- 1. ID Task Name Duration Start Finish Predecessors
0 24 January 2016 15 days? Mon 25/01/16 Mon 15/02/16
1
2 Australia Day 26 January 1 day Mon 25/01/16 Wed 27/01/16
3
4 Roof 1 day Mon 25/01/16 Wed 27/01/16
5 Roof Cowells Dektites 1 day Mon 25/01/16 Wed 27/01/16
6 Capping 1 day Mon 25/01/16 Wed 27/01/16
7
8 GCS Scaffold 5.6 days Mon 25/01/16 Tue 2/02/16
9 West 0.2 days Mon 25/01/16 Mon 25/01/16
10 Hop Ups 15 and 16 0.2 days Mon 25/01/16 Mon 25/01/16
11 East and North 3.5 days Thu 28/01/16 Tue 2/02/16
12 Remove Roof and 1st Floor 1 day Thu 28/01/16 Fri 29/01/16 36
13 Remove Ground 0.5 days Fri 29/01/16 Sat 30/01/16 12
14 Hoists and Chute TBA 1 day Sat 30/01/16 Mon 1/02/16 13
15 Remove from Site 1 day Mon 1/02/16 Tue 2/02/16 14
16
17 Camillo 1st Aid 0458 109 454 1 day? Mon 25/01/16 Wed 27/01/16
18 Cover Windows Herdsman Pde and Eas 1 day? Mon 25/01/16 Wed 27/01/16
19
20 EuroRock 4.6 days Mon 25/01/16 Mon 1/02/16
21 Float Garage reveals 1, 5 and 9 0.1 days Mon 25/01/16 Mon 25/01/16
22 Float Stairwells 12 - 16 1 day Mon 25/01/16 Wed 27/01/16 21
23 Float West 1st 15 and 16 1 day Wed 27/01/16 Thu 28/01/16 22
24 Float South 16 0.5 days Thu 28/01/16 Fri 29/01/16 23
25 Float East 12 - 16 1 day Fri 29/01/16 Sat 30/01/16 24
26 Float Balconies Type A 1 day Sat 30/01/16 Mon 1/02/16 25
27
28 Marten Set 7 days Mon 25/01/16 Thu 4/02/16
29 Units 1-5 3 days Mon 25/01/16 Fri 29/01/16
30 Stairwells 2 days Fri 29/01/16 Mon 1/02/16 29
31 Patching 2 days Mon 1/02/16 Thu 4/02/16 30
32
33 Pacific West 4.1 days Mon 25/01/16 Sat 30/01/16
34 Reveals Garages 1, 5 and 9 0.3 days Mon 25/01/16 Mon 25/01/16
35 Unit 11 and Roof Level 1 day Mon 25/01/16 Wed 27/01/16 21
36 !st Floor 1 day Wed 27/01/16 Thu 28/01/16 35
37 Ground 12 - 16 2 days Thu 28/01/16 Sat 30/01/16 36
38
39 ICP Ceilings 5 days Mon 25/01/16 Mon 1/02/16
40 Gap & Sand 6 - 11 2 days Mon 25/01/16 Thu 28/01/16
41 Complete Units 1 & 2 3 days Thu 28/01/16 Mon 1/02/16 40
42
43 Cool and Cosy Glass 8.6 days Mon 25/01/16 Sat 6/02/16
44 Glaze West 12 -16 1 day Mon 25/01/16 Wed 27/01/16
45 Note Ground 6-11 Early Feb 3 days Tue 2/02/16 Sat 6/02/16 15
46
47 New Hope Tiling 14 days Mon 25/01/16 Sat 13/02/16
48 Grout 12 - 16 Floors 1 day Mon 25/01/16 Wed 27/01/16
49 Wall Tiling 3 days Wed 27/01/16 Sat 30/01/16 48
50 Grout 12 - 16 Walls 1 day Sat 30/01/16 Mon 1/02/16 49
51 Waterproof 6 - 11 2 days Mon 1/02/16 Thu 4/02/16 50
52 Floor Tile 6 - 11 2 days Thu 4/02/16 Sat 6/02/16 51
53 Kung Hei Fat Choy 2 days Mon 8/02/16 Wed 10/02/16
54 Grout 6 - 11 0.5 days Wed 10/02/16 Wed 10/02/16 53
55 Wall Tiling 6 - 11 3 days Fri 5/02/16 Wed 10/02/16 61
56 Screed 1 - 5 1 day Wed 10/02/16 Thu 11/02/16 55
57 Grout Walls 6 - 11 1 day Wed 10/02/16 Thu 11/02/16 55
58 Waterproof 1 - 6 2 days Thu 11/02/16 Sat 13/02/16 57
59
60 BF Cabinets 8 days Thu 4/02/16 Mon 15/02/16
61 Vanities 6 - 11 1 day Thu 4/02/16 Fri 5/02/16 51
62 Vanities 1 - 5 1 day Sat 13/02/16 Mon 15/02/16 58
63
64 WCG Carpentry 4 days Mon 25/01/16 Sat 30/01/16
65 Doors 12 - 16 1 day Mon 25/01/16 Wed 27/01/16
66 Skirtings 12 - 16 1 day Wed 27/01/16 Thu 28/01/16 65
67 Doors 6 - 11 1 day Thu 28/01/16 Fri 29/01/16 66
68 Skirtings 6 - 11 1 day Fri 29/01/16 Sat 30/01/16 67
69
70 Exclusive Painting 4 days Wed 27/01/16 Mon 1/02/16
71 Capping 1 day Wed 27/01/16 Thu 28/01/16 6
72 Ceilings 6 - 11 3 days Thu 28/01/16 Mon 1/02/16 71
73 Gap and prime 12 - 16 1 day Thu 28/01/16 Fri 29/01/16 66
74
75 Ben Survey 1 day Mon 25/01/16 Wed 27/01/16
76 Peg 1 day Mon 25/01/16 Wed 27/01/16
77
78 Hank Concretor 4 days Wed 27/01/16 Mon 1/02/16
79 Footings 4 days Wed 27/01/16 Mon 1/02/16 76
80
81 Shift Bricks 1 day Mon 25/01/16 Wed 27/01/16
82
83 Declan Bricklayer 4 days Mon 1/02/16 Sat 6/02/16
84 Screen Walls 4 days Mon 1/02/16 Sat 6/02/16 79
Australia Day 26 January 27/01
Roof Cowells Dektites 27/01
Capping 27/01
Hop Ups 15 and 16 25/01
Remove Roof and 1st Floor 29/01
Remove Ground 30/01
Hoists and Chute TBA 1/02
Remove from Site 2/02
Cover Windows Herdsman Pde and Eas 27/01
Float Garage reveals 1, 5 and 9 25/01
Float Stairwells 12 - 16 27/01
Float West 1st 15 and 16 28/01
Float South 16 29/01
Float East 12 - 16 30/01
Float Balconies Type A 1/02
Units 1-5 29/01
Stairwells 1/02
Patching 4/02
Reveals Garages 1, 5 and 9 25/01
Unit 11 and Roof Level 27/01
!st Floor 28/01
Ground 12 - 16 30/01
Gap & Sand 6 - 11 28/01
Complete Units 1 & 2 1/02
Glaze West 12 -16 27/01
Note Ground 6-11 Early Feb 6/02
Grout 12 - 16 Floors 27/01
Wall Tiling 30/01
Grout 12 - 16 Walls 1/02
Waterproof 6 - 11 4/02
Floor Tile 6 - 11 6/02
Kung Hei Fat Choy 10/02
Grout 6 - 11 10/02
Wall Tiling 6 - 11 10/02
Screed 1 - 5 11/02
Grout Walls 6 - 11 11/02
Waterproof 1 - 6 13/02
Vanities 6 - 11 5/02
Vanities 1 - 5
Doors 12 - 16 27/01
Skirtings 12 - 16 28/01
Doors 6 - 11 29/01
Skirtings 6 - 11 30/01
Capping 28/01
Ceilings 6 - 11 1/02
Gap and prime 12 - 16 29/01
Peg 27/01
Footings 1/02
Shift Bricks 27/01
Screen Walls 6/02
T F S S M T W T F S S M T W T F S S M T W T F S S
25 Jan '16 1 Feb '16 8 Feb '16