SlideShare a Scribd company logo
1 of 71
Development
Length
Toe Myint Naing
Curtin Sarawak
Intern
KSI Engineering
Bond
Basic assumptions in Flexural theory
Strain in concrete is the same as in reinforcing
bars at the same level, provided that the bond between
the steel and concrete is sufficient to keep them acting
together under the different load stages i.e., no slip can
occur between the two materials.
No bond, no development length, no anchorage, rebar will
pull loose from concrete
2
Help in transferring force
from steel to concrete and concrete to steel.
The stress which is acting on the outer interface of steel to the surrounding concrete
is called bond stress.
• Bond stresses are also drastically affected by the
development of tension cracks in the concrete.
• At a point where a crack occurs, all of the
longitudinal tension will be resisted by the
reinforcing bar.
• At a small distance along the bar at a point away
from the crack, the longitudinal tension will be
resisted by both the bar and the uncracked
concrete.
3
Bond Stress
Development
Length
is the length of embedment
necessary to develop the full
tensile strength of the bar,
controlled by either pullout or
splitting
4
5
Development Length
Development lengths are needed in:
1. Lapping
2. Hooks
3. Cut off
6
Development Length in tension
Tension Development Length Ldt
𝐿 𝑑 =
3
40
×
𝑓𝑦
𝑓′ 𝑐
×
ψ 𝑡ψ 𝑒ψ 𝑠λ
(𝑐 𝑏 + 𝐾𝑡𝑟)
𝑑 𝑏
× 𝑑 𝑏
(1) ψ 𝑡(𝛼)=reinforcement location factor
=1.3 for top horizontal reinforcement bars
(i.e., 12” or more of concrete is cast in a
single concreting below the development
length of splice in question)
=1.0 for other reinforcement bars
7
Development Length
Tension Development Length Ldt
𝐿 𝑑 =
3
40
×
𝑓𝑦
𝑓′ 𝑐
×
ψ 𝑡ψ 𝑒ψ 𝑠λ
(𝑐 𝑏 + 𝐾𝑡𝑟)
𝑑 𝑏
× 𝑑 𝑏
(2) ψ 𝑒 =Coating factor
=1.5 for epoxy-coated bar with cover < 3𝑑 𝑏 or
clear spacing < 6𝑑 𝑏
=1.2 for all other epoxy-coated bar
=1.0 for Uncoated and zinc-coated reinforcement
(1) ψ 𝑡(𝛼)=reinforcement location factor
=1.3 for top horizontal reinforcement bars
(i.e., 12” or more of concrete is cast in a
single concreting below the development
length of splice in question)
=1.0 for other reinforcement bars
Development Length in tension
8
Development Length
Tension Development Length Ldt
𝐿 𝑑 =
3
40
×
𝑓𝑦
𝑓′ 𝑐
×
ψ 𝑡ψ 𝑒ψ 𝑠λ
(𝑐 𝑏 + 𝐾𝑡𝑟)
𝑑 𝑏
× 𝑑 𝑏
(2) ψ 𝑒 =Coating factor
=1.5 for epoxy-coated bar with cover < 3𝑑 𝑏 or
clear spacing < 6𝑑 𝑏
=1.2 for all other epoxy-coated bar
=1.0 for Uncoated and zinc-coated reinforcement
(1) ψ 𝑡(𝛼)=reinforcement location factor
=1.3 for top horizontal reinforcement bars
(i.e., 12” or more of concrete is cast in a
single concreting below the development
length of splice in question)
=1.0 for other reinforcement bars
(3) ψ 𝑠 =reinforcement size factor
=0.8 for No.6 and smaller bars
=1.0 for No.7 and larger bars
Development Length in tension
9
Development Length
Tension Development Length Ldt
𝐿 𝑑 =
3
40
×
𝑓𝑦
𝑓′ 𝑐
×
ψ 𝑡ψ 𝑒ψ 𝑠λ
(𝑐 𝑏 + 𝐾𝑡𝑟)
𝑑 𝑏
× 𝑑 𝑏
(2) ψ 𝑒 =Coating factor
=1.5 for epoxy-coated bar with cover < 3𝑑 𝑏 or
clear spacing < 6𝑑 𝑏
=1.2 for all other epoxy-coated bar
=1.0 for Uncoated and zinc-coated reinforcement
(1) ψ 𝑡(𝛼)=reinforcement location factor
=1.3 for top horizontal reinforcement bars
(i.e., 12” or more of concrete is cast in a
single concreting below the development
length of splice in question)
=1.0 for other reinforcement bars
(3) ψ 𝑠 =reinforcement size factor
=0.8 for No.6 and smaller bars
=1.0 for No.7 and larger bars
(4) λ =lightweight aggregate concrete factor
=1.3 for all-lightweight and
sand-lightweight concrete
=1.0 for normal weight concrete
Development Length in tension
10
Development Length
Tension Development Length Ldt
𝐿 𝑑 =
3
40
×
𝑓𝑦
𝑓′ 𝑐
×
ψ 𝑡ψ 𝑒ψ 𝑠λ
(𝑐 𝑏 + 𝐾𝑡𝑟)
𝑑 𝑏
× 𝑑 𝑏
(2) ψ 𝑒 =Coating factor
=1.5 for epoxy-coated bar with cover < 3𝑑 𝑏 or
clear spacing < 6𝑑 𝑏
=1.2 for all other epoxy-coated bar
=1.0 for Uncoated and zinc-coated reinforcement
(1) ψ 𝑡(𝛼)=reinforcement location factor
=1.3 for top horizontal reinforcement bars
(i.e., 12” or more of concrete is cast in a
single concreting below the development
length of splice in question)
=1.0 for other reinforcement bars
(3) ψ 𝑠 =reinforcement size factor
=0.8 for No.6 and smaller bars
=1.0 for No.7 and larger bars
(4) λ =lightweight aggregate concrete factor
=1.3 for all-lightweight and
sand-lightweight concrete
=1.0 for normal weight concrete
(3) 𝑐 𝑏 =spacing or cover dimension
(𝑐 𝑏+𝐾𝑡𝑟)
𝑑 𝑏
≤2.5
Development Length in tension
11
Development Length
Tension Development Length Ldt
𝐿 𝑑 =
3
40
×
𝑓𝑦
𝑓′ 𝑐
×
ψ 𝑡ψ 𝑒ψ 𝑠λ
(𝑐 𝑏 + 𝐾𝑡𝑟)
𝑑 𝑏
× 𝑑 𝑏
(2) ψ 𝑒 =Coating factor
=1.5 for epoxy-coated bar with cover < 3𝑑 𝑏 or
clear spacing < 6𝑑 𝑏
=1.2 for all other epoxy-coated bar
=1.0 for Uncoated and zinc-coated reinforcement
(1) ψ 𝑡(𝛼)=reinforcement location factor
=1.3 for top horizontal reinforcement bars
(i.e., 12” or more of concrete is cast in a
single concreting below the development
length of splice in question)
=1.0 for other reinforcement bars
(3) ψ 𝑠 =reinforcement size factor
=0.8 for No.6 and smaller bars
=1.0 for No.7 and larger bars
(4) λ =lightweight aggregate concrete factor
=1.3 for all-lightweight and
sand-lightweight concrete
=1.0 for normal weight concrete
(3) 𝑐 𝑏 =spacing or cover dimension
(𝑐 𝑏+𝐾𝑡𝑟)
𝑑 𝑏
≤2.5
(3) 𝑓′ 𝑐 ≤ 100psi
Development Length in tension
12
Development Length
Tension Development Length
Ldt
𝐿 𝑑 =
3
40
×
𝑓𝑦
𝑓′ 𝑐
×
ψ 𝑡ψ 𝑒ψ 𝑠λ
(𝑐 𝑏 + 𝐾𝑡𝑟)
𝑑 𝑏
× 𝑑 𝑏
𝐿 𝑑 =
𝑓𝑦ψ 𝑡ψ 𝑒λ
25 𝑓′ 𝑐
× 𝑑 𝑏
𝐿 𝑑 =
𝑓𝑦ψ 𝑡ψ 𝑒λ
20 𝑓′ 𝑐
× 𝑑 𝑏
For No.6 (20mm) and smaller bars,
For No.7 (22mm) and larger bars,
𝐿 𝑑 =
𝑓𝑦 𝛼
25 𝑓′ 𝑐
× 𝑑 𝑏
𝐿 𝑑 =
𝑓𝑦 𝛼
20 𝑓′ 𝑐
× 𝑑 𝑏
For Normal concrete,Simplified Tension Development Length
𝐿 𝑑:
1
𝑓′ 𝑐
𝐿 𝑑: 𝑑 𝑏
𝐿 𝑑: 𝑓𝑦
Development Length in tension
13
Development Length
Ldt
For No.6 (20mm) and smaller bars, 𝐿 𝑑 =
𝑓𝑦 𝛼
25 𝑓′ 𝑐
× 𝑑 𝑏 ≥ 12"
𝐿 𝑑 =
𝑓𝑦 𝛼
20 𝑓′ 𝑐
× 𝑑 𝑏 ≥ 12"
Simplified Tension Development Length
Modification factor
𝑙 𝑑 may also be modified by (
As required
As provided
)
𝑙 𝑑 ≥12” (in all cases)
For No.7 (22mm) and larger bars,
Development Length in tension
14
Development Length
Ldt
Simplified Tension Development Length
by table
Modification factor
𝑙 𝑑 may also be modified by (
As required
As provided
)
𝑙 𝑑 ≥12” (in all cases)
Development Length in tension
15
Standard Bar Hooks
When desired tensile stress in a bar cannot be developed by bond alone, it is
necessary to provide special anchorage at the end of the bar
Bar Size, db Minimum Diameter, Ø
No.3 (10mm) through No.8 (25mm) 6 𝑑 𝑏
No.9,10 and 11 (No.29,32 and 36 ) 8 𝑑 𝑏
No.14 (43mm) through No.18 (57mm) 10 𝑑 𝑏
Hooked-Bar details for Development of standard hook
(b) Stirrups and Ties
(a) Main Reinforcement
22
16
Development Length of Hooked deformed Bar in
tension, 𝐼 𝑑ℎ
𝐿 𝑑ℎ =
0.02ψ 𝑒λ𝑓𝑦
𝑓′ 𝑐
× 𝑑 𝑏
(1) ψ 𝑒 =Coating factor
=1.2 for all other epoxy-coated bar
=1.0 for Uncoated and zinc-coated reinforcement
17
𝐿 𝑑ℎ =
0.02ψ 𝑒λ𝑓𝑦
𝑓′ 𝑐
× 𝑑 𝑏
(1) ψ 𝑒 =Coating factor
=1.2 for all other epoxy-coated bar
=1.0 for Uncoated and zinc-coated reinforcement
(2) λ =lightweight aggregate concrete factor
=1.3 for all-lightweight and
sand-lightweight concrete
=1.0 for normal weight concrete
Development Length of Hooked deformed Bar in
tension, 𝐼 𝑑ℎ
18
Development Length of Hooked deformed Bar, 𝐼 𝑑ℎ
𝐿 𝑑ℎ =
0.02ψ 𝑒λ𝑓𝑦
𝑓′ 𝑐
× 𝑑 𝑏
(1) ψ 𝑒 =Coating factor
=1.2 for all other epoxy-coated bar
=1.0 for Uncoated and zinc-coated reinforcement
(2) λ =lightweight aggregate concrete factor
=1.3 for all-lightweight and
sand-lightweight concrete
=1.0 for normal weight concrete
For Normal Concrete,
𝐿 𝑑ℎ =
0.02𝑓𝑦
𝑓′ 𝑐
× 𝑑 𝑏
Modification factors
𝑙 𝑑ℎ may be modified by (
As required
As provided
)
For No.11 and smaller bar hooks with side cover ≥2.5” and for 90° hooks
with clear cover on bar extension ≥2.0”, 𝑙 𝑑ℎ is multiplied by 0.7
For No.11 and smaller bars hooks that are enclosed within ties or stirrups
at spacing ≤ 3𝑑 𝑏 along 𝑙 𝑑ℎ, 𝑙 𝑑ℎ is multiplied by 0.8
Development Length of Hooked deformed Bar in
tension, 𝐼 𝑑ℎ
Development Length of Hooked deformed Bar in
tension, 𝐼 𝑑ℎ
19
X 0.7
X 0.8 X 0.8
20
Development Length or Anchorage
( 𝑙 𝑑 or 𝑙 𝑑ℎ )
(a) (b) (c)
Hook development length, 𝑙 𝑑ℎ is used only when development length, 𝑙 𝑑 is not adequate
21
Development Length
Compression Development Length Ldc
𝐿 𝑑 =
0.02𝑓𝑦
𝑓′ 𝑐
× 𝑑 𝑏 ≥ 0.0003𝑓𝑦 ≥ 8"
𝐿 𝑑𝑐 shorter than 𝐿 𝑑𝑡
Modification factor
𝑙 𝑑 may be modified by (
As required
As provided
)
For No.4 ties < 4” c/c spacing , 𝑙 𝑑 may also be modified by 0.75
𝑙 𝑑 ≥8” (in all cases)
Hooks shall not be used to develop bars in compression (12.5.5 ACI 318-05)
Development Length in compression
End Anchorage Lengths
22
(A) Using Standard Hooks
𝑙 𝑏1 ≥ 𝑙 𝑑ℎ ≥ 8𝑑 𝑏 𝑜𝑟 6"
𝑙 𝑎1 ≥ 𝑙 𝑑ℎ ≥ 8𝑑 𝑏 𝑜𝑟 6"
𝑙 𝑏1 ≥ 𝑙 𝑑ℎ ≥ 8𝑑 𝑏 𝑜𝑟 6"
𝑙 𝑎1 ≥ 𝑙 𝑑ℎ ≥ 8𝑑 𝑏 𝑜𝑟 6"
Wide Column
Clear cover
≥ 2"
Clear cover
≥ 2"
Primary
Beam
(a) Beam – Column Connections (b) Beam – Girder Connections
To pg-15
End Anchorage Lengths
23
(B) Using Alternate Method
𝑙𝑏2≥𝑙𝑑ℎ+14𝑑𝑏
𝑙 𝑎2 ≥ 𝑙 𝑑ℎ + 14𝑑 𝑏
Narrow Column
Clear cover
≥ 2"
Clear cover
≥ 2"
Primary
Beam
(a) Beam – Column Connections (b) Beam – Girder Connections
𝑙 𝑎2 ≥ 𝑙 𝑑ℎ + 14𝑑 𝑏
𝑙𝑏2≥𝑙𝑑ℎ+11𝑑𝑏
≥ 8𝑑 𝑏 𝑜𝑟 6"
≥ 8𝑑 𝑏 𝑜𝑟 6"
End Anchorage Lengths
24
Anchorage Length for Girder with smaller bar sizes
𝑙 𝑚𝑎𝑥 ≈ 𝑏 + ℎ − 5.875 - 2.5 𝑑 𝑏 (for the outermost layer)
𝑙 𝑚𝑎𝑥 ≈ 𝑏 + ℎ − 5.875 - 6.5 𝑑 𝑏 (for the second layer)
𝑙 𝑚𝑎𝑥 ≈ 𝑏 + ℎ − 5.875 - 10.5 𝑑 𝑏 (for the third layer)
h, b = depth and width of primary beam
h
End Anchorage Lengths
25
Structural Integrity Requirement
Development Length from column to footing
For the case where all the column bars
are in compression, the dowels must
extend into the footing a compression
development length ldc .
(a)Longitudinal bars in column are in
compression
The dowel bars are usually hooked and extend to the level
of the flexural reinforcement in the footing. According to
Section 12.5.5 ACI 318-05, the hooked portion of the
dowels cannot be considered effective for developing the
dowel bars in compression.
26
Development Length from column to footing
Either direct or uplift forces or transfer
by a moment tensile force can act from
column, the dowels must extend into
the footing a tension development
length ldt .
(b)Longitudinal bars in column are in
tension
Tensile anchorage of the dowel bars into a footing is
typically accomplished by providing 90-degree standard
hooks at the ends of the dowel bars with the development
length of the hooked bar, ldh, determined in accordance
with Section 12.5 of ACI 318-14.
27
Development
Length
Toe Myint Naing
Curtin Sarawak
Intern
KSI Engineering
Development Length (Lap splice inTension)
29
Class A Splice: 𝑙 𝑠𝑝𝑙𝑖𝑐𝑒,𝑡𝑒𝑛……………………….……….……….…..1.0𝑙 𝑑 ≥ 12”
Class B Splice: 𝑙 𝑠𝑝𝑙𝑖𝑐𝑒,𝑡𝑒𝑛………………………….….………….…..1.3𝑙 𝑑 ≥ 12”
For No.6 (20mm)
and smaller bars,
𝐿 𝑑 =
𝑓𝑦 𝛼
25 𝑓′ 𝑐
× 𝑑 𝑏
𝐿 𝑑 =
𝑓𝑦 𝛼
20 𝑓′ 𝑐
× 𝑑 𝑏
For No.7 (22mm)
and larger bars,
Lap splicing of No.14 and No.18 bars
in tension is prohibited.
50%
Development Length (Lap splice in Compression)
30
𝒇 𝒚 ≤ 60,000 psi 𝒇 𝒚 >60,000 psi
𝑙 𝑠𝑝𝑙𝑖𝑐𝑒,𝑐𝑜𝑚 0.0005𝑓𝑦 𝑑 𝑏 (0.0009𝑓𝑦-24) 𝑑 𝑏 ≥ 12”
For 𝑓′ 𝑐 < 3000 psi, 𝑙 𝑠𝑝𝑙𝑖𝑐𝑒,𝑐𝑜𝑚 shell be increased by one-third
Where ties throughout the lap splice length have an effective area ≥ 0.0015h s, lap splice length shall be
permitted to be multiplied by 0.83 ≥ 12”
Lap splicing of No.14 and No.18 bars to No.11 and smaller bars in
compression shell be permitted when
𝑙 𝑠𝑝𝑙𝑖𝑐𝑒,𝑐𝑜𝑚 = larger of [ 𝑙 𝑑𝑐 of larger bar and 𝑙 𝑠𝑝𝑙𝑖𝑐𝑒,𝑐𝑜𝑚 of smaller bar ]
Development Length (Lap splice in Column)
31
Column – no restrictions Column – no restrictions Column – mid
Development Length (Lap splice in Column)
32
50% LAPPING, CQHP
Development Length (Lap splice inTension only in Column)
33
Class A Splice: 𝑙 𝑠𝑝𝑙𝑖𝑐𝑒,𝑡𝑒𝑛……………………….……….……….…..1.0𝑙 𝑑 ≥ 12”
Class B Splice: 𝑙 𝑠𝑝𝑙𝑖𝑐𝑒,𝑡𝑒𝑛………………………….….………….…..1.3𝑙 𝑑 ≥ 12”
For No.6 (20mm)
and smaller bars,
𝐿 𝑑 =
𝑓𝑦 𝛼
25 𝑓′ 𝑐
× 𝑑 𝑏
𝐿 𝑑 =
𝑓𝑦 𝛼
20 𝑓′ 𝑐
× 𝑑 𝑏
For No.7 (22mm)
and larger bars,
Lap splicing of No.14 and No.18 bars
in tension is prohibited.
100%
Development Length (Lap splice in Column)
34
Development Length (Lap splice in Column)
35
Development Length (Lap splice in Column)
36
Development Length (Lap splice in Column)
37
Development Length (Lap splice in Column)
38
Development Length (Lap splice in Column)
39
Development Length (Lap splice in Column)
40
Development Length (Lap splice in Column)
41
Development Length (Lap splice in Column)
42
Development Length (Lap splice in Column)
43
Development Length (Lap splice in Column)
44
Development Length (Lap splice in Column)
45
Development Length (Lap splice in Column)
46
Development Length (Lap splice in Column)
47
Development Length (Lap splice in Column)
48
Development Length (Lap splice in Column)
49
Development Length (Lap splice in Column)
50
Development Length (Lap splice in Column)
51
Development Length (Lap splice in Column)
52
Development Length (Lap splice in Column)
53
Development Length (Lap splice in Column)
54
Development Length (Lap splice in Column)
55
Development Length (Lap splice in Column)
56
Development Length (Lap splice in Column)
57
Development Length (Lap splice in Column)
58
Development Length (Lap splice in Beam)
59
Ordinary Moment-Resisting Frame
Beam
Top Bar – Mid
Bot Bar – At Support or 2h
Beam
Top Bar – Mid
Bot Bar – Outside 2h within L/3
Development Length (Lap splice in Beam)
60
Ordinary Moment-Resisting Frame
For closed stirrups for torsion spacing, smax =
𝑃ℎ
8
or 12”
Development Length (Lap splice in Beam)
61
Intermediate Moment-Resisting Frame Special Moment-Resisting Frame
Outside 2h
ACI 318-05 ACI 318-08
Stirrups
without seismic
hook
Stirrups with
seismic hook
Beam
Top Bar – Mid
Bot Bar – Mid
Development Length (Lap splice in Beam)
62
Hoop reinforcement for beams
Crosstie — A continuous reinforcing
bar having a seismic hook at one end
and a hook not less than 90° with at
least a 6db extension at the other
end.
Hoop — A closed tie or continuously
wound tie. A closed tie can be made up
of several reinforcement elements each
having seismic hooks at both ends. A
continuously wound tie shall have a
seismic hook at both ends.
Development Length (OMRF)
63
Slabs (Cutoff)
Development Length
64
Bars must extend the longer of d or 12db past the flexural cutoff
points except at supports or the ends of cantilevers
Structural Integrity Requirement
65
Simple Supports: At least one-third of the positive moment
reinforcement must be extended 15 cm. into the supports
Structural Integrity Requirement
Development Length
66
Continuous interior beams with closed stirrups: At least one-fourth of the positive moment
reinforcement must be extended 15 cm. into the support
Structural Integrity Requirement
Development Length
67
Continuous interior beams without closed stirrups: At least one-fourth of the positive
moment reinforcement must be continuous or shall be spliced near the support with a
class B tension splice and at non-continuous supports be terminated with a standard hook
Splice Class
ACI 318-05 ACI 318-08
Class A Class B
Structural Integrity Requirement
Development Length
68
Beams forming part of a frame that is the primary lateral load resisting system for the
building.: This reinforcement must be anchored to develop the specified yield strength, fy ,
at the face of the support
Structural Integrity Requirement
Development Length
69
Interior beams: At least one-third of the negative moment reinforcement must be
extended by the greatest of d, 12 db or
𝑙 𝑛
16
past the negative moment point of inflection.
Structural Integrity Requirement
Development Length
70
Perimeter beams: In addition,
1
6
of the (-) reinforcement required at the support must be
made continuous at mid-span. This can be achieved by means of a class B tension splice at
mid-span
Splice Class
ACI 318-05 ACI 318-08
Class A Class B
Structural Integrity Requirement
Development Length
Q&A
71

More Related Content

What's hot

Module 1 Behaviour of RC beams in Shear and Torsion
Module 1   Behaviour of RC beams in Shear and TorsionModule 1   Behaviour of RC beams in Shear and Torsion
Module 1 Behaviour of RC beams in Shear and TorsionVVIETCIVIL
 
Combined footings
Combined footingsCombined footings
Combined footingsseemavgiri
 
Onewayslab
OnewayslabOnewayslab
OnewayslabP Ramana
 
Cable Layout, Continuous Beam & Load Balancing Method
 Cable Layout, Continuous Beam & Load Balancing Method Cable Layout, Continuous Beam & Load Balancing Method
Cable Layout, Continuous Beam & Load Balancing MethodMd Tanvir Alam
 
Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma ABHISHEK SHARMA
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)ahsanrabbani
 
Design of compression members
Design of compression membersDesign of compression members
Design of compression membersSabna Thilakan
 
Design Procedure of Singly,Doubly & T-Beam(As Per ACI code)
Design Procedure of Singly,Doubly & T-Beam(As Per ACI code)Design Procedure of Singly,Doubly & T-Beam(As Per ACI code)
Design Procedure of Singly,Doubly & T-Beam(As Per ACI code)Jahidur Rahman
 
Design of torsion reinforcement
 Design of torsion reinforcement Design of torsion reinforcement
Design of torsion reinforcementMuskanDeura
 
Singly R.C. beam
Singly R.C. beam  Singly R.C. beam
Singly R.C. beam Yash Patel
 
Part (1) basics of plastic analysis
Part (1) basics of plastic analysisPart (1) basics of plastic analysis
Part (1) basics of plastic analysisAshraf Sabbagh
 
Ch 1 structural analysis stiffness method
Ch 1 structural analysis stiffness methodCh 1 structural analysis stiffness method
Ch 1 structural analysis stiffness method280632796
 

What's hot (20)

Module 1 Behaviour of RC beams in Shear and Torsion
Module 1   Behaviour of RC beams in Shear and TorsionModule 1   Behaviour of RC beams in Shear and Torsion
Module 1 Behaviour of RC beams in Shear and Torsion
 
Combined footings
Combined footingsCombined footings
Combined footings
 
Onewayslab
OnewayslabOnewayslab
Onewayslab
 
Cable Layout, Continuous Beam & Load Balancing Method
 Cable Layout, Continuous Beam & Load Balancing Method Cable Layout, Continuous Beam & Load Balancing Method
Cable Layout, Continuous Beam & Load Balancing Method
 
Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)
 
Design of compression members
Design of compression membersDesign of compression members
Design of compression members
 
Presentation o beam
Presentation o beamPresentation o beam
Presentation o beam
 
05 chapter 6 mat foundations
05 chapter 6 mat foundations05 chapter 6 mat foundations
05 chapter 6 mat foundations
 
Shear wall and its design guidelines
Shear wall and its design guidelinesShear wall and its design guidelines
Shear wall and its design guidelines
 
Design Procedure of Singly,Doubly & T-Beam(As Per ACI code)
Design Procedure of Singly,Doubly & T-Beam(As Per ACI code)Design Procedure of Singly,Doubly & T-Beam(As Per ACI code)
Design Procedure of Singly,Doubly & T-Beam(As Per ACI code)
 
4. Shallow Foundations
4. Shallow Foundations4. Shallow Foundations
4. Shallow Foundations
 
Design of torsion reinforcement
 Design of torsion reinforcement Design of torsion reinforcement
Design of torsion reinforcement
 
Singly R.C. beam
Singly R.C. beam  Singly R.C. beam
Singly R.C. beam
 
Design of footing as per IS 456-2000
Design of footing as per IS 456-2000Design of footing as per IS 456-2000
Design of footing as per IS 456-2000
 
Deep beam aci # l 1
Deep beam  aci  # l 1 Deep beam  aci  # l 1
Deep beam aci # l 1
 
Prestressed concrete continuous beam
Prestressed concrete continuous beamPrestressed concrete continuous beam
Prestressed concrete continuous beam
 
Part (1) basics of plastic analysis
Part (1) basics of plastic analysisPart (1) basics of plastic analysis
Part (1) basics of plastic analysis
 
Ch 1 structural analysis stiffness method
Ch 1 structural analysis stiffness methodCh 1 structural analysis stiffness method
Ch 1 structural analysis stiffness method
 
SHALLOW FOUNDATION
SHALLOW FOUNDATIONSHALLOW FOUNDATION
SHALLOW FOUNDATION
 

Similar to Development length

Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdfDiv_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdfLandelSmith1
 
Design of Main Girder [Compatibility Mode].pdf
Design of Main Girder [Compatibility Mode].pdfDesign of Main Girder [Compatibility Mode].pdf
Design of Main Girder [Compatibility Mode].pdfmohamed abdo
 
Dowel bars, tie bars and their design
Dowel bars, tie bars and their designDowel bars, tie bars and their design
Dowel bars, tie bars and their designBhavya Jaiswal
 
Connections in steel structures
Connections in steel structuresConnections in steel structures
Connections in steel structuresanand bhatnagar
 
Lecture chapter 1u
Lecture chapter 1uLecture chapter 1u
Lecture chapter 1urgo-amo
 
Lecture Riveted Joints by molvie imran.pptx
Lecture  Riveted Joints by molvie imran.pptxLecture  Riveted Joints by molvie imran.pptx
Lecture Riveted Joints by molvie imran.pptxBDULQAYYUM
 
Design analysis of Cotter joint used in piston rod and crosshead a.pptx
Design analysis of Cotter joint used in piston rod and crosshead a.pptxDesign analysis of Cotter joint used in piston rod and crosshead a.pptx
Design analysis of Cotter joint used in piston rod and crosshead a.pptx138HemangiAhire
 
Tension members
Tension membersTension members
Tension memberssky hawk
 
Connections
ConnectionsConnections
Connectionssky hawk
 
Sd i-module2- rajesh sir
Sd i-module2- rajesh sirSd i-module2- rajesh sir
Sd i-module2- rajesh sirSHAMJITH KM
 
CVEN 440_540 Classnotes (6) --- Static analysis of pile foundation.pptx
CVEN 440_540 Classnotes (6) --- Static analysis of pile foundation.pptxCVEN 440_540 Classnotes (6) --- Static analysis of pile foundation.pptx
CVEN 440_540 Classnotes (6) --- Static analysis of pile foundation.pptxmoloholo90
 
crack control and crack width estimation
crack control and crack width estimationcrack control and crack width estimation
crack control and crack width estimationKumar Anjneya
 
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxxDSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxxADITYAPILLAI29
 
Chapter 6 column
Chapter 6   columnChapter 6   column
Chapter 6 columnSimon Foo
 
Lec 13-14-15-flexural analysis and design of beams-2007-r
Lec 13-14-15-flexural analysis and design of beams-2007-rLec 13-14-15-flexural analysis and design of beams-2007-r
Lec 13-14-15-flexural analysis and design of beams-2007-rCivil Zone
 

Similar to Development length (20)

Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdfDiv_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
 
Design of One-Way Slab
Design of One-Way SlabDesign of One-Way Slab
Design of One-Way Slab
 
Design of Main Girder [Compatibility Mode].pdf
Design of Main Girder [Compatibility Mode].pdfDesign of Main Girder [Compatibility Mode].pdf
Design of Main Girder [Compatibility Mode].pdf
 
0 ne way slab
0 ne way slab0 ne way slab
0 ne way slab
 
Dowel bars, tie bars and their design
Dowel bars, tie bars and their designDowel bars, tie bars and their design
Dowel bars, tie bars and their design
 
Connections in steel structures
Connections in steel structuresConnections in steel structures
Connections in steel structures
 
Lecture chapter 1u
Lecture chapter 1uLecture chapter 1u
Lecture chapter 1u
 
Casing design
Casing designCasing design
Casing design
 
Lecture Riveted Joints by molvie imran.pptx
Lecture  Riveted Joints by molvie imran.pptxLecture  Riveted Joints by molvie imran.pptx
Lecture Riveted Joints by molvie imran.pptx
 
Design analysis of Cotter joint used in piston rod and crosshead a.pptx
Design analysis of Cotter joint used in piston rod and crosshead a.pptxDesign analysis of Cotter joint used in piston rod and crosshead a.pptx
Design analysis of Cotter joint used in piston rod and crosshead a.pptx
 
Tension members
Tension membersTension members
Tension members
 
Connections
ConnectionsConnections
Connections
 
Sd i-module2- rajesh sir
Sd i-module2- rajesh sirSd i-module2- rajesh sir
Sd i-module2- rajesh sir
 
CVEN 440_540 Classnotes (6) --- Static analysis of pile foundation.pptx
CVEN 440_540 Classnotes (6) --- Static analysis of pile foundation.pptxCVEN 440_540 Classnotes (6) --- Static analysis of pile foundation.pptx
CVEN 440_540 Classnotes (6) --- Static analysis of pile foundation.pptx
 
D013142435
D013142435D013142435
D013142435
 
crack control and crack width estimation
crack control and crack width estimationcrack control and crack width estimation
crack control and crack width estimation
 
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxxDSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
 
Chapter 6 column
Chapter 6   columnChapter 6   column
Chapter 6 column
 
Lec 13-14-15-flexural analysis and design of beams-2007-r
Lec 13-14-15-flexural analysis and design of beams-2007-rLec 13-14-15-flexural analysis and design of beams-2007-r
Lec 13-14-15-flexural analysis and design of beams-2007-r
 
Lec 13-14-15
Lec 13-14-15Lec 13-14-15
Lec 13-14-15
 

More from Toe Myint Naing

Design of Low Rise Reinforced Concrete Buildings
Design of Low Rise Reinforced Concrete Buildings Design of Low Rise Reinforced Concrete Buildings
Design of Low Rise Reinforced Concrete Buildings Toe Myint Naing
 
CAPM Exam preparation - series 1
CAPM Exam preparation - series 1CAPM Exam preparation - series 1
CAPM Exam preparation - series 1Toe Myint Naing
 
Proposed Bridge over the Preston River in East Bunbury, Western Australia
Proposed Bridge over the Preston River in East Bunbury, Western AustraliaProposed Bridge over the Preston River in East Bunbury, Western Australia
Proposed Bridge over the Preston River in East Bunbury, Western AustraliaToe Myint Naing
 
Properties of area presentation
Properties of area presentationProperties of area presentation
Properties of area presentationToe Myint Naing
 
4 story steel presentation ETABs
4 story steel presentation ETABs4 story steel presentation ETABs
4 story steel presentation ETABsToe Myint Naing
 

More from Toe Myint Naing (10)

BIM BIM.pdf
BIM BIM.pdfBIM BIM.pdf
BIM BIM.pdf
 
Design of Low Rise Reinforced Concrete Buildings
Design of Low Rise Reinforced Concrete Buildings Design of Low Rise Reinforced Concrete Buildings
Design of Low Rise Reinforced Concrete Buildings
 
CAPM Exam preparation - series 1
CAPM Exam preparation - series 1CAPM Exam preparation - series 1
CAPM Exam preparation - series 1
 
Proposed Bridge over the Preston River in East Bunbury, Western Australia
Proposed Bridge over the Preston River in East Bunbury, Western AustraliaProposed Bridge over the Preston River in East Bunbury, Western Australia
Proposed Bridge over the Preston River in East Bunbury, Western Australia
 
Piling design intro
Piling design introPiling design intro
Piling design intro
 
Floor systems
Floor systemsFloor systems
Floor systems
 
Rage comics
Rage comicsRage comics
Rage comics
 
Properties of area presentation
Properties of area presentationProperties of area presentation
Properties of area presentation
 
8 storyey presentation
8 storyey presentation8 storyey presentation
8 storyey presentation
 
4 story steel presentation ETABs
4 story steel presentation ETABs4 story steel presentation ETABs
4 story steel presentation ETABs
 

Recently uploaded

CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 

Recently uploaded (20)

CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 

Development length

  • 1. Development Length Toe Myint Naing Curtin Sarawak Intern KSI Engineering
  • 2. Bond Basic assumptions in Flexural theory Strain in concrete is the same as in reinforcing bars at the same level, provided that the bond between the steel and concrete is sufficient to keep them acting together under the different load stages i.e., no slip can occur between the two materials. No bond, no development length, no anchorage, rebar will pull loose from concrete 2 Help in transferring force from steel to concrete and concrete to steel.
  • 3. The stress which is acting on the outer interface of steel to the surrounding concrete is called bond stress. • Bond stresses are also drastically affected by the development of tension cracks in the concrete. • At a point where a crack occurs, all of the longitudinal tension will be resisted by the reinforcing bar. • At a small distance along the bar at a point away from the crack, the longitudinal tension will be resisted by both the bar and the uncracked concrete. 3 Bond Stress
  • 4. Development Length is the length of embedment necessary to develop the full tensile strength of the bar, controlled by either pullout or splitting 4
  • 5. 5 Development Length Development lengths are needed in: 1. Lapping 2. Hooks 3. Cut off
  • 6. 6 Development Length in tension Tension Development Length Ldt 𝐿 𝑑 = 3 40 × 𝑓𝑦 𝑓′ 𝑐 × ψ 𝑡ψ 𝑒ψ 𝑠λ (𝑐 𝑏 + 𝐾𝑡𝑟) 𝑑 𝑏 × 𝑑 𝑏 (1) ψ 𝑡(𝛼)=reinforcement location factor =1.3 for top horizontal reinforcement bars (i.e., 12” or more of concrete is cast in a single concreting below the development length of splice in question) =1.0 for other reinforcement bars
  • 7. 7 Development Length Tension Development Length Ldt 𝐿 𝑑 = 3 40 × 𝑓𝑦 𝑓′ 𝑐 × ψ 𝑡ψ 𝑒ψ 𝑠λ (𝑐 𝑏 + 𝐾𝑡𝑟) 𝑑 𝑏 × 𝑑 𝑏 (2) ψ 𝑒 =Coating factor =1.5 for epoxy-coated bar with cover < 3𝑑 𝑏 or clear spacing < 6𝑑 𝑏 =1.2 for all other epoxy-coated bar =1.0 for Uncoated and zinc-coated reinforcement (1) ψ 𝑡(𝛼)=reinforcement location factor =1.3 for top horizontal reinforcement bars (i.e., 12” or more of concrete is cast in a single concreting below the development length of splice in question) =1.0 for other reinforcement bars Development Length in tension
  • 8. 8 Development Length Tension Development Length Ldt 𝐿 𝑑 = 3 40 × 𝑓𝑦 𝑓′ 𝑐 × ψ 𝑡ψ 𝑒ψ 𝑠λ (𝑐 𝑏 + 𝐾𝑡𝑟) 𝑑 𝑏 × 𝑑 𝑏 (2) ψ 𝑒 =Coating factor =1.5 for epoxy-coated bar with cover < 3𝑑 𝑏 or clear spacing < 6𝑑 𝑏 =1.2 for all other epoxy-coated bar =1.0 for Uncoated and zinc-coated reinforcement (1) ψ 𝑡(𝛼)=reinforcement location factor =1.3 for top horizontal reinforcement bars (i.e., 12” or more of concrete is cast in a single concreting below the development length of splice in question) =1.0 for other reinforcement bars (3) ψ 𝑠 =reinforcement size factor =0.8 for No.6 and smaller bars =1.0 for No.7 and larger bars Development Length in tension
  • 9. 9 Development Length Tension Development Length Ldt 𝐿 𝑑 = 3 40 × 𝑓𝑦 𝑓′ 𝑐 × ψ 𝑡ψ 𝑒ψ 𝑠λ (𝑐 𝑏 + 𝐾𝑡𝑟) 𝑑 𝑏 × 𝑑 𝑏 (2) ψ 𝑒 =Coating factor =1.5 for epoxy-coated bar with cover < 3𝑑 𝑏 or clear spacing < 6𝑑 𝑏 =1.2 for all other epoxy-coated bar =1.0 for Uncoated and zinc-coated reinforcement (1) ψ 𝑡(𝛼)=reinforcement location factor =1.3 for top horizontal reinforcement bars (i.e., 12” or more of concrete is cast in a single concreting below the development length of splice in question) =1.0 for other reinforcement bars (3) ψ 𝑠 =reinforcement size factor =0.8 for No.6 and smaller bars =1.0 for No.7 and larger bars (4) λ =lightweight aggregate concrete factor =1.3 for all-lightweight and sand-lightweight concrete =1.0 for normal weight concrete Development Length in tension
  • 10. 10 Development Length Tension Development Length Ldt 𝐿 𝑑 = 3 40 × 𝑓𝑦 𝑓′ 𝑐 × ψ 𝑡ψ 𝑒ψ 𝑠λ (𝑐 𝑏 + 𝐾𝑡𝑟) 𝑑 𝑏 × 𝑑 𝑏 (2) ψ 𝑒 =Coating factor =1.5 for epoxy-coated bar with cover < 3𝑑 𝑏 or clear spacing < 6𝑑 𝑏 =1.2 for all other epoxy-coated bar =1.0 for Uncoated and zinc-coated reinforcement (1) ψ 𝑡(𝛼)=reinforcement location factor =1.3 for top horizontal reinforcement bars (i.e., 12” or more of concrete is cast in a single concreting below the development length of splice in question) =1.0 for other reinforcement bars (3) ψ 𝑠 =reinforcement size factor =0.8 for No.6 and smaller bars =1.0 for No.7 and larger bars (4) λ =lightweight aggregate concrete factor =1.3 for all-lightweight and sand-lightweight concrete =1.0 for normal weight concrete (3) 𝑐 𝑏 =spacing or cover dimension (𝑐 𝑏+𝐾𝑡𝑟) 𝑑 𝑏 ≤2.5 Development Length in tension
  • 11. 11 Development Length Tension Development Length Ldt 𝐿 𝑑 = 3 40 × 𝑓𝑦 𝑓′ 𝑐 × ψ 𝑡ψ 𝑒ψ 𝑠λ (𝑐 𝑏 + 𝐾𝑡𝑟) 𝑑 𝑏 × 𝑑 𝑏 (2) ψ 𝑒 =Coating factor =1.5 for epoxy-coated bar with cover < 3𝑑 𝑏 or clear spacing < 6𝑑 𝑏 =1.2 for all other epoxy-coated bar =1.0 for Uncoated and zinc-coated reinforcement (1) ψ 𝑡(𝛼)=reinforcement location factor =1.3 for top horizontal reinforcement bars (i.e., 12” or more of concrete is cast in a single concreting below the development length of splice in question) =1.0 for other reinforcement bars (3) ψ 𝑠 =reinforcement size factor =0.8 for No.6 and smaller bars =1.0 for No.7 and larger bars (4) λ =lightweight aggregate concrete factor =1.3 for all-lightweight and sand-lightweight concrete =1.0 for normal weight concrete (3) 𝑐 𝑏 =spacing or cover dimension (𝑐 𝑏+𝐾𝑡𝑟) 𝑑 𝑏 ≤2.5 (3) 𝑓′ 𝑐 ≤ 100psi Development Length in tension
  • 12. 12 Development Length Tension Development Length Ldt 𝐿 𝑑 = 3 40 × 𝑓𝑦 𝑓′ 𝑐 × ψ 𝑡ψ 𝑒ψ 𝑠λ (𝑐 𝑏 + 𝐾𝑡𝑟) 𝑑 𝑏 × 𝑑 𝑏 𝐿 𝑑 = 𝑓𝑦ψ 𝑡ψ 𝑒λ 25 𝑓′ 𝑐 × 𝑑 𝑏 𝐿 𝑑 = 𝑓𝑦ψ 𝑡ψ 𝑒λ 20 𝑓′ 𝑐 × 𝑑 𝑏 For No.6 (20mm) and smaller bars, For No.7 (22mm) and larger bars, 𝐿 𝑑 = 𝑓𝑦 𝛼 25 𝑓′ 𝑐 × 𝑑 𝑏 𝐿 𝑑 = 𝑓𝑦 𝛼 20 𝑓′ 𝑐 × 𝑑 𝑏 For Normal concrete,Simplified Tension Development Length 𝐿 𝑑: 1 𝑓′ 𝑐 𝐿 𝑑: 𝑑 𝑏 𝐿 𝑑: 𝑓𝑦 Development Length in tension
  • 13. 13 Development Length Ldt For No.6 (20mm) and smaller bars, 𝐿 𝑑 = 𝑓𝑦 𝛼 25 𝑓′ 𝑐 × 𝑑 𝑏 ≥ 12" 𝐿 𝑑 = 𝑓𝑦 𝛼 20 𝑓′ 𝑐 × 𝑑 𝑏 ≥ 12" Simplified Tension Development Length Modification factor 𝑙 𝑑 may also be modified by ( As required As provided ) 𝑙 𝑑 ≥12” (in all cases) For No.7 (22mm) and larger bars, Development Length in tension
  • 14. 14 Development Length Ldt Simplified Tension Development Length by table Modification factor 𝑙 𝑑 may also be modified by ( As required As provided ) 𝑙 𝑑 ≥12” (in all cases) Development Length in tension
  • 15. 15 Standard Bar Hooks When desired tensile stress in a bar cannot be developed by bond alone, it is necessary to provide special anchorage at the end of the bar Bar Size, db Minimum Diameter, Ø No.3 (10mm) through No.8 (25mm) 6 𝑑 𝑏 No.9,10 and 11 (No.29,32 and 36 ) 8 𝑑 𝑏 No.14 (43mm) through No.18 (57mm) 10 𝑑 𝑏 Hooked-Bar details for Development of standard hook (b) Stirrups and Ties (a) Main Reinforcement 22
  • 16. 16 Development Length of Hooked deformed Bar in tension, 𝐼 𝑑ℎ 𝐿 𝑑ℎ = 0.02ψ 𝑒λ𝑓𝑦 𝑓′ 𝑐 × 𝑑 𝑏 (1) ψ 𝑒 =Coating factor =1.2 for all other epoxy-coated bar =1.0 for Uncoated and zinc-coated reinforcement
  • 17. 17 𝐿 𝑑ℎ = 0.02ψ 𝑒λ𝑓𝑦 𝑓′ 𝑐 × 𝑑 𝑏 (1) ψ 𝑒 =Coating factor =1.2 for all other epoxy-coated bar =1.0 for Uncoated and zinc-coated reinforcement (2) λ =lightweight aggregate concrete factor =1.3 for all-lightweight and sand-lightweight concrete =1.0 for normal weight concrete Development Length of Hooked deformed Bar in tension, 𝐼 𝑑ℎ
  • 18. 18 Development Length of Hooked deformed Bar, 𝐼 𝑑ℎ 𝐿 𝑑ℎ = 0.02ψ 𝑒λ𝑓𝑦 𝑓′ 𝑐 × 𝑑 𝑏 (1) ψ 𝑒 =Coating factor =1.2 for all other epoxy-coated bar =1.0 for Uncoated and zinc-coated reinforcement (2) λ =lightweight aggregate concrete factor =1.3 for all-lightweight and sand-lightweight concrete =1.0 for normal weight concrete For Normal Concrete, 𝐿 𝑑ℎ = 0.02𝑓𝑦 𝑓′ 𝑐 × 𝑑 𝑏 Modification factors 𝑙 𝑑ℎ may be modified by ( As required As provided ) For No.11 and smaller bar hooks with side cover ≥2.5” and for 90° hooks with clear cover on bar extension ≥2.0”, 𝑙 𝑑ℎ is multiplied by 0.7 For No.11 and smaller bars hooks that are enclosed within ties or stirrups at spacing ≤ 3𝑑 𝑏 along 𝑙 𝑑ℎ, 𝑙 𝑑ℎ is multiplied by 0.8 Development Length of Hooked deformed Bar in tension, 𝐼 𝑑ℎ
  • 19. Development Length of Hooked deformed Bar in tension, 𝐼 𝑑ℎ 19 X 0.7 X 0.8 X 0.8
  • 20. 20 Development Length or Anchorage ( 𝑙 𝑑 or 𝑙 𝑑ℎ ) (a) (b) (c) Hook development length, 𝑙 𝑑ℎ is used only when development length, 𝑙 𝑑 is not adequate
  • 21. 21 Development Length Compression Development Length Ldc 𝐿 𝑑 = 0.02𝑓𝑦 𝑓′ 𝑐 × 𝑑 𝑏 ≥ 0.0003𝑓𝑦 ≥ 8" 𝐿 𝑑𝑐 shorter than 𝐿 𝑑𝑡 Modification factor 𝑙 𝑑 may be modified by ( As required As provided ) For No.4 ties < 4” c/c spacing , 𝑙 𝑑 may also be modified by 0.75 𝑙 𝑑 ≥8” (in all cases) Hooks shall not be used to develop bars in compression (12.5.5 ACI 318-05) Development Length in compression
  • 22. End Anchorage Lengths 22 (A) Using Standard Hooks 𝑙 𝑏1 ≥ 𝑙 𝑑ℎ ≥ 8𝑑 𝑏 𝑜𝑟 6" 𝑙 𝑎1 ≥ 𝑙 𝑑ℎ ≥ 8𝑑 𝑏 𝑜𝑟 6" 𝑙 𝑏1 ≥ 𝑙 𝑑ℎ ≥ 8𝑑 𝑏 𝑜𝑟 6" 𝑙 𝑎1 ≥ 𝑙 𝑑ℎ ≥ 8𝑑 𝑏 𝑜𝑟 6" Wide Column Clear cover ≥ 2" Clear cover ≥ 2" Primary Beam (a) Beam – Column Connections (b) Beam – Girder Connections To pg-15
  • 23. End Anchorage Lengths 23 (B) Using Alternate Method 𝑙𝑏2≥𝑙𝑑ℎ+14𝑑𝑏 𝑙 𝑎2 ≥ 𝑙 𝑑ℎ + 14𝑑 𝑏 Narrow Column Clear cover ≥ 2" Clear cover ≥ 2" Primary Beam (a) Beam – Column Connections (b) Beam – Girder Connections 𝑙 𝑎2 ≥ 𝑙 𝑑ℎ + 14𝑑 𝑏 𝑙𝑏2≥𝑙𝑑ℎ+11𝑑𝑏 ≥ 8𝑑 𝑏 𝑜𝑟 6" ≥ 8𝑑 𝑏 𝑜𝑟 6"
  • 24. End Anchorage Lengths 24 Anchorage Length for Girder with smaller bar sizes 𝑙 𝑚𝑎𝑥 ≈ 𝑏 + ℎ − 5.875 - 2.5 𝑑 𝑏 (for the outermost layer) 𝑙 𝑚𝑎𝑥 ≈ 𝑏 + ℎ − 5.875 - 6.5 𝑑 𝑏 (for the second layer) 𝑙 𝑚𝑎𝑥 ≈ 𝑏 + ℎ − 5.875 - 10.5 𝑑 𝑏 (for the third layer) h, b = depth and width of primary beam h
  • 25. End Anchorage Lengths 25 Structural Integrity Requirement
  • 26. Development Length from column to footing For the case where all the column bars are in compression, the dowels must extend into the footing a compression development length ldc . (a)Longitudinal bars in column are in compression The dowel bars are usually hooked and extend to the level of the flexural reinforcement in the footing. According to Section 12.5.5 ACI 318-05, the hooked portion of the dowels cannot be considered effective for developing the dowel bars in compression. 26
  • 27. Development Length from column to footing Either direct or uplift forces or transfer by a moment tensile force can act from column, the dowels must extend into the footing a tension development length ldt . (b)Longitudinal bars in column are in tension Tensile anchorage of the dowel bars into a footing is typically accomplished by providing 90-degree standard hooks at the ends of the dowel bars with the development length of the hooked bar, ldh, determined in accordance with Section 12.5 of ACI 318-14. 27
  • 28. Development Length Toe Myint Naing Curtin Sarawak Intern KSI Engineering
  • 29. Development Length (Lap splice inTension) 29 Class A Splice: 𝑙 𝑠𝑝𝑙𝑖𝑐𝑒,𝑡𝑒𝑛……………………….……….……….…..1.0𝑙 𝑑 ≥ 12” Class B Splice: 𝑙 𝑠𝑝𝑙𝑖𝑐𝑒,𝑡𝑒𝑛………………………….….………….…..1.3𝑙 𝑑 ≥ 12” For No.6 (20mm) and smaller bars, 𝐿 𝑑 = 𝑓𝑦 𝛼 25 𝑓′ 𝑐 × 𝑑 𝑏 𝐿 𝑑 = 𝑓𝑦 𝛼 20 𝑓′ 𝑐 × 𝑑 𝑏 For No.7 (22mm) and larger bars, Lap splicing of No.14 and No.18 bars in tension is prohibited. 50%
  • 30. Development Length (Lap splice in Compression) 30 𝒇 𝒚 ≤ 60,000 psi 𝒇 𝒚 >60,000 psi 𝑙 𝑠𝑝𝑙𝑖𝑐𝑒,𝑐𝑜𝑚 0.0005𝑓𝑦 𝑑 𝑏 (0.0009𝑓𝑦-24) 𝑑 𝑏 ≥ 12” For 𝑓′ 𝑐 < 3000 psi, 𝑙 𝑠𝑝𝑙𝑖𝑐𝑒,𝑐𝑜𝑚 shell be increased by one-third Where ties throughout the lap splice length have an effective area ≥ 0.0015h s, lap splice length shall be permitted to be multiplied by 0.83 ≥ 12” Lap splicing of No.14 and No.18 bars to No.11 and smaller bars in compression shell be permitted when 𝑙 𝑠𝑝𝑙𝑖𝑐𝑒,𝑐𝑜𝑚 = larger of [ 𝑙 𝑑𝑐 of larger bar and 𝑙 𝑠𝑝𝑙𝑖𝑐𝑒,𝑐𝑜𝑚 of smaller bar ]
  • 31. Development Length (Lap splice in Column) 31 Column – no restrictions Column – no restrictions Column – mid
  • 32. Development Length (Lap splice in Column) 32 50% LAPPING, CQHP
  • 33. Development Length (Lap splice inTension only in Column) 33 Class A Splice: 𝑙 𝑠𝑝𝑙𝑖𝑐𝑒,𝑡𝑒𝑛……………………….……….……….…..1.0𝑙 𝑑 ≥ 12” Class B Splice: 𝑙 𝑠𝑝𝑙𝑖𝑐𝑒,𝑡𝑒𝑛………………………….….………….…..1.3𝑙 𝑑 ≥ 12” For No.6 (20mm) and smaller bars, 𝐿 𝑑 = 𝑓𝑦 𝛼 25 𝑓′ 𝑐 × 𝑑 𝑏 𝐿 𝑑 = 𝑓𝑦 𝛼 20 𝑓′ 𝑐 × 𝑑 𝑏 For No.7 (22mm) and larger bars, Lap splicing of No.14 and No.18 bars in tension is prohibited. 100%
  • 34. Development Length (Lap splice in Column) 34
  • 35. Development Length (Lap splice in Column) 35
  • 36. Development Length (Lap splice in Column) 36
  • 37. Development Length (Lap splice in Column) 37
  • 38. Development Length (Lap splice in Column) 38
  • 39. Development Length (Lap splice in Column) 39
  • 40. Development Length (Lap splice in Column) 40
  • 41. Development Length (Lap splice in Column) 41
  • 42. Development Length (Lap splice in Column) 42
  • 43. Development Length (Lap splice in Column) 43
  • 44. Development Length (Lap splice in Column) 44
  • 45. Development Length (Lap splice in Column) 45
  • 46. Development Length (Lap splice in Column) 46
  • 47. Development Length (Lap splice in Column) 47
  • 48. Development Length (Lap splice in Column) 48
  • 49. Development Length (Lap splice in Column) 49
  • 50. Development Length (Lap splice in Column) 50
  • 51. Development Length (Lap splice in Column) 51
  • 52. Development Length (Lap splice in Column) 52
  • 53. Development Length (Lap splice in Column) 53
  • 54. Development Length (Lap splice in Column) 54
  • 55. Development Length (Lap splice in Column) 55
  • 56. Development Length (Lap splice in Column) 56
  • 57. Development Length (Lap splice in Column) 57
  • 58. Development Length (Lap splice in Column) 58
  • 59. Development Length (Lap splice in Beam) 59 Ordinary Moment-Resisting Frame Beam Top Bar – Mid Bot Bar – At Support or 2h Beam Top Bar – Mid Bot Bar – Outside 2h within L/3
  • 60. Development Length (Lap splice in Beam) 60 Ordinary Moment-Resisting Frame For closed stirrups for torsion spacing, smax = 𝑃ℎ 8 or 12”
  • 61. Development Length (Lap splice in Beam) 61 Intermediate Moment-Resisting Frame Special Moment-Resisting Frame Outside 2h ACI 318-05 ACI 318-08 Stirrups without seismic hook Stirrups with seismic hook Beam Top Bar – Mid Bot Bar – Mid
  • 62. Development Length (Lap splice in Beam) 62 Hoop reinforcement for beams Crosstie — A continuous reinforcing bar having a seismic hook at one end and a hook not less than 90° with at least a 6db extension at the other end. Hoop — A closed tie or continuously wound tie. A closed tie can be made up of several reinforcement elements each having seismic hooks at both ends. A continuously wound tie shall have a seismic hook at both ends.
  • 64. Development Length 64 Bars must extend the longer of d or 12db past the flexural cutoff points except at supports or the ends of cantilevers Structural Integrity Requirement
  • 65. 65 Simple Supports: At least one-third of the positive moment reinforcement must be extended 15 cm. into the supports Structural Integrity Requirement Development Length
  • 66. 66 Continuous interior beams with closed stirrups: At least one-fourth of the positive moment reinforcement must be extended 15 cm. into the support Structural Integrity Requirement Development Length
  • 67. 67 Continuous interior beams without closed stirrups: At least one-fourth of the positive moment reinforcement must be continuous or shall be spliced near the support with a class B tension splice and at non-continuous supports be terminated with a standard hook Splice Class ACI 318-05 ACI 318-08 Class A Class B Structural Integrity Requirement Development Length
  • 68. 68 Beams forming part of a frame that is the primary lateral load resisting system for the building.: This reinforcement must be anchored to develop the specified yield strength, fy , at the face of the support Structural Integrity Requirement Development Length
  • 69. 69 Interior beams: At least one-third of the negative moment reinforcement must be extended by the greatest of d, 12 db or 𝑙 𝑛 16 past the negative moment point of inflection. Structural Integrity Requirement Development Length
  • 70. 70 Perimeter beams: In addition, 1 6 of the (-) reinforcement required at the support must be made continuous at mid-span. This can be achieved by means of a class B tension splice at mid-span Splice Class ACI 318-05 ACI 318-08 Class A Class B Structural Integrity Requirement Development Length

Editor's Notes

  1. Sir Aung Myat Thu Pin – No moment – Compression Ldc Fix base – Moment transfer - Ldt
  2. During the placing and vibration of the concrete, some air and excess water tend to rise toward the top of the concrete, and some portion may be caught under the higher bars. In addition, there may be some settlement of the concrete below. As a result, the reinforcement does not bond as well to the concrete underneath, and increased development lengths will be needed
  3. Sir Aung Myat Thu Pin – No moment – Compression Ldc Fix base – Moment transfer - Ldt
  4. Sir Aung Myat Thu Pin – No moment – Compression Ldc Fix base – Moment transfer - Ldt
  5. Sir Aung Myat Thu Pin – No moment – Compression Ldc Fix base – Moment transfer - Ldt
  6. Sir Aung Myat Thu Pin – No moment – Compression Ldc Fix base – Moment transfer - Ldt
  7. Sir Aung Myat Thu Pin – No moment – Compression Ldc Fix base – Moment transfer - Ldt
  8. (c+ktr)/db = 1.5
  9. In high seismic cases cant use modification factor
  10. In high seismic cases cant use modification factor
  11. In high seismic cases cant use modification factor
  12. In high seismic cases cant use modification factor
  13. In high seismic cases cant use modification factor
  14. In high seismic cases cant use modification factor
  15. Cover < 2.5”, 0.8x doesnt not apply
  16. No.4 - 0.5” In the case of bars in compression, a part of total force is transferred by bond along the embedded length and a part is transferred by end bearing of the bars on the concrete. Because the surrounding concrete is relatively free of cracks and because of the beneficial effect of end bearing, Idc shorter Idt ,
  17. Cover beam , column = 1.5” Below concrete are already casted
  18. Cover beam , column = 1.5” Reduce bar size – reduce ld
  19. Cover beam , column = 1.5” Reduce beam size – reduce ld
  20. Cover beam , column = 1.5” Reduce beam size – reduce ld To develop fy at the face of support
  21. Straight Dowel bar – push straight dowels down into the concrete while it is still in concrete plastic stage. Theoretically, if the steel column is subjected to axial force only, then yes, there is no need for dowel bars | anchor bolts. But that is rarely the case. Column bases are almost always subjected to bending moments in addition to compression, sometimes even torsion. Moments and | or torsion causes tension at one side of the column base making it move outwards and upwards.
  22. Development length မလံုေလာက္ခဲ့ရင္ standard 90° hook သံုးၿပီး Ldh ေျပာင္းတြက္ရပါမယ္၊ ဇကာ သံလံုးကို 16mm ကေန 25mm ၾကား သံုးေလ့ ရွိၾကတာမို႔ အၾကမ္းဖ်င္း ေျပာရရင္ေတာ့ 5 ေပ ပတ္လည္ေအာက္ footing ေတြဟာ Ld မလံုေလာက္တတ္ပါဘူး၊ hook လိုအပ္ေလ့ ရွိၾကပါတယ္။ Compression forces are transferred through direct bearing while tension forces are transferred through developed reinforcement. When column sizes are not same, Bot large, top small. Pe.. Eccentricity The only way the moment can be transfered into the footing is through tension reinforcement that will keep the column from cracking and breaking free from the footing due to the bending moment. T
  23. bar forces are so large they can split the concrete and destroy the effectiveness of the lap splice. The development length ld used to obtain lap length should be based on fy because the splice classifications already reflect any excess reinforcement at the splice location; therefore, the factor from 12.2.5 for excess As should not be used. သံေခ်ာင္းတစ္ေခ်ာင္း၏ေပရွည္သည္ 12Meter…39.5Ft ရွိပါသည္။
  24. Tie area >= 0.0015hs
  25. There are no restrictions on the location of lap splices in intermediate or ordinary moment frames. smax Note that the column splice should satisfy requirements for all load combinations for the column. Frequently, the basic gravity load combination will govern the design of the column itself, but a load combination including wind or seismic loads may induce greater tension in some column bars, and the column splice should be designed for this tension. (Reinforcing bars in columns may be subjected to comp or tension or different load combination, both ten and compression. ACI code 12.17 require that a minimum tension capacity be provided in each face of all columns even where analysis indicates compression only. Ordinary compressive lap splices provide sufficient tensile resistance, but end-bearing splices may require additional bars for tension, unless the splices are staggered. ) If bar stress due to factored load is compression, compression splice When stress is tension <0.5fy, spliced ½ of bar, Class B. Spliced <=1/2 of bar and splices are staggered by ld, Class A. When stress is tension >0.5fy, Class B Max slope 1:6 Can lap 100% in SMRF, according to CQHP 50%
  26. If bar stress due to factored load is compression, compression splice When stress is tension <0.5fy, spliced ½ of bar, Class B. Spliced <=1/2 of bar and splices are staggered by ld, Class A. When stress is tension >0.5fy, Class B
  27. Minimum steel
  28. Minimum steel
  29. Minimum steel
  30. Minimum steel
  31. Minimum steel
  32. Minimum steel
  33. Minimum steel
  34. Minimum steel
  35. Minimum steel
  36. Minimum steel
  37. Minimum steel
  38. SPECIAL TIES TO RESIST OUTWARD THRUST
  39. Minimum steel
  40. Minimum steel
  41. Minimum steel
  42. Minimum steel
  43. Minimum steel
  44. Minimum steel
  45. Column ကို (SMRF) စဥ္းစားျပီး lapping လုပ္မယ္ဆိုရင္ ၾကိဳက္တဲ့ rebar ကို crank လုပ္ျပီး ဆက္လို႔ရပါတယ္။ တစ္ခ်ိဳ႕က ေအာက္က လာတဲ့ rebar ကို တစ္ခါတည္း crank လုပ္ျပီး အေပၚက rebar နဲ႕ဆက္ၾကပါတယ္။ တစ္ခ်ိဳ႕ကေတာ့ rebar position ခ်တဲ့အခါ မွားမွာစိုးလို႔ ေအာက္က လာတဲ့ rebar ကို အေျဖာင့္ထားျပီး အေပၚက rebar ကို crank လုပ္ကာ ဆက္ၾကပါတယ္။ အဆင္ေျပသလို ဆက္နိုင္ပါတယ္။ ဒါေပမဲ့ တကယ္လို႔မ်ား အေၾကာင္းအမ်ိဳးမ်ိဳးေၾကာင့္ floor level မွာ rebar ကို lapping လုပ္ရမယ္ဆိုရင္ေတာ့ က်ေနာ္တို႔မွာ စဥ္းစားစရာေတြ ရွိလာပါမယ္။ (1) ေအာက္က လာတဲ့ rebar ကို crank လုပ္ျပီး lapping လုပ္မလား (2) အေပၚက လာတဲ့ rebar ကို crank လုပ္ျပီ္း lapping လုပ္မလား (3) အေျဖာင့္အတိုင္း ဆက္မလား (No. 1) အမ်ိဳးအစားျဖစ္တဲ့ ေအာက္က လာတဲ့ rebar ကို crank လုပ္ျပီး lapping ဆက္ျခင္းကို အသံုးျပဳသင့္ပါတယ္။ ဘာလို႔လဲဆိုေတာ့ ဒီလို ဆက္ျခင္းက Flexural strength ကိုေတာ့ နည္းပါးေစပါတယ္။ ဒါေပမဲ့ deformation ႏွင့္ energy dissipation capacities ကို ျမင့္မားပါတယ္။ Concrete ဟာ brittle material ျဖစ္တဲ့အတြက္ ၾကြပ္ဆပ္ပါတယ္။ ဒါေၾကာင့္ သတ္မွတ္ဝန္အားထက္ ပိုသက္ေရာက္လာတဲ့အခါမ်ိဳးမွာ ခ်က္ခ်င္းက်ိဳးက်ပ်က္စီးတာမ်ိဳးေတြ ျဖစ္ပါမယ္။ ဒါေပမဲ့ ဒီလိုဆက္ျခင္းအားျဖင့္ concrete ဟာ deformation ျဖစ္တာ (တနည္းအားျဖင့္) ductility ျဖစ္တာ ေတြ ပိုအားေကာင္းလာတဲ့ အတြက္ေၾကာင့္ ဝန္အား ပိုသက္ေအာက္တဲ့အခါ မ်ိဳးမွာ ခ်က္ျခင္းက်ိဳးတာေတြ မျဖစ္ေစပဲ မူလပံုသဏၭာန္မွ deformation ျဖစ္သြားတာကို အတိုင္းအတာတစ္ခုထိ ခံနိုင္သြားပါမယ္။ Energy Dissipation ဆိုတာက Deformation နဲ႔ ဆက္စပ္ပါတယ္။ Energy Dissipation မ်ားရင္ Deformation မ်ားပါတယ္။ သက္မွတ္ဝန္အားထက္ ပိုသက္ေရာက္လာတဲ့ အခါမ်ိဳးမွာ member ေတြဟာ deformation ျဖစ္ပါတယ္။ အခု ဒီလိုဆက္ျခင္းက Dissipation energy မ်ားတဲ့အတြက္ deformation ျဖစ္တာကိုလည္း No.(2) ႏွင့္ No.(3) လို lapping လုပ္ျခင္းထက္ ပိုခံနိုင္ပါမယ္။ Crank လုပ္တဲ့အခါလည္း Slab ေလာင္းျပီးလို႔ floor level ေရာက္မွ rebar ကို crank လုပ္တာမ်ိဳးမဟုတ္ပဲ Slab မေလာင္းခင္ကတည္းက rebar ကို crank လုပ္ေပးရပါမယ္။ ျပီးေတာ့ crank length ကို beam rebar အတြင္းမွာ ထားျပီး သံဆင္ရပါမယ္။ ACI code က (16 mm) rebar နဲ႕ ေအာက္ rebar ေတြကိုပဲ Site မွာ crank လုပ္ခြင့္ေပးပါတယ္။ (16 mm) rebar နဲ႕ အထက္ rebar ေတြကို အပူေပးျပီးမွ crank လုပ္ဖို႔ ခြင့္ျပဳထားပါတယ္။ အပူမေပးပဲ crank လုပ္တဲ့အခါ rebar နာသြားျပီး ခံနိုင္အား နည္းသြားလို႔ လုပ္ခြင့္မေပးတာပါ။
  46. Minimum steel
  47. Minimum steel
  48. Minimum steel
  49. Minimum steel
  50. Column ကို (SMRF) စဥ္းစားျပီး lapping လုပ္မယ္ဆိုရင္ ၾကိဳက္တဲ့ rebar ကို crank လုပ္ျပီး ဆက္လို႔ရပါတယ္။ တစ္ခ်ိဳ႕က ေအာက္က လာတဲ့ rebar ကို တစ္ခါတည္း crank လုပ္ျပီး အေပၚက rebar နဲ႕ဆက္ၾကပါတယ္။ တစ္ခ်ိဳ႕ကေတာ့ rebar position ခ်တဲ့အခါ မွားမွာစိုးလို႔ ေအာက္က လာတဲ့ rebar ကို အေျဖာင့္ထားျပီး အေပၚက rebar ကို crank လုပ္ကာ ဆက္ၾကပါတယ္။ အဆင္ေျပသလို ဆက္နိုင္ပါတယ္။ ဒါေပမဲ့ တကယ္လို႔မ်ား အေၾကာင္းအမ်ိဳးမ်ိဳးေၾကာင့္ floor level မွာ rebar ကို lapping လုပ္ရမယ္ဆိုရင္ေတာ့ က်ေနာ္တို႔မွာ စဥ္းစားစရာေတြ ရွိလာပါမယ္။ (1) ေအာက္က လာတဲ့ rebar ကို crank လုပ္ျပီး lapping လုပ္မလား (2) အေပၚက လာတဲ့ rebar ကို crank လုပ္ျပီ္း lapping လုပ္မလား (3) အေျဖာင့္အတိုင္း ဆက္မလား (No. 1) အမ်ိဳးအစားျဖစ္တဲ့ ေအာက္က လာတဲ့ rebar ကို crank လုပ္ျပီး lapping ဆက္ျခင္းကို အသံုးျပဳသင့္ပါတယ္။ ဘာလို႔လဲဆိုေတာ့ ဒီလို ဆက္ျခင္းက Flexural strength ကိုေတာ့ နည္းပါးေစပါတယ္။ ဒါေပမဲ့ deformation ႏွင့္ energy dissipation capacities ကို ျမင့္မားပါတယ္။ Concrete ဟာ brittle material ျဖစ္တဲ့အတြက္ ၾကြပ္ဆပ္ပါတယ္။ ဒါေၾကာင့္ သတ္မွတ္ဝန္အားထက္ ပိုသက္ေရာက္လာတဲ့အခါမ်ိဳးမွာ ခ်က္ခ်င္းက်ိဳးက်ပ်က္စီးတာမ်ိဳးေတြ ျဖစ္ပါမယ္။ ဒါေပမဲ့ ဒီလိုဆက္ျခင္းအားျဖင့္ concrete ဟာ deformation ျဖစ္တာ (တနည္းအားျဖင့္) ductility ျဖစ္တာ ေတြ ပိုအားေကာင္းလာတဲ့ အတြက္ေၾကာင့္ ဝန္အား ပိုသက္ေအာက္တဲ့အခါ မ်ိဳးမွာ ခ်က္ျခင္းက်ိဳးတာေတြ မျဖစ္ေစပဲ မူလပံုသဏၭာန္မွ deformation ျဖစ္သြားတာကို အတိုင္းအတာတစ္ခုထိ ခံနိုင္သြားပါမယ္။ Energy Dissipation ဆိုတာက Deformation နဲ႔ ဆက္စပ္ပါတယ္။ Energy Dissipation မ်ားရင္ Deformation မ်ားပါတယ္။ သက္မွတ္ဝန္အားထက္ ပိုသက္ေရာက္လာတဲ့ အခါမ်ိဳးမွာ member ေတြဟာ deformation ျဖစ္ပါတယ္။ အခု ဒီလိုဆက္ျခင္းက Dissipation energy မ်ားတဲ့အတြက္ deformation ျဖစ္တာကိုလည္း No.(2) ႏွင့္ No.(3) လို lapping လုပ္ျခင္းထက္ ပိုခံနိုင္ပါမယ္။ Crank လုပ္တဲ့အခါလည္း Slab ေလာင္းျပီးလို႔ floor level ေရာက္မွ rebar ကို crank လုပ္တာမ်ိဳးမဟုတ္ပဲ Slab မေလာင္းခင္ကတည္းက rebar ကို crank လုပ္ေပးရပါမယ္။ ျပီးေတာ့ crank length ကို beam rebar အတြင္းမွာ ထားျပီး သံဆင္ရပါမယ္။ ACI code က (16 mm) rebar နဲ႕ ေအာက္ rebar ေတြကိုပဲ Site မွာ crank လုပ္ခြင့္ေပးပါတယ္။ (16 mm) rebar နဲ႕ အထက္ rebar ေတြကို အပူေပးျပီးမွ crank လုပ္ဖို႔ ခြင့္ျပဳထားပါတယ္။ အပူမေပးပဲ crank လုပ္တဲ့အခါ rebar နာသြားျပီး ခံနိုင္အား နည္းသြားလို႔ လုပ္ခြင့္မေပးတာပါ။
  51. There are no restrictions on the location of lap splices in intermediate or ordinary moment frames. Note that the column splice should satisfy requirements for all load combinations for the column. Frequently, the basic gravity load combination will govern the design of the column itself, but a load combination including wind or seismic loads may induce greater tension in some column bars, and the column splice should be designed for this tension. (Reinforcing bars in columns may be subjected to comp or tension or different load combination, both ten and compression. ACI code 12.17 require that a minimum tension capacity be provided in each face of all columns even where analysis indicates compression only. Ordinary compressive lap splices provide sufficient tensile resistance, but end-bearing splices may require additional bars for tension, unless the splices are staggered. ) If bar stress due to factored load is compression, compression splice When stress is tension <0.5fy, spliced ½ of bar, Class B. Spliced <=1/2 of bar and splices are staggered by ld, Class A. When stress is tension >0.5fy, Class B Max slope 1:6
  52. Support ကေန L/3 အတြင္းမွာ cutting length ျဖတ္ေပးရပါမယ္။ End support / middle support သေဘာတရားအတူတူပါပဲ။ ဘာလို႔လဲဆိုေတာ့ က်ေနာ္တို႔က L/3 ေနရာကို negative moment ကေန positive moment ေျပာင္းတဲ့ေနရာလို႔ ယူဆထားပါတယ္။ Engineering အေခၚအရ point of inflection လို႔ေခၚပါတယ္။ moment zero ျဖစ္တဲ့ေနရာပါ။ တကယ္တမ္းက L/3 ေနရာမွာ point of inflection ျဖစ္ခ်င္မွျဖစ္ပါမယ္။ ကိုယ္တိုင္ moment diagram ဆြဲၾကည့္မွ သိနိုင္ပါမယ္။ ဒါေပမဲ့ L/3 ေနရာဟာ rebar ကို cutting length လုပ္ရင္ safe ျဖစ္တဲ့အတြက္ L/3 ေနရာကိုပဲ လုပ္ငန္းခြင္မွာ ျဖတ္ၾကပါတယ္။ အျခဳပ္ေျပာရရင္ = L/3 ေနရာဟာ negative moment အတြက္ rebar လိုအပ္ခ်က္ လံုေလာက္တယ္လို႔ ယူဆတဲ့အတြက္ L/3 ေနရာမွာ ျဖတ္ျခင္းျဖစ္ပါတယ္။ At locations where analysis indicates flexural yielding caused by inelastic lateral displacements of the frame
  53. ØVc = Ø 2 √f’c bd Ph = perimeter of stirrup centre
  54. U nyi hla nge – inter – seismic Lap splices are not to be used: • Within joints. • Within 2h • At locations where analysis indicates flexural yielding caused by inelastic lateral displacements of the frame. Column hoops should be configured with at least 3 hoop or crosstie legs restraining longitudinal bars along each face. A single perimeter hoop without crossties, legally permitted by ACI 318 for small column cross section
  55. Support ကေန L/3 အတြင္းမွာ cutting length ျဖတ္ေပးရပါမယ္။ End support / middle support သေဘာတရားအတူတူပါပဲ။ ဘာလို႔လဲဆိုေတာ့ က်ေနာ္တို႔က L/3 ေနရာကို negative moment ကေန positive moment ေျပာင္းတဲ့ေနရာလို႔ ယူဆထားပါတယ္။ Engineering အေခၚအရ point of inflection လို႔ေခၚပါတယ္။ moment zero ျဖစ္တဲ့ေနရာပါ။ တကယ္တမ္းက L/3 ေနရာမွာ point of inflection ျဖစ္ခ်င္မွျဖစ္ပါမယ္။ ကိုယ္တိုင္ moment diagram ဆြဲၾကည့္မွ သိနိုင္ပါမယ္။ ဒါေပမဲ့ L/3 ေနရာဟာ rebar ကို cutting length လုပ္ရင္ safe ျဖစ္တဲ့အတြက္ L/3 ေနရာကိုပဲ လုပ္ငန္းခြင္မွာ ျဖတ္ၾကပါတယ္။ အျခဳပ္ေျပာရရင္ = L/3 ေနရာဟာ negative moment အတြက္ rebar လိုအပ္ခ်က္ လံုေလာက္တယ္လို႔ ယူဆတဲ့အတြက္ L/3 ေနရာမွာ ျဖတ္ျခင္းျဖစ္ပါတယ္။
  56. Class B ACI 7.13.2.2 (b)
  57. Class B
  58. Class B
  59. Class B