SlideShare a Scribd company logo
1 of 23
Incorporation Risk
Through Simulation
Presentation forming group
• Zulfiqar Ansari 12IN118
• Shehroze Mughal 12IN01
• Jazib Zai 12IN126
• Zahid Ali Abbasi 12IN127
• Mohsin Shaikh 12IN132
• Serwan Ali Memon 12-11IN54
Contents
• Introduction
• Incorporation
• Risk
• Simulation
• Risk and Simulation
• Example
• Risk in Decision Making
• Risk Analysis
• Monte Carlo Simulation
• Problem
• Conclusion
Introduction
The term risk today has many different meaning. In financial circles however the
term risk has a definite and distinct meaning. Risk refers to the situation where
decision are based on the calculation of probabilities that certain outcomes will
materialize or where probabilities based on historical information and statistical
frequency distribution are known
Incorporation
• Incorporation is the forming of a new corporation
• The process of legally declaring a corporate entity as separate from its owners
• A corporation is a company or group of people authorized to act as a single
entity (legally a person) and recognized as such in law
Risk
• Risk is potential of losing something of valuable
• Risk is a consequence of action taken in spite of uncertainty
• The probability or threat of quantifiable damage, injury, liability, loss, or any
other negative occurrence that is caused by external or internal vulnerabilities,
and that may be avoided through preemptive action
Simulation
• The act or process of pretending
• The technique of representing the real world by a computer program
• The act of giving a false appearance
• An attempt to model a real-life or hypothetical situation on a computer so that it
can be studied to see how the system works
Risk and Simulation
• Simulation allows you to evaluate, compare and optimize alternatives designs,
plans and policies through visualization
• The act of simulating the probabilistic data into statistical form
• Simulation is used when the level of uncertainty is high and the alternatives are
not quite feasible and taking any action will cause the heavy damages
• The complexity of the uncertainties requires the visualization of future
consequences
Example 1
A fisheries biologist could dynamically simulate the salmon population in a river in
order to predict changes to the population and quantitatively understand the
impacts on salmon of possible action (e.g. fishing, loss of habitat)to ensure that
they don't go extinct at some point in the future
Example 2
• When implementing a strategic plan for a company the impacts are likely to take
months (or years) to materialize. Simulation is particularly valuable when there
is significant uncertainty regarding the outcome or consequences of a particular
alternative under consideration. Probabilistic simulation allows dealing with this
uncertainty in a quantifiable way
Example 3
• The newsvendor problem is one in which a retailer for instance needs to
purchase some quantity of an item prior to demand being known. If too few are
ordered must be heavily discounted. This fundamental problem commonly
occurs in retailing such as when a store needs to order seasonal or perishable
merchandise. However it also exists for manufacturers of products that decline
in value after they are produced. For example, in the fast changing electronics
industry, if a company commits to manufacturing too many handled computers it
will be left with product that is worth only a fraction of what is was worth when
produced. Even transpiration services such as airlines face a form of this
problem since airlines must decide ahead of time how frequently to fly a give
route and which type of aircraft to use.
Risk in Decision Making
• The unpredictable consequence as a result of taking decision
• Decision making requires an understanding of the requirements and objectives,
their relative importance, and how to assess options and make the 'best'
decision
• For a successful decision making, understanding the level of risk and its
consequence is needed to select the best possible solution
Risk Analysis
Risk Analysis involves following steps
Define the
problem
Construct
the Model
Assess
Input
Variables
Calculate
Interpret
the Model
Output
Use the
Risk
analysis in
Decision
Making
Monte Carlo Simulation
• Monte Carlo methods are quite useful for simulating systems with many coupled
degrees of freedom
• Monte Carlo methods can be used to solve any problem having a probabilistic
interpretation
• Monte Carlo simulation uses repeated sampling to determine the properties of
some phenomenon (or behavior).
• Monte Carlo simulations sample are taken from a probability distribution for
each variable to produce hundreds or thousands of possible outcomes
• Monte Carlo methods are especially useful for simulating phenomena with
significant uncertainty in inputs and systems with a large number of coupled
degrees of freedom
Problem
Consider a firm that has three unrelated product lines and needs to forecast its
total net profit for the coming year. Uncertainty exists in the revenue and cost
structures of each product; however, the three divisional managers have
assessed their profit distributions as shown in table. These profit distributions are
assumed to be
Table: Profit Distributions for three products
Product 1 Product 2 Product 3
Profit Probability Profit Probability Profit Probability
800000 01
75000 0.2 850000 0.3 500000 0.5
125000 0.5 990000 0.5 550000 0.5
175000 0.3 950000 0.1
∑=1 ∑=1 ∑=1
Table: Evaluation of all possible outcomes
Product 1 Product 2 Product 3 Total Probability
75 800 500 1375 0.2*0.1*0.5=0.01
75 800 550 1425 0.2*0.1*0.5=0.01
75 850 500 1425 0.2*0.3*0.5=0.03
75 850 550 1475 0.2*0.3*0.5=0.03
75 900 500 1475 0.2*0.5*0.5=0.05
75 900 550 1525 0.2*0.5*0.5=0.05
75 950 500 1525 0.2*0.1*0.5=0.01
75 950 550 1575 0.2*0.1*0.5=0.01
125 800 500 1425 0.5*0.1*0.5=0.025
125 800 550 1475 0.5*0.1*0.5=0.025
125 850 500 1475 0.5*0.3*0.5=0.075
125 850 550 1525 0.5*0.3*0.5=0.075
125 900 500 1525 0.5*0.5*0.5=0.125
125 900 550 1575 0.5*0.5*0.5=0.125
125 950 500 1575 0.5*0.1*0.5=0.025
125 950 550 1625 0.5*0.1*0.5=0.025
175 800 500 1475 0.3*0.1*0.5=0.015
175 800 550 1525 0.3*0.1*0.5=0.015
175 850 500 1525 0.3*0.3*0.5=0.045
175 850 550 1575 0.3*0.3*0.5=0.045
175 900 500 1575 0.3*0.5*0.5=0.075
175 900 550 1625 0.3*0.5*0.5=0.075
175 950 500 1625 0.3*0.1*0.5=0.015
175 950 550 1675 0.3*0.1*0.5=0.015
Total profit Distribution
Profit(thousands) Probability
1375 0.01
1425 0.065
1475 0.195
1525 0.32
1575 0.26
1625 0.115
1675 0.015
∑=1
Assignment of Random Numbers to profit Values
Random Numbers Trial profit Values
0,1 75
2,3,4,5,6 125
7,8,9 175
Random
Numbers
Trial Profit
0 800
1,2,3 850
4,5,6,7,8 900
9 950
Random
Numbers
Trial Profit
0,1,2,3,4 500
5,6,7,8,9 550
Product 2 Product 3
Table: Monte Carlo Results for the Total Profit Distribution
Profit 1375 1425 1475 1525 1575 1625 1675 Approximant Computer
Time Per Run
True
Probabilities
0.01 0.065 0.195 0.32 0.26 0.115 0.015
No: of Trials
10 0 0 1 2 4 3 0
10 0 0 1 6 2 1 0 < 1 Second
10 0 1 2 4 2 1 0
100 0 4 24 28 34 9 1
100 2 6 22 26 27 17 0 1 ¼ Seconds
100 1 5 15 34 28 15 2
100 0 9 26 31 24 8 2
1000 7 63 191 318 279 120 22 11 Seconds
1000 11 62 207 317 283 101 19
1000 6 77 198 299 290 108 22
10000 97 659 1955 3228 2744 1151 166 < 2 minutes
10000 104 646 1945 3208 2833 1108 158
10000 103 637 1945 3196 2803 1155 161
100000 1025 6393 19622 32028 28074 11276 1582 < 16 minutes
Conclusion
Use of the simulations can be helpful in solving complex decisions but they are
very expensive and need additional training to use them. Selecting the simulation
is also the a big problem because they are not made for the short term decisions .
Monte Carlo decision model is helpful very much and mostly it has been used
because it provides us an accurate results
Incorporation risk1

More Related Content

Similar to Incorporation risk1

Forward-Looking ALLL: Computing Qualitative Adjustments
Forward-Looking ALLL: Computing Qualitative AdjustmentsForward-Looking ALLL: Computing Qualitative Adjustments
Forward-Looking ALLL: Computing Qualitative AdjustmentsLibby Bierman
 
The Impact of Complexity Costs on Operations Planning
The Impact of Complexity Costs on Operations PlanningThe Impact of Complexity Costs on Operations Planning
The Impact of Complexity Costs on Operations PlanningWilson Perumal and Company
 
MLX 2018 - Marcos López de Prado, Lawrence Berkeley National Laboratory Comp...
MLX 2018 - Marcos López de Prado, Lawrence Berkeley National Laboratory Comp...MLX 2018 - Marcos López de Prado, Lawrence Berkeley National Laboratory Comp...
MLX 2018 - Marcos López de Prado, Lawrence Berkeley National Laboratory Comp...Mehdi Merai Ph.D.(c)
 
Stop Flying Blind! Quantifying Risk with Monte Carlo Simulation
Stop Flying Blind! Quantifying Risk with Monte Carlo SimulationStop Flying Blind! Quantifying Risk with Monte Carlo Simulation
Stop Flying Blind! Quantifying Risk with Monte Carlo SimulationSam McAfee
 
Stochastic Modeling - Financial Reporting
Stochastic Modeling - Financial ReportingStochastic Modeling - Financial Reporting
Stochastic Modeling - Financial ReportingRon Harasym
 
Unit2 montecarlosimulation
Unit2 montecarlosimulationUnit2 montecarlosimulation
Unit2 montecarlosimulationDevaKumari Vijay
 
Unit 4 simulation and queing theory(m/m/1)
Unit 4  simulation and queing theory(m/m/1)Unit 4  simulation and queing theory(m/m/1)
Unit 4 simulation and queing theory(m/m/1)DevaKumari Vijay
 
Evaluation of transport safety policies in commercial motorcycle operation in...
Evaluation of transport safety policies in commercial motorcycle operation in...Evaluation of transport safety policies in commercial motorcycle operation in...
Evaluation of transport safety policies in commercial motorcycle operation in...Institute for Transport Studies (ITS)
 
Unit 2 monte carlo simulation
Unit 2 monte carlo simulationUnit 2 monte carlo simulation
Unit 2 monte carlo simulationDevaKumari Vijay
 
Maintaining Credit Quality in Banks and Credit Unions
Maintaining Credit Quality in Banks and Credit UnionsMaintaining Credit Quality in Banks and Credit Unions
Maintaining Credit Quality in Banks and Credit UnionsLibby Bierman
 
Smart solutions for productivity gain IQA conference 2017
Smart solutions for productivity gain   IQA conference 2017Smart solutions for productivity gain   IQA conference 2017
Smart solutions for productivity gain IQA conference 2017Steve Franklin
 
Risk_Management_Final_Report
Risk_Management_Final_ReportRisk_Management_Final_Report
Risk_Management_Final_ReportRohan Sanas
 
Introduction To Six Sigma
Introduction To Six SigmaIntroduction To Six Sigma
Introduction To Six Sigmaskoscielak
 
Introduction to Six Sigma
Introduction to Six SigmaIntroduction to Six Sigma
Introduction to Six SigmaKanriConsulting
 
OPERATION RESEARCH Simulation
OPERATION RESEARCH SimulationOPERATION RESEARCH Simulation
OPERATION RESEARCH SimulationKomal Hambir
 
Six Sigma and Its Implementation
Six Sigma and Its ImplementationSix Sigma and Its Implementation
Six Sigma and Its ImplementationAnsar Lawi
 

Similar to Incorporation risk1 (20)

Forward-Looking ALLL: Computing Qualitative Adjustments
Forward-Looking ALLL: Computing Qualitative AdjustmentsForward-Looking ALLL: Computing Qualitative Adjustments
Forward-Looking ALLL: Computing Qualitative Adjustments
 
SIMULATION.pptx
SIMULATION.pptxSIMULATION.pptx
SIMULATION.pptx
 
The Impact of Complexity Costs on Operations Planning
The Impact of Complexity Costs on Operations PlanningThe Impact of Complexity Costs on Operations Planning
The Impact of Complexity Costs on Operations Planning
 
MLX 2018 - Marcos López de Prado, Lawrence Berkeley National Laboratory Comp...
MLX 2018 - Marcos López de Prado, Lawrence Berkeley National Laboratory Comp...MLX 2018 - Marcos López de Prado, Lawrence Berkeley National Laboratory Comp...
MLX 2018 - Marcos López de Prado, Lawrence Berkeley National Laboratory Comp...
 
Stop Flying Blind! Quantifying Risk with Monte Carlo Simulation
Stop Flying Blind! Quantifying Risk with Monte Carlo SimulationStop Flying Blind! Quantifying Risk with Monte Carlo Simulation
Stop Flying Blind! Quantifying Risk with Monte Carlo Simulation
 
Stochastic Modeling - Financial Reporting
Stochastic Modeling - Financial ReportingStochastic Modeling - Financial Reporting
Stochastic Modeling - Financial Reporting
 
Unit2 montecarlosimulation
Unit2 montecarlosimulationUnit2 montecarlosimulation
Unit2 montecarlosimulation
 
Unit 4 simulation and queing theory(m/m/1)
Unit 4  simulation and queing theory(m/m/1)Unit 4  simulation and queing theory(m/m/1)
Unit 4 simulation and queing theory(m/m/1)
 
Six sigma technique
Six sigma techniqueSix sigma technique
Six sigma technique
 
Evaluation of transport safety policies in commercial motorcycle operation in...
Evaluation of transport safety policies in commercial motorcycle operation in...Evaluation of transport safety policies in commercial motorcycle operation in...
Evaluation of transport safety policies in commercial motorcycle operation in...
 
AUDITO TOOLS
AUDITO TOOLSAUDITO TOOLS
AUDITO TOOLS
 
Unit 2 monte carlo simulation
Unit 2 monte carlo simulationUnit 2 monte carlo simulation
Unit 2 monte carlo simulation
 
Maintaining Credit Quality in Banks and Credit Unions
Maintaining Credit Quality in Banks and Credit UnionsMaintaining Credit Quality in Banks and Credit Unions
Maintaining Credit Quality in Banks and Credit Unions
 
Smart solutions for productivity gain IQA conference 2017
Smart solutions for productivity gain   IQA conference 2017Smart solutions for productivity gain   IQA conference 2017
Smart solutions for productivity gain IQA conference 2017
 
Risk_Management_Final_Report
Risk_Management_Final_ReportRisk_Management_Final_Report
Risk_Management_Final_Report
 
Six Sigma Overview
Six Sigma OverviewSix Sigma Overview
Six Sigma Overview
 
Introduction To Six Sigma
Introduction To Six SigmaIntroduction To Six Sigma
Introduction To Six Sigma
 
Introduction to Six Sigma
Introduction to Six SigmaIntroduction to Six Sigma
Introduction to Six Sigma
 
OPERATION RESEARCH Simulation
OPERATION RESEARCH SimulationOPERATION RESEARCH Simulation
OPERATION RESEARCH Simulation
 
Six Sigma and Its Implementation
Six Sigma and Its ImplementationSix Sigma and Its Implementation
Six Sigma and Its Implementation
 

Recently uploaded

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 

Recently uploaded (20)

(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 

Incorporation risk1

  • 2. Presentation forming group • Zulfiqar Ansari 12IN118 • Shehroze Mughal 12IN01 • Jazib Zai 12IN126 • Zahid Ali Abbasi 12IN127 • Mohsin Shaikh 12IN132 • Serwan Ali Memon 12-11IN54
  • 3. Contents • Introduction • Incorporation • Risk • Simulation • Risk and Simulation • Example • Risk in Decision Making • Risk Analysis • Monte Carlo Simulation • Problem • Conclusion
  • 4. Introduction The term risk today has many different meaning. In financial circles however the term risk has a definite and distinct meaning. Risk refers to the situation where decision are based on the calculation of probabilities that certain outcomes will materialize or where probabilities based on historical information and statistical frequency distribution are known
  • 5. Incorporation • Incorporation is the forming of a new corporation • The process of legally declaring a corporate entity as separate from its owners • A corporation is a company or group of people authorized to act as a single entity (legally a person) and recognized as such in law
  • 6. Risk • Risk is potential of losing something of valuable • Risk is a consequence of action taken in spite of uncertainty • The probability or threat of quantifiable damage, injury, liability, loss, or any other negative occurrence that is caused by external or internal vulnerabilities, and that may be avoided through preemptive action
  • 7. Simulation • The act or process of pretending • The technique of representing the real world by a computer program • The act of giving a false appearance • An attempt to model a real-life or hypothetical situation on a computer so that it can be studied to see how the system works
  • 8. Risk and Simulation • Simulation allows you to evaluate, compare and optimize alternatives designs, plans and policies through visualization • The act of simulating the probabilistic data into statistical form • Simulation is used when the level of uncertainty is high and the alternatives are not quite feasible and taking any action will cause the heavy damages • The complexity of the uncertainties requires the visualization of future consequences
  • 9. Example 1 A fisheries biologist could dynamically simulate the salmon population in a river in order to predict changes to the population and quantitatively understand the impacts on salmon of possible action (e.g. fishing, loss of habitat)to ensure that they don't go extinct at some point in the future
  • 10. Example 2 • When implementing a strategic plan for a company the impacts are likely to take months (or years) to materialize. Simulation is particularly valuable when there is significant uncertainty regarding the outcome or consequences of a particular alternative under consideration. Probabilistic simulation allows dealing with this uncertainty in a quantifiable way
  • 11. Example 3 • The newsvendor problem is one in which a retailer for instance needs to purchase some quantity of an item prior to demand being known. If too few are ordered must be heavily discounted. This fundamental problem commonly occurs in retailing such as when a store needs to order seasonal or perishable merchandise. However it also exists for manufacturers of products that decline in value after they are produced. For example, in the fast changing electronics industry, if a company commits to manufacturing too many handled computers it will be left with product that is worth only a fraction of what is was worth when produced. Even transpiration services such as airlines face a form of this problem since airlines must decide ahead of time how frequently to fly a give route and which type of aircraft to use.
  • 12. Risk in Decision Making • The unpredictable consequence as a result of taking decision • Decision making requires an understanding of the requirements and objectives, their relative importance, and how to assess options and make the 'best' decision • For a successful decision making, understanding the level of risk and its consequence is needed to select the best possible solution
  • 13. Risk Analysis Risk Analysis involves following steps Define the problem Construct the Model Assess Input Variables Calculate Interpret the Model Output Use the Risk analysis in Decision Making
  • 14. Monte Carlo Simulation • Monte Carlo methods are quite useful for simulating systems with many coupled degrees of freedom • Monte Carlo methods can be used to solve any problem having a probabilistic interpretation • Monte Carlo simulation uses repeated sampling to determine the properties of some phenomenon (or behavior). • Monte Carlo simulations sample are taken from a probability distribution for each variable to produce hundreds or thousands of possible outcomes • Monte Carlo methods are especially useful for simulating phenomena with significant uncertainty in inputs and systems with a large number of coupled degrees of freedom
  • 15. Problem Consider a firm that has three unrelated product lines and needs to forecast its total net profit for the coming year. Uncertainty exists in the revenue and cost structures of each product; however, the three divisional managers have assessed their profit distributions as shown in table. These profit distributions are assumed to be Table: Profit Distributions for three products Product 1 Product 2 Product 3 Profit Probability Profit Probability Profit Probability 800000 01 75000 0.2 850000 0.3 500000 0.5 125000 0.5 990000 0.5 550000 0.5 175000 0.3 950000 0.1 ∑=1 ∑=1 ∑=1
  • 16. Table: Evaluation of all possible outcomes Product 1 Product 2 Product 3 Total Probability 75 800 500 1375 0.2*0.1*0.5=0.01 75 800 550 1425 0.2*0.1*0.5=0.01 75 850 500 1425 0.2*0.3*0.5=0.03 75 850 550 1475 0.2*0.3*0.5=0.03 75 900 500 1475 0.2*0.5*0.5=0.05 75 900 550 1525 0.2*0.5*0.5=0.05 75 950 500 1525 0.2*0.1*0.5=0.01 75 950 550 1575 0.2*0.1*0.5=0.01 125 800 500 1425 0.5*0.1*0.5=0.025 125 800 550 1475 0.5*0.1*0.5=0.025 125 850 500 1475 0.5*0.3*0.5=0.075 125 850 550 1525 0.5*0.3*0.5=0.075 125 900 500 1525 0.5*0.5*0.5=0.125 125 900 550 1575 0.5*0.5*0.5=0.125 125 950 500 1575 0.5*0.1*0.5=0.025
  • 17. 125 950 550 1625 0.5*0.1*0.5=0.025 175 800 500 1475 0.3*0.1*0.5=0.015 175 800 550 1525 0.3*0.1*0.5=0.015 175 850 500 1525 0.3*0.3*0.5=0.045 175 850 550 1575 0.3*0.3*0.5=0.045 175 900 500 1575 0.3*0.5*0.5=0.075 175 900 550 1625 0.3*0.5*0.5=0.075 175 950 500 1625 0.3*0.1*0.5=0.015 175 950 550 1675 0.3*0.1*0.5=0.015
  • 18. Total profit Distribution Profit(thousands) Probability 1375 0.01 1425 0.065 1475 0.195 1525 0.32 1575 0.26 1625 0.115 1675 0.015 ∑=1
  • 19. Assignment of Random Numbers to profit Values Random Numbers Trial profit Values 0,1 75 2,3,4,5,6 125 7,8,9 175 Random Numbers Trial Profit 0 800 1,2,3 850 4,5,6,7,8 900 9 950 Random Numbers Trial Profit 0,1,2,3,4 500 5,6,7,8,9 550 Product 2 Product 3
  • 20. Table: Monte Carlo Results for the Total Profit Distribution Profit 1375 1425 1475 1525 1575 1625 1675 Approximant Computer Time Per Run True Probabilities 0.01 0.065 0.195 0.32 0.26 0.115 0.015 No: of Trials 10 0 0 1 2 4 3 0 10 0 0 1 6 2 1 0 < 1 Second 10 0 1 2 4 2 1 0 100 0 4 24 28 34 9 1 100 2 6 22 26 27 17 0 1 ¼ Seconds 100 1 5 15 34 28 15 2 100 0 9 26 31 24 8 2 1000 7 63 191 318 279 120 22 11 Seconds 1000 11 62 207 317 283 101 19 1000 6 77 198 299 290 108 22
  • 21. 10000 97 659 1955 3228 2744 1151 166 < 2 minutes 10000 104 646 1945 3208 2833 1108 158 10000 103 637 1945 3196 2803 1155 161 100000 1025 6393 19622 32028 28074 11276 1582 < 16 minutes
  • 22. Conclusion Use of the simulations can be helpful in solving complex decisions but they are very expensive and need additional training to use them. Selecting the simulation is also the a big problem because they are not made for the short term decisions . Monte Carlo decision model is helpful very much and mostly it has been used because it provides us an accurate results