The International Journal Of Engineering And Science (IJES)
||Volume||3 ||Issue|| 3||Pages|| 58-66||2014||
ISSN(e): 2319 – 1813 ISSN(p): 2319 – 1805
www.theijes.com The IJES Page 58
Heuristic Selection for Housing Projects: A Case of Total
Resource Usage
Mee-Edoiye M. Andawei
Department of Civil Engineering Niger Delta University Wilberforce Island Amassoma
Bayelsa State-Nigeria
-------------------------------------------------ABSTRACT---------------------------------------------------------
Resources required for the execution of housing projects fluctuates randomly. This uneven disposition of
resources has resulted to high project cost and avoidable elongation of project duration. Admittedly,
maintaining optimum resource level in housing projects during implementation is one of the major challenges of
project managers. Construction industry practitioners that play leading roles in housing development have
continuously searched for priority rules that are easy to adopt to ensure resource optimality during
construction. This paper highlights the usefulness of total resource usage heuristic in the resource allocation
process that guarantees greater resource utilization in housing projects.
KEYWORDS: Heuristics, resource allocation, housing project, resource utilization
---------------------------------------------------------------------------------------------------------------------------------------
Date of Submission: 03 February 2014 Date of Acceptance: 15 March 2014
---------------------------------------------------------------------------------------------------------------------------------------
I. INTRODUCTION
The shelter needs of man are provided through a series of processes. These processes which involve
several stages, utilizes machines, men of varying skills, materials, space and time. The transformation process,
which utilize raw resources share the characteristics of a project. The project manager is required by function to
plan, organize and control resources of the project activities so that the project is not only completed on
schedule but within the estimated cost and performance limits. The success rate of a project is accordingly
measured by the extent to which these tripartite project criteria of cost, time and performance are achieved. The
knowledge of the effect of project resource level on the project cost throughout the project life therefore remains
fundamental to the successful completion of any project. Notable complexities introduced in the construction
industry by the technological innovations have in the opinion of Spinner (1997) made job co-ordination and
resource allocation practically more difficult. This difficulty has called for the search for better resource
scheduling model(s). Resource scheduling process allocates available resource capacities to jobs, activities and
or customers. It is considered as the most constrained decision in the hierarchy of capacity planning. Resource
scheduling, a time-phased plan, ensures the determination and allocation of resources within the resources’
limits in the best manner. Oxley and Poskitt (1980) opined that resource scheduling is time related and involves
the leveling of project resources. The assumption of unlimited resource availability by network techniques could
no longer hold, they said. This is because the constraining indices of the different resource categories are not the
same at all points of the project during implementation. They rather considered resource availability at the
required quantity and time in the project life as critical. They then concluded by recommending resource
leveling and smoothening as the solution for resource and time constrained situations, respectively.
II. WORK CONTENT
Attempts at ascertaining the level of project resources which should be kept for any given project
activity assumed another dimension with the application of work content methodology. Work content is defined
as the average usage of a particular resource over the entire project duration as determined by the critical path
technique. The reason for this may be due to the fact that work content is a by-product of resource usage, the
main determinant of price of the product. The project completion time in a limited resource situation is also a
function of individual activity time, maximum resource level and intensity of usage of all the resources and
above all the activity selection at each node when more than one activity is due for consideration. With all these
complexities, Akpan (1997) observed that there is bound to be idle resource usage as a result of precedence or
resource constraint or both. In a simplified form, work content may be mathematically expressed as:
Heuristic selection for housing projects…
www.theijes.com The IJES Page 59
2.2/
1






 
PQDcontentwork
n
j
Where Q = Quantity of a particular resource demanded by an activity
D = Duration of each activity
n = Number of activities
P = Project duration
The above calculation is done for all resources and the values so computed are normally raised to the
nearest integer. He contended that this measure of work content is inadequate because a particular activity may
require more resources for a particular type than the calculated values. Secondly, the resources were not
uniformly utilized, as the application of work content seems to imply. He further affirmed that resource levels
based on work content have failed to produce the project duration as dictated by the critical path technique and
that estimates derived thereof are unnecessarily high for some resources. As a result, he adopted random activity
selection heuristic with resource utilization so as to enable the selection of that resource which ought to be
increased to give a reduction in project completion time.
Earlier work by Muggard et al (1974) favored the choice of resource utilization using GERT-Q. GERT-
Q incorporates limited resource availability as well as resource identification and GERT-III-Q [a simulation
model of GERT that allows queue to build up at certain nodes], they were able to identity the ‘bottleneck’
stations as the stations with highest mean waiting time and also a very high percentage utilization. Their results
also revealed that an overall time reduction of 26.2% when a bottleneck station was eliminated with an
additional station in parallel. With the discrete nature of the problem under investigation, it was also found that
two or more resources are likely to have the same utilization percentage. More variables were then introduced to
break the tie each time with an improved result. The different resources were assigned cost, and then discounted
using a continuous flow pattern with discrete discounting of the form:
    3.21
1 0











 
n
N
K
n
n rdttcc
Where cn = Discounted cash flow
N = Number of resources
C (t) = Cash flow
r = Interest rate
When all effort failed to break the tie, “constraining index’ was envisaged. The constraining index is
defined as the number of times the resource requirement has hit the resource ceiling i.e. the time units in which
the resource requirement is equal to maximum resource available and the higher the number, it is assumed, the
more constrained it is. If the index is zero, it indicates that the resource in question is available in sufficient
quantity for the chosen schedule. He then concluded that, this combined approach of resource utilization and
constraining index is more superior model in constrained resource problems.
Constrained resource scheduling
The concept of constrained-resource scheduling is aimed at minimizing the periodic fluctuation of
resource levels. This is done by shifting tasks within their slack allowances and still ensuring that the maximum
resource availability levels at those points are not exceeded (Kernzer 1995). This will undoubtedly lead to
longer project duration. The purpose is to create a smoother distribution of resource demand, supply and usage.
The optimum resource levels of the various resource categories under this situation can be obtained either by
heuristic or mathematical models. Historically, a lot of work has been done in this area of constrained resource
problems, analytical and heuristic abound. Gonguet (1969) utilized linear programming in his model
formulation. He commented that while there is no difficulty in problem formulation, there are a large number of
variables and constraints even for small sized problems and as such, the model has very little practical
application. A similar approach was adopted by Pritsker et al (1969) and Prabhaker (1970). While Davis and
Patterson (1973) approached the problem using a branch and bound algorithm and Balas (1971) and Talbot
(1980) used implicit enumeration and integer programming. They all recorded little improvement and came out
with the same conclusion as Gonguet (1969).There are basically two fundamental approaches to constrained-
resource allocation problems: heuristic and optimization models. While heuristic employs rule of thumb and
produces reasonable and better solution, optimization models seek the best solution through an objective
Heuristic selection for housing projects…
www.theijes.com The IJES Page 60
function and constraint equation(s), which limits its application. I shall dwell on heuristic models in this paper.
Readers interested to know more about optimization models are referred to earlier work of the author.
III. HEURISTIC MODELS
The difficulties with the analytical problem formulation, particularly in constrained-resource situation
gave rise to the renewed interest in heuristic-based procedures Meredith and Mantel (1995). Heuristic models
start with the PERT/CPM schedule and analyze resource usage period-by-period and resource-by-resource. In a
period when the available supply of resources are exceeded, the heuristic examines the tasks in that period and
allocates the scarce resources to them sequentially, according to any given priority rule.
We shall look at six heuristics for the purpose of the paper. They are minimum slack, greatest resource
utilization, greatest resource demand, most possible jobs, shortest processing time and total resource usage
heuristic.Greatest resource utilization rule gives priority to that combination of activities or projects that result in
maximum resource utilization or minimum idle time during each scheduling period. This rule, according to
Meredith and Mantel[1995], was found to be approximately and as effective as the minimum slack rule for
multi-project scheduling, where the criterion used is project slippage. Greatest resource demand heuristic
assigns priority on the basis of total resource requirements, with higher priority given to activities with the
greatest resource demand. Project or task priority is computed as:
4.2
1
,  
m
i
jij rdpriority
dj = duration of activity j
rij = per period requirement of resource i by activity j
m = number of resource types
In most possible jobs heuristic, priority is given to the set of activities that result in the greatest number of
activities being scheduled in any period. This rule requires the solution of 0-1 integer program. In shortest
processing heuristic, time tasks are ordered in terms of duration, with the shortest first. In general, this rule will
maximize the number of tasks that can be completed by a system during some time period.
Minimum slack heuristic, activities are ordered by the amount of slack with the one with the least slack going
first. In this regard, resources would be devoted to critical or near critical activities, delaying those with greater
slack. Delay of an activity uses some of its slack, so the activity will have a better chance of receiving resources
in the next allocation.Random Activity Selection rule, which forms the core of Akpan[2000] but appeared minor
in the earlier work of Davis[1975] selects the activities randomly. In it, parallel activities are randomly selected,
ranked and scheduled. Those activities that cannot be scheduled due to insufficient resources are moved forward
to a later time period. This procedure is repeated and continued until all the activities are scheduled.Total
Resource usage heuristic believes that resources available can be either allocated in full and or in part at any
point of the project. The model envisages that the remainder of any uncompleted activity is carried over to the
next time period and this will form part of the workload for that time period for consideration.
IV. HEURISTIC SELECTION
Works of Fendley (1968), Kurtulus and Davis (1982), and Kurtulus and Davis (1985) focused on the
best heuristic for resource scheduling. While their findings vary somewhat because of their differing
assumptions, the minimum slack rule was found to be the best. This choice according to them was based on the
fact that minimum slack heuristic results to minimum project schedule slippage, the best utilization of facilities
and a minimum total system occupancy time. Other studies were also going on to find a heuristic of general
application. Kelly (1963) in his earlier work did not recommend any single heuristic as the best for all projects
but rather recommended that the best test of goodness of a particular heuristic should be the one, which
produces ‘reasonable’ schedule. Davis (1974) in one of his study tried heuristic in different problems and found
that a particular heuristic may produce a good result in one problem and fail in another. He concluded that in
order to be certain of achieving the best solution, it may be necessary to try different heuristic and to select the
one which may give the optimal or near optimal result. The results recorded so far have increased the range of
uncertainty in the choice of heuristic that should be considered generally suitable and optimal. In efforts to
narrow the region of choice, the idea of random activity selection was proposed by Akpan (2000).
V. METHODOLOGY
The paper adopted a comparative analysis of the six heuristic models to analyze project data of ten
selected projects. Project time overrun and average resource utilization were the two criteria to assess the degree
of optimality of the heuristic models. The average resource utilization is computed by the summation of
resources actually allocated for the project duration divided by the product of resource ceiling and completion
time; while the time overrun is computed by the project duration when the priority is applied less the project
Heuristic selection for housing projects…
www.theijes.com The IJES Page 61
normal duration without the application of the priority rule divided by the actual duration. The result is
multiplied by 100. Mathematically, the average resource utilization is computed using the following formula:
 
1.4%1001




x
nxc
r
ru
ni
i
i
Where
Ru= average resource allocation
n = project completion time using the priority rule
c = resource ceiling
∑[r] = summation of the resources actually allocated weekly
While the project time overrun is computed thus:
2.4100
2
21


x
d
dd
to
Where:
To = project time overrun
d1 = project completion time using the priority rule
d2 = project completion time using critical path.
Project 1
Resources Considered for Allocation: A-Labor and B-Labor
Resource Ceiling: 7units each
Table 1 Project Network details for case 1
Activity Duration Resource Demand
(weeks) A B
1-2 2 3 4
2-3 3 3 4
3-4 2 4 3
4-5 2 3 4
4-6 3 4 4
4-7 2 3 3
5-7 2 4 3
6-7 3 4 3
7-8 3 4 4
8-9 4 3 4
Source: Bayelsa State Housing and Property Development Authority, Nigeria 2004.
Project 2
Resources Considered for Allocation: A-Labor
Resource ceiling: 6units
Table 2 Project Network details for case 2
Activity Duration Resource Demand
A
1-2 3 3
2-3 3 4
3-4 3 3
4-5 3 4
4-6 2 3
5-7 2 3
6-7 3 3
7-8 3 3
Source: Rivers State Housing and Property Development Authority, Nigeria 2000.
Heuristic selection for housing projects…
www.theijes.com The IJES Page 62
Project 3
Resources Considered for Allocation: A-Labor
Resource ceiling: 10units
Table 3 Project Network details for case 3
Activity Duration Resource Demand
A
1-2 3 4
2-3 4 3
3-4 2 4
3-5 3 4
3-6 3 4
4-6 1 2
5-6 3 4
6-7 4 2
Source: Bayelsa State Housing and Property Development Authority, Nigeria 2004.
Project 4
Resources Considered for Allocation: A-Labor
Resource ceiling: 8units
Table 4 Project Network details for case 4
Activity Duration Resource Demand
A
1-2 2 3
2-3 3 3
2-4 2 4
2-5 2 3
3-5 3 4
4-5 2 3
5-6 2 4
6-7 3 4
Source: Lagos State Property Development Corporation Nigeria 2000.
Project 5
Resources Considered for Allocation: A-Labor
Resource Ceiling: 6units each
Table 5 Project Network details for case 5
Activity Duration Resource Demand
A B
1-2 1 4 3
2-3 1 3 4
2-4 2 4 4
3-4 3 2 2
4-5 3 4 2
4-6 2 2 3
5-6 1 2 4
6-7 2 4 4
Source: Lagos State Property Development Corporation Nigeria 2004.
Project 6
Resources Considered for Allocation: A-Labor
Resource Ceiling: 4units each
Heuristic selection for housing projects…
www.theijes.com The IJES Page 63
Table 6 Project Network details for case 6
Activity Duration Resource Demand
A B
1-2 3 3 1
1-3 2 2 3
2-3 1 4 1
2-4 2 2 1
2-5 1 3 2
3-7 3 4 1
4-6 2 3 3
5-7 3 2 1
6-7 1 3 2
7-8 1 3 3
Source: Lagos State Property Development Corporation 2000.
Project 7
Resources Considered for Allocation: A-Labor
Resource Ceiling: 5units
Table Project Network details for case 7
Activity Duration Resource Demand
A
1-2 1 4
2-3 2 3
2-4 3 1
3-5 2 2
3-6 1 2
4-6 1 3
5-7 1 4
6-7 2 2
7-8 1 3
Source: Lagos State Property Development Corporation Nigeria 2004.
Project 8
Resources Considered for Allocation: A-Labor
Resource Ceiling: 4units
Table 8 Project Network details for case 8
Activity Duration Resource Demand
A
1-2 2 3
1-3 1 2
1-4 3 3
2-4 1 2
2-6 2 4
3-4 2 1
3-7 3 2
3-5 4 3
6-7 1 2
6-8 2 4
5-8 1 3
7-8 3 3
4-7 4 3
Source: Lagos State Property Development Corporation Nigeria 2004.
Heuristic selection for housing projects…
www.theijes.com The IJES Page 64
Project 9
Resources Considered for Allocation: A-Labor
Resource Ceiling: 6units
Table 9 Project Network details for case 9
Activity Duration Resource Demand
A
1-2 2 4
1-3 3 2
2-4 3 3
2-3 4 2
4-5 2 3
3-5 3 4
4-6 3 4
5-6 2 3
Source: Lagos State Property Development Corporation Nigeria 2004.
Project 10
Resources Considered for Allocation: A-Labor
Resource Ceiling: 5units
Table 10 Project Network details for case 10
Activity Duration Resource Demand
A
1-2 2 4
1-3 3 2
2-4 3 3
2-3 4 2
4-5 2 3
3-5 3 4
4-6 3 4
5-6 2 3
Source: Bayelsa State Housing and Property Development Authority, Nigeria 2004.
The outcome of the allocation for the six heuristics are as tabulated below.
Table 11 Summary of Resource Utilization Level
Case
Studies
Heuristic Models
RAS MSL SPT TRU GRD GRU
1 59% 59% 54% 62% 54% 54%
2 60% 60% 60% 67% 60% 60%
3 46% 46% 46% 46% 46% 46%
4 62% 55% 49% 64% 49% 49%
5 71% 71% 71% 71% 71% 71%
6 84% 79% 79% 100% 79% 79%
7 73% 73% 73% 73% 73% 73%
8 81% 78% 78% 100% 78% 78%
9 74% 70% 74% 90% 70% 70%
10 84% 74% 79% 95% 74% 74%
*ras- random activity selection *msl -minimum slack *spt- shortest processing time
*tru- total resource usage *grd- greatest resource demand *gru- greatest resource usage
Heuristic selection for housing projects…
www.theijes.com The IJES Page 65
Table 12 Summary of Time Overrun Level
Case
Studies
Heuristic Models
RAS MSL SPT TRU GRD GRU
1 10% 10% 20% 5% 20% 20%
2 18% 18% 18% 6% 18% 18%
3 0 0 0 0 0 0
4 0 8% 15% 0 15% 15%
5 0 0 0 0 0 0
6 78% 89% 89% 56% 89% 89%
7 13% 13% 13% 13% 13% 13%
8 150% 160% 160% 100% 160% 160%
9 36% 46% 36% 18% 46% 46%
10 46% 64% 55% 36% 64% 64%
The results highlighted the behavioral pattern of the heuristic models under varying project demand/availability.
The outcome of the allocation for the six heuristics are as tabulated below.
Table 11 Summary of Resource Utilization Level
Case
Studies
Heuristic Models
RAS MSL SPT TRU GRD GRU
1 59% 59% 54% 62% 54% 54%
2 60% 60% 60% 67% 60% 60%
3 46% 46% 46% 46% 46% 46%
4 62% 55% 49% 64% 49% 49%
5 71% 71% 71% 71% 71% 71%
6 84% 79% 79% 100% 79% 79%
7 73% 73% 73% 73% 73% 73%
8 81% 78% 78% 100% 78% 78%
9 74% 70% 74% 90% 70% 70%
10 84% 74% 79% 95% 74% 74%
*ras- random activity selection *msl -minimum slack *spt- shortest processing time
*tru- total resource usage *grd- greatest resource demand *gru- greatest resource usage
Table 12 Summary of Time Overrun Level
Case
Studies
Heuristic Models
RAS MSL SPT TRU GRD GRU
1 10% 10% 20% 5% 20% 20%
2 18% 18% 18% 6% 18% 18%
3 0 0 0 0 0 0
4 0 8% 15% 0 15% 15%
5 0 0 0 0 0 0
6 78% 89% 89% 56% 89% 89%
7 13% 13% 13% 13% 13% 13%
8 150% 160% 160% 100% 160% 160%
9 36% 46% 36% 18% 46% 46%
10 46% 64% 55% 36% 64% 64%
The results highlighted the behavioral pattern of the heuristic models under varying project demand/availability.
VI. DISCUSSION OF RESULTS
From the above summary allocation process, random activity selection, minimum slack, shortest
processing time, greatest resource usage and greatest resource demand allocate resource to project activities that
can be 100% completed and not to activities that can be completed in part at any time period of the project. This
implies that resources are allocated to activities only when resource supply is equal or more than resource
demand. However, the Total Resource Usage heuristic believes that resources available can be either allocated
Heuristic selection for housing projects…
www.theijes.com The IJES Page 66
in full or in part. The model envisages that the remainder of any uncompleted activity is carried over to the next
time period and this will form part of the workload for that time period for resource Out of the six heuristics,
total resource usage gave the highest resource utilization and least project time overrun and is therefore
adjudged the most optimal.
VII. CONCLUSION
Resource allocation under a resource-limited situation has been a source of concern, particularly, in the
construction industry. Efforts at optimizing project resources during implementation stages of projects are
noticeably numerous. The superiority of heuristic models and indeed total resource usage heuristic over
optimization models in allocating project resources is indeed commendable. Its application in the housing sub-
sector would certainly reduce resource wastage.
REFERENCE
[1] A.B. Pritsker, L.J. Walters and P.M. Wolfe, Multi-project scheduling with limited resources; a zero-one programming approach,
Management Science, 16, 1969, 93-108.
[2] C.M. Popescu and C. Charoenngam, Project planning, scheduling and control in construction. an encyclopedia of terms and
applications,(New York: Wiley, 1995).
[3] E. Balas, Project scheduling with resources constraints (in) Applications of Mathematical Programming Techniques, 1970, 187-200.
[4] E.O.P Akpan, Priority rules in project scheduling: a case for random activity selection, Journal of Production Planning and
Control, 11(2), 2000, 165-170.
[5] E.O.P Akpan, Optimum resource determination for project scheduling. International Journal of Production Planning and Control,
8(5), 1997, 402-468.
[6] E.W. Davis and J.H Patterson, A comparison of heuristic and optimum solutions in resource constrained project scheduling.
Management Science, 21(6), 1975, 718-722.
[7] E.W. Davis, Networks resource allocation, Industrial Engineering, 4(4), 1974, 22-32.
[8] F.B. Talbot, Project scheduling with resource-duration interaction: The Non-preemptive case, Working paper No. 200 Graduate
School of Business Administration, University of Michigan, 1980, January.
I. Kurtulus and E.W. Davis, Multi-project scheduling, analysis of project performance, IEE Transactions in Engineering
Management, 1985, March.
[9] Kurtulus and E.W. Davis, Multi-project scheduling categorization of heuristic rules performance. Management Science, 28(2),
1982, 161-172.
[10] J.E. Kelly, The critical path method, resource planning and scheduling. Industrial scheduling (Ed) by Muth and Thompson
(Englewood cliffs, N.J. Prentice-Hall, 1963).
[11] J.H. Patterson, Alternative methods of project scheduling with limited resources, Naval research logistic quarterly, 1973,
December.
[12] Kernzer Harold, Project management: a systems approach to planning, scheduling and controlling (New York, Van Nostrand
Reinhold, 1995).
[13] L.G. Fendley, Towards the development of a complete multi-project scheduling system, Journal of Industrial Engineering, 19(10),
1968, 505-515.
[14] L. Gonguet, L(1969). Comparison of three heuristic procedures for allocating resources and producing schedules (in) Project
planning by network models, (North Holland, Amsterdam, 1969).
[15] M.P. Spinner, Project management principles and practices. (New Jersey, Prentice Hall 1997).
[16] R.J. Meredith and S. J. Mantel, Project management: a managerial approach,(New York: John Willey and sons, 1995).
[17] T. Prabhaker, Resource allocation/leveling in engineering construction projects: A paper, 37th
meeting of ORSA, 1970, 20-22.

More Related Content

What's hot

Time Cost Trade off Optimization Using Harmony Search and Monte-Carlo Method
Time Cost Trade off Optimization Using Harmony Search and Monte-Carlo Method Time Cost Trade off Optimization Using Harmony Search and Monte-Carlo Method
Time Cost Trade off Optimization Using Harmony Search and Monte-Carlo Method Mohammad Lemar ZALMAİ
 
Transmisison & generation_expansion_planning_ijepes-d-13-00427_r1_accepted
Transmisison & generation_expansion_planning_ijepes-d-13-00427_r1_acceptedTransmisison & generation_expansion_planning_ijepes-d-13-00427_r1_accepted
Transmisison & generation_expansion_planning_ijepes-d-13-00427_r1_acceptedNeeraj Gupta
 
AN INTEGER-LINEAR ALGORITHM FOR OPTIMIZING ENERGY EFFICIENCY IN DATA CENTERS
AN INTEGER-LINEAR ALGORITHM FOR OPTIMIZING ENERGY EFFICIENCY IN DATA CENTERSAN INTEGER-LINEAR ALGORITHM FOR OPTIMIZING ENERGY EFFICIENCY IN DATA CENTERS
AN INTEGER-LINEAR ALGORITHM FOR OPTIMIZING ENERGY EFFICIENCY IN DATA CENTERSijfcstjournal
 
Max Min Fair Scheduling Algorithm using In Grid Scheduling with Load Balancing
Max Min Fair Scheduling Algorithm using In Grid Scheduling with Load Balancing Max Min Fair Scheduling Algorithm using In Grid Scheduling with Load Balancing
Max Min Fair Scheduling Algorithm using In Grid Scheduling with Load Balancing IJORCS
 
Surveying, Planning and Scheduling For A Hill Road Work at Kalrayan Hills by ...
Surveying, Planning and Scheduling For A Hill Road Work at Kalrayan Hills by ...Surveying, Planning and Scheduling For A Hill Road Work at Kalrayan Hills by ...
Surveying, Planning and Scheduling For A Hill Road Work at Kalrayan Hills by ...IJSRD
 
Optimization of Resource Allocation Strategy Using Modified PSO in Cloud Envi...
Optimization of Resource Allocation Strategy Using Modified PSO in Cloud Envi...Optimization of Resource Allocation Strategy Using Modified PSO in Cloud Envi...
Optimization of Resource Allocation Strategy Using Modified PSO in Cloud Envi...IJCSIS Research Publications
 
OPTIMIZED RESOURCE PROVISIONING METHOD FOR COMPUTATIONAL GRID
OPTIMIZED RESOURCE PROVISIONING METHOD FOR COMPUTATIONAL GRID OPTIMIZED RESOURCE PROVISIONING METHOD FOR COMPUTATIONAL GRID
OPTIMIZED RESOURCE PROVISIONING METHOD FOR COMPUTATIONAL GRID ijgca
 
Multiple dag applications
Multiple dag applicationsMultiple dag applications
Multiple dag applicationscsandit
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)theijes
 
High-Performance Concrete Compressive Strength Prediction Based Weighted Supp...
High-Performance Concrete Compressive Strength Prediction Based Weighted Supp...High-Performance Concrete Compressive Strength Prediction Based Weighted Supp...
High-Performance Concrete Compressive Strength Prediction Based Weighted Supp...IJERA Editor
 
2use of dss in ems to reduce responce time
2use of dss in ems to reduce responce time2use of dss in ems to reduce responce time
2use of dss in ems to reduce responce timeosaleem0123
 
STUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHM
STUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHMSTUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHM
STUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHMAvay Minni
 
Sharing of cluster resources among multiple Workflow Applications
Sharing of cluster resources among multiple Workflow ApplicationsSharing of cluster resources among multiple Workflow Applications
Sharing of cluster resources among multiple Workflow Applicationsijcsit
 

What's hot (17)

Journal paper 1
Journal paper 1Journal paper 1
Journal paper 1
 
Time Cost Trade off Optimization Using Harmony Search and Monte-Carlo Method
Time Cost Trade off Optimization Using Harmony Search and Monte-Carlo Method Time Cost Trade off Optimization Using Harmony Search and Monte-Carlo Method
Time Cost Trade off Optimization Using Harmony Search and Monte-Carlo Method
 
Transmisison & generation_expansion_planning_ijepes-d-13-00427_r1_accepted
Transmisison & generation_expansion_planning_ijepes-d-13-00427_r1_acceptedTransmisison & generation_expansion_planning_ijepes-d-13-00427_r1_accepted
Transmisison & generation_expansion_planning_ijepes-d-13-00427_r1_accepted
 
AN INTEGER-LINEAR ALGORITHM FOR OPTIMIZING ENERGY EFFICIENCY IN DATA CENTERS
AN INTEGER-LINEAR ALGORITHM FOR OPTIMIZING ENERGY EFFICIENCY IN DATA CENTERSAN INTEGER-LINEAR ALGORITHM FOR OPTIMIZING ENERGY EFFICIENCY IN DATA CENTERS
AN INTEGER-LINEAR ALGORITHM FOR OPTIMIZING ENERGY EFFICIENCY IN DATA CENTERS
 
Max Min Fair Scheduling Algorithm using In Grid Scheduling with Load Balancing
Max Min Fair Scheduling Algorithm using In Grid Scheduling with Load Balancing Max Min Fair Scheduling Algorithm using In Grid Scheduling with Load Balancing
Max Min Fair Scheduling Algorithm using In Grid Scheduling with Load Balancing
 
Surveying, Planning and Scheduling For A Hill Road Work at Kalrayan Hills by ...
Surveying, Planning and Scheduling For A Hill Road Work at Kalrayan Hills by ...Surveying, Planning and Scheduling For A Hill Road Work at Kalrayan Hills by ...
Surveying, Planning and Scheduling For A Hill Road Work at Kalrayan Hills by ...
 
Optimization of Resource Allocation Strategy Using Modified PSO in Cloud Envi...
Optimization of Resource Allocation Strategy Using Modified PSO in Cloud Envi...Optimization of Resource Allocation Strategy Using Modified PSO in Cloud Envi...
Optimization of Resource Allocation Strategy Using Modified PSO in Cloud Envi...
 
OPTIMIZED RESOURCE PROVISIONING METHOD FOR COMPUTATIONAL GRID
OPTIMIZED RESOURCE PROVISIONING METHOD FOR COMPUTATIONAL GRID OPTIMIZED RESOURCE PROVISIONING METHOD FOR COMPUTATIONAL GRID
OPTIMIZED RESOURCE PROVISIONING METHOD FOR COMPUTATIONAL GRID
 
Korean Text mining
Korean Text miningKorean Text mining
Korean Text mining
 
C1803052327
C1803052327C1803052327
C1803052327
 
Bulk transfer scheduling and path reservations in research networks
Bulk transfer scheduling and path reservations in research networksBulk transfer scheduling and path reservations in research networks
Bulk transfer scheduling and path reservations in research networks
 
Multiple dag applications
Multiple dag applicationsMultiple dag applications
Multiple dag applications
 
The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)The International Journal of Engineering and Science (The IJES)
The International Journal of Engineering and Science (The IJES)
 
High-Performance Concrete Compressive Strength Prediction Based Weighted Supp...
High-Performance Concrete Compressive Strength Prediction Based Weighted Supp...High-Performance Concrete Compressive Strength Prediction Based Weighted Supp...
High-Performance Concrete Compressive Strength Prediction Based Weighted Supp...
 
2use of dss in ems to reduce responce time
2use of dss in ems to reduce responce time2use of dss in ems to reduce responce time
2use of dss in ems to reduce responce time
 
STUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHM
STUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHMSTUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHM
STUDY ON PROJECT MANAGEMENT THROUGH GENETIC ALGORITHM
 
Sharing of cluster resources among multiple Workflow Applications
Sharing of cluster resources among multiple Workflow ApplicationsSharing of cluster resources among multiple Workflow Applications
Sharing of cluster resources among multiple Workflow Applications
 

Viewers also liked

I03202074078
I03202074078I03202074078
I03202074078theijes
 
F03302045050
F03302045050F03302045050
F03302045050theijes
 
B032107011
B032107011B032107011
B032107011theijes
 
C0324011015
C0324011015C0324011015
C0324011015theijes
 
F021203036039
F021203036039F021203036039
F021203036039theijes
 
D021201031040
D021201031040D021201031040
D021201031040theijes
 
J03202079086
J03202079086 J03202079086
J03202079086 theijes
 
D03310019025
D03310019025D03310019025
D03310019025theijes
 
C03202012017
C03202012017C03202012017
C03202012017theijes
 
I021201065070
I021201065070I021201065070
I021201065070theijes
 
A03210106
A03210106A03210106
A03210106theijes
 
H03202051073
H03202051073H03202051073
H03202051073theijes
 
C0212014018
C0212014018C0212014018
C0212014018theijes
 
E021203026035
E021203026035E021203026035
E021203026035theijes
 
C021201024030
C021201024030C021201024030
C021201024030theijes
 
A02120201010
A02120201010A02120201010
A02120201010theijes
 
G0324036043
G0324036043G0324036043
G0324036043theijes
 
A0331001008
A0331001008A0331001008
A0331001008theijes
 
G032030056067
G032030056067G032030056067
G032030056067theijes
 

Viewers also liked (19)

I03202074078
I03202074078I03202074078
I03202074078
 
F03302045050
F03302045050F03302045050
F03302045050
 
B032107011
B032107011B032107011
B032107011
 
C0324011015
C0324011015C0324011015
C0324011015
 
F021203036039
F021203036039F021203036039
F021203036039
 
D021201031040
D021201031040D021201031040
D021201031040
 
J03202079086
J03202079086 J03202079086
J03202079086
 
D03310019025
D03310019025D03310019025
D03310019025
 
C03202012017
C03202012017C03202012017
C03202012017
 
I021201065070
I021201065070I021201065070
I021201065070
 
A03210106
A03210106A03210106
A03210106
 
H03202051073
H03202051073H03202051073
H03202051073
 
C0212014018
C0212014018C0212014018
C0212014018
 
E021203026035
E021203026035E021203026035
E021203026035
 
C021201024030
C021201024030C021201024030
C021201024030
 
A02120201010
A02120201010A02120201010
A02120201010
 
G0324036043
G0324036043G0324036043
G0324036043
 
A0331001008
A0331001008A0331001008
A0331001008
 
G032030056067
G032030056067G032030056067
G032030056067
 

Similar to H03302058066

Applicability of heuristic approach in planning and scheduling project
Applicability of heuristic approach in planning and scheduling projectApplicability of heuristic approach in planning and scheduling project
Applicability of heuristic approach in planning and scheduling projectAlexander Decker
 
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case StudyTime-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Studyijceronline
 
ABIJU_Software _project _scheduling.pptx
ABIJU_Software _project _scheduling.pptxABIJU_Software _project _scheduling.pptx
ABIJU_Software _project _scheduling.pptxBVimala1
 
Implementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise BuildingImplementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise BuildingIJERA Editor
 
Optimized Resource Provisioning Method for Computational Grid
Optimized Resource Provisioning Method for Computational GridOptimized Resource Provisioning Method for Computational Grid
Optimized Resource Provisioning Method for Computational Gridijgca
 
A Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To ConcreteA Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To ConcreteDawn Cook
 
A heuristic project buffer management algorithm in the scheduling phase of a...
A heuristic project buffer management algorithm in the  scheduling phase of a...A heuristic project buffer management algorithm in the  scheduling phase of a...
A heuristic project buffer management algorithm in the scheduling phase of a...ShakibZohrevandi1
 
I0313048051
I0313048051I0313048051
I0313048051theijes
 
Surveying, Planning and Scheduling For A Hill Road Work at Kalrayan Hills by ...
Surveying, Planning and Scheduling For A Hill Road Work at Kalrayan Hills by ...Surveying, Planning and Scheduling For A Hill Road Work at Kalrayan Hills by ...
Surveying, Planning and Scheduling For A Hill Road Work at Kalrayan Hills by ...IJSRD
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPSagar Kaptan
 
Understanding the effect of Financing Variability Using Chance- Constrained A...
Understanding the effect of Financing Variability Using Chance- Constrained A...Understanding the effect of Financing Variability Using Chance- Constrained A...
Understanding the effect of Financing Variability Using Chance- Constrained A...IRJET Journal
 
Complex Project Crashing Algorithm
Complex Project Crashing AlgorithmComplex Project Crashing Algorithm
Complex Project Crashing AlgorithmIOSR Journals
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET Journal
 
Procurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projectsProcurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projectseSAT Publishing House
 
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisC:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisInSync Conference
 
Ieeepro techno solutions 2014 ieee java project - deadline based resource p...
Ieeepro techno solutions   2014 ieee java project - deadline based resource p...Ieeepro techno solutions   2014 ieee java project - deadline based resource p...
Ieeepro techno solutions 2014 ieee java project - deadline based resource p...hemanthbbc
 

Similar to H03302058066 (20)

Applicability of heuristic approach in planning and scheduling project
Applicability of heuristic approach in planning and scheduling projectApplicability of heuristic approach in planning and scheduling project
Applicability of heuristic approach in planning and scheduling project
 
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case StudyTime-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
Time-Cost Trade-Off Analysis in a Construction Project Problem: Case Study
 
Isarc2007 4.3 2-065
Isarc2007 4.3 2-065Isarc2007 4.3 2-065
Isarc2007 4.3 2-065
 
ABIJU_Software _project _scheduling.pptx
ABIJU_Software _project _scheduling.pptxABIJU_Software _project _scheduling.pptx
ABIJU_Software _project _scheduling.pptx
 
Implementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise BuildingImplementation of Line of Balance Method for Scheduling High-rise Building
Implementation of Line of Balance Method for Scheduling High-rise Building
 
Optimized Resource Provisioning Method for Computational Grid
Optimized Resource Provisioning Method for Computational GridOptimized Resource Provisioning Method for Computational Grid
Optimized Resource Provisioning Method for Computational Grid
 
A Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To ConcreteA Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To Concrete
 
A heuristic project buffer management algorithm in the scheduling phase of a...
A heuristic project buffer management algorithm in the  scheduling phase of a...A heuristic project buffer management algorithm in the  scheduling phase of a...
A heuristic project buffer management algorithm in the scheduling phase of a...
 
I0313048051
I0313048051I0313048051
I0313048051
 
Surveying, Planning and Scheduling For A Hill Road Work at Kalrayan Hills by ...
Surveying, Planning and Scheduling For A Hill Road Work at Kalrayan Hills by ...Surveying, Planning and Scheduling For A Hill Road Work at Kalrayan Hills by ...
Surveying, Planning and Scheduling For A Hill Road Work at Kalrayan Hills by ...
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
Understanding the effect of Financing Variability Using Chance- Constrained A...
Understanding the effect of Financing Variability Using Chance- Constrained A...Understanding the effect of Financing Variability Using Chance- Constrained A...
Understanding the effect of Financing Variability Using Chance- Constrained A...
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
Complex Project Crashing Algorithm
Complex Project Crashing AlgorithmComplex Project Crashing Algorithm
Complex Project Crashing Algorithm
 
B1303020508
B1303020508B1303020508
B1303020508
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
Procurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projectsProcurement principle towards effective management of construction projects
Procurement principle towards effective management of construction projects
 
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisC:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
 
Duration
DurationDuration
Duration
 
Ieeepro techno solutions 2014 ieee java project - deadline based resource p...
Ieeepro techno solutions   2014 ieee java project - deadline based resource p...Ieeepro techno solutions   2014 ieee java project - deadline based resource p...
Ieeepro techno solutions 2014 ieee java project - deadline based resource p...
 

Recently uploaded

chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 

Recently uploaded (20)

chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 

H03302058066

  • 1. The International Journal Of Engineering And Science (IJES) ||Volume||3 ||Issue|| 3||Pages|| 58-66||2014|| ISSN(e): 2319 – 1813 ISSN(p): 2319 – 1805 www.theijes.com The IJES Page 58 Heuristic Selection for Housing Projects: A Case of Total Resource Usage Mee-Edoiye M. Andawei Department of Civil Engineering Niger Delta University Wilberforce Island Amassoma Bayelsa State-Nigeria -------------------------------------------------ABSTRACT--------------------------------------------------------- Resources required for the execution of housing projects fluctuates randomly. This uneven disposition of resources has resulted to high project cost and avoidable elongation of project duration. Admittedly, maintaining optimum resource level in housing projects during implementation is one of the major challenges of project managers. Construction industry practitioners that play leading roles in housing development have continuously searched for priority rules that are easy to adopt to ensure resource optimality during construction. This paper highlights the usefulness of total resource usage heuristic in the resource allocation process that guarantees greater resource utilization in housing projects. KEYWORDS: Heuristics, resource allocation, housing project, resource utilization --------------------------------------------------------------------------------------------------------------------------------------- Date of Submission: 03 February 2014 Date of Acceptance: 15 March 2014 --------------------------------------------------------------------------------------------------------------------------------------- I. INTRODUCTION The shelter needs of man are provided through a series of processes. These processes which involve several stages, utilizes machines, men of varying skills, materials, space and time. The transformation process, which utilize raw resources share the characteristics of a project. The project manager is required by function to plan, organize and control resources of the project activities so that the project is not only completed on schedule but within the estimated cost and performance limits. The success rate of a project is accordingly measured by the extent to which these tripartite project criteria of cost, time and performance are achieved. The knowledge of the effect of project resource level on the project cost throughout the project life therefore remains fundamental to the successful completion of any project. Notable complexities introduced in the construction industry by the technological innovations have in the opinion of Spinner (1997) made job co-ordination and resource allocation practically more difficult. This difficulty has called for the search for better resource scheduling model(s). Resource scheduling process allocates available resource capacities to jobs, activities and or customers. It is considered as the most constrained decision in the hierarchy of capacity planning. Resource scheduling, a time-phased plan, ensures the determination and allocation of resources within the resources’ limits in the best manner. Oxley and Poskitt (1980) opined that resource scheduling is time related and involves the leveling of project resources. The assumption of unlimited resource availability by network techniques could no longer hold, they said. This is because the constraining indices of the different resource categories are not the same at all points of the project during implementation. They rather considered resource availability at the required quantity and time in the project life as critical. They then concluded by recommending resource leveling and smoothening as the solution for resource and time constrained situations, respectively. II. WORK CONTENT Attempts at ascertaining the level of project resources which should be kept for any given project activity assumed another dimension with the application of work content methodology. Work content is defined as the average usage of a particular resource over the entire project duration as determined by the critical path technique. The reason for this may be due to the fact that work content is a by-product of resource usage, the main determinant of price of the product. The project completion time in a limited resource situation is also a function of individual activity time, maximum resource level and intensity of usage of all the resources and above all the activity selection at each node when more than one activity is due for consideration. With all these complexities, Akpan (1997) observed that there is bound to be idle resource usage as a result of precedence or resource constraint or both. In a simplified form, work content may be mathematically expressed as:
  • 2. Heuristic selection for housing projects… www.theijes.com The IJES Page 59 2.2/ 1         PQDcontentwork n j Where Q = Quantity of a particular resource demanded by an activity D = Duration of each activity n = Number of activities P = Project duration The above calculation is done for all resources and the values so computed are normally raised to the nearest integer. He contended that this measure of work content is inadequate because a particular activity may require more resources for a particular type than the calculated values. Secondly, the resources were not uniformly utilized, as the application of work content seems to imply. He further affirmed that resource levels based on work content have failed to produce the project duration as dictated by the critical path technique and that estimates derived thereof are unnecessarily high for some resources. As a result, he adopted random activity selection heuristic with resource utilization so as to enable the selection of that resource which ought to be increased to give a reduction in project completion time. Earlier work by Muggard et al (1974) favored the choice of resource utilization using GERT-Q. GERT- Q incorporates limited resource availability as well as resource identification and GERT-III-Q [a simulation model of GERT that allows queue to build up at certain nodes], they were able to identity the ‘bottleneck’ stations as the stations with highest mean waiting time and also a very high percentage utilization. Their results also revealed that an overall time reduction of 26.2% when a bottleneck station was eliminated with an additional station in parallel. With the discrete nature of the problem under investigation, it was also found that two or more resources are likely to have the same utilization percentage. More variables were then introduced to break the tie each time with an improved result. The different resources were assigned cost, and then discounted using a continuous flow pattern with discrete discounting of the form:     3.21 1 0              n N K n n rdttcc Where cn = Discounted cash flow N = Number of resources C (t) = Cash flow r = Interest rate When all effort failed to break the tie, “constraining index’ was envisaged. The constraining index is defined as the number of times the resource requirement has hit the resource ceiling i.e. the time units in which the resource requirement is equal to maximum resource available and the higher the number, it is assumed, the more constrained it is. If the index is zero, it indicates that the resource in question is available in sufficient quantity for the chosen schedule. He then concluded that, this combined approach of resource utilization and constraining index is more superior model in constrained resource problems. Constrained resource scheduling The concept of constrained-resource scheduling is aimed at minimizing the periodic fluctuation of resource levels. This is done by shifting tasks within their slack allowances and still ensuring that the maximum resource availability levels at those points are not exceeded (Kernzer 1995). This will undoubtedly lead to longer project duration. The purpose is to create a smoother distribution of resource demand, supply and usage. The optimum resource levels of the various resource categories under this situation can be obtained either by heuristic or mathematical models. Historically, a lot of work has been done in this area of constrained resource problems, analytical and heuristic abound. Gonguet (1969) utilized linear programming in his model formulation. He commented that while there is no difficulty in problem formulation, there are a large number of variables and constraints even for small sized problems and as such, the model has very little practical application. A similar approach was adopted by Pritsker et al (1969) and Prabhaker (1970). While Davis and Patterson (1973) approached the problem using a branch and bound algorithm and Balas (1971) and Talbot (1980) used implicit enumeration and integer programming. They all recorded little improvement and came out with the same conclusion as Gonguet (1969).There are basically two fundamental approaches to constrained- resource allocation problems: heuristic and optimization models. While heuristic employs rule of thumb and produces reasonable and better solution, optimization models seek the best solution through an objective
  • 3. Heuristic selection for housing projects… www.theijes.com The IJES Page 60 function and constraint equation(s), which limits its application. I shall dwell on heuristic models in this paper. Readers interested to know more about optimization models are referred to earlier work of the author. III. HEURISTIC MODELS The difficulties with the analytical problem formulation, particularly in constrained-resource situation gave rise to the renewed interest in heuristic-based procedures Meredith and Mantel (1995). Heuristic models start with the PERT/CPM schedule and analyze resource usage period-by-period and resource-by-resource. In a period when the available supply of resources are exceeded, the heuristic examines the tasks in that period and allocates the scarce resources to them sequentially, according to any given priority rule. We shall look at six heuristics for the purpose of the paper. They are minimum slack, greatest resource utilization, greatest resource demand, most possible jobs, shortest processing time and total resource usage heuristic.Greatest resource utilization rule gives priority to that combination of activities or projects that result in maximum resource utilization or minimum idle time during each scheduling period. This rule, according to Meredith and Mantel[1995], was found to be approximately and as effective as the minimum slack rule for multi-project scheduling, where the criterion used is project slippage. Greatest resource demand heuristic assigns priority on the basis of total resource requirements, with higher priority given to activities with the greatest resource demand. Project or task priority is computed as: 4.2 1 ,   m i jij rdpriority dj = duration of activity j rij = per period requirement of resource i by activity j m = number of resource types In most possible jobs heuristic, priority is given to the set of activities that result in the greatest number of activities being scheduled in any period. This rule requires the solution of 0-1 integer program. In shortest processing heuristic, time tasks are ordered in terms of duration, with the shortest first. In general, this rule will maximize the number of tasks that can be completed by a system during some time period. Minimum slack heuristic, activities are ordered by the amount of slack with the one with the least slack going first. In this regard, resources would be devoted to critical or near critical activities, delaying those with greater slack. Delay of an activity uses some of its slack, so the activity will have a better chance of receiving resources in the next allocation.Random Activity Selection rule, which forms the core of Akpan[2000] but appeared minor in the earlier work of Davis[1975] selects the activities randomly. In it, parallel activities are randomly selected, ranked and scheduled. Those activities that cannot be scheduled due to insufficient resources are moved forward to a later time period. This procedure is repeated and continued until all the activities are scheduled.Total Resource usage heuristic believes that resources available can be either allocated in full and or in part at any point of the project. The model envisages that the remainder of any uncompleted activity is carried over to the next time period and this will form part of the workload for that time period for consideration. IV. HEURISTIC SELECTION Works of Fendley (1968), Kurtulus and Davis (1982), and Kurtulus and Davis (1985) focused on the best heuristic for resource scheduling. While their findings vary somewhat because of their differing assumptions, the minimum slack rule was found to be the best. This choice according to them was based on the fact that minimum slack heuristic results to minimum project schedule slippage, the best utilization of facilities and a minimum total system occupancy time. Other studies were also going on to find a heuristic of general application. Kelly (1963) in his earlier work did not recommend any single heuristic as the best for all projects but rather recommended that the best test of goodness of a particular heuristic should be the one, which produces ‘reasonable’ schedule. Davis (1974) in one of his study tried heuristic in different problems and found that a particular heuristic may produce a good result in one problem and fail in another. He concluded that in order to be certain of achieving the best solution, it may be necessary to try different heuristic and to select the one which may give the optimal or near optimal result. The results recorded so far have increased the range of uncertainty in the choice of heuristic that should be considered generally suitable and optimal. In efforts to narrow the region of choice, the idea of random activity selection was proposed by Akpan (2000). V. METHODOLOGY The paper adopted a comparative analysis of the six heuristic models to analyze project data of ten selected projects. Project time overrun and average resource utilization were the two criteria to assess the degree of optimality of the heuristic models. The average resource utilization is computed by the summation of resources actually allocated for the project duration divided by the product of resource ceiling and completion time; while the time overrun is computed by the project duration when the priority is applied less the project
  • 4. Heuristic selection for housing projects… www.theijes.com The IJES Page 61 normal duration without the application of the priority rule divided by the actual duration. The result is multiplied by 100. Mathematically, the average resource utilization is computed using the following formula:   1.4%1001     x nxc r ru ni i i Where Ru= average resource allocation n = project completion time using the priority rule c = resource ceiling ∑[r] = summation of the resources actually allocated weekly While the project time overrun is computed thus: 2.4100 2 21   x d dd to Where: To = project time overrun d1 = project completion time using the priority rule d2 = project completion time using critical path. Project 1 Resources Considered for Allocation: A-Labor and B-Labor Resource Ceiling: 7units each Table 1 Project Network details for case 1 Activity Duration Resource Demand (weeks) A B 1-2 2 3 4 2-3 3 3 4 3-4 2 4 3 4-5 2 3 4 4-6 3 4 4 4-7 2 3 3 5-7 2 4 3 6-7 3 4 3 7-8 3 4 4 8-9 4 3 4 Source: Bayelsa State Housing and Property Development Authority, Nigeria 2004. Project 2 Resources Considered for Allocation: A-Labor Resource ceiling: 6units Table 2 Project Network details for case 2 Activity Duration Resource Demand A 1-2 3 3 2-3 3 4 3-4 3 3 4-5 3 4 4-6 2 3 5-7 2 3 6-7 3 3 7-8 3 3 Source: Rivers State Housing and Property Development Authority, Nigeria 2000.
  • 5. Heuristic selection for housing projects… www.theijes.com The IJES Page 62 Project 3 Resources Considered for Allocation: A-Labor Resource ceiling: 10units Table 3 Project Network details for case 3 Activity Duration Resource Demand A 1-2 3 4 2-3 4 3 3-4 2 4 3-5 3 4 3-6 3 4 4-6 1 2 5-6 3 4 6-7 4 2 Source: Bayelsa State Housing and Property Development Authority, Nigeria 2004. Project 4 Resources Considered for Allocation: A-Labor Resource ceiling: 8units Table 4 Project Network details for case 4 Activity Duration Resource Demand A 1-2 2 3 2-3 3 3 2-4 2 4 2-5 2 3 3-5 3 4 4-5 2 3 5-6 2 4 6-7 3 4 Source: Lagos State Property Development Corporation Nigeria 2000. Project 5 Resources Considered for Allocation: A-Labor Resource Ceiling: 6units each Table 5 Project Network details for case 5 Activity Duration Resource Demand A B 1-2 1 4 3 2-3 1 3 4 2-4 2 4 4 3-4 3 2 2 4-5 3 4 2 4-6 2 2 3 5-6 1 2 4 6-7 2 4 4 Source: Lagos State Property Development Corporation Nigeria 2004. Project 6 Resources Considered for Allocation: A-Labor Resource Ceiling: 4units each
  • 6. Heuristic selection for housing projects… www.theijes.com The IJES Page 63 Table 6 Project Network details for case 6 Activity Duration Resource Demand A B 1-2 3 3 1 1-3 2 2 3 2-3 1 4 1 2-4 2 2 1 2-5 1 3 2 3-7 3 4 1 4-6 2 3 3 5-7 3 2 1 6-7 1 3 2 7-8 1 3 3 Source: Lagos State Property Development Corporation 2000. Project 7 Resources Considered for Allocation: A-Labor Resource Ceiling: 5units Table Project Network details for case 7 Activity Duration Resource Demand A 1-2 1 4 2-3 2 3 2-4 3 1 3-5 2 2 3-6 1 2 4-6 1 3 5-7 1 4 6-7 2 2 7-8 1 3 Source: Lagos State Property Development Corporation Nigeria 2004. Project 8 Resources Considered for Allocation: A-Labor Resource Ceiling: 4units Table 8 Project Network details for case 8 Activity Duration Resource Demand A 1-2 2 3 1-3 1 2 1-4 3 3 2-4 1 2 2-6 2 4 3-4 2 1 3-7 3 2 3-5 4 3 6-7 1 2 6-8 2 4 5-8 1 3 7-8 3 3 4-7 4 3 Source: Lagos State Property Development Corporation Nigeria 2004.
  • 7. Heuristic selection for housing projects… www.theijes.com The IJES Page 64 Project 9 Resources Considered for Allocation: A-Labor Resource Ceiling: 6units Table 9 Project Network details for case 9 Activity Duration Resource Demand A 1-2 2 4 1-3 3 2 2-4 3 3 2-3 4 2 4-5 2 3 3-5 3 4 4-6 3 4 5-6 2 3 Source: Lagos State Property Development Corporation Nigeria 2004. Project 10 Resources Considered for Allocation: A-Labor Resource Ceiling: 5units Table 10 Project Network details for case 10 Activity Duration Resource Demand A 1-2 2 4 1-3 3 2 2-4 3 3 2-3 4 2 4-5 2 3 3-5 3 4 4-6 3 4 5-6 2 3 Source: Bayelsa State Housing and Property Development Authority, Nigeria 2004. The outcome of the allocation for the six heuristics are as tabulated below. Table 11 Summary of Resource Utilization Level Case Studies Heuristic Models RAS MSL SPT TRU GRD GRU 1 59% 59% 54% 62% 54% 54% 2 60% 60% 60% 67% 60% 60% 3 46% 46% 46% 46% 46% 46% 4 62% 55% 49% 64% 49% 49% 5 71% 71% 71% 71% 71% 71% 6 84% 79% 79% 100% 79% 79% 7 73% 73% 73% 73% 73% 73% 8 81% 78% 78% 100% 78% 78% 9 74% 70% 74% 90% 70% 70% 10 84% 74% 79% 95% 74% 74% *ras- random activity selection *msl -minimum slack *spt- shortest processing time *tru- total resource usage *grd- greatest resource demand *gru- greatest resource usage
  • 8. Heuristic selection for housing projects… www.theijes.com The IJES Page 65 Table 12 Summary of Time Overrun Level Case Studies Heuristic Models RAS MSL SPT TRU GRD GRU 1 10% 10% 20% 5% 20% 20% 2 18% 18% 18% 6% 18% 18% 3 0 0 0 0 0 0 4 0 8% 15% 0 15% 15% 5 0 0 0 0 0 0 6 78% 89% 89% 56% 89% 89% 7 13% 13% 13% 13% 13% 13% 8 150% 160% 160% 100% 160% 160% 9 36% 46% 36% 18% 46% 46% 10 46% 64% 55% 36% 64% 64% The results highlighted the behavioral pattern of the heuristic models under varying project demand/availability. The outcome of the allocation for the six heuristics are as tabulated below. Table 11 Summary of Resource Utilization Level Case Studies Heuristic Models RAS MSL SPT TRU GRD GRU 1 59% 59% 54% 62% 54% 54% 2 60% 60% 60% 67% 60% 60% 3 46% 46% 46% 46% 46% 46% 4 62% 55% 49% 64% 49% 49% 5 71% 71% 71% 71% 71% 71% 6 84% 79% 79% 100% 79% 79% 7 73% 73% 73% 73% 73% 73% 8 81% 78% 78% 100% 78% 78% 9 74% 70% 74% 90% 70% 70% 10 84% 74% 79% 95% 74% 74% *ras- random activity selection *msl -minimum slack *spt- shortest processing time *tru- total resource usage *grd- greatest resource demand *gru- greatest resource usage Table 12 Summary of Time Overrun Level Case Studies Heuristic Models RAS MSL SPT TRU GRD GRU 1 10% 10% 20% 5% 20% 20% 2 18% 18% 18% 6% 18% 18% 3 0 0 0 0 0 0 4 0 8% 15% 0 15% 15% 5 0 0 0 0 0 0 6 78% 89% 89% 56% 89% 89% 7 13% 13% 13% 13% 13% 13% 8 150% 160% 160% 100% 160% 160% 9 36% 46% 36% 18% 46% 46% 10 46% 64% 55% 36% 64% 64% The results highlighted the behavioral pattern of the heuristic models under varying project demand/availability. VI. DISCUSSION OF RESULTS From the above summary allocation process, random activity selection, minimum slack, shortest processing time, greatest resource usage and greatest resource demand allocate resource to project activities that can be 100% completed and not to activities that can be completed in part at any time period of the project. This implies that resources are allocated to activities only when resource supply is equal or more than resource demand. However, the Total Resource Usage heuristic believes that resources available can be either allocated
  • 9. Heuristic selection for housing projects… www.theijes.com The IJES Page 66 in full or in part. The model envisages that the remainder of any uncompleted activity is carried over to the next time period and this will form part of the workload for that time period for resource Out of the six heuristics, total resource usage gave the highest resource utilization and least project time overrun and is therefore adjudged the most optimal. VII. CONCLUSION Resource allocation under a resource-limited situation has been a source of concern, particularly, in the construction industry. Efforts at optimizing project resources during implementation stages of projects are noticeably numerous. The superiority of heuristic models and indeed total resource usage heuristic over optimization models in allocating project resources is indeed commendable. Its application in the housing sub- sector would certainly reduce resource wastage. REFERENCE [1] A.B. Pritsker, L.J. Walters and P.M. Wolfe, Multi-project scheduling with limited resources; a zero-one programming approach, Management Science, 16, 1969, 93-108. [2] C.M. Popescu and C. Charoenngam, Project planning, scheduling and control in construction. an encyclopedia of terms and applications,(New York: Wiley, 1995). [3] E. Balas, Project scheduling with resources constraints (in) Applications of Mathematical Programming Techniques, 1970, 187-200. [4] E.O.P Akpan, Priority rules in project scheduling: a case for random activity selection, Journal of Production Planning and Control, 11(2), 2000, 165-170. [5] E.O.P Akpan, Optimum resource determination for project scheduling. International Journal of Production Planning and Control, 8(5), 1997, 402-468. [6] E.W. Davis and J.H Patterson, A comparison of heuristic and optimum solutions in resource constrained project scheduling. Management Science, 21(6), 1975, 718-722. [7] E.W. Davis, Networks resource allocation, Industrial Engineering, 4(4), 1974, 22-32. [8] F.B. Talbot, Project scheduling with resource-duration interaction: The Non-preemptive case, Working paper No. 200 Graduate School of Business Administration, University of Michigan, 1980, January. I. Kurtulus and E.W. Davis, Multi-project scheduling, analysis of project performance, IEE Transactions in Engineering Management, 1985, March. [9] Kurtulus and E.W. Davis, Multi-project scheduling categorization of heuristic rules performance. Management Science, 28(2), 1982, 161-172. [10] J.E. Kelly, The critical path method, resource planning and scheduling. Industrial scheduling (Ed) by Muth and Thompson (Englewood cliffs, N.J. Prentice-Hall, 1963). [11] J.H. Patterson, Alternative methods of project scheduling with limited resources, Naval research logistic quarterly, 1973, December. [12] Kernzer Harold, Project management: a systems approach to planning, scheduling and controlling (New York, Van Nostrand Reinhold, 1995). [13] L.G. Fendley, Towards the development of a complete multi-project scheduling system, Journal of Industrial Engineering, 19(10), 1968, 505-515. [14] L. Gonguet, L(1969). Comparison of three heuristic procedures for allocating resources and producing schedules (in) Project planning by network models, (North Holland, Amsterdam, 1969). [15] M.P. Spinner, Project management principles and practices. (New Jersey, Prentice Hall 1997). [16] R.J. Meredith and S. J. Mantel, Project management: a managerial approach,(New York: John Willey and sons, 1995). [17] T. Prabhaker, Resource allocation/leveling in engineering construction projects: A paper, 37th meeting of ORSA, 1970, 20-22.