Proposed Bridge over the Preston River in East Bunbury, Western Australia
Kyawt Yamin Thwin -700020607 Khant Htut Lwin -700020600
Toe Myint Naing -700020605 Anthony Mak Chao Jun -700014760
Project Background
A new bridge is required to replace an existing bridge which crosses
over the Preston River in Bunbury, Western Australia. The prosed
bridge types is cable-stayed bridge.
Key objective and client’s intent
• to optimize between the bridge aesthetics and the
construction cost and time.
• Minimis environmental impact
Relevant Standards and Design Specification
• AS 3600_2018: Austria Standard Concrete Structure
• AS 5100.1_2017: Austria Standard: Bridge Design: Scope
and General Principles
• AS 5100.2_2017: Austria Standard: Bridge Design: Design
Loads
• AS 5100.5_2017: Austria Standard: Bridge Design: Concrete
Construction method
Preliminary Drawing
Site preparation
1. Demolition
2. Removing asbestos
3. Site Clearing
4. Site surveying and set out
5. Earthwork
Substructure
1. Initiate the caisson system
2. Pump out water
3. Drive piles into the ground according to design
4. Assemble footing according to design.
5. Erect piers to designated level.
Superstructure
1. Erect pylons and girder simultaneously fixing it to the piers.
2. Initiate balanced free cantilevering system using derrick cranes
3.
Install stay cables stressing it to relieve the bending moments in
the girders
4. Install final stay cables
Item Detail Justification
Bride span 66 meters • Estimated from Google Maps.
Bridge type Cable-stayed Bridge • Less steel cable, faster to build n incorporate more precast concrete section
• Higher stiffness and display smaller deflections than suspension bridges
Pylon 12 m • Optimal Height of pylon that can comply with 0.25 𝑙
• The higher the tower above the road level, the lower the cable forces and the
required quantity of cable steel.
2 number • A single tower design cost more and the height of tower need to be higher than that
of twin tower. Single tower height of pylon must comply with 1.8 𝑙
20 m from left edge • The side span of the cable stayed bridge shell be about 0.42 time that of the main
span.
• Pylon was in the between of the main span 46m and the side span 20m.
Cable Semi-harp shape cable configuration • The structure’s aesthetics is really pleasing
3 numbers at each tower • to reduce the bending moments of the beam
• decrease the individual cable forces to be anchored.
15m c/c on deck • By adjusting the angle of the stay (α) nearer to the pylon, the required stay cables
size will decrease, and the height of pylon will increase
1 m c/c on tower • To develop semi-harp shape arrangement of cables
• Easy to maintain
Footing Pile footing • Drilled pile footing
• Pile cap
Preliminary design
Cable Cable Force (P) No. of stands
Cable 1 3153.55 kN 67 nos
Cable 2 5256.02 kN 111 nos
Cable 3 6713.74 kN 142 nos
Construction cost
Specifications Total cost Cost per Area Price Index
2020
Cost per Area
(Proposed Bridge)
Total Cost 2020
ANZAC Bridge
(Pyrmontm,
New South
Wales,
Australia)
Width: 32m
Length: 805m
Longest Span: 345m
Year of Complete: 1995
AUD 170 million AUD 6,599.38 260% AUD 17,142.16 AUD 18.1 million
Eleanor
Schonell Bridge
(Dutton Park,
Queensland,
Australia)
Width: 20m
Length: 390m
Longest Span: 183m
Year of Complete: 2006
AUD 56 million AUD 7,179.49 142% AUD 10,195.10 AUD 10.8 million
Reference:
“Design and Analysis of Cable Stayed Bridge” 2017 -Murkute U.T.
“Cable Stayed Bridges With Prestressed Concrete”- Fritz Leonhardt
Project Timeline

More Related Content

What's hot

design of steel flyover
design of steel flyoverdesign of steel flyover
design of steel flyoverPeer Mohideen
 
PIS Obajana - Cement Factory
PIS Obajana - Cement FactoryPIS Obajana - Cement Factory
PIS Obajana - Cement FactorySven Maedler
 
Case Study_Lake Windermere Great Britain_GB
Case Study_Lake Windermere Great Britain_GBCase Study_Lake Windermere Great Britain_GB
Case Study_Lake Windermere Great Britain_GBStefanie Straubert
 
Repair Options for Concrete Roadways
Repair Options for Concrete RoadwaysRepair Options for Concrete Roadways
Repair Options for Concrete RoadwaysJill Reeves
 
IRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing TechniqueIRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing TechniqueIRJET Journal
 
What are Highways Works, Street works, Road works and Diversionary Works
What are Highways Works, Street works, Road works and Diversionary WorksWhat are Highways Works, Street works, Road works and Diversionary Works
What are Highways Works, Street works, Road works and Diversionary WorksCarlo Gabriele Borri MACostE AMICE
 
Access Engineering PLC - Training Presentation
Access Engineering PLC - Training PresentationAccess Engineering PLC - Training Presentation
Access Engineering PLC - Training PresentationGihan Anuradha Bombuwala
 
Design Appraisal report
Design Appraisal reportDesign Appraisal report
Design Appraisal reportConor Meaney
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road constructionSatish Kambaliya
 
Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report finalShubham Parab
 
Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Rabindra Shrestha
 

What's hot (17)

design of steel flyover
design of steel flyoverdesign of steel flyover
design of steel flyover
 
PIS Obajana - Cement Factory
PIS Obajana - Cement FactoryPIS Obajana - Cement Factory
PIS Obajana - Cement Factory
 
Case Study_Lake Windermere Great Britain_GB
Case Study_Lake Windermere Great Britain_GBCase Study_Lake Windermere Great Britain_GB
Case Study_Lake Windermere Great Britain_GB
 
Repair Options for Concrete Roadways
Repair Options for Concrete RoadwaysRepair Options for Concrete Roadways
Repair Options for Concrete Roadways
 
IRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing TechniqueIRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing Technique
 
What are Highways Works, Street works, Road works and Diversionary Works
What are Highways Works, Street works, Road works and Diversionary WorksWhat are Highways Works, Street works, Road works and Diversionary Works
What are Highways Works, Street works, Road works and Diversionary Works
 
Access Engineering PLC - Training Presentation
Access Engineering PLC - Training PresentationAccess Engineering PLC - Training Presentation
Access Engineering PLC - Training Presentation
 
Casting yard
Casting yardCasting yard
Casting yard
 
Design Appraisal report
Design Appraisal reportDesign Appraisal report
Design Appraisal report
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road construction
 
CHENAB BRIDGE
CHENAB BRIDGECHENAB BRIDGE
CHENAB BRIDGE
 
Boiler layout engineering
Boiler layout engineeringBoiler layout engineering
Boiler layout engineering
 
Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report final
 
The conjuring
The conjuringThe conjuring
The conjuring
 
Sbhep vivek kumar
Sbhep vivek kumarSbhep vivek kumar
Sbhep vivek kumar
 
Training PPT
Training PPTTraining PPT
Training PPT
 
Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)Mahakali Bridge Project Presentation (2077 chaitra 11)
Mahakali Bridge Project Presentation (2077 chaitra 11)
 

Similar to Proposed Preston River Bridge in Bunbury, WA

Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Rajesh Prasad
 
CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE
CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE  CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE
CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE AIT Solutions
 
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...Rajesh Prasad
 
Chenab Bridge.pdf
Chenab Bridge.pdfChenab Bridge.pdf
Chenab Bridge.pdfPpt Creater
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEsrinivas cnu
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiKrystian Gnysinski
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefitPerwez Ahmad
 
SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)dgonano
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhiRajesh Prasad
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxPraveendubey82
 
Experimental study of precast portal frame
Experimental study of precast portal frameExperimental study of precast portal frame
Experimental study of precast portal frameSatish Kambaliya
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea linkKAVYA H
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...Arman Hashmi
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
Design of Foot Over Bridge
Design of Foot Over BridgeDesign of Foot Over Bridge
Design of Foot Over Bridgejupallipavan2911
 
Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)varun km
 
Arup Presentation Iqpc Warschau 03112010
Arup Presentation Iqpc Warschau 03112010Arup Presentation Iqpc Warschau 03112010
Arup Presentation Iqpc Warschau 03112010Sander den Blanken
 

Similar to Proposed Preston River Bridge in Bunbury, WA (20)

Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE
CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE  CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE
CHALLENGES OF AN ICONIC PEDESTRIAN BRIDGE
 
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
 
Chenab Bridge.pdf
Chenab Bridge.pdfChenab Bridge.pdf
Chenab Bridge.pdf
 
Airport Boulevard Railroad Grade Separation Project
Airport Boulevard Railroad Grade Separation ProjectAirport Boulevard Railroad Grade Separation Project
Airport Boulevard Railroad Grade Separation Project
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGE
 
Linkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian GnysinskiLinkedin Presentation Krysyian Gnysinski
Linkedin Presentation Krysyian Gnysinski
 
Pt slab design philosophy with slides and pictures showing benefit
Pt slab design philosophy  with slides and pictures showing benefitPt slab design philosophy  with slides and pictures showing benefit
Pt slab design philosophy with slides and pictures showing benefit
 
SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)SynTerra / US Bridge Presentation (10 24 11)
SynTerra / US Bridge Presentation (10 24 11)
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
 
UMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptxUMAID IQBAL SEMINAR.pptx
UMAID IQBAL SEMINAR.pptx
 
Experimental study of precast portal frame
Experimental study of precast portal frameExperimental study of precast portal frame
Experimental study of precast portal frame
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
Design of Foot Over Bridge
Design of Foot Over BridgeDesign of Foot Over Bridge
Design of Foot Over Bridge
 
Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)Case study on signature bridge ppt (1)
Case study on signature bridge ppt (1)
 
report
reportreport
report
 
Arup Presentation Iqpc Warschau 03112010
Arup Presentation Iqpc Warschau 03112010Arup Presentation Iqpc Warschau 03112010
Arup Presentation Iqpc Warschau 03112010
 

More from Toe Myint Naing

More from Toe Myint Naing (10)

BIM BIM.pdf
BIM BIM.pdfBIM BIM.pdf
BIM BIM.pdf
 
Design of Low Rise Reinforced Concrete Buildings
Design of Low Rise Reinforced Concrete Buildings Design of Low Rise Reinforced Concrete Buildings
Design of Low Rise Reinforced Concrete Buildings
 
CAPM Exam preparation - series 1
CAPM Exam preparation - series 1CAPM Exam preparation - series 1
CAPM Exam preparation - series 1
 
Piling design intro
Piling design introPiling design intro
Piling design intro
 
Floor systems
Floor systemsFloor systems
Floor systems
 
Rage comics
Rage comicsRage comics
Rage comics
 
Properties of area presentation
Properties of area presentationProperties of area presentation
Properties of area presentation
 
Development length
Development length Development length
Development length
 
8 storyey presentation
8 storyey presentation8 storyey presentation
8 storyey presentation
 
4 story steel presentation ETABs
4 story steel presentation ETABs4 story steel presentation ETABs
4 story steel presentation ETABs
 

Recently uploaded

HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 

Recently uploaded (20)

HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 

Proposed Preston River Bridge in Bunbury, WA

  • 1. Proposed Bridge over the Preston River in East Bunbury, Western Australia Kyawt Yamin Thwin -700020607 Khant Htut Lwin -700020600 Toe Myint Naing -700020605 Anthony Mak Chao Jun -700014760 Project Background A new bridge is required to replace an existing bridge which crosses over the Preston River in Bunbury, Western Australia. The prosed bridge types is cable-stayed bridge. Key objective and client’s intent • to optimize between the bridge aesthetics and the construction cost and time. • Minimis environmental impact Relevant Standards and Design Specification • AS 3600_2018: Austria Standard Concrete Structure • AS 5100.1_2017: Austria Standard: Bridge Design: Scope and General Principles • AS 5100.2_2017: Austria Standard: Bridge Design: Design Loads • AS 5100.5_2017: Austria Standard: Bridge Design: Concrete Construction method Preliminary Drawing Site preparation 1. Demolition 2. Removing asbestos 3. Site Clearing 4. Site surveying and set out 5. Earthwork Substructure 1. Initiate the caisson system 2. Pump out water 3. Drive piles into the ground according to design 4. Assemble footing according to design. 5. Erect piers to designated level. Superstructure 1. Erect pylons and girder simultaneously fixing it to the piers. 2. Initiate balanced free cantilevering system using derrick cranes 3. Install stay cables stressing it to relieve the bending moments in the girders 4. Install final stay cables Item Detail Justification Bride span 66 meters • Estimated from Google Maps. Bridge type Cable-stayed Bridge • Less steel cable, faster to build n incorporate more precast concrete section • Higher stiffness and display smaller deflections than suspension bridges Pylon 12 m • Optimal Height of pylon that can comply with 0.25 𝑙 • The higher the tower above the road level, the lower the cable forces and the required quantity of cable steel. 2 number • A single tower design cost more and the height of tower need to be higher than that of twin tower. Single tower height of pylon must comply with 1.8 𝑙 20 m from left edge • The side span of the cable stayed bridge shell be about 0.42 time that of the main span. • Pylon was in the between of the main span 46m and the side span 20m. Cable Semi-harp shape cable configuration • The structure’s aesthetics is really pleasing 3 numbers at each tower • to reduce the bending moments of the beam • decrease the individual cable forces to be anchored. 15m c/c on deck • By adjusting the angle of the stay (α) nearer to the pylon, the required stay cables size will decrease, and the height of pylon will increase 1 m c/c on tower • To develop semi-harp shape arrangement of cables • Easy to maintain Footing Pile footing • Drilled pile footing • Pile cap Preliminary design Cable Cable Force (P) No. of stands Cable 1 3153.55 kN 67 nos Cable 2 5256.02 kN 111 nos Cable 3 6713.74 kN 142 nos Construction cost Specifications Total cost Cost per Area Price Index 2020 Cost per Area (Proposed Bridge) Total Cost 2020 ANZAC Bridge (Pyrmontm, New South Wales, Australia) Width: 32m Length: 805m Longest Span: 345m Year of Complete: 1995 AUD 170 million AUD 6,599.38 260% AUD 17,142.16 AUD 18.1 million Eleanor Schonell Bridge (Dutton Park, Queensland, Australia) Width: 20m Length: 390m Longest Span: 183m Year of Complete: 2006 AUD 56 million AUD 7,179.49 142% AUD 10,195.10 AUD 10.8 million Reference: “Design and Analysis of Cable Stayed Bridge” 2017 -Murkute U.T. “Cable Stayed Bridges With Prestressed Concrete”- Fritz Leonhardt Project Timeline