DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM

  1. 1. TAJUKDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
  2. 2. PWD 203A Standard Form of Contract (Ed.1983)This form of contract contain no expressed provision that allows the Contractor tosuspend the works if his payment was unduly delayed or he is not getting hispayment at all.In the PWD203A Form of Contract (2007), it is stipulated that the period forhonouring the certificate is 30 days from the date of the issuance of the certificate.Clause 30.1 of the PAM Form of Contract (2006) stated that the period of honouringcertificate is within 21 days after the issuance of the certificate. Any payment madelater than the stipulated time frame can be considered as late or delayed paymentPAM Form of Contract 1998There is no express provision that permits the Contractor to suspend his work whenhe is not paid or his payment was not forthcoming in due time after receiving theInterim Certificate. Clause 25(1) (ii) and Clause 23.4 state that the Contractor is toproceed regularly and diligently and he is to use his best endeavours to preventdelay. The clauses clearly demand the Contractor to show a good performance andcontinue with the work to prevent disruption to the progress of the project.PAM Form of Contract 2006But the new PAM 2006 contains provision that give the Contractor to suspend theprogress of work if the Contractor is faced with problem of delayed or non paymentby the Employer. It is clearly stated in clause 30.7. But it requires the Contractor togive a written a notice to Employer with reason to suspend the works until theEmployer has paid the amount due to the Contractor
  3. 3. THE DIFFERENCE BETWEEN JKR/PWD AND PAM CONTRACT JKR/PWD PAM- Standard form of contract for government and - Standard form of contract for private sectorpublic sector project. and traditional general contract- JKR/PWD covered all building and engineering - PAM covered building work only.work. - PAM contract not covered- Standard form for JKR/PWD are : I. Engineering construction contract (other I. 203 (Rev 10/83) – without quantities than building II. 203A (Rev 10/83) – with quantities II. Package deal / Turnkey III. 203N (Rev 10/83) – for NSC III. Management type IV. Domestic subcontract IV. 203P (Rev 10/83) – for nominated V. Serial contract suppliers VI. Periodic /Term contract V. PWP Form DB/T (2000 Edn) For Design VII. Continuation control And Build Turnkey Contracts VIII. Other miscellaneous contract Miscellaneous : - Standard form for PAM : I. CIDB Form for building contracts 2000 (Building Works) Edn I. PAM 98 – with quantities II. Modified JKR/PWD Forms, eg LPK, MHA II. PAM 98 – without quantities etc III. PAM NSC 98
  4. 4. ISSUES PERIOD OF ISSUE OF PERIOD OF ISSUING AMOUNT INTERIM INTERIM HONOURING PERSON TO BE CERTIFICATE CERTIFICATE THE PAID OF SITE CERTIFICATE VALUATIONCONTRACTFORMPWD One month 14 days after 30 days from Superintending Value of [Clause 47(a)] site the Officer (S.O) Work203A valuation date of the Done + [Clause 47 (b)] issuance 90% of the Interim Material On Certificate Site [Clause 47(d)]PAM One Month Upon the 14 days from Architect Value of [Clause 30.2) receipt of the date Work Done1998 Contractors of the + 90% details issuance of Material On and particulars Interim Site [Clause 30.2] Certificate [Clause 30.2]

×