SlideShare a Scribd company logo
1 of 24
1
OCCUPATIONAL SAFETY AND HEALTH
       OSHA              ADMINISTRATION

            Subpart T - Demolition
         1926.850 Preparatory operations
1926.850(a) “Prior to permitting employees to start
demolition operations, an engineering survey shall be
made, by a competent person, of the structure to
determine the condition of the framing, floors, and
walls, and possibility of unplanned collapse of any
portion of the structure. Any adjacent structure where
employees may be exposed shall also be similarly
checked. The employer shall have in writing evidence
that such a survey has been performed.”
                                                     2
3
OCCUPATIONAL SAFETY AND HEALTH
      OSHA               ADMINISTRATION

           Subpart T - Demolition
        1926.850 Preparatory operations
1926.850(c) “All electric, gas, water, sewer, and other
service lines shall be shut off, capped, or otherwise
controlled, outside the building line before
demolition work is started. In each case, any utility
company which is involved shall be notified in
advance.”



                                                          4
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

            Subpart T - Demolition
         1926.850 Preparatory operations
1926.850(h) “When debris is dropped through holes in
the floor without the use of chutes, the area onto which
the material is dropped shall be completely enclosed
with barricades not less than 42 inches high and not
less than 6 feet back from the projected edge of the
opening above. Signs, warning of the hazard of falling
materials, shall be posted at each level. Removal shall
not be permitted in this lower area until debris
handling ceases above.”
                                                       5
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

            Subpart T - Demolition
         1926.850 Preparatory operations
1926.850(g) “Where a hazard exists to employees
falling through wall openings, the opening shall be
protected to a height of approximately 42 inches.”




                                                      7
42"




      8
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

            Subpart T - Demolition
         1926.850 Preparatory operations
1926.850(h) “When debris is dropped through holes in
the floor without the use of chutes, the area onto which
the material is dropped shall be completely enclosed
with barricades not less than 42 inches high and not
less than 6 feet back from the projected edge of the
opening above. Signs, warning of the hazard of falling
materials, shall be posted at each level. Removal shall
not be permitted in this lower area until debris
handling ceases above.”
                                                       9
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

            Subpart T - Demolition
        1926.850 Preparatory operations
1926.850(i) “All floor openings, not used as material
drops, shall be covered over with material substantial
enough to support the weight of any load which may
be imposed. Such material shall be properly secured
to prevent its accidental movement.”




                                                         11
12
OCCUPATIONAL SAFETY AND HEALTH
       OSHA                ADMINISTRATION

          Subpart T - Demolition
                   1926.852 Chutes
1926.852(a) “No material shall be dropped to any point
lying outside the exterior walls of the structure unless the
area is effectively protected.”

1926.852(b) “All materials chutes, or sections thereof, at an
angle of more than 450 from the horizontal , shall be
entirely enclosed, except for openings equipped with
closures at or about floor level for the insertion of
materials. The openings shall not exceed 48 inches in
height measured along the wall of the chute. At all stories
below the top floor, such openings shall be kept closed   13

when not in use.”
14
15
OCCUPATIONAL SAFETY AND HEALTH
     OSHA               ADMINISTRATION

           Subpart T - Demolition
    1926.853 Removal of materials through
               floor openings
“Any openings cut in a floor for the disposal of
materials shall be no larger in size than 25 percent
of the aggregate of the total floor area, unless the
lateral supports of the removed flooring remain in
place. Floors weakened or otherwise made unsafe by
demolition operations shall be shored to carry safely
the intended imposed load from demolition
operations.”
                                                    16
OCCUPATIONAL SAFETY AND HEALTH
      OSHA              ADMINISTRATION

           Subpart T - Demolition
       1926.859 Mechanical demolition
1926.859(a) “No workers shall be permitted in any
area, which can be adversely affected by demolition
operations, when balling or clamming is being
performed. Only those workers necessary for the
performance of the operations shall be permitted in
this area at any other time.”



                                                      17
18
!
                     48" Max




Openings kept closed when not in use
•Guardrails installed
                        !
where men drop                       48" Max
debris




               •Space between chute and
               edge of floor solidly covered
!
48" Max




     •Toeboard or bumper
     •4” thick X 6” high
     •Securely attached
OCCUPATIONAL SAFETY AND HEALTH
      OSHA               ADMINISTRATION

            Subpart T - Demolition
         1926.859 Mechanical demolition
1926.859(b) “The weight of the demolition ball shall
not exceed 50 percent of the crane’s rated load, based
on the length of the boom and the maximum angle of
operation at which the demolition ball will be used, or
it shall not exceed 25 percent of the nominal breaking
strength of the line by which it is suspended,
whichever results in a lesser value.”

                                                      23
24

More Related Content

What's hot

Safety precautions during demolition
Safety precautions during demolitionSafety precautions during demolition
Safety precautions during demolition
Manthan Vaghasiya
 
Fall Prevention Safety posters roll out
Fall Prevention Safety posters roll outFall Prevention Safety posters roll out
Fall Prevention Safety posters roll out
Barrie O'Sullivan
 

What's hot (20)

Excavation & Trenching Safety
Excavation & Trenching Safety Excavation & Trenching Safety
Excavation & Trenching Safety
 
Excavations ppt
Excavations pptExcavations ppt
Excavations ppt
 
A Part 6 Lifting Operations
A  Part 6 Lifting OperationsA  Part 6 Lifting Operations
A Part 6 Lifting Operations
 
1926 concrete safety 2017
1926 concrete safety 20171926 concrete safety 2017
1926 concrete safety 2017
 
Slips trips falls
Slips trips fallsSlips trips falls
Slips trips falls
 
Electrical Safety in Construction.ppt
Electrical Safety in Construction.pptElectrical Safety in Construction.ppt
Electrical Safety in Construction.ppt
 
Scaffold safe work method statement
Scaffold safe work method statementScaffold safe work method statement
Scaffold safe work method statement
 
Aerial and scissor lift safety 2
Aerial and scissor lift safety 2Aerial and scissor lift safety 2
Aerial and scissor lift safety 2
 
SCAFFOLDING
SCAFFOLDINGSCAFFOLDING
SCAFFOLDING
 
Safety precautions during demolition
Safety precautions during demolitionSafety precautions during demolition
Safety precautions during demolition
 
Risk Assessments 96 pages
Risk Assessments 96 pagesRisk Assessments 96 pages
Risk Assessments 96 pages
 
Abrasive wheels presentation
Abrasive wheels presentationAbrasive wheels presentation
Abrasive wheels presentation
 
Struck by hazards 2019
Struck by hazards 2019Struck by hazards 2019
Struck by hazards 2019
 
Safety during construction
Safety during construction Safety during construction
Safety during construction
 
scaffolding safety.pdf
scaffolding safety.pdfscaffolding safety.pdf
scaffolding safety.pdf
 
Scaffolding by UTK
Scaffolding by UTKScaffolding by UTK
Scaffolding by UTK
 
Boom lift training
Boom lift trainingBoom lift training
Boom lift training
 
Lifting plan
Lifting planLifting plan
Lifting plan
 
Fall Prevention Safety posters roll out
Fall Prevention Safety posters roll outFall Prevention Safety posters roll out
Fall Prevention Safety posters roll out
 
Erection of scaffolding
Erection of scaffoldingErection of scaffolding
Erection of scaffolding
 

Viewers also liked

Subpart E - PPE
Subpart E  - PPESubpart E  - PPE
Subpart E - PPE
FFSafety
 
ΜΕΣΑ ΑΤΟΜΙΚΗΣ ΠΡΟΣΤΑΣΙΑΣ (ΜΑΠ) 2011
ΜΕΣΑ ΑΤΟΜΙΚΗΣ ΠΡΟΣΤΑΣΙΑΣ (ΜΑΠ) 2011ΜΕΣΑ ΑΤΟΜΙΚΗΣ ΠΡΟΣΤΑΣΙΑΣ (ΜΑΠ) 2011
ΜΕΣΑ ΑΤΟΜΙΚΗΣ ΠΡΟΣΤΑΣΙΑΣ (ΜΑΠ) 2011
hagar18
 
ερευνητική εργασία υγιεινή και ασφάλεια στους χώρους εργασίας
ερευνητική εργασία υγιεινή και ασφάλεια στους  χώρους εργασίαςερευνητική εργασία υγιεινή και ασφάλεια στους  χώρους εργασίας
ερευνητική εργασία υγιεινή και ασφάλεια στους χώρους εργασίας
gouvou
 
Best Safety Management Practice_KKAB - Demolition 2015-10 TJ Edits
Best Safety Management Practice_KKAB - Demolition 2015-10 TJ EditsBest Safety Management Practice_KKAB - Demolition 2015-10 TJ Edits
Best Safety Management Practice_KKAB - Demolition 2015-10 TJ Edits
safetyraghu
 
Subpart H - Material Handling
Subpart H -  Material HandlingSubpart H -  Material Handling
Subpart H - Material Handling
FFSafety
 
Subpart L - Scaffolding
Subpart L - ScaffoldingSubpart L - Scaffolding
Subpart L - Scaffolding
FFSafety
 

Viewers also liked (20)

Subpart E - PPE
Subpart E  - PPESubpart E  - PPE
Subpart E - PPE
 
Just a safety minute scissor lift reminder
Just a safety minute scissor lift reminderJust a safety minute scissor lift reminder
Just a safety minute scissor lift reminder
 
SAFE-SERIES: Offer Anti-Slip Solutions For The Industries
SAFE-SERIES: Offer Anti-Slip Solutions For The IndustriesSAFE-SERIES: Offer Anti-Slip Solutions For The Industries
SAFE-SERIES: Offer Anti-Slip Solutions For The Industries
 
Περιβαλλοντική Ευθύνη
Περιβαλλοντική ΕυθύνηΠεριβαλλοντική Ευθύνη
Περιβαλλοντική Ευθύνη
 
ΕΦΑΡΜΟΓΗ ΤΗΣ ΟΔΗΓΙΑΣ ΓΙΑ ΤΗΝ ΠΕΡΙΒΑΛΛΟΝΤΙΚΗ ΕΥΘΥΝΗ ΣΕ ΕΘΝΙΚΟ ΕΠΙΠΕΔΟ
ΕΦΑΡΜΟΓΗ ΤΗΣ ΟΔΗΓΙΑΣ ΓΙΑ ΤΗΝ ΠΕΡΙΒΑΛΛΟΝΤΙΚΗ ΕΥΘΥΝΗ ΣΕ ΕΘΝΙΚΟ ΕΠΙΠΕΔΟΕΦΑΡΜΟΓΗ ΤΗΣ ΟΔΗΓΙΑΣ ΓΙΑ ΤΗΝ ΠΕΡΙΒΑΛΛΟΝΤΙΚΗ ΕΥΘΥΝΗ ΣΕ ΕΘΝΙΚΟ ΕΠΙΠΕΔΟ
ΕΦΑΡΜΟΓΗ ΤΗΣ ΟΔΗΓΙΑΣ ΓΙΑ ΤΗΝ ΠΕΡΙΒΑΛΛΟΝΤΙΚΗ ΕΥΘΥΝΗ ΣΕ ΕΘΝΙΚΟ ΕΠΙΠΕΔΟ
 
Safety Inspection Checklist for – (Bobcat, Dingo and Excavator)
Safety Inspection Checklist for – (Bobcat, Dingo and Excavator)Safety Inspection Checklist for – (Bobcat, Dingo and Excavator)
Safety Inspection Checklist for – (Bobcat, Dingo and Excavator)
 
Ηλεκτρονικό Περιβαλλοντικό Μητρώο
Ηλεκτρονικό Περιβαλλοντικό ΜητρώοΗλεκτρονικό Περιβαλλοντικό Μητρώο
Ηλεκτρονικό Περιβαλλοντικό Μητρώο
 
ΜΕΣΑ ΑΤΟΜΙΚΗΣ ΠΡΟΣΤΑΣΙΑΣ (ΜΑΠ) 2011
ΜΕΣΑ ΑΤΟΜΙΚΗΣ ΠΡΟΣΤΑΣΙΑΣ (ΜΑΠ) 2011ΜΕΣΑ ΑΤΟΜΙΚΗΣ ΠΡΟΣΤΑΣΙΑΣ (ΜΑΠ) 2011
ΜΕΣΑ ΑΤΟΜΙΚΗΣ ΠΡΟΣΤΑΣΙΑΣ (ΜΑΠ) 2011
 
Demolition Safety 2015
Demolition Safety 2015Demolition Safety 2015
Demolition Safety 2015
 
Personal protective equipment 111911
Personal protective equipment 111911Personal protective equipment 111911
Personal protective equipment 111911
 
Sharpsawareness final 2015
Sharpsawareness final 2015Sharpsawareness final 2015
Sharpsawareness final 2015
 
Scissor Lift Pre-Shift Inspection
Scissor Lift Pre-Shift Inspection Scissor Lift Pre-Shift Inspection
Scissor Lift Pre-Shift Inspection
 
ερευνητική εργασία υγιεινή και ασφάλεια στους χώρους εργασίας
ερευνητική εργασία υγιεινή και ασφάλεια στους  χώρους εργασίαςερευνητική εργασία υγιεινή και ασφάλεια στους  χώρους εργασίας
ερευνητική εργασία υγιεινή και ασφάλεια στους χώρους εργασίας
 
Asbestos awareness 2011
Asbestos awareness 2011Asbestos awareness 2011
Asbestos awareness 2011
 
Asbestos Awareness Presentation Contractors Introduction
Asbestos Awareness Presentation   Contractors IntroductionAsbestos Awareness Presentation   Contractors Introduction
Asbestos Awareness Presentation Contractors Introduction
 
Aerial and scissor lift safety
Aerial and scissor lift safetyAerial and scissor lift safety
Aerial and scissor lift safety
 
Best Safety Management Practice_KKAB - Demolition 2015-10 TJ Edits
Best Safety Management Practice_KKAB - Demolition 2015-10 TJ EditsBest Safety Management Practice_KKAB - Demolition 2015-10 TJ Edits
Best Safety Management Practice_KKAB - Demolition 2015-10 TJ Edits
 
Σύνδεση πίνακα αυτονομίας θέρμανσης
Σύνδεση πίνακα αυτονομίας θέρμανσηςΣύνδεση πίνακα αυτονομίας θέρμανσης
Σύνδεση πίνακα αυτονομίας θέρμανσης
 
Subpart H - Material Handling
Subpart H -  Material HandlingSubpart H -  Material Handling
Subpart H - Material Handling
 
Subpart L - Scaffolding
Subpart L - ScaffoldingSubpart L - Scaffolding
Subpart L - Scaffolding
 

Similar to Subpart T - Demolition

Subpart P - Excavations
Subpart P - ExcavationsSubpart P - Excavations
Subpart P - Excavations
FFSafety
 
Subpart X - Ladders
Subpart X -  LaddersSubpart X -  Ladders
Subpart X - Ladders
FFSafety
 
Subpart Q Concrete Written
Subpart Q   Concrete   WrittenSubpart Q   Concrete   Written
Subpart Q Concrete Written
FFSafety
 
Subpart N - Cranes
Subpart N - CranesSubpart N - Cranes
Subpart N - Cranes
FFSafety
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers reference
ssuser2c065e
 
Subpart I - Tools
Subpart I - ToolsSubpart I - Tools
Subpart I - Tools
FFSafety
 

Similar to Subpart T - Demolition (15)

Subpart P - Excavations
Subpart P - ExcavationsSubpart P - Excavations
Subpart P - Excavations
 
Subpart X - Ladders
Subpart X -  LaddersSubpart X -  Ladders
Subpart X - Ladders
 
Subpart Q Concrete Written
Subpart Q   Concrete   WrittenSubpart Q   Concrete   Written
Subpart Q Concrete Written
 
OSHA demolition
OSHA demolitionOSHA demolition
OSHA demolition
 
510 tunneling safety 2016
510 tunneling safety 2016510 tunneling safety 2016
510 tunneling safety 2016
 
Subpart N - Cranes
Subpart N - CranesSubpart N - Cranes
Subpart N - Cranes
 
Suspended personnel platforms 2017
Suspended personnel platforms 2017Suspended personnel platforms 2017
Suspended personnel platforms 2017
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers reference
 
OSHA Trenching and Excavation Requirements
OSHA Trenching and Excavation Requirements OSHA Trenching and Excavation Requirements
OSHA Trenching and Excavation Requirements
 
National Safety Fall_protection_Presentation.ppt
National Safety Fall_protection_Presentation.pptNational Safety Fall_protection_Presentation.ppt
National Safety Fall_protection_Presentation.ppt
 
Construction safety manual
Construction safety manualConstruction safety manual
Construction safety manual
 
21 Pump Jack Scaffolding
21 Pump Jack Scaffolding21 Pump Jack Scaffolding
21 Pump Jack Scaffolding
 
Subpart I - Tools
Subpart I - ToolsSubpart I - Tools
Subpart I - Tools
 
fall protection 2015
 fall protection 2015 fall protection 2015
fall protection 2015
 
Trench excavationsafety
Trench excavationsafetyTrench excavationsafety
Trench excavationsafety
 

More from FFSafety

S A F E T Y P H O T O S P R E S E N T A T I O N
S A F E T Y  P H O T O S  P R E S E N T A T I O NS A F E T Y  P H O T O S  P R E S E N T A T I O N
S A F E T Y P H O T O S P R E S E N T A T I O N
FFSafety
 
Fall Protection, Gtech
Fall Protection, GtechFall Protection, Gtech
Fall Protection, Gtech
FFSafety
 
Site Photos, 0608
Site Photos, 0608Site Photos, 0608
Site Photos, 0608
FFSafety
 
00999 Focus Four 131
00999 Focus Four 13100999 Focus Four 131
00999 Focus Four 131
FFSafety
 
Recordkeeping 00150 22
Recordkeeping 00150 22Recordkeeping 00150 22
Recordkeeping 00150 22
FFSafety
 
Subpart R - Steel Erection
Subpart R -  Steel ErectionSubpart R -  Steel Erection
Subpart R - Steel Erection
FFSafety
 
Subpart O - Motor Vehicles
Subpart O - Motor VehiclesSubpart O - Motor Vehicles
Subpart O - Motor Vehicles
FFSafety
 
Subpart M - Fall Protection
Subpart M  - Fall ProtectionSubpart M  - Fall Protection
Subpart M - Fall Protection
FFSafety
 
Subpart K - Electrical
Subpart K - ElectricalSubpart K - Electrical
Subpart K - Electrical
FFSafety
 
Subpart J - Welding
Subpart J  - WeldingSubpart J  - Welding
Subpart J - Welding
FFSafety
 
Subpart H - Material Handling
Subpart H -  Material HandlingSubpart H -  Material Handling
Subpart H - Material Handling
FFSafety
 
Subpart G - Signs and Signals
Subpart G - Signs and SignalsSubpart G - Signs and Signals
Subpart G - Signs and Signals
FFSafety
 
Subpart F - Fire Protection
Subpart F -  Fire ProtectionSubpart F -  Fire Protection
Subpart F - Fire Protection
FFSafety
 
Subpart D - Health & Environment
Subpart D - Health & EnvironmentSubpart D - Health & Environment
Subpart D - Health & Environment
FFSafety
 
Subpart C Safety And Health
Subpart C   Safety And HealthSubpart C   Safety And Health
Subpart C Safety And Health
FFSafety
 
Focus Four Ppp
Focus Four PppFocus Four Ppp
Focus Four Ppp
FFSafety
 
Scaffolding
ScaffoldingScaffolding
Scaffolding
FFSafety
 
Scaffolds C
Scaffolds CScaffolds C
Scaffolds C
FFSafety
 

More from FFSafety (20)

S A F E T Y P H O T O S P R E S E N T A T I O N
S A F E T Y  P H O T O S  P R E S E N T A T I O NS A F E T Y  P H O T O S  P R E S E N T A T I O N
S A F E T Y P H O T O S P R E S E N T A T I O N
 
Fall Protection, Gtech
Fall Protection, GtechFall Protection, Gtech
Fall Protection, Gtech
 
Site Photos, 0608
Site Photos, 0608Site Photos, 0608
Site Photos, 0608
 
00999 Focus Four 131
00999 Focus Four 13100999 Focus Four 131
00999 Focus Four 131
 
Recordkeeping 00150 22
Recordkeeping 00150 22Recordkeeping 00150 22
Recordkeeping 00150 22
 
Subpart R - Steel Erection
Subpart R -  Steel ErectionSubpart R -  Steel Erection
Subpart R - Steel Erection
 
Subpart O - Motor Vehicles
Subpart O - Motor VehiclesSubpart O - Motor Vehicles
Subpart O - Motor Vehicles
 
Subpart M - Fall Protection
Subpart M  - Fall ProtectionSubpart M  - Fall Protection
Subpart M - Fall Protection
 
Subpart K - Electrical
Subpart K - ElectricalSubpart K - Electrical
Subpart K - Electrical
 
Subpart J - Welding
Subpart J  - WeldingSubpart J  - Welding
Subpart J - Welding
 
Subpart H - Material Handling
Subpart H -  Material HandlingSubpart H -  Material Handling
Subpart H - Material Handling
 
Subpart G - Signs and Signals
Subpart G - Signs and SignalsSubpart G - Signs and Signals
Subpart G - Signs and Signals
 
Subpart F - Fire Protection
Subpart F -  Fire ProtectionSubpart F -  Fire Protection
Subpart F - Fire Protection
 
Subpart D - Health & Environment
Subpart D - Health & EnvironmentSubpart D - Health & Environment
Subpart D - Health & Environment
 
Subpart C Safety And Health
Subpart C   Safety And HealthSubpart C   Safety And Health
Subpart C Safety And Health
 
Article
ArticleArticle
Article
 
Focus Four Ppp
Focus Four PppFocus Four Ppp
Focus Four Ppp
 
Ppe C
Ppe CPpe C
Ppe C
 
Scaffolding
ScaffoldingScaffolding
Scaffolding
 
Scaffolds C
Scaffolds CScaffolds C
Scaffolds C
 

Recently uploaded

Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
Nauman Safdar
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
ZurliaSoop
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
daisycvs
 

Recently uploaded (20)

Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan CytotecJual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
Jual Obat Aborsi ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan Cytotec
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDINGBerhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
Berhampur 70918*19311 CALL GIRLS IN ESCORT SERVICE WE ARE PROVIDING
 
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...joint cost.pptx  COST ACCOUNTING  Sixteenth Edition                          ...
joint cost.pptx COST ACCOUNTING Sixteenth Edition ...
 
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service AvailableNashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
Nashik Call Girl Just Call 7091819311 Top Class Call Girl Service Available
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All TimeCall 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
Call 7737669865 Vadodara Call Girls Service at your Door Step Available All Time
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book nowPARK STREET 💋 Call Girl 9827461493 Call Girls in  Escort service book now
PARK STREET 💋 Call Girl 9827461493 Call Girls in Escort service book now
 
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
Ooty Call Gril 80022//12248 Only For Sex And High Profile Best Gril Sex Avail...
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur DubaiUAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
UAE Bur Dubai Call Girls ☏ 0564401582 Call Girl in Bur Dubai
 
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAIGetting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
Getting Real with AI - Columbus DAW - May 2024 - Nick Woo from AlignAI
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 

Subpart T - Demolition

  • 1. 1
  • 2. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart T - Demolition 1926.850 Preparatory operations 1926.850(a) “Prior to permitting employees to start demolition operations, an engineering survey shall be made, by a competent person, of the structure to determine the condition of the framing, floors, and walls, and possibility of unplanned collapse of any portion of the structure. Any adjacent structure where employees may be exposed shall also be similarly checked. The employer shall have in writing evidence that such a survey has been performed.” 2
  • 3. 3
  • 4. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart T - Demolition 1926.850 Preparatory operations 1926.850(c) “All electric, gas, water, sewer, and other service lines shall be shut off, capped, or otherwise controlled, outside the building line before demolition work is started. In each case, any utility company which is involved shall be notified in advance.” 4
  • 5. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart T - Demolition 1926.850 Preparatory operations 1926.850(h) “When debris is dropped through holes in the floor without the use of chutes, the area onto which the material is dropped shall be completely enclosed with barricades not less than 42 inches high and not less than 6 feet back from the projected edge of the opening above. Signs, warning of the hazard of falling materials, shall be posted at each level. Removal shall not be permitted in this lower area until debris handling ceases above.” 5
  • 6.
  • 7. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart T - Demolition 1926.850 Preparatory operations 1926.850(g) “Where a hazard exists to employees falling through wall openings, the opening shall be protected to a height of approximately 42 inches.” 7
  • 8. 42" 8
  • 9. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart T - Demolition 1926.850 Preparatory operations 1926.850(h) “When debris is dropped through holes in the floor without the use of chutes, the area onto which the material is dropped shall be completely enclosed with barricades not less than 42 inches high and not less than 6 feet back from the projected edge of the opening above. Signs, warning of the hazard of falling materials, shall be posted at each level. Removal shall not be permitted in this lower area until debris handling ceases above.” 9
  • 10.
  • 11. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart T - Demolition 1926.850 Preparatory operations 1926.850(i) “All floor openings, not used as material drops, shall be covered over with material substantial enough to support the weight of any load which may be imposed. Such material shall be properly secured to prevent its accidental movement.” 11
  • 12. 12
  • 13. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart T - Demolition 1926.852 Chutes 1926.852(a) “No material shall be dropped to any point lying outside the exterior walls of the structure unless the area is effectively protected.” 1926.852(b) “All materials chutes, or sections thereof, at an angle of more than 450 from the horizontal , shall be entirely enclosed, except for openings equipped with closures at or about floor level for the insertion of materials. The openings shall not exceed 48 inches in height measured along the wall of the chute. At all stories below the top floor, such openings shall be kept closed 13 when not in use.”
  • 14. 14
  • 15. 15
  • 16. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart T - Demolition 1926.853 Removal of materials through floor openings “Any openings cut in a floor for the disposal of materials shall be no larger in size than 25 percent of the aggregate of the total floor area, unless the lateral supports of the removed flooring remain in place. Floors weakened or otherwise made unsafe by demolition operations shall be shored to carry safely the intended imposed load from demolition operations.” 16
  • 17. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart T - Demolition 1926.859 Mechanical demolition 1926.859(a) “No workers shall be permitted in any area, which can be adversely affected by demolition operations, when balling or clamming is being performed. Only those workers necessary for the performance of the operations shall be permitted in this area at any other time.” 17
  • 18. 18
  • 19. ! 48" Max Openings kept closed when not in use
  • 20. •Guardrails installed ! where men drop 48" Max debris •Space between chute and edge of floor solidly covered
  • 21. ! 48" Max •Toeboard or bumper •4” thick X 6” high •Securely attached
  • 22.
  • 23. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart T - Demolition 1926.859 Mechanical demolition 1926.859(b) “The weight of the demolition ball shall not exceed 50 percent of the crane’s rated load, based on the length of the boom and the maximum angle of operation at which the demolition ball will be used, or it shall not exceed 25 percent of the nominal breaking strength of the line by which it is suspended, whichever results in a lesser value.” 23
  • 24. 24