SlideShare a Scribd company logo
1 of 15
Download to read offline
March 8, 2021
Eglinton Crosstown LRT
Leaside-Laird CLC
Leaside Station
LEASIDE STATION UPDATE
3
Activity Location Approx. Date & Duration
Station Box Construction
โ€ข Waterproofing
โ€ข Rebar, steel, and conduit installations
โ€ข Formwork
โ€ข Concrete pours
โ€ข Masonry block installations
Underneath Eglinton Avenue within the Station Box
โ€ข Crews are currently working at the roof level
Underway through mid 2021
Main Entrance Construction
โ€ข Rebar, steel and M&E installations
โ€ข Formwork installations
โ€ข Concrete pours
โ€ข Masonry block installations
South east corner of Bayview Ave and Eglinton Ave
โ€ข Crews are currently working at surface level
Underway through early 2021
โ€ข 24-hour work ongoing Monday through Saturday
for approximately five (5) months
Secondary Entrance Construction
โ€ข Waterproofing
โ€ข Rebar, steel, and conduit installations
โ€ข Formwork
โ€ข Concrete pours
North west corner of Bayview Ave and Eglinton Ave
โ€ข Crews are working approx. 5m below surface level
Underway through early 2021
โ€ข 24-hour work ongoing Monday through Saturday
for approximately five (5) months
LEASIDE STATION EXTENDED HOURS โ€“ STATION ENTRANCES
4
โ€ข Extended construction hours are underway at Leaside Stationโ€™s main and secondary entrance sites.
โ€ข Work will take place on a 24-hour basis Monday โ€“ Saturday and between 7:00 a.m. โ€“ 5:00 p.m. on Sundays for
approximately six (6) months
โ€ข Activities will include formwork installation and site maintenance work
Noise mitigation measures include:
โœ“ Transport construction materials and equipment into the work zone before 11:00 p.m.
โœ“ No deliveries will be scheduled between 11:00 p.m. โ€“ 5:00 a.m.
โœ“ Use of white noise/broadband back-up alarms on trucks and equipment.
โœ“ Carefully lift and lower loads into the work zone.
โœ“ Limit the use of construction vehicles (skid steerers/loaders) between 11:00 p.m. โ€“ 6:00 a.m.
โœ“ Pre-shift briefing on operational mitigation measures will be conducted.
INSERT FOOTER
MAIN ENTRANCE
FORMWORK
LEASIDE STATION LOOK-AHEAD
5
Year What to Expect
2021
โ€ข Construction will continue to take place on a 24-hour basis Monday through Saturday for
approximately five (5) months.
โ€ข Periodic lane closures may be required to facilitate deliveries, dewatering and concrete works.
โ€ข Permanent works are ongoing within the station box and entrances, and will continue into early
2021, including waterproofing, formwork, rebar installation and concrete works.
โ€ข Above ground construction of the Main Entrance is underway, with crews installing forms for the
roof slab and street level walls.
โ€ข Architectural works, including masonry block installations, have begun at the Main Entrance.
Structural steel and pre-cast panel installations are expected to start in Spring 2021.
โ€ข Construction of the Secondary Entrance is progressing upwards and is expected to reach street
level in Spring 2021.
CURRENT TRAFFIC CONFIGURATION
6
Through Summer 2021.
CONSTRUCTION PROGRESS PHOTOS
7
SECONDARY ENTRANCE
PROGRESS
REBAR & CONDUIT INSTALLATIONS AT
THE STATION BOX ROOF
CONSTRUCTION PROGRESS PHOTOS
MAIN ENTRANCE OVERVIEW
8
WALL FORMWORK ROOF FORMWORK
Laird Station
LAIRD STATION UPDATE
10
Activity Location Approx. Date & Duration
Main Entrance Construction
Shaft build-back and architectural works
Main Entrance
Monday โ€“ Sunday, 6:00 a.m. โ€“ 1:00 a.m.
through March 2021
Secondary Entrance Construction
Shaft build-back and wall construction
Secondary Entrance
Monday โ€“ Sunday, 24 hours through March
2021
Station Box
Track installation, TVS, mechanical and
electrical installation
Beneath Eglinton Ave Underway through spring 2021
Crane Demobilization
Short-term traffic change
Main Entrance As early as mid March 2021 for one (1) week
Escalator Delivery
Short-term traffic change (same as crane
demobilization configuration)
Main Entrance As early as mid March 2021 for two (2) weeks
CURRENT TRAFFIC CONFIGURATION
11
Until approximately mid March 2021
UPCOMING TRAFFIC CONFIGURATION
12
As early as mid March 2021 โ€“ April 2021
CONSTRUCTION PROGRESS PHOTOS
13
SECONDARY ENTRANCE
CAVERN
RETAINING WALL CONSTRUCTION
NORTH SIDE OF EGLINTON
EAST OF BRENTCLIFFE ROAD
14
โ€ข This retaining wall is required to hold the
embankment created from the widened Eglinton
Ave.
โ€ข Retaining wall construction was put on hold
while temporary slope stabilization work took
place
โ€ข Slope stabilization work is now complete and
retaining wall construction will resume in March
2021
โ€ข Slope restoration design is in review by CTS and
the City of Toronto
Leaside and Laird CLC 8Mar2021

More Related Content

What's hot

Central open house - oct 2019
Central open house - oct 2019Central open house - oct 2019
Central open house - oct 2019
Crosstown TO
ย 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018
Crosstown TO
ย 
Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018
Crosstown TO
ย 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Crosstown TO
ย 
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
Crosstown TO
ย 
Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018
Crosstown TO
ย 
Eglinton & Mt Pleasant CLC - March 2020
Eglinton & Mt Pleasant CLC - March 2020 Eglinton & Mt Pleasant CLC - March 2020
Eglinton & Mt Pleasant CLC - March 2020
Crosstown TO
ย 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Crosstown TO
ย 

What's hot (20)

CLC Eglinton and Mount Pleasant
CLC Eglinton and Mount PleasantCLC Eglinton and Mount Pleasant
CLC Eglinton and Mount Pleasant
ย 
Central East Crosstown Open House Presentation
Central East Crosstown Open House PresentationCentral East Crosstown Open House Presentation
Central East Crosstown Open House Presentation
ย 
CLC: Leaside and Laird - Sept 13 2021
CLC: Leaside and Laird - Sept 13 2021 CLC: Leaside and Laird - Sept 13 2021
CLC: Leaside and Laird - Sept 13 2021
ย 
CLC Pharmacy to Kennedy January
CLC Pharmacy to Kennedy JanuaryCLC Pharmacy to Kennedy January
CLC Pharmacy to Kennedy January
ย 
Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021
ย 
Central open house - oct 2019
Central open house - oct 2019Central open house - oct 2019
Central open house - oct 2019
ย 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018
ย 
Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018Public Meeting of Facility Services Building at Eglinton Station - May 2018
Public Meeting of Facility Services Building at Eglinton Station - May 2018
ย 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
ย 
Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021
ย 
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
ย 
Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018Leaside - Laird Construction Liaison Committee Meeting - May 2018
Leaside - Laird Construction Liaison Committee Meeting - May 2018
ย 
Eglinton & Mt Pleasant CLC - March 2020
Eglinton & Mt Pleasant CLC - March 2020 Eglinton & Mt Pleasant CLC - March 2020
Eglinton & Mt Pleasant CLC - March 2020
ย 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021
ย 
Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021
ย 
Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020
ย 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
ย 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020Eglinton and Mount Pleasant Construction Liaison Committee Meeting  - Jan 2020
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2020
ย 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meeting
ย 
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021Leaside-Laird CLC Meeting - Presentation - November 8, 2021
Leaside-Laird CLC Meeting - Presentation - November 8, 2021
ย 

Similar to Leaside and Laird CLC 8Mar2021

Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018
Crosstown TO
ย 
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Crosstown TO
ย 
Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018
Crosstown TO
ย 

Similar to Leaside and Laird CLC 8Mar2021 (20)

Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021
ย 
Leaside& Laird CLC - 12July2021
Leaside& Laird CLC - 12July2021Leaside& Laird CLC - 12July2021
Leaside& Laird CLC - 12July2021
ย 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021
ย 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
ย 
Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November
ย 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021
ย 
Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)
ย 
Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018
ย 
Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)
ย 
Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019
ย 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
ย 
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
ย 
CLC Pharmacy to Kennedy 2021
CLC Pharmacy to Kennedy 2021CLC Pharmacy to Kennedy 2021
CLC Pharmacy to Kennedy 2021
ย 
Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018
ย 
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxChaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
ย 
Avenue & Chaplin CLC - Construction Update: January 5, 2022
Avenue & Chaplin CLC - Construction Update: January 5, 2022Avenue & Chaplin CLC - Construction Update: January 5, 2022
Avenue & Chaplin CLC - Construction Update: January 5, 2022
ย 
Eglinton & Mt Pleasant CLC - January 2022
Eglinton & Mt Pleasant CLC - January 2022Eglinton & Mt Pleasant CLC - January 2022
Eglinton & Mt Pleasant CLC - January 2022
ย 
Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021
ย 
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021
ย 
Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)
ย 

More from Crosstown TO

More from Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
ย 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
ย 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
ย 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
ย 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
ย 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
ย 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
ย 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
ย 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
ย 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
ย 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
ย 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
ย 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
ย 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
ย 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
ย 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
ย 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
ย 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
ย 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
ย 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
ย 

Recently uploaded

Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
SUHANI PANDEY
ย 
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
SUHANI PANDEY
ย 
Russian๐ŸŒDazzling Hottie Getโ˜Ž๏ธ 9053900678 โ˜Ž๏ธcall girl In Chandigarh By Chandig...
Russian๐ŸŒDazzling Hottie Getโ˜Ž๏ธ 9053900678 โ˜Ž๏ธcall girl In Chandigarh By Chandig...Russian๐ŸŒDazzling Hottie Getโ˜Ž๏ธ 9053900678 โ˜Ž๏ธcall girl In Chandigarh By Chandig...
Russian๐ŸŒDazzling Hottie Getโ˜Ž๏ธ 9053900678 โ˜Ž๏ธcall girl In Chandigarh By Chandig...
Chandigarh Call girls 9053900678 Call girls in Chandigarh
ย 
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakurbest call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
SUHANI PANDEY
ย 
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
ย 
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
SUHANI PANDEY
ย 
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
ย 

Recently uploaded (20)

A PPT on digital India initiative by Government of India
A PPT on digital India initiative by Government of IndiaA PPT on digital India initiative by Government of India
A PPT on digital India initiative by Government of India
ย 
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
Nanded City ? Russian Call Girls Pune - 450+ Call Girl Cash Payment 800573673...
ย 
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
VIP Model Call Girls Narhe ( Pune ) Call ON 8005736733 Starting From 5K to 25...
ย 
Top Rated Pune Call Girls Bhosari โŸŸ 6297143586 โŸŸ Call Me For Genuine Sex Ser...
Top Rated  Pune Call Girls Bhosari โŸŸ 6297143586 โŸŸ Call Me For Genuine Sex Ser...Top Rated  Pune Call Girls Bhosari โŸŸ 6297143586 โŸŸ Call Me For Genuine Sex Ser...
Top Rated Pune Call Girls Bhosari โŸŸ 6297143586 โŸŸ Call Me For Genuine Sex Ser...
ย 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
ย 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
ย 
Russian๐ŸŒDazzling Hottie Getโ˜Ž๏ธ 9053900678 โ˜Ž๏ธcall girl In Chandigarh By Chandig...
Russian๐ŸŒDazzling Hottie Getโ˜Ž๏ธ 9053900678 โ˜Ž๏ธcall girl In Chandigarh By Chandig...Russian๐ŸŒDazzling Hottie Getโ˜Ž๏ธ 9053900678 โ˜Ž๏ธcall girl In Chandigarh By Chandig...
Russian๐ŸŒDazzling Hottie Getโ˜Ž๏ธ 9053900678 โ˜Ž๏ธcall girl In Chandigarh By Chandig...
ย 
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
ย 
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
ย 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
ย 
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakurbest call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
ย 
Top Rated Pune Call Girls Hadapsar โŸŸ 6297143586 โŸŸ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Hadapsar โŸŸ 6297143586 โŸŸ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Hadapsar โŸŸ 6297143586 โŸŸ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Hadapsar โŸŸ 6297143586 โŸŸ Call Me For Genuine Sex Se...
ย 
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Agra 7001035870 Whatsapp Number, 24/07 Booking
ย 
Scaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processScaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP process
ย 
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
ย 
Chakan ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Chakan ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Chakan ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Chakan ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
ย 
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...Call On 6297143586  Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
Call On 6297143586 Yerwada Call Girls In All Pune 24/7 Provide Call With Bes...
ย 
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
ย 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - Poster
ย 
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
ย 

Leaside and Laird CLC 8Mar2021

  • 1. March 8, 2021 Eglinton Crosstown LRT Leaside-Laird CLC
  • 3. LEASIDE STATION UPDATE 3 Activity Location Approx. Date & Duration Station Box Construction โ€ข Waterproofing โ€ข Rebar, steel, and conduit installations โ€ข Formwork โ€ข Concrete pours โ€ข Masonry block installations Underneath Eglinton Avenue within the Station Box โ€ข Crews are currently working at the roof level Underway through mid 2021 Main Entrance Construction โ€ข Rebar, steel and M&E installations โ€ข Formwork installations โ€ข Concrete pours โ€ข Masonry block installations South east corner of Bayview Ave and Eglinton Ave โ€ข Crews are currently working at surface level Underway through early 2021 โ€ข 24-hour work ongoing Monday through Saturday for approximately five (5) months Secondary Entrance Construction โ€ข Waterproofing โ€ข Rebar, steel, and conduit installations โ€ข Formwork โ€ข Concrete pours North west corner of Bayview Ave and Eglinton Ave โ€ข Crews are working approx. 5m below surface level Underway through early 2021 โ€ข 24-hour work ongoing Monday through Saturday for approximately five (5) months
  • 4. LEASIDE STATION EXTENDED HOURS โ€“ STATION ENTRANCES 4 โ€ข Extended construction hours are underway at Leaside Stationโ€™s main and secondary entrance sites. โ€ข Work will take place on a 24-hour basis Monday โ€“ Saturday and between 7:00 a.m. โ€“ 5:00 p.m. on Sundays for approximately six (6) months โ€ข Activities will include formwork installation and site maintenance work Noise mitigation measures include: โœ“ Transport construction materials and equipment into the work zone before 11:00 p.m. โœ“ No deliveries will be scheduled between 11:00 p.m. โ€“ 5:00 a.m. โœ“ Use of white noise/broadband back-up alarms on trucks and equipment. โœ“ Carefully lift and lower loads into the work zone. โœ“ Limit the use of construction vehicles (skid steerers/loaders) between 11:00 p.m. โ€“ 6:00 a.m. โœ“ Pre-shift briefing on operational mitigation measures will be conducted. INSERT FOOTER MAIN ENTRANCE FORMWORK
  • 5. LEASIDE STATION LOOK-AHEAD 5 Year What to Expect 2021 โ€ข Construction will continue to take place on a 24-hour basis Monday through Saturday for approximately five (5) months. โ€ข Periodic lane closures may be required to facilitate deliveries, dewatering and concrete works. โ€ข Permanent works are ongoing within the station box and entrances, and will continue into early 2021, including waterproofing, formwork, rebar installation and concrete works. โ€ข Above ground construction of the Main Entrance is underway, with crews installing forms for the roof slab and street level walls. โ€ข Architectural works, including masonry block installations, have begun at the Main Entrance. Structural steel and pre-cast panel installations are expected to start in Spring 2021. โ€ข Construction of the Secondary Entrance is progressing upwards and is expected to reach street level in Spring 2021.
  • 7. CONSTRUCTION PROGRESS PHOTOS 7 SECONDARY ENTRANCE PROGRESS REBAR & CONDUIT INSTALLATIONS AT THE STATION BOX ROOF
  • 8. CONSTRUCTION PROGRESS PHOTOS MAIN ENTRANCE OVERVIEW 8 WALL FORMWORK ROOF FORMWORK
  • 10. LAIRD STATION UPDATE 10 Activity Location Approx. Date & Duration Main Entrance Construction Shaft build-back and architectural works Main Entrance Monday โ€“ Sunday, 6:00 a.m. โ€“ 1:00 a.m. through March 2021 Secondary Entrance Construction Shaft build-back and wall construction Secondary Entrance Monday โ€“ Sunday, 24 hours through March 2021 Station Box Track installation, TVS, mechanical and electrical installation Beneath Eglinton Ave Underway through spring 2021 Crane Demobilization Short-term traffic change Main Entrance As early as mid March 2021 for one (1) week Escalator Delivery Short-term traffic change (same as crane demobilization configuration) Main Entrance As early as mid March 2021 for two (2) weeks
  • 11. CURRENT TRAFFIC CONFIGURATION 11 Until approximately mid March 2021
  • 12. UPCOMING TRAFFIC CONFIGURATION 12 As early as mid March 2021 โ€“ April 2021
  • 14. RETAINING WALL CONSTRUCTION NORTH SIDE OF EGLINTON EAST OF BRENTCLIFFE ROAD 14 โ€ข This retaining wall is required to hold the embankment created from the widened Eglinton Ave. โ€ข Retaining wall construction was put on hold while temporary slope stabilization work took place โ€ข Slope stabilization work is now complete and retaining wall construction will resume in March 2021 โ€ข Slope restoration design is in review by CTS and the City of Toronto