SlideShare a Scribd company logo
1 of 12
1
May 2014 Construction Update
2
May 2014 Construction Update
3
May 2014 Construction Update
4
May 2014 Construction Update
Change House
Environmental
Enclosure #1
Environmental
Enclosure #3
Laboratory
PCAPP EDS Site Overview
5
PCAPP EDS Safety
As of April 30, the
PCAPP EDS project staff
has accomplished:
 20 Safe Work Days
 2,497 Safe Work Hours
6
Workers smooth concrete on May 8
after the first concrete slab pour for
Environmental Enclosure #1.
PCAPP EDS Construction
Staffing –26 employees
 Construction
 Workers: 6
–Subcontractor
personnel – 20
A worker sets screws for the forms in
preparation for the concrete slab pour for
Environmental Enclosure #2
7
NOT STARTED
IN PROGRESS (POTENTIAL ISSUES)
IN PROGRESS (NO ISSUES)
COMPLETE
Key Milestone
DESIGN START (DEC 2013)
SITE DESIGN COMPLETE (MAR 2014)
CONSTRUCTION STARTS (27 MAR 2014)
CONSTRUCTION COMPLETE (OCT 2014)
E-DAY – EDS START OF
AGENT OPERATIONS (OCT 2014)
CONSTRUCTION CONTRACT AWARD (NOV 2013)
PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013)
PCAPP EDS Schedule
(JPME-P Working Schedule)
CONCRETE POURS BEGIN (17 APR 2014)
MODULES (COMMAND POST, CHANGE HOUSE, TREATY TRAILER, ETC.)
BEGIN TO ARRIVE (MAY 2014)
MILITARY FABRIC STRUCTURES FOR EDS ENVIRONMENTAL
ENCLOSURES ARRIVE (JUN 2014)
ARRIVAL OF FIRST EDS UNIT (AUGUST 2014)
8
PCAPP EDS Permitting Progress
NOT STARTED
IN PROGRESS (POTENTIAL ISSUES)
IN PROGRESS (NO ISSUES)
COMPLETE
Key Milestone
CLASS III PERMIT MODIFICATION SUBMITTED TO CDPHE (24 OCT 2013)
STATE APPROVAL OF TEMPORARY AUTHORIZATION
FOR CONSTRUCTION (7 MAR 2014)
SITE CONSTRUCTION START (27MAR 2014)
APPROVAL OF CLASS III MODIFICATION
FOR OPERATIONS (SEP 2014)
E-DAY – EDS START OF AGENT
OPERATIONS (OCT 2014)
PCD RCRA PERMIT RENEWED (JAN 2014)
SUBMIT CERTIFICATE OF DESIGNATION (CD) (DEC 2013)
PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013)
APPROVAL OF CD FOR OPERATIONS
(OCT 2014)
COUNTY APPROVAL OF TEMPORARY AUTHORIZATION
FOR CONSTRUCTION (26 MAR 2014)
RECORD OF ENVIRONMENTAL CONSIDERATION (DEC 2013)
9
Site Progress
10
Processing dirt, the job of mixing the fill with water
under the weight of heavy equipment, makes for
better compaction when it’s later moved into the
enclosures as a base for the slabs that will be poured.
Site Progress
11
Measure twice, dig once.
A worker confirms the
depth of the trench being
carved out. This for the
pipes that will be part of
the fire line that will
serve the EDS site when
complete.
Questions?
12
Acting Principal Deputy Assistant Secretary of Defense Dr.
A. Tom Hopkins (third from left), Program Executive Officer
ACWA Conrad Whyne (second from left) and PCAPP Project
Manager Rick Holmes, listen to Jake Torres explain the
munition process in the Vapor Containment Room.

More Related Content

What's hot

What's hot (6)

Vedam Design: Engineering Solutions - Gas Ships
Vedam Design: Engineering Solutions - Gas ShipsVedam Design: Engineering Solutions - Gas Ships
Vedam Design: Engineering Solutions - Gas Ships
 
Site Visits 6.5
Site Visits 6.5Site Visits 6.5
Site Visits 6.5
 
DSD-INT 2014 - Symposium Next Generation Hydro Software (NGHS) - How to set u...
DSD-INT 2014 - Symposium Next Generation Hydro Software (NGHS) - How to set u...DSD-INT 2014 - Symposium Next Generation Hydro Software (NGHS) - How to set u...
DSD-INT 2014 - Symposium Next Generation Hydro Software (NGHS) - How to set u...
 
Presentation
PresentationPresentation
Presentation
 
Mitigtion Plan Presentation
Mitigtion Plan PresentationMitigtion Plan Presentation
Mitigtion Plan Presentation
 
Retirement - short
Retirement - shortRetirement - short
Retirement - short
 

Similar to May 2014 Construction Update PCAPP EDS

" Design of Flexible Pavement "
" Design of Flexible Pavement "" Design of Flexible Pavement "
" Design of Flexible Pavement "Nishant Pandey
 
Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015Ian Rowell
 
Manish Ray - CV
Manish Ray - CVManish Ray - CV
Manish Ray - CVManish Ray
 
Mark Deskin - Resume_BR_0816
Mark Deskin - Resume_BR_0816Mark Deskin - Resume_BR_0816
Mark Deskin - Resume_BR_0816William Deskin
 
CV DAVE BEVERIDGE 12.04.15
CV DAVE BEVERIDGE 12.04.15CV DAVE BEVERIDGE 12.04.15
CV DAVE BEVERIDGE 12.04.15Dave Beveridge
 
Leading Naval Architectural Firm Leverages 3D to Solve Large Scale Problems
Leading Naval Architectural Firm Leverages 3D to Solve Large Scale ProblemsLeading Naval Architectural Firm Leverages 3D to Solve Large Scale Problems
Leading Naval Architectural Firm Leverages 3D to Solve Large Scale ProblemsJake Rosenbaum
 
Resume Nazrul Mazdi Mokhtar - Piping Designer
Resume Nazrul Mazdi Mokhtar - Piping DesignerResume Nazrul Mazdi Mokhtar - Piping Designer
Resume Nazrul Mazdi Mokhtar - Piping DesignerNazrul Mokhtar
 
Jared Kasper Resume
Jared Kasper ResumeJared Kasper Resume
Jared Kasper ResumeJared Kasper
 
CV_2015_David_Darr
CV_2015_David_DarrCV_2015_David_Darr
CV_2015_David_DarrDavid Darr
 

Similar to May 2014 Construction Update PCAPP EDS (20)

PCAPP Update 30 April 2014
PCAPP Update 30 April 2014PCAPP Update 30 April 2014
PCAPP Update 30 April 2014
 
PCAPP Update 25 June 2014
PCAPP Update 25 June 2014PCAPP Update 25 June 2014
PCAPP Update 25 June 2014
 
Mvcv v10
Mvcv v10Mvcv v10
Mvcv v10
 
" Design of Flexible Pavement "
" Design of Flexible Pavement "" Design of Flexible Pavement "
" Design of Flexible Pavement "
 
final year presentation revised
final year presentation revisedfinal year presentation revised
final year presentation revised
 
M.s. resume 290817
M.s. resume 290817M.s. resume 290817
M.s. resume 290817
 
Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015
 
Manish Ray - CV
Manish Ray - CVManish Ray - CV
Manish Ray - CV
 
Kalorama Community Meeting (July 17, 2014)
Kalorama Community Meeting (July 17, 2014)Kalorama Community Meeting (July 17, 2014)
Kalorama Community Meeting (July 17, 2014)
 
M.s. resume 150316
M.s. resume 150316M.s. resume 150316
M.s. resume 150316
 
PCAPP Update 28 May 2014
PCAPP Update 28 May 2014PCAPP Update 28 May 2014
PCAPP Update 28 May 2014
 
EIA Report
EIA ReportEIA Report
EIA Report
 
Rahman cv
Rahman cvRahman cv
Rahman cv
 
Final report
Final reportFinal report
Final report
 
Mark Deskin - Resume_BR_0816
Mark Deskin - Resume_BR_0816Mark Deskin - Resume_BR_0816
Mark Deskin - Resume_BR_0816
 
CV DAVE BEVERIDGE 12.04.15
CV DAVE BEVERIDGE 12.04.15CV DAVE BEVERIDGE 12.04.15
CV DAVE BEVERIDGE 12.04.15
 
Leading Naval Architectural Firm Leverages 3D to Solve Large Scale Problems
Leading Naval Architectural Firm Leverages 3D to Solve Large Scale ProblemsLeading Naval Architectural Firm Leverages 3D to Solve Large Scale Problems
Leading Naval Architectural Firm Leverages 3D to Solve Large Scale Problems
 
Resume Nazrul Mazdi Mokhtar - Piping Designer
Resume Nazrul Mazdi Mokhtar - Piping DesignerResume Nazrul Mazdi Mokhtar - Piping Designer
Resume Nazrul Mazdi Mokhtar - Piping Designer
 
Jared Kasper Resume
Jared Kasper ResumeJared Kasper Resume
Jared Kasper Resume
 
CV_2015_David_Darr
CV_2015_David_DarrCV_2015_David_Darr
CV_2015_David_Darr
 

More from Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)

More from Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA) (20)

CAC/CDCAB Vent Recommendation 5 March 2013
CAC/CDCAB Vent Recommendation 5 March 2013CAC/CDCAB Vent Recommendation 5 March 2013
CAC/CDCAB Vent Recommendation 5 March 2013
 
Secondary Waste Working Group 12 March 2014
Secondary Waste Working Group 12 March 2014Secondary Waste Working Group 12 March 2014
Secondary Waste Working Group 12 March 2014
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
 
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
 
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
 
June '13 cdcab
June '13 cdcabJune '13 cdcab
June '13 cdcab
 
M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013
 
2015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 20142015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 2014
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
 
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
 
Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014
 
BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2013BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2013
 
BGCAPP Year in Review Dec. 11, 2012
BGCAPP Year in Review Dec. 11, 2012BGCAPP Year in Review Dec. 11, 2012
BGCAPP Year in Review Dec. 11, 2012
 
Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013
 
Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012
 
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons ConventionOPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
 
CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012
 
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
 

Recently uploaded

An Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCAn Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCNAP Global Network
 
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberCall Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberSareena Khatun
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30JSchaus & Associates
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)NAP Global Network
 
2024: The FAR, Federal Acquisition Regulations, Part 32
2024: The FAR, Federal Acquisition Regulations, Part 322024: The FAR, Federal Acquisition Regulations, Part 32
2024: The FAR, Federal Acquisition Regulations, Part 32JSchaus & Associates
 
Unique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfUnique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfScottMeyers35
 
NAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptxNAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptxNAP Global Network
 
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899Cara Menggugurkan Kandungan 087776558899
 
31st World Press Freedom Day Conference.
31st World Press Freedom Day Conference.31st World Press Freedom Day Conference.
31st World Press Freedom Day Conference.Christina Parmionova
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCNAP Global Network
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'NAP Global Network
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfSamirsinh Parmar
 
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...Christina Parmionova
 
sponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfsponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfSERUDS INDIA
 
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...
Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...Namrata Singh
 
Dating Call Girls inBaloda Bazar Bhatapara 9332606886Call Girls Advance Cash...
Dating Call Girls inBaloda Bazar Bhatapara  9332606886Call Girls Advance Cash...Dating Call Girls inBaloda Bazar Bhatapara  9332606886Call Girls Advance Cash...
Dating Call Girls inBaloda Bazar Bhatapara 9332606886Call Girls Advance Cash...kumargunjan9515
 
3 May, Journalism in the face of the Environmental Crisis.
3 May, Journalism in the face of the Environmental Crisis.3 May, Journalism in the face of the Environmental Crisis.
3 May, Journalism in the face of the Environmental Crisis.Christina Parmionova
 
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...gajnagarg
 

Recently uploaded (20)

An Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCAn Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCC
 
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and NumberCall Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Mehsana / 8250092165 Genuine Call girls with real Photos and Number
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)
 
2024: The FAR, Federal Acquisition Regulations, Part 32
2024: The FAR, Federal Acquisition Regulations, Part 322024: The FAR, Federal Acquisition Regulations, Part 32
2024: The FAR, Federal Acquisition Regulations, Part 32
 
Unique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdfUnique Value Prop slide deck________.pdf
Unique Value Prop slide deck________.pdf
 
NAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptxNAP Expo - Delivering effective and adequate adaptation.pptx
NAP Expo - Delivering effective and adequate adaptation.pptx
 
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition PlansSustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
 
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
Cara Gugurkan Pembuahan Secara Alami Dan Cepat ABORSI KANDUNGAN 087776558899
 
31st World Press Freedom Day Conference.
31st World Press Freedom Day Conference.31st World Press Freedom Day Conference.
31st World Press Freedom Day Conference.
 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCC
 
Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'Coastal Protection Measures in Hulhumale'
Coastal Protection Measures in Hulhumale'
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 
Panchayath circular KLC -Panchayath raj act s 169, 218
Panchayath circular KLC -Panchayath raj act s 169, 218Panchayath circular KLC -Panchayath raj act s 169, 218
Panchayath circular KLC -Panchayath raj act s 169, 218
 
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
31st World Press Freedom Day - A Press for the Planet: Journalism in the face...
 
sponsor for poor old age person food.pdf
sponsor for poor old age person food.pdfsponsor for poor old age person food.pdf
sponsor for poor old age person food.pdf
 
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...
Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...Kolkata Call Girls Halisahar  💯Call Us 🔝 8005736733 🔝 💃  Top Class Call Girl ...
Kolkata Call Girls Halisahar 💯Call Us 🔝 8005736733 🔝 💃 Top Class Call Girl ...
 
Dating Call Girls inBaloda Bazar Bhatapara 9332606886Call Girls Advance Cash...
Dating Call Girls inBaloda Bazar Bhatapara  9332606886Call Girls Advance Cash...Dating Call Girls inBaloda Bazar Bhatapara  9332606886Call Girls Advance Cash...
Dating Call Girls inBaloda Bazar Bhatapara 9332606886Call Girls Advance Cash...
 
3 May, Journalism in the face of the Environmental Crisis.
3 May, Journalism in the face of the Environmental Crisis.3 May, Journalism in the face of the Environmental Crisis.
3 May, Journalism in the face of the Environmental Crisis.
 
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
 

May 2014 Construction Update PCAPP EDS

  • 5. Change House Environmental Enclosure #1 Environmental Enclosure #3 Laboratory PCAPP EDS Site Overview 5
  • 6. PCAPP EDS Safety As of April 30, the PCAPP EDS project staff has accomplished:  20 Safe Work Days  2,497 Safe Work Hours 6 Workers smooth concrete on May 8 after the first concrete slab pour for Environmental Enclosure #1.
  • 7. PCAPP EDS Construction Staffing –26 employees  Construction  Workers: 6 –Subcontractor personnel – 20 A worker sets screws for the forms in preparation for the concrete slab pour for Environmental Enclosure #2 7
  • 8. NOT STARTED IN PROGRESS (POTENTIAL ISSUES) IN PROGRESS (NO ISSUES) COMPLETE Key Milestone DESIGN START (DEC 2013) SITE DESIGN COMPLETE (MAR 2014) CONSTRUCTION STARTS (27 MAR 2014) CONSTRUCTION COMPLETE (OCT 2014) E-DAY – EDS START OF AGENT OPERATIONS (OCT 2014) CONSTRUCTION CONTRACT AWARD (NOV 2013) PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013) PCAPP EDS Schedule (JPME-P Working Schedule) CONCRETE POURS BEGIN (17 APR 2014) MODULES (COMMAND POST, CHANGE HOUSE, TREATY TRAILER, ETC.) BEGIN TO ARRIVE (MAY 2014) MILITARY FABRIC STRUCTURES FOR EDS ENVIRONMENTAL ENCLOSURES ARRIVE (JUN 2014) ARRIVAL OF FIRST EDS UNIT (AUGUST 2014) 8
  • 9. PCAPP EDS Permitting Progress NOT STARTED IN PROGRESS (POTENTIAL ISSUES) IN PROGRESS (NO ISSUES) COMPLETE Key Milestone CLASS III PERMIT MODIFICATION SUBMITTED TO CDPHE (24 OCT 2013) STATE APPROVAL OF TEMPORARY AUTHORIZATION FOR CONSTRUCTION (7 MAR 2014) SITE CONSTRUCTION START (27MAR 2014) APPROVAL OF CLASS III MODIFICATION FOR OPERATIONS (SEP 2014) E-DAY – EDS START OF AGENT OPERATIONS (OCT 2014) PCD RCRA PERMIT RENEWED (JAN 2014) SUBMIT CERTIFICATE OF DESIGNATION (CD) (DEC 2013) PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013) APPROVAL OF CD FOR OPERATIONS (OCT 2014) COUNTY APPROVAL OF TEMPORARY AUTHORIZATION FOR CONSTRUCTION (26 MAR 2014) RECORD OF ENVIRONMENTAL CONSIDERATION (DEC 2013) 9
  • 10. Site Progress 10 Processing dirt, the job of mixing the fill with water under the weight of heavy equipment, makes for better compaction when it’s later moved into the enclosures as a base for the slabs that will be poured.
  • 11. Site Progress 11 Measure twice, dig once. A worker confirms the depth of the trench being carved out. This for the pipes that will be part of the fire line that will serve the EDS site when complete.
  • 12. Questions? 12 Acting Principal Deputy Assistant Secretary of Defense Dr. A. Tom Hopkins (third from left), Program Executive Officer ACWA Conrad Whyne (second from left) and PCAPP Project Manager Rick Holmes, listen to Jake Torres explain the munition process in the Vapor Containment Room.