Construction Liaison Committee meeting for March 2021

CLC Pharmacy to Kennedy 2021

  1. 1. March 30, 2021 Eglinton Crosstown LRT Construction Update Victoria Park Avenue to Kennedy Station
  2. 2. Section Three and Four At-Grade: O’Connor Stop to Ionview Stop
  3. 3. CONSTRUCTION ACTIVITIES 3 Location Activity Approx. Date & Duration O’Connor Stop to Ionview Stop • Light poles installation (stops) • Completed March O’Connor Stop (Victoria Park Ave) • Shelter finishing activities; platform ramps, walls • Ongoing through April Pharmacy Stop • Shelter finishing activities; platform ramps, walls • Ongoing through April Hakimi Lebovic Stop • Concrete for both east & west planter curbs • Shelter finishing activities; platform ramps, walls • Completed March • Ongoing through April Golden Mile Stop (Warden Ave) • Shelter finishing activities; platform ramps, walls • Ongoing through April Birchmount Stop • Shelter finishing activities; platform ramps, walls • Ongoing through April Massey Creek Culvert • West wing wall construction • Backfill • Completed March • Ongoing through April Ionview Stop • Shelter finishing activities; platform ramps, walls • Ongoing until April
  4. 4. ROSEMOUNT DRIVE AND EGLINTON AVE E 4 Until as early as April 2021 • North side closure for Massey Creek Construction • Crews have completed filling old culvert • Crews have completed the wingwall construction • Crews continue with backfilling and minor paving activities
  5. 5. CONSTRUCTION PROGRESS PHOTOS 5 CURB COMPLETE O’CONNOR STOP PLANTERS COMPLETED PHARMACY STOP
  6. 6. CONSTRUCTION PROGRESS PHOTOS 6 PLANTERS COMPLETED PHARMACY STOP CURBS COMPLETE BIRCHMOUNT STOP
  7. 7. Kennedy Station
  8. 8. KENNEDY STATION UPDATE 8 Location Activity Approx. Date & Duration Kennedy Rd and Eglinton Ave E • Pedestrian Change • Ongoing for approx. six months Kennedy Portal (west of Kennedy Road) • Track works • Ongoing through Spring Kennedy Station Main Entrance • Conduit installation, plumbing and sheet metal works, tiling, masonry works • Elevator & escalator installation • TPSS & TVS electrical fit up • Ongoing through 2021 • Ongoing through 2021 • Ongoing until May Kennedy Station Box • Concrete works, rebar, and shoring • Floor tiling • Ongoing through Spring • Ongoing through 2021 Kennedy Station GO Entrance and Platform • GO entrance precast installation • Excavation & concrete works • Retaining wall construction • Weekend utility work • Completed March • Ongoing through June • Ongoing through Spring • April 2 - 4 Kennedy Station – East of GO • Final invert pour; waterproofing • Concrete & masonry works • Platform construction, track & drainage alignment • Electrical and mechanical works • Completed March • Ongoing through Spring • Ongoing through 2021 • Ongoing through 2021
  9. 9. KENNEDY CURRENT TRAFFIC CONFIGURATION 9 March 2021 for approx. six months
  10. 10. UTILITY CASING CROSSING 10 • Installation of utility casing includes the use of excavators, front end loaders, rollers, and tampers • Crews will be excavating to install the casing, and then refilling and levelling the demolition site with fresh granular material and compaction of the material into the ground • Noise and vibration can be expected April 2-4, 2021
  11. 11. GO WEST PLATFORM RELOCATION AND PEDESTRIAN DETOUR 11 • As part of GO Transit improvements at Kennedy GO Station, crews at Kennedy Station have temporarily relocated the west GO Transit platform • Pedestrians will be rerouted through the Kennedy TTC Station • This configuration will remain in place for approximately one year. August 17, 2020 for approx. one year
  12. 12. CONSTRUCTION PROGRESS PHOTOS 12 CONCRETE WORKS GO EAST PLATFORM CEILING GRID INSTALLATION PLATFORM LEVEL
  13. 13. CONSTRUCTION PROGRESS PHOTOS 13 REBAR AND CONCRETE WORK STATION BOX PRECAST INSTALLATION GO ENTRANCE

×