ID Task
Mode
%
Complete
Task Name Duration Start Finish Predecessors Baseline Start
1 100% Encanex Access Barge Project 173.55 daysThu 15/08/13 Sat 08/03/14 Thu 15/08/13
2 100% Contract Award 1 day Thu 15/08/13 Fri 16/08/13 Thu 15/08/13
3 100% Materials Procurement 122 days Mon 19/08/13 Fri 10/01/14 2FS+2 days Mon 19/08/13
4 100% Mobilize Containers to Fab shop -Halifax-134 days Mon 19/08/13 Fri 24/01/14 2FS+2 days Mon 19/08/13
5 100% Module 1 Containers (6 Containers) 30.35 days Sat 01/02/14 Sat 08/03/14 Sat 01/02/14
6 100% Place Insulation and Steel Plates in
Bottom of Containers
10 days Thu 13/02/14 Tue 25/02/14 4FS+16 days Thu 13/02/14
7 100% HVAC Penetrations 8 days Sat 15/02/14 Tue 25/02/14 6SS+2 days Sat 15/02/14
8 100% Window and Door Openings 8 days Sat 15/02/14 Tue 25/02/14 7SS Sat 15/02/14
9 100% Structural Re-Enforcement 11 days Mon 17/02/14 Sat 01/03/14 8SS+1 day Mon 17/02/14
10 100% NDT 11 days Tue 18/02/14 Mon 03/03/14 9SS+1 day Tue 18/02/14
11 100% Interior Tracking Installed 9 days Tue 18/02/14 Fri 28/02/14 9SS+1 day Tue 18/02/14
12 100% Exterior sand blasting 6 days Sat 22/02/14 Sat 01/03/14 11FS-5 days Sat 22/02/14
13 100% Primer and Painting 5 days Mon 24/02/14 Sat 01/03/14 12SS+1 day Mon 24/02/14
14 100% Rough wiring 1 day Wed 26/02/14 Thu 27/02/14 13FS-3 days Wed 26/02/14
15 100% Insulation Installation 1 day Thu 27/02/14 Fri 28/02/14 14SS+1 day Thu 27/02/14
16 100% Interior flooring Installation 9 days Tue 25/02/14 Fri 07/03/14 15FF+1 day Tue 25/02/14
17 100% Cladding, Arborite and Interior Walls 5 days Tue 25/02/14 Mon 03/03/14 13SS+1 day Tue 25/02/14
18 100% Window and Door Installation 2 days Wed 05/03/14 Fri 07/03/14 17 Wed 05/03/14
19 100% Interior Fixtures 12 days Fri 21/02/14 Fri 07/03/14 17SS-3 days Fri 21/02/14
20 100% Electrical Finish 7 days Thu 27/02/14 Fri 07/03/14 17SS+2 days Thu 27/02/14
21 100% Furnature Interior 6 days Fri 28/02/14 Fri 07/03/14 20SS+1 day Fri 28/02/14
22 100% Preparation for transportation to Quebic2 days Tue 04/03/14 Sat 08/03/14 21FF Tue 04/03/14
23 100% Sewage Tanks 26 days Sat 01/02/14 Tue 04/03/14 Sat 01/02/14
24 100% Pump Room 5.9 days Mon 03/03/14 Sat 08/03/14 Mon 03/03/14
25 100% Module 2 Containers ( 40 Containers) 151 days Mon 19/08/13 Fri 14/02/14 Mon 19/08/13
26 100% Place Insulation and Steel Plates in
Bottom of Containers
33 days Mon 19/08/13 Fri 27/09/13 4SS Mon 19/08/13
27 100% HVAC Penetrations 46 days Mon 26/08/13 Sat 19/10/13 26SS+6 days Mon 26/08/13
28 100% Window and Door Openings 127 days Mon 26/08/13 Thu 23/01/14 27SS Mon 26/08/13
29 100% Structural Re-Enforcement 118 days Fri 06/09/13 Fri 24/01/14 28SS+10 days Fri 06/09/13
30 100% NDT 20 days Thu 02/01/14 Sat 25/01/14 29FF+1 day Thu 02/01/14
31 100% Interior Tracking Installed 119 days Mon 09/09/13 Tue 28/01/14 29SS+2 days Mon 09/09/13
32 100% Exterior sand blasting 116 days Mon 16/09/13 Fri 31/01/14 31SS+6 days Mon 16/09/13
33 100% Primer and Painting 116 days Tue 17/09/13 Sat 01/02/14 32SS+1 day Tue 17/09/13
34 100% Rough wiring 112 days Mon 23/09/13 Sat 01/02/14 33SS+4 days Mon 23/09/13
35 100% Insulation Installation 60 days Mon 25/11/13 Tue 04/02/14 34FF+2 days Mon 25/11/13
36 100% Interior flooring Installation 87 days Mon 28/10/13 Fri 07/02/14 35FF+3 days Mon 28/10/13
37 100% Cladding, Arborite and Interior Walls 85 days Thu 31/10/13 Mon 10/02/14 36SS+3 days Thu 31/10/13
38 100% Window and Door Installation 41 days Mon 23/12/13 Mon 10/02/14 37SS+44 days Mon 23/12/13
39 100% Interior Fixtures 54 days Mon 09/12/13 Tue 11/02/14 38SS-12 days Mon 09/12/13
17 10 31 21 12 02 23 14 04 25 15 06
01 January 21 February 11 April 01 June 21 July 11 September
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Critical
Critical Split
Baseline
Progress
Encanex Access, Captians, Power, cEMENT BARGES, ICS Baskets Projects
all- Sch-Rev A Page 1 3 March 14
ID Task
Mode
%
Complete
Task Name Duration Start Finish Predecessors Baseline Start
40 100% Electrical Finish 76 days Thu 14/11/13 Thu 13/02/14 37SS+12 days Thu 14/11/13
41 100% Furnature Interior 46 days Fri 20/12/13 Thu 13/02/14 40SS+30 days Fri 20/12/13
42 100% Final Preparation 46 days Fri 20/12/13 Thu 13/02/14 41SS Fri 20/12/13
43 100% Transportation to Quebic 42 days Thu 26/12/13 Fri 14/02/14 42SS+1 day Thu 26/12/13
44 100% Sewage Tanks Installation 65 days Fri 22/11/13 Fri 07/02/14 Fri 22/11/13
45 100% Module 3 Containers (36 Containers) 164.6 days Mon 26/08/13 Sat 08/03/14 Mon 26/08/13
46 100% Place Insulation and Steel Plates in
Bottom of Containers
145 days Mon 26/08/13 Thu 13/02/14 Mon 26/08/13
47 100% HVAC Penetrations 157 days Mon 26/08/13 Thu 27/02/14 Mon 26/08/13
48 100% Structural Re-Enforcement 145 days Fri 06/09/13 Tue 25/02/14 Fri 06/09/13
49 100% NDT 145 days Fri 06/09/13 Tue 25/02/14 Fri 06/09/13
50 100% Window and Door Openings 143 days Wed 11/09/13 Thu 27/02/14 Wed 11/09/13
51 100% Interior Tracking Installed 139 days Tue 17/09/13 Fri 28/02/14 Tue 17/09/13
52 100% exterior sand blasting 141 days Wed 18/09/13 Tue 04/03/14 Wed 18/09/13
53 100% Primer and Painting 141 days Wed 18/09/13 Tue 04/03/14 Wed 18/09/13
54 100% Rough wiring 133 days Tue 24/09/13 Fri 28/02/14 Tue 24/09/13
55 100% Insulation Installation 64 days Fri 20/12/13 Thu 06/03/14 Fri 20/12/13
56 100% Interior flooring Installation 86 days Mon 25/11/13 Thu 06/03/14 Mon 25/11/13
57 100% Cladding, Arborite and Interior Walls 79 days Tue 03/12/13 Thu 06/03/14 Tue 03/12/13
58 100% Window and Door Installation 21 days Mon 10/02/14 Thu 06/03/14 Mon 10/02/14
59 100% Electrical Finish 28 days Mon 03/02/14 Fri 07/03/14 Mon 03/02/14
60 100% furnature Interior 28 days Mon 03/02/14 Fri 07/03/14 Mon 03/02/14
61 100% Preparation for transportation to Quebic20 days Thu 13/02/14 Sat 08/03/14 Thu 13/02/14
62 91% Encanex Captain Bridge Project 31.9 days Mon 03/02/14 Wed 12/03/14 Mon 03/02/14
63 100% Contract Award 1 day Mon 03/02/14 Mon 03/02/14 Mon 03/02/14
64 100% Materials Procurement 26 days Mon 03/02/14 Wed 05/03/14 63SS Mon 03/02/14
65 82% Cabin 14.2 days Mon 24/02/14 Wed 12/03/14 Mon 24/02/14
66 100% HVAC Penetrations 2 days Mon 24/02/14 Tue 25/02/14 Mon 24/02/14
67 100% HVAC Ducting Fabrication 5 days Wed 26/02/14 Tue 04/03/14 66 Wed 26/02/14
68 100% Window and Door Openings 0 days Mon 24/02/14 Mon 24/02/14 66SS Mon 24/02/14
69 100% Structural Re-Enforcement 2 days Wed 26/02/14 Thu 27/02/14 66 Wed 26/02/14
70 100% NDT 1 day Thu 27/02/14 Thu 27/02/14 69FF Thu 27/02/14
71 100% Interior Tracking Installed 0.5 days Fri 28/02/14 Fri 28/02/14 70 Fri 28/02/14
72 100% checker plate steel flooring Installation0.5 days Fri 28/02/14 Fri 28/02/14 71 Fri 28/02/14
73 100% Exterior sand blasting 1 day Sat 01/03/14 Mon 03/03/14 72 Sat 01/03/14
74 100% Primer and Painting 1 day Sun 02/03/14 Mon 03/03/14 73 Sun 02/03/14
75 100% Interior Walls Panels Installation 1 day Mon 03/03/14 Tue 04/03/14 74 Mon 03/03/14
76 80% Electrical Rough wiring 4 days Tue 04/03/14 Sat 08/03/14 75 Tue 04/03/14
77 80% Fire /Gas system wiring 0.5 days Fri 07/03/14 Sat 08/03/14 76FF Fri 07/03/14
78 100% Fire supression system Installation 1 day Wed 05/03/14 Thu 06/03/14 75FS+1 day Wed 05/03/14
79 80% Electrical Finish / Dedectors Installation2 days Thu 06/03/14 Sat 08/03/14 76FF,77FF Thu 06/03/14
24/02
17 10 31 21 12 02 23 14 04 25 15 06
01 January 21 February 11 April 01 June 21 July 11 September
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Critical
Critical Split
Baseline
Progress
Encanex Access, Captians, Power, cEMENT BARGES, ICS Baskets Projects
all- Sch-Rev A Page 2 3 March 14
ID Task
Mode
%
Complete
Task Name Duration Start Finish Predecessors Baseline Start
80 100% HVAC Installation 3 days Tue 04/03/14 Fri 07/03/14 67,75 Tue 04/03/14
81 100% Window and Door Installation 1 day Thu 06/03/14 Fri 07/03/14 80FF Thu 06/03/14
82 0% Desks Interior 1 day Sat 08/03/14 Mon 10/03/14 80FS+1 day Sat 08/03/14
83 0% Final FAT / Commissioning 1 day Mon 10/03/14 Tue 11/03/14 82 Mon 10/03/14
84 0% HVAC Unit Dismantling / Packaging 1 day Tue 11/03/14 Wed 12/03/14 83 Tue 11/03/14
85 0% Decommissioning and Packaging 1 day Tue 11/03/14 Wed 12/03/14 83 Tue 11/03/14
86 0% Shipping 0 days Wed 12/03/14 Wed 12/03/14 85 Wed 12/03/14
87 53% Encanex Power Barge Project 37.1 days Mon 03/02/14 Tue 18/03/14 Mon 03/02/14
88 100% Contract Award 1 day Mon 03/02/14 Mon 03/02/14 Mon 03/02/14
89 100% Materials Procurement 22 days Mon 03/02/14 Fri 28/02/14 88SS Mon 03/02/14
90 27% Tool Crib Cabin 13 days Mon 03/03/14 Tue 18/03/14 Mon 03/03/14
91 100% Place Insulation and Steel Plates in Bottom of Containers2 days Mon 03/03/14 Tue 04/03/14 Mon 03/03/14
92 99% HVAC Penetrations 1 day Mon 03/03/14 Tue 04/03/14 91SS+1 day Mon 03/03/14
93 100% Window and Door Openings 1 day Tue 04/03/14 Tue 04/03/14 92SS Tue 04/03/14
94 50% Structural Re-Enforcement 2 days Wed 05/03/14 Thu 06/03/14 93 Wed 05/03/14
95 50% NDT 2 days Wed 05/03/14 Thu 06/03/14 94FF Wed 05/03/14
96 20% Interior Tracking Installed 1 day Fri 07/03/14 Fri 07/03/14 94 Fri 07/03/14
97 0% Rough wiring 1 day Sat 08/03/14 Mon 10/03/14 96 Sat 08/03/14
98 0% Exterior sand blasting 2 days Mon 10/03/14 Wed 12/03/14 97 Mon 10/03/14
99 0% Primer and Painting 2 days Mon 10/03/14 Wed 12/03/14 98SS Mon 10/03/14
100 0% Insulation Installation 1 day Wed 12/03/14 Thu 13/03/14 99 Wed 12/03/14
101 0% Interior flooring Installation 1 day Wed 12/03/14 Thu 13/03/14 100SS Wed 12/03/14
102 0% A0, A60,Cladding, Arborite and Interior Walls2 days Thu 13/03/14 Sat 15/03/14 101 Thu 13/03/14
103 0% Window and Door Installation 2 days Thu 13/03/14 Sat 15/03/14 102SS Thu 13/03/14
104 0% Electrical Finish 1 day Sat 15/03/14 Mon 17/03/14 102 Sat 15/03/14
105 0% Furnature Interior 1 day Sat 15/03/14 Mon 17/03/14 104SS Sat 15/03/14
106 0% Preparation for transportation 1 day Mon 17/03/14 Tue 18/03/14 105 Mon 17/03/14
107 30% Comm/Data Room 11.5 days Wed 05/03/14 Tue 18/03/14 Wed 05/03/14
108 100% Place Insulation and Steel Plates in Bottom of Containers2 days Wed 05/03/14 Thu 06/03/14 91 Wed 05/03/14
109 100% Door Openings 0.5 days Thu 06/03/14 Thu 06/03/14 108FF Thu 06/03/14
110 0% HVAC Penetrations 0 days Fri 07/03/14 Fri 07/03/14 109FS+1 day Fri 07/03/14
111 70% Structural Re-Enforcement 2 days Fri 07/03/14 Mon 10/03/14 109 Fri 07/03/14
112 70% NDT 2 days Fri 07/03/14 Mon 10/03/14 111FF Fri 07/03/14
113 0% Interior Tracking Installed 0.5 days Mon 10/03/14 Mon 10/03/14 111 Mon 10/03/14
114 0% Rough wiring 0.5 days Mon 10/03/14 Tue 11/03/14 113 Mon 10/03/14
115 0% Exterior sand blasting 2 days Tue 11/03/14 Thu 13/03/14 114 Tue 11/03/14
116 0% Primer and Painting 2 days Tue 11/03/14 Thu 13/03/14 115SS Tue 11/03/14
117 0% Insulation Installation 1 day Thu 13/03/14 Fri 14/03/14 116 Thu 13/03/14
118 0% Interior flooring Installation 1 day Thu 13/03/14 Fri 14/03/14 117SS Thu 13/03/14
119 0% A0, A60,Cladding, Arborite and Interior Walls2 days Fri 14/03/14 Mon 17/03/14 118 Fri 14/03/14
120 0% Door Installation 0.5 days Fri 14/03/14 Fri 14/03/14 119SS Fri 14/03/14
12/03
07/03
17 10 31 21 12 02 23 14 04 25 15 06
01 January 21 February 11 April 01 June 21 July 11 September
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Critical
Critical Split
Baseline
Progress
Encanex Access, Captians, Power, cEMENT BARGES, ICS Baskets Projects
all- Sch-Rev A Page 3 3 March 14
ID Task
Mode
%
Complete
Task Name Duration Start Finish Predecessors Baseline Start
121 0% Electrical Finish 0.5 days Mon 17/03/14 Mon 17/03/14 119 Mon 17/03/14
122 0% Preparation for transportation 1 day Mon 17/03/14 Tue 18/03/14 121 Mon 17/03/14
123 0% Closing Out Project 1 day Mon 17/03/14 Tue 18/03/14 Mon 17/03/14
124 0% Shipping Documents Sign-Off and shipping1 day Mon 17/03/14 Tue 18/03/14 106SS,122SS Mon 17/03/14
125 9% Encanex Cement Barge Project 60.5 days Mon 03/02/14 Tue 15/04/14 Mon 03/02/14
126 100% Contract Award 1 day Mon 03/02/14 Mon 03/02/14 Mon 03/02/14
127 55% Materials Procurement 48 days Mon 03/02/14 Mon 31/03/14 126SS Mon 03/02/14
128 0% Module 1 Containers (24 Containers, 1
S.T & P.R)
31 days Mon 10/03/14 Tue 15/04/14 Mon 10/03/14
129 0% Place Insulation and Steel Plates in Bottom of Containers12 days Mon 10/03/14 Mon 24/03/14 Mon 10/03/14
130 0% HVAC Penetrations 12 days Tue 11/03/14 Wed 26/03/14 129SS+2 days Tue 11/03/14
131 0% Window and Door Openings 12 days Wed 12/03/14 Wed 26/03/14 130SS Wed 12/03/14
132 0% Structural Re-Enforcement 14 days Thu 13/03/14 Sat 29/03/14 129SS+1 day,130SS+1 day,131SS+1 dayThu 13/03/14
133 0% Required Welding Complete and NDT 12 days Sat 15/03/14 Sat 29/03/14 132FF Sat 15/03/14
134 0% Interior Tracking Installed 14 days Fri 14/03/14 Mon 31/03/14 132SS+1.5 daysFri 14/03/14
135 0% Rough wiring 18 days Sat 15/03/14 Sat 05/04/14 134SS+1 day Sat 15/03/14
136 0% Exterior sand blasting 19 days Mon 17/03/14 Tue 08/04/14 135SS+1 day Mon 17/03/14
137 0% Primer and Painting 19 days Tue 18/03/14 Wed 09/04/14 136SS+0.5 daysTue 18/03/14
138 0% Cladding, Arborite and Interior Walls 18 days Thu 20/03/14 Thu 10/04/14 137SS+2 days Thu 20/03/14
139 0% Insulation Installation 10 days Thu 27/03/14 Tue 08/04/14 138FF-2 days Thu 27/03/14
140 0% Interior Fixtures 8 days Wed 02/04/14 Fri 11/04/14 138FF+1 day Wed 02/04/14
141 0% Electrical Finish 17 days Sat 22/03/14 Fri 11/04/14 138SS+2 days,140FFSat 22/03/14
142 0% Interior flooring Installation 18 days Sat 22/03/14 Sat 12/04/14 138SS+2 days,140FF+1 day,141FF+1 daySat 22/03/14
143 0% Window and Door Installation 18 days Mon 24/03/14 Mon 14/04/14 138SS+3 days,140FF+2 daysMon 24/03/14
144 0% Caulking Completion 19 days Mon 24/03/14 Tue 15/04/14 138SS+3 days,143FF+1 dayMon 24/03/14
145 0% Sewage Tank & Pump Room 12 days Mon 31/03/14 Mon 14/04/14 132FS+1 day Mon 31/03/14
146 0% Shipping 18 days Tue 25/03/14 Tue 15/04/14 144SS+1 day Tue 25/03/14
147 8% ICS Baskets 32.6 days Mon 03/03/14 Thu 10/04/14 Mon 03/03/14
148 20% Materials Procurement 15 days Mon 03/03/14 Thu 20/03/14 Mon 03/03/14
149 0% Fabrication of Baskets 12.8 days Mon 17/03/14 Mon 31/03/14 Mon 17/03/14
150 0% Painting 4 days Tue 01/04/14 Fri 04/04/14 149 Tue 01/04/14
151 0% Lifting/Load Test 3 days Sat 05/04/14 Wed 09/04/14 150 Sat 05/04/14
152 0% Shipping 1 day Wed 09/04/14 Thu 10/04/14 151 Wed 09/04/14
153 0% NSCSA Confined Space Training Container 55.2 days Wed 05/03/14 Fri 09/05/14 Wed 05/03/14
154 0% Contract Award 1 day Wed 05/03/14 Wed 05/03/14 Wed 05/03/14
155 0% Materials Procurement 20 days Mon 24/03/14 Wed 16/04/14 154FS+10 daysMon 24/03/14
156 0% Cabin 16.5 days Sat 19/04/14 Fri 09/05/14 Sat 19/04/14
157 0% HVAC Penetrations 1 day Sat 19/04/14 Mon 21/04/14 155FS+3 days Sat 19/04/14
158 0% Window/ Door/ Man Hole Openings 2 days Mon 21/04/14 Wed 23/04/14 157SS+1 day Mon 21/04/14
159 0% Container Dividing (Partitions) Installation2 days Wed 23/04/14 Fri 25/04/14 158 Wed 23/04/14
160 0% Structural Re-Enforcement 2 days Fri 25/04/14 Mon 28/04/14 159 Fri 25/04/14
17 10 31 21 12 02 23 14 04 25 15 06
01 January 21 February 11 April 01 June 21 July 11 September
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Critical
Critical Split
Baseline
Progress
Encanex Access, Captians, Power, cEMENT BARGES, ICS Baskets Projects
all- Sch-Rev A Page 4 3 March 14
ID Task
Mode
%
Complete
Task Name Duration Start Finish Predecessors Baseline Start
161 0% NDT 1 day Sat 26/04/14 Mon 28/04/14 160FF Sat 26/04/14
162 0% Interior Tracking Installed 1 day Mon 28/04/14 Tue 29/04/14 161 Mon 28/04/14
163 0% Electrical Rough wiring 1 day Tue 29/04/14 Wed 30/04/14 162 Tue 29/04/14
164 0% Exterior sand blasting 0.5 days Wed 30/04/14 Wed 30/04/14 163 Wed 30/04/14
165 0% Primer and Painting 1 day Thu 01/05/14 Thu 01/05/14 164 Thu 01/05/14
166 0% 3/4'' plywood flooring Installation 1 day Fri 02/05/14 Fri 02/05/14 165 Fri 02/05/14
167 0% 3/8'' plywood Interior Walls Panels Installation1 day Sat 03/05/14 Mon 05/05/14 166 Sat 03/05/14
168 0% Farm Fan with Louvers Installation 0.5 days Mon 05/05/14 Mon 05/05/14 167 Mon 05/05/14
169 0% Electrical Finish Installation 1 day Mon 05/05/14 Tue 06/05/14 167 Mon 05/05/14
170 0% Culverts Installation 1 day Tue 06/05/14 Wed 07/05/14 169 Tue 06/05/14
171 0% Man Hole Covers / Door Installation 2 days Mon 05/05/14 Wed 07/05/14 167 Mon 05/05/14
172 0% Guard Rail Installation 1 day Wed 07/05/14 Thu 08/05/14 171 Wed 07/05/14
173 0% Testing and Packaging 1 day Thu 08/05/14 Fri 09/05/14 170,172 Thu 08/05/14
174 0% Shipping 0 days Fri 09/05/14 Fri 09/05/14 173 Fri 09/05/14
175 0% Hebron Topsides Project 190 days Mon 03/03/14 Tue 14/10/14 Mon 03/03/14
176 0% Project Approval and Contract Award 1 day Mon 03/03/14 Mon 03/03/14 Mon 03/03/14
177 0% Kick-off Meeting 1 day Tue 04/03/14 Tue 04/03/14 176 Tue 04/03/14
178 0% Engineering and Design Work 36 days Wed 05/03/14 Wed 16/04/14 176FS+1 day Wed 05/03/14
179 0% Documentation submittals 36 days Wed 05/03/14 Wed 16/04/14 178SS Wed 05/03/14
180 0% Worley Parsons Approval 36 days Wed 12/03/14 Wed 23/04/14 178SS+6 days Wed 12/03/14
181 0% DNV 2.7-1 Approval 48 days Wed 23/04/14 Thu 19/06/14 180 Wed 23/04/14
182 0% Materials Procurement 48 days Thu 24/04/14 Fri 20/06/14 180FS+1 day Thu 24/04/14
183 0% Module 1 Containers (4 nos Cabin , 4 nos Lunch Room)46 days Fri 20/06/14 Thu 14/08/14 Fri 20/06/14
184 0% Structural Steel Fabrication Work 24 days Fri 20/06/14 Fri 18/07/14 181FS+1 day,182SSFri 20/06/14
185 0% In-house NDT Inspection 18 days Fri 27/06/14 Fri 18/07/14 184SS+6 days Fri 27/06/14
186 0% 3rd Party NDT Inspection 18 days Sat 28/06/14 Sat 19/07/14 185FF+1 day Sat 28/06/14
187 0% HVAC Penetrations 16 days Sat 05/07/14 Thu 24/07/14 186SS+6 days Sat 05/07/14
188 0% Window and Door Openings 16 days Sat 05/07/14 Thu 24/07/14 187SS Sat 05/07/14
189 0% Interior Tracking Installed 16 days Sat 05/07/14 Thu 24/07/14 186SS+6 days Sat 05/07/14
190 0% Sand Blasting 16 days Mon 07/07/14 Fri 25/07/14 186SS+3 days,189SS+1 dayMon 07/07/14
191 0% Primer and Painting 16 days Tue 08/07/14 Mon 28/07/14 190SS+1 day Tue 08/07/14
192 0% Insulation Installation 16 days Wed 09/07/14 Tue 29/07/14 191SS+1 day Wed 09/07/14
193 0% Rough Wiring 16 days Thu 10/07/14 Wed 30/07/14 189SS+4 days,191SS+2 daysThu 10/07/14
194 0% HVAC Ducting Installation 16 days Fri 11/07/14 Thu 31/07/14 193SS+1 day Fri 11/07/14
195 0% Interior flooring Installation 16 days Mon 14/07/14 Sat 02/08/14 194SS+2 days Mon 14/07/14
196 0% Plumbing Installation 16 days Wed 16/07/14 Tue 05/08/14 195SS+2 days Wed 16/07/14
197 0% Fire Protection Installation 16 days Wed 16/07/14 Tue 05/08/14 196SS Wed 16/07/14
198 0% Cladding, Arborite and Interior Walls Installation18 days Thu 17/07/14 Fri 08/08/14 194SS,197SS+1 dayThu 17/07/14
199 0% Window and Door Installation 16 days Sat 12/07/14 Fri 01/08/14 192SS+3 days Sat 12/07/14
200 0% Caulking Installation 16 days Mon 14/07/14 Sat 02/08/14 199FF+1 day Mon 14/07/14
201 0% Electrical outlets/panels Finish 16 days Mon 21/07/14 Fri 08/08/14 198SS+2 days Mon 21/07/14
09/05
17 10 31 21 12 02 23 14 04 25 15 06
01 January 21 February 11 April 01 June 21 July 11 September
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Critical
Critical Split
Baseline
Progress
Encanex Access, Captians, Power, cEMENT BARGES, ICS Baskets Projects
all- Sch-Rev A Page 5 3 March 14
ID Task
Mode
%
Complete
Task Name Duration Start Finish Predecessors Baseline Start
202 0% Fire Alram Installation 16 days Mon 21/07/14 Fri 08/08/14 201SS Mon 21/07/14
203 0% Controls Systems Installation 16 days Mon 21/07/14 Fri 08/08/14 201SS Mon 21/07/14
204 0% HVAC Finish 10 days Wed 23/07/14 Mon 04/08/14 194SS,198SS+4 daysWed 23/07/14
205 0% Interior Fixtures 10 days Thu 24/07/14 Tue 05/08/14 198SS+5 days Thu 24/07/14
206 0% Electrical Testing/Commissioning 8 days Fri 01/08/14 Mon 11/08/14 201FF+2 days,202FF+2 days,203FF+2 daysFri 01/08/14
207 0% HVAC Testing/Commissioning 8 days Fri 01/08/14 Mon 11/08/14 204FF+1 day,206SSFri 01/08/14
208 0% DNV Approval/ Certification 8 days Sat 02/08/14 Tue 12/08/14 206FF+1 day,207FF+1 daySat 02/08/14
209 0% Furnature Interior Installation 16 days Sat 26/07/14 Thu 14/08/14 205SS,206FF+3 days,207FF+3 daysSat 26/07/14
210 0% Setting Level 1 Containers 8 days Tue 05/08/14 Thu 14/08/14 209FF Tue 05/08/14
211 0% Module 2 Containers (4 nos Cabin , 1 no Female Wash and Change Room, 1 no Male Washroom,1 no Male Change Room)45 days Fri 25/07/14 Tue 16/09/14 Fri 25/07/14
212 0% Structural Steel Fabrication Work 21 days Fri 25/07/14 Tue 19/08/14 189 Fri 25/07/14
213 0% In-house NDT Inspection 15 days Fri 01/08/14 Tue 19/08/14 212SS+6 days Fri 01/08/14
214 0% 3rd Party NDT Inspection 15 days Sat 02/08/14 Wed 20/08/14 213FF+1 day Sat 02/08/14
215 0% HVAC Penetrations 16 days Sat 09/08/14 Thu 28/08/14 214SS+6 days Sat 09/08/14
216 0% Window and Door Openings 16 days Sat 09/08/14 Thu 28/08/14 215SS Sat 09/08/14
217 0% Interior Tracking Installed 16 days Sat 09/08/14 Thu 28/08/14 214SS+6 days Sat 09/08/14
218 0% Sand Blasting 16 days Mon 11/08/14 Fri 29/08/14 214SS+3 days,217SS+1 dayMon 11/08/14
219 0% Primer and Painting 16 days Tue 12/08/14 Sat 30/08/14 218SS+1 day Tue 12/08/14
220 0% Insulation Installation 16 days Wed 13/08/14 Mon 01/09/14 219SS+1 day Wed 13/08/14
221 0% Rough Wiring 16 days Thu 14/08/14 Tue 02/09/14 217SS+4 days,219SS+2 daysThu 14/08/14
222 0% HVAC Ducting Installation 16 days Fri 15/08/14 Wed 03/09/14 221SS+1 day Fri 15/08/14
223 0% Interior flooring Installation 16 days Mon 18/08/14 Fri 05/09/14 222SS+2 days Mon 18/08/14
224 0% Plumbing Installation 16 days Wed 20/08/14 Mon 08/09/14 223SS+2 days Wed 20/08/14
225 0% Fire Protection Installation 16 days Wed 20/08/14 Mon 08/09/14 224SS Wed 20/08/14
226 0% Cladding, Arborite and Interior Walls Installation18 days Thu 21/08/14 Thu 11/09/14 222SS,225SS+1 dayThu 21/08/14
227 0% Window and Door Installation 16 days Sat 16/08/14 Thu 04/09/14 220SS+3 days Sat 16/08/14
228 0% Caulking Installation 16 days Mon 18/08/14 Fri 05/09/14 227FF+1 day Mon 18/08/14
229 0% Electrical outlets/panels Finish 16 days Sat 23/08/14 Thu 11/09/14 226SS+2 days Sat 23/08/14
230 0% Fire Alram Installation 16 days Sat 23/08/14 Thu 11/09/14 229SS Sat 23/08/14
231 0% Controls Systems Installation 16 days Sat 23/08/14 Thu 11/09/14 229SS Sat 23/08/14
232 0% HVAC Finish 10 days Tue 26/08/14 Sat 06/09/14 222SS,226SS+4 daysTue 26/08/14
233 0% Interior Fixtures 10 days Wed 27/08/14 Mon 08/09/14 226SS+5 days Wed 27/08/14
234 0% Electrical Testing/Commissioning 8 days Wed 03/09/14 Fri 12/09/14 229FF+1 day,230FF+1 day,231FF+1 dayWed 03/09/14
235 0% HVAC Testing/Commissioning 8 days Wed 03/09/14 Fri 12/09/14 232FF+1 day,234SSWed 03/09/14
236 0% DNV Approval/ Certification 8 days Thu 04/09/14 Sat 13/09/14 234FF+1 day,235FF+1 dayThu 04/09/14
237 0% Furnature Interior Installation 16 days Thu 28/08/14 Tue 16/09/14 233SS,234FF+3 days,235FF+3 daysThu 28/08/14
238 0% Setting Level 2 Containers 7 days Mon 08/09/14 Tue 16/09/14 237FF Mon 08/09/14
239 0% Module 3 Containers (2 nos of 3 man cabin)37 days Thu 28/08/14 Sat 11/10/14 Thu 28/08/14
240 0% Structural Steel Fabrication Work 12 days Thu 28/08/14 Thu 11/09/14 217 Thu 28/08/14
241 0% In-house NDT Inspection 7 days Wed 03/09/14 Thu 11/09/14 240SS+5 days Wed 03/09/14
242 0% 3rd Party NDT Inspection 7 days Thu 04/09/14 Fri 12/09/14 241FF+1 day Thu 04/09/14
17 10 31 21 12 02 23 14 04 25 15 06
01 January 21 February 11 April 01 June 21 July 11 September
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Critical
Critical Split
Baseline
Progress
Encanex Access, Captians, Power, cEMENT BARGES, ICS Baskets Projects
all- Sch-Rev A Page 6 3 March 14
ID Task
Mode
%
Complete
Task Name Duration Start Finish Predecessors Baseline Start
243 0% HVAC Penetrations 9 days Thu 11/09/14 Mon 22/09/14 242SS+6 days Thu 11/09/14
244 0% Window and Door Openings 9 days Thu 11/09/14 Mon 22/09/14 243SS Thu 11/09/14
245 0% Interior Tracking Installed 9 days Thu 11/09/14 Mon 22/09/14 242SS+6 days Thu 11/09/14
246 0% Sand Blasting 9 days Fri 12/09/14 Tue 23/09/14 242SS+3 days,245SS+1 dayFri 12/09/14
247 0% Primer and Painting 9 days Sat 13/09/14 Wed 24/09/14 246SS+1 day Sat 13/09/14
248 0% Insulation Installation 9 days Mon 15/09/14 Thu 25/09/14 247SS+1 day Mon 15/09/14
249 0% Rough Wiring 9 days Tue 16/09/14 Fri 26/09/14 245SS+4 days,247SS+2 daysTue 16/09/14
250 0% HVAC Ducting Installation 9 days Wed 17/09/14 Sat 27/09/14 249SS+1 day Wed 17/09/14
251 0% Interior flooring Installation 9 days Fri 19/09/14 Tue 30/09/14 250SS+2 days Fri 19/09/14
252 0% Plumbing Installation 9 days Mon 22/09/14 Thu 02/10/14 251SS+2 days Mon 22/09/14
253 0% Fire Protection Installation 9 days Mon 22/09/14 Thu 02/10/14 252SS Mon 22/09/14
254 0% Cladding, Arborite and Interior Walls Installation10 days Tue 23/09/14 Mon 06/10/14 250SS,253SS+1 dayTue 23/09/14
255 0% Window and Door Installation 9 days Thu 18/09/14 Mon 29/09/14 248SS+3 days Thu 18/09/14
256 0% Caulking Installation 9 days Fri 19/09/14 Tue 30/09/14 255FF+1 day Fri 19/09/14
257 0% Setting Level 3 Containers 1 day Wed 01/10/14 Wed 01/10/14 256 Wed 01/10/14
258 0% Electrical outlets/panels Finish 6 days Thu 02/10/14 Thu 09/10/14 254SS+2 days,257Thu 02/10/14
259 0% Fire Alram Installation 6 days Thu 02/10/14 Thu 09/10/14 258SS Thu 02/10/14
260 0% Controls Systems Installation 6 days Thu 02/10/14 Thu 09/10/14 258SS Thu 02/10/14
261 0% HVAC Finish 3 days Thu 02/10/14 Mon 06/10/14 250SS,254SS+4 days,260SSThu 02/10/14
262 0% Interior Fixtures 3 days Tue 30/09/14 Thu 02/10/14 254SS+5 days Tue 30/09/14
263 0% Electrical Testing/Commissioning 2 days Wed 08/10/14 Fri 10/10/14 258FF+1 day,259FF+1 day,260FF+1 dayWed 08/10/14
264 0% HVAC Testing/Commissioning 2 days Wed 08/10/14 Fri 10/10/14 261FF+1 day,263SSWed 08/10/14
265 0% DNV Approval/ Certification 2 days Thu 09/10/14 Sat 11/10/14 263FF+1 day,264FF+1 dayThu 09/10/14
266 0% Furnature Interior Installation 6 days Fri 03/10/14 Fri 10/10/14 262SS,263FF,264FFFri 03/10/14
267 0% Stairs and Walkways 37 days Fri 25/07/14 Sat 06/09/14 Fri 25/07/14
268 0% Structural Steel Fabrication Work 30 days Fri 25/07/14 Fri 29/08/14 189 Fri 25/07/14
269 0% In-house NDT Inspection 25 days Thu 31/07/14 Fri 29/08/14 268SS+5 days Thu 31/07/14
270 0% 3rd Party NDT Inspection 25 days Sat 02/08/14 Mon 01/09/14 269SS+2 days Sat 02/08/14
271 0% Sand Blasting 16 days Fri 15/08/14 Wed 03/09/14 270SS+11 daysFri 15/08/14
272 0% Primer and Painting 16 days Sat 16/08/14 Thu 04/09/14 271SS+1 day Sat 16/08/14
273 0% DNV Approval/ Certification 2 days Thu 04/09/14 Sat 06/09/14 272 Thu 04/09/14
274 0% Structural Fitting/Testig and Commissioning61 days Fri 01/08/14 Mon 13/10/14 Fri 01/08/14
275 0% Level 1 Containers 11 days Fri 01/08/14 Thu 14/08/14 206SS,210FF Fri 01/08/14
276 0% Level 2 Containers 11 days Wed 03/09/14 Tue 16/09/14 234SS,238FF Wed 03/09/14
277 0% Level 3 Containers 8 days Wed 01/10/14 Fri 10/10/14 257SS,266FF Wed 01/10/14
278 0% All Levels Containers as one unit complete2 days Fri 10/10/14 Mon 13/10/14 277 Fri 10/10/14
279 0% Closing out 8 days Sat 04/10/14 Tue 14/10/14 Sat 04/10/14
280 0% Preparation for transportation 8 days Sat 04/10/14 Tue 14/10/14 276SS+1 day,278FF+1 daySat 04/10/14
281 0% Final Documentation sign-off 0 days Tue 14/10/14 Tue 14/10/14 280 Tue 14/10/14 14/10
17 10 31 21 12 02 23 14 04 25 15 06
01 January 21 February 11 April 01 June 21 July 11 September
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Critical
Critical Split
Baseline
Progress
Encanex Access, Captians, Power, cEMENT BARGES, ICS Baskets Projects
all- Sch-Rev A Page 7 3 March 14

More Related Content

Similar to Encanex Access Barge Project Schedule

Schedule Pelebaran Jalan Laluan - Batu Besar.pdf
Schedule Pelebaran Jalan Laluan - Batu Besar.pdfSchedule Pelebaran Jalan Laluan - Batu Besar.pdf
Schedule Pelebaran Jalan Laluan - Batu Besar.pdfssuserccc2e41
 
Engineering Design Center Project Schedule
Engineering Design Center Project ScheduleEngineering Design Center Project Schedule
Engineering Design Center Project ScheduleVirginia Kam
 
MS Project - 24 January 2016
MS Project - 24 January 2016MS Project - 24 January 2016
MS Project - 24 January 2016Gordon Morton
 
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design ScheduleFitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design ScheduleGary Hayes
 
Northwestern AU+Automation Timeline REV6 6-15-12
Northwestern AU+Automation Timeline REV6  6-15-12Northwestern AU+Automation Timeline REV6  6-15-12
Northwestern AU+Automation Timeline REV6 6-15-12Bin Kallan
 
Northwestern AU+Automation Timeline REV6 6-15-12
Northwestern AU+Automation Timeline REV6  6-15-12Northwestern AU+Automation Timeline REV6  6-15-12
Northwestern AU+Automation Timeline REV6 6-15-12Bin Kallan
 
Jadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdfJadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdfGaluhWulandari10
 
ECN Plan For C-005 Final
ECN Plan For C-005 FinalECN Plan For C-005 Final
ECN Plan For C-005 FinalOmid Latifzadeh
 
POW STTF 1 2023 (PT. SAM)NEW.pdf
POW STTF 1 2023 (PT. SAM)NEW.pdfPOW STTF 1 2023 (PT. SAM)NEW.pdf
POW STTF 1 2023 (PT. SAM)NEW.pdfSitiAuliaRamadhany1
 
Nework digram .pdf
Nework digram .pdfNework digram .pdf
Nework digram .pdfdks
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisDeborah Obasogie
 
Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Ayon Pal
 
Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis ayonpal
 
Antalya su kayaği 15-02-2008
Antalya su kayaği 15-02-2008Antalya su kayaği 15-02-2008
Antalya su kayaği 15-02-2008esregroup
 
ABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.pptABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.pptKingHaroldDeLeon
 
MOL Schedule about health and environment
MOL Schedule about health and environmentMOL Schedule about health and environment
MOL Schedule about health and environmentFasiullahShah1
 

Similar to Encanex Access Barge Project Schedule (19)

MS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation ScheduleMS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation Schedule
 
Schedule Pelebaran Jalan Laluan - Batu Besar.pdf
Schedule Pelebaran Jalan Laluan - Batu Besar.pdfSchedule Pelebaran Jalan Laluan - Batu Besar.pdf
Schedule Pelebaran Jalan Laluan - Batu Besar.pdf
 
Engineering Design Center Project Schedule
Engineering Design Center Project ScheduleEngineering Design Center Project Schedule
Engineering Design Center Project Schedule
 
MS Project - 24 January 2016
MS Project - 24 January 2016MS Project - 24 January 2016
MS Project - 24 January 2016
 
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design ScheduleFitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
 
Northwestern AU+Automation Timeline REV6 6-15-12
Northwestern AU+Automation Timeline REV6  6-15-12Northwestern AU+Automation Timeline REV6  6-15-12
Northwestern AU+Automation Timeline REV6 6-15-12
 
Northwestern AU+Automation Timeline REV6 6-15-12
Northwestern AU+Automation Timeline REV6  6-15-12Northwestern AU+Automation Timeline REV6  6-15-12
Northwestern AU+Automation Timeline REV6 6-15-12
 
Jadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdfJadwal Pelaksanaan PPI.pdf
Jadwal Pelaksanaan PPI.pdf
 
ECN Plan For C-005 Final
ECN Plan For C-005 FinalECN Plan For C-005 Final
ECN Plan For C-005 Final
 
POW STTF 1 2023 (PT. SAM)NEW.pdf
POW STTF 1 2023 (PT. SAM)NEW.pdfPOW STTF 1 2023 (PT. SAM)NEW.pdf
POW STTF 1 2023 (PT. SAM)NEW.pdf
 
Nework digram .pdf
Nework digram .pdfNework digram .pdf
Nework digram .pdf
 
Test
TestTest
Test
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value Analysis
 
Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis Sample Project Monitoring-EVM Analysis
Sample Project Monitoring-EVM Analysis
 
Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis Project Monitoring with EVM Analysis
Project Monitoring with EVM Analysis
 
Antalya su kayaği 15-02-2008
Antalya su kayaği 15-02-2008Antalya su kayaği 15-02-2008
Antalya su kayaği 15-02-2008
 
- Project.pdf
- Project.pdf- Project.pdf
- Project.pdf
 
ABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.pptABC_3rd Progress Mtg Briefing_050115_draft.ppt
ABC_3rd Progress Mtg Briefing_050115_draft.ppt
 
MOL Schedule about health and environment
MOL Schedule about health and environmentMOL Schedule about health and environment
MOL Schedule about health and environment
 

Encanex Access Barge Project Schedule

  • 1. ID Task Mode % Complete Task Name Duration Start Finish Predecessors Baseline Start 1 100% Encanex Access Barge Project 173.55 daysThu 15/08/13 Sat 08/03/14 Thu 15/08/13 2 100% Contract Award 1 day Thu 15/08/13 Fri 16/08/13 Thu 15/08/13 3 100% Materials Procurement 122 days Mon 19/08/13 Fri 10/01/14 2FS+2 days Mon 19/08/13 4 100% Mobilize Containers to Fab shop -Halifax-134 days Mon 19/08/13 Fri 24/01/14 2FS+2 days Mon 19/08/13 5 100% Module 1 Containers (6 Containers) 30.35 days Sat 01/02/14 Sat 08/03/14 Sat 01/02/14 6 100% Place Insulation and Steel Plates in Bottom of Containers 10 days Thu 13/02/14 Tue 25/02/14 4FS+16 days Thu 13/02/14 7 100% HVAC Penetrations 8 days Sat 15/02/14 Tue 25/02/14 6SS+2 days Sat 15/02/14 8 100% Window and Door Openings 8 days Sat 15/02/14 Tue 25/02/14 7SS Sat 15/02/14 9 100% Structural Re-Enforcement 11 days Mon 17/02/14 Sat 01/03/14 8SS+1 day Mon 17/02/14 10 100% NDT 11 days Tue 18/02/14 Mon 03/03/14 9SS+1 day Tue 18/02/14 11 100% Interior Tracking Installed 9 days Tue 18/02/14 Fri 28/02/14 9SS+1 day Tue 18/02/14 12 100% Exterior sand blasting 6 days Sat 22/02/14 Sat 01/03/14 11FS-5 days Sat 22/02/14 13 100% Primer and Painting 5 days Mon 24/02/14 Sat 01/03/14 12SS+1 day Mon 24/02/14 14 100% Rough wiring 1 day Wed 26/02/14 Thu 27/02/14 13FS-3 days Wed 26/02/14 15 100% Insulation Installation 1 day Thu 27/02/14 Fri 28/02/14 14SS+1 day Thu 27/02/14 16 100% Interior flooring Installation 9 days Tue 25/02/14 Fri 07/03/14 15FF+1 day Tue 25/02/14 17 100% Cladding, Arborite and Interior Walls 5 days Tue 25/02/14 Mon 03/03/14 13SS+1 day Tue 25/02/14 18 100% Window and Door Installation 2 days Wed 05/03/14 Fri 07/03/14 17 Wed 05/03/14 19 100% Interior Fixtures 12 days Fri 21/02/14 Fri 07/03/14 17SS-3 days Fri 21/02/14 20 100% Electrical Finish 7 days Thu 27/02/14 Fri 07/03/14 17SS+2 days Thu 27/02/14 21 100% Furnature Interior 6 days Fri 28/02/14 Fri 07/03/14 20SS+1 day Fri 28/02/14 22 100% Preparation for transportation to Quebic2 days Tue 04/03/14 Sat 08/03/14 21FF Tue 04/03/14 23 100% Sewage Tanks 26 days Sat 01/02/14 Tue 04/03/14 Sat 01/02/14 24 100% Pump Room 5.9 days Mon 03/03/14 Sat 08/03/14 Mon 03/03/14 25 100% Module 2 Containers ( 40 Containers) 151 days Mon 19/08/13 Fri 14/02/14 Mon 19/08/13 26 100% Place Insulation and Steel Plates in Bottom of Containers 33 days Mon 19/08/13 Fri 27/09/13 4SS Mon 19/08/13 27 100% HVAC Penetrations 46 days Mon 26/08/13 Sat 19/10/13 26SS+6 days Mon 26/08/13 28 100% Window and Door Openings 127 days Mon 26/08/13 Thu 23/01/14 27SS Mon 26/08/13 29 100% Structural Re-Enforcement 118 days Fri 06/09/13 Fri 24/01/14 28SS+10 days Fri 06/09/13 30 100% NDT 20 days Thu 02/01/14 Sat 25/01/14 29FF+1 day Thu 02/01/14 31 100% Interior Tracking Installed 119 days Mon 09/09/13 Tue 28/01/14 29SS+2 days Mon 09/09/13 32 100% Exterior sand blasting 116 days Mon 16/09/13 Fri 31/01/14 31SS+6 days Mon 16/09/13 33 100% Primer and Painting 116 days Tue 17/09/13 Sat 01/02/14 32SS+1 day Tue 17/09/13 34 100% Rough wiring 112 days Mon 23/09/13 Sat 01/02/14 33SS+4 days Mon 23/09/13 35 100% Insulation Installation 60 days Mon 25/11/13 Tue 04/02/14 34FF+2 days Mon 25/11/13 36 100% Interior flooring Installation 87 days Mon 28/10/13 Fri 07/02/14 35FF+3 days Mon 28/10/13 37 100% Cladding, Arborite and Interior Walls 85 days Thu 31/10/13 Mon 10/02/14 36SS+3 days Thu 31/10/13 38 100% Window and Door Installation 41 days Mon 23/12/13 Mon 10/02/14 37SS+44 days Mon 23/12/13 39 100% Interior Fixtures 54 days Mon 09/12/13 Tue 11/02/14 38SS-12 days Mon 09/12/13 17 10 31 21 12 02 23 14 04 25 15 06 01 January 21 February 11 April 01 June 21 July 11 September Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Critical Critical Split Baseline Progress Encanex Access, Captians, Power, cEMENT BARGES, ICS Baskets Projects all- Sch-Rev A Page 1 3 March 14
  • 2. ID Task Mode % Complete Task Name Duration Start Finish Predecessors Baseline Start 40 100% Electrical Finish 76 days Thu 14/11/13 Thu 13/02/14 37SS+12 days Thu 14/11/13 41 100% Furnature Interior 46 days Fri 20/12/13 Thu 13/02/14 40SS+30 days Fri 20/12/13 42 100% Final Preparation 46 days Fri 20/12/13 Thu 13/02/14 41SS Fri 20/12/13 43 100% Transportation to Quebic 42 days Thu 26/12/13 Fri 14/02/14 42SS+1 day Thu 26/12/13 44 100% Sewage Tanks Installation 65 days Fri 22/11/13 Fri 07/02/14 Fri 22/11/13 45 100% Module 3 Containers (36 Containers) 164.6 days Mon 26/08/13 Sat 08/03/14 Mon 26/08/13 46 100% Place Insulation and Steel Plates in Bottom of Containers 145 days Mon 26/08/13 Thu 13/02/14 Mon 26/08/13 47 100% HVAC Penetrations 157 days Mon 26/08/13 Thu 27/02/14 Mon 26/08/13 48 100% Structural Re-Enforcement 145 days Fri 06/09/13 Tue 25/02/14 Fri 06/09/13 49 100% NDT 145 days Fri 06/09/13 Tue 25/02/14 Fri 06/09/13 50 100% Window and Door Openings 143 days Wed 11/09/13 Thu 27/02/14 Wed 11/09/13 51 100% Interior Tracking Installed 139 days Tue 17/09/13 Fri 28/02/14 Tue 17/09/13 52 100% exterior sand blasting 141 days Wed 18/09/13 Tue 04/03/14 Wed 18/09/13 53 100% Primer and Painting 141 days Wed 18/09/13 Tue 04/03/14 Wed 18/09/13 54 100% Rough wiring 133 days Tue 24/09/13 Fri 28/02/14 Tue 24/09/13 55 100% Insulation Installation 64 days Fri 20/12/13 Thu 06/03/14 Fri 20/12/13 56 100% Interior flooring Installation 86 days Mon 25/11/13 Thu 06/03/14 Mon 25/11/13 57 100% Cladding, Arborite and Interior Walls 79 days Tue 03/12/13 Thu 06/03/14 Tue 03/12/13 58 100% Window and Door Installation 21 days Mon 10/02/14 Thu 06/03/14 Mon 10/02/14 59 100% Electrical Finish 28 days Mon 03/02/14 Fri 07/03/14 Mon 03/02/14 60 100% furnature Interior 28 days Mon 03/02/14 Fri 07/03/14 Mon 03/02/14 61 100% Preparation for transportation to Quebic20 days Thu 13/02/14 Sat 08/03/14 Thu 13/02/14 62 91% Encanex Captain Bridge Project 31.9 days Mon 03/02/14 Wed 12/03/14 Mon 03/02/14 63 100% Contract Award 1 day Mon 03/02/14 Mon 03/02/14 Mon 03/02/14 64 100% Materials Procurement 26 days Mon 03/02/14 Wed 05/03/14 63SS Mon 03/02/14 65 82% Cabin 14.2 days Mon 24/02/14 Wed 12/03/14 Mon 24/02/14 66 100% HVAC Penetrations 2 days Mon 24/02/14 Tue 25/02/14 Mon 24/02/14 67 100% HVAC Ducting Fabrication 5 days Wed 26/02/14 Tue 04/03/14 66 Wed 26/02/14 68 100% Window and Door Openings 0 days Mon 24/02/14 Mon 24/02/14 66SS Mon 24/02/14 69 100% Structural Re-Enforcement 2 days Wed 26/02/14 Thu 27/02/14 66 Wed 26/02/14 70 100% NDT 1 day Thu 27/02/14 Thu 27/02/14 69FF Thu 27/02/14 71 100% Interior Tracking Installed 0.5 days Fri 28/02/14 Fri 28/02/14 70 Fri 28/02/14 72 100% checker plate steel flooring Installation0.5 days Fri 28/02/14 Fri 28/02/14 71 Fri 28/02/14 73 100% Exterior sand blasting 1 day Sat 01/03/14 Mon 03/03/14 72 Sat 01/03/14 74 100% Primer and Painting 1 day Sun 02/03/14 Mon 03/03/14 73 Sun 02/03/14 75 100% Interior Walls Panels Installation 1 day Mon 03/03/14 Tue 04/03/14 74 Mon 03/03/14 76 80% Electrical Rough wiring 4 days Tue 04/03/14 Sat 08/03/14 75 Tue 04/03/14 77 80% Fire /Gas system wiring 0.5 days Fri 07/03/14 Sat 08/03/14 76FF Fri 07/03/14 78 100% Fire supression system Installation 1 day Wed 05/03/14 Thu 06/03/14 75FS+1 day Wed 05/03/14 79 80% Electrical Finish / Dedectors Installation2 days Thu 06/03/14 Sat 08/03/14 76FF,77FF Thu 06/03/14 24/02 17 10 31 21 12 02 23 14 04 25 15 06 01 January 21 February 11 April 01 June 21 July 11 September Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Critical Critical Split Baseline Progress Encanex Access, Captians, Power, cEMENT BARGES, ICS Baskets Projects all- Sch-Rev A Page 2 3 March 14
  • 3. ID Task Mode % Complete Task Name Duration Start Finish Predecessors Baseline Start 80 100% HVAC Installation 3 days Tue 04/03/14 Fri 07/03/14 67,75 Tue 04/03/14 81 100% Window and Door Installation 1 day Thu 06/03/14 Fri 07/03/14 80FF Thu 06/03/14 82 0% Desks Interior 1 day Sat 08/03/14 Mon 10/03/14 80FS+1 day Sat 08/03/14 83 0% Final FAT / Commissioning 1 day Mon 10/03/14 Tue 11/03/14 82 Mon 10/03/14 84 0% HVAC Unit Dismantling / Packaging 1 day Tue 11/03/14 Wed 12/03/14 83 Tue 11/03/14 85 0% Decommissioning and Packaging 1 day Tue 11/03/14 Wed 12/03/14 83 Tue 11/03/14 86 0% Shipping 0 days Wed 12/03/14 Wed 12/03/14 85 Wed 12/03/14 87 53% Encanex Power Barge Project 37.1 days Mon 03/02/14 Tue 18/03/14 Mon 03/02/14 88 100% Contract Award 1 day Mon 03/02/14 Mon 03/02/14 Mon 03/02/14 89 100% Materials Procurement 22 days Mon 03/02/14 Fri 28/02/14 88SS Mon 03/02/14 90 27% Tool Crib Cabin 13 days Mon 03/03/14 Tue 18/03/14 Mon 03/03/14 91 100% Place Insulation and Steel Plates in Bottom of Containers2 days Mon 03/03/14 Tue 04/03/14 Mon 03/03/14 92 99% HVAC Penetrations 1 day Mon 03/03/14 Tue 04/03/14 91SS+1 day Mon 03/03/14 93 100% Window and Door Openings 1 day Tue 04/03/14 Tue 04/03/14 92SS Tue 04/03/14 94 50% Structural Re-Enforcement 2 days Wed 05/03/14 Thu 06/03/14 93 Wed 05/03/14 95 50% NDT 2 days Wed 05/03/14 Thu 06/03/14 94FF Wed 05/03/14 96 20% Interior Tracking Installed 1 day Fri 07/03/14 Fri 07/03/14 94 Fri 07/03/14 97 0% Rough wiring 1 day Sat 08/03/14 Mon 10/03/14 96 Sat 08/03/14 98 0% Exterior sand blasting 2 days Mon 10/03/14 Wed 12/03/14 97 Mon 10/03/14 99 0% Primer and Painting 2 days Mon 10/03/14 Wed 12/03/14 98SS Mon 10/03/14 100 0% Insulation Installation 1 day Wed 12/03/14 Thu 13/03/14 99 Wed 12/03/14 101 0% Interior flooring Installation 1 day Wed 12/03/14 Thu 13/03/14 100SS Wed 12/03/14 102 0% A0, A60,Cladding, Arborite and Interior Walls2 days Thu 13/03/14 Sat 15/03/14 101 Thu 13/03/14 103 0% Window and Door Installation 2 days Thu 13/03/14 Sat 15/03/14 102SS Thu 13/03/14 104 0% Electrical Finish 1 day Sat 15/03/14 Mon 17/03/14 102 Sat 15/03/14 105 0% Furnature Interior 1 day Sat 15/03/14 Mon 17/03/14 104SS Sat 15/03/14 106 0% Preparation for transportation 1 day Mon 17/03/14 Tue 18/03/14 105 Mon 17/03/14 107 30% Comm/Data Room 11.5 days Wed 05/03/14 Tue 18/03/14 Wed 05/03/14 108 100% Place Insulation and Steel Plates in Bottom of Containers2 days Wed 05/03/14 Thu 06/03/14 91 Wed 05/03/14 109 100% Door Openings 0.5 days Thu 06/03/14 Thu 06/03/14 108FF Thu 06/03/14 110 0% HVAC Penetrations 0 days Fri 07/03/14 Fri 07/03/14 109FS+1 day Fri 07/03/14 111 70% Structural Re-Enforcement 2 days Fri 07/03/14 Mon 10/03/14 109 Fri 07/03/14 112 70% NDT 2 days Fri 07/03/14 Mon 10/03/14 111FF Fri 07/03/14 113 0% Interior Tracking Installed 0.5 days Mon 10/03/14 Mon 10/03/14 111 Mon 10/03/14 114 0% Rough wiring 0.5 days Mon 10/03/14 Tue 11/03/14 113 Mon 10/03/14 115 0% Exterior sand blasting 2 days Tue 11/03/14 Thu 13/03/14 114 Tue 11/03/14 116 0% Primer and Painting 2 days Tue 11/03/14 Thu 13/03/14 115SS Tue 11/03/14 117 0% Insulation Installation 1 day Thu 13/03/14 Fri 14/03/14 116 Thu 13/03/14 118 0% Interior flooring Installation 1 day Thu 13/03/14 Fri 14/03/14 117SS Thu 13/03/14 119 0% A0, A60,Cladding, Arborite and Interior Walls2 days Fri 14/03/14 Mon 17/03/14 118 Fri 14/03/14 120 0% Door Installation 0.5 days Fri 14/03/14 Fri 14/03/14 119SS Fri 14/03/14 12/03 07/03 17 10 31 21 12 02 23 14 04 25 15 06 01 January 21 February 11 April 01 June 21 July 11 September Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Critical Critical Split Baseline Progress Encanex Access, Captians, Power, cEMENT BARGES, ICS Baskets Projects all- Sch-Rev A Page 3 3 March 14
  • 4. ID Task Mode % Complete Task Name Duration Start Finish Predecessors Baseline Start 121 0% Electrical Finish 0.5 days Mon 17/03/14 Mon 17/03/14 119 Mon 17/03/14 122 0% Preparation for transportation 1 day Mon 17/03/14 Tue 18/03/14 121 Mon 17/03/14 123 0% Closing Out Project 1 day Mon 17/03/14 Tue 18/03/14 Mon 17/03/14 124 0% Shipping Documents Sign-Off and shipping1 day Mon 17/03/14 Tue 18/03/14 106SS,122SS Mon 17/03/14 125 9% Encanex Cement Barge Project 60.5 days Mon 03/02/14 Tue 15/04/14 Mon 03/02/14 126 100% Contract Award 1 day Mon 03/02/14 Mon 03/02/14 Mon 03/02/14 127 55% Materials Procurement 48 days Mon 03/02/14 Mon 31/03/14 126SS Mon 03/02/14 128 0% Module 1 Containers (24 Containers, 1 S.T & P.R) 31 days Mon 10/03/14 Tue 15/04/14 Mon 10/03/14 129 0% Place Insulation and Steel Plates in Bottom of Containers12 days Mon 10/03/14 Mon 24/03/14 Mon 10/03/14 130 0% HVAC Penetrations 12 days Tue 11/03/14 Wed 26/03/14 129SS+2 days Tue 11/03/14 131 0% Window and Door Openings 12 days Wed 12/03/14 Wed 26/03/14 130SS Wed 12/03/14 132 0% Structural Re-Enforcement 14 days Thu 13/03/14 Sat 29/03/14 129SS+1 day,130SS+1 day,131SS+1 dayThu 13/03/14 133 0% Required Welding Complete and NDT 12 days Sat 15/03/14 Sat 29/03/14 132FF Sat 15/03/14 134 0% Interior Tracking Installed 14 days Fri 14/03/14 Mon 31/03/14 132SS+1.5 daysFri 14/03/14 135 0% Rough wiring 18 days Sat 15/03/14 Sat 05/04/14 134SS+1 day Sat 15/03/14 136 0% Exterior sand blasting 19 days Mon 17/03/14 Tue 08/04/14 135SS+1 day Mon 17/03/14 137 0% Primer and Painting 19 days Tue 18/03/14 Wed 09/04/14 136SS+0.5 daysTue 18/03/14 138 0% Cladding, Arborite and Interior Walls 18 days Thu 20/03/14 Thu 10/04/14 137SS+2 days Thu 20/03/14 139 0% Insulation Installation 10 days Thu 27/03/14 Tue 08/04/14 138FF-2 days Thu 27/03/14 140 0% Interior Fixtures 8 days Wed 02/04/14 Fri 11/04/14 138FF+1 day Wed 02/04/14 141 0% Electrical Finish 17 days Sat 22/03/14 Fri 11/04/14 138SS+2 days,140FFSat 22/03/14 142 0% Interior flooring Installation 18 days Sat 22/03/14 Sat 12/04/14 138SS+2 days,140FF+1 day,141FF+1 daySat 22/03/14 143 0% Window and Door Installation 18 days Mon 24/03/14 Mon 14/04/14 138SS+3 days,140FF+2 daysMon 24/03/14 144 0% Caulking Completion 19 days Mon 24/03/14 Tue 15/04/14 138SS+3 days,143FF+1 dayMon 24/03/14 145 0% Sewage Tank & Pump Room 12 days Mon 31/03/14 Mon 14/04/14 132FS+1 day Mon 31/03/14 146 0% Shipping 18 days Tue 25/03/14 Tue 15/04/14 144SS+1 day Tue 25/03/14 147 8% ICS Baskets 32.6 days Mon 03/03/14 Thu 10/04/14 Mon 03/03/14 148 20% Materials Procurement 15 days Mon 03/03/14 Thu 20/03/14 Mon 03/03/14 149 0% Fabrication of Baskets 12.8 days Mon 17/03/14 Mon 31/03/14 Mon 17/03/14 150 0% Painting 4 days Tue 01/04/14 Fri 04/04/14 149 Tue 01/04/14 151 0% Lifting/Load Test 3 days Sat 05/04/14 Wed 09/04/14 150 Sat 05/04/14 152 0% Shipping 1 day Wed 09/04/14 Thu 10/04/14 151 Wed 09/04/14 153 0% NSCSA Confined Space Training Container 55.2 days Wed 05/03/14 Fri 09/05/14 Wed 05/03/14 154 0% Contract Award 1 day Wed 05/03/14 Wed 05/03/14 Wed 05/03/14 155 0% Materials Procurement 20 days Mon 24/03/14 Wed 16/04/14 154FS+10 daysMon 24/03/14 156 0% Cabin 16.5 days Sat 19/04/14 Fri 09/05/14 Sat 19/04/14 157 0% HVAC Penetrations 1 day Sat 19/04/14 Mon 21/04/14 155FS+3 days Sat 19/04/14 158 0% Window/ Door/ Man Hole Openings 2 days Mon 21/04/14 Wed 23/04/14 157SS+1 day Mon 21/04/14 159 0% Container Dividing (Partitions) Installation2 days Wed 23/04/14 Fri 25/04/14 158 Wed 23/04/14 160 0% Structural Re-Enforcement 2 days Fri 25/04/14 Mon 28/04/14 159 Fri 25/04/14 17 10 31 21 12 02 23 14 04 25 15 06 01 January 21 February 11 April 01 June 21 July 11 September Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Critical Critical Split Baseline Progress Encanex Access, Captians, Power, cEMENT BARGES, ICS Baskets Projects all- Sch-Rev A Page 4 3 March 14
  • 5. ID Task Mode % Complete Task Name Duration Start Finish Predecessors Baseline Start 161 0% NDT 1 day Sat 26/04/14 Mon 28/04/14 160FF Sat 26/04/14 162 0% Interior Tracking Installed 1 day Mon 28/04/14 Tue 29/04/14 161 Mon 28/04/14 163 0% Electrical Rough wiring 1 day Tue 29/04/14 Wed 30/04/14 162 Tue 29/04/14 164 0% Exterior sand blasting 0.5 days Wed 30/04/14 Wed 30/04/14 163 Wed 30/04/14 165 0% Primer and Painting 1 day Thu 01/05/14 Thu 01/05/14 164 Thu 01/05/14 166 0% 3/4'' plywood flooring Installation 1 day Fri 02/05/14 Fri 02/05/14 165 Fri 02/05/14 167 0% 3/8'' plywood Interior Walls Panels Installation1 day Sat 03/05/14 Mon 05/05/14 166 Sat 03/05/14 168 0% Farm Fan with Louvers Installation 0.5 days Mon 05/05/14 Mon 05/05/14 167 Mon 05/05/14 169 0% Electrical Finish Installation 1 day Mon 05/05/14 Tue 06/05/14 167 Mon 05/05/14 170 0% Culverts Installation 1 day Tue 06/05/14 Wed 07/05/14 169 Tue 06/05/14 171 0% Man Hole Covers / Door Installation 2 days Mon 05/05/14 Wed 07/05/14 167 Mon 05/05/14 172 0% Guard Rail Installation 1 day Wed 07/05/14 Thu 08/05/14 171 Wed 07/05/14 173 0% Testing and Packaging 1 day Thu 08/05/14 Fri 09/05/14 170,172 Thu 08/05/14 174 0% Shipping 0 days Fri 09/05/14 Fri 09/05/14 173 Fri 09/05/14 175 0% Hebron Topsides Project 190 days Mon 03/03/14 Tue 14/10/14 Mon 03/03/14 176 0% Project Approval and Contract Award 1 day Mon 03/03/14 Mon 03/03/14 Mon 03/03/14 177 0% Kick-off Meeting 1 day Tue 04/03/14 Tue 04/03/14 176 Tue 04/03/14 178 0% Engineering and Design Work 36 days Wed 05/03/14 Wed 16/04/14 176FS+1 day Wed 05/03/14 179 0% Documentation submittals 36 days Wed 05/03/14 Wed 16/04/14 178SS Wed 05/03/14 180 0% Worley Parsons Approval 36 days Wed 12/03/14 Wed 23/04/14 178SS+6 days Wed 12/03/14 181 0% DNV 2.7-1 Approval 48 days Wed 23/04/14 Thu 19/06/14 180 Wed 23/04/14 182 0% Materials Procurement 48 days Thu 24/04/14 Fri 20/06/14 180FS+1 day Thu 24/04/14 183 0% Module 1 Containers (4 nos Cabin , 4 nos Lunch Room)46 days Fri 20/06/14 Thu 14/08/14 Fri 20/06/14 184 0% Structural Steel Fabrication Work 24 days Fri 20/06/14 Fri 18/07/14 181FS+1 day,182SSFri 20/06/14 185 0% In-house NDT Inspection 18 days Fri 27/06/14 Fri 18/07/14 184SS+6 days Fri 27/06/14 186 0% 3rd Party NDT Inspection 18 days Sat 28/06/14 Sat 19/07/14 185FF+1 day Sat 28/06/14 187 0% HVAC Penetrations 16 days Sat 05/07/14 Thu 24/07/14 186SS+6 days Sat 05/07/14 188 0% Window and Door Openings 16 days Sat 05/07/14 Thu 24/07/14 187SS Sat 05/07/14 189 0% Interior Tracking Installed 16 days Sat 05/07/14 Thu 24/07/14 186SS+6 days Sat 05/07/14 190 0% Sand Blasting 16 days Mon 07/07/14 Fri 25/07/14 186SS+3 days,189SS+1 dayMon 07/07/14 191 0% Primer and Painting 16 days Tue 08/07/14 Mon 28/07/14 190SS+1 day Tue 08/07/14 192 0% Insulation Installation 16 days Wed 09/07/14 Tue 29/07/14 191SS+1 day Wed 09/07/14 193 0% Rough Wiring 16 days Thu 10/07/14 Wed 30/07/14 189SS+4 days,191SS+2 daysThu 10/07/14 194 0% HVAC Ducting Installation 16 days Fri 11/07/14 Thu 31/07/14 193SS+1 day Fri 11/07/14 195 0% Interior flooring Installation 16 days Mon 14/07/14 Sat 02/08/14 194SS+2 days Mon 14/07/14 196 0% Plumbing Installation 16 days Wed 16/07/14 Tue 05/08/14 195SS+2 days Wed 16/07/14 197 0% Fire Protection Installation 16 days Wed 16/07/14 Tue 05/08/14 196SS Wed 16/07/14 198 0% Cladding, Arborite and Interior Walls Installation18 days Thu 17/07/14 Fri 08/08/14 194SS,197SS+1 dayThu 17/07/14 199 0% Window and Door Installation 16 days Sat 12/07/14 Fri 01/08/14 192SS+3 days Sat 12/07/14 200 0% Caulking Installation 16 days Mon 14/07/14 Sat 02/08/14 199FF+1 day Mon 14/07/14 201 0% Electrical outlets/panels Finish 16 days Mon 21/07/14 Fri 08/08/14 198SS+2 days Mon 21/07/14 09/05 17 10 31 21 12 02 23 14 04 25 15 06 01 January 21 February 11 April 01 June 21 July 11 September Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Critical Critical Split Baseline Progress Encanex Access, Captians, Power, cEMENT BARGES, ICS Baskets Projects all- Sch-Rev A Page 5 3 March 14
  • 6. ID Task Mode % Complete Task Name Duration Start Finish Predecessors Baseline Start 202 0% Fire Alram Installation 16 days Mon 21/07/14 Fri 08/08/14 201SS Mon 21/07/14 203 0% Controls Systems Installation 16 days Mon 21/07/14 Fri 08/08/14 201SS Mon 21/07/14 204 0% HVAC Finish 10 days Wed 23/07/14 Mon 04/08/14 194SS,198SS+4 daysWed 23/07/14 205 0% Interior Fixtures 10 days Thu 24/07/14 Tue 05/08/14 198SS+5 days Thu 24/07/14 206 0% Electrical Testing/Commissioning 8 days Fri 01/08/14 Mon 11/08/14 201FF+2 days,202FF+2 days,203FF+2 daysFri 01/08/14 207 0% HVAC Testing/Commissioning 8 days Fri 01/08/14 Mon 11/08/14 204FF+1 day,206SSFri 01/08/14 208 0% DNV Approval/ Certification 8 days Sat 02/08/14 Tue 12/08/14 206FF+1 day,207FF+1 daySat 02/08/14 209 0% Furnature Interior Installation 16 days Sat 26/07/14 Thu 14/08/14 205SS,206FF+3 days,207FF+3 daysSat 26/07/14 210 0% Setting Level 1 Containers 8 days Tue 05/08/14 Thu 14/08/14 209FF Tue 05/08/14 211 0% Module 2 Containers (4 nos Cabin , 1 no Female Wash and Change Room, 1 no Male Washroom,1 no Male Change Room)45 days Fri 25/07/14 Tue 16/09/14 Fri 25/07/14 212 0% Structural Steel Fabrication Work 21 days Fri 25/07/14 Tue 19/08/14 189 Fri 25/07/14 213 0% In-house NDT Inspection 15 days Fri 01/08/14 Tue 19/08/14 212SS+6 days Fri 01/08/14 214 0% 3rd Party NDT Inspection 15 days Sat 02/08/14 Wed 20/08/14 213FF+1 day Sat 02/08/14 215 0% HVAC Penetrations 16 days Sat 09/08/14 Thu 28/08/14 214SS+6 days Sat 09/08/14 216 0% Window and Door Openings 16 days Sat 09/08/14 Thu 28/08/14 215SS Sat 09/08/14 217 0% Interior Tracking Installed 16 days Sat 09/08/14 Thu 28/08/14 214SS+6 days Sat 09/08/14 218 0% Sand Blasting 16 days Mon 11/08/14 Fri 29/08/14 214SS+3 days,217SS+1 dayMon 11/08/14 219 0% Primer and Painting 16 days Tue 12/08/14 Sat 30/08/14 218SS+1 day Tue 12/08/14 220 0% Insulation Installation 16 days Wed 13/08/14 Mon 01/09/14 219SS+1 day Wed 13/08/14 221 0% Rough Wiring 16 days Thu 14/08/14 Tue 02/09/14 217SS+4 days,219SS+2 daysThu 14/08/14 222 0% HVAC Ducting Installation 16 days Fri 15/08/14 Wed 03/09/14 221SS+1 day Fri 15/08/14 223 0% Interior flooring Installation 16 days Mon 18/08/14 Fri 05/09/14 222SS+2 days Mon 18/08/14 224 0% Plumbing Installation 16 days Wed 20/08/14 Mon 08/09/14 223SS+2 days Wed 20/08/14 225 0% Fire Protection Installation 16 days Wed 20/08/14 Mon 08/09/14 224SS Wed 20/08/14 226 0% Cladding, Arborite and Interior Walls Installation18 days Thu 21/08/14 Thu 11/09/14 222SS,225SS+1 dayThu 21/08/14 227 0% Window and Door Installation 16 days Sat 16/08/14 Thu 04/09/14 220SS+3 days Sat 16/08/14 228 0% Caulking Installation 16 days Mon 18/08/14 Fri 05/09/14 227FF+1 day Mon 18/08/14 229 0% Electrical outlets/panels Finish 16 days Sat 23/08/14 Thu 11/09/14 226SS+2 days Sat 23/08/14 230 0% Fire Alram Installation 16 days Sat 23/08/14 Thu 11/09/14 229SS Sat 23/08/14 231 0% Controls Systems Installation 16 days Sat 23/08/14 Thu 11/09/14 229SS Sat 23/08/14 232 0% HVAC Finish 10 days Tue 26/08/14 Sat 06/09/14 222SS,226SS+4 daysTue 26/08/14 233 0% Interior Fixtures 10 days Wed 27/08/14 Mon 08/09/14 226SS+5 days Wed 27/08/14 234 0% Electrical Testing/Commissioning 8 days Wed 03/09/14 Fri 12/09/14 229FF+1 day,230FF+1 day,231FF+1 dayWed 03/09/14 235 0% HVAC Testing/Commissioning 8 days Wed 03/09/14 Fri 12/09/14 232FF+1 day,234SSWed 03/09/14 236 0% DNV Approval/ Certification 8 days Thu 04/09/14 Sat 13/09/14 234FF+1 day,235FF+1 dayThu 04/09/14 237 0% Furnature Interior Installation 16 days Thu 28/08/14 Tue 16/09/14 233SS,234FF+3 days,235FF+3 daysThu 28/08/14 238 0% Setting Level 2 Containers 7 days Mon 08/09/14 Tue 16/09/14 237FF Mon 08/09/14 239 0% Module 3 Containers (2 nos of 3 man cabin)37 days Thu 28/08/14 Sat 11/10/14 Thu 28/08/14 240 0% Structural Steel Fabrication Work 12 days Thu 28/08/14 Thu 11/09/14 217 Thu 28/08/14 241 0% In-house NDT Inspection 7 days Wed 03/09/14 Thu 11/09/14 240SS+5 days Wed 03/09/14 242 0% 3rd Party NDT Inspection 7 days Thu 04/09/14 Fri 12/09/14 241FF+1 day Thu 04/09/14 17 10 31 21 12 02 23 14 04 25 15 06 01 January 21 February 11 April 01 June 21 July 11 September Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Critical Critical Split Baseline Progress Encanex Access, Captians, Power, cEMENT BARGES, ICS Baskets Projects all- Sch-Rev A Page 6 3 March 14
  • 7. ID Task Mode % Complete Task Name Duration Start Finish Predecessors Baseline Start 243 0% HVAC Penetrations 9 days Thu 11/09/14 Mon 22/09/14 242SS+6 days Thu 11/09/14 244 0% Window and Door Openings 9 days Thu 11/09/14 Mon 22/09/14 243SS Thu 11/09/14 245 0% Interior Tracking Installed 9 days Thu 11/09/14 Mon 22/09/14 242SS+6 days Thu 11/09/14 246 0% Sand Blasting 9 days Fri 12/09/14 Tue 23/09/14 242SS+3 days,245SS+1 dayFri 12/09/14 247 0% Primer and Painting 9 days Sat 13/09/14 Wed 24/09/14 246SS+1 day Sat 13/09/14 248 0% Insulation Installation 9 days Mon 15/09/14 Thu 25/09/14 247SS+1 day Mon 15/09/14 249 0% Rough Wiring 9 days Tue 16/09/14 Fri 26/09/14 245SS+4 days,247SS+2 daysTue 16/09/14 250 0% HVAC Ducting Installation 9 days Wed 17/09/14 Sat 27/09/14 249SS+1 day Wed 17/09/14 251 0% Interior flooring Installation 9 days Fri 19/09/14 Tue 30/09/14 250SS+2 days Fri 19/09/14 252 0% Plumbing Installation 9 days Mon 22/09/14 Thu 02/10/14 251SS+2 days Mon 22/09/14 253 0% Fire Protection Installation 9 days Mon 22/09/14 Thu 02/10/14 252SS Mon 22/09/14 254 0% Cladding, Arborite and Interior Walls Installation10 days Tue 23/09/14 Mon 06/10/14 250SS,253SS+1 dayTue 23/09/14 255 0% Window and Door Installation 9 days Thu 18/09/14 Mon 29/09/14 248SS+3 days Thu 18/09/14 256 0% Caulking Installation 9 days Fri 19/09/14 Tue 30/09/14 255FF+1 day Fri 19/09/14 257 0% Setting Level 3 Containers 1 day Wed 01/10/14 Wed 01/10/14 256 Wed 01/10/14 258 0% Electrical outlets/panels Finish 6 days Thu 02/10/14 Thu 09/10/14 254SS+2 days,257Thu 02/10/14 259 0% Fire Alram Installation 6 days Thu 02/10/14 Thu 09/10/14 258SS Thu 02/10/14 260 0% Controls Systems Installation 6 days Thu 02/10/14 Thu 09/10/14 258SS Thu 02/10/14 261 0% HVAC Finish 3 days Thu 02/10/14 Mon 06/10/14 250SS,254SS+4 days,260SSThu 02/10/14 262 0% Interior Fixtures 3 days Tue 30/09/14 Thu 02/10/14 254SS+5 days Tue 30/09/14 263 0% Electrical Testing/Commissioning 2 days Wed 08/10/14 Fri 10/10/14 258FF+1 day,259FF+1 day,260FF+1 dayWed 08/10/14 264 0% HVAC Testing/Commissioning 2 days Wed 08/10/14 Fri 10/10/14 261FF+1 day,263SSWed 08/10/14 265 0% DNV Approval/ Certification 2 days Thu 09/10/14 Sat 11/10/14 263FF+1 day,264FF+1 dayThu 09/10/14 266 0% Furnature Interior Installation 6 days Fri 03/10/14 Fri 10/10/14 262SS,263FF,264FFFri 03/10/14 267 0% Stairs and Walkways 37 days Fri 25/07/14 Sat 06/09/14 Fri 25/07/14 268 0% Structural Steel Fabrication Work 30 days Fri 25/07/14 Fri 29/08/14 189 Fri 25/07/14 269 0% In-house NDT Inspection 25 days Thu 31/07/14 Fri 29/08/14 268SS+5 days Thu 31/07/14 270 0% 3rd Party NDT Inspection 25 days Sat 02/08/14 Mon 01/09/14 269SS+2 days Sat 02/08/14 271 0% Sand Blasting 16 days Fri 15/08/14 Wed 03/09/14 270SS+11 daysFri 15/08/14 272 0% Primer and Painting 16 days Sat 16/08/14 Thu 04/09/14 271SS+1 day Sat 16/08/14 273 0% DNV Approval/ Certification 2 days Thu 04/09/14 Sat 06/09/14 272 Thu 04/09/14 274 0% Structural Fitting/Testig and Commissioning61 days Fri 01/08/14 Mon 13/10/14 Fri 01/08/14 275 0% Level 1 Containers 11 days Fri 01/08/14 Thu 14/08/14 206SS,210FF Fri 01/08/14 276 0% Level 2 Containers 11 days Wed 03/09/14 Tue 16/09/14 234SS,238FF Wed 03/09/14 277 0% Level 3 Containers 8 days Wed 01/10/14 Fri 10/10/14 257SS,266FF Wed 01/10/14 278 0% All Levels Containers as one unit complete2 days Fri 10/10/14 Mon 13/10/14 277 Fri 10/10/14 279 0% Closing out 8 days Sat 04/10/14 Tue 14/10/14 Sat 04/10/14 280 0% Preparation for transportation 8 days Sat 04/10/14 Tue 14/10/14 276SS+1 day,278FF+1 daySat 04/10/14 281 0% Final Documentation sign-off 0 days Tue 14/10/14 Tue 14/10/14 280 Tue 14/10/14 14/10 17 10 31 21 12 02 23 14 04 25 15 06 01 January 21 February 11 April 01 June 21 July 11 September Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Critical Critical Split Baseline Progress Encanex Access, Captians, Power, cEMENT BARGES, ICS Baskets Projects all- Sch-Rev A Page 7 3 March 14