A Summer
Training
Presentation on
400/220kv
substation
School of Electrical & Electronics Engineering
Lovely Professional University, Punjab
By:-
Anurag Savarn
Reg No:-11504716
Introduction of Substation
 It is situated in Kafen, Muzaffarpur
and is 50km away from Patna,
capital of Bihar
 It was inaugurated on 26 august
2006, and has a total
transformation capacity of 1115
MVA
 It has been constructed by PGCIL,
as a part of east-north
interconnector
 Breaker and a half scheme has
been used in 400kv switchyard
while 220kv switchyard has double
main and Transfer Bus scheme
Associated transmission Lines
 400kv Purnea-Muzaffarpur Line (Double circuit, 239kms)
 400kv Gorakhpur-Muzaffarpur Line (Double circuit,
261kms)
 400kv Biharsarif-Muzaffarpur Line (Double circuit, 131kms)
 400kv Darbhanga-Muzaffarpur Line (Double circuit, 64kms)
 220kv kanti MTPS-Muzaffarpur Line (Double circuit,
24kms)
 220kv Hazipur-Muzaffarpur Line (Double circuit, 55kms)
 220kv Dhalkebar-Muzaffarpur Line (Double circuit,
128kms)
Equipments used in Substation
 Busbar
 Lightning Arrestors
 Capacitive Voltage Transformer
 Circuit Breaker
 Isolators
 Current Transformers
 Wave Trap
 Interconnected Transformers
 Shunt Reactor
Busbars
 It is a thick stripe of
copper or aluminium that
conducts electricity
within a switch board or
substation
 In Muzaffarpur substation
flexible ACSR bus is used
with Quad conductors
 Rated voltage= 400kv
 Rated current=3150A
Lightning Arrestor
 It is used to ground the high
voltages surges falling on line
due to lightning
 Core of LA is made of ZnO2,
which acts as Non linear
resistance
 ZnO2 offers high resistance
during normal conditions and
Low resistance during high
surge voltages
 A ring type structure is
provided on top to reduce
corona effect
Capacitive voltage Transformer
 It is used to step down
extra high voltages to low
values for metering and
protection purposes
 It has 3 secondary cores in
which two are used for
protection and one is used
for metering
 It is always connected in
parallel
Circuit Breakers
 It is an automatically
operated electrical switch
designed to protect an
electric circuit from
damage caused by short
circuit or overload
 SF6 circuit breakers are
widely used in substations
these days because of its
excellent arc
extinguishing ability
Isolators
 It is a switch used to
completely de-energize an
electrical circuit
 It operates under no load
conditions
 It provides isolation of
apparatus such as circuit
breakers, transformers
and transmission lines
during maintenance
Current Transformers
 It is used for protection
and metering
 It has primary coil of one
or more turns of thick
wire connected in series
with the line whose
current is to be measured
 Secondary consists of
large number of turns of
fine wires and is
connected across
ammeter terminals
Wave Trap
 A wave trap is used on those
transmission lines which are
equipped with PLCC (Power
Line Carrier Communication).
 As the communication signal
frequency is much different
from line frequency, it is quite
necessary to separate the
power signal and
communication signal.
 This task is performed by a
wave trap which simply consists
of L-C series and parallel
filters.
Interconnected transformers
 It is the costliest equipment of
substations
 It is used to step up or step down
voltages in substations without
change in frequency
 In Muzaffarpur substation two
transformers of 315MVA and one
transformer of 500MVA is used
 Secondary winding provides 220kV
voltages
 There is tertiary winding also
which provides 33kv and can be
used as auxiliary power purpose
Shunt Reactor
 It is a thyristor controlled
high impedance
transformer
 It is used to absorb excess
of reactive power in
transmission line
 It compensates the
capacitive VAR generated
in line
Control Room
 The control room has various control panels which shows
the information like incoming power, outgoing power,
frequency, time common to all substations, status of
various lines (healthy, faulted, under outage or
maintenance), status of various protective instruments
like isolators, circuit breakers; temperatures of various
instruments, working tap of transformers etc.
Control panels in a control room
Relay Room
 It has Relay Panels for protection purposes
 The protection system is so fast that it can
detect a fault within 30 ms and hence the
circuit breaker can be operated within as
less as 80 ms.
 All relays used here are numerical and are
either from Siemens OR ABB .
Relay panels
Conclusion
 During these four weeks of work there I
developed my team work, analytical thinking
and various important information about
electric power system. The main objective of
this whole training program is to provide an
opportunity to identify, observe and practice
how engineering is applicable in the real
industry.

More Related Content

What's hot

132 kv substation
132 kv substation132 kv substation
132 kv substationWipro
 
Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training Sakshi Rastogi
 
industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substationpk130992
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at JassureShuvam Pathania
 
industrial Training report in PTCUL Substation dehradun
industrial Training report in PTCUL Substation dehradunindustrial Training report in PTCUL Substation dehradun
industrial Training report in PTCUL Substation dehradunsurendra rawat
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV Girish Gupta
 
220KV Substation Training Report
220KV Substation Training Report220KV Substation Training Report
220KV Substation Training ReportSWAPNILKUMARGUPTA
 
Summer Internship Report -By Rahul Mehra
Summer Internship Report -By Rahul MehraSummer Internship Report -By Rahul Mehra
Summer Internship Report -By Rahul MehraRahul Mehra
 
ELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFjang041
 
substation internship report
substation internship report substation internship report
substation internship report Arun Thapa
 
Visit to 400 kV substation, Hadala
Visit to 400 kV substation, HadalaVisit to 400 kV substation, Hadala
Visit to 400 kV substation, HadalaNandan Desai
 
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONPPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONSwatantra SwAt
 
Electrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakirElectrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakirSheikh Shakir
 
substation 220 kv
substation 220 kv substation 220 kv
substation 220 kv student
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation Tejveer Choudhary
 
A Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationA Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationSubhrajit Ghosh
 

What's hot (20)

132 kv substation
132 kv substation132 kv substation
132 kv substation
 
132 kv gss
132 kv gss132 kv gss
132 kv gss
 
Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training Presentation on 132/33 KVSubstation Training
Presentation on 132/33 KVSubstation Training
 
industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substation
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
 
industrial Training report in PTCUL Substation dehradun
industrial Training report in PTCUL Substation dehradunindustrial Training report in PTCUL Substation dehradun
industrial Training report in PTCUL Substation dehradun
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV
 
220KV Substation Training Report
220KV Substation Training Report220KV Substation Training Report
220KV Substation Training Report
 
Summer Internship Report -By Rahul Mehra
Summer Internship Report -By Rahul MehraSummer Internship Report -By Rahul Mehra
Summer Internship Report -By Rahul Mehra
 
ELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEF
 
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, AllahabadSummer Training presentation on 132/33 KV sub-station Minto park, Allahabad
Summer Training presentation on 132/33 KV sub-station Minto park, Allahabad
 
substation internship report
substation internship report substation internship report
substation internship report
 
ppt
pptppt
ppt
 
Visit to 400 kV substation, Hadala
Visit to 400 kV substation, HadalaVisit to 400 kV substation, Hadala
Visit to 400 kV substation, Hadala
 
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONPPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
 
Electrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakirElectrical 132kv substation project .. shakir
Electrical 132kv substation project .. shakir
 
substation 220 kv
substation 220 kv substation 220 kv
substation 220 kv
 
220 kv gss
220 kv gss220 kv gss
220 kv gss
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation
 
A Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationA Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv Substation
 

Similar to Summer internship at pgcil

Rajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxRajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxsohaib268827
 
Sharavati receiving station
Sharavati  receiving stationSharavati  receiving station
Sharavati receiving stationH.C.Naveen Kumar
 
PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...
PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...
PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...Abrar Ahmad
 
WBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportWBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportArijit Basu
 
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfDevesh54
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptAshutosh Srivastava
 
132 kv sub-station, power transmission
132 kv sub-station, power transmission132 kv sub-station, power transmission
132 kv sub-station, power transmissionprasantakcs
 
INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG
INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG  INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG
INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG Muneeb Amin Khan
 
sub subsation seminar ppt.pptx
sub subsation seminar ppt.pptxsub subsation seminar ppt.pptx
sub subsation seminar ppt.pptxfallinhay
 
220 kv g.s.s, report
 220 kv g.s.s, report 220 kv g.s.s, report
220 kv g.s.s, reportpanna rayal
 
132 kv g.s.s chambal jaipur
132 kv g.s.s chambal jaipur132 kv g.s.s chambal jaipur
132 kv g.s.s chambal jaipurmonga786
 
220kv GSS, VKIA, jaipur
220kv GSS, VKIA, jaipur 220kv GSS, VKIA, jaipur
220kv GSS, VKIA, jaipur Renuka Verma
 
400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPURsahid raja khan
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxAkshaiSai2
 
400 kv Heerapura gss ppt by ishan pdf
400 kv Heerapura gss ppt by ishan pdf 400 kv Heerapura gss ppt by ishan pdf
400 kv Heerapura gss ppt by ishan pdf Ishan Khandelwal
 
Manish Kumar Gangey- 19ESKEE095.pptx
Manish Kumar Gangey- 19ESKEE095.pptxManish Kumar Gangey- 19ESKEE095.pptx
Manish Kumar Gangey- 19ESKEE095.pptxManish Gangwal
 
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...Rishabhlko
 
industrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxindustrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxShubhoDas5
 

Similar to Summer internship at pgcil (20)

Rajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptxRajasthan Rajya Vidyut Prasaran Nigam.pptx
Rajasthan Rajya Vidyut Prasaran Nigam.pptx
 
Sharavati receiving station
Sharavati  receiving stationSharavati  receiving station
Sharavati receiving station
 
PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...
PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...
PPT ON SUMMER VOCATIONAL TRAINING ON 132/33 KV AT MOHADDIPUR, SUB-STATION, GO...
 
WBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportWBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training Report
 
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdfindustrialsummertrainingon220kvsubstationppt-170413134021.pdf
industrialsummertrainingon220kvsubstationppt-170413134021.pdf
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation ppt
 
132 kv sub-station, power transmission
132 kv sub-station, power transmission132 kv sub-station, power transmission
132 kv sub-station, power transmission
 
INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG
INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG  INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG
INDUSTRIAL TRAINING PRESENTATION OF 132/33Kv, 130MVA WANPOH GRID ANANTNAG
 
sub subsation seminar ppt.pptx
sub subsation seminar ppt.pptxsub subsation seminar ppt.pptx
sub subsation seminar ppt.pptx
 
220 kv g.s.s, report
 220 kv g.s.s, report 220 kv g.s.s, report
220 kv g.s.s, report
 
132 kv g.s.s chambal jaipur
132 kv g.s.s chambal jaipur132 kv g.s.s chambal jaipur
132 kv g.s.s chambal jaipur
 
220kv GSS, VKIA, jaipur
220kv GSS, VKIA, jaipur 220kv GSS, VKIA, jaipur
220kv GSS, VKIA, jaipur
 
400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR400 KV GSS HEERAPURA, JAIPUR
400 KV GSS HEERAPURA, JAIPUR
 
Ashwani kumar
Ashwani kumarAshwani kumar
Ashwani kumar
 
psp.pptx
psp.pptxpsp.pptx
psp.pptx
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptx
 
400 kv Heerapura gss ppt by ishan pdf
400 kv Heerapura gss ppt by ishan pdf 400 kv Heerapura gss ppt by ishan pdf
400 kv Heerapura gss ppt by ishan pdf
 
Manish Kumar Gangey- 19ESKEE095.pptx
Manish Kumar Gangey- 19ESKEE095.pptxManish Kumar Gangey- 19ESKEE095.pptx
Manish Kumar Gangey- 19ESKEE095.pptx
 
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
 
industrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptxindustrial-training-at-howrah-220-kv-substation.pptx
industrial-training-at-howrah-220-kv-substation.pptx
 

Recently uploaded

IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 

Recently uploaded (20)

IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 

Summer internship at pgcil

  • 1. A Summer Training Presentation on 400/220kv substation School of Electrical & Electronics Engineering Lovely Professional University, Punjab By:- Anurag Savarn Reg No:-11504716
  • 2. Introduction of Substation  It is situated in Kafen, Muzaffarpur and is 50km away from Patna, capital of Bihar  It was inaugurated on 26 august 2006, and has a total transformation capacity of 1115 MVA  It has been constructed by PGCIL, as a part of east-north interconnector  Breaker and a half scheme has been used in 400kv switchyard while 220kv switchyard has double main and Transfer Bus scheme
  • 3. Associated transmission Lines  400kv Purnea-Muzaffarpur Line (Double circuit, 239kms)  400kv Gorakhpur-Muzaffarpur Line (Double circuit, 261kms)  400kv Biharsarif-Muzaffarpur Line (Double circuit, 131kms)  400kv Darbhanga-Muzaffarpur Line (Double circuit, 64kms)  220kv kanti MTPS-Muzaffarpur Line (Double circuit, 24kms)  220kv Hazipur-Muzaffarpur Line (Double circuit, 55kms)  220kv Dhalkebar-Muzaffarpur Line (Double circuit, 128kms)
  • 4. Equipments used in Substation  Busbar  Lightning Arrestors  Capacitive Voltage Transformer  Circuit Breaker  Isolators  Current Transformers  Wave Trap  Interconnected Transformers  Shunt Reactor
  • 5. Busbars  It is a thick stripe of copper or aluminium that conducts electricity within a switch board or substation  In Muzaffarpur substation flexible ACSR bus is used with Quad conductors  Rated voltage= 400kv  Rated current=3150A
  • 6. Lightning Arrestor  It is used to ground the high voltages surges falling on line due to lightning  Core of LA is made of ZnO2, which acts as Non linear resistance  ZnO2 offers high resistance during normal conditions and Low resistance during high surge voltages  A ring type structure is provided on top to reduce corona effect
  • 7. Capacitive voltage Transformer  It is used to step down extra high voltages to low values for metering and protection purposes  It has 3 secondary cores in which two are used for protection and one is used for metering  It is always connected in parallel
  • 8. Circuit Breakers  It is an automatically operated electrical switch designed to protect an electric circuit from damage caused by short circuit or overload  SF6 circuit breakers are widely used in substations these days because of its excellent arc extinguishing ability
  • 9. Isolators  It is a switch used to completely de-energize an electrical circuit  It operates under no load conditions  It provides isolation of apparatus such as circuit breakers, transformers and transmission lines during maintenance
  • 10. Current Transformers  It is used for protection and metering  It has primary coil of one or more turns of thick wire connected in series with the line whose current is to be measured  Secondary consists of large number of turns of fine wires and is connected across ammeter terminals
  • 11. Wave Trap  A wave trap is used on those transmission lines which are equipped with PLCC (Power Line Carrier Communication).  As the communication signal frequency is much different from line frequency, it is quite necessary to separate the power signal and communication signal.  This task is performed by a wave trap which simply consists of L-C series and parallel filters.
  • 12. Interconnected transformers  It is the costliest equipment of substations  It is used to step up or step down voltages in substations without change in frequency  In Muzaffarpur substation two transformers of 315MVA and one transformer of 500MVA is used  Secondary winding provides 220kV voltages  There is tertiary winding also which provides 33kv and can be used as auxiliary power purpose
  • 13. Shunt Reactor  It is a thyristor controlled high impedance transformer  It is used to absorb excess of reactive power in transmission line  It compensates the capacitive VAR generated in line
  • 14. Control Room  The control room has various control panels which shows the information like incoming power, outgoing power, frequency, time common to all substations, status of various lines (healthy, faulted, under outage or maintenance), status of various protective instruments like isolators, circuit breakers; temperatures of various instruments, working tap of transformers etc.
  • 15. Control panels in a control room
  • 16. Relay Room  It has Relay Panels for protection purposes  The protection system is so fast that it can detect a fault within 30 ms and hence the circuit breaker can be operated within as less as 80 ms.  All relays used here are numerical and are either from Siemens OR ABB .
  • 18. Conclusion  During these four weeks of work there I developed my team work, analytical thinking and various important information about electric power system. The main objective of this whole training program is to provide an opportunity to identify, observe and practice how engineering is applicable in the real industry.