SlideShare a Scribd company logo
1 of 15
Download to read offline
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 1
STATISTICAL ANALYSIS OF VARIOUS SUB-SYSTEMS OF PANEL
PRODUCTION SYSTEM IN UNDERGROUND COAL MINE
Md. Soyeb Alam1
1
Assistant Professor, Department of Mining Engineering, Indian School of Mines, Dhanbad-826004, Jharkhand, India,
multisoyeb2004@gmail.com
Abstract
System Analysis Approach has been applied in the present field based research paper for a deep and gassy coal mine of Jharia coal
fields. The working panel was considered as a System, splitted into various sub-Systems. The Sub-Systems were statistically analyzed
in terms of frequency distribution (after prolonged field observations). The Mean, Median, Mode, Standard deviation, Variance and
co-efficient of variation were calculated. Among the Mean, Median and Mode, Mean was considered for Capacity (in terms of
production) calculation of various Sub-systems
-----------------------------------------------------------------------***----------------------------------------------------------------------
1. INTRODUCTION
The Supremacy of Coal as a Prime and secured source of
energy is unlikely to be challenged in foreseeable future
particularly in Indian context. The demands estimates of 620
million ton and 780 million ton during the terminal phases of
XI and XII plan respectively also substantiate the larger
dependence on coal (Chaoji, 2002 ; Rai et al, 2005). To cater
the projected demand targets, the Indian coal industry needs
be geared up for accelerated growth in terms of production as
well as productivity. The open cast mining, with state of art
mechanization is likely to become uneconomical beyond a
certain depth, as the open cast technology and equipment have
already reached a stage of plateau beyond which further
growth is mostly unforeseen (Rai, 2001). Karmakar (1996) has
also expressed that production of coal will depend more on
underground mine as against present predominance of surface
mines. Looking from these standpoints, the Industry may be
compelled to increase its share of coal production from
underground mines in forth coming years, particularly for
deep seated reserves which are vastly untapped at this point of
time.
At present, the underground coal mines of our country are
generally stricken with problem of low production and
productivity (sachdev, 1993 & Mathur, 1999). This is largely
because of the fact that production planning for the
underground coal mines is a cumbersome process which calls
for sound understanding of various underlying operations to
critically assess the sensitive interrelationships amongst them
(Mukhopadhaya et al, 1993). Hence, immediate attention and
investigation into the performance and appropriate planning
process for the underground mines is imperative as also
pointed by Bhattacherjee et al, 1996.
The system anlysis based approach appears to offer
rationalized solution to solving the complex and intricate
production planning from underground mines. In this
approach the entire mine (or even a part of the mine) may be
considered as system, the capacity of which is dependent on
its related sub-systems (Ray et al, 1978). A proper
understanding of any system and its related sub-systems could
provide intriguing facts in order to practice of this approach in
a large underground coal mine which falls in prime coking
coal zone of Jharia Coal fields, Dhanbad, India.
2. AIMS OF THE STUDY:
As already stated, the present research paper aims at deploying
the System Analysis approach for large underground Coal
Mine of Jharia Coal Fields. The specific aims of the present
work are enumerated as
1. To study the Panel as a system and to identify the
important sub-systems for the panel
2. To Critically analysed the various sub-systems
Statistically.
3. RELEVANT DETAILS OF THE MINE & MINE
WORKINGS:
The present Research work was undertaken in a large,
privately owned underground ‘Mine-A’, Jharia Coal Field.
One seam, namely XI was being worked in the mine. The bore
hole section of the Mine-A has been shown in fig.1.The salient
geo-mining details of the Coal seam is as per table 1 & details
of panels working as per table 2.
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 2
Table 1: Salient geo-mining details of the Coal seam
ITEM XI SEAM
Av. thickness 7.31 m
Av. depth 400 m
Av. dip 1in 7
Dip direction S760
50' W
Shape of seam Basin like
Degree of gassiness Degree II
R.M.R. Value 34.46 (not good)
Geological features Highly faulted with Intrusion
Mode of entry 3 shaft
Type of ventilation CVS
Coal transportation Through incline by Belt
Conveyor upto Surface
50.91 m
1.67 m
16 A SEAM(C OAL)
16 SEAM (C OAL)
14 A SEAM (JHAMA)
13 SEAM (JHAMA)
12 SEAM (COAL & JHAMA)
11 SEAM (C OAL)
10 SEAM (COAL & JHAMA)
9 SEAM (COAL)
84.14 m
157.92 m
199.39 m
209.14 m
236.58 m
255.94 m
283.10 m
320.14 m
337.42 m
386.64 m
3.20 m
1.83 m
8.23 m
3.20 m
8.23 m
7.01 m
3.5 m
7.31 m
4.09 m
7.27 m
15 A SEAM (C OAL)
15 SEAM (C OAL)
14 SEAM (C OAL)
Fig 1: Bore hole section at 9 pit ‘Mine-A’
Table 2: Details of panel working in the Mine-A
Panel
Name
Minimum
Avg.depth
(m)
Avg.
pillar
size(m)
Gallery Size (m)
(w×h)
Coal preparation
method
Loading Transport
Panel-
11/10-S
370 45 × 45 4.2 × 3.0,
4.8 × 3.0 (slice)
Bord &Pillar (dep.,
bottom sec.)
SDL Conveyor
Panel-
11/7-S
400 45 × 45 4.2 × 2.8,
4.8× 2.8 (slice)
Bord & Pillar (dev. &
dep., top sec.)
SDL Conveyor
Panel-
11/3-S
400 45 × 45 4.2× 2.7,
4.8× 2.7 (slice)
Bord & Pillar (dep.,
top sec.)
manual Conveyor
Panel-
11/9-S
325 45 × 45 4.2× 2.7,
4.8× 2.7 (slice)
Bord & Pillar (dev. &
dep., bottom & top
sec. both)
SDL Conveyor
4. BRIEF DESCRIPTION OF COAL WINNING IN
THE STUDY PANEL
There were three semi-mechanised panels namely, panel
‘11/7-S’, ‘11/10-S’ & ‘11/9-S’ and one manual panel namely
panel ‘11/3-S’ in the given mine. The study was conducted in
the semi-mechanised panel 11/7-S in the mine. The
description of the coal winning in the study panel as follows:
Bottom section of panel 11/7-S had been developed and
depillared upto 3.0 m height by bord and pillar (B/P) method
of working in conjunction with hydraulic sand stowing. some
portion of bottom section had been left for the purpose of
sumping. Depillaring in bottom section had been done by
splitting pillar into four parts. After leaving a parting of almost
1.5 m, top section 2.8m was being developed & depillared
simultaneously by B/P method of working. Top section
depillaring by means of modified depillaring method in which
taking dip-rise slice simultaneously then judicial extraction of
rib in conjunction with hydraulic sand stowing
Panel consisted of 3 SDLs, (one SDL for development and
two SDLs for depillaring) loading coal on separate light duty
chain conveyor (LDCC). Coal broken by drilling & blasting
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 3
was loaded on LDCC by means of side discharge loader
(SDL) with bucket capacity of 1.5cu.m. face conveyor
discharged the coal on the belt conveyor to be carried out bye
through a system of belts up to the coal washery located on
surface. The galleries, splits and slices were supported
systematically by the roof bolts having yield load of 5 tonne.
5. RESEARCH METHODOLOGY
The aforesaid concept of breaking a mine system into sub-
systems for finer analysis, has been adopted in the present case
study, considering Panel as a system. According the major
sub-systems were formulated as given in fig.2.
PANEL AS A SYSTEM
Face
preparation Loading
Transportation
ventilation stowing pumping
Material
supply
Roof
dressing
Roof
bolting
Face
dressing
Production
drilling
Prim.,charg,
Stem.& blast
Fume
clearance
W ater
spraying
Loose
dressing
Side
bolting
Fig. 2: Formulated systematic proposed model for Present working
6. FIELD OBSERVATIONS:
6.1 Time and Motion Study of Various Sub-Systems:
As per the formulated system model (fig.2) the time & motion
studies were conducted at field scale for various sub-
systems. The statistical data pertaining to the time & motion
studies of various sub-systems such as, face preparation (roof
dressing, roof bolting, side bolting etc.) loading etc. in
statistical format is tabulated in tables 3 to 20. Based on the
statistical tables the mean, median, mode, standard deviation
& co-efficient of variation for face preparation & loading and
mean (average) for stowing & ventilation sub-systems.
Table 3: Frequency distribution of roof dressing per face (minute)
Class
mark
(x)
Frequency
(f)
fx Cumulative
frequency
(c.f)
d = x-A
= x-20.18
d² fd²
14 11 154 11 -6.18 38.19 420.12
15 18 270 29 -5.18 26.83 482.98
16 7 112 36 -4.18 17.47 122.31
17 3 51 39 -3.18 10.11 30.34
18 3 54 42 -2.18 4.75 14.26
19 2 38 44 -1.18 1.39 2.78
20 2 40 46 -.18 .03 .06
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 4
50 1 50 47 29.82 889.23 889.23
55 1 55 48 34.82 1212.43 1212.43
60 1 60 49 39.82 1585.63 1585.63
70 1 70 50 49.82 2482 2482
75 1 75 51 54.82 3005.23 3005.23
∑f = 51 ∑fx = 1029 ∑fd²=10247.37
Mean (A) = ∑fx ⁄ ∑f = 1029⁄51 = 20.18, Median (M) = 15,
Mode (Mo) =15,
Standard deviation (σ) = √(∑fd²⁄∑f) = 14.17, Variance (σ²) =
200.92 and
Co-efficient of variation = (σ ⁄ A)×100 = 70.24%
Table 4: Frequency distribution of roof bolting per bolt (minute)
Class
interval
Class
mark (x)
Frequency
(f)
fx c.f d = x-A
= x-7.32
d² fd²
4-6 5 40 200 40 -2.32 5.38 215.29
6-8 7 118 826 158 -.32 .10 12.08
8-10 9 20 180 178 1.68 2.82 56.45
10-12 11 2 22 180 3.68 13.54 27.08
12-14 13 2 26 182 5.68 32.26 64.52
14-16 15 5 75 187 7.68 58.98 294.91
16-18 17 3 51 190 9.68 93.7 281.10
18-20 19 1 19 191 11.68 136.42 136.42
∑f = 191 ∑fx = 1399 ∑fd²=1087.85
Mean (A) = ∑fx ⁄ ∑f = 1399⁄191 = 7.32, Median (M) = 6.94,
Mode (Mo) = 6.88,
Standard deviation (σ) = √(∑fd²⁄∑f) =2.38, Variance (σ²) =
5.69 and
Co-efficient of variation = (σ ⁄ A)×100 = 32.5%
Table 5: Frequency distribution of side bolting per face (minute)
Class
interval
Class
mark
(x)
Frequency
(f)
fx c.f d = x-A
= x-3.97
d² fd²
2.5-3.0 2.75 6 16.5 6 -1.22 1.490 8.93
3.0-3.5 3.25 5 16.25 11 -0.72 0.52 2.59
3.5-4.0 3.75 17 63.75 28 -0.22 0.0484 0.82
4.0-4.5 4.25 6 25.5 34 0.5 0.25 1.5
4.5-5.0 4.75 13 61.75 47 0.78 0.61 7.91
5.0-5.5 5.25 1 5.25 48 1.28 1.64 1.64
5.5-6.0 5.75 1 5.75 49 1.78 3.17 3.17
∑f = 49 ∑fx = 194.75 ∑fd²=26.56
Mean (A) = ∑fx ⁄ ∑f =194.75⁄49 = 3.97, Median (M) =
3.89,Mode (Mo) = 3.76,
Standard deviation (σ) = √(∑fd²⁄∑f) =0.736, Variance (σ²) =
0.542 and
Co-efficient of variation = (σ ⁄ A)×100 =18.53 %
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 5
Table 6: Frequency distribution of face dressing per face (minute)
Class
interval
Class
mark
(x)
Frequency
(f)
fx c.f d = x-A
= x-8.84
d² fd²
6-7 6.5 10 65 10 -2.34 5.475 54.75
7-8 7.5 14 105 24 -1.34 1.795 25.14
8-9 8.5 8 68 32 -0.34 0.115 .92
9-10 9.5 8 76 40 0.66 0.435 3.48
10-11 10.5 0 0 40 1.66 2.755 0
11-12 11.5 0 0 40 2.66 7.075 0
12-13 12.5 0 0 40 3.66 13.395 0
13-14 13.5 2 27 42 4.66 21.72 43.43
14-15 14.5 3 43.5 45 5.66 32.03 96.11
15-16 16.5 2 31.0 47 6.66 44.75 88.71
∑f = 47 ∑fx = 415.5 ∑fd²=312.54
Mean (A) = ∑fx ⁄ ∑f = 415.5 ⁄ 47 = 8.84, Median (M) = 7.96,
Mode (Mo) = 7.4,
Standard deviation (σ) = √(∑fd²⁄∑f) = 2.578, Variance (σ²) =
6.65 and
Co-efficient of variation = (σ ⁄ A)×100 = 29.16%
Table 7: Frequency distribution of production drilling per hole (second)
Class
interval
Class
mark
(x)
Frequency
(f)
fx c.f d = x-A
= x-80
d² fd²
0-20 10 1 10 1 -70 4900 4900
20-40 30 9 570 10 -50 2500 22500
40-60 50 19 950 29 -30 900 17100
60-80 70 51 3570 80 -10 100 5100
80-100 90 26 2340 106 10 100 2600
100-120 110 17 1870 123 30 900 15300
120-140 130 68 1040 131 50 2500 20000
140-160 150 2 300 133 70 4900 9800
∑f = 133 ∑fx = 10650 ∑fd²=97300
Mean (A) =∑fx ⁄ ∑f =10650⁄133 = 80, Median (M) = 74.7,
Mode (Mo) = 71.23,
Standard deviation (σ) = √(∑fd²⁄∑f) =27.04, Variance (σ²) =
731.57 and
Co-efficient of variation = (σ ⁄ A)×100 = 33.7%
Table 8: Frequency distribution of preparing sand capsule, 36 capsule with 3 men (minute)
Class
mark (x)
Frequency
(f)
fx c.f d = x-A
= x-17.44
d² fd²
12 1 12 1 -5.44 29.59 29.59
13 3 39 4 -4.44 19.71 59.14
14 4 56 8 -3.44 11.83 47.33
15 6 90 14 -2.44 5.95 35.72
16 4 64 18 -1.44 2.07 8.29
17 3 51 21 -.44 0.19 .58
18 3 54 24 1.44 2.07 6.21
30 1 30 25 12.56 157.75 157.75
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 6
35 1 35 26 17.56 308.35 308.35
40 1 40 27 22.56 508.95 508.95
∑f = 27 ∑fx = 471 ∑fd²=1161.91
Mean (A) = ∑fx ⁄ ∑f = 471⁄27 = 17.44, Median (M) = 15,
Mode (Mo) =15,
Standard deviation (σ) = √(∑fd²⁄∑f) = 6.56, Variance (σ²) =
43.03 and
Co-efficient of variation = (σ ⁄ A)×100 =37.61 %
Table 9: Frequency distribution of charging and blasting per face (minute)
Class
interval
Class
mark
(x)
Frequency
(f)
fx c.f d = x-A
= x-36
d² fd²
29-31 30 7 210 7 -6 36 252
31-33 32 4 128 11 -4 16 64
33-35 34 7 238 18 -2 4 8
35-37 36 1 36 19 0 0 0
37-39 38 6 228 25 2 4 24
39-41 40 4 160 29 4 16 64
41-43 42 3 126 32 6 36 108
43-45 44 2 88 34 8 64 128
45-47 46 1 46 35 10 100 100
∑f = 35 ∑fx =1260 ∑fd²=768
Mean (A) = ∑fx ⁄ ∑f = 1260 ⁄ 35 = 36, Median (M) = 34.85,
Mode (Mo) =
33.67, Standard deviation (σ) = √(∑fd²⁄∑f) = 4.68, Variance
(σ²) = 21.94 and
Co-efficient of variation = (σ ⁄ A)×100 = 13%
Table 10: Frequency distribution of fume clearance per face (minute)
Class
interval
Class
mark
(x)
Frequency
(f)
fx c.f d = x-A
= x-4.78
d² fd²
3.5-4.0 3.75 2 7.5 2 -1.03 1.06 2.12
4.0-4.5 4.25 12 51 14 -0.53 0.28 3.37
4.5-5.0 4.75 13 61.75 27 -0.03 .0009 0.0117
5.0-5.5 5.25 6 31.5 33 0.47 .22 1.325
5.5-6.0 5.75 4 23 37 0.97 0.94 3.76
6.0-6.5 6.25 0 0 37 1.47 2.16 0
6.5-7.0 6.75 1 6.75 38 1.97 3.88 3.88
∑f = 38 ∑fx =181.5 ∑fd²=14.46
Mean (A) = ∑fx ⁄ ∑f = 181.5 ⁄ 38 = 4.78, Median (M) =
4.69, Mode (Mo) = 4.56,
Standard deviation (σ) = √(∑fd²⁄∑f) = 0.616, Variance (σ²) =
0.381 and
Co-efficient of variation = (σ ⁄ A)×100 = 12.88%
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 7
Table 11: Frequency distribution of time study of water spraying and loose dressing per face (minute)
Class
interval
Class
mark
(x)
Frequency
(f)
fx c.f d = x-A
= x-17.98
d² fd²
14-15 14.5 2 29 2 -3.48 12.11 24.22
15-16 15.5 3 46.5 5 -2.48 6.15 18.45
16-17 16.5 2 33 7 -1.48 2.19 4.38
17-18 17.5 6 105 13 -0.48 .23 1.38
18-19 18.5 6 111 19 0.58 .27 1.68
19-20 19.5 4 78 23 1.58 2.31 9.24
20-21 20.5 3 61.5 26 2.52 6.35 19.05
21-22 21.5 1 21.5 27 3.52 12.39 12.39
∑f = 27 ∑fx =485.5 ∑fd²=295.32
Mean (A) = ∑fx ⁄ ∑f = 485.5 ⁄ 27 = 17.98, Median (M) =
18.08, Mode (Mo) =18
Standard deviation (σ) =√(∑fd²⁄∑f) = 3.31, Variance (σ²) =
10.93 and
Co-efficient of variation = (σ ⁄ A)×100 = 18.41%
Table 12: Frequency distribution of loading cycle time (second) at lead up to 5 metres
Class
interval
Class
mark
(x)
Frequency
(f)
fx c.f d = x-A
= x-51.12
d² fd²
35-40 37.5 8 300 8 -13.62 185.50 1484.03
40-45 42.5 23 977.5 31 -8.62 74.30 1709.00
45-50 47.5 19 902.5 50 -3.62 13.10 248.98
50-55 52.5 10 525 60 1.38 1.90 19.04
55-60 57.5 17 977.5 77 6.38 40.70 691.97
60-65 62.5 9 562.5 86 11.38 129.50 1165.53
65-70 67.5 5 337.5 91 16.38 268.30 1341.52
70-75 72.5 2 145 93 21.38 457.10 914.21
75-80 77.5 1 77.5 94 26.38 695.90 695.90
∑f = 94 ∑fx = 4805 ∑fd²=8270.18
Mean (A) = ∑fx ⁄ ∑f = 4805 ⁄ 94= 51.12, Median (M) =
49.21, Mode (Mo) = 43.95
Standard deviation (σ) = √(∑fd²⁄∑f) =9.38, Variance (σ²) =
87.98 and
Co-efficient of variation = (σ ⁄ A)×100 = 18.34%
Table 13: Frequency distribution of loading cycle time (second) at lead 5-10 metres
Class
interval
Class
mark
(x)
Frequency
(f)
fx c.f d = x-A
= x-75.58
d² fd²
65-70 67.5 15 1012.5 15 -8.08 65.28 979.29
70-75 72.5 17 1232.5 32 -3.08 9.48 161.27
75-80 77.5 3 232.5 35 1.92 3.68 11.06
80-85 82.5 3 247.5 38 6.92 47.88 143.66
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 8
85-90 87.5 3 262.5 41 11.92 142.08 426.24
90-95 92.5 4 370 45 16.92 286.28 1145.14
95-100 97.5 2 195 47 21.92 480.48 960.97
∑f = 47 ∑fx =3552.5 ∑fd²=3827.63
Mean (A) = ∑fx ⁄ ∑f = 3552.5⁄47 = 75.58, Median (M) =
72.5, Mode (Mo) = 70.63
Standard deviation (σ) = √(∑fd²⁄∑f) =9.02, Variance (σ²)
=81.44 and
Co-efficient of variation = (σ ⁄ A)×100 =11.94 %
Table 14: Frequency distribution of loading cycle time (second) at lead 10-15 metres
Class
interval
Class
mark
(x)
Frequency
(f)
fx c.f d = x-A
= x-83.29
d² fd²
70-75 72.5 5 362.5 5 -10.79 116.42 582.12
75-80 77.5 7 542.5 12 -5.79 33.52 134.67
80-85 82.5 17 1402.5 29 -0.79 .624 10.61
85-90 87.5 9 787.5 38 4.21 17.72 159.52
90-95 92.5 4 370 42 9.21 84.82 339.29
95-100 97.5 1 97.5 43 14.21 201.92 201.92
100-105 102.5 1 102.5 44 19.21 369.02 369.02
∑f = 44 ∑fx =3665 ∑fd²=1897.15
Mean (A) = ∑fx ⁄ ∑f = 3665 ⁄44 = 83.29, Median (M) =
82.94, Mode (Mo) = 82.77
Standard deviation (σ) = √(∑fd²⁄∑f) =6.57, Variance (σ²)
=43.11
And Co-efficient of variation = (σ ⁄ A)×100 =7.88 %
Table 15: Frequency distribution of loading cycle time (second) at lead 15-20 metres
Class
interval
Class
mark
(x)
Frequency
(f)
fx c.f d = x-A
= x-99.74
d² fd²
90-95 92.5 17 1572.5 17 -7.24 52.42 891.14
95-100 97.5 14 1365 31 -2.24 5.02 70.25
100-105 102.5 7 717.5 38 2.76 7.62 53.32
105-110 107.5 5 537.5 43 7.76 60.22 301.08
110-115 112.5 3 337.5 46 12.76 162.82 488.45
115-120 117.5 2 235 48 17.76 315.42 630.83
120-125 122.5 1 122.5 49 22.76 518.02 518.02
∑f =49 ∑fx =4887.5 ∑fd²=2453.09
Mean (A) =∑fx ⁄ ∑f = 4887.5 ⁄49 = 99.74, Median (M) =
97.67, Mode (Mo) = 94.25
Standard deviation (σ) = √(∑fd²⁄∑f) =7.07, Variance (σ²)
=50.06 and
Co-efficient of variation = (σ ⁄ A)×100 =7.09 %
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 9
Table 16: Frequency distribution of loading cycle time (second) at lead 20-25 metres
Class
interval
Class
mark
(x)
Frequency
(f)
fx c.f d = x-A
= x-122.09
d² fd²
110-115 112.5 16 1800 16 -9.59 91.96 1471.48
115-120 117.5 11 1292.5 27 -4.59 21.06 231.75
120-125 122.5 6 735 33 0.41 .168 1.00
125-130 127.5 4 510 37 5.41 29.27 117.07
130-135 132.5 5 662.5 42 10.41 108.37 541.84
135-140 137.5 4 550 46 15.41 237.47 949.87
140-145 142.5 2 285 48 20.41 416.56 833.14
145-150 147.5 1 147.5 49 25.41 645.67 645.67
∑f =49 ∑fx =5982.5 ∑fd²=4791.82
Mean (A) =∑fx ⁄ ∑f = 5982.5 ⁄49 =122.09, Median (M) =
118.86,Mode (Mo) =113.07
Standard deviation (σ) = √(∑fd²⁄∑f) =9.88, Variance (σ²)
=97.79 and
Co-efficient of variation = (σ ⁄ A)×100 =8.09 %
Table 17: Frequency distribution of loading cycle time (second) at lead 25-30metres
Class
interval
Class
mark
(x)
Frequency
(f)
fx c.f d = x-A
= x-153.09
d² fd²
120-130 125 7 875 7 -28.09 789.05 5523.33
130-140 135 9 1215 16 -18.09 327.25 2945.23
140-150 145 6 870 22 -8.09 65.45 392.68
150-160 155 7 1085 29 1.91 3.65 25.54
160-170 165 2 330 31 11.91 141.85 283.69
170-180 175 3 525 34 21.91 480.05 1440.14
180-190 185 5 925 39 31.91 1018.25 5091.24
190-200 195 1 195 40 41.91 1756.45 1756.45
200-210 205 2 410 42 51.91 2694.65 5389.29
∑f =42 ∑fx =6430 ∑fd²=22842.49
Mean (A) =∑fx ⁄ ∑f = 6430 ⁄ 42=153.09, Median (M) =
148.33, Mode (Mo) = 134,
Standard deviation (σ) = √(∑fd²⁄∑f) =23.32, Variance (σ²)
=543.86 and
Co-efficient of variation = (σ ⁄ A)×100 = 15.23%
Table 18: Average loading cycle time w.r.t. different lead
Lead ( metre) Average cycle time (second)
Upto 5 51.12
5-10 75.58
10-15 83.29
15-20 99.74
20-25 122.09
25-30 153.09
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 10
Table 19: Monthly average stowing rate (te/hr) during the study period
Date Daily Stowing
rate (te/hr.)
Date Daily Stowing
rate (te/hr.)
Monthly average
stowing rate (te/hr)
2/4/2006 105 2/5/2006 87.5
(90.95+96.05)/2
= 93.5
3/4/2006 92.85 3/5/2006 100
5/4/2006 89.65 4/5/2006 100
10/4/2006 94.16 8/5/2006 100
11/4/2006 90 9/5/2006 90.9
14/4/2006 57.14 10/5/2006 95
17/4/2006 90.47 11/5/2006 85.71
19/4/2006 100 18/5/2006 100
24/4/2006 88.88 19/5/2006 97.43
25/4/2006 92.31 20/5/2006 100
26/4/2006 100 28/5/2006 100
Monthly daily
average stowing rate
(te/hr.)
90.95 96.05
Table 20: Average intake quantity, Quantity at LVC and VEQ (%)
Measurement
Date
Intake quantity
(cu.m /min.)
Quantity at LVC
(cu.m /min.)
VEQ (%)
4/10/2005 1017 763 75
31/10/2005 1067 610 57.16
5/11/2005 1050 720 68.57
24/11/2005 1024 694 67.77
2/12/2005 1008 696 69
16/12/2005 1064 750 70.48
4/01/2006 1085 772 71.15
18/01/2006 1117 805 72.06
4/02/2006 1101 794 72.11
18/02/2006 902 742 82.26
7/3/2006 1113 834.75 75
16/3/2006 746 554 74.26
4/4/2006 763 534 69.98
2/4/2006 931 847 90.9
15/5/2006 706 669 94.75
Average 979.6 718.98 74.03
7. RESULTS & DISCUSSION
7.1 Results of Various Operations
Results of various operations of face preparation sub-system
& loading sub-system are plotted as frequency distribution
curves, and, shown in fig. 3to 17. Frequency distribution
curves have been drawn from table 3 to 17. From these
frequency distribution curves various time elements have been
estimated and used for the computation of system capacities.
Further, in order to estimate the average loading cycle time
(by SDLs at various lead distances) the SDL loading time was
studied in the field & the results are graphically plotted as
shown in fig. 18. Graph has been plotted from table 18.
Again, in order to estimate the average stowing rate the
stowing operation was studied in the field & the results are
graphically plotted in fig. 19. Graph has been plotted from
table 19.
Again, in order to estimate the intake quantity, quantity at
LVC & VEQ (%) ventilation operation was studied in the field
& the results are graphically plotted in fig. 20. Graph has been
plotted from table 20.
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 11
0
2
4
6
8
10
12
14
16
18
20
0 20 40 60 80
Roof dressing time per face(minutes)
Frequency
Fig. 3: Roof dressing time per face vs. Frequency
0
20
40
60
80
100
120
140
0 5 10 15 20
Roof bolting time per bolt (minutes)
Frequency
Fig. 4: Roof bolting time per bolt vs. Frequency
0
2
4
6
8
10
12
14
16
18
0 1 2 3 4 5 6 7
Side boltingtime per bolt (minutes)
Frequency
Fig. 5: Side bolting time per bolt vs. Frequency
-2
0
2
4
6
8
10
12
14
16
0 5 10 15 20
Face dressing time per face (minutes)
Frequency
Fig. 6: Face dressing time per face vs. Frequency
0
10
20
30
40
50
60
0 20 40 60 80 100 120 140 160
Production drilling time per hole (seconds)
Frequency
Fig. 7: Production drilling time per hole vs. Frequency
0
1
2
3
4
5
6
7
0 10 20 30 40 50
Time (minutes) for 36 capsules per 3 men
Frequency
Fig. 8: Time for 36 sand capsules per 3 men vs. Frequency
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 12
0
1
2
3
4
5
6
7
8
0 10 20 30 40 50
Charging & blasting time per face (minutes)
Frequency
Fig. 9: Charging and blasting time per face vs. Frequency
-2
0
2
4
6
8
10
12
14
0 1 2 3 4 5 6 7 8
Fume clearance time per face (minutes)
Frequency
Fig. 10: Fume clearance time per face vs. Frequency
0
1
2
3
4
5
6
7
0 5 10 15 20 25
Water spraying& loose dressing time per face (minutes)
Frequency
Fig. 11: Water spraying & loose dressing time per face vs.
Frequency
0
5
10
15
20
25
0 20 40 60 80 100
Time per cycle (seconds)
Frequency
Fig. 12: Loading cycle time (lead up to 5m) vs. Frequency
0
2
4
6
8
10
12
14
16
18
0 20 40 60 80 100 120
Time per cycle (seconds)
Frequency
Fig. 13: Loading cycle time (lead 5-10m) vs. Frequency
0
2
4
6
8
10
12
14
16
18
0 20 40 60 80 100 120
Time per cycle (seconds)
Frequency
Fig. 14: Loading cycle time (lead 10-15m) vs. Frequency
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 13
0
2
4
6
8
10
12
14
16
18
0 20 40 60 80 100 120 140
Time per cycle (seconds)
Frequency
Fig.15: Loading cycle time (lead 15-20m) vs. Frequency
0
5
10
15
20
0 50 100 150 200
Time per cycle (seconds)
Frequency
Fig. 16: Loading cycle time (lead 20-25m) vs. Frequency
0
2
4
6
8
10
0 50 100 150 200 250
Time per cycle (seconds)
Frequency
Fig. 17: Loading cycle time (lead 25-30m) vs. Frequency
51.12
75.58
83.29
99.74
122.09
153.09
0
20
40
60
80
100
120
140
160
180
0 5 10 15 20 25 30
Lead (meters)
Averageloadingcycletime(seconds)
Fig. 18: Lead vs. Average loading cycle time
0
20
40
60
80
100
120
0 2 4 6 8 10
Time (weekly)
Stowingrate(te/hr)
Fig. 19: Time vs. stowing rate
0
200
400
600
800
1000
1200
4/10/20055/11/20052/12/20054/1/20064/2/20067/3/20064/4/200615/05/06
Time( 1st fortnight & 2nd fortnight of each month from
oct.05 to may 06)
Intakequantity,quantityatLVC
&VEQ(%)
Intake quantity
Quantity at LVC
VEQ (%)
Fig. 20: Time vs. Intake quantity (cu.m/min.), Quantity at
LVC and VEQ (%)
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 14
7.2 Statistical Results of Face Preparation & Loading
Sub-System:
Statistical results of face preparation & loading sub-system are
tabulated in table 21. Results in this table have been drawn
from frequency distribution table 3 to 17 (Except table 8)
Table 21: Integrated table showing the statistical results of face preparation and loading sub-systems
Operations Mean Median Mode Standard
Deviation
Variance Co-efficient
of variation
(%)
face preparation time
1. Roof dressing per face(minutes) 20.18 15 15 14.17 200.92 70.24
2. Roof bolting per bolt (minutes) 7.32 6.94 6.88 2.38 5.69 32.51
3.Side bolting per bolt(minutes) 3.97 3.89 3.76 0.736 0.542 18.53
4.Face dressing per face(minutes) 8.84 7.96 7.4 2.57 6.65 29.16
5.Production drilling per hole (seconds) 80 74.7 71.23 27.04 731.57 33.7
6.Charging & blasting per face (minutes) 36 34.85 33.67 4.68 21.94 13
7.Fume clearance per face(minutes) 4.78 4.69 4.56 .616 .381 12.88
8.WS+LD per face(minutes) 17.98 18.08 18 3.31 10.93 18.41
Loading cycle time (seconds)
1 Lead (0-5m) 51.12 49.21 43.95 9.38 87.98 18.34
2. Lead (5-10m) 75.58 72.5 70.63 9.02 81.44 11.94
3.Lead (10-155m) 83.29 82.94 82.77 6.57 43.11 7.88
4.Lead (15-20m) 99.74 97.67 94.25 7.07 50.06 7.09
5.Lead (20-25m) 122.1 118.86 113.07 9.88 7.79 8.09
6.Lead (25-30m) 153.1 148.33 134 23.321 543.86 15.23
From the analysis of the results as given in table 21 the
following important discussion may be drawn:
Statistical analysis of roof dressing operation shows
significantly high value of co-efficient of variation (70.24%)
in comparison to other operations which shows that data is not
consistent. This, in turn, implies that the roof dressing
operation is inconsistent in nature, being dependent and the
prevailing geo-mining conditions. In this panel, particularly,
the roof conditions were bad & variable due to presence of
carbonaceous shale.
7.3 Results for Capacity Estimation:
From the fore going table 21 & related statistical computation
(mean, median, mode, standard deviation & co-efficient of
variation), it is quite justified to use the mean time element for
the purpose of capacity estimation. Median & Mode appears
to provide very optimistic data in uncertain geo-mining
conditions. That is why the mean appears justifiable.
Table 22 & 23 provides the mean time element for various
sub-systems under study.
Table 22: Mean time elements for various operations used for
capacity estimation of sub-systems (Face Preparation &
Loading)
Operations Statistical
Time
(mean)
Face preparation time:
1. Roof dressing per face(minutes) 20.18
2. Roof bolting per bolt(minutes) 7.32
3.Side bolting per bolt(minutes) 3.97
4.Face dressing per face(minutes) 8.84
5.Production drilling per hole (seconds) 80
6. Charging & blasting per face
(minutes)
36
7.Fume clearance per face(minutes) 4.78
8.Water spraying & Loose dressing per
face (minutes)
17.98
Loading cycle time (seconds):
1. Lead (15-20m) 99.74
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
__________________________________________________________________________________________
Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 15
Table 23: Mean time elements for various operations used for capacity estimation of sub-systems (ventilation, transportation &
stowing)
Ventilation sub-system Transportation sub-system Stowing sub-system
Average intake quantity
=979.6 cu.m/min.
Tipper belt= 20hrs./day Average stowing rate
93.5 te/hr(on monthly basis)
Average quantity at LVC
=718.98 cu.m/min.
Trunk belt= 20 hrs./day
Average leakages quantity
=260.62 cu.m/min.
Sectional belt = 18hrs./day
Face chain conveyor =18 hrs./day
CONCLUSIONS
1. Statistical analysis of roof dressing operation shows
significantly high value of co- efficient of variation
which means roof condition is not good.
2. Mean time elements will be considered as standard
time for Capacity estimation purpose of various Sub-
Systems
REFERENCES
[1] Bhattcherjee, A., Maiti, J. and Mukherjee, N. “An
investigation of system performance of mechanized
bord-and-pillar mine working through discrete event
simulation modeling”, Minetech Journal., Vol. 17,
No.6, Nov.-Dec.,1996, pp.33-37.
[2] Chaoji, S.V. “Environmental challenges and future of
Indian coal”, Journal of Mines, Metals and Fuels, Vol.
50, No.7, July, 2002, pp.257-261
[3] Karmakar, H.N. “New generation mine modeling for
higher production and productivity of underground coal
mines”, Minetech Journal, Vol. 17, No.6, Nov.-
Dec.,1996, pp. 39-42.
[4] Mathur, S.P. “Labour productivity and cost reduction in
Indian coal mines”. Minetech Journal, Vol.11, No. 3,
May-June, 1999, pp. 5-9
[5] Mukhopadhyay, S.B. and Babu, A.V. “System analysis
approach in mining operations-an overview”, Minetech
Journal,Vol.14, No.5-6, Sep-Dec.,1993. pp.30-36.
[6] Rai,P. & Singh, Arvind Kumar. “System analysis
approach for production planning in underground coal
mine”, Minetech, Vol.26, No.2, Mar- Apr.,2005, pp.23-
28
[7] Rai, P. “Some aspects of material transportation by rear
dump trucks in opencast mines”, Minetech Journal,
Vol.22, No.3, May-Jun., 2001, pp.3-10.
[8] Ray, S.C. And Sinha, D.K. “Capacity analysis of mine
system-a pre-requisite for production planning in
underground mines”, Indian Mining & Engineering
Journal, Vol.17., No.5, May,1978, pp.7-12.
[9] Sachdev, B.K. “Coal industry in India development
issues” Procs. 4th Asian mining international
conference on geology, mining and mineral processing.
Nov. 24-28, Calcutta, 1993.

More Related Content

What's hot

Technical article reprint turbo-abrasive maching
Technical article reprint turbo-abrasive machingTechnical article reprint turbo-abrasive maching
Technical article reprint turbo-abrasive machingDave Davidson
 
IRJET- Parametric Study on Behaviour of RCC Box Culvert for Dynamic Loading
IRJET- Parametric Study on Behaviour of RCC Box Culvert for Dynamic LoadingIRJET- Parametric Study on Behaviour of RCC Box Culvert for Dynamic Loading
IRJET- Parametric Study on Behaviour of RCC Box Culvert for Dynamic LoadingIRJET Journal
 
Geometric regeneration and mechanical analysis of a gas turbine blade type Fr...
Geometric regeneration and mechanical analysis of a gas turbine blade type Fr...Geometric regeneration and mechanical analysis of a gas turbine blade type Fr...
Geometric regeneration and mechanical analysis of a gas turbine blade type Fr...Barhm Mohamad
 
Passive control of structures using sliding isolators at intermediate floor l...
Passive control of structures using sliding isolators at intermediate floor l...Passive control of structures using sliding isolators at intermediate floor l...
Passive control of structures using sliding isolators at intermediate floor l...eSAT Publishing House
 
Cost optimization of using geogrids vs piles in the foundation of interchange...
Cost optimization of using geogrids vs piles in the foundation of interchange...Cost optimization of using geogrids vs piles in the foundation of interchange...
Cost optimization of using geogrids vs piles in the foundation of interchange...IAEME Publication
 
Fixity depth of offshore piles in elastoplastic soft clay under dynamic load
Fixity depth of offshore piles in elastoplastic soft clay under dynamic loadFixity depth of offshore piles in elastoplastic soft clay under dynamic load
Fixity depth of offshore piles in elastoplastic soft clay under dynamic loadeSAT Journals
 
Cdd mahesh dasar ijertv2 is120775
Cdd mahesh dasar ijertv2 is120775Cdd mahesh dasar ijertv2 is120775
Cdd mahesh dasar ijertv2 is120775Mahesh Dasar
 
Study on rutting and surface behaviour of urban flexible pavement
Study on rutting and surface behaviour of urban flexible pavementStudy on rutting and surface behaviour of urban flexible pavement
Study on rutting and surface behaviour of urban flexible pavementeSAT Publishing House
 
IRJET- Assessment of Slope Stability in Opencast Coal Mines using Software
IRJET-  	  Assessment of Slope Stability in Opencast Coal Mines using SoftwareIRJET-  	  Assessment of Slope Stability in Opencast Coal Mines using Software
IRJET- Assessment of Slope Stability in Opencast Coal Mines using SoftwareIRJET Journal
 
Effect of l b ratio of stone column on bearing capacity and relative settleme...
Effect of l b ratio of stone column on bearing capacity and relative settleme...Effect of l b ratio of stone column on bearing capacity and relative settleme...
Effect of l b ratio of stone column on bearing capacity and relative settleme...IAEME Publication
 
Ge6251 bcme notes with question bank
Ge6251   bcme notes with question bankGe6251   bcme notes with question bank
Ge6251 bcme notes with question bankgokulfea
 
Research 2
Research 2Research 2
Research 2Ali Iraq
 
Finite element analysis of underground metro tunnels
Finite element analysis of underground metro tunnelsFinite element analysis of underground metro tunnels
Finite element analysis of underground metro tunnelsIAEME Publication
 
3617 the-effect-of-rotor-balance-during-crushing-of-intermetallic-compounds-i...
3617 the-effect-of-rotor-balance-during-crushing-of-intermetallic-compounds-i...3617 the-effect-of-rotor-balance-during-crushing-of-intermetallic-compounds-i...
3617 the-effect-of-rotor-balance-during-crushing-of-intermetallic-compounds-i...mkpq pasha
 
Optimization of productivity with surface miner using
Optimization of productivity with surface miner usingOptimization of productivity with surface miner using
Optimization of productivity with surface miner usingeSAT Publishing House
 
Rock Mass Characteristics Modification Using Back Analysis Method for Isfahan...
Rock Mass Characteristics Modification Using Back Analysis Method for Isfahan...Rock Mass Characteristics Modification Using Back Analysis Method for Isfahan...
Rock Mass Characteristics Modification Using Back Analysis Method for Isfahan...IJERA Editor
 
Assessment of Soil Structure Interaction on RCC Underpass Bridge
Assessment of Soil Structure Interaction on RCC Underpass BridgeAssessment of Soil Structure Interaction on RCC Underpass Bridge
Assessment of Soil Structure Interaction on RCC Underpass BridgeIRJET Journal
 

What's hot (19)

Technical article reprint turbo-abrasive maching
Technical article reprint turbo-abrasive machingTechnical article reprint turbo-abrasive maching
Technical article reprint turbo-abrasive maching
 
IRJET- Parametric Study on Behaviour of RCC Box Culvert for Dynamic Loading
IRJET- Parametric Study on Behaviour of RCC Box Culvert for Dynamic LoadingIRJET- Parametric Study on Behaviour of RCC Box Culvert for Dynamic Loading
IRJET- Parametric Study on Behaviour of RCC Box Culvert for Dynamic Loading
 
Geometric regeneration and mechanical analysis of a gas turbine blade type Fr...
Geometric regeneration and mechanical analysis of a gas turbine blade type Fr...Geometric regeneration and mechanical analysis of a gas turbine blade type Fr...
Geometric regeneration and mechanical analysis of a gas turbine blade type Fr...
 
Ijciet 10 01_196-2
Ijciet 10 01_196-2Ijciet 10 01_196-2
Ijciet 10 01_196-2
 
Passive control of structures using sliding isolators at intermediate floor l...
Passive control of structures using sliding isolators at intermediate floor l...Passive control of structures using sliding isolators at intermediate floor l...
Passive control of structures using sliding isolators at intermediate floor l...
 
Cost optimization of using geogrids vs piles in the foundation of interchange...
Cost optimization of using geogrids vs piles in the foundation of interchange...Cost optimization of using geogrids vs piles in the foundation of interchange...
Cost optimization of using geogrids vs piles in the foundation of interchange...
 
Fixity depth of offshore piles in elastoplastic soft clay under dynamic load
Fixity depth of offshore piles in elastoplastic soft clay under dynamic loadFixity depth of offshore piles in elastoplastic soft clay under dynamic load
Fixity depth of offshore piles in elastoplastic soft clay under dynamic load
 
Cdd mahesh dasar ijertv2 is120775
Cdd mahesh dasar ijertv2 is120775Cdd mahesh dasar ijertv2 is120775
Cdd mahesh dasar ijertv2 is120775
 
Study on rutting and surface behaviour of urban flexible pavement
Study on rutting and surface behaviour of urban flexible pavementStudy on rutting and surface behaviour of urban flexible pavement
Study on rutting and surface behaviour of urban flexible pavement
 
IRJET- Assessment of Slope Stability in Opencast Coal Mines using Software
IRJET-  	  Assessment of Slope Stability in Opencast Coal Mines using SoftwareIRJET-  	  Assessment of Slope Stability in Opencast Coal Mines using Software
IRJET- Assessment of Slope Stability in Opencast Coal Mines using Software
 
Effect of l b ratio of stone column on bearing capacity and relative settleme...
Effect of l b ratio of stone column on bearing capacity and relative settleme...Effect of l b ratio of stone column on bearing capacity and relative settleme...
Effect of l b ratio of stone column on bearing capacity and relative settleme...
 
Ge6251 bcme notes with question bank
Ge6251   bcme notes with question bankGe6251   bcme notes with question bank
Ge6251 bcme notes with question bank
 
Research 2
Research 2Research 2
Research 2
 
Finite element analysis of underground metro tunnels
Finite element analysis of underground metro tunnelsFinite element analysis of underground metro tunnels
Finite element analysis of underground metro tunnels
 
3617 the-effect-of-rotor-balance-during-crushing-of-intermetallic-compounds-i...
3617 the-effect-of-rotor-balance-during-crushing-of-intermetallic-compounds-i...3617 the-effect-of-rotor-balance-during-crushing-of-intermetallic-compounds-i...
3617 the-effect-of-rotor-balance-during-crushing-of-intermetallic-compounds-i...
 
Optimization of productivity with surface miner using
Optimization of productivity with surface miner usingOptimization of productivity with surface miner using
Optimization of productivity with surface miner using
 
Rock Mass Characteristics Modification Using Back Analysis Method for Isfahan...
Rock Mass Characteristics Modification Using Back Analysis Method for Isfahan...Rock Mass Characteristics Modification Using Back Analysis Method for Isfahan...
Rock Mass Characteristics Modification Using Back Analysis Method for Isfahan...
 
Assessment of Soil Structure Interaction on RCC Underpass Bridge
Assessment of Soil Structure Interaction on RCC Underpass BridgeAssessment of Soil Structure Interaction on RCC Underpass Bridge
Assessment of Soil Structure Interaction on RCC Underpass Bridge
 
Bd4101318323
Bd4101318323Bd4101318323
Bd4101318323
 

Viewers also liked

Survey on software remodularization techniques
Survey on software remodularization techniquesSurvey on software remodularization techniques
Survey on software remodularization techniqueseSAT Publishing House
 
Comparative assessment of noise levels in various laboratories and constructi...
Comparative assessment of noise levels in various laboratories and constructi...Comparative assessment of noise levels in various laboratories and constructi...
Comparative assessment of noise levels in various laboratories and constructi...eSAT Publishing House
 
Igbt based on vector control of induction motor drive
Igbt based on vector control of induction motor driveIgbt based on vector control of induction motor drive
Igbt based on vector control of induction motor driveeSAT Publishing House
 
Interventions for scientific and enterprise applications
Interventions for scientific and enterprise applicationsInterventions for scientific and enterprise applications
Interventions for scientific and enterprise applicationseSAT Publishing House
 
Performance improvement of bottleneck link in red vegas over heterogeneous ne...
Performance improvement of bottleneck link in red vegas over heterogeneous ne...Performance improvement of bottleneck link in red vegas over heterogeneous ne...
Performance improvement of bottleneck link in red vegas over heterogeneous ne...eSAT Publishing House
 
Properties of fa l g hollow masonry blocks
Properties of fa l g hollow masonry blocksProperties of fa l g hollow masonry blocks
Properties of fa l g hollow masonry blockseSAT Publishing House
 
Power spectrum sequence analysis of rheumatic
Power spectrum sequence analysis of rheumaticPower spectrum sequence analysis of rheumatic
Power spectrum sequence analysis of rheumaticeSAT Publishing House
 
Quality of service parameter centric resource allocation for lte advanced
Quality of service parameter centric resource allocation for lte advancedQuality of service parameter centric resource allocation for lte advanced
Quality of service parameter centric resource allocation for lte advancedeSAT Publishing House
 
Assessment of groundwater quality for irrigation use
Assessment of groundwater quality for irrigation useAssessment of groundwater quality for irrigation use
Assessment of groundwater quality for irrigation useeSAT Publishing House
 
Uw as ns design challenges in transport layer
Uw as ns design challenges in transport layerUw as ns design challenges in transport layer
Uw as ns design challenges in transport layereSAT Publishing House
 
Lsb hiding using random approach for image watermarking
Lsb hiding using random approach for image watermarkingLsb hiding using random approach for image watermarking
Lsb hiding using random approach for image watermarkingeSAT Publishing House
 
Directly coupled microstrip array antennas for wideband application
Directly coupled microstrip array antennas for wideband applicationDirectly coupled microstrip array antennas for wideband application
Directly coupled microstrip array antennas for wideband applicationeSAT Publishing House
 
Molecular interaction analysis of polar liquids
Molecular interaction analysis of polar liquidsMolecular interaction analysis of polar liquids
Molecular interaction analysis of polar liquidseSAT Publishing House
 
Influence of carbon sources on α amylase production by brevibacillus sp. unde...
Influence of carbon sources on α amylase production by brevibacillus sp. unde...Influence of carbon sources on α amylase production by brevibacillus sp. unde...
Influence of carbon sources on α amylase production by brevibacillus sp. unde...eSAT Publishing House
 
Lake sediment thickness estimation using ground penetrating radar
Lake sediment thickness estimation using ground penetrating radarLake sediment thickness estimation using ground penetrating radar
Lake sediment thickness estimation using ground penetrating radareSAT Publishing House
 
Applications of dampers for vibration control of
Applications of dampers for vibration control ofApplications of dampers for vibration control of
Applications of dampers for vibration control ofeSAT Publishing House
 
Limnological studies related to physico chemical
Limnological studies related to physico chemicalLimnological studies related to physico chemical
Limnological studies related to physico chemicaleSAT Publishing House
 
Stabilizationsolidification of iron ore mine tailings
Stabilizationsolidification of iron ore mine tailingsStabilizationsolidification of iron ore mine tailings
Stabilizationsolidification of iron ore mine tailingseSAT Publishing House
 

Viewers also liked (20)

Survey on software remodularization techniques
Survey on software remodularization techniquesSurvey on software remodularization techniques
Survey on software remodularization techniques
 
Comparative assessment of noise levels in various laboratories and constructi...
Comparative assessment of noise levels in various laboratories and constructi...Comparative assessment of noise levels in various laboratories and constructi...
Comparative assessment of noise levels in various laboratories and constructi...
 
Igbt based on vector control of induction motor drive
Igbt based on vector control of induction motor driveIgbt based on vector control of induction motor drive
Igbt based on vector control of induction motor drive
 
Interventions for scientific and enterprise applications
Interventions for scientific and enterprise applicationsInterventions for scientific and enterprise applications
Interventions for scientific and enterprise applications
 
Performance improvement of bottleneck link in red vegas over heterogeneous ne...
Performance improvement of bottleneck link in red vegas over heterogeneous ne...Performance improvement of bottleneck link in red vegas over heterogeneous ne...
Performance improvement of bottleneck link in red vegas over heterogeneous ne...
 
Properties of fa l g hollow masonry blocks
Properties of fa l g hollow masonry blocksProperties of fa l g hollow masonry blocks
Properties of fa l g hollow masonry blocks
 
Power spectrum sequence analysis of rheumatic
Power spectrum sequence analysis of rheumaticPower spectrum sequence analysis of rheumatic
Power spectrum sequence analysis of rheumatic
 
Accelerated seam carving using cuda
Accelerated seam carving using cudaAccelerated seam carving using cuda
Accelerated seam carving using cuda
 
Nokia morph technology
Nokia morph technologyNokia morph technology
Nokia morph technology
 
Quality of service parameter centric resource allocation for lte advanced
Quality of service parameter centric resource allocation for lte advancedQuality of service parameter centric resource allocation for lte advanced
Quality of service parameter centric resource allocation for lte advanced
 
Assessment of groundwater quality for irrigation use
Assessment of groundwater quality for irrigation useAssessment of groundwater quality for irrigation use
Assessment of groundwater quality for irrigation use
 
Uw as ns design challenges in transport layer
Uw as ns design challenges in transport layerUw as ns design challenges in transport layer
Uw as ns design challenges in transport layer
 
Lsb hiding using random approach for image watermarking
Lsb hiding using random approach for image watermarkingLsb hiding using random approach for image watermarking
Lsb hiding using random approach for image watermarking
 
Directly coupled microstrip array antennas for wideband application
Directly coupled microstrip array antennas for wideband applicationDirectly coupled microstrip array antennas for wideband application
Directly coupled microstrip array antennas for wideband application
 
Molecular interaction analysis of polar liquids
Molecular interaction analysis of polar liquidsMolecular interaction analysis of polar liquids
Molecular interaction analysis of polar liquids
 
Influence of carbon sources on α amylase production by brevibacillus sp. unde...
Influence of carbon sources on α amylase production by brevibacillus sp. unde...Influence of carbon sources on α amylase production by brevibacillus sp. unde...
Influence of carbon sources on α amylase production by brevibacillus sp. unde...
 
Lake sediment thickness estimation using ground penetrating radar
Lake sediment thickness estimation using ground penetrating radarLake sediment thickness estimation using ground penetrating radar
Lake sediment thickness estimation using ground penetrating radar
 
Applications of dampers for vibration control of
Applications of dampers for vibration control ofApplications of dampers for vibration control of
Applications of dampers for vibration control of
 
Limnological studies related to physico chemical
Limnological studies related to physico chemicalLimnological studies related to physico chemical
Limnological studies related to physico chemical
 
Stabilizationsolidification of iron ore mine tailings
Stabilizationsolidification of iron ore mine tailingsStabilizationsolidification of iron ore mine tailings
Stabilizationsolidification of iron ore mine tailings
 

Similar to Statistical analysis of various sub systems of panel

AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPEAN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPEIRJET Journal
 
A Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
A Theoretical Study on Strata Behaviour and Ground Control in Coal MinesA Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
A Theoretical Study on Strata Behaviour and Ground Control in Coal MinesIRJET Journal
 
Kiln tire tightening
Kiln tire tightening Kiln tire tightening
Kiln tire tightening mkpq pasha
 
Seismic comparative study on tmd structure an overview
Seismic comparative study on tmd structure  an overviewSeismic comparative study on tmd structure  an overview
Seismic comparative study on tmd structure an overvieweSAT Journals
 
IRJET- CFD based Performance Analysis of a Roughened Solar Air Heater Duc...
IRJET-  	  CFD based Performance Analysis of a Roughened Solar Air Heater Duc...IRJET-  	  CFD based Performance Analysis of a Roughened Solar Air Heater Duc...
IRJET- CFD based Performance Analysis of a Roughened Solar Air Heater Duc...IRJET Journal
 
Optimization of productivity with surface miner using conveyor loading and tr...
Optimization of productivity with surface miner using conveyor loading and tr...Optimization of productivity with surface miner using conveyor loading and tr...
Optimization of productivity with surface miner using conveyor loading and tr...eSAT Journals
 
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITYAN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITYIRJET Journal
 
Rehabilitation Study of NH34 Kabrai to Maudaha through the 35.00 Km Section L...
Rehabilitation Study of NH34 Kabrai to Maudaha through the 35.00 Km Section L...Rehabilitation Study of NH34 Kabrai to Maudaha through the 35.00 Km Section L...
Rehabilitation Study of NH34 Kabrai to Maudaha through the 35.00 Km Section L...IRJET Journal
 
Comparative study of tribological characteristics of
Comparative study of tribological characteristics ofComparative study of tribological characteristics of
Comparative study of tribological characteristics ofeSAT Publishing House
 
Comparative study of tribological characteristics of aa2024+10% fly ash compo...
Comparative study of tribological characteristics of aa2024+10% fly ash compo...Comparative study of tribological characteristics of aa2024+10% fly ash compo...
Comparative study of tribological characteristics of aa2024+10% fly ash compo...eSAT Journals
 
Stress distribution in grinding by finite element analysis
Stress distribution in grinding by finite element analysisStress distribution in grinding by finite element analysis
Stress distribution in grinding by finite element analysisBijoy Das
 
STRESS DISTRIBUTION IN GRINDING BY FINITE ELEMENT ANALYSIS
STRESS DISTRIBUTION IN GRINDING BY FINITE ELEMENT ANALYSISSTRESS DISTRIBUTION IN GRINDING BY FINITE ELEMENT ANALYSIS
STRESS DISTRIBUTION IN GRINDING BY FINITE ELEMENT ANALYSISBijoy Das
 
Seismic analysis of water tank considering effect on time period
Seismic analysis of water tank considering effect on time periodSeismic analysis of water tank considering effect on time period
Seismic analysis of water tank considering effect on time periodeSAT Journals
 
Support system (Underground Coal Mining) by Prof. S Jayantu.pdf
Support system (Underground Coal Mining) by Prof. S Jayantu.pdfSupport system (Underground Coal Mining) by Prof. S Jayantu.pdf
Support system (Underground Coal Mining) by Prof. S Jayantu.pdfpraanyakishore
 
Design of tractor mounted hydraulically operated soil compaction measurement ...
Design of tractor mounted hydraulically operated soil compaction measurement ...Design of tractor mounted hydraulically operated soil compaction measurement ...
Design of tractor mounted hydraulically operated soil compaction measurement ...Ramesh Sahni
 
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
Experimental and numerical study of defects in pressuresed cylindrical shells...
Experimental and numerical study of defects in pressuresed cylindrical shells...Experimental and numerical study of defects in pressuresed cylindrical shells...
Experimental and numerical study of defects in pressuresed cylindrical shells...eSAT Journals
 
IRJET- Study on Comparison Analysis of Circular and Intze Water Tank on Slopi...
IRJET- Study on Comparison Analysis of Circular and Intze Water Tank on Slopi...IRJET- Study on Comparison Analysis of Circular and Intze Water Tank on Slopi...
IRJET- Study on Comparison Analysis of Circular and Intze Water Tank on Slopi...IRJET Journal
 

Similar to Statistical analysis of various sub systems of panel (20)

AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPEAN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
 
A Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
A Theoretical Study on Strata Behaviour and Ground Control in Coal MinesA Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
A Theoretical Study on Strata Behaviour and Ground Control in Coal Mines
 
Kiln tire tightening
Kiln tire tightening Kiln tire tightening
Kiln tire tightening
 
Seismic comparative study on tmd structure an overview
Seismic comparative study on tmd structure  an overviewSeismic comparative study on tmd structure  an overview
Seismic comparative study on tmd structure an overview
 
IRJET- CFD based Performance Analysis of a Roughened Solar Air Heater Duc...
IRJET-  	  CFD based Performance Analysis of a Roughened Solar Air Heater Duc...IRJET-  	  CFD based Performance Analysis of a Roughened Solar Air Heater Duc...
IRJET- CFD based Performance Analysis of a Roughened Solar Air Heater Duc...
 
SPE-212574-MS.pdf
SPE-212574-MS.pdfSPE-212574-MS.pdf
SPE-212574-MS.pdf
 
Optimization of productivity with surface miner using conveyor loading and tr...
Optimization of productivity with surface miner using conveyor loading and tr...Optimization of productivity with surface miner using conveyor loading and tr...
Optimization of productivity with surface miner using conveyor loading and tr...
 
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITYAN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
AN INVESTIGATION ON MINE OVERBURDEN DUMP SLOPE STABILITY
 
Rehabilitation Study of NH34 Kabrai to Maudaha through the 35.00 Km Section L...
Rehabilitation Study of NH34 Kabrai to Maudaha through the 35.00 Km Section L...Rehabilitation Study of NH34 Kabrai to Maudaha through the 35.00 Km Section L...
Rehabilitation Study of NH34 Kabrai to Maudaha through the 35.00 Km Section L...
 
On3425302537
On3425302537On3425302537
On3425302537
 
Comparative study of tribological characteristics of
Comparative study of tribological characteristics ofComparative study of tribological characteristics of
Comparative study of tribological characteristics of
 
Comparative study of tribological characteristics of aa2024+10% fly ash compo...
Comparative study of tribological characteristics of aa2024+10% fly ash compo...Comparative study of tribological characteristics of aa2024+10% fly ash compo...
Comparative study of tribological characteristics of aa2024+10% fly ash compo...
 
Stress distribution in grinding by finite element analysis
Stress distribution in grinding by finite element analysisStress distribution in grinding by finite element analysis
Stress distribution in grinding by finite element analysis
 
STRESS DISTRIBUTION IN GRINDING BY FINITE ELEMENT ANALYSIS
STRESS DISTRIBUTION IN GRINDING BY FINITE ELEMENT ANALYSISSTRESS DISTRIBUTION IN GRINDING BY FINITE ELEMENT ANALYSIS
STRESS DISTRIBUTION IN GRINDING BY FINITE ELEMENT ANALYSIS
 
Seismic analysis of water tank considering effect on time period
Seismic analysis of water tank considering effect on time periodSeismic analysis of water tank considering effect on time period
Seismic analysis of water tank considering effect on time period
 
Support system (Underground Coal Mining) by Prof. S Jayantu.pdf
Support system (Underground Coal Mining) by Prof. S Jayantu.pdfSupport system (Underground Coal Mining) by Prof. S Jayantu.pdf
Support system (Underground Coal Mining) by Prof. S Jayantu.pdf
 
Design of tractor mounted hydraulically operated soil compaction measurement ...
Design of tractor mounted hydraulically operated soil compaction measurement ...Design of tractor mounted hydraulically operated soil compaction measurement ...
Design of tractor mounted hydraulically operated soil compaction measurement ...
 
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
Experimental and numerical study of defects in pressuresed cylindrical shells...
Experimental and numerical study of defects in pressuresed cylindrical shells...Experimental and numerical study of defects in pressuresed cylindrical shells...
Experimental and numerical study of defects in pressuresed cylindrical shells...
 
IRJET- Study on Comparison Analysis of Circular and Intze Water Tank on Slopi...
IRJET- Study on Comparison Analysis of Circular and Intze Water Tank on Slopi...IRJET- Study on Comparison Analysis of Circular and Intze Water Tank on Slopi...
IRJET- Study on Comparison Analysis of Circular and Intze Water Tank on Slopi...
 

More from eSAT Publishing House

Likely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnamLikely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnameSAT Publishing House
 
Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...eSAT Publishing House
 
Hudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnamHudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnameSAT Publishing House
 
Groundwater investigation using geophysical methods a case study of pydibhim...
Groundwater investigation using geophysical methods  a case study of pydibhim...Groundwater investigation using geophysical methods  a case study of pydibhim...
Groundwater investigation using geophysical methods a case study of pydibhim...eSAT Publishing House
 
Flood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, indiaFlood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, indiaeSAT Publishing House
 
Enhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity buildingEnhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity buildingeSAT Publishing House
 
Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...eSAT Publishing House
 
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...eSAT Publishing House
 
Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...eSAT Publishing House
 
Shear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a reviewShear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a revieweSAT Publishing House
 
Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...eSAT Publishing House
 
Risk analysis and environmental hazard management
Risk analysis and environmental hazard managementRisk analysis and environmental hazard management
Risk analysis and environmental hazard managementeSAT Publishing House
 
Review study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear wallsReview study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear wallseSAT Publishing House
 
Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...eSAT Publishing House
 
Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...eSAT Publishing House
 
Coastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of indiaCoastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of indiaeSAT Publishing House
 
Can fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structuresCan fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structureseSAT Publishing House
 
Assessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildingsAssessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildingseSAT Publishing House
 
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...eSAT Publishing House
 
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...eSAT Publishing House
 

More from eSAT Publishing House (20)

Likely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnamLikely impacts of hudhud on the environment of visakhapatnam
Likely impacts of hudhud on the environment of visakhapatnam
 
Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...Impact of flood disaster in a drought prone area – case study of alampur vill...
Impact of flood disaster in a drought prone area – case study of alampur vill...
 
Hudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnamHudhud cyclone – a severe disaster in visakhapatnam
Hudhud cyclone – a severe disaster in visakhapatnam
 
Groundwater investigation using geophysical methods a case study of pydibhim...
Groundwater investigation using geophysical methods  a case study of pydibhim...Groundwater investigation using geophysical methods  a case study of pydibhim...
Groundwater investigation using geophysical methods a case study of pydibhim...
 
Flood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, indiaFlood related disasters concerned to urban flooding in bangalore, india
Flood related disasters concerned to urban flooding in bangalore, india
 
Enhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity buildingEnhancing post disaster recovery by optimal infrastructure capacity building
Enhancing post disaster recovery by optimal infrastructure capacity building
 
Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...Effect of lintel and lintel band on the global performance of reinforced conc...
Effect of lintel and lintel band on the global performance of reinforced conc...
 
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
Wind damage to trees in the gitam university campus at visakhapatnam by cyclo...
 
Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...Wind damage to buildings, infrastrucuture and landscape elements along the be...
Wind damage to buildings, infrastrucuture and landscape elements along the be...
 
Shear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a reviewShear strength of rc deep beam panels – a review
Shear strength of rc deep beam panels – a review
 
Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...Role of voluntary teams of professional engineers in dissater management – ex...
Role of voluntary teams of professional engineers in dissater management – ex...
 
Risk analysis and environmental hazard management
Risk analysis and environmental hazard managementRisk analysis and environmental hazard management
Risk analysis and environmental hazard management
 
Review study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear wallsReview study on performance of seismically tested repaired shear walls
Review study on performance of seismically tested repaired shear walls
 
Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...Monitoring and assessment of air quality with reference to dust particles (pm...
Monitoring and assessment of air quality with reference to dust particles (pm...
 
Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...Low cost wireless sensor networks and smartphone applications for disaster ma...
Low cost wireless sensor networks and smartphone applications for disaster ma...
 
Coastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of indiaCoastal zones – seismic vulnerability an analysis from east coast of india
Coastal zones – seismic vulnerability an analysis from east coast of india
 
Can fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structuresCan fracture mechanics predict damage due disaster of structures
Can fracture mechanics predict damage due disaster of structures
 
Assessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildingsAssessment of seismic susceptibility of rc buildings
Assessment of seismic susceptibility of rc buildings
 
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
A geophysical insight of earthquake occurred on 21 st may 2014 off paradip, b...
 
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
Effect of hudhud cyclone on the development of visakhapatnam as smart and gre...
 

Recently uploaded

chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 

Recently uploaded (20)

chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 

Statistical analysis of various sub systems of panel

  • 1. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 1 STATISTICAL ANALYSIS OF VARIOUS SUB-SYSTEMS OF PANEL PRODUCTION SYSTEM IN UNDERGROUND COAL MINE Md. Soyeb Alam1 1 Assistant Professor, Department of Mining Engineering, Indian School of Mines, Dhanbad-826004, Jharkhand, India, multisoyeb2004@gmail.com Abstract System Analysis Approach has been applied in the present field based research paper for a deep and gassy coal mine of Jharia coal fields. The working panel was considered as a System, splitted into various sub-Systems. The Sub-Systems were statistically analyzed in terms of frequency distribution (after prolonged field observations). The Mean, Median, Mode, Standard deviation, Variance and co-efficient of variation were calculated. Among the Mean, Median and Mode, Mean was considered for Capacity (in terms of production) calculation of various Sub-systems -----------------------------------------------------------------------***---------------------------------------------------------------------- 1. INTRODUCTION The Supremacy of Coal as a Prime and secured source of energy is unlikely to be challenged in foreseeable future particularly in Indian context. The demands estimates of 620 million ton and 780 million ton during the terminal phases of XI and XII plan respectively also substantiate the larger dependence on coal (Chaoji, 2002 ; Rai et al, 2005). To cater the projected demand targets, the Indian coal industry needs be geared up for accelerated growth in terms of production as well as productivity. The open cast mining, with state of art mechanization is likely to become uneconomical beyond a certain depth, as the open cast technology and equipment have already reached a stage of plateau beyond which further growth is mostly unforeseen (Rai, 2001). Karmakar (1996) has also expressed that production of coal will depend more on underground mine as against present predominance of surface mines. Looking from these standpoints, the Industry may be compelled to increase its share of coal production from underground mines in forth coming years, particularly for deep seated reserves which are vastly untapped at this point of time. At present, the underground coal mines of our country are generally stricken with problem of low production and productivity (sachdev, 1993 & Mathur, 1999). This is largely because of the fact that production planning for the underground coal mines is a cumbersome process which calls for sound understanding of various underlying operations to critically assess the sensitive interrelationships amongst them (Mukhopadhaya et al, 1993). Hence, immediate attention and investigation into the performance and appropriate planning process for the underground mines is imperative as also pointed by Bhattacherjee et al, 1996. The system anlysis based approach appears to offer rationalized solution to solving the complex and intricate production planning from underground mines. In this approach the entire mine (or even a part of the mine) may be considered as system, the capacity of which is dependent on its related sub-systems (Ray et al, 1978). A proper understanding of any system and its related sub-systems could provide intriguing facts in order to practice of this approach in a large underground coal mine which falls in prime coking coal zone of Jharia Coal fields, Dhanbad, India. 2. AIMS OF THE STUDY: As already stated, the present research paper aims at deploying the System Analysis approach for large underground Coal Mine of Jharia Coal Fields. The specific aims of the present work are enumerated as 1. To study the Panel as a system and to identify the important sub-systems for the panel 2. To Critically analysed the various sub-systems Statistically. 3. RELEVANT DETAILS OF THE MINE & MINE WORKINGS: The present Research work was undertaken in a large, privately owned underground ‘Mine-A’, Jharia Coal Field. One seam, namely XI was being worked in the mine. The bore hole section of the Mine-A has been shown in fig.1.The salient geo-mining details of the Coal seam is as per table 1 & details of panels working as per table 2.
  • 2. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 2 Table 1: Salient geo-mining details of the Coal seam ITEM XI SEAM Av. thickness 7.31 m Av. depth 400 m Av. dip 1in 7 Dip direction S760 50' W Shape of seam Basin like Degree of gassiness Degree II R.M.R. Value 34.46 (not good) Geological features Highly faulted with Intrusion Mode of entry 3 shaft Type of ventilation CVS Coal transportation Through incline by Belt Conveyor upto Surface 50.91 m 1.67 m 16 A SEAM(C OAL) 16 SEAM (C OAL) 14 A SEAM (JHAMA) 13 SEAM (JHAMA) 12 SEAM (COAL & JHAMA) 11 SEAM (C OAL) 10 SEAM (COAL & JHAMA) 9 SEAM (COAL) 84.14 m 157.92 m 199.39 m 209.14 m 236.58 m 255.94 m 283.10 m 320.14 m 337.42 m 386.64 m 3.20 m 1.83 m 8.23 m 3.20 m 8.23 m 7.01 m 3.5 m 7.31 m 4.09 m 7.27 m 15 A SEAM (C OAL) 15 SEAM (C OAL) 14 SEAM (C OAL) Fig 1: Bore hole section at 9 pit ‘Mine-A’ Table 2: Details of panel working in the Mine-A Panel Name Minimum Avg.depth (m) Avg. pillar size(m) Gallery Size (m) (w×h) Coal preparation method Loading Transport Panel- 11/10-S 370 45 × 45 4.2 × 3.0, 4.8 × 3.0 (slice) Bord &Pillar (dep., bottom sec.) SDL Conveyor Panel- 11/7-S 400 45 × 45 4.2 × 2.8, 4.8× 2.8 (slice) Bord & Pillar (dev. & dep., top sec.) SDL Conveyor Panel- 11/3-S 400 45 × 45 4.2× 2.7, 4.8× 2.7 (slice) Bord & Pillar (dep., top sec.) manual Conveyor Panel- 11/9-S 325 45 × 45 4.2× 2.7, 4.8× 2.7 (slice) Bord & Pillar (dev. & dep., bottom & top sec. both) SDL Conveyor 4. BRIEF DESCRIPTION OF COAL WINNING IN THE STUDY PANEL There were three semi-mechanised panels namely, panel ‘11/7-S’, ‘11/10-S’ & ‘11/9-S’ and one manual panel namely panel ‘11/3-S’ in the given mine. The study was conducted in the semi-mechanised panel 11/7-S in the mine. The description of the coal winning in the study panel as follows: Bottom section of panel 11/7-S had been developed and depillared upto 3.0 m height by bord and pillar (B/P) method of working in conjunction with hydraulic sand stowing. some portion of bottom section had been left for the purpose of sumping. Depillaring in bottom section had been done by splitting pillar into four parts. After leaving a parting of almost 1.5 m, top section 2.8m was being developed & depillared simultaneously by B/P method of working. Top section depillaring by means of modified depillaring method in which taking dip-rise slice simultaneously then judicial extraction of rib in conjunction with hydraulic sand stowing Panel consisted of 3 SDLs, (one SDL for development and two SDLs for depillaring) loading coal on separate light duty chain conveyor (LDCC). Coal broken by drilling & blasting
  • 3. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 3 was loaded on LDCC by means of side discharge loader (SDL) with bucket capacity of 1.5cu.m. face conveyor discharged the coal on the belt conveyor to be carried out bye through a system of belts up to the coal washery located on surface. The galleries, splits and slices were supported systematically by the roof bolts having yield load of 5 tonne. 5. RESEARCH METHODOLOGY The aforesaid concept of breaking a mine system into sub- systems for finer analysis, has been adopted in the present case study, considering Panel as a system. According the major sub-systems were formulated as given in fig.2. PANEL AS A SYSTEM Face preparation Loading Transportation ventilation stowing pumping Material supply Roof dressing Roof bolting Face dressing Production drilling Prim.,charg, Stem.& blast Fume clearance W ater spraying Loose dressing Side bolting Fig. 2: Formulated systematic proposed model for Present working 6. FIELD OBSERVATIONS: 6.1 Time and Motion Study of Various Sub-Systems: As per the formulated system model (fig.2) the time & motion studies were conducted at field scale for various sub- systems. The statistical data pertaining to the time & motion studies of various sub-systems such as, face preparation (roof dressing, roof bolting, side bolting etc.) loading etc. in statistical format is tabulated in tables 3 to 20. Based on the statistical tables the mean, median, mode, standard deviation & co-efficient of variation for face preparation & loading and mean (average) for stowing & ventilation sub-systems. Table 3: Frequency distribution of roof dressing per face (minute) Class mark (x) Frequency (f) fx Cumulative frequency (c.f) d = x-A = x-20.18 d² fd² 14 11 154 11 -6.18 38.19 420.12 15 18 270 29 -5.18 26.83 482.98 16 7 112 36 -4.18 17.47 122.31 17 3 51 39 -3.18 10.11 30.34 18 3 54 42 -2.18 4.75 14.26 19 2 38 44 -1.18 1.39 2.78 20 2 40 46 -.18 .03 .06
  • 4. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 4 50 1 50 47 29.82 889.23 889.23 55 1 55 48 34.82 1212.43 1212.43 60 1 60 49 39.82 1585.63 1585.63 70 1 70 50 49.82 2482 2482 75 1 75 51 54.82 3005.23 3005.23 ∑f = 51 ∑fx = 1029 ∑fd²=10247.37 Mean (A) = ∑fx ⁄ ∑f = 1029⁄51 = 20.18, Median (M) = 15, Mode (Mo) =15, Standard deviation (σ) = √(∑fd²⁄∑f) = 14.17, Variance (σ²) = 200.92 and Co-efficient of variation = (σ ⁄ A)×100 = 70.24% Table 4: Frequency distribution of roof bolting per bolt (minute) Class interval Class mark (x) Frequency (f) fx c.f d = x-A = x-7.32 d² fd² 4-6 5 40 200 40 -2.32 5.38 215.29 6-8 7 118 826 158 -.32 .10 12.08 8-10 9 20 180 178 1.68 2.82 56.45 10-12 11 2 22 180 3.68 13.54 27.08 12-14 13 2 26 182 5.68 32.26 64.52 14-16 15 5 75 187 7.68 58.98 294.91 16-18 17 3 51 190 9.68 93.7 281.10 18-20 19 1 19 191 11.68 136.42 136.42 ∑f = 191 ∑fx = 1399 ∑fd²=1087.85 Mean (A) = ∑fx ⁄ ∑f = 1399⁄191 = 7.32, Median (M) = 6.94, Mode (Mo) = 6.88, Standard deviation (σ) = √(∑fd²⁄∑f) =2.38, Variance (σ²) = 5.69 and Co-efficient of variation = (σ ⁄ A)×100 = 32.5% Table 5: Frequency distribution of side bolting per face (minute) Class interval Class mark (x) Frequency (f) fx c.f d = x-A = x-3.97 d² fd² 2.5-3.0 2.75 6 16.5 6 -1.22 1.490 8.93 3.0-3.5 3.25 5 16.25 11 -0.72 0.52 2.59 3.5-4.0 3.75 17 63.75 28 -0.22 0.0484 0.82 4.0-4.5 4.25 6 25.5 34 0.5 0.25 1.5 4.5-5.0 4.75 13 61.75 47 0.78 0.61 7.91 5.0-5.5 5.25 1 5.25 48 1.28 1.64 1.64 5.5-6.0 5.75 1 5.75 49 1.78 3.17 3.17 ∑f = 49 ∑fx = 194.75 ∑fd²=26.56 Mean (A) = ∑fx ⁄ ∑f =194.75⁄49 = 3.97, Median (M) = 3.89,Mode (Mo) = 3.76, Standard deviation (σ) = √(∑fd²⁄∑f) =0.736, Variance (σ²) = 0.542 and Co-efficient of variation = (σ ⁄ A)×100 =18.53 %
  • 5. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 5 Table 6: Frequency distribution of face dressing per face (minute) Class interval Class mark (x) Frequency (f) fx c.f d = x-A = x-8.84 d² fd² 6-7 6.5 10 65 10 -2.34 5.475 54.75 7-8 7.5 14 105 24 -1.34 1.795 25.14 8-9 8.5 8 68 32 -0.34 0.115 .92 9-10 9.5 8 76 40 0.66 0.435 3.48 10-11 10.5 0 0 40 1.66 2.755 0 11-12 11.5 0 0 40 2.66 7.075 0 12-13 12.5 0 0 40 3.66 13.395 0 13-14 13.5 2 27 42 4.66 21.72 43.43 14-15 14.5 3 43.5 45 5.66 32.03 96.11 15-16 16.5 2 31.0 47 6.66 44.75 88.71 ∑f = 47 ∑fx = 415.5 ∑fd²=312.54 Mean (A) = ∑fx ⁄ ∑f = 415.5 ⁄ 47 = 8.84, Median (M) = 7.96, Mode (Mo) = 7.4, Standard deviation (σ) = √(∑fd²⁄∑f) = 2.578, Variance (σ²) = 6.65 and Co-efficient of variation = (σ ⁄ A)×100 = 29.16% Table 7: Frequency distribution of production drilling per hole (second) Class interval Class mark (x) Frequency (f) fx c.f d = x-A = x-80 d² fd² 0-20 10 1 10 1 -70 4900 4900 20-40 30 9 570 10 -50 2500 22500 40-60 50 19 950 29 -30 900 17100 60-80 70 51 3570 80 -10 100 5100 80-100 90 26 2340 106 10 100 2600 100-120 110 17 1870 123 30 900 15300 120-140 130 68 1040 131 50 2500 20000 140-160 150 2 300 133 70 4900 9800 ∑f = 133 ∑fx = 10650 ∑fd²=97300 Mean (A) =∑fx ⁄ ∑f =10650⁄133 = 80, Median (M) = 74.7, Mode (Mo) = 71.23, Standard deviation (σ) = √(∑fd²⁄∑f) =27.04, Variance (σ²) = 731.57 and Co-efficient of variation = (σ ⁄ A)×100 = 33.7% Table 8: Frequency distribution of preparing sand capsule, 36 capsule with 3 men (minute) Class mark (x) Frequency (f) fx c.f d = x-A = x-17.44 d² fd² 12 1 12 1 -5.44 29.59 29.59 13 3 39 4 -4.44 19.71 59.14 14 4 56 8 -3.44 11.83 47.33 15 6 90 14 -2.44 5.95 35.72 16 4 64 18 -1.44 2.07 8.29 17 3 51 21 -.44 0.19 .58 18 3 54 24 1.44 2.07 6.21 30 1 30 25 12.56 157.75 157.75
  • 6. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 6 35 1 35 26 17.56 308.35 308.35 40 1 40 27 22.56 508.95 508.95 ∑f = 27 ∑fx = 471 ∑fd²=1161.91 Mean (A) = ∑fx ⁄ ∑f = 471⁄27 = 17.44, Median (M) = 15, Mode (Mo) =15, Standard deviation (σ) = √(∑fd²⁄∑f) = 6.56, Variance (σ²) = 43.03 and Co-efficient of variation = (σ ⁄ A)×100 =37.61 % Table 9: Frequency distribution of charging and blasting per face (minute) Class interval Class mark (x) Frequency (f) fx c.f d = x-A = x-36 d² fd² 29-31 30 7 210 7 -6 36 252 31-33 32 4 128 11 -4 16 64 33-35 34 7 238 18 -2 4 8 35-37 36 1 36 19 0 0 0 37-39 38 6 228 25 2 4 24 39-41 40 4 160 29 4 16 64 41-43 42 3 126 32 6 36 108 43-45 44 2 88 34 8 64 128 45-47 46 1 46 35 10 100 100 ∑f = 35 ∑fx =1260 ∑fd²=768 Mean (A) = ∑fx ⁄ ∑f = 1260 ⁄ 35 = 36, Median (M) = 34.85, Mode (Mo) = 33.67, Standard deviation (σ) = √(∑fd²⁄∑f) = 4.68, Variance (σ²) = 21.94 and Co-efficient of variation = (σ ⁄ A)×100 = 13% Table 10: Frequency distribution of fume clearance per face (minute) Class interval Class mark (x) Frequency (f) fx c.f d = x-A = x-4.78 d² fd² 3.5-4.0 3.75 2 7.5 2 -1.03 1.06 2.12 4.0-4.5 4.25 12 51 14 -0.53 0.28 3.37 4.5-5.0 4.75 13 61.75 27 -0.03 .0009 0.0117 5.0-5.5 5.25 6 31.5 33 0.47 .22 1.325 5.5-6.0 5.75 4 23 37 0.97 0.94 3.76 6.0-6.5 6.25 0 0 37 1.47 2.16 0 6.5-7.0 6.75 1 6.75 38 1.97 3.88 3.88 ∑f = 38 ∑fx =181.5 ∑fd²=14.46 Mean (A) = ∑fx ⁄ ∑f = 181.5 ⁄ 38 = 4.78, Median (M) = 4.69, Mode (Mo) = 4.56, Standard deviation (σ) = √(∑fd²⁄∑f) = 0.616, Variance (σ²) = 0.381 and Co-efficient of variation = (σ ⁄ A)×100 = 12.88%
  • 7. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 7 Table 11: Frequency distribution of time study of water spraying and loose dressing per face (minute) Class interval Class mark (x) Frequency (f) fx c.f d = x-A = x-17.98 d² fd² 14-15 14.5 2 29 2 -3.48 12.11 24.22 15-16 15.5 3 46.5 5 -2.48 6.15 18.45 16-17 16.5 2 33 7 -1.48 2.19 4.38 17-18 17.5 6 105 13 -0.48 .23 1.38 18-19 18.5 6 111 19 0.58 .27 1.68 19-20 19.5 4 78 23 1.58 2.31 9.24 20-21 20.5 3 61.5 26 2.52 6.35 19.05 21-22 21.5 1 21.5 27 3.52 12.39 12.39 ∑f = 27 ∑fx =485.5 ∑fd²=295.32 Mean (A) = ∑fx ⁄ ∑f = 485.5 ⁄ 27 = 17.98, Median (M) = 18.08, Mode (Mo) =18 Standard deviation (σ) =√(∑fd²⁄∑f) = 3.31, Variance (σ²) = 10.93 and Co-efficient of variation = (σ ⁄ A)×100 = 18.41% Table 12: Frequency distribution of loading cycle time (second) at lead up to 5 metres Class interval Class mark (x) Frequency (f) fx c.f d = x-A = x-51.12 d² fd² 35-40 37.5 8 300 8 -13.62 185.50 1484.03 40-45 42.5 23 977.5 31 -8.62 74.30 1709.00 45-50 47.5 19 902.5 50 -3.62 13.10 248.98 50-55 52.5 10 525 60 1.38 1.90 19.04 55-60 57.5 17 977.5 77 6.38 40.70 691.97 60-65 62.5 9 562.5 86 11.38 129.50 1165.53 65-70 67.5 5 337.5 91 16.38 268.30 1341.52 70-75 72.5 2 145 93 21.38 457.10 914.21 75-80 77.5 1 77.5 94 26.38 695.90 695.90 ∑f = 94 ∑fx = 4805 ∑fd²=8270.18 Mean (A) = ∑fx ⁄ ∑f = 4805 ⁄ 94= 51.12, Median (M) = 49.21, Mode (Mo) = 43.95 Standard deviation (σ) = √(∑fd²⁄∑f) =9.38, Variance (σ²) = 87.98 and Co-efficient of variation = (σ ⁄ A)×100 = 18.34% Table 13: Frequency distribution of loading cycle time (second) at lead 5-10 metres Class interval Class mark (x) Frequency (f) fx c.f d = x-A = x-75.58 d² fd² 65-70 67.5 15 1012.5 15 -8.08 65.28 979.29 70-75 72.5 17 1232.5 32 -3.08 9.48 161.27 75-80 77.5 3 232.5 35 1.92 3.68 11.06 80-85 82.5 3 247.5 38 6.92 47.88 143.66
  • 8. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 8 85-90 87.5 3 262.5 41 11.92 142.08 426.24 90-95 92.5 4 370 45 16.92 286.28 1145.14 95-100 97.5 2 195 47 21.92 480.48 960.97 ∑f = 47 ∑fx =3552.5 ∑fd²=3827.63 Mean (A) = ∑fx ⁄ ∑f = 3552.5⁄47 = 75.58, Median (M) = 72.5, Mode (Mo) = 70.63 Standard deviation (σ) = √(∑fd²⁄∑f) =9.02, Variance (σ²) =81.44 and Co-efficient of variation = (σ ⁄ A)×100 =11.94 % Table 14: Frequency distribution of loading cycle time (second) at lead 10-15 metres Class interval Class mark (x) Frequency (f) fx c.f d = x-A = x-83.29 d² fd² 70-75 72.5 5 362.5 5 -10.79 116.42 582.12 75-80 77.5 7 542.5 12 -5.79 33.52 134.67 80-85 82.5 17 1402.5 29 -0.79 .624 10.61 85-90 87.5 9 787.5 38 4.21 17.72 159.52 90-95 92.5 4 370 42 9.21 84.82 339.29 95-100 97.5 1 97.5 43 14.21 201.92 201.92 100-105 102.5 1 102.5 44 19.21 369.02 369.02 ∑f = 44 ∑fx =3665 ∑fd²=1897.15 Mean (A) = ∑fx ⁄ ∑f = 3665 ⁄44 = 83.29, Median (M) = 82.94, Mode (Mo) = 82.77 Standard deviation (σ) = √(∑fd²⁄∑f) =6.57, Variance (σ²) =43.11 And Co-efficient of variation = (σ ⁄ A)×100 =7.88 % Table 15: Frequency distribution of loading cycle time (second) at lead 15-20 metres Class interval Class mark (x) Frequency (f) fx c.f d = x-A = x-99.74 d² fd² 90-95 92.5 17 1572.5 17 -7.24 52.42 891.14 95-100 97.5 14 1365 31 -2.24 5.02 70.25 100-105 102.5 7 717.5 38 2.76 7.62 53.32 105-110 107.5 5 537.5 43 7.76 60.22 301.08 110-115 112.5 3 337.5 46 12.76 162.82 488.45 115-120 117.5 2 235 48 17.76 315.42 630.83 120-125 122.5 1 122.5 49 22.76 518.02 518.02 ∑f =49 ∑fx =4887.5 ∑fd²=2453.09 Mean (A) =∑fx ⁄ ∑f = 4887.5 ⁄49 = 99.74, Median (M) = 97.67, Mode (Mo) = 94.25 Standard deviation (σ) = √(∑fd²⁄∑f) =7.07, Variance (σ²) =50.06 and Co-efficient of variation = (σ ⁄ A)×100 =7.09 %
  • 9. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 9 Table 16: Frequency distribution of loading cycle time (second) at lead 20-25 metres Class interval Class mark (x) Frequency (f) fx c.f d = x-A = x-122.09 d² fd² 110-115 112.5 16 1800 16 -9.59 91.96 1471.48 115-120 117.5 11 1292.5 27 -4.59 21.06 231.75 120-125 122.5 6 735 33 0.41 .168 1.00 125-130 127.5 4 510 37 5.41 29.27 117.07 130-135 132.5 5 662.5 42 10.41 108.37 541.84 135-140 137.5 4 550 46 15.41 237.47 949.87 140-145 142.5 2 285 48 20.41 416.56 833.14 145-150 147.5 1 147.5 49 25.41 645.67 645.67 ∑f =49 ∑fx =5982.5 ∑fd²=4791.82 Mean (A) =∑fx ⁄ ∑f = 5982.5 ⁄49 =122.09, Median (M) = 118.86,Mode (Mo) =113.07 Standard deviation (σ) = √(∑fd²⁄∑f) =9.88, Variance (σ²) =97.79 and Co-efficient of variation = (σ ⁄ A)×100 =8.09 % Table 17: Frequency distribution of loading cycle time (second) at lead 25-30metres Class interval Class mark (x) Frequency (f) fx c.f d = x-A = x-153.09 d² fd² 120-130 125 7 875 7 -28.09 789.05 5523.33 130-140 135 9 1215 16 -18.09 327.25 2945.23 140-150 145 6 870 22 -8.09 65.45 392.68 150-160 155 7 1085 29 1.91 3.65 25.54 160-170 165 2 330 31 11.91 141.85 283.69 170-180 175 3 525 34 21.91 480.05 1440.14 180-190 185 5 925 39 31.91 1018.25 5091.24 190-200 195 1 195 40 41.91 1756.45 1756.45 200-210 205 2 410 42 51.91 2694.65 5389.29 ∑f =42 ∑fx =6430 ∑fd²=22842.49 Mean (A) =∑fx ⁄ ∑f = 6430 ⁄ 42=153.09, Median (M) = 148.33, Mode (Mo) = 134, Standard deviation (σ) = √(∑fd²⁄∑f) =23.32, Variance (σ²) =543.86 and Co-efficient of variation = (σ ⁄ A)×100 = 15.23% Table 18: Average loading cycle time w.r.t. different lead Lead ( metre) Average cycle time (second) Upto 5 51.12 5-10 75.58 10-15 83.29 15-20 99.74 20-25 122.09 25-30 153.09
  • 10. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 10 Table 19: Monthly average stowing rate (te/hr) during the study period Date Daily Stowing rate (te/hr.) Date Daily Stowing rate (te/hr.) Monthly average stowing rate (te/hr) 2/4/2006 105 2/5/2006 87.5 (90.95+96.05)/2 = 93.5 3/4/2006 92.85 3/5/2006 100 5/4/2006 89.65 4/5/2006 100 10/4/2006 94.16 8/5/2006 100 11/4/2006 90 9/5/2006 90.9 14/4/2006 57.14 10/5/2006 95 17/4/2006 90.47 11/5/2006 85.71 19/4/2006 100 18/5/2006 100 24/4/2006 88.88 19/5/2006 97.43 25/4/2006 92.31 20/5/2006 100 26/4/2006 100 28/5/2006 100 Monthly daily average stowing rate (te/hr.) 90.95 96.05 Table 20: Average intake quantity, Quantity at LVC and VEQ (%) Measurement Date Intake quantity (cu.m /min.) Quantity at LVC (cu.m /min.) VEQ (%) 4/10/2005 1017 763 75 31/10/2005 1067 610 57.16 5/11/2005 1050 720 68.57 24/11/2005 1024 694 67.77 2/12/2005 1008 696 69 16/12/2005 1064 750 70.48 4/01/2006 1085 772 71.15 18/01/2006 1117 805 72.06 4/02/2006 1101 794 72.11 18/02/2006 902 742 82.26 7/3/2006 1113 834.75 75 16/3/2006 746 554 74.26 4/4/2006 763 534 69.98 2/4/2006 931 847 90.9 15/5/2006 706 669 94.75 Average 979.6 718.98 74.03 7. RESULTS & DISCUSSION 7.1 Results of Various Operations Results of various operations of face preparation sub-system & loading sub-system are plotted as frequency distribution curves, and, shown in fig. 3to 17. Frequency distribution curves have been drawn from table 3 to 17. From these frequency distribution curves various time elements have been estimated and used for the computation of system capacities. Further, in order to estimate the average loading cycle time (by SDLs at various lead distances) the SDL loading time was studied in the field & the results are graphically plotted as shown in fig. 18. Graph has been plotted from table 18. Again, in order to estimate the average stowing rate the stowing operation was studied in the field & the results are graphically plotted in fig. 19. Graph has been plotted from table 19. Again, in order to estimate the intake quantity, quantity at LVC & VEQ (%) ventilation operation was studied in the field & the results are graphically plotted in fig. 20. Graph has been plotted from table 20.
  • 11. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 11 0 2 4 6 8 10 12 14 16 18 20 0 20 40 60 80 Roof dressing time per face(minutes) Frequency Fig. 3: Roof dressing time per face vs. Frequency 0 20 40 60 80 100 120 140 0 5 10 15 20 Roof bolting time per bolt (minutes) Frequency Fig. 4: Roof bolting time per bolt vs. Frequency 0 2 4 6 8 10 12 14 16 18 0 1 2 3 4 5 6 7 Side boltingtime per bolt (minutes) Frequency Fig. 5: Side bolting time per bolt vs. Frequency -2 0 2 4 6 8 10 12 14 16 0 5 10 15 20 Face dressing time per face (minutes) Frequency Fig. 6: Face dressing time per face vs. Frequency 0 10 20 30 40 50 60 0 20 40 60 80 100 120 140 160 Production drilling time per hole (seconds) Frequency Fig. 7: Production drilling time per hole vs. Frequency 0 1 2 3 4 5 6 7 0 10 20 30 40 50 Time (minutes) for 36 capsules per 3 men Frequency Fig. 8: Time for 36 sand capsules per 3 men vs. Frequency
  • 12. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 12 0 1 2 3 4 5 6 7 8 0 10 20 30 40 50 Charging & blasting time per face (minutes) Frequency Fig. 9: Charging and blasting time per face vs. Frequency -2 0 2 4 6 8 10 12 14 0 1 2 3 4 5 6 7 8 Fume clearance time per face (minutes) Frequency Fig. 10: Fume clearance time per face vs. Frequency 0 1 2 3 4 5 6 7 0 5 10 15 20 25 Water spraying& loose dressing time per face (minutes) Frequency Fig. 11: Water spraying & loose dressing time per face vs. Frequency 0 5 10 15 20 25 0 20 40 60 80 100 Time per cycle (seconds) Frequency Fig. 12: Loading cycle time (lead up to 5m) vs. Frequency 0 2 4 6 8 10 12 14 16 18 0 20 40 60 80 100 120 Time per cycle (seconds) Frequency Fig. 13: Loading cycle time (lead 5-10m) vs. Frequency 0 2 4 6 8 10 12 14 16 18 0 20 40 60 80 100 120 Time per cycle (seconds) Frequency Fig. 14: Loading cycle time (lead 10-15m) vs. Frequency
  • 13. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 13 0 2 4 6 8 10 12 14 16 18 0 20 40 60 80 100 120 140 Time per cycle (seconds) Frequency Fig.15: Loading cycle time (lead 15-20m) vs. Frequency 0 5 10 15 20 0 50 100 150 200 Time per cycle (seconds) Frequency Fig. 16: Loading cycle time (lead 20-25m) vs. Frequency 0 2 4 6 8 10 0 50 100 150 200 250 Time per cycle (seconds) Frequency Fig. 17: Loading cycle time (lead 25-30m) vs. Frequency 51.12 75.58 83.29 99.74 122.09 153.09 0 20 40 60 80 100 120 140 160 180 0 5 10 15 20 25 30 Lead (meters) Averageloadingcycletime(seconds) Fig. 18: Lead vs. Average loading cycle time 0 20 40 60 80 100 120 0 2 4 6 8 10 Time (weekly) Stowingrate(te/hr) Fig. 19: Time vs. stowing rate 0 200 400 600 800 1000 1200 4/10/20055/11/20052/12/20054/1/20064/2/20067/3/20064/4/200615/05/06 Time( 1st fortnight & 2nd fortnight of each month from oct.05 to may 06) Intakequantity,quantityatLVC &VEQ(%) Intake quantity Quantity at LVC VEQ (%) Fig. 20: Time vs. Intake quantity (cu.m/min.), Quantity at LVC and VEQ (%)
  • 14. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 14 7.2 Statistical Results of Face Preparation & Loading Sub-System: Statistical results of face preparation & loading sub-system are tabulated in table 21. Results in this table have been drawn from frequency distribution table 3 to 17 (Except table 8) Table 21: Integrated table showing the statistical results of face preparation and loading sub-systems Operations Mean Median Mode Standard Deviation Variance Co-efficient of variation (%) face preparation time 1. Roof dressing per face(minutes) 20.18 15 15 14.17 200.92 70.24 2. Roof bolting per bolt (minutes) 7.32 6.94 6.88 2.38 5.69 32.51 3.Side bolting per bolt(minutes) 3.97 3.89 3.76 0.736 0.542 18.53 4.Face dressing per face(minutes) 8.84 7.96 7.4 2.57 6.65 29.16 5.Production drilling per hole (seconds) 80 74.7 71.23 27.04 731.57 33.7 6.Charging & blasting per face (minutes) 36 34.85 33.67 4.68 21.94 13 7.Fume clearance per face(minutes) 4.78 4.69 4.56 .616 .381 12.88 8.WS+LD per face(minutes) 17.98 18.08 18 3.31 10.93 18.41 Loading cycle time (seconds) 1 Lead (0-5m) 51.12 49.21 43.95 9.38 87.98 18.34 2. Lead (5-10m) 75.58 72.5 70.63 9.02 81.44 11.94 3.Lead (10-155m) 83.29 82.94 82.77 6.57 43.11 7.88 4.Lead (15-20m) 99.74 97.67 94.25 7.07 50.06 7.09 5.Lead (20-25m) 122.1 118.86 113.07 9.88 7.79 8.09 6.Lead (25-30m) 153.1 148.33 134 23.321 543.86 15.23 From the analysis of the results as given in table 21 the following important discussion may be drawn: Statistical analysis of roof dressing operation shows significantly high value of co-efficient of variation (70.24%) in comparison to other operations which shows that data is not consistent. This, in turn, implies that the roof dressing operation is inconsistent in nature, being dependent and the prevailing geo-mining conditions. In this panel, particularly, the roof conditions were bad & variable due to presence of carbonaceous shale. 7.3 Results for Capacity Estimation: From the fore going table 21 & related statistical computation (mean, median, mode, standard deviation & co-efficient of variation), it is quite justified to use the mean time element for the purpose of capacity estimation. Median & Mode appears to provide very optimistic data in uncertain geo-mining conditions. That is why the mean appears justifiable. Table 22 & 23 provides the mean time element for various sub-systems under study. Table 22: Mean time elements for various operations used for capacity estimation of sub-systems (Face Preparation & Loading) Operations Statistical Time (mean) Face preparation time: 1. Roof dressing per face(minutes) 20.18 2. Roof bolting per bolt(minutes) 7.32 3.Side bolting per bolt(minutes) 3.97 4.Face dressing per face(minutes) 8.84 5.Production drilling per hole (seconds) 80 6. Charging & blasting per face (minutes) 36 7.Fume clearance per face(minutes) 4.78 8.Water spraying & Loose dressing per face (minutes) 17.98 Loading cycle time (seconds): 1. Lead (15-20m) 99.74
  • 15. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 __________________________________________________________________________________________ Volume: 02 Issue: 12 | Dec-2013, Available @ http://www.ijret.org 15 Table 23: Mean time elements for various operations used for capacity estimation of sub-systems (ventilation, transportation & stowing) Ventilation sub-system Transportation sub-system Stowing sub-system Average intake quantity =979.6 cu.m/min. Tipper belt= 20hrs./day Average stowing rate 93.5 te/hr(on monthly basis) Average quantity at LVC =718.98 cu.m/min. Trunk belt= 20 hrs./day Average leakages quantity =260.62 cu.m/min. Sectional belt = 18hrs./day Face chain conveyor =18 hrs./day CONCLUSIONS 1. Statistical analysis of roof dressing operation shows significantly high value of co- efficient of variation which means roof condition is not good. 2. Mean time elements will be considered as standard time for Capacity estimation purpose of various Sub- Systems REFERENCES [1] Bhattcherjee, A., Maiti, J. and Mukherjee, N. “An investigation of system performance of mechanized bord-and-pillar mine working through discrete event simulation modeling”, Minetech Journal., Vol. 17, No.6, Nov.-Dec.,1996, pp.33-37. [2] Chaoji, S.V. “Environmental challenges and future of Indian coal”, Journal of Mines, Metals and Fuels, Vol. 50, No.7, July, 2002, pp.257-261 [3] Karmakar, H.N. “New generation mine modeling for higher production and productivity of underground coal mines”, Minetech Journal, Vol. 17, No.6, Nov.- Dec.,1996, pp. 39-42. [4] Mathur, S.P. “Labour productivity and cost reduction in Indian coal mines”. Minetech Journal, Vol.11, No. 3, May-June, 1999, pp. 5-9 [5] Mukhopadhyay, S.B. and Babu, A.V. “System analysis approach in mining operations-an overview”, Minetech Journal,Vol.14, No.5-6, Sep-Dec.,1993. pp.30-36. [6] Rai,P. & Singh, Arvind Kumar. “System analysis approach for production planning in underground coal mine”, Minetech, Vol.26, No.2, Mar- Apr.,2005, pp.23- 28 [7] Rai, P. “Some aspects of material transportation by rear dump trucks in opencast mines”, Minetech Journal, Vol.22, No.3, May-Jun., 2001, pp.3-10. [8] Ray, S.C. And Sinha, D.K. “Capacity analysis of mine system-a pre-requisite for production planning in underground mines”, Indian Mining & Engineering Journal, Vol.17., No.5, May,1978, pp.7-12. [9] Sachdev, B.K. “Coal industry in India development issues” Procs. 4th Asian mining international conference on geology, mining and mineral processing. Nov. 24-28, Calcutta, 1993.