applicable in the real
industry.