SlideShare a Scribd company logo
1 of 22
Rajasthan Rajya Vidyut Prasaran Nigam
220Kv Grid Substation
(Kunda Ki Dhani, Kukas, Jaipur)
Submitted by
Palak Gupta
Submitted to
Department of Electrical and Electronics Engineering
Birla Institute of Technology, Mesra
Rajasthan Rajya Vidyut Prasaran Nigam Limited
 RVPN is a company of Rajasthan State Electricity Board(RSEB) established by the government of
Rajasthan.
 Aim Of RVPN is to provide reliable transmission service to customers.
 RVPN provides a pathway for power within the whole of Rajasthan. It owns, builds, maintains, and
operates the high voltage electric transmission system that helps to keep the lights on, businesses
running and communities strong.
Introduction
• The present-day electrical power system is A.C. i.e., electric power is
generated, transmitted, and distributed in the form of alternating
current. The electric power is produced at the power stations which are
located at favourable places, generally quite away from the consumers. It
is delivered to the consumers through a large network of transmission
and distribution.
• Along the transmission lines, secondary substations are created where
voltage is further stepped down to sub-transmission and primary
distribution voltage.
• A substation is an assembly of apparatus, which transforms the
characteristics of electrical energy from one form to another say from
one voltage level to another level. Hence a substation is an intermediate
link between the generating station and the consumer.
• For economic transmission the voltage should be high, so it is necessary
to step up the generated voltage for transmission and step down the
transmitted voltage for distribution. For this substations are installed.
The normal voltages for transmission are 400kv, 220kv,132kv, and for
distribution 33kv,11kv, etc.
220 kv GSS, Kunda ki Dhani ,Jaipur
 The 220 KV GSS is situated in KUNDA ki Dhani, Jaipur. In the GSS single main and auxillary scheme is used. There are
total three incoming feeder and many outgoing feeders which are mentioned in the next section.
 The GSS step down the voltage level from 220KV to 132 KV and 132 KV to 33 KV or 11 KV in different manner.
 There are three bus bar arrangement, main bus bar used at a time and auxillary bus bar are connected through bus
coupler. In case of main bus or other equipment are out of order or other maintenance purpose than supply should be
given through auxiliary bus bar without interruption in supply.
FEEDERS
Incoming Feeders:
 220 KV PGCIL-KKD
 132 KV KUKAS-KKD 1st
 132 KV KUKAS-KKD 2nd
Outgoing Feeders:
 220 KV KKD- KUKAS
 132 KV KKD-PURANGHAT
 33KV
► Achrol
► Amber
► Bund Gate 1
► Bund Gate 2
► JDA
► Hotel Indana
 11 KV
► Natata
► Kunda water works
► Kukas
BUS BARS
 Bus bars are a common electrical component through which a large number of feeders operating at some
voltage have to be connected.
 Electrical Busbar consists of the number of lines electrically, which are operating at the same voltage and
frequencies. Generally, copper or aluminum conducting material is used in the construction of bus bars.
 Bus bars are arranged in different configurations, any particular arrangement of the bus bar is to achieve
adequate operating flexibility, sufficient reliability, and minimum cost.
ISOLATORS
 It isolates the device from live line when there is a maintenance.
 It operates when there is no load.
 It is also used to change bus bar line from main to reserve and vice versa.
Circuit Breaker
 A circuit breaker is an automatically operated
electrical switch designed to protect an
electrical circuit from damage caused by
overload or short circuit. Its basic function is
to detect a fault condition and interrupt
current flow.
 A circuit breaker can be reset (either
manually or automatically) to resume normal
operation, unlike fuse(which operates once).
 Today, two most popular circuit breakers are
used in substation which are: Vacuum Circuit
Breaker and SF6.
Lightning Arrestor
 A lightning arrester is a device used on electrical power systems to protect the insulation on the system
from the damaging effect of lightning.
 When a lightning surge or switching surge travels down the power system to the arrester, the current from
the surge is diverted around the protected insulation in most cases to earth.
 A lightning arrestor has two terminals viz a high voltage terminal and ground terminal .
INSULATOR
 The electrical insulator is a device
that provides the required insulation
between the line conductor and
earth. Due to this insulation,
leakage current can’t flow from the
line conductor to earth.
 Insulator has very high resistivity
(offers very high resistance). Due to
this high resistance, electrical
current does not flow from one
point to another.
RELAY
 In a power system it is inevitable that immediately or later some failure does occur
somewhere in the system. When a failure occurs on any part of the system, it must be
quickly detected and disconnected from the system. Rapid disconnection of faulted
apparatus limits the amount of damage to it and prevents the effects of fault from
spreading into the system.
 For high voltage circuits relays are employed to serve the desired function of automatic
protective gear. The relays detect the fault and supply the information to the circuit
breaker. The electrical quantities which may change under fault condition are voltage,
frequency, current, phase angle.
WAVE TRAP
 Line trap also is known as Wave trap.
 A Line trap (high frequency stopper) is a maintenance free inductor , mounted inline on high
voltage Ac transmission power lines to prevent the transmission of high frequency(40kHz to
100 kHz) carrier signals of line communication to unwanted destinations.
 What it does is trapping the high frequency communication signals sent on the tine from the
remote substation and diverting them to the telecom/teleportation panel in the substation
control room (through coupling capacitor and LMU).This is relevant in Power Line Carrier
Communication (PLCC) systems for communication among various substations without
dependence on the telecom company network.
Transformers
 Transformer is a static machine, which transforms the potential of alternating current at
same frequency. It means the transformer transforms the low voltage into high voltage &
high voltage to low voltage at same frequency. It works on the principle of static induction
principle.
 When the energy is transformed into a higher voltage, the transformer is called step up
transformer but in case of other is known as step down transformer.
POWER TRANSFORMER
 The Power transformer is one type of transformer that is
used to transmit electrical energy in any component of the
electronic or electrical circuit between the distribution
primary circuits and the generator. These transformers are
utilized in distribution networks to interface step down and
step up voltages. The usual form of power transformer is
fluid immersed, and the life cycle of these instruments is
approximately 30 years. Power transformers can be divided
into three types according to the ranges. They are large
power transformers, medium power transformers, and small
power transformers.
 The range of large power transformers can be from 100MVA
and beyond
 The range of medium power transformers can be from -
100MVA
 The range of low power transformers can be from 500-
7500kVA
CURRENT TRANSFORMER
 There are 3 sets of the current transformers
installed at the sub-station. Each set have three
current transformers. Like any other
transformer, a current transformer has a
primary winding, a magnetic core, and a
secondary winding. The alternating current
flowing in the primary produces a magnetic
field in the core, which then induces a current
in the secondary winding circuit.
 . A primary objective of current transformer
design is to ensure that the primary and
secondary circuits are efficiently coupled so
that the secondary current bears an accurate
relationship to the primary current.
Potential Transformer
 Potential transformers are instrument
transformers.
 They have a large number of primary turns and a
few number of secondary turns. It is used to
control the large value of voltage.
 These are used for the metering purposes. The
potential transformer works along the same
principle of other transformers.
 It converts voltages from high to low. It will take
the thousands of volts behind power transmission
systems and step the voltage down to something
that meters can handle. These transformers work
for single and three phase systems, and are
attached at a point where it is convenient to
measure the voltage.
 Potential Transformer is designed for monitoring
single-phase and three-phase power line voltages
in power metering applications.
CAPACITIVE VOLTAGE
TRANSFORMER
 A capacitor voltage transformer (CVT), or
capacitance coupled voltage transformer
(CCVT) is a transformer used in power
systems to step down extra high voltage
signals and provide a low voltage signal,
for measurement or to operate a
protective relay.
 In its most basic form the device consists
of three parts: two capacitors across
which the transmission line signal is split,
an inductive element to tune the device
to the line frequency, and a transformer
to isolate and further step down the
voltage for the instrumentation or
protective relay.
TRANSFORMER OIL
TESTING
 Oil testing of transformer is how blood testing to human beings. Transformer oil testing is a proven and best-
known loss prevention technique that should be part of any maintenance program of an organization. It not
only acts as an early warning system but also helps us to understand the inner health of the transformer
without disrupting its operation.
 Transformer oil testing when done on a regular time interval allows the maintenance department to identify
priorities, plan work assignments and gives enough time to arrange outside vendors for transformer servicing or
maybe order necessary parts and materials.
FEW OIL TESTING TECHNIQUES
 Visual Examination: One of the first test which is generally conducted
in lab is visual examination which is done by passing a beam of light
through it to determine transparency and identify foreign matters.
 Dielectric Breakdown Voltage (BDV Test)-With this test, the
dielectric strength of the insulating oil is tested or on other words we
measure the voltage at which the oil fails electrically which is a good
indication of the amount of oil containment or moisture present inside the
oil. This test is conducted by placing oil sample between two electrodes
and voltage is applied gradually till the time electrodes have enough
potential and starts to conduct through the oil and that’s what we call as
the breakdown voltage of the oil.
 Flash Point or Fire Point- This test is used to check the volatility of
the oil. It is the minimum temperature at which the heated oil starts to give
out sufficient vapor to form flammable moisture with the air. The
international standard used for this test is ASTM D92
.
Single Line Diagram, KKD
CONCLUSION
 We think that our training was successful and we
think that the 220KV sub-station at RVPN, KUNDA
KI DHANI ,KUKAS, JAIPUR is an excellent training
centre for inquisitive emerging electrical engineers
to learn about the transmission and distribution of
high voltage electricity and all other protective
devices. In the training session we came to know
about the fundamentals of power system which
may be quite useful for our fore coming studies.
 The three wings of the electrical system viz
generation, transmission, and distribution are
connected to each other that to very perfectly.
THANK -YOU

More Related Content

What's hot

industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substationpk130992
 
EHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniquesEHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniquesYashwant Chaudhari
 
Training report on substation presentation
Training report on substation presentationTraining report on substation presentation
Training report on substation presentationKanahiya Lal
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & MaintenanceHimansu Pradhan
 
Design of substation
Design of substationDesign of substation
Design of substationSayanSarkar55
 
Ppt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurPpt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurkishankky
 
Electric substation
Electric substation Electric substation
Electric substation ANNU KUMAR
 
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPSOperational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPSPradeep Avanigadda
 
ppt on summer training on uppcl
ppt on summer training on uppclppt on summer training on uppcl
ppt on summer training on uppclSunny Daksh
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSPartha Parida
 
Training report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substationTraining report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substationankesh kumar
 
ELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFjang041
 
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONPPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONSwatantra SwAt
 
132 k v-substation-training-for-students
132 k v-substation-training-for-students132 k v-substation-training-for-students
132 k v-substation-training-for-studentsSanjay Kumar Sharma
 
Overhead line work ppt
Overhead line work pptOverhead line work ppt
Overhead line work pptDemsew Mitiku
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformerssiddharam kantoli
 

What's hot (20)

industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substation
 
EHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniquesEHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniques
 
Training report on substation presentation
Training report on substation presentationTraining report on substation presentation
Training report on substation presentation
 
220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance220 KV Substation Operation & Maintenance
220 KV Substation Operation & Maintenance
 
Design of substation
Design of substationDesign of substation
Design of substation
 
220 kv gss
220 kv gss220 kv gss
220 kv gss
 
Ppt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipurPpt of 132kv gss sitapura jaipur
Ppt of 132kv gss sitapura jaipur
 
Electric substation
Electric substation Electric substation
Electric substation
 
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPSOperational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
 
ppt on summer training on uppcl
ppt on summer training on uppclppt on summer training on uppcl
ppt on summer training on uppcl
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
 
220 kv gss renwal ppt
220 kv gss renwal ppt220 kv gss renwal ppt
220 kv gss renwal ppt
 
Training report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substationTraining report-in-a-132-k-v-substation
Training report-in-a-132-k-v-substation
 
ELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEFELECTRIC SUB-STATION IN BRIEF
ELECTRIC SUB-STATION IN BRIEF
 
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATIONPPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
PPT ON SUMMER TRAINING FROM UPPCL 132/33 KV SUB STATION
 
132 k v-substation-training-for-students
132 k v-substation-training-for-students132 k v-substation-training-for-students
132 k v-substation-training-for-students
 
Switch yard & Protection
Switch yard & ProtectionSwitch yard & Protection
Switch yard & Protection
 
Overhead line work ppt
Overhead line work pptOverhead line work ppt
Overhead line work ppt
 
33kv substation
33kv substation33kv substation
33kv substation
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformers
 

Similar to Rajasthan Rajya Vidyut Prasaran Nigam.pptx

Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limitedVSRAGHU
 
sub subsation seminar ppt.pptx
sub subsation seminar ppt.pptxsub subsation seminar ppt.pptx
sub subsation seminar ppt.pptxfallinhay
 
Sharavati receiving station
Sharavati  receiving stationSharavati  receiving station
Sharavati receiving stationH.C.Naveen Kumar
 
Uttar Pradesh Power Corporation 132kv
Uttar Pradesh Power Corporation 132kv Uttar Pradesh Power Corporation 132kv
Uttar Pradesh Power Corporation 132kv Vikash Raaz
 
132 kv g.s.s chambal jaipur
132 kv g.s.s chambal jaipur132 kv g.s.s chambal jaipur
132 kv g.s.s chambal jaipurmonga786
 
WBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportWBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportArijit Basu
 
Load Distribution
Load DistributionLoad Distribution
Load DistributionArpit Gupta
 
Tanuj sharma on industrial training 2.pptx
Tanuj sharma on industrial training 2.pptxTanuj sharma on industrial training 2.pptx
Tanuj sharma on industrial training 2.pptxtanujsharma345942
 
PPT ON 220KV GSS
PPT ON 220KV GSSPPT ON 220KV GSS
PPT ON 220KV GSSMohitkalal4
 
Report On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-StationReport On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-StationEkram Bin Mamun
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at JassureShuvam Pathania
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLyohannes feleke
 
Switchyard design overview
Switchyard design overviewSwitchyard design overview
Switchyard design overviewMilind Punj
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentationKamal Mittal
 
Internship doc 33 11 kv substation
Internship doc 33 11 kv substation  Internship doc 33 11 kv substation
Internship doc 33 11 kv substation Madeen Kumar
 
Manish Kumar Gangey- 19ESKEE095.pptx
Manish Kumar Gangey- 19ESKEE095.pptxManish Kumar Gangey- 19ESKEE095.pptx
Manish Kumar Gangey- 19ESKEE095.pptxManish Gangwal
 

Similar to Rajasthan Rajya Vidyut Prasaran Nigam.pptx (20)

Uttar pradesh power corporation limited
Uttar pradesh power corporation limitedUttar pradesh power corporation limited
Uttar pradesh power corporation limited
 
sub subsation seminar ppt.pptx
sub subsation seminar ppt.pptxsub subsation seminar ppt.pptx
sub subsation seminar ppt.pptx
 
Sharavati receiving station
Sharavati  receiving stationSharavati  receiving station
Sharavati receiving station
 
Uttar Pradesh Power Corporation 132kv
Uttar Pradesh Power Corporation 132kv Uttar Pradesh Power Corporation 132kv
Uttar Pradesh Power Corporation 132kv
 
132 kv g.s.s chambal jaipur
132 kv g.s.s chambal jaipur132 kv g.s.s chambal jaipur
132 kv g.s.s chambal jaipur
 
WBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training ReportWBSETCL Subhash Gram 220KV Substation Training Report
WBSETCL Subhash Gram 220KV Substation Training Report
 
Gss ppt by kanhaiya
Gss ppt  by kanhaiyaGss ppt  by kanhaiya
Gss ppt by kanhaiya
 
Ashwani kumar
Ashwani kumarAshwani kumar
Ashwani kumar
 
rough.pptx
rough.pptxrough.pptx
rough.pptx
 
Load Distribution
Load DistributionLoad Distribution
Load Distribution
 
Tanuj sharma on industrial training 2.pptx
Tanuj sharma on industrial training 2.pptxTanuj sharma on industrial training 2.pptx
Tanuj sharma on industrial training 2.pptx
 
PPT ON 220KV GSS
PPT ON 220KV GSSPPT ON 220KV GSS
PPT ON 220KV GSS
 
Report On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-StationReport On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-Station
 
Report on 220kv substation at Jassure
Report on 220kv substation at JassureReport on 220kv substation at Jassure
Report on 220kv substation at Jassure
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROL
 
Ashish.pptx
Ashish.pptxAshish.pptx
Ashish.pptx
 
Switchyard design overview
Switchyard design overviewSwitchyard design overview
Switchyard design overview
 
Substation Training presentation
Substation Training presentationSubstation Training presentation
Substation Training presentation
 
Internship doc 33 11 kv substation
Internship doc 33 11 kv substation  Internship doc 33 11 kv substation
Internship doc 33 11 kv substation
 
Manish Kumar Gangey- 19ESKEE095.pptx
Manish Kumar Gangey- 19ESKEE095.pptxManish Kumar Gangey- 19ESKEE095.pptx
Manish Kumar Gangey- 19ESKEE095.pptx
 

Recently uploaded

Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
An introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxAn introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxPurva Nikam
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 

Recently uploaded (20)

Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
An introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptxAn introduction to Semiconductor and its types.pptx
An introduction to Semiconductor and its types.pptx
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 

Rajasthan Rajya Vidyut Prasaran Nigam.pptx

  • 1. Rajasthan Rajya Vidyut Prasaran Nigam 220Kv Grid Substation (Kunda Ki Dhani, Kukas, Jaipur) Submitted by Palak Gupta Submitted to Department of Electrical and Electronics Engineering Birla Institute of Technology, Mesra
  • 2. Rajasthan Rajya Vidyut Prasaran Nigam Limited  RVPN is a company of Rajasthan State Electricity Board(RSEB) established by the government of Rajasthan.  Aim Of RVPN is to provide reliable transmission service to customers.  RVPN provides a pathway for power within the whole of Rajasthan. It owns, builds, maintains, and operates the high voltage electric transmission system that helps to keep the lights on, businesses running and communities strong.
  • 3. Introduction • The present-day electrical power system is A.C. i.e., electric power is generated, transmitted, and distributed in the form of alternating current. The electric power is produced at the power stations which are located at favourable places, generally quite away from the consumers. It is delivered to the consumers through a large network of transmission and distribution. • Along the transmission lines, secondary substations are created where voltage is further stepped down to sub-transmission and primary distribution voltage. • A substation is an assembly of apparatus, which transforms the characteristics of electrical energy from one form to another say from one voltage level to another level. Hence a substation is an intermediate link between the generating station and the consumer. • For economic transmission the voltage should be high, so it is necessary to step up the generated voltage for transmission and step down the transmitted voltage for distribution. For this substations are installed. The normal voltages for transmission are 400kv, 220kv,132kv, and for distribution 33kv,11kv, etc.
  • 4. 220 kv GSS, Kunda ki Dhani ,Jaipur  The 220 KV GSS is situated in KUNDA ki Dhani, Jaipur. In the GSS single main and auxillary scheme is used. There are total three incoming feeder and many outgoing feeders which are mentioned in the next section.  The GSS step down the voltage level from 220KV to 132 KV and 132 KV to 33 KV or 11 KV in different manner.  There are three bus bar arrangement, main bus bar used at a time and auxillary bus bar are connected through bus coupler. In case of main bus or other equipment are out of order or other maintenance purpose than supply should be given through auxiliary bus bar without interruption in supply.
  • 5. FEEDERS Incoming Feeders:  220 KV PGCIL-KKD  132 KV KUKAS-KKD 1st  132 KV KUKAS-KKD 2nd Outgoing Feeders:  220 KV KKD- KUKAS  132 KV KKD-PURANGHAT  33KV ► Achrol ► Amber ► Bund Gate 1 ► Bund Gate 2 ► JDA ► Hotel Indana  11 KV ► Natata ► Kunda water works ► Kukas
  • 6. BUS BARS  Bus bars are a common electrical component through which a large number of feeders operating at some voltage have to be connected.  Electrical Busbar consists of the number of lines electrically, which are operating at the same voltage and frequencies. Generally, copper or aluminum conducting material is used in the construction of bus bars.  Bus bars are arranged in different configurations, any particular arrangement of the bus bar is to achieve adequate operating flexibility, sufficient reliability, and minimum cost.
  • 7. ISOLATORS  It isolates the device from live line when there is a maintenance.  It operates when there is no load.  It is also used to change bus bar line from main to reserve and vice versa.
  • 8. Circuit Breaker  A circuit breaker is an automatically operated electrical switch designed to protect an electrical circuit from damage caused by overload or short circuit. Its basic function is to detect a fault condition and interrupt current flow.  A circuit breaker can be reset (either manually or automatically) to resume normal operation, unlike fuse(which operates once).  Today, two most popular circuit breakers are used in substation which are: Vacuum Circuit Breaker and SF6.
  • 9. Lightning Arrestor  A lightning arrester is a device used on electrical power systems to protect the insulation on the system from the damaging effect of lightning.  When a lightning surge or switching surge travels down the power system to the arrester, the current from the surge is diverted around the protected insulation in most cases to earth.  A lightning arrestor has two terminals viz a high voltage terminal and ground terminal .
  • 10. INSULATOR  The electrical insulator is a device that provides the required insulation between the line conductor and earth. Due to this insulation, leakage current can’t flow from the line conductor to earth.  Insulator has very high resistivity (offers very high resistance). Due to this high resistance, electrical current does not flow from one point to another.
  • 11. RELAY  In a power system it is inevitable that immediately or later some failure does occur somewhere in the system. When a failure occurs on any part of the system, it must be quickly detected and disconnected from the system. Rapid disconnection of faulted apparatus limits the amount of damage to it and prevents the effects of fault from spreading into the system.  For high voltage circuits relays are employed to serve the desired function of automatic protective gear. The relays detect the fault and supply the information to the circuit breaker. The electrical quantities which may change under fault condition are voltage, frequency, current, phase angle.
  • 12. WAVE TRAP  Line trap also is known as Wave trap.  A Line trap (high frequency stopper) is a maintenance free inductor , mounted inline on high voltage Ac transmission power lines to prevent the transmission of high frequency(40kHz to 100 kHz) carrier signals of line communication to unwanted destinations.  What it does is trapping the high frequency communication signals sent on the tine from the remote substation and diverting them to the telecom/teleportation panel in the substation control room (through coupling capacitor and LMU).This is relevant in Power Line Carrier Communication (PLCC) systems for communication among various substations without dependence on the telecom company network.
  • 13. Transformers  Transformer is a static machine, which transforms the potential of alternating current at same frequency. It means the transformer transforms the low voltage into high voltage & high voltage to low voltage at same frequency. It works on the principle of static induction principle.  When the energy is transformed into a higher voltage, the transformer is called step up transformer but in case of other is known as step down transformer.
  • 14. POWER TRANSFORMER  The Power transformer is one type of transformer that is used to transmit electrical energy in any component of the electronic or electrical circuit between the distribution primary circuits and the generator. These transformers are utilized in distribution networks to interface step down and step up voltages. The usual form of power transformer is fluid immersed, and the life cycle of these instruments is approximately 30 years. Power transformers can be divided into three types according to the ranges. They are large power transformers, medium power transformers, and small power transformers.  The range of large power transformers can be from 100MVA and beyond  The range of medium power transformers can be from - 100MVA  The range of low power transformers can be from 500- 7500kVA
  • 15. CURRENT TRANSFORMER  There are 3 sets of the current transformers installed at the sub-station. Each set have three current transformers. Like any other transformer, a current transformer has a primary winding, a magnetic core, and a secondary winding. The alternating current flowing in the primary produces a magnetic field in the core, which then induces a current in the secondary winding circuit.  . A primary objective of current transformer design is to ensure that the primary and secondary circuits are efficiently coupled so that the secondary current bears an accurate relationship to the primary current.
  • 16. Potential Transformer  Potential transformers are instrument transformers.  They have a large number of primary turns and a few number of secondary turns. It is used to control the large value of voltage.  These are used for the metering purposes. The potential transformer works along the same principle of other transformers.  It converts voltages from high to low. It will take the thousands of volts behind power transmission systems and step the voltage down to something that meters can handle. These transformers work for single and three phase systems, and are attached at a point where it is convenient to measure the voltage.  Potential Transformer is designed for monitoring single-phase and three-phase power line voltages in power metering applications.
  • 17. CAPACITIVE VOLTAGE TRANSFORMER  A capacitor voltage transformer (CVT), or capacitance coupled voltage transformer (CCVT) is a transformer used in power systems to step down extra high voltage signals and provide a low voltage signal, for measurement or to operate a protective relay.  In its most basic form the device consists of three parts: two capacitors across which the transmission line signal is split, an inductive element to tune the device to the line frequency, and a transformer to isolate and further step down the voltage for the instrumentation or protective relay.
  • 18. TRANSFORMER OIL TESTING  Oil testing of transformer is how blood testing to human beings. Transformer oil testing is a proven and best- known loss prevention technique that should be part of any maintenance program of an organization. It not only acts as an early warning system but also helps us to understand the inner health of the transformer without disrupting its operation.  Transformer oil testing when done on a regular time interval allows the maintenance department to identify priorities, plan work assignments and gives enough time to arrange outside vendors for transformer servicing or maybe order necessary parts and materials.
  • 19. FEW OIL TESTING TECHNIQUES  Visual Examination: One of the first test which is generally conducted in lab is visual examination which is done by passing a beam of light through it to determine transparency and identify foreign matters.  Dielectric Breakdown Voltage (BDV Test)-With this test, the dielectric strength of the insulating oil is tested or on other words we measure the voltage at which the oil fails electrically which is a good indication of the amount of oil containment or moisture present inside the oil. This test is conducted by placing oil sample between two electrodes and voltage is applied gradually till the time electrodes have enough potential and starts to conduct through the oil and that’s what we call as the breakdown voltage of the oil.  Flash Point or Fire Point- This test is used to check the volatility of the oil. It is the minimum temperature at which the heated oil starts to give out sufficient vapor to form flammable moisture with the air. The international standard used for this test is ASTM D92 .
  • 21. CONCLUSION  We think that our training was successful and we think that the 220KV sub-station at RVPN, KUNDA KI DHANI ,KUKAS, JAIPUR is an excellent training centre for inquisitive emerging electrical engineers to learn about the transmission and distribution of high voltage electricity and all other protective devices. In the training session we came to know about the fundamentals of power system which may be quite useful for our fore coming studies.  The three wings of the electrical system viz generation, transmission, and distribution are connected to each other that to very perfectly.