SlideShare a Scribd company logo
1 of 17
CN2114- CONTRACT LAWS AND REGULATIONS
SRM UNIVERSITY
Kattankulathur, Chennai – 603203
A presentation on
DISPUTE REVIEW BOARDS
By
T.Surya Prakash reddy - RA1612002010030
CONTACT NO 8008916165
REASONS FOR ALTERNATE DISPUTE
RESOLUTION
1. Variation in the quantities of work
2. Payment of rates for the excess/ extra quantities
3. Interpretation of the contract drawings and designs
4. Sub soil classification
5. Quantum of de-watering during excavation
6. Quality of work and workmanship
7. Time of performance and extensions
8. Delays in performance of the contract due to faults of the
owner/engineer
9. Delay in the performance due to faults on the part of the
contractor
10. Delay in getting possession of the site work and its actual
release
11. Delay in making due payment to the contractor
12. Decisions as regards the delay falling within the scope
13. Refund and failure of security deposit
14. Quality of materials used
NEED OF ADR
• The number of litigation in civil is rising at an
alarming rate.
• The resources to deal with cases in the courts are
also very limited.
• The number of judges and court rooms are also
not sufficient.
• We have to spend a considerable portion of funds
to meet with the costs of litigation and for
payment to lawyers.
• The procedure is cumbersome and involves loss of
time.
• Money spent on fighting court cases and paying
fees to lawyers can be utilized for the best
interests of the beneficiaries of developmental
activities.
NEED OF ADR…….Contd
• It is therefore, high time, that some systems and
methods of alternative dispute resolution are
developed, so that the disputes can be decided during
process of the execution of the work/project by way,
of mutual understanding and necessarily not after the
disputes are placed before the arbitrator.
METHODS OF ALTERNATE DISPUTE
RESOLUTION
1. Advisory Arbitration
2. Dispute review boards (DRB)
3. Conciliation
4. Executive tribunal
5. Expert appraisal
6. Negotiations
AIM/RESPONSIBILITIES OF DRB
• Reduction in court over crowding.
• Lowering of barriers to access.
• Achievement of superior resolution.
• Injecting power into local communities to
handle their own disputes.
• Reduction of costs.
• Production of a less contentious society by
adopting a process of resolution by effective
use of mediation, arbitration and various
composite techniques.
DISPUTE REVIEW BOARDS
• The DRB method of dispute resolution was developed by the
committee on contracting practices of the underground technology
research council of ASCE.
• For major engineering projects, the method of dispute review and
resolution boards sounds to be the most appropriate method.
• This consists of appointing a high level body, consisting of the
representatives of the owner/engineer as well the contracting
agency.
• The board also includes the Project managers of different
professions concerned with the implementation of the project as
well as representative of the contractor.
• Professional and legal experts who are not a part of the project
organization, can also be made member of the dispute resolution
board(DRB).
• The DRB should be appointed right at the time of the commencement of
the project and award of contracts.
• A specific clause should be prescribed in the contract stating all disputes
relating to the contract shall be put up to the DRB and the decision of the
board shall be final and binding to all the parties to a contract.
• The DRB comprises three members: one selected by the owner, one by the
contractor, and a third selected by the first two.
• All DRB members are impartial and experienced in construction. They are
appointed soon after the contract is awarded
• DRB members are sent progress reports and visit the project periodically.
• The DRB is not used for routine claims or differences of opinion, but for
the resolution of major problems.
• The recommendations of the DRB are not legally binding, but are not
likely to be reversed in litigation.
PROCESS OF DRB
• The DRB operates under rules specified in the contract. Usually these rules
are the rules of a nominating authority such as the National Technology
Dispute Centre.
• At the commencement of the project, the DRB meets and is provided with
sufficient project documentation to enable them to become familiar with the
project deliverables, schedules, budgets, risks and issues. The DRB meets on
a regular basis, usually on site and usually with representatives from the
parties’ project teams.
• When a dispute or issue is referred to the DRB, the DRB considers the
dispute and makes a recommendation. Unless a party objects within a set
period of time, the recommendation becomes binding under the contract.
• If a party objects the dispute may be referred to other resolution mechanisms,
usually litigation. The recommendations of a DRB are usually “with
prejudice”. That is, the recommendations can be used by a party during
litigation.
COST OF DRB
• There are two costs associated with a DRB.
• The first is the initial set up cost. This provides the
parties with the structure within which to establish the
DRB. The set up cost includes a license to use the DRB
Rules, the clauses to add into a contract and a
nominating authority to appoint members if the parties
can not.
• The second cost is the monthly retainer for each DRB
member. For most large projects this is equivalent to 2-
3 man days for each member per month. For smaller
projects it can be as low as 1 man day for each member
per month.
FUNCTIONS OF DRB
• The primary function of a Dispute Board is to assist the parties to avoid disputes if possible
by facilitating and improving communication and encouraging the resolution of
contentious issues by the parties at the job level before they become disputes, or if not, to
assist them to resolve disputes quickly and cost effectively without the need for arbitration
or litigation.
• The DRB shall serve as an advisory body to assist in the resolution of disputes between
the State and the Contractor, hereinafter referred to as the "parties."
• The DRB can be made to meet at regular periodical intervals to review the activities
relating to the contracts and also discuss and decide the issues which are likely to result
into disputes.
• This would help in solving the problems before the actual disputes, both the parties i.e the
Engineer in charge and the contractor can put up their views and claims before the DRB.
• The board, after hearing the views put up by both parties and its own evaluation and
examination of relevant materials on record, can take a final decision leading to the
resolution of dispute.
In case of government and public sector organizations DRB’s can be
constituted at various levels.
1.For small projects at district level
a) District collector – Chairman
b)Concerned executive engineer – Member
c) Other executive engineer – Member
d) Representative of the contractor – Member
2.For medium and regional level projects
a) Concerned Chief engineer – Chairman
b)Concerned superintending engineer – Member
c) One other superintending engineer – Member
d) One outside expert – Member
d) Representative of the contractor – Member
3.At state level and for major projects
a) Chief executive of the organization – Chairman
b)Financial advisor/controller – Member
c) Engineer in chief – Member
d) Two senior outside experts – Members
(one to be nominated by contractor)
d) Representative of the contractor – Member
ADVANTAGES OF DISPUTES REVIEW BOARDS
• The DRB hears disputes on an informal basis and can provide
recommendations for their timely resolution before parties
adopt hard positions leading to litigation.
• The parties are comfortable with the recommendations of the
DRB since the selection of the DRB members is controlled by
the owner and the contractor.
• Because they meet periodically and they are sent progress
reports, the DRB members are familiar with the elements of the
project.
• Although the DRB recommendations are not binding on either
party, there is strong motivation to accept the findings
DISADVANTAGES OF DISPUTES REVIEW
BOARDS
• The impartiality and conflict-of- interest portion of the
DRB specification is so tough that sometimes there are
not enough qualified people for the DRB.
• The project must be large enough, and the probability of
the occurrence of disputes throughout the course of the
project must be high enough to justify the expense of
retaining the services of the DRB members for the entire
duration of the project.
LIMITATIONS OF DISPUTE REVIEW BOARDS
•DRBs add expense but not add value to the project
•presence of bias or lack of qualifications in Board
members
•DRBs impose personal equity rather than contract
provisions
•presence of a DRB will promote claims
•DRBs are unreliable because they lack the formalities of
legal proceedings
•historical culture of “power & control”
•expectation of a binding decision
•in high value disputes, losing party motivated to try
litigation
•parties may undermine the DRB process
CONCLUSION
• Alternate dispute resolution mechanism
will relieve us from the tedious court
procedures and defects of arbitration.
• It would save both National time and
National costs.
DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS- ADVANTAGES AND DIS ADVANTAGES

More Related Content

What's hot

Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Processarpantripathi2
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & managementManit Agarwal
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Constructionshillier38
 
Presentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionPresentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionJustin DeMerchant
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-ContractsNikhil Kumar
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in constructionMahSobeh
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and ArbitrationJIT KUMAR GUPTA
 
BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTVISHNU VIJAYAN
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tenderingvvsasane
 

What's hot (20)

Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Process
 
Construction planning & management
Construction planning & managementConstruction planning & management
Construction planning & management
 
fidic , jct and nec contracts
fidic , jct and nec contractsfidic , jct and nec contracts
fidic , jct and nec contracts
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Construction disputes
Construction disputesConstruction disputes
Construction disputes
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Construction
 
Presentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute ResolutionPresentation - Construction Contract Dispute Resolution
Presentation - Construction Contract Dispute Resolution
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Unit-2_Tender
Unit-2_TenderUnit-2_Tender
Unit-2_Tender
 
Construction tender process
Construction tender processConstruction tender process
Construction tender process
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in construction
 
contract procedure
contract procedurecontract procedure
contract procedure
 
Contract and Arbitration
Contract and ArbitrationContract and Arbitration
Contract and Arbitration
 
Tpt's tendering process at a glance
Tpt's tendering process at a glanceTpt's tendering process at a glance
Tpt's tendering process at a glance
 
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B M
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B MModule-1:Introduction to Construction Management by Dr. Vinay Kumar B M
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B M
 
Contracts
ContractsContracts
Contracts
 
BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACT
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 

Similar to DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS- ADVANTAGES AND DIS ADVANTAGES

Civil engineering practice (lec 5)
Civil engineering practice (lec 5)Civil engineering practice (lec 5)
Civil engineering practice (lec 5)Muhammad Khan
 
Early Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction IndustryEarly Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction IndustryFrancis Ho
 
Chapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptxChapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptxssuserc0bf9b
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptxjairam131
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxIrfanAwan25
 
01 drbf event almaty 2018 adriana eng
01 drbf event almaty 2018 adriana eng01 drbf event almaty 2018 adriana eng
01 drbf event almaty 2018 adriana engAndrey Artyushenko
 
Professional Practice for Architecture II
Professional Practice for Architecture IIProfessional Practice for Architecture II
Professional Practice for Architecture IIAr. Mukunda K.S
 
Waste Contracts Administration and Performance Monitoring
Waste Contracts Administration and Performance MonitoringWaste Contracts Administration and Performance Monitoring
Waste Contracts Administration and Performance MonitoringCircular Economy Asia
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014SHKLaw
 
CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxAditya Mane
 
ConstructionFlow
ConstructionFlowConstructionFlow
ConstructionFlowJeff Dixon
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract AdministrationGerald R. (Jerry) Genge
 

Similar to DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS- ADVANTAGES AND DIS ADVANTAGES (20)

Civil engineering practice (lec 5)
Civil engineering practice (lec 5)Civil engineering practice (lec 5)
Civil engineering practice (lec 5)
 
Early Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction IndustryEarly Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction Industry
 
Peer Review and "53 G"
Peer Review and "53 G"Peer Review and "53 G"
Peer Review and "53 G"
 
Chapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptxChapter_2-Procurement and Contract management.pptx
Chapter_2-Procurement and Contract management.pptx
 
Unit V - Contracts.pptx
Unit V - Contracts.pptxUnit V - Contracts.pptx
Unit V - Contracts.pptx
 
PECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptxPECDisputeResolution25102018.pptx
PECDisputeResolution25102018.pptx
 
01 drbf event almaty 2018 adriana eng
01 drbf event almaty 2018 adriana eng01 drbf event almaty 2018 adriana eng
01 drbf event almaty 2018 adriana eng
 
CCDC 2 Dispute Resolution
CCDC 2 Dispute ResolutionCCDC 2 Dispute Resolution
CCDC 2 Dispute Resolution
 
Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]Chapter 4 [compatibility mode]
Chapter 4 [compatibility mode]
 
Professional Practice for Architecture II
Professional Practice for Architecture IIProfessional Practice for Architecture II
Professional Practice for Architecture II
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
 
Lecture 1.pptx
Lecture 1.pptxLecture 1.pptx
Lecture 1.pptx
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
Waste Contracts Administration and Performance Monitoring
Waste Contracts Administration and Performance MonitoringWaste Contracts Administration and Performance Monitoring
Waste Contracts Administration and Performance Monitoring
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptx
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
ConstructionFlow
ConstructionFlowConstructionFlow
ConstructionFlow
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 

Recently uploaded

High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 

Recently uploaded (20)

High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 

DISPUTE REVIEW BOARDS -REASONS-NEED-METHODS-RESPONSIBILITIES-PROCESFUNCTIONS- ADVANTAGES AND DIS ADVANTAGES

  • 1. CN2114- CONTRACT LAWS AND REGULATIONS SRM UNIVERSITY Kattankulathur, Chennai – 603203 A presentation on DISPUTE REVIEW BOARDS By T.Surya Prakash reddy - RA1612002010030 CONTACT NO 8008916165
  • 2. REASONS FOR ALTERNATE DISPUTE RESOLUTION 1. Variation in the quantities of work 2. Payment of rates for the excess/ extra quantities 3. Interpretation of the contract drawings and designs 4. Sub soil classification 5. Quantum of de-watering during excavation 6. Quality of work and workmanship 7. Time of performance and extensions 8. Delays in performance of the contract due to faults of the owner/engineer 9. Delay in the performance due to faults on the part of the contractor 10. Delay in getting possession of the site work and its actual release 11. Delay in making due payment to the contractor 12. Decisions as regards the delay falling within the scope 13. Refund and failure of security deposit 14. Quality of materials used
  • 3. NEED OF ADR • The number of litigation in civil is rising at an alarming rate. • The resources to deal with cases in the courts are also very limited. • The number of judges and court rooms are also not sufficient. • We have to spend a considerable portion of funds to meet with the costs of litigation and for payment to lawyers. • The procedure is cumbersome and involves loss of time. • Money spent on fighting court cases and paying fees to lawyers can be utilized for the best interests of the beneficiaries of developmental activities.
  • 4. NEED OF ADR…….Contd • It is therefore, high time, that some systems and methods of alternative dispute resolution are developed, so that the disputes can be decided during process of the execution of the work/project by way, of mutual understanding and necessarily not after the disputes are placed before the arbitrator.
  • 5. METHODS OF ALTERNATE DISPUTE RESOLUTION 1. Advisory Arbitration 2. Dispute review boards (DRB) 3. Conciliation 4. Executive tribunal 5. Expert appraisal 6. Negotiations
  • 6. AIM/RESPONSIBILITIES OF DRB • Reduction in court over crowding. • Lowering of barriers to access. • Achievement of superior resolution. • Injecting power into local communities to handle their own disputes. • Reduction of costs. • Production of a less contentious society by adopting a process of resolution by effective use of mediation, arbitration and various composite techniques.
  • 7. DISPUTE REVIEW BOARDS • The DRB method of dispute resolution was developed by the committee on contracting practices of the underground technology research council of ASCE. • For major engineering projects, the method of dispute review and resolution boards sounds to be the most appropriate method. • This consists of appointing a high level body, consisting of the representatives of the owner/engineer as well the contracting agency. • The board also includes the Project managers of different professions concerned with the implementation of the project as well as representative of the contractor. • Professional and legal experts who are not a part of the project organization, can also be made member of the dispute resolution board(DRB).
  • 8. • The DRB should be appointed right at the time of the commencement of the project and award of contracts. • A specific clause should be prescribed in the contract stating all disputes relating to the contract shall be put up to the DRB and the decision of the board shall be final and binding to all the parties to a contract. • The DRB comprises three members: one selected by the owner, one by the contractor, and a third selected by the first two. • All DRB members are impartial and experienced in construction. They are appointed soon after the contract is awarded • DRB members are sent progress reports and visit the project periodically. • The DRB is not used for routine claims or differences of opinion, but for the resolution of major problems. • The recommendations of the DRB are not legally binding, but are not likely to be reversed in litigation.
  • 9. PROCESS OF DRB • The DRB operates under rules specified in the contract. Usually these rules are the rules of a nominating authority such as the National Technology Dispute Centre. • At the commencement of the project, the DRB meets and is provided with sufficient project documentation to enable them to become familiar with the project deliverables, schedules, budgets, risks and issues. The DRB meets on a regular basis, usually on site and usually with representatives from the parties’ project teams. • When a dispute or issue is referred to the DRB, the DRB considers the dispute and makes a recommendation. Unless a party objects within a set period of time, the recommendation becomes binding under the contract. • If a party objects the dispute may be referred to other resolution mechanisms, usually litigation. The recommendations of a DRB are usually “with prejudice”. That is, the recommendations can be used by a party during litigation.
  • 10. COST OF DRB • There are two costs associated with a DRB. • The first is the initial set up cost. This provides the parties with the structure within which to establish the DRB. The set up cost includes a license to use the DRB Rules, the clauses to add into a contract and a nominating authority to appoint members if the parties can not. • The second cost is the monthly retainer for each DRB member. For most large projects this is equivalent to 2- 3 man days for each member per month. For smaller projects it can be as low as 1 man day for each member per month.
  • 11. FUNCTIONS OF DRB • The primary function of a Dispute Board is to assist the parties to avoid disputes if possible by facilitating and improving communication and encouraging the resolution of contentious issues by the parties at the job level before they become disputes, or if not, to assist them to resolve disputes quickly and cost effectively without the need for arbitration or litigation. • The DRB shall serve as an advisory body to assist in the resolution of disputes between the State and the Contractor, hereinafter referred to as the "parties." • The DRB can be made to meet at regular periodical intervals to review the activities relating to the contracts and also discuss and decide the issues which are likely to result into disputes. • This would help in solving the problems before the actual disputes, both the parties i.e the Engineer in charge and the contractor can put up their views and claims before the DRB. • The board, after hearing the views put up by both parties and its own evaluation and examination of relevant materials on record, can take a final decision leading to the resolution of dispute.
  • 12. In case of government and public sector organizations DRB’s can be constituted at various levels. 1.For small projects at district level a) District collector – Chairman b)Concerned executive engineer – Member c) Other executive engineer – Member d) Representative of the contractor – Member 2.For medium and regional level projects a) Concerned Chief engineer – Chairman b)Concerned superintending engineer – Member c) One other superintending engineer – Member d) One outside expert – Member d) Representative of the contractor – Member 3.At state level and for major projects a) Chief executive of the organization – Chairman b)Financial advisor/controller – Member c) Engineer in chief – Member d) Two senior outside experts – Members (one to be nominated by contractor) d) Representative of the contractor – Member
  • 13. ADVANTAGES OF DISPUTES REVIEW BOARDS • The DRB hears disputes on an informal basis and can provide recommendations for their timely resolution before parties adopt hard positions leading to litigation. • The parties are comfortable with the recommendations of the DRB since the selection of the DRB members is controlled by the owner and the contractor. • Because they meet periodically and they are sent progress reports, the DRB members are familiar with the elements of the project. • Although the DRB recommendations are not binding on either party, there is strong motivation to accept the findings
  • 14. DISADVANTAGES OF DISPUTES REVIEW BOARDS • The impartiality and conflict-of- interest portion of the DRB specification is so tough that sometimes there are not enough qualified people for the DRB. • The project must be large enough, and the probability of the occurrence of disputes throughout the course of the project must be high enough to justify the expense of retaining the services of the DRB members for the entire duration of the project.
  • 15. LIMITATIONS OF DISPUTE REVIEW BOARDS •DRBs add expense but not add value to the project •presence of bias or lack of qualifications in Board members •DRBs impose personal equity rather than contract provisions •presence of a DRB will promote claims •DRBs are unreliable because they lack the formalities of legal proceedings •historical culture of “power & control” •expectation of a binding decision •in high value disputes, losing party motivated to try litigation •parties may undermine the DRB process
  • 16. CONCLUSION • Alternate dispute resolution mechanism will relieve us from the tedious court procedures and defects of arbitration. • It would save both National time and National costs.