GOVERNMENT OF KHYBER
PAKHTUNKHWA
REVISED UMBRELLA
PC-I
“Tourism Area Integrated Development
Project
(Establishment of Provincial Tourism
Authority)”
ADP No. 1397/160584
FY-2017-18
Total Cost Rs. 2714.610 Million
SPORTS, TOURISM, ARCHAEOLOGY,
MUSEUMS, CULTURE & YOUTH AFFAIRS
DEPARTMENT
Page 2 of 15
PC-1 FORM
1. Name of the Project “Tourism Area Integrated Development Project (Establishment of
Provincial Tourism Authority)”
ADP No. 1397/150472
2. Location Sports, Tourism, Archaeology, Museums, Culture & Youth Affair
Department
3. Authority responsible
for:
i. Sponsoring
ii. Execution
iii. O & M
i. Sports, Tourism, Archaeology, Museums, Culture & Youth
Affair Department Govt. of Khyber Pakhtunkhwa.
ii. Tourism Department Govt. of Khyber Pakhtunkhwa
iii.Tourism Department Govt. of Khyber Pakhtunkhwa
4. Plan Provision The scheme was included in ADP vide Computer No. 160584 at a
total cost of Rs. 2500 Million which has been revised to Rs.
2714.610 million on the revenue side for implementation by the
Tourism Area Integrated Development Unit of the Department.
5. Project objectives and
its relationship with
Sectoral objectives
Khyber Pakhtunkhwa is generally recognized as the tourism hub of
Pakistan, with its beautiful valleys, lakes, archaeological sites,
historic remains, rivers, mountains, glaciers, civilizations, culture
and people.
Efforts have resulted in promotion of tourism in this province but
have not been able to fully explore the tourism potential of the
province. There are many causes normally referred for under-
development of the tourism in the province, however, the chief
indicators are lack of motivation, lack of political will, low priority
accorded by the government, meagre financial resource allocations
and prevailing inadequate tourism organizational structure.
The proposed project for Integrated Tourism Area Development
Project will assist Khyber Pakhtunkhwa in better designing and
implementing a management approach to promote
environmentally sound tourism development and reduce ecological
degradation through enhancing environmental protection, spatial
development, institutional capacity and governance of the area.
The project objectives are in line with sectoral priorities of
institutional strengthening and capacity building, studies and
research as given in Khyber Pakhtunkhwa Comprehensive
Development Strategy 2010-2017.
6. Description,
justification and technical
parameters
Description
The project entails:
 Establishment of ‘Tourism Area Integrated Development
Unit’ in Tourism Department for formulation and
implementation of management plans for promotion,
development and uplift of tourism related areas.
 Block allocation for implementing area development projects at
tourism related areas.
 Necessary development/ spadework for “Establishment of
Provincial Tourism Authority”.
Justification
Tourism Corporation Khyber Pakhtunkhwa (TCKP) is assigned
with the total responsibility for promotion of tourism activities.
Page 3 of 15
The Corporation acts as a field wing of the Tourism Department.
However due to introduction of new avenues and establishment of
area development authorities like Kalam Development Authority,
Malakand Development Authority etc the Tourism Department has
added responsibility to plan and execute tourism related projects.
Tourism Area Integrated Development Project is a concept
based on the analogy of Urban Development Unit & Special Area
Development Unit to develop those areas where tourism is only or
main source of income generation. These interventions will help
not only in uplift of the socio-economic life standard of locals but
also allows all stakeholders involved in tourism industry to benefit
equally.
Key features of this project will include:
 A full-fledged Tourism Area Integrated Development Unit to
plan, develop, execute and monitor projects benefiting
development of tourism.
 Development of tourist facilities in areas with tourist potential
where private sector is shy to invest.
 Develop/ prepare plans for development of tourist areas by
involving all stakeholders.
 Provide a launch pad to the private sector organizations in the
areas of hotel management, consultancies, leisure organization
etc.
 Promotion and development of tourism in province.
 Coordination of provincial tourism plans and activities.
 Publicity within the country and abroad.
 Interacting international organizations and conducting
agreements relating to tourism.
 Facilitation of travel for tourists.
 Training and research in tourism.
Technical Parameters:
Once initiated, the project will be managed by a central unit with
field offices at Swat for Malakand Division, at Abbottabad for
Hazara Division and at D.I. Khan for Southern Areas. The Unit
combines the technical capabilities to deliver the project in a
fruitful manner while field offices will provide technical support
for planned interventions.
It will be a three years project and staff will be hired both on
project policy moreover suitable government servants can also be
posted in this project on deputation basis as per policy.
The Unit will be headed by Project Director TAIDU who will
report to Additional Secretary Tourism Department through
Managing Director TCKP (Organogram of the Unit is Annexed).
Planning & Design Mechanism:
The project will caters for development/ uplift schemes to be
identified by project technical staff based at head office and field
offices in consultation with all relevant stakeholders i.e. govt.
departments, district/ divisional administration, local MNA/ MPA,
private sector and general public. All such schemes will be
executed under this umbrella PC-I after approval of competent
forum.
Page 4 of 15
Scheme Execution Mechanism:
For execution of the schemes identified TAIDU will hire
consultants on open competitive bidding on the analogy of
“Project Coordination Unit” of Police Department. The Consultant
so hired will do all work from planning, preparation of PC-I to
implementation and execution. Technical staff of TAIDU will
perform the routine monitoring duties and Departmental
Monitoring Committee will be responsible to review performance
of each scheme on monthly basis.
Scheme Selection/ Approval/ Monitoring Mechanism:
A Departmental Monitoring Committee headed by Secretary
Tourism Department and assisted by MD TCKP, Manager
Accounts TCKP, Incharge Engineering Wing & Project Director
(TAIDU) will be constituted to identify/ evaluate proposals
submitted by field offices/ head office. After identification the
same will be recommended to Project Steering Committee. This
Committee will also be responsible for financial and technical
monitoring of the each project every month as well as will serve as
Project Consultant Selection Committee (PCSC) who will select
consultant for identification, execution & implementation of
proposals approved by the Competent Forum.
Project Steering Committee:
The following Committee will be constituted as Project Steering
Committee to steer the project:
1. ACS P&D Chairman
2. Secretary Tourism Department Member
3. Secretary LG&RDD Member
4. Deputy Commissioner (Concerned) Member
5. Managing Director (TCKP) Member
6. Project Director (TAIDU) Member cum Secretary
TORs of the Committee are as under::
 To approve the schemes identified by the Departmental
Monitoring Committee for further processing of DDWP/
PDWP.
 To review the project performance after 3 months.
 To take any other policy decision for smooth functioning of
project.
Funds allocated/ released for this project will be managed by
Accounts/ Finance Officer of the project under relevant rules.
Establishment of Provincial Tourism Authority:
Tourism Department and TCKP will take all necessary steps for
establishment of PTA. The activities undertaken in this scheme
will be later be overtaken by PTA.
Page 5 of 15
7.Capital Cost
Estimates
8. Annual
Operating &
Maintenance Cost
After Completion
Of Project
The project will be shifted to current side after completion and fulfilment
of objectives. Details of Capital and Operational Cost is at Annex-III &
IV respectively.
9. Demand and
Supply Analysis
Currently the department has no specific setup to assess, identify and
develop the potential areas where tourism can become main livelihood/
economic development tool.
Incorporating this scheme will lead to uplifting of tourism in a systematic
way.
10. Financial Plan
and mode of
financing
ADP 2016-17 onwards
11. Project benefits
and analysis.
Financial:
N/A
Social benefits with indicators:
Provision of facilities in tourism oriented areas will create soft image of
the province. Moreover it has a trickledown effect over the society in the
form of creating awareness regarding the tourism, promoting cultural
heritage, archaeological awareness etc.
Employment Generation (direct and indirect):
Creation of TAIDU will result in direct employment. Uplift and provision
of necessary facilities through this scheme will create economic
generation opportunities in the target areas.
Environmental Impact:
Environmental Specialist hired under this project will also assess and
identify ways & means to preserve environment and natural resources.
Impact of delays on project cost and viability:
Any delay in the project execution will lead to cost and time overrun.
Total Revised Difference
1 HR Cost 48.760 68.380 19.62
2 Capital Cost 26.430 26.430 -
3 Operational Cost 25.950 25.950 -
4 Establishment of PTA 13.000 13.000 -
5
Block Allocation for
Developmental Activities
2,386.000 2580.540 -
5.1 Sub Component Kalam (1,263.000) (1,492.520) 229.52
5.2 Sub Component Naran (511.000) (657.380) 164.38
5.3 Sub Component Chitral - (375.360) -
5.4 Sub Component Buner - (55.280) -
6 Total (Rs. in Million) 2,500.140 2,714.610 214.470
7
Total Expenditure as of
31/12/2017, since start
897.500
Total Financial Implications
(2016-17-18-19) Rs. in MillionS # Name of Component
Page 6 of 15
Furthermore the project objectives will not be achieved in time and the
quality of work will be compromised and the projects as ever will not be
completed in time.
12. Implementation
schedule
Starting Date: From issuance of the A.A
Ending Date: 30th June 2019
13. Management
structure &
manpower
requirements
including
Specialized skills
during execution
and operational
phases
Management structure and manpower requirements including specialized
skills during execution and operational phases is given at Annex-I. While
the qualifications and job descriptions are at Annex-II.
14.Additional
projects/decisions
required to
maximize socio-
economic benefits
from the proposed
project
Since this is the first ever project which is to be implemented at the
provincial level, therefore, its sustainability in the long run is imperative.
For the purpose the project after completion needs to be regularised
through current budget.
15. Certified
that the project
proposal has been
prepared on the
basis of
instructions
provided by the
Planning
Commission for the
preparation of PC-
I for Social Sector
projects.
Prepared by:
Planning Officer
Sports, Tourism, Archaeology, Museums, Culture & Youth Affair
Department
Checked by:
Chief Planning Officer
Sports, Tourism, Archaeology, Museums, Culture & Youth Affair
Department
Secretary
Sports, Tourism, Archaeology, Museums, Culture & Youth Affair
Department
Approved by:
PDWP
Page 7 of 15
(Annexure-I)
S. # Post & Designation BPS
No. of
Posts
Monthly
Salary
2016-17
(9 Months)
Annual
Increase
2017-18
2017-18
(with
increase)
Annual
Increase
2018-19
2018-19
(with
increase)
Total
1 Project Director 19 1 175,000 1,575,000 105,000 2,205,000 105,000 2,310,000 6,090,000
2 Dy. Project Director 18 1 125,000 1,125,000 75,000 1,575,000 75,000 1,650,000 4,350,000
3 Assistant Director 17 2 90,000 1,620,000 54,000 2,268,000 54,000 2,322,000 6,210,000
4
Assistant Director
(Accounts & Finance)
17 1 90,000 810,000 54,000 1,134,000 54,000 1,188,000 3,132,000
5 M&E Officer 17 1 90,000 810,000 54,000 1,134,000 54,000 1,188,000 3,132,000
6 Technical Engineers 17 4 90,000 3,240,000 54,000 4,536,000 54,000 4,590,000 12,366,000
7 IT/ GIS Specialist 17 1 90,000 810,000 54,000 1,134,000 54,000 1,188,000 3,132,000
8 Assistant 16 3 60,000 1,620,000 36,000 2,268,000 36,000 2,304,000 6,192,000
9 Sub. Engi 14 3 40,000 1,080,000 24,000 1,512,000 24,000 1,536,000 4,128,000
10 Computer Operators 14 3 40,000 1,080,000 24,000 1,512,000 24,000 1,536,000 4,128,000
11 Junior Clerk 14 5 40,000 1,800,000 24,000 2,520,000 24,000 2,544,000 6,864,000
12 Site Surveyors 14 3 40,000 1,080,000 24,000 1,512,000 24,000 1,536,000 4,128,000
13 Drivers 5 1 20,000 180,000 12,000 252,000 12,000 264,000 696,000
14 Naib Qasid 2 7 16,000 1,008,000 9,600 1,411,200 9,600 1,420,800 3,840,000
Total 36 1,006,000 17,838,000 24,973,200 25,576,800 68,388,000
HR Cost of Tourism Development Unit (TAIDU)
Page 8 of 15
(Annexure-II)
STAFF QUALIFICATION
S.
#
Post &
Designation
BPS
Job Specifications (required
education skills)
Job Description
(duties)
1
Project
Director
19
 Master’s degree in Social Sciences/
Management Sciences or any other
relevant field.
 Work experience of at least 12
years in govt. setup and
management of multiple projects as
a leader.
 Proficiency in the use of computer.
 Retired Civil/ Military Officers
(not below BPS-18 at the time of
retirement) will be preferred.
1.Direct, coordinate, and lead
activities
2.Responsible for the
performance of all his
subordinates.
3.Analyse the future needs of
resources or new projects for
risk management and give
recommendations in advance.
4.Recognize and solve potential
problems and evaluate project
effectiveness.
5.Outline work plan to assign
duties, responsibilities, and
scope of authority.
6.Accomplishes special project
results by identifying and
clarifying issues and priorities,
communicating and
coordinating requirements,
expediting fulfilment,
evaluating milestone
accomplishments, evaluating
optional courses of action,
changing assumptions and
directions.
7.Guides management and
employee actions by
researching, developing,
deciding, and updating policies,
procedures, methods, and
guidelines; communicating and
enforcing organization values.
8.Network with local, regional,
state and national agencies; and
private sector business interests
for future program
development.
9.Making sure that each stage is
progressing on time, on budget
and to the right quality
standards.
10. Take final decision on
the assignment
2
Deputy
Project
Director
18
 Master’s in Project Management or
Business Administration or Social
Sciences.
1.Work with Project Director in
strategic planning & project
management in order to achieve
project objectives.
Page 9 of 15
 Work experience of at least 05 years
in Govt. or Semi Govt. Department
or private organizations of national
level.
 Having Computer Proficiency.
 Analytical Skills
 Team building skill
 Risk management skill.
 Effective communication skills and
interpersonal skills.
 Decision making skills.
 Age Limit: 40 Years
2.Attend and participate in
professional group meetings, be
connected with other interested
organizations & provide
answers to their inquiries about
relevant project issues.
3.Deputy Project Director will
assist Project Director in
management of project
activities.
4.Regularly report to Project
Director about the progress of
the project & inform him about
any variances from project
objectives.
5.Supervise, direct & control the
activities of Assistant Manager
& check their progress towards
objectives of the project.
6.Will participate in project
strategic planning & help in
implementation of policies &
procedures approved.
7.Will act as Project Director in
his absence.
3
Assistant
Director
17
 Master’s/ B.Sc (Hons) or
equivalent degree in Project
Management or Business
Administration or Social Sciences.
 Work experience of at least 03
years in Govt. or Semi Govt.
Department or private
organizations of national level.
 Any Office Management related
course (not less than 3 months &
recognized by Board of Technical
Education or any other Govt.
Institute)
 Strong communication and
interpersonal skills are required
 He should be efficient in general
management of tasks and having
good persuasive skills.
 Ability to perform the essential
duties and responsibilities with in
time and work in the
 Stressful conditions effectively.
 Age Limit: 35 Years
1.Direct basic office management
functions that may include
technical and functional
supervision of others
2.Monitor and coordinate the
daily operation of assigned
project or department; perform
Administrative detail work and
maintain appropriate records
and statistics.
3.Measure operational staff
activities to standards & if
deficiency exist provide
training or go for new
recruitment.
4.Assist in the development of
new strategic plans &
recommend modifications in
existing plans in order to
achieve the objective.
5.Assist in the preparation of a
budget; prepare budget
recommendations relative to
assigned areas of responsibility;
research past expenditures and
project next year increases.
6.Provide responsible
Page 10 of 15
paraprofessional and technical
assistance in the analysis,
implementation, and
monitoring of department
planes, investigate, analyse,
develop and prepare special
studies and planes as per the
need of department.
4
Assistant
Director
(Accounts &
Finance)
17
 Masters/ B.Sc (Hons) or equivalent
Degree in Finance or Accounts or
Management Sciences or
Economics from a HEC recognized
university.
 Work experience of at least 03
years in Govt. or Semi Govt.
Department or private
organizations of national level.
 Any finance/ accounts related
course (not less than 3 months &
recognized by Board of Technical
Education or any other Govt.
Institute)
 Advanced knowledge of public
sector financial, accounting, and
budgeting principles and
procedures.
 Knowledge of a range of automated
financial systems and applications
software.
 Knowledge of computerized
information systems used in
financial and/or accounting
applications.
 Age Limit: 35 Years
1.Prepares financial statements at
the organizational level;
prepares fiscal and budget
reports for internal
management and external
agencies.
2. Oversees the approval and
processing of accounts,
expenditure, and position
control documents, ledger and
account maintenance and data
entry, ensuring compliance
with policies and regulations.
3. Recommends and participates
in the development and
procedures; may serve on
planning and policy-making
committees.
4. Performs miscellaneous job-
related duties as assigned.
5
Technical
Engineers
17
 BS (Hons)/ B.Sc or equivalent
degree in Civil Engineering
 Work experience of at least 03 years
in Govt. or Semi Govt. Department
or private organizations of national
level.
 Excellent knowledge of design and
visualisations software such as
AutoCAD, Civil 3D or similar.
 Proficiency in site layout, grading,
utility design, erosion control,
regulatory approvals etc.
 Project management and
supervision skills
 Strong communication and
interpersonal skills
 Licence of professional engineer
1. Head of Field Offices.
2. Identify schemes, proposals
in consultation with local
administration, elected reps
and other stakeholders for
promotion of tourism.
3. Undertaking technical and
feasibility studies including
site investigations
4. Compiling job specs and
supervising tendering
procedures
5. Resolving design and
development problems
6. Managing budgets and
project resources
7. Scheduling material and
equipment purchases and
Page 11 of 15
(PEC Number).
 Age Limit: 35 Years
deliveries
8. Making sure the project
complies with legal
requirements
9. Assessing the sustainability
and environmental impact of
projects
10. Ensuring projects run
smoothly and structures are
completed within budget and
on time.
11. Carry out technical and
feasibility studies and draw
up blueprints that satisfy
technical specifications
12. Provide advice and resolve
creatively any emerging
problems/deficiencies
13. Handle over the resulting
structures and services for use
14. Monitor progress and compile
reports in project status
15. Comply with guidelines and
regulations including permits,
safety etc.s and deliver
technical files and other
technical documentation as
required.
6 IT Specialist 17
 Master’s Degree/ B.Sc (Hons) in
Computer Science/IT or equivalent
qualification in the field of
Computer Science from a HEC
recognized university/ institute with
one year Post Graduate Diploma in
GIS from a recognized University/
Institute.
 At least 03 years’ experience in IT
field in Govt. or Semi Govt.
Department or private organizations
of national level.
 Candidates having experience in
GIS Mapping and Spatial Analysis
using GIS software like ESRI
Software will be preferred.
 Age limit: up to 35 years
1.Collects data by identifying
sources of information;
designing survey and
collection methods.
2.Organizes information by
studying, analysing,
interpreting, and classifying
data.
3.Resolves retrieval problems by
altering design to meet
requirements.
4.Prepares reports by collecting,
analysing, and summarizing
information.
5.Prepares reference for users by
writing operating instructions.
6.Maintains historical records by
documenting system changes
and revisions.
7.Contributes to team effort by
accomplishing related results
as needed.
8.Establishes and revises
database by conferring with
Page 12 of 15
analysts and programmers to
code and retrieve data.
7 Assistant 16
 B.A/ B.Sc or equivalent Degree
from a HEC recognized university.
 At least 01 years’ experience in
Govt. or Semi Govt. Department or
private organizations of national
level.
 Any office management related
course (not less than 3 months &
recognized by Board of Technical
Education or any other Govt.
Institute).
 Age Limit: 30 Years
1.Perform the duties of
secretaries or file clerks, such
as filing, Record keeping,
assets management and
maintenance of assets record.
2.Issuance of letters, reports etc.
3.Ensure timely provision of
necessary demands/ items.
4. To monitor the timings of
staff, attendance register.
5.Any other duty assigned by
high ups.
8
Sub.
Engineer
14
 BE/BS/BSc/B.Tech/DAE Civil
Engineering.
 At least 03 years in Govt. or Semi
Govt. Department or private
organizations of national level.
 Excellent knowledge of design and
visualisations software such as
AutoCAD, Civil 3D or similar.
 Able to work independently with
minimum supervision
 Able to meet deadlines in a high
pressure environment.
 Licence of professional engineer
(PEC Number)
 Age Limit: upto 30 Years
1.Regular supervision of
construction works to ensure
completion within stipulated
time.
2.To provide technical guidance
on site as per design, drawing
& specifications.
3.To report regularly to the
Project Manager on all matters
related to the site
4.To arrange the construction
material within required time
and budget for smooth
execution of the project.
5.Prepare & review the work
schedule of different activities
to ensure progress on work.
6.Carry out correspondence with
the Project Manager regarding
any variation order due to
additional works.
7.Any other task assigned by the
supervisor.
9
Computer
Operators
14
 F.Sc. Computer Science. Or
intermediate with DIT from govt.
recognised institute.
 Typing speed 35 WPM.
 At least 01 years’ experience as a
computer operator & data entry post
in govt. or semi govt. or private firm
of national level.
 Any Computer related course (not
less than 3 months & recognized by
Board of Technical Education or
any other Govt. Institute)
 Age Limit: upto 30 Years
1.To ensure accurate and timely
entry of data into the database
2.To ensure proper filing of data.
3.To work according to the
priorities set by high ups.
Page 13 of 15
10
Site
Surveyors
11
 DAE (03 years) Civil Engineering.
 At least 01 years’ experience as a
site surveyors in govt. or semi govt.
or private firm of national level.
 Should have advance knowledge of
current trends and engineering
standards
Age Limit: upto 30 Years
1.Prepare and maintain sketches,
maps, reports, and legal
descriptions of surveys in order
to describe, certify, and assume
liability for work performed.
2.Verify the accuracy of survey
data, including measurements
and calculations conducted at
survey sites.
3.Direct or conduct surveys in
order to establish legal
boundaries for properties, based
on legal deeds and titles.
4.Record the results of surveys,
including the shape, contour,
location, elevation, and
dimensions of land or land
features.
5.Calculate heights, depths,
relative positions, property
lines, and other characteristics
of terrain.
6.Plan and conduct ground
surveys designed to establish
baselines, elevations, and other
geodetic measurements.
7.Search legal records, survey
records, and land titles in order
to obtain information about
property boundaries in areas to
be surveyed.
Page 14 of 15
(Annexure-III)
Capital CostEstimates of Tourism Area Integrated Tourism Development
Unit (TAIDU)
S.
No
Items
Number
Required
Unit Cost Total Cost
1 Desktop PC 5 120,000 600,000
2 Laptops Core I7 10 120,000 1,200,000
3 Photocopier 1 400,000 400,000
4 UPS 1 KVA 5 15,000 75,000
5 Printers laserjet 5 15,000 75,000
6 Scanner 1 10,000 10,000
7 DSLR Professional Camera 1 500,000 500,000
8 Misc. Accessories 1 200,000 200,000
9 Generator 1 800,000 800,000
10 Vehicles with Registration 10 2,000,000 20,000,000
Total 23,860,000
Page 15 of 15
(Annexure-IV)
Operational Cost of Tourism Area Integrated Development Unit
(TAIDU)
Object Head 2016-17 2017-18 2018-19 Total
03000-Other Allowances
03400-Medical Charges 100,000 100,000 100,000 300,000
03400-Conveyance Charges 100,000 100,000 100,000 300,000
03000 Total Other Allowances 200,000 200,000 200,000 400,000
04000-Reapair of Durable Goods
42000-Repair & Maintenance of
Electrical/Electronic Equipment e.g. Computers,
Printers, Tonners etc
50,000 150,000 150,000 350,000
04000-Total Repair & Maintenance of Durable
Goods
50,000 150,000 150,000 200,000
5000-Commodoties Services
51100-TA/DA for entire Staff 1,000,000 1,000,000 1,000,000 3,000,000
51300-POL for Vehicles & Generator 1,000,000 1,000,000 1,000,000 3,000,000
5000-Total Commodities Services 2,000,000 2,000,000 2,000,000 4,000,000
52000-Communication
52100-Postage & Telegram 300,000 300,000 300,000 900,000
52200-Telephone/Fax/Internet/DSL/Utility
Charges
500,000 500,000 500,000 1,500,000
52000-Total Communication 800,000 800,000 800,000 1,600,000
Stationary
54000- Stationery 500,000 500,000 500,000 1,500,000
Total Stationery 500,000 500,000 500,000 1,500,000
59000-Other Expenditure
59500 Advertisement/Promotional/Publicity
Charges
500,000 500,000 500,000 1,500,000
Interior & Exterior Décor/ Renovation 4,000,000 0 0 4,000,000
Rent for Office (Rs. 50,000 P.M x 4 sites) 1,800,000 2,400,000 2,400,000 6,600,000
59900- Other Contingencies 500,000 500,000 500,000 1,500,000
59000-Total Other Expenditure 6,800,000 3,400,000 3,400,000 13,600,000
67000-Entertainment 500,000 500,000 500,000 1,500,000
76000-Total Entertainment 500,000 500,000 500,000 1,500,000
Total Operational Cost 10,850,000 7,550,000 7,550,000 25,950,000
In Million 10.85 7.55 7.55 25.95

More Related Content

What's hot

2010-2013_Izmir_Regional_Plan
2010-2013_Izmir_Regional_Plan2010-2013_Izmir_Regional_Plan
2010-2013_Izmir_Regional_PlanBeg Tatari
 
Tourism development and management plan of bhaktapur district (2012 2016)
Tourism  development and management plan of bhaktapur district (2012 2016)Tourism  development and management plan of bhaktapur district (2012 2016)
Tourism development and management plan of bhaktapur district (2012 2016)Basudev Lamichhane
 
Evaluation of tourism policy 2010
Evaluation of tourism policy 2010Evaluation of tourism policy 2010
Evaluation of tourism policy 2010A B Siddique
 
36317_CV (Revised) Nana Opare-Djan.doc2
36317_CV (Revised) Nana Opare-Djan.doc236317_CV (Revised) Nana Opare-Djan.doc2
36317_CV (Revised) Nana Opare-Djan.doc2Nana Opare-Djan
 
12th year plan of india related with tourism
12th year plan of india related with tourism12th year plan of india related with tourism
12th year plan of india related with tourismjyoti chandani
 
PHD English Report
PHD English ReportPHD English Report
PHD English ReportGhazal Fateh
 
City development plan guwahati
City development plan guwahatiCity development plan guwahati
City development plan guwahatiAnupama Krishnan
 

What's hot (10)

2010-2013_Izmir_Regional_Plan
2010-2013_Izmir_Regional_Plan2010-2013_Izmir_Regional_Plan
2010-2013_Izmir_Regional_Plan
 
U-lead with Europe - eng
U-lead with Europe - engU-lead with Europe - eng
U-lead with Europe - eng
 
Tourism development and management plan of bhaktapur district (2012 2016)
Tourism  development and management plan of bhaktapur district (2012 2016)Tourism  development and management plan of bhaktapur district (2012 2016)
Tourism development and management plan of bhaktapur district (2012 2016)
 
Evaluation of tourism policy 2010
Evaluation of tourism policy 2010Evaluation of tourism policy 2010
Evaluation of tourism policy 2010
 
36317_CV (Revised) Nana Opare-Djan.doc2
36317_CV (Revised) Nana Opare-Djan.doc236317_CV (Revised) Nana Opare-Djan.doc2
36317_CV (Revised) Nana Opare-Djan.doc2
 
12th year plan of india related with tourism
12th year plan of india related with tourism12th year plan of india related with tourism
12th year plan of india related with tourism
 
PHD English Report
PHD English ReportPHD English Report
PHD English Report
 
City development plan guwahati
City development plan guwahatiCity development plan guwahati
City development plan guwahati
 
C0351017030
C0351017030C0351017030
C0351017030
 
jaipur development authority .
 jaipur development authority . jaipur development authority .
jaipur development authority .
 

Similar to Pc i integrated tourism development unitunderrevision201826january18

BANGLADESH TOURISM FOUNDATION
BANGLADESH TOURISM FOUNDATIONBANGLADESH TOURISM FOUNDATION
BANGLADESH TOURISM FOUNDATIONKhaled Hasan
 
Draft of minutes developmental committee
Draft of minutes developmental committeeDraft of minutes developmental committee
Draft of minutes developmental committeehayat alishah
 
Pc i khan pur fery project 12 m
Pc i khan pur fery project 12 mPc i khan pur fery project 12 m
Pc i khan pur fery project 12 mhayat alishah
 
Brief description of Tourism Guidebook for Local Government Units.pdf
Brief description of Tourism Guidebook for Local Government Units.pdfBrief description of Tourism Guidebook for Local Government Units.pdf
Brief description of Tourism Guidebook for Local Government Units.pdfMarissaMalones3
 
Pc i revised umbrella tourism initiatives 2018-19 20-12-2017
Pc i revised umbrella tourism initiatives 2018-19 20-12-2017Pc i revised umbrella tourism initiatives 2018-19 20-12-2017
Pc i revised umbrella tourism initiatives 2018-19 20-12-2017hosting guests
 
Pc i revised umbrella tourism initiatives 2018-19 20-12-2017
Pc i revised umbrella tourism initiatives 2018-19 20-12-2017Pc i revised umbrella tourism initiatives 2018-19 20-12-2017
Pc i revised umbrella tourism initiatives 2018-19 20-12-2017hosting guests
 
SOUTH AFRICA - Corporate Plan 2015_2016 to 2019_2020
SOUTH AFRICA - Corporate Plan 2015_2016 to 2019_2020SOUTH AFRICA - Corporate Plan 2015_2016 to 2019_2020
SOUTH AFRICA - Corporate Plan 2015_2016 to 2019_2020BTO Educational
 
A PROJECT PROPOSAL ON INTERACTIVE TOURISM MAPPING AND PREDICTION OF TOURISTS ...
A PROJECT PROPOSAL ON INTERACTIVE TOURISM MAPPING AND PREDICTION OF TOURISTS ...A PROJECT PROPOSAL ON INTERACTIVE TOURISM MAPPING AND PREDICTION OF TOURISTS ...
A PROJECT PROPOSAL ON INTERACTIVE TOURISM MAPPING AND PREDICTION OF TOURISTS ...Jody Sullivan
 
Pc i 2011-12 15m wing
Pc i  2011-12 15m wingPc i  2011-12 15m wing
Pc i 2011-12 15m winghayat alishah
 
Pc i 2011-12 15m wing (2)
Pc i  2011-12 15m wing (2)Pc i  2011-12 15m wing (2)
Pc i 2011-12 15m wing (2)hayat alishah
 
1 GHANA MINISTRY OF ROADS AND HIGHWAYS 2013
1 GHANA MINISTRY OF ROADS AND HIGHWAYS 20131 GHANA MINISTRY OF ROADS AND HIGHWAYS 2013
1 GHANA MINISTRY OF ROADS AND HIGHWAYS 2013Philip Ryan
 
Stacy five years plan revised only for tourism
Stacy five years plan revised only for tourismStacy five years plan revised only for tourism
Stacy five years plan revised only for tourismhayat alishah
 
Stacy five years_plan_revised_only_for_tourism
Stacy five years_plan_revised_only_for_tourismStacy five years_plan_revised_only_for_tourism
Stacy five years_plan_revised_only_for_tourismhosting guests
 
2011-07-06 Report on investment policy and activities
2011-07-06 Report on investment policy and activities2011-07-06 Report on investment policy and activities
2011-07-06 Report on investment policy and activitiesVasilije Ćetković
 
Stacy five years plan upadatetourismone
Stacy five years plan upadatetourismoneStacy five years plan upadatetourismone
Stacy five years plan upadatetourismonehayat alishah
 
Chuong 1 quy hoach
Chuong 1 quy hoachChuong 1 quy hoach
Chuong 1 quy hoachTan Pham
 
Evaluation of tourism policy 2010
 Evaluation of tourism policy 2010 Evaluation of tourism policy 2010
Evaluation of tourism policy 2010A B Siddique
 

Similar to Pc i integrated tourism development unitunderrevision201826january18 (20)

BANGLADESH TOURISM FOUNDATION
BANGLADESH TOURISM FOUNDATIONBANGLADESH TOURISM FOUNDATION
BANGLADESH TOURISM FOUNDATION
 
Draft of minutes developmental committee
Draft of minutes developmental committeeDraft of minutes developmental committee
Draft of minutes developmental committee
 
Pc i khan pur fery project 12 m
Pc i khan pur fery project 12 mPc i khan pur fery project 12 m
Pc i khan pur fery project 12 m
 
Brief description of Tourism Guidebook for Local Government Units.pdf
Brief description of Tourism Guidebook for Local Government Units.pdfBrief description of Tourism Guidebook for Local Government Units.pdf
Brief description of Tourism Guidebook for Local Government Units.pdf
 
Pc i revised umbrella tourism initiatives 2018-19 20-12-2017
Pc i revised umbrella tourism initiatives 2018-19 20-12-2017Pc i revised umbrella tourism initiatives 2018-19 20-12-2017
Pc i revised umbrella tourism initiatives 2018-19 20-12-2017
 
Pc i revised umbrella tourism initiatives 2018-19 20-12-2017
Pc i revised umbrella tourism initiatives 2018-19 20-12-2017Pc i revised umbrella tourism initiatives 2018-19 20-12-2017
Pc i revised umbrella tourism initiatives 2018-19 20-12-2017
 
SOUTH AFRICA - Corporate Plan 2015_2016 to 2019_2020
SOUTH AFRICA - Corporate Plan 2015_2016 to 2019_2020SOUTH AFRICA - Corporate Plan 2015_2016 to 2019_2020
SOUTH AFRICA - Corporate Plan 2015_2016 to 2019_2020
 
A PROJECT PROPOSAL ON INTERACTIVE TOURISM MAPPING AND PREDICTION OF TOURISTS ...
A PROJECT PROPOSAL ON INTERACTIVE TOURISM MAPPING AND PREDICTION OF TOURISTS ...A PROJECT PROPOSAL ON INTERACTIVE TOURISM MAPPING AND PREDICTION OF TOURISTS ...
A PROJECT PROPOSAL ON INTERACTIVE TOURISM MAPPING AND PREDICTION OF TOURISTS ...
 
Piano Strategico del Turismo 2017-2022 (ENG)
Piano Strategico del Turismo 2017-2022 (ENG)Piano Strategico del Turismo 2017-2022 (ENG)
Piano Strategico del Turismo 2017-2022 (ENG)
 
cARLESPresentation1ProjectTREASURE
cARLESPresentation1ProjectTREASUREcARLESPresentation1ProjectTREASURE
cARLESPresentation1ProjectTREASURE
 
Pc i 2011-12 15m wing
Pc i  2011-12 15m wingPc i  2011-12 15m wing
Pc i 2011-12 15m wing
 
Pc i 2011-12 15m wing (2)
Pc i  2011-12 15m wing (2)Pc i  2011-12 15m wing (2)
Pc i 2011-12 15m wing (2)
 
1 GHANA MINISTRY OF ROADS AND HIGHWAYS 2013
1 GHANA MINISTRY OF ROADS AND HIGHWAYS 20131 GHANA MINISTRY OF ROADS AND HIGHWAYS 2013
1 GHANA MINISTRY OF ROADS AND HIGHWAYS 2013
 
Stacy five years plan revised only for tourism
Stacy five years plan revised only for tourismStacy five years plan revised only for tourism
Stacy five years plan revised only for tourism
 
Stacy five years_plan_revised_only_for_tourism
Stacy five years_plan_revised_only_for_tourismStacy five years_plan_revised_only_for_tourism
Stacy five years_plan_revised_only_for_tourism
 
2011-07-06 Report on investment policy and activities
2011-07-06 Report on investment policy and activities2011-07-06 Report on investment policy and activities
2011-07-06 Report on investment policy and activities
 
HRIDAY Scheme.pptx
HRIDAY Scheme.pptxHRIDAY Scheme.pptx
HRIDAY Scheme.pptx
 
Stacy five years plan upadatetourismone
Stacy five years plan upadatetourismoneStacy five years plan upadatetourismone
Stacy five years plan upadatetourismone
 
Chuong 1 quy hoach
Chuong 1 quy hoachChuong 1 quy hoach
Chuong 1 quy hoach
 
Evaluation of tourism policy 2010
 Evaluation of tourism policy 2010 Evaluation of tourism policy 2010
Evaluation of tourism policy 2010
 

More from hosting guests

Tourism task force updated tariq sab
Tourism task force updated tariq sabTourism task force updated tariq sab
Tourism task force updated tariq sabhosting guests
 
Kp delegation-of-financial-power-rules-2018
Kp delegation-of-financial-power-rules-2018Kp delegation-of-financial-power-rules-2018
Kp delegation-of-financial-power-rules-2018hosting guests
 
Tourism task force final
Tourism task force finalTourism task force final
Tourism task force finalhosting guests
 
Khyber pass economic corridor project p159577 (1)
Khyber pass economic corridor project   p159577 (1)Khyber pass economic corridor project   p159577 (1)
Khyber pass economic corridor project p159577 (1)hosting guests
 
Final implement ppt.03.05.2018
Final implement ppt.03.05.2018Final implement ppt.03.05.2018
Final implement ppt.03.05.2018hosting guests
 
Working paper on 1st off road rally (final)
Working paper on 1st off road rally (final)Working paper on 1st off road rally (final)
Working paper on 1st off road rally (final)hosting guests
 
Draft to rs for dmps clean
Draft to rs for dmps   cleanDraft to rs for dmps   clean
Draft to rs for dmps cleanhosting guests
 
Project management unit for kite project (1)
Project management unit for kite project (1)Project management unit for kite project (1)
Project management unit for kite project (1)hosting guests
 
Tourism task force with input of aftab rana
Tourism task force with input of aftab ranaTourism task force with input of aftab rana
Tourism task force with input of aftab ranahosting guests
 
Performance review benchmarks
Performance review benchmarksPerformance review benchmarks
Performance review benchmarkshosting guests
 
Provision of small machinery
Provision of small machineryProvision of small machinery
Provision of small machineryhosting guests
 
Small scale youth business
Small scale youth businessSmall scale youth business
Small scale youth businesshosting guests
 
Geological mapping 27.04.18 updated (only mapping)
Geological mapping   27.04.18 updated (only mapping)Geological mapping   27.04.18 updated (only mapping)
Geological mapping 27.04.18 updated (only mapping)hosting guests
 

More from hosting guests (20)

Tourism task force updated tariq sab
Tourism task force updated tariq sabTourism task force updated tariq sab
Tourism task force updated tariq sab
 
Kp delegation-of-financial-power-rules-2018
Kp delegation-of-financial-power-rules-2018Kp delegation-of-financial-power-rules-2018
Kp delegation-of-financial-power-rules-2018
 
Tourism task force final
Tourism task force finalTourism task force final
Tourism task force final
 
Khyber pass economic corridor project p159577 (1)
Khyber pass economic corridor project   p159577 (1)Khyber pass economic corridor project   p159577 (1)
Khyber pass economic corridor project p159577 (1)
 
Frame work on tourism
Frame work on tourismFrame work on tourism
Frame work on tourism
 
Final implement ppt.03.05.2018
Final implement ppt.03.05.2018Final implement ppt.03.05.2018
Final implement ppt.03.05.2018
 
Swm wssp
Swm wsspSwm wssp
Swm wssp
 
Working paper on 1st off road rally (final)
Working paper on 1st off road rally (final)Working paper on 1st off road rally (final)
Working paper on 1st off road rally (final)
 
Draft to rs for dmps clean
Draft to rs for dmps   cleanDraft to rs for dmps   clean
Draft to rs for dmps clean
 
Mineral mapping
Mineral mappingMineral mapping
Mineral mapping
 
Project management unit for kite project (1)
Project management unit for kite project (1)Project management unit for kite project (1)
Project management unit for kite project (1)
 
Tourism task force with input of aftab rana
Tourism task force with input of aftab ranaTourism task force with input of aftab rana
Tourism task force with input of aftab rana
 
Performance review benchmarks
Performance review benchmarksPerformance review benchmarks
Performance review benchmarks
 
Wte
WteWte
Wte
 
Strategic roadmap
Strategic roadmapStrategic roadmap
Strategic roadmap
 
Provision of small machinery
Provision of small machineryProvision of small machinery
Provision of small machinery
 
Small scale youth business
Small scale youth businessSmall scale youth business
Small scale youth business
 
Solid waste
Solid wasteSolid waste
Solid waste
 
Geological mapping 27.04.18 updated (only mapping)
Geological mapping   27.04.18 updated (only mapping)Geological mapping   27.04.18 updated (only mapping)
Geological mapping 27.04.18 updated (only mapping)
 
Slf
SlfSlf
Slf
 

Recently uploaded

8377087607 Full Enjoy @24/7 Call Girls in INA Market Dilli Hatt Delhi NCR
8377087607 Full Enjoy @24/7 Call Girls in INA Market Dilli Hatt Delhi NCR8377087607 Full Enjoy @24/7 Call Girls in INA Market Dilli Hatt Delhi NCR
8377087607 Full Enjoy @24/7 Call Girls in INA Market Dilli Hatt Delhi NCRdollysharma2066
 
Inspirational Quotes About Italy and Food
Inspirational Quotes About Italy and FoodInspirational Quotes About Italy and Food
Inspirational Quotes About Italy and FoodKasia Chojecki
 
69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)
69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)
69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)Escort Service
 
Exploring Sicily Your Comprehensive Ebook Travel Guide
Exploring Sicily Your Comprehensive Ebook Travel GuideExploring Sicily Your Comprehensive Ebook Travel Guide
Exploring Sicily Your Comprehensive Ebook Travel GuideTime for Sicily
 
How Safe Is It To Witness Whales In Maui’s Waters
How Safe Is It To Witness Whales In Maui’s WatersHow Safe Is It To Witness Whales In Maui’s Waters
How Safe Is It To Witness Whales In Maui’s WatersMakena Coast Charters
 
(8264348440) 🔝 Call Girls In Nand Nagri 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Nand Nagri 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Nand Nagri 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Nand Nagri 🔝 Delhi NCRsoniya singh
 
"Fly with Ease: Booking Your Flights with Air Europa"
"Fly with Ease: Booking Your Flights with Air Europa""Fly with Ease: Booking Your Flights with Air Europa"
"Fly with Ease: Booking Your Flights with Air Europa"flyn goo
 
5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)
5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)
5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)Mazie Garcia
 
Italia Lucca 1 Un tesoro nascosto tra le sue mura
Italia Lucca 1 Un tesoro nascosto tra le sue muraItalia Lucca 1 Un tesoro nascosto tra le sue mura
Italia Lucca 1 Un tesoro nascosto tra le sue murasandamichaela *
 
VIP Call Girls in Noida 9711199012 Escorts in Greater Noida,Ms
VIP Call Girls in Noida 9711199012 Escorts in Greater Noida,MsVIP Call Girls in Noida 9711199012 Escorts in Greater Noida,Ms
VIP Call Girls in Noida 9711199012 Escorts in Greater Noida,Msankitnayak356677
 
Apply Indian E-Visa Process Online (Evisa)
Apply Indian E-Visa Process Online (Evisa)Apply Indian E-Visa Process Online (Evisa)
Apply Indian E-Visa Process Online (Evisa)RanjeetKumar108130
 
Where to Stay in Lagos, Portugal.pptxasd
Where to Stay in Lagos, Portugal.pptxasdWhere to Stay in Lagos, Portugal.pptxasd
Where to Stay in Lagos, Portugal.pptxasdusmanghaniwixpatriot
 
Dubai Call Girls O528786472 Call Girls Dubai Big Juicy
Dubai Call Girls O528786472 Call Girls Dubai Big JuicyDubai Call Girls O528786472 Call Girls Dubai Big Juicy
Dubai Call Girls O528786472 Call Girls Dubai Big Juicyhf8803863
 
Moving to Italy - A Relocation Rollercoaster
Moving to Italy - A Relocation RollercoasterMoving to Italy - A Relocation Rollercoaster
Moving to Italy - A Relocation RollercoasterStefSmulders1
 
Aeromexico Airlines Flight Name Change Policy
Aeromexico Airlines Flight Name Change PolicyAeromexico Airlines Flight Name Change Policy
Aeromexico Airlines Flight Name Change PolicyFlyFairTravels
 
Call Girls In Panjim Mariott Resort ₰8588052666₰ North ...
Call Girls In Panjim Mariott Resort ₰8588052666₰ North ...Call Girls In Panjim Mariott Resort ₰8588052666₰ North ...
Call Girls In Panjim Mariott Resort ₰8588052666₰ North ...nishakur201
 
Revolutionalizing Travel: A VacAI Update
Revolutionalizing Travel: A VacAI UpdateRevolutionalizing Travel: A VacAI Update
Revolutionalizing Travel: A VacAI Updatejoymorrison10
 
Haitian culture and stuff and places and food and travel.pptx
Haitian culture and stuff and places and food and travel.pptxHaitian culture and stuff and places and food and travel.pptx
Haitian culture and stuff and places and food and travel.pptxhxhlixia
 

Recently uploaded (20)

8377087607 Full Enjoy @24/7 Call Girls in INA Market Dilli Hatt Delhi NCR
8377087607 Full Enjoy @24/7 Call Girls in INA Market Dilli Hatt Delhi NCR8377087607 Full Enjoy @24/7 Call Girls in INA Market Dilli Hatt Delhi NCR
8377087607 Full Enjoy @24/7 Call Girls in INA Market Dilli Hatt Delhi NCR
 
Inspirational Quotes About Italy and Food
Inspirational Quotes About Italy and FoodInspirational Quotes About Italy and Food
Inspirational Quotes About Italy and Food
 
69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)
69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)
69 Girls ✠ 9599264170 ✠ Call Girls In East Of Kailash (VIP)
 
Exploring Sicily Your Comprehensive Ebook Travel Guide
Exploring Sicily Your Comprehensive Ebook Travel GuideExploring Sicily Your Comprehensive Ebook Travel Guide
Exploring Sicily Your Comprehensive Ebook Travel Guide
 
How Safe Is It To Witness Whales In Maui’s Waters
How Safe Is It To Witness Whales In Maui’s WatersHow Safe Is It To Witness Whales In Maui’s Waters
How Safe Is It To Witness Whales In Maui’s Waters
 
(8264348440) 🔝 Call Girls In Nand Nagri 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Nand Nagri 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Nand Nagri 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Nand Nagri 🔝 Delhi NCR
 
"Fly with Ease: Booking Your Flights with Air Europa"
"Fly with Ease: Booking Your Flights with Air Europa""Fly with Ease: Booking Your Flights with Air Europa"
"Fly with Ease: Booking Your Flights with Air Europa"
 
5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)
5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)
5S - House keeping (Seiri, Seiton, Seiso, Seiketsu, Shitsuke)
 
Italia Lucca 1 Un tesoro nascosto tra le sue mura
Italia Lucca 1 Un tesoro nascosto tra le sue muraItalia Lucca 1 Un tesoro nascosto tra le sue mura
Italia Lucca 1 Un tesoro nascosto tra le sue mura
 
VIP Call Girls in Noida 9711199012 Escorts in Greater Noida,Ms
VIP Call Girls in Noida 9711199012 Escorts in Greater Noida,MsVIP Call Girls in Noida 9711199012 Escorts in Greater Noida,Ms
VIP Call Girls in Noida 9711199012 Escorts in Greater Noida,Ms
 
Apply Indian E-Visa Process Online (Evisa)
Apply Indian E-Visa Process Online (Evisa)Apply Indian E-Visa Process Online (Evisa)
Apply Indian E-Visa Process Online (Evisa)
 
Where to Stay in Lagos, Portugal.pptxasd
Where to Stay in Lagos, Portugal.pptxasdWhere to Stay in Lagos, Portugal.pptxasd
Where to Stay in Lagos, Portugal.pptxasd
 
Dubai Call Girls O528786472 Call Girls Dubai Big Juicy
Dubai Call Girls O528786472 Call Girls Dubai Big JuicyDubai Call Girls O528786472 Call Girls Dubai Big Juicy
Dubai Call Girls O528786472 Call Girls Dubai Big Juicy
 
Moving to Italy - A Relocation Rollercoaster
Moving to Italy - A Relocation RollercoasterMoving to Italy - A Relocation Rollercoaster
Moving to Italy - A Relocation Rollercoaster
 
Aeromexico Airlines Flight Name Change Policy
Aeromexico Airlines Flight Name Change PolicyAeromexico Airlines Flight Name Change Policy
Aeromexico Airlines Flight Name Change Policy
 
Enjoy ➥8448380779▻ Call Girls In Sector 62 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 62 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 62 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 62 Noida Escorts Delhi NCR
 
Call Girls In Panjim Mariott Resort ₰8588052666₰ North ...
Call Girls In Panjim Mariott Resort ₰8588052666₰ North ...Call Girls In Panjim Mariott Resort ₰8588052666₰ North ...
Call Girls In Panjim Mariott Resort ₰8588052666₰ North ...
 
Revolutionalizing Travel: A VacAI Update
Revolutionalizing Travel: A VacAI UpdateRevolutionalizing Travel: A VacAI Update
Revolutionalizing Travel: A VacAI Update
 
Enjoy ➥8448380779▻ Call Girls In Sector 74 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 74 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 74 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 74 Noida Escorts Delhi NCR
 
Haitian culture and stuff and places and food and travel.pptx
Haitian culture and stuff and places and food and travel.pptxHaitian culture and stuff and places and food and travel.pptx
Haitian culture and stuff and places and food and travel.pptx
 

Pc i integrated tourism development unitunderrevision201826january18

  • 1. GOVERNMENT OF KHYBER PAKHTUNKHWA REVISED UMBRELLA PC-I “Tourism Area Integrated Development Project (Establishment of Provincial Tourism Authority)” ADP No. 1397/160584 FY-2017-18 Total Cost Rs. 2714.610 Million SPORTS, TOURISM, ARCHAEOLOGY, MUSEUMS, CULTURE & YOUTH AFFAIRS DEPARTMENT
  • 2. Page 2 of 15 PC-1 FORM 1. Name of the Project “Tourism Area Integrated Development Project (Establishment of Provincial Tourism Authority)” ADP No. 1397/150472 2. Location Sports, Tourism, Archaeology, Museums, Culture & Youth Affair Department 3. Authority responsible for: i. Sponsoring ii. Execution iii. O & M i. Sports, Tourism, Archaeology, Museums, Culture & Youth Affair Department Govt. of Khyber Pakhtunkhwa. ii. Tourism Department Govt. of Khyber Pakhtunkhwa iii.Tourism Department Govt. of Khyber Pakhtunkhwa 4. Plan Provision The scheme was included in ADP vide Computer No. 160584 at a total cost of Rs. 2500 Million which has been revised to Rs. 2714.610 million on the revenue side for implementation by the Tourism Area Integrated Development Unit of the Department. 5. Project objectives and its relationship with Sectoral objectives Khyber Pakhtunkhwa is generally recognized as the tourism hub of Pakistan, with its beautiful valleys, lakes, archaeological sites, historic remains, rivers, mountains, glaciers, civilizations, culture and people. Efforts have resulted in promotion of tourism in this province but have not been able to fully explore the tourism potential of the province. There are many causes normally referred for under- development of the tourism in the province, however, the chief indicators are lack of motivation, lack of political will, low priority accorded by the government, meagre financial resource allocations and prevailing inadequate tourism organizational structure. The proposed project for Integrated Tourism Area Development Project will assist Khyber Pakhtunkhwa in better designing and implementing a management approach to promote environmentally sound tourism development and reduce ecological degradation through enhancing environmental protection, spatial development, institutional capacity and governance of the area. The project objectives are in line with sectoral priorities of institutional strengthening and capacity building, studies and research as given in Khyber Pakhtunkhwa Comprehensive Development Strategy 2010-2017. 6. Description, justification and technical parameters Description The project entails:  Establishment of ‘Tourism Area Integrated Development Unit’ in Tourism Department for formulation and implementation of management plans for promotion, development and uplift of tourism related areas.  Block allocation for implementing area development projects at tourism related areas.  Necessary development/ spadework for “Establishment of Provincial Tourism Authority”. Justification Tourism Corporation Khyber Pakhtunkhwa (TCKP) is assigned with the total responsibility for promotion of tourism activities.
  • 3. Page 3 of 15 The Corporation acts as a field wing of the Tourism Department. However due to introduction of new avenues and establishment of area development authorities like Kalam Development Authority, Malakand Development Authority etc the Tourism Department has added responsibility to plan and execute tourism related projects. Tourism Area Integrated Development Project is a concept based on the analogy of Urban Development Unit & Special Area Development Unit to develop those areas where tourism is only or main source of income generation. These interventions will help not only in uplift of the socio-economic life standard of locals but also allows all stakeholders involved in tourism industry to benefit equally. Key features of this project will include:  A full-fledged Tourism Area Integrated Development Unit to plan, develop, execute and monitor projects benefiting development of tourism.  Development of tourist facilities in areas with tourist potential where private sector is shy to invest.  Develop/ prepare plans for development of tourist areas by involving all stakeholders.  Provide a launch pad to the private sector organizations in the areas of hotel management, consultancies, leisure organization etc.  Promotion and development of tourism in province.  Coordination of provincial tourism plans and activities.  Publicity within the country and abroad.  Interacting international organizations and conducting agreements relating to tourism.  Facilitation of travel for tourists.  Training and research in tourism. Technical Parameters: Once initiated, the project will be managed by a central unit with field offices at Swat for Malakand Division, at Abbottabad for Hazara Division and at D.I. Khan for Southern Areas. The Unit combines the technical capabilities to deliver the project in a fruitful manner while field offices will provide technical support for planned interventions. It will be a three years project and staff will be hired both on project policy moreover suitable government servants can also be posted in this project on deputation basis as per policy. The Unit will be headed by Project Director TAIDU who will report to Additional Secretary Tourism Department through Managing Director TCKP (Organogram of the Unit is Annexed). Planning & Design Mechanism: The project will caters for development/ uplift schemes to be identified by project technical staff based at head office and field offices in consultation with all relevant stakeholders i.e. govt. departments, district/ divisional administration, local MNA/ MPA, private sector and general public. All such schemes will be executed under this umbrella PC-I after approval of competent forum.
  • 4. Page 4 of 15 Scheme Execution Mechanism: For execution of the schemes identified TAIDU will hire consultants on open competitive bidding on the analogy of “Project Coordination Unit” of Police Department. The Consultant so hired will do all work from planning, preparation of PC-I to implementation and execution. Technical staff of TAIDU will perform the routine monitoring duties and Departmental Monitoring Committee will be responsible to review performance of each scheme on monthly basis. Scheme Selection/ Approval/ Monitoring Mechanism: A Departmental Monitoring Committee headed by Secretary Tourism Department and assisted by MD TCKP, Manager Accounts TCKP, Incharge Engineering Wing & Project Director (TAIDU) will be constituted to identify/ evaluate proposals submitted by field offices/ head office. After identification the same will be recommended to Project Steering Committee. This Committee will also be responsible for financial and technical monitoring of the each project every month as well as will serve as Project Consultant Selection Committee (PCSC) who will select consultant for identification, execution & implementation of proposals approved by the Competent Forum. Project Steering Committee: The following Committee will be constituted as Project Steering Committee to steer the project: 1. ACS P&D Chairman 2. Secretary Tourism Department Member 3. Secretary LG&RDD Member 4. Deputy Commissioner (Concerned) Member 5. Managing Director (TCKP) Member 6. Project Director (TAIDU) Member cum Secretary TORs of the Committee are as under::  To approve the schemes identified by the Departmental Monitoring Committee for further processing of DDWP/ PDWP.  To review the project performance after 3 months.  To take any other policy decision for smooth functioning of project. Funds allocated/ released for this project will be managed by Accounts/ Finance Officer of the project under relevant rules. Establishment of Provincial Tourism Authority: Tourism Department and TCKP will take all necessary steps for establishment of PTA. The activities undertaken in this scheme will be later be overtaken by PTA.
  • 5. Page 5 of 15 7.Capital Cost Estimates 8. Annual Operating & Maintenance Cost After Completion Of Project The project will be shifted to current side after completion and fulfilment of objectives. Details of Capital and Operational Cost is at Annex-III & IV respectively. 9. Demand and Supply Analysis Currently the department has no specific setup to assess, identify and develop the potential areas where tourism can become main livelihood/ economic development tool. Incorporating this scheme will lead to uplifting of tourism in a systematic way. 10. Financial Plan and mode of financing ADP 2016-17 onwards 11. Project benefits and analysis. Financial: N/A Social benefits with indicators: Provision of facilities in tourism oriented areas will create soft image of the province. Moreover it has a trickledown effect over the society in the form of creating awareness regarding the tourism, promoting cultural heritage, archaeological awareness etc. Employment Generation (direct and indirect): Creation of TAIDU will result in direct employment. Uplift and provision of necessary facilities through this scheme will create economic generation opportunities in the target areas. Environmental Impact: Environmental Specialist hired under this project will also assess and identify ways & means to preserve environment and natural resources. Impact of delays on project cost and viability: Any delay in the project execution will lead to cost and time overrun. Total Revised Difference 1 HR Cost 48.760 68.380 19.62 2 Capital Cost 26.430 26.430 - 3 Operational Cost 25.950 25.950 - 4 Establishment of PTA 13.000 13.000 - 5 Block Allocation for Developmental Activities 2,386.000 2580.540 - 5.1 Sub Component Kalam (1,263.000) (1,492.520) 229.52 5.2 Sub Component Naran (511.000) (657.380) 164.38 5.3 Sub Component Chitral - (375.360) - 5.4 Sub Component Buner - (55.280) - 6 Total (Rs. in Million) 2,500.140 2,714.610 214.470 7 Total Expenditure as of 31/12/2017, since start 897.500 Total Financial Implications (2016-17-18-19) Rs. in MillionS # Name of Component
  • 6. Page 6 of 15 Furthermore the project objectives will not be achieved in time and the quality of work will be compromised and the projects as ever will not be completed in time. 12. Implementation schedule Starting Date: From issuance of the A.A Ending Date: 30th June 2019 13. Management structure & manpower requirements including Specialized skills during execution and operational phases Management structure and manpower requirements including specialized skills during execution and operational phases is given at Annex-I. While the qualifications and job descriptions are at Annex-II. 14.Additional projects/decisions required to maximize socio- economic benefits from the proposed project Since this is the first ever project which is to be implemented at the provincial level, therefore, its sustainability in the long run is imperative. For the purpose the project after completion needs to be regularised through current budget. 15. Certified that the project proposal has been prepared on the basis of instructions provided by the Planning Commission for the preparation of PC- I for Social Sector projects. Prepared by: Planning Officer Sports, Tourism, Archaeology, Museums, Culture & Youth Affair Department Checked by: Chief Planning Officer Sports, Tourism, Archaeology, Museums, Culture & Youth Affair Department Secretary Sports, Tourism, Archaeology, Museums, Culture & Youth Affair Department Approved by: PDWP
  • 7. Page 7 of 15 (Annexure-I) S. # Post & Designation BPS No. of Posts Monthly Salary 2016-17 (9 Months) Annual Increase 2017-18 2017-18 (with increase) Annual Increase 2018-19 2018-19 (with increase) Total 1 Project Director 19 1 175,000 1,575,000 105,000 2,205,000 105,000 2,310,000 6,090,000 2 Dy. Project Director 18 1 125,000 1,125,000 75,000 1,575,000 75,000 1,650,000 4,350,000 3 Assistant Director 17 2 90,000 1,620,000 54,000 2,268,000 54,000 2,322,000 6,210,000 4 Assistant Director (Accounts & Finance) 17 1 90,000 810,000 54,000 1,134,000 54,000 1,188,000 3,132,000 5 M&E Officer 17 1 90,000 810,000 54,000 1,134,000 54,000 1,188,000 3,132,000 6 Technical Engineers 17 4 90,000 3,240,000 54,000 4,536,000 54,000 4,590,000 12,366,000 7 IT/ GIS Specialist 17 1 90,000 810,000 54,000 1,134,000 54,000 1,188,000 3,132,000 8 Assistant 16 3 60,000 1,620,000 36,000 2,268,000 36,000 2,304,000 6,192,000 9 Sub. Engi 14 3 40,000 1,080,000 24,000 1,512,000 24,000 1,536,000 4,128,000 10 Computer Operators 14 3 40,000 1,080,000 24,000 1,512,000 24,000 1,536,000 4,128,000 11 Junior Clerk 14 5 40,000 1,800,000 24,000 2,520,000 24,000 2,544,000 6,864,000 12 Site Surveyors 14 3 40,000 1,080,000 24,000 1,512,000 24,000 1,536,000 4,128,000 13 Drivers 5 1 20,000 180,000 12,000 252,000 12,000 264,000 696,000 14 Naib Qasid 2 7 16,000 1,008,000 9,600 1,411,200 9,600 1,420,800 3,840,000 Total 36 1,006,000 17,838,000 24,973,200 25,576,800 68,388,000 HR Cost of Tourism Development Unit (TAIDU)
  • 8. Page 8 of 15 (Annexure-II) STAFF QUALIFICATION S. # Post & Designation BPS Job Specifications (required education skills) Job Description (duties) 1 Project Director 19  Master’s degree in Social Sciences/ Management Sciences or any other relevant field.  Work experience of at least 12 years in govt. setup and management of multiple projects as a leader.  Proficiency in the use of computer.  Retired Civil/ Military Officers (not below BPS-18 at the time of retirement) will be preferred. 1.Direct, coordinate, and lead activities 2.Responsible for the performance of all his subordinates. 3.Analyse the future needs of resources or new projects for risk management and give recommendations in advance. 4.Recognize and solve potential problems and evaluate project effectiveness. 5.Outline work plan to assign duties, responsibilities, and scope of authority. 6.Accomplishes special project results by identifying and clarifying issues and priorities, communicating and coordinating requirements, expediting fulfilment, evaluating milestone accomplishments, evaluating optional courses of action, changing assumptions and directions. 7.Guides management and employee actions by researching, developing, deciding, and updating policies, procedures, methods, and guidelines; communicating and enforcing organization values. 8.Network with local, regional, state and national agencies; and private sector business interests for future program development. 9.Making sure that each stage is progressing on time, on budget and to the right quality standards. 10. Take final decision on the assignment 2 Deputy Project Director 18  Master’s in Project Management or Business Administration or Social Sciences. 1.Work with Project Director in strategic planning & project management in order to achieve project objectives.
  • 9. Page 9 of 15  Work experience of at least 05 years in Govt. or Semi Govt. Department or private organizations of national level.  Having Computer Proficiency.  Analytical Skills  Team building skill  Risk management skill.  Effective communication skills and interpersonal skills.  Decision making skills.  Age Limit: 40 Years 2.Attend and participate in professional group meetings, be connected with other interested organizations & provide answers to their inquiries about relevant project issues. 3.Deputy Project Director will assist Project Director in management of project activities. 4.Regularly report to Project Director about the progress of the project & inform him about any variances from project objectives. 5.Supervise, direct & control the activities of Assistant Manager & check their progress towards objectives of the project. 6.Will participate in project strategic planning & help in implementation of policies & procedures approved. 7.Will act as Project Director in his absence. 3 Assistant Director 17  Master’s/ B.Sc (Hons) or equivalent degree in Project Management or Business Administration or Social Sciences.  Work experience of at least 03 years in Govt. or Semi Govt. Department or private organizations of national level.  Any Office Management related course (not less than 3 months & recognized by Board of Technical Education or any other Govt. Institute)  Strong communication and interpersonal skills are required  He should be efficient in general management of tasks and having good persuasive skills.  Ability to perform the essential duties and responsibilities with in time and work in the  Stressful conditions effectively.  Age Limit: 35 Years 1.Direct basic office management functions that may include technical and functional supervision of others 2.Monitor and coordinate the daily operation of assigned project or department; perform Administrative detail work and maintain appropriate records and statistics. 3.Measure operational staff activities to standards & if deficiency exist provide training or go for new recruitment. 4.Assist in the development of new strategic plans & recommend modifications in existing plans in order to achieve the objective. 5.Assist in the preparation of a budget; prepare budget recommendations relative to assigned areas of responsibility; research past expenditures and project next year increases. 6.Provide responsible
  • 10. Page 10 of 15 paraprofessional and technical assistance in the analysis, implementation, and monitoring of department planes, investigate, analyse, develop and prepare special studies and planes as per the need of department. 4 Assistant Director (Accounts & Finance) 17  Masters/ B.Sc (Hons) or equivalent Degree in Finance or Accounts or Management Sciences or Economics from a HEC recognized university.  Work experience of at least 03 years in Govt. or Semi Govt. Department or private organizations of national level.  Any finance/ accounts related course (not less than 3 months & recognized by Board of Technical Education or any other Govt. Institute)  Advanced knowledge of public sector financial, accounting, and budgeting principles and procedures.  Knowledge of a range of automated financial systems and applications software.  Knowledge of computerized information systems used in financial and/or accounting applications.  Age Limit: 35 Years 1.Prepares financial statements at the organizational level; prepares fiscal and budget reports for internal management and external agencies. 2. Oversees the approval and processing of accounts, expenditure, and position control documents, ledger and account maintenance and data entry, ensuring compliance with policies and regulations. 3. Recommends and participates in the development and procedures; may serve on planning and policy-making committees. 4. Performs miscellaneous job- related duties as assigned. 5 Technical Engineers 17  BS (Hons)/ B.Sc or equivalent degree in Civil Engineering  Work experience of at least 03 years in Govt. or Semi Govt. Department or private organizations of national level.  Excellent knowledge of design and visualisations software such as AutoCAD, Civil 3D or similar.  Proficiency in site layout, grading, utility design, erosion control, regulatory approvals etc.  Project management and supervision skills  Strong communication and interpersonal skills  Licence of professional engineer 1. Head of Field Offices. 2. Identify schemes, proposals in consultation with local administration, elected reps and other stakeholders for promotion of tourism. 3. Undertaking technical and feasibility studies including site investigations 4. Compiling job specs and supervising tendering procedures 5. Resolving design and development problems 6. Managing budgets and project resources 7. Scheduling material and equipment purchases and
  • 11. Page 11 of 15 (PEC Number).  Age Limit: 35 Years deliveries 8. Making sure the project complies with legal requirements 9. Assessing the sustainability and environmental impact of projects 10. Ensuring projects run smoothly and structures are completed within budget and on time. 11. Carry out technical and feasibility studies and draw up blueprints that satisfy technical specifications 12. Provide advice and resolve creatively any emerging problems/deficiencies 13. Handle over the resulting structures and services for use 14. Monitor progress and compile reports in project status 15. Comply with guidelines and regulations including permits, safety etc.s and deliver technical files and other technical documentation as required. 6 IT Specialist 17  Master’s Degree/ B.Sc (Hons) in Computer Science/IT or equivalent qualification in the field of Computer Science from a HEC recognized university/ institute with one year Post Graduate Diploma in GIS from a recognized University/ Institute.  At least 03 years’ experience in IT field in Govt. or Semi Govt. Department or private organizations of national level.  Candidates having experience in GIS Mapping and Spatial Analysis using GIS software like ESRI Software will be preferred.  Age limit: up to 35 years 1.Collects data by identifying sources of information; designing survey and collection methods. 2.Organizes information by studying, analysing, interpreting, and classifying data. 3.Resolves retrieval problems by altering design to meet requirements. 4.Prepares reports by collecting, analysing, and summarizing information. 5.Prepares reference for users by writing operating instructions. 6.Maintains historical records by documenting system changes and revisions. 7.Contributes to team effort by accomplishing related results as needed. 8.Establishes and revises database by conferring with
  • 12. Page 12 of 15 analysts and programmers to code and retrieve data. 7 Assistant 16  B.A/ B.Sc or equivalent Degree from a HEC recognized university.  At least 01 years’ experience in Govt. or Semi Govt. Department or private organizations of national level.  Any office management related course (not less than 3 months & recognized by Board of Technical Education or any other Govt. Institute).  Age Limit: 30 Years 1.Perform the duties of secretaries or file clerks, such as filing, Record keeping, assets management and maintenance of assets record. 2.Issuance of letters, reports etc. 3.Ensure timely provision of necessary demands/ items. 4. To monitor the timings of staff, attendance register. 5.Any other duty assigned by high ups. 8 Sub. Engineer 14  BE/BS/BSc/B.Tech/DAE Civil Engineering.  At least 03 years in Govt. or Semi Govt. Department or private organizations of national level.  Excellent knowledge of design and visualisations software such as AutoCAD, Civil 3D or similar.  Able to work independently with minimum supervision  Able to meet deadlines in a high pressure environment.  Licence of professional engineer (PEC Number)  Age Limit: upto 30 Years 1.Regular supervision of construction works to ensure completion within stipulated time. 2.To provide technical guidance on site as per design, drawing & specifications. 3.To report regularly to the Project Manager on all matters related to the site 4.To arrange the construction material within required time and budget for smooth execution of the project. 5.Prepare & review the work schedule of different activities to ensure progress on work. 6.Carry out correspondence with the Project Manager regarding any variation order due to additional works. 7.Any other task assigned by the supervisor. 9 Computer Operators 14  F.Sc. Computer Science. Or intermediate with DIT from govt. recognised institute.  Typing speed 35 WPM.  At least 01 years’ experience as a computer operator & data entry post in govt. or semi govt. or private firm of national level.  Any Computer related course (not less than 3 months & recognized by Board of Technical Education or any other Govt. Institute)  Age Limit: upto 30 Years 1.To ensure accurate and timely entry of data into the database 2.To ensure proper filing of data. 3.To work according to the priorities set by high ups.
  • 13. Page 13 of 15 10 Site Surveyors 11  DAE (03 years) Civil Engineering.  At least 01 years’ experience as a site surveyors in govt. or semi govt. or private firm of national level.  Should have advance knowledge of current trends and engineering standards Age Limit: upto 30 Years 1.Prepare and maintain sketches, maps, reports, and legal descriptions of surveys in order to describe, certify, and assume liability for work performed. 2.Verify the accuracy of survey data, including measurements and calculations conducted at survey sites. 3.Direct or conduct surveys in order to establish legal boundaries for properties, based on legal deeds and titles. 4.Record the results of surveys, including the shape, contour, location, elevation, and dimensions of land or land features. 5.Calculate heights, depths, relative positions, property lines, and other characteristics of terrain. 6.Plan and conduct ground surveys designed to establish baselines, elevations, and other geodetic measurements. 7.Search legal records, survey records, and land titles in order to obtain information about property boundaries in areas to be surveyed.
  • 14. Page 14 of 15 (Annexure-III) Capital CostEstimates of Tourism Area Integrated Tourism Development Unit (TAIDU) S. No Items Number Required Unit Cost Total Cost 1 Desktop PC 5 120,000 600,000 2 Laptops Core I7 10 120,000 1,200,000 3 Photocopier 1 400,000 400,000 4 UPS 1 KVA 5 15,000 75,000 5 Printers laserjet 5 15,000 75,000 6 Scanner 1 10,000 10,000 7 DSLR Professional Camera 1 500,000 500,000 8 Misc. Accessories 1 200,000 200,000 9 Generator 1 800,000 800,000 10 Vehicles with Registration 10 2,000,000 20,000,000 Total 23,860,000
  • 15. Page 15 of 15 (Annexure-IV) Operational Cost of Tourism Area Integrated Development Unit (TAIDU) Object Head 2016-17 2017-18 2018-19 Total 03000-Other Allowances 03400-Medical Charges 100,000 100,000 100,000 300,000 03400-Conveyance Charges 100,000 100,000 100,000 300,000 03000 Total Other Allowances 200,000 200,000 200,000 400,000 04000-Reapair of Durable Goods 42000-Repair & Maintenance of Electrical/Electronic Equipment e.g. Computers, Printers, Tonners etc 50,000 150,000 150,000 350,000 04000-Total Repair & Maintenance of Durable Goods 50,000 150,000 150,000 200,000 5000-Commodoties Services 51100-TA/DA for entire Staff 1,000,000 1,000,000 1,000,000 3,000,000 51300-POL for Vehicles & Generator 1,000,000 1,000,000 1,000,000 3,000,000 5000-Total Commodities Services 2,000,000 2,000,000 2,000,000 4,000,000 52000-Communication 52100-Postage & Telegram 300,000 300,000 300,000 900,000 52200-Telephone/Fax/Internet/DSL/Utility Charges 500,000 500,000 500,000 1,500,000 52000-Total Communication 800,000 800,000 800,000 1,600,000 Stationary 54000- Stationery 500,000 500,000 500,000 1,500,000 Total Stationery 500,000 500,000 500,000 1,500,000 59000-Other Expenditure 59500 Advertisement/Promotional/Publicity Charges 500,000 500,000 500,000 1,500,000 Interior & Exterior Décor/ Renovation 4,000,000 0 0 4,000,000 Rent for Office (Rs. 50,000 P.M x 4 sites) 1,800,000 2,400,000 2,400,000 6,600,000 59900- Other Contingencies 500,000 500,000 500,000 1,500,000 59000-Total Other Expenditure 6,800,000 3,400,000 3,400,000 13,600,000 67000-Entertainment 500,000 500,000 500,000 1,500,000 76000-Total Entertainment 500,000 500,000 500,000 1,500,000 Total Operational Cost 10,850,000 7,550,000 7,550,000 25,950,000 In Million 10.85 7.55 7.55 25.95