SlideShare a Scribd company logo
1 of 28
01
PRESENTATION ON
PLANNING & SCHDEULING OF
G+1 BUNGALOW
ADITYA . P . MANE
M.TECH-CM-222030008
GUIDED BY
PROF. (DR) M.M. SHARMA
02
TABLE OF CONTENT
2. BACKGROUND
1. GENERAL INTRODUCTION
6. CONCLUSION
3. PROJECT PLANS
4. PROJECT DESCRIPTION
5. MICROSOFT PROJECT
GENERAL INTRODUCTION
03
• India has been experiencing rapid economic growth, averaging at 7.9% for
the last six years, making it the world's fastest-developing country.
• With the imminent rise of urbanization, there is a significant demand for
building houses, and the construction industry, which contributes to 12% of
the country's GDP, is growing at a rate of 9% annually.
• To meet the need for housing, at least 30 to 36 thousand units need to be
built per day for the next seven years.
• Housing is a fundamental human need, and as the population continues to
grow, there is a pressing need for a more reliable, faster, and sustainable
method of construction.
• While the aim of constructing buildings in the most economical way
remains the same, the construction industry has developed new
technologies to meet the demands of modern construction.
BACKGROUND
• Constructing a building from start to finish can be a challenging and time-consuming
task that requires significant effort and investment.
• However, it ultimately results in a permanent asset.
• Skilled individuals must undertake the systematic process of constructing a residential
building. Therefore, it is crucial to take caution during the construction process.
• Critical factors, such as the purpose of construction, financial proficiency, and demand
for work, should be considered before initiating any building project.
• Once the decision to construct a building is made, the planning phase begins.
• This presentation will discuss the step-by-step process of building construction from
start to finish.
04
PROJECT PLANS
05
Ground Floor Plan
PROJECT PLANS
06
First Floor Plan
PROJECT PLANS
07
Elevation
PROJECT PLANS
08
3D View
PROJECT PLANS
09
3D View
PROJECT DESCRIPTION
10
• The Total cost of the project is 23,08,337/-
• The duration of Project is 141 days.
• The Total Built-Up Area for each floor is =167 sqm
• The Total Carpet Area for each floor is = 141 sqm
• Footing, column, beam, slab, lintel, staircase, chajja, and
landing are constructed using M25 grade concrete.
• PCC (Plain Cement Concrete) is done using concrete mixed
in the proportion of 1:2:4.
• RCC (Reinforced Cement Concrete) work for lintel, staircase,
chajja, and landing is done using M25 grade concrete.
PROJECT DESCRIPTION
11
• Walls are built using 1st class brick with cement mortar
mixed in the proportion of 1:5.
• Backfilling is done using moorum.
• A damp proof course of 25mm thickness is provided and laid
using M25 grade cement concrete and bitumen or cement
mixed with a waterproofing compound, and the formwork is
used for the same.
• RMC (Ready-Mix Concrete) is used for huge concreting
works if required.
• On-site arrangements are made for material storage.
12
MICROSOFT PROJECT
2. STEPS INVOLVED
1.INTRODUCTION
3. WBS OF PROJECT
4. PROJECT WORK
5. REPORTS
INTRODUCTION
13
• Microsoft Project is project management software developed by
Microsoft
• It helps project managers with planning, resource allocation, progress
tracking, budget management, and workload analysis
• The software creates critical path schedules and allows for resource
leveling
• Resource definitions can be shared across multiple projects using a
shared resource pool.Each resource can have a personalized calendar to
define availability
• Assignment costs are calculated using resource rates
• Project data can be centralized and stored in a database using Microsoft
Office Project Server
• Microsoft Project Web Access enables authorized users to access and
update data remotely
14
WBS OF PROJECT
• A work breakdown structure
(WBS) is a visual tool used to break
down a complex project or task into
smaller, more manageable
components. The WBS helps to
organize the work, assign
responsibilities, and track progress.
STEPS INVOLVED
15
• Creating a Calendar
• Creating Activity & Enter Duration
• Entering Predecessors
• Creating Resource Sheet
• Assigning Resources
• Tracking Project
• Report Generation
16
PROJECT WORK
CALENDARS
• Calendars in Microsoft
Project define the
working and non-
working days of a
project, and are used to
calculate project
schedules.
17
ACTIVITY, DURATION & PREDECESSOR
• In Microsoft Project, an
activity refers to a specific task
or work item that needs to be
completed as part of a project.
Duration refers to the amount
of time it will take to complete
the activity, while predecessor
refers to any activities that
must be completed before the
current activity can begin.
18
NETWORK DIAGRAM
• A network diagram is a visual
representation of a network's
components and their
relationships. It is a graphical
representation of a network's
topology, which shows how
the different components of the
network are connected to each
other
19
RESOURCE SHEET
• Resources refer to anything
that can be used to accomplish
a task or goal, such as people,
equipment, time, money, or
materials. In order to complete
a project or achieve a goal, it is
important to effectively assign
resources and manage them
throughout the process.
20
GANTT CHART
• A Gantt chart is a visual tool used
in project management to display
a schedule of project tasks and
their durations. The chart is
composed of horizontal bars
representing the tasks, with the
length of each bar indicating the
duration of the task. The bars are
arranged along a timeline, which
is typically represented on the
chart as a horizontal axis.
21
PROJECT TRACKING & UPDATING
• To track your project in Microsoft
Project, you need to first set up
your project schedule, define a
baseline, enter actual progress,
compare it to the baseline, and
update the project plan
accordingly.
PROJECT REPORTS
22
• Microsoft Project provides various reports that you can
generate to communicate project status to stakeholders.
These reports can be customized to display the information
that is relevant to your project.
• In further slides we will see different types of reports.
23
CASH-FLOW REPORT
• A cash flow report is a financial
statement that shows the inflows
and outflows of cash for a
business over a specific period of
time. It provides an overview of
the cash position of a business,
including its ability to generate
cash from operations, investing
activities, and financing activities.
24
RESOURCE OVERVIEW REPORT
• A resource overview report is a
document that provides
information about the resources
that are available or required for a
particular project, activity, or task.
• The purpose of this report is to
give stakeholders an
understanding of the resources
needed to achieve project goals,
including the costs and timeframes
associated with acquiring or
utilizing those resources.
25
CRITICAL TASK REPORT
• The critical task report will
display all tasks that are critical to
the project's completion within the
specified timescale. The report
will show the task name, duration,
start date, finish date, and percent
complete for each critical task.
26
WORK OVERVIEW REPORT
• The work overview report
provides an overview of the work
done in your project, including the
amount of work completed, the
remaining work, and the work yet
to be completed. It also includes a
summary of the total work hours
and the number of tasks completed
within a specific timeframe.
27
CONCLUSION
• Effective planning and scheduling are crucial for the success of any
project.
• They provide valuable insights into various aspects such as schedule,
resources, workforce, Gantt chart, network diagram, team planner,
tracking Gantt, timeline, and task sheet.
• These insights facilitate efficient management of the project by
enabling risk management, time management, and resource
management.
• Relying solely on personal experience for planning and calculation
can be time-consuming and challenging to achieve objectives.
• Project management technology provides comprehensive
management of projects and offers features such as timely, accurate,
rapid, and convenient management.
29
THANK YOU

More Related Content

Similar to Planning & Scheduling 222030008.pptx

Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&tNishant Pandey
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalAMIT PAYAL
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPSagar Kaptan
 
Project Management.pptx
 Project  Management.pptx Project  Management.pptx
Project Management.pptxHafixFarhan
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..pptPedadaSaikumar
 
Project Scope Management in IT Project and Software Project
Project Scope Management in IT Project and Software ProjectProject Scope Management in IT Project and Software Project
Project Scope Management in IT Project and Software ProjectHengSovannarith
 
Use of computer in project management
Use of computer in project managementUse of computer in project management
Use of computer in project managementImran Nawaz
 
CTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxCTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxRaoAnkitYadav1
 
CTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxCTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxRaoAnkitYadav1
 
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdfctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdfGagandeepKaur617299
 
Mujtaba Ahmed Khan Resume (2)
Mujtaba Ahmed Khan Resume (2)Mujtaba Ahmed Khan Resume (2)
Mujtaba Ahmed Khan Resume (2)Mujtaba Khan
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1Ahmad Basim Hamza
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...IRJET Journal
 
Advanced CM_04.09.2022.pptx
Advanced CM_04.09.2022.pptxAdvanced CM_04.09.2022.pptx
Advanced CM_04.09.2022.pptxSiharaGallage
 
Construction project scheduling and quality control
Construction project scheduling and quality controlConstruction project scheduling and quality control
Construction project scheduling and quality controlmonishkumark
 

Similar to Planning & Scheduling 222030008.pptx (20)

Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&t
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Project Management.pptx
 Project  Management.pptx Project  Management.pptx
Project Management.pptx
 
7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt7. (lecture 5) Project scheduling..ppt
7. (lecture 5) Project scheduling..ppt
 
Project Scope Management in IT Project and Software Project
Project Scope Management in IT Project and Software ProjectProject Scope Management in IT Project and Software Project
Project Scope Management in IT Project and Software Project
 
PMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptxPMNM101 Lesson 2 2022.pptx
PMNM101 Lesson 2 2022.pptx
 
sample456.pptx
sample456.pptxsample456.pptx
sample456.pptx
 
Use of computer in project management
Use of computer in project managementUse of computer in project management
Use of computer in project management
 
CTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptxCTM - 02 - Construction Project Planning - Copy.pptx
CTM - 02 - Construction Project Planning - Copy.pptx
 
CTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptxCTM - 02 - Construction Project Planning.pptx
CTM - 02 - Construction Project Planning.pptx
 
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdfctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
ctm-02-constructionprojectplanning-copy-220827180427-63b477c3.pdf
 
Mujtaba Ahmed Khan Resume (2)
Mujtaba Ahmed Khan Resume (2)Mujtaba Ahmed Khan Resume (2)
Mujtaba Ahmed Khan Resume (2)
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1
 
MandC.pdf
MandC.pdfMandC.pdf
MandC.pdf
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 
Advanced CM_04.09.2022.pptx
Advanced CM_04.09.2022.pptxAdvanced CM_04.09.2022.pptx
Advanced CM_04.09.2022.pptx
 
Construction project scheduling and quality control
Construction project scheduling and quality controlConstruction project scheduling and quality control
Construction project scheduling and quality control
 

More from Aditya Mane

CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxAditya Mane
 
Construction Disputes & Settlement.pptx
Construction Disputes & Settlement.pptxConstruction Disputes & Settlement.pptx
Construction Disputes & Settlement.pptxAditya Mane
 
CCCN GROUP ASSIGNMENT No-4pptx.pptx
CCCN GROUP ASSIGNMENT No-4pptx.pptxCCCN GROUP ASSIGNMENT No-4pptx.pptx
CCCN GROUP ASSIGNMENT No-4pptx.pptxAditya Mane
 
CCCN GROUP ASSIGNMENT No-4.pptx
CCCN GROUP ASSIGNMENT No-4.pptxCCCN GROUP ASSIGNMENT No-4.pptx
CCCN GROUP ASSIGNMENT No-4.pptxAditya Mane
 
Contracts PPT.pptx
Contracts PPT.pptxContracts PPT.pptx
Contracts PPT.pptxAditya Mane
 
WBS OF TUNNEL.pptx
WBS OF TUNNEL.pptxWBS OF TUNNEL.pptx
WBS OF TUNNEL.pptxAditya Mane
 
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptxModule 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptxAditya Mane
 
Rehabilitation ppt.pptx
Rehabilitation ppt.pptxRehabilitation ppt.pptx
Rehabilitation ppt.pptxAditya Mane
 
queuingtheory-091005084417-phpapp01 (2).pdf
queuingtheory-091005084417-phpapp01 (2).pdfqueuingtheory-091005084417-phpapp01 (2).pdf
queuingtheory-091005084417-phpapp01 (2).pdfAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 

More from Aditya Mane (11)

CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptx
 
Construction Disputes & Settlement.pptx
Construction Disputes & Settlement.pptxConstruction Disputes & Settlement.pptx
Construction Disputes & Settlement.pptx
 
CCCN GROUP ASSIGNMENT No-4pptx.pptx
CCCN GROUP ASSIGNMENT No-4pptx.pptxCCCN GROUP ASSIGNMENT No-4pptx.pptx
CCCN GROUP ASSIGNMENT No-4pptx.pptx
 
CCCN GROUP ASSIGNMENT No-4.pptx
CCCN GROUP ASSIGNMENT No-4.pptxCCCN GROUP ASSIGNMENT No-4.pptx
CCCN GROUP ASSIGNMENT No-4.pptx
 
Contracts PPT.pptx
Contracts PPT.pptxContracts PPT.pptx
Contracts PPT.pptx
 
WBS OF TUNNEL.pptx
WBS OF TUNNEL.pptxWBS OF TUNNEL.pptx
WBS OF TUNNEL.pptx
 
Module 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptxModule 3.1_Project Planning.pptx
Module 3.1_Project Planning.pptx
 
Rehabilitation ppt.pptx
Rehabilitation ppt.pptxRehabilitation ppt.pptx
Rehabilitation ppt.pptx
 
queuingtheory-091005084417-phpapp01 (2).pdf
queuingtheory-091005084417-phpapp01 (2).pdfqueuingtheory-091005084417-phpapp01 (2).pdf
queuingtheory-091005084417-phpapp01 (2).pdf
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 

Recently uploaded

SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 

Recently uploaded (20)

SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 

Planning & Scheduling 222030008.pptx

  • 1. 01 PRESENTATION ON PLANNING & SCHDEULING OF G+1 BUNGALOW ADITYA . P . MANE M.TECH-CM-222030008 GUIDED BY PROF. (DR) M.M. SHARMA
  • 2. 02 TABLE OF CONTENT 2. BACKGROUND 1. GENERAL INTRODUCTION 6. CONCLUSION 3. PROJECT PLANS 4. PROJECT DESCRIPTION 5. MICROSOFT PROJECT
  • 3. GENERAL INTRODUCTION 03 • India has been experiencing rapid economic growth, averaging at 7.9% for the last six years, making it the world's fastest-developing country. • With the imminent rise of urbanization, there is a significant demand for building houses, and the construction industry, which contributes to 12% of the country's GDP, is growing at a rate of 9% annually. • To meet the need for housing, at least 30 to 36 thousand units need to be built per day for the next seven years. • Housing is a fundamental human need, and as the population continues to grow, there is a pressing need for a more reliable, faster, and sustainable method of construction. • While the aim of constructing buildings in the most economical way remains the same, the construction industry has developed new technologies to meet the demands of modern construction.
  • 4. BACKGROUND • Constructing a building from start to finish can be a challenging and time-consuming task that requires significant effort and investment. • However, it ultimately results in a permanent asset. • Skilled individuals must undertake the systematic process of constructing a residential building. Therefore, it is crucial to take caution during the construction process. • Critical factors, such as the purpose of construction, financial proficiency, and demand for work, should be considered before initiating any building project. • Once the decision to construct a building is made, the planning phase begins. • This presentation will discuss the step-by-step process of building construction from start to finish. 04
  • 10. PROJECT DESCRIPTION 10 • The Total cost of the project is 23,08,337/- • The duration of Project is 141 days. • The Total Built-Up Area for each floor is =167 sqm • The Total Carpet Area for each floor is = 141 sqm • Footing, column, beam, slab, lintel, staircase, chajja, and landing are constructed using M25 grade concrete. • PCC (Plain Cement Concrete) is done using concrete mixed in the proportion of 1:2:4. • RCC (Reinforced Cement Concrete) work for lintel, staircase, chajja, and landing is done using M25 grade concrete.
  • 11. PROJECT DESCRIPTION 11 • Walls are built using 1st class brick with cement mortar mixed in the proportion of 1:5. • Backfilling is done using moorum. • A damp proof course of 25mm thickness is provided and laid using M25 grade cement concrete and bitumen or cement mixed with a waterproofing compound, and the formwork is used for the same. • RMC (Ready-Mix Concrete) is used for huge concreting works if required. • On-site arrangements are made for material storage.
  • 12. 12 MICROSOFT PROJECT 2. STEPS INVOLVED 1.INTRODUCTION 3. WBS OF PROJECT 4. PROJECT WORK 5. REPORTS
  • 13. INTRODUCTION 13 • Microsoft Project is project management software developed by Microsoft • It helps project managers with planning, resource allocation, progress tracking, budget management, and workload analysis • The software creates critical path schedules and allows for resource leveling • Resource definitions can be shared across multiple projects using a shared resource pool.Each resource can have a personalized calendar to define availability • Assignment costs are calculated using resource rates • Project data can be centralized and stored in a database using Microsoft Office Project Server • Microsoft Project Web Access enables authorized users to access and update data remotely
  • 14. 14 WBS OF PROJECT • A work breakdown structure (WBS) is a visual tool used to break down a complex project or task into smaller, more manageable components. The WBS helps to organize the work, assign responsibilities, and track progress.
  • 15. STEPS INVOLVED 15 • Creating a Calendar • Creating Activity & Enter Duration • Entering Predecessors • Creating Resource Sheet • Assigning Resources • Tracking Project • Report Generation
  • 16. 16 PROJECT WORK CALENDARS • Calendars in Microsoft Project define the working and non- working days of a project, and are used to calculate project schedules.
  • 17. 17 ACTIVITY, DURATION & PREDECESSOR • In Microsoft Project, an activity refers to a specific task or work item that needs to be completed as part of a project. Duration refers to the amount of time it will take to complete the activity, while predecessor refers to any activities that must be completed before the current activity can begin.
  • 18. 18 NETWORK DIAGRAM • A network diagram is a visual representation of a network's components and their relationships. It is a graphical representation of a network's topology, which shows how the different components of the network are connected to each other
  • 19. 19 RESOURCE SHEET • Resources refer to anything that can be used to accomplish a task or goal, such as people, equipment, time, money, or materials. In order to complete a project or achieve a goal, it is important to effectively assign resources and manage them throughout the process.
  • 20. 20 GANTT CHART • A Gantt chart is a visual tool used in project management to display a schedule of project tasks and their durations. The chart is composed of horizontal bars representing the tasks, with the length of each bar indicating the duration of the task. The bars are arranged along a timeline, which is typically represented on the chart as a horizontal axis.
  • 21. 21 PROJECT TRACKING & UPDATING • To track your project in Microsoft Project, you need to first set up your project schedule, define a baseline, enter actual progress, compare it to the baseline, and update the project plan accordingly.
  • 22. PROJECT REPORTS 22 • Microsoft Project provides various reports that you can generate to communicate project status to stakeholders. These reports can be customized to display the information that is relevant to your project. • In further slides we will see different types of reports.
  • 23. 23 CASH-FLOW REPORT • A cash flow report is a financial statement that shows the inflows and outflows of cash for a business over a specific period of time. It provides an overview of the cash position of a business, including its ability to generate cash from operations, investing activities, and financing activities.
  • 24. 24 RESOURCE OVERVIEW REPORT • A resource overview report is a document that provides information about the resources that are available or required for a particular project, activity, or task. • The purpose of this report is to give stakeholders an understanding of the resources needed to achieve project goals, including the costs and timeframes associated with acquiring or utilizing those resources.
  • 25. 25 CRITICAL TASK REPORT • The critical task report will display all tasks that are critical to the project's completion within the specified timescale. The report will show the task name, duration, start date, finish date, and percent complete for each critical task.
  • 26. 26 WORK OVERVIEW REPORT • The work overview report provides an overview of the work done in your project, including the amount of work completed, the remaining work, and the work yet to be completed. It also includes a summary of the total work hours and the number of tasks completed within a specific timeframe.
  • 27. 27 CONCLUSION • Effective planning and scheduling are crucial for the success of any project. • They provide valuable insights into various aspects such as schedule, resources, workforce, Gantt chart, network diagram, team planner, tracking Gantt, timeline, and task sheet. • These insights facilitate efficient management of the project by enabling risk management, time management, and resource management. • Relying solely on personal experience for planning and calculation can be time-consuming and challenging to achieve objectives. • Project management technology provides comprehensive management of projects and offers features such as timely, accurate, rapid, and convenient management.