SlideShare a Scribd company logo
1 of 14
Download to read offline
CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER
THERMAL POWER STATION
A. Radhakrishna1
, V. Srikant2
and N. Jayaraman3
ABSTRACT: Addition of a 500 MW unit to the existing units at Ramagundum Thermal Power
Station requires blasting of large volumes of rock very close to sensitive installations like Turbo
generator, Generator transformer and Power cycle equipments. Levelling of the areas and
excavations for footings are, therefore, to be carried out cautiously. The existing sensitive
installations should be protected against ground vibrations and flyrock. The paper describes the
details of a few of the many blasts carried out successfully wherein the ground vibrations were
restricted and flyrock was avoided.
______________________________________________________________________________
INTRODUCTION
National Thermal Power Corporation Limited (NTPC), a Government of India Enterprise with a
vision to become one of the world's largest and best power utilities, continued its excellent
performance on financial, operational, project execution and environmental fronts. NTPC's total
installed capacity is 20,844 MW. Data monitor, UK has ranked NTPC as the sixth largest
Company in the world in terms of thermal generation and second most efficient in capacity
utilisation on the basis of 1998 data. NTPC is making an all out effort to realise its vision of
becoming a 40,000 MW plus company by 2012. As a step towards this vision, one 500 MW unit
______________________________________________________________________________
1
Asst. General Manager (Projects), NTPC LTD., RAMAGUNDUM AREA, A.P.
2
Managing Director, 3
Executive Director, UTTAM BLASTECH PVT. LTD., HYDERABAD-44, A.P., Tele/Fax:
+91-040-7561339, Email: uttam@vsnl.in
Copyright © 2003 International Society of Explosives Engineers
2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 1 of 14
is being added at Ramagundum Super Thermal Power Station which has already an installed
capacity of 2100 MW (3*200 MW + 3* 500 MW).
NTPC-Ramagundum station is situated on the banks of river Godavari in Karimnagar District of
Andhra Pradesh across coal pit head of Singareni Collieries Co. Ltd., and is known for its all
round excellence in power generation, plant load factor, environmental management, safety and
human resource development. The station supplies power to Southern grid which comprises of
five State electricity boards (viz., Andhra Pradesh, Karnataka, Tamilnadu, Pondichery and
Kerala), two other central power utilities (viz., Neyveli Lignite Power Corporation and Nuclear
Power Corporation) and a few independent power producers. The average peak power demand in
Southern grid is 500 MU while average supply is 440 MU. There is always a gap between
demand and supply. Supply being less than demand, the grid operates at low frequencies at
almost all times of the day. To cater to the growing demand for power in Southern grid, the 7th
unit of 500 MW is being added. The unit under construction is scheduled to be in commercial
operation by the end of February, 2005.
EXISTING FACILITY AND THE TASK
The existing plant has 6 units and was built in two stages. First stage is consisting of 3 units each
of 200 MW and the second phase is consisting of 3 units each of 500 MW capacity. The existing
arrangement of turbo generators, boiler plants and associated transformer / switchyards is shown
in Figure 1.
The seventh unit, a 500 MW unit, is being added as continuation to existing three 500 MW units.
The main power house having turbo generator (TG) hall of 34.0 m span (AB bay) and power
cycle equipment bay of 10.0 m span (BC bay) is envisaged to be extended to house seventh unit
Copyright © 2003 International Society of Explosives Engineers
2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 2 of 14
TG and power cycle equipment. The proposed extension is shown in Figure 1. From Figure 1, it
can be seen that the foundations for TG building, generator transformer, station transformer, TG,
power cycle equipment, steam generator, and mills are coming in close proximity to operating
units. Various ground levels presently existing prior to start of construction of stage - III are
indicated in Figure 1.
The locations of various footings / foundations and envisaged finished ground levels for seventh
unit are indicated in Figure 1. To achieve these ground levels, site levelling involves about
150,000 cum. of earth removal and about 30,000 cum. of excavation in rock requiring blasting is
to be carried out adjoining to running units. Further, for founding various facilities, excavation of
70,000 cum. in rock requiring blasting is to be carried out at depths varying from ( - ) 1.50 m to
( - ) 10.0 m. Therefore, a total of about 100,000 cum. of excavation in rock requiring blasting is
to be carried out adjoining a running plant.
As per Geo-physical survey, the soil layer varies from 0.4 to 1.2 m in depth. The soil layer is
under lain by bed rock consisting of thick sandstone. The sandstone is characterised by P-wave
velocity of 2200 - 2500 m/sec indicating that it is more or less uniform through out the area and
is saturated with water. Average value of elastic constants of the sandstone are:
Young's Modules (E) : 127 x 105
KN/ m2
Shear Modules (G) : 59 x 105
KN/ m2
Poisson's ratio : 0.073
The borehole data are given in Figure 2.
CRITICAL INSTALLATIONS SENSITIVE TO BLASTING
The blasting operations should be carried out in such a manner that it must not and should not
Copyright © 2003 International Society of Explosives Engineers
2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 3 of 14
Figure 1: Existing and Proposed arrangement of facilities at NTPC Ramagundum
Copyright © 2003 International Society of Explosives Engineers
2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 4 of 14
Elevation(m)Elevation(m)
154.0
Figure2:SoilProfilealongNSdirectionNTPCRamagundumStage-IIIMainPlantArea.
Copyright © 2003 International Society of Explosives Engineers
2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 5 of 14
affect the smooth and safe operations of power generation through NTPC-Ramagundum area.
Some of the sensitive areas as declared critical (shown in Fig. 3) for blasting operations by the
NTPC-Ramagundum authorities comprise of;
i. Turbo generator (TG) located at a distance of 40.0 m, and unit transformers situated at a
distance of 26.0 m from the Eastern edge of the Main Area.
ii. Circulating Water (CW) Pump House housing seven pumps each of 30,000cum./hr
capacity common to (3* 500 MW) stage - II, situated at a distance of 20.0 m from the
Western edge of Main Area.
iii. TG hall column foundation F1 at a distance of 6.0 m from running 6th
unit TG hall.
iv. Common Fuel oil Tanks and common ash slurry pump house for stage - II located at a
distance of 20.0 m from culvert foundation.
v. Coal Mill foundation at a distance of 8.0 m from 6th
unit control room.
vi. Chlorination buildings at a minimum distance of 18.0 m as the blast for cooling towers of
7th
unit progresses.
FACTORS TO BE CONSIDERED WHILE BLASTING IN THE CRITICAL AREAS
As the blasting sites are very close to the sensitive installations, the following factors are to be
considered while planning the blasts:
i. Ground vibrations.
ii. Fly rocks. (The porcelain insulators of transformers, particularly, are easily prone to
damage.)
PLANNING THE BLAST
In order to avoid the above said problems, proper planning is essential. The following factors are
to be considered while planning the blasts.
Copyright © 2003 International Society of Explosives Engineers
2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 6 of 14
Figure 3: Location of Blast Areas with reference to Sensetiveness (Not to scale).
INDEX
-------- Proposed
Structure
_____ Existing
Structure Conrol Room
Copyright © 2003 International Society of Explosives Engineers
2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 7 of 14
i. Blast geometry: Choosing proper burden and spacing is essential so that the rock is well
fragmented, but not thrown much.
ii. Charge factor: Too high a charge factor will result in fly rock while a low charge factor
will result in poor fragment size.
iii. Stemming: Ensuring adequate depth of burial of the charge so that while good top
breakage is ensured, ejections of fragments at high velocities are avoided.
iv. Relief: Blast should have adequate relief. The direction of movement of the rock must be
regulated.
BLASTS IN CRITICAL AREAS
The blasts in the Main Area had free face with a maximum height of 7.5 m while the blasts in
other areas were mainly for footings (no free face available), the depth varying from 4.5 - 5.0 m.
While the total charge quantity in the Main Area blasts were of the order of 800 Kgs., blasts for
footings used about 125 - 150 Kgs. of explosives. A typical blast in the Main Area and two blasts
for footings are described below. Other blasts were similar to the above except for some minor
variations.
BLASTS IN THE MAIN AREA
Blasting was started in the main area from the Western end (farthest from TG area and the
transformer yard) and progressed towards East. On the basis of a few initial trial blasts, the
following parameters were chosen:
1. Hole diameter : 41/2" (115 mm)
2. Inclination : 20o
3. Sub grade drilling : 0.3-0.5 m
4. Burden and Spacing : 2.5 m * 3.25 m
5. Bench height : 7.0 - 7.5 m
6. Stemming length : 3.0 - 3.3m
7. Max. Charge per delay : 30 - 58 Kgs.
8. Charge factor : 0.6 - 0.7 kg/m3
9. Shock tube down line : 200ms
Copyright © 2003 International Society of Explosives Engineers
2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 8 of 14
10. Surface shock tubes : 17ms and 42ms
A hole diameter of 21/2" would have been better, but due to non-availability of drills of that size,
41/2" diameter was adopted. As the face reached within 15-20m of the Eastern edge, the face
direction was changed and the blasting was started from the Northern edge so that material would
move only towards the open area in the front and not towards East. Otherwise, the Eastern edge
could act as a free face and some material would move forward towards transformer yard and TG
area of the running 6th
unit thereby causing damage, resulting in stoppage of power generation.
However, as the rock in the NW-NE-Eastern edge was steeply slopping, it was not possible to
drill with the available drilling machine. Therefore, top soil was dumped to a height of about 1 to
1.5 m in this area so that a level ground for the machine to stand on was available to the extent
possible. Even with this arrangement the toe burden was around 6.5 mts. The edge holes were
positioned in such a way that with an inclination of 200
, the toe burden was reduced to around 3.6
to 3.8 mts. The direction of initiation was also adjusted such that the rock moved away from the
East edge. With this amount of burden, and with a proper amount of bottom charge, the toe was
well fragmented but no movement towards East occurred. The blast could be well excavated but
for a few boulders. This process was continued till the limit line towards South edge was reached.
Throughout this phase, there was no flyrock and excavation was smooth. In order to ensure that
no splinter material from blast would get ejected, the top and also the face of the bench were
covered with old conveyor belts well overlapped (Covering mats are not presently available).
Sand bags were placed over the conveyor belt with a covering density of 80 kg/m 2
. The details of
a blast at NW edge and typical initiation pattern is given in figure 4 and 5 respectively.
Copyright © 2003 International Society of Explosives Engineers
2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 9 of 14
SAND BAGS OLD CONVEYOR BELTS
200
SAND BAGS
2.5 M 3.6 - 3.8 M
118 76 34
101 59 17
84 42 Z
101 59 17
118 76 34
160 118 76
NORTH WEST
EDGE SLOPE
Figure 4: Details of a blast at NW edge (Not to scale)
7.0 - 7.5 M
Ground Level
EXPLOSIVES
STEMMING
EAST EDGE SLOPE TOWARDS TG AND TRANSFORMER YARD OF 6th
UNIT
Figure 5 : Blasting initiation pattern at the Main Area.
76 : Delay Timing of the hole excluding Down the hole delay time.
VERTICAL FACE WESTERN EDGE
FREE
FACE
NORTH
EDGE
SLOPE
L
I
M
I
T
O
F
E
X
C
A
V
A
T
I
O
N
Copyright © 2003 International Society of Explosives Engineers
2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 10 of 14
BLASTING FOR FOOTINGS
In case of blasting for footings, the problem of flyrock is more since blasting is done without
any free face (except ground surface). The details of blasts for footings F1 and E33 are given
below in Figure 6 and Figure 7 respectively. In the initial blasts, there was fly rock within an area
of 30m radius all round. Hence, two layers of belts at right angle to each other were used. The
sand bag density was also increased to 100 kg/m 2
of area blasted, while reducing the charge
factor to 0.50 to 0.60 kg/m 3
. The blasts resulted in proper fragmentation and full depth was
excavated. There was hardly any fly rock in these blasts.
Description of Column footing F1
1. Pattern : 2.0m *2.5m
2. Hole depth : 4.0m
3. Depth to be achieved : 3.6m
4. No. of Holes : 15
5. Quantity of explosives : 125 Kgs.
6. charge factor : 0.55 kg/m3
7. Down the hole delay : 250ms
8. Surface delay : 17ms and 42ms
9. Distance from existing structure : 6.0 Mts.
10. Remarks : a). No back break.
b). Good fragmentation achieved.
c). Full depth achieved.
118 76 17 76 118
5.6 m
101 59 Z 59 101
135 93 42 93 135
Figure 6: Initiation pattern for footing F1.
11.25 m
42 : Delay timing of the hole excluding Down the hole delay time.
Copyright © 2003 International Society of Explosives Engineers
2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 11 of 14
Description of Column footing E33
1. Pattern : 2.0m *2.0m
2. Hole depth : 4.6m
3. Depth to be achieved : 4.2m
4. No. of Holes : 12
5. Quantity of explosives : 102 Kgs.
6. charge factor : 0.7 kg/m3
7. Down the hole delay : 250ms
8. Surface delay : 17ms and 42ms
9. Distance from existing Structure : 8.0 Mts.
10. Remarks : a). No back break.
b). Good fragmentation achieved.
c). Full depth achieved.
6.5m
5.0m
GROUND VIBRATIONS
The ground vibrations were controlled by delaying each hole and also limiting the charge in the
hole. A maximum peak particle velocity (ppv) of 0.47 inch per second (46.5 Hz.) was obtained at
the ground level of cooling water pipe lines at the nearest distance of 13m when the blasting was
done in the Main Area. The vibration report of the blast is shown as Figure 8. The maximum ppv
at the Transformer yard (at 26.0 m from the blast in the Main Area) was 0.24 inch per second.
Figure 7 : Initiation pattern for column footing E33.
68 17 17 68
51 Z Z 51
93 34 34 93
17 : Delay Timing of the hole excluding Down the hole delay time.
Copyright © 2003 International Society of Explosives Engineers
2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 12 of 14
Figure 8: Vibration Report of NW edge of blast.
Copyright © 2003 International Society of Explosives Engineers
2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 13 of 14
The monitored values for the blasts in the main area were in general well below the standard and
prescribed limits. The monitored values of peak particle value for blasting for footings were of
the order of 0.25 inch per second.
FLYROCK
The flyrock has been totally minimised by having a proper stemming column which did not vent
out the gases prematurely. The use of conveyor belt and sand bags minimised the possibility of
any small pieces from flying.
CONCLUSIONS
While blasting close to sensitive installations, ground vibrations and flyrock are to be reduced
mainly by having a proper blast design. Burden chosen should be such that the gases are confined
effectively for sufficient period so as to shear the rock at toe level and move the same. Proper
stemming of sufficient height will ensure that no premature venting of gases takes place, as
otherwise the venting will result in flyrock. Use of individual delay for each hole with bottom
initiation and restricting the charge to the minimum ensures that charge weight per delay is under
control thereby reducing the vibrations to within limits.
***
Copyright © 2003 International Society of Explosives Engineers
2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 14 of 14

More Related Content

What's hot

Highwall Mining System
Highwall Mining SystemHighwall Mining System
Highwall Mining Systemibrahim şenol
 
HIGHWALL MINING-INDIAN SCENARIO (1)
HIGHWALL MINING-INDIAN SCENARIO (1)HIGHWALL MINING-INDIAN SCENARIO (1)
HIGHWALL MINING-INDIAN SCENARIO (1)Pushon Ghosh
 
coal mining training report
coal mining training report coal mining training report
coal mining training report VIKRAMSINGH1231
 
Underground coal mining in india
Underground coal mining in indiaUnderground coal mining in india
Underground coal mining in indiaMD.Suresh Kumar
 
Highwall Mining
Highwall MiningHighwall Mining
Highwall MiningAnurag Jha
 
IRJET- Planning, Design & Analysis of a Commercial Building with Flat Sla...
IRJET-  	  Planning, Design & Analysis of a Commercial Building with Flat Sla...IRJET-  	  Planning, Design & Analysis of a Commercial Building with Flat Sla...
IRJET- Planning, Design & Analysis of a Commercial Building with Flat Sla...IRJET Journal
 
Coal Sccl
Coal ScclCoal Sccl
Coal ScclVR M
 
Rion antirion - yerevan - oct 2003
Rion antirion - yerevan  - oct 2003Rion antirion - yerevan  - oct 2003
Rion antirion - yerevan - oct 2003gefyra-rion
 
Highwall Mining Technology
Highwall Mining TechnologyHighwall Mining Technology
Highwall Mining TechnologyVR M
 
Develpoment and extraction of coal pillar by continuous
Develpoment and extraction of coal pillar by continuousDevelpoment and extraction of coal pillar by continuous
Develpoment and extraction of coal pillar by continuousShubham Agrawal
 
Working of icc bwe-rock breaker
Working of icc bwe-rock breakerWorking of icc bwe-rock breaker
Working of icc bwe-rock breakerSATYANARAYANA I
 
Coal Mining Technlogy Brief_Low Coal Seam_HOT Mining
Coal Mining Technlogy Brief_Low Coal Seam_HOT MiningCoal Mining Technlogy Brief_Low Coal Seam_HOT Mining
Coal Mining Technlogy Brief_Low Coal Seam_HOT MiningSerena Fu
 
Design of 3 d rc frame on sloping ground
Design of 3 d rc frame on sloping groundDesign of 3 d rc frame on sloping ground
Design of 3 d rc frame on sloping groundeSAT Publishing House
 
Ottawa Co Model Wind Turbine Ord
Ottawa Co Model Wind Turbine OrdOttawa Co Model Wind Turbine Ord
Ottawa Co Model Wind Turbine Ordbuildingplace
 
Longwall mining at shallow depth
Longwall mining at shallow depthLongwall mining at shallow depth
Longwall mining at shallow depthMD.Suresh Kumar
 

What's hot (20)

Highwall Mining System
Highwall Mining SystemHighwall Mining System
Highwall Mining System
 
HIGHWALL MINING-INDIAN SCENARIO (1)
HIGHWALL MINING-INDIAN SCENARIO (1)HIGHWALL MINING-INDIAN SCENARIO (1)
HIGHWALL MINING-INDIAN SCENARIO (1)
 
Extraction of developed pillars by opencast mine: acase study
Extraction of developed pillars by opencast mine:   acase studyExtraction of developed pillars by opencast mine:   acase study
Extraction of developed pillars by opencast mine: acase study
 
coal mining training report
coal mining training report coal mining training report
coal mining training report
 
Underground coal mining in india
Underground coal mining in indiaUnderground coal mining in india
Underground coal mining in india
 
Highwall Mining
Highwall MiningHighwall Mining
Highwall Mining
 
IRJET- Planning, Design & Analysis of a Commercial Building with Flat Sla...
IRJET-  	  Planning, Design & Analysis of a Commercial Building with Flat Sla...IRJET-  	  Planning, Design & Analysis of a Commercial Building with Flat Sla...
IRJET- Planning, Design & Analysis of a Commercial Building with Flat Sla...
 
Coal Sccl
Coal ScclCoal Sccl
Coal Sccl
 
Rion antirion - yerevan - oct 2003
Rion antirion - yerevan  - oct 2003Rion antirion - yerevan  - oct 2003
Rion antirion - yerevan - oct 2003
 
Continuous miner
Continuous minerContinuous miner
Continuous miner
 
Highwall Mining Technology
Highwall Mining TechnologyHighwall Mining Technology
Highwall Mining Technology
 
Surface miner
Surface minerSurface miner
Surface miner
 
Develpoment and extraction of coal pillar by continuous
Develpoment and extraction of coal pillar by continuousDevelpoment and extraction of coal pillar by continuous
Develpoment and extraction of coal pillar by continuous
 
Highwall mining
Highwall miningHighwall mining
Highwall mining
 
Working of icc bwe-rock breaker
Working of icc bwe-rock breakerWorking of icc bwe-rock breaker
Working of icc bwe-rock breaker
 
Coal Mining Technlogy Brief_Low Coal Seam_HOT Mining
Coal Mining Technlogy Brief_Low Coal Seam_HOT MiningCoal Mining Technlogy Brief_Low Coal Seam_HOT Mining
Coal Mining Technlogy Brief_Low Coal Seam_HOT Mining
 
PRO_51
PRO_51PRO_51
PRO_51
 
Design of 3 d rc frame on sloping ground
Design of 3 d rc frame on sloping groundDesign of 3 d rc frame on sloping ground
Design of 3 d rc frame on sloping ground
 
Ottawa Co Model Wind Turbine Ord
Ottawa Co Model Wind Turbine OrdOttawa Co Model Wind Turbine Ord
Ottawa Co Model Wind Turbine Ord
 
Longwall mining at shallow depth
Longwall mining at shallow depthLongwall mining at shallow depth
Longwall mining at shallow depth
 

Similar to Isee paper - Uttam Blastech

AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITYAN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITYIRJET Journal
 
Adoption of advanced coal mining practices for production augmentation by und...
Adoption of advanced coal mining practices for production augmentation by und...Adoption of advanced coal mining practices for production augmentation by und...
Adoption of advanced coal mining practices for production augmentation by und...AMIT SAHU
 
A Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
A Theoretical Study on Strata Behaviour and Ground Control in Coal MinesA Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
A Theoretical Study on Strata Behaviour and Ground Control in Coal MinesIRJET Journal
 
Wind Power Plant Planning And Commisioning
Wind Power Plant  Planning  And CommisioningWind Power Plant  Planning  And Commisioning
Wind Power Plant Planning And CommisioningSuraj Naik
 
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPEAN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPEIRJET Journal
 
An experience of Loading pattern on Power supports with Sand stone roof in SCCL
An experience of Loading pattern on Power supports with Sand stone roof in SCCLAn experience of Loading pattern on Power supports with Sand stone roof in SCCL
An experience of Loading pattern on Power supports with Sand stone roof in SCCLMD.Suresh Kumar
 
Nuclear power plant kakarapar
Nuclear power plant kakaraparNuclear power plant kakarapar
Nuclear power plant kakaraparnaitik997
 
In-situ testing to verify ground improvement
In-situ testing to verify ground improvementIn-situ testing to verify ground improvement
In-situ testing to verify ground improvementInfocengrs63
 
IRJET- Assessment of Slope Stability in Opencast Coal Mines using Software
IRJET-  	  Assessment of Slope Stability in Opencast Coal Mines using SoftwareIRJET-  	  Assessment of Slope Stability in Opencast Coal Mines using Software
IRJET- Assessment of Slope Stability in Opencast Coal Mines using SoftwareIRJET Journal
 
Dankuni Coal Complex
Dankuni Coal ComplexDankuni Coal Complex
Dankuni Coal ComplexKumar Saurabh
 
Statistical analysis of various sub systems of panel
Statistical analysis of various sub systems of panelStatistical analysis of various sub systems of panel
Statistical analysis of various sub systems of paneleSAT Publishing House
 
A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.Saurabh Biswas
 

Similar to Isee paper - Uttam Blastech (20)

AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITYAN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
 
Adoption of advanced coal mining practices for production augmentation by und...
Adoption of advanced coal mining practices for production augmentation by und...Adoption of advanced coal mining practices for production augmentation by und...
Adoption of advanced coal mining practices for production augmentation by und...
 
A Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
A Theoretical Study on Strata Behaviour and Ground Control in Coal MinesA Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
A Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
 
Wind Power Plant Planning And Commisioning
Wind Power Plant  Planning  And CommisioningWind Power Plant  Planning  And Commisioning
Wind Power Plant Planning And Commisioning
 
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPEAN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
 
40220140507002
4022014050700240220140507002
40220140507002
 
40220140507002
4022014050700240220140507002
40220140507002
 
An experience of Loading pattern on Power supports with Sand stone roof in SCCL
An experience of Loading pattern on Power supports with Sand stone roof in SCCLAn experience of Loading pattern on Power supports with Sand stone roof in SCCL
An experience of Loading pattern on Power supports with Sand stone roof in SCCL
 
Nuclear power plant kakarapar
Nuclear power plant kakaraparNuclear power plant kakarapar
Nuclear power plant kakarapar
 
In-situ testing to verify ground improvement
In-situ testing to verify ground improvementIn-situ testing to verify ground improvement
In-situ testing to verify ground improvement
 
Choosing Right Transformer
Choosing Right TransformerChoosing Right Transformer
Choosing Right Transformer
 
IRJET- Assessment of Slope Stability in Opencast Coal Mines using Software
IRJET-  	  Assessment of Slope Stability in Opencast Coal Mines using SoftwareIRJET-  	  Assessment of Slope Stability in Opencast Coal Mines using Software
IRJET- Assessment of Slope Stability in Opencast Coal Mines using Software
 
Gulshan rahangdale
Gulshan rahangdaleGulshan rahangdale
Gulshan rahangdale
 
Dankuni Coal Complex
Dankuni Coal ComplexDankuni Coal Complex
Dankuni Coal Complex
 
40220140507001
4022014050700140220140507001
40220140507001
 
40220140507001
4022014050700140220140507001
40220140507001
 
Statistical analysis of various sub systems of panel
Statistical analysis of various sub systems of panelStatistical analysis of various sub systems of panel
Statistical analysis of various sub systems of panel
 
Aircooling underground coal mine
 Aircooling underground coal mine Aircooling underground coal mine
Aircooling underground coal mine
 
A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.
 
My report vfd
My  report vfdMy  report vfd
My report vfd
 

More from Uttam Blastech

Uttam Blastech - Services & Products
Uttam Blastech - Services & ProductsUttam Blastech - Services & Products
Uttam Blastech - Services & ProductsUttam Blastech
 
Do youknow - Uttam Blastech
Do youknow - Uttam BlastechDo youknow - Uttam Blastech
Do youknow - Uttam BlastechUttam Blastech
 
Uttam blastech - Brochure
Uttam blastech - BrochureUttam blastech - Brochure
Uttam blastech - BrochureUttam Blastech
 
Seismograph tips - Uttam Blastech
Seismograph tips - Uttam Blastech Seismograph tips - Uttam Blastech
Seismograph tips - Uttam Blastech Uttam Blastech
 
Testimonials srilaxmi - Uttam Blastech
Testimonials srilaxmi - Uttam Blastech Testimonials srilaxmi - Uttam Blastech
Testimonials srilaxmi - Uttam Blastech Uttam Blastech
 

More from Uttam Blastech (6)

Uttam Blastech - Logo
Uttam Blastech - LogoUttam Blastech - Logo
Uttam Blastech - Logo
 
Uttam Blastech - Services & Products
Uttam Blastech - Services & ProductsUttam Blastech - Services & Products
Uttam Blastech - Services & Products
 
Do youknow - Uttam Blastech
Do youknow - Uttam BlastechDo youknow - Uttam Blastech
Do youknow - Uttam Blastech
 
Uttam blastech - Brochure
Uttam blastech - BrochureUttam blastech - Brochure
Uttam blastech - Brochure
 
Seismograph tips - Uttam Blastech
Seismograph tips - Uttam Blastech Seismograph tips - Uttam Blastech
Seismograph tips - Uttam Blastech
 
Testimonials srilaxmi - Uttam Blastech
Testimonials srilaxmi - Uttam Blastech Testimonials srilaxmi - Uttam Blastech
Testimonials srilaxmi - Uttam Blastech
 

Recently uploaded

microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 

Recently uploaded (20)

microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 

Isee paper - Uttam Blastech

  • 1. CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION A. Radhakrishna1 , V. Srikant2 and N. Jayaraman3 ABSTRACT: Addition of a 500 MW unit to the existing units at Ramagundum Thermal Power Station requires blasting of large volumes of rock very close to sensitive installations like Turbo generator, Generator transformer and Power cycle equipments. Levelling of the areas and excavations for footings are, therefore, to be carried out cautiously. The existing sensitive installations should be protected against ground vibrations and flyrock. The paper describes the details of a few of the many blasts carried out successfully wherein the ground vibrations were restricted and flyrock was avoided. ______________________________________________________________________________ INTRODUCTION National Thermal Power Corporation Limited (NTPC), a Government of India Enterprise with a vision to become one of the world's largest and best power utilities, continued its excellent performance on financial, operational, project execution and environmental fronts. NTPC's total installed capacity is 20,844 MW. Data monitor, UK has ranked NTPC as the sixth largest Company in the world in terms of thermal generation and second most efficient in capacity utilisation on the basis of 1998 data. NTPC is making an all out effort to realise its vision of becoming a 40,000 MW plus company by 2012. As a step towards this vision, one 500 MW unit ______________________________________________________________________________ 1 Asst. General Manager (Projects), NTPC LTD., RAMAGUNDUM AREA, A.P. 2 Managing Director, 3 Executive Director, UTTAM BLASTECH PVT. LTD., HYDERABAD-44, A.P., Tele/Fax: +91-040-7561339, Email: uttam@vsnl.in Copyright © 2003 International Society of Explosives Engineers 2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 1 of 14
  • 2. is being added at Ramagundum Super Thermal Power Station which has already an installed capacity of 2100 MW (3*200 MW + 3* 500 MW). NTPC-Ramagundum station is situated on the banks of river Godavari in Karimnagar District of Andhra Pradesh across coal pit head of Singareni Collieries Co. Ltd., and is known for its all round excellence in power generation, plant load factor, environmental management, safety and human resource development. The station supplies power to Southern grid which comprises of five State electricity boards (viz., Andhra Pradesh, Karnataka, Tamilnadu, Pondichery and Kerala), two other central power utilities (viz., Neyveli Lignite Power Corporation and Nuclear Power Corporation) and a few independent power producers. The average peak power demand in Southern grid is 500 MU while average supply is 440 MU. There is always a gap between demand and supply. Supply being less than demand, the grid operates at low frequencies at almost all times of the day. To cater to the growing demand for power in Southern grid, the 7th unit of 500 MW is being added. The unit under construction is scheduled to be in commercial operation by the end of February, 2005. EXISTING FACILITY AND THE TASK The existing plant has 6 units and was built in two stages. First stage is consisting of 3 units each of 200 MW and the second phase is consisting of 3 units each of 500 MW capacity. The existing arrangement of turbo generators, boiler plants and associated transformer / switchyards is shown in Figure 1. The seventh unit, a 500 MW unit, is being added as continuation to existing three 500 MW units. The main power house having turbo generator (TG) hall of 34.0 m span (AB bay) and power cycle equipment bay of 10.0 m span (BC bay) is envisaged to be extended to house seventh unit Copyright © 2003 International Society of Explosives Engineers 2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 2 of 14
  • 3. TG and power cycle equipment. The proposed extension is shown in Figure 1. From Figure 1, it can be seen that the foundations for TG building, generator transformer, station transformer, TG, power cycle equipment, steam generator, and mills are coming in close proximity to operating units. Various ground levels presently existing prior to start of construction of stage - III are indicated in Figure 1. The locations of various footings / foundations and envisaged finished ground levels for seventh unit are indicated in Figure 1. To achieve these ground levels, site levelling involves about 150,000 cum. of earth removal and about 30,000 cum. of excavation in rock requiring blasting is to be carried out adjoining to running units. Further, for founding various facilities, excavation of 70,000 cum. in rock requiring blasting is to be carried out at depths varying from ( - ) 1.50 m to ( - ) 10.0 m. Therefore, a total of about 100,000 cum. of excavation in rock requiring blasting is to be carried out adjoining a running plant. As per Geo-physical survey, the soil layer varies from 0.4 to 1.2 m in depth. The soil layer is under lain by bed rock consisting of thick sandstone. The sandstone is characterised by P-wave velocity of 2200 - 2500 m/sec indicating that it is more or less uniform through out the area and is saturated with water. Average value of elastic constants of the sandstone are: Young's Modules (E) : 127 x 105 KN/ m2 Shear Modules (G) : 59 x 105 KN/ m2 Poisson's ratio : 0.073 The borehole data are given in Figure 2. CRITICAL INSTALLATIONS SENSITIVE TO BLASTING The blasting operations should be carried out in such a manner that it must not and should not Copyright © 2003 International Society of Explosives Engineers 2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 3 of 14
  • 4. Figure 1: Existing and Proposed arrangement of facilities at NTPC Ramagundum Copyright © 2003 International Society of Explosives Engineers 2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 4 of 14
  • 5. Elevation(m)Elevation(m) 154.0 Figure2:SoilProfilealongNSdirectionNTPCRamagundumStage-IIIMainPlantArea. Copyright © 2003 International Society of Explosives Engineers 2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 5 of 14
  • 6. affect the smooth and safe operations of power generation through NTPC-Ramagundum area. Some of the sensitive areas as declared critical (shown in Fig. 3) for blasting operations by the NTPC-Ramagundum authorities comprise of; i. Turbo generator (TG) located at a distance of 40.0 m, and unit transformers situated at a distance of 26.0 m from the Eastern edge of the Main Area. ii. Circulating Water (CW) Pump House housing seven pumps each of 30,000cum./hr capacity common to (3* 500 MW) stage - II, situated at a distance of 20.0 m from the Western edge of Main Area. iii. TG hall column foundation F1 at a distance of 6.0 m from running 6th unit TG hall. iv. Common Fuel oil Tanks and common ash slurry pump house for stage - II located at a distance of 20.0 m from culvert foundation. v. Coal Mill foundation at a distance of 8.0 m from 6th unit control room. vi. Chlorination buildings at a minimum distance of 18.0 m as the blast for cooling towers of 7th unit progresses. FACTORS TO BE CONSIDERED WHILE BLASTING IN THE CRITICAL AREAS As the blasting sites are very close to the sensitive installations, the following factors are to be considered while planning the blasts: i. Ground vibrations. ii. Fly rocks. (The porcelain insulators of transformers, particularly, are easily prone to damage.) PLANNING THE BLAST In order to avoid the above said problems, proper planning is essential. The following factors are to be considered while planning the blasts. Copyright © 2003 International Society of Explosives Engineers 2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 6 of 14
  • 7. Figure 3: Location of Blast Areas with reference to Sensetiveness (Not to scale). INDEX -------- Proposed Structure _____ Existing Structure Conrol Room Copyright © 2003 International Society of Explosives Engineers 2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 7 of 14
  • 8. i. Blast geometry: Choosing proper burden and spacing is essential so that the rock is well fragmented, but not thrown much. ii. Charge factor: Too high a charge factor will result in fly rock while a low charge factor will result in poor fragment size. iii. Stemming: Ensuring adequate depth of burial of the charge so that while good top breakage is ensured, ejections of fragments at high velocities are avoided. iv. Relief: Blast should have adequate relief. The direction of movement of the rock must be regulated. BLASTS IN CRITICAL AREAS The blasts in the Main Area had free face with a maximum height of 7.5 m while the blasts in other areas were mainly for footings (no free face available), the depth varying from 4.5 - 5.0 m. While the total charge quantity in the Main Area blasts were of the order of 800 Kgs., blasts for footings used about 125 - 150 Kgs. of explosives. A typical blast in the Main Area and two blasts for footings are described below. Other blasts were similar to the above except for some minor variations. BLASTS IN THE MAIN AREA Blasting was started in the main area from the Western end (farthest from TG area and the transformer yard) and progressed towards East. On the basis of a few initial trial blasts, the following parameters were chosen: 1. Hole diameter : 41/2" (115 mm) 2. Inclination : 20o 3. Sub grade drilling : 0.3-0.5 m 4. Burden and Spacing : 2.5 m * 3.25 m 5. Bench height : 7.0 - 7.5 m 6. Stemming length : 3.0 - 3.3m 7. Max. Charge per delay : 30 - 58 Kgs. 8. Charge factor : 0.6 - 0.7 kg/m3 9. Shock tube down line : 200ms Copyright © 2003 International Society of Explosives Engineers 2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 8 of 14
  • 9. 10. Surface shock tubes : 17ms and 42ms A hole diameter of 21/2" would have been better, but due to non-availability of drills of that size, 41/2" diameter was adopted. As the face reached within 15-20m of the Eastern edge, the face direction was changed and the blasting was started from the Northern edge so that material would move only towards the open area in the front and not towards East. Otherwise, the Eastern edge could act as a free face and some material would move forward towards transformer yard and TG area of the running 6th unit thereby causing damage, resulting in stoppage of power generation. However, as the rock in the NW-NE-Eastern edge was steeply slopping, it was not possible to drill with the available drilling machine. Therefore, top soil was dumped to a height of about 1 to 1.5 m in this area so that a level ground for the machine to stand on was available to the extent possible. Even with this arrangement the toe burden was around 6.5 mts. The edge holes were positioned in such a way that with an inclination of 200 , the toe burden was reduced to around 3.6 to 3.8 mts. The direction of initiation was also adjusted such that the rock moved away from the East edge. With this amount of burden, and with a proper amount of bottom charge, the toe was well fragmented but no movement towards East occurred. The blast could be well excavated but for a few boulders. This process was continued till the limit line towards South edge was reached. Throughout this phase, there was no flyrock and excavation was smooth. In order to ensure that no splinter material from blast would get ejected, the top and also the face of the bench were covered with old conveyor belts well overlapped (Covering mats are not presently available). Sand bags were placed over the conveyor belt with a covering density of 80 kg/m 2 . The details of a blast at NW edge and typical initiation pattern is given in figure 4 and 5 respectively. Copyright © 2003 International Society of Explosives Engineers 2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 9 of 14
  • 10. SAND BAGS OLD CONVEYOR BELTS 200 SAND BAGS 2.5 M 3.6 - 3.8 M 118 76 34 101 59 17 84 42 Z 101 59 17 118 76 34 160 118 76 NORTH WEST EDGE SLOPE Figure 4: Details of a blast at NW edge (Not to scale) 7.0 - 7.5 M Ground Level EXPLOSIVES STEMMING EAST EDGE SLOPE TOWARDS TG AND TRANSFORMER YARD OF 6th UNIT Figure 5 : Blasting initiation pattern at the Main Area. 76 : Delay Timing of the hole excluding Down the hole delay time. VERTICAL FACE WESTERN EDGE FREE FACE NORTH EDGE SLOPE L I M I T O F E X C A V A T I O N Copyright © 2003 International Society of Explosives Engineers 2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 10 of 14
  • 11. BLASTING FOR FOOTINGS In case of blasting for footings, the problem of flyrock is more since blasting is done without any free face (except ground surface). The details of blasts for footings F1 and E33 are given below in Figure 6 and Figure 7 respectively. In the initial blasts, there was fly rock within an area of 30m radius all round. Hence, two layers of belts at right angle to each other were used. The sand bag density was also increased to 100 kg/m 2 of area blasted, while reducing the charge factor to 0.50 to 0.60 kg/m 3 . The blasts resulted in proper fragmentation and full depth was excavated. There was hardly any fly rock in these blasts. Description of Column footing F1 1. Pattern : 2.0m *2.5m 2. Hole depth : 4.0m 3. Depth to be achieved : 3.6m 4. No. of Holes : 15 5. Quantity of explosives : 125 Kgs. 6. charge factor : 0.55 kg/m3 7. Down the hole delay : 250ms 8. Surface delay : 17ms and 42ms 9. Distance from existing structure : 6.0 Mts. 10. Remarks : a). No back break. b). Good fragmentation achieved. c). Full depth achieved. 118 76 17 76 118 5.6 m 101 59 Z 59 101 135 93 42 93 135 Figure 6: Initiation pattern for footing F1. 11.25 m 42 : Delay timing of the hole excluding Down the hole delay time. Copyright © 2003 International Society of Explosives Engineers 2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 11 of 14
  • 12. Description of Column footing E33 1. Pattern : 2.0m *2.0m 2. Hole depth : 4.6m 3. Depth to be achieved : 4.2m 4. No. of Holes : 12 5. Quantity of explosives : 102 Kgs. 6. charge factor : 0.7 kg/m3 7. Down the hole delay : 250ms 8. Surface delay : 17ms and 42ms 9. Distance from existing Structure : 8.0 Mts. 10. Remarks : a). No back break. b). Good fragmentation achieved. c). Full depth achieved. 6.5m 5.0m GROUND VIBRATIONS The ground vibrations were controlled by delaying each hole and also limiting the charge in the hole. A maximum peak particle velocity (ppv) of 0.47 inch per second (46.5 Hz.) was obtained at the ground level of cooling water pipe lines at the nearest distance of 13m when the blasting was done in the Main Area. The vibration report of the blast is shown as Figure 8. The maximum ppv at the Transformer yard (at 26.0 m from the blast in the Main Area) was 0.24 inch per second. Figure 7 : Initiation pattern for column footing E33. 68 17 17 68 51 Z Z 51 93 34 34 93 17 : Delay Timing of the hole excluding Down the hole delay time. Copyright © 2003 International Society of Explosives Engineers 2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 12 of 14
  • 13. Figure 8: Vibration Report of NW edge of blast. Copyright © 2003 International Society of Explosives Engineers 2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 13 of 14
  • 14. The monitored values for the blasts in the main area were in general well below the standard and prescribed limits. The monitored values of peak particle value for blasting for footings were of the order of 0.25 inch per second. FLYROCK The flyrock has been totally minimised by having a proper stemming column which did not vent out the gases prematurely. The use of conveyor belt and sand bags minimised the possibility of any small pieces from flying. CONCLUSIONS While blasting close to sensitive installations, ground vibrations and flyrock are to be reduced mainly by having a proper blast design. Burden chosen should be such that the gases are confined effectively for sufficient period so as to shear the rock at toe level and move the same. Proper stemming of sufficient height will ensure that no premature venting of gases takes place, as otherwise the venting will result in flyrock. Use of individual delay for each hole with bottom initiation and restricting the charge to the minimum ensures that charge weight per delay is under control thereby reducing the vibrations to within limits. *** Copyright © 2003 International Society of Explosives Engineers 2003G Volume 2 - CAUTIOUS BLASTING IN CRITICAL AREAS AT RAMAGUNDAM SUPER THERMAL POWER STATION 14 of 14