Movement to the full
Digital Substation
CIGRE
Ravindranauth Ramlachan
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 2
• Safety issues – equipment isolation, touch and step potentials, EMC
• Copper – raw material cost has increased 400% in 10 years
• Material cost – cubicle wiring and test costs, labour cost per wire end
termination
• Schematic design - verification cost, excessive on-site work content
• Civil work costs – trays, troughing, cable access/egress…
• Maintainability cost
Why Digital - Wiring, wiring, wiring…….
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 3
What is a Digital Substation?
Digital substations are those which have embedded processing
intelligence in order to implement part of their operational duties,
and as such typically exceed the capability of their analogue
predecessors. The intelligence adds:
• Ease of use
• Asset management
• Modularity
• Vendor interoperability
• Real time awareness
Realized by digitizing the data related to the primary process at
the point where it is measured
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 4
The Digital Substation – Architect Levels
CIT & NCIT
CTs and VTs
Station Control
Protection and
Control
Primary
Equipment
Process
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 5
Key Drivers
Improved Safety
-Eliminate open circuit CTs
Asset Optimisation
-Intelligent monitoring of equipment
Reduced Maintenance Cost
-Condition-based maintenance
Optimisation of New Investments
Increased Reliability and Availability
extensive self-diagnosis capability, redundancy
Why install a digital substation?
“Not only does it optimise overall lifecycle costs, it is easier
to use. Asset managers now have a vital tool that, with less
wiring and fewer commissioning tests, accommodates
preventive maintenance and can extend transformer and
switchgear lifetime. Digital substations are modular, so they
can be tailored to system needs and open to third-party
devices. It is easy to retrofit protection and control schemes
with minimal outage constraints. Ultimately, operators
manage a smarter grid, with better, more complete real-time
situational awareness, making the system more available and
secure.”
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 6
Key Drivers
Standardisation and Interoperability
-Multi Vendor
Ease of Refurbishment
-Refurbish with minimum primary outage
Improved communication capability
-Data available to all levels
Environmental Responsibility
-Wiring is reduced by typically 80%.
Why install a digital substation?
“Not only does it optimise overall lifecycle costs, it is easier
to use. Asset managers now have a vital tool that, with less
wiring and fewer commissioning tests, accommodates
preventive maintenance and can extend transformer and
switchgear lifetime. Digital substations are modular, so they
can be tailored to system needs and open to third-party
devices. It is easy to retrofit protection and control schemes
with minimal outage constraints. Ultimately, operators
manage a smarter grid, with better, more complete real-time
situational awareness, making the system more available and
secure.”
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 7
Technology Enablers and Standards
• Ethernet (typically 100Mbit/s, moving towards 1Gb)
• IEC 61850
−IEC 61850-8-1 and GOOSE Service
−IEC 61850-9-2LE for Sample Values
• IEC 62439-3
−PRP for redundant star architecture
−HSR for redundant ring architecture
• IEEE C37.118 – phasor measurement
• Precision time synchronising (µs)
−GPS (1pps)
−IEEE 1588
• Non Conventional CTs (NCIT) & Merging Units (MU)
• Cyber security
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 8
What does IEC 61850 solve?
Control Centre HMI, Station
controller
Gateway
Relay
X1
Bay
Controller
Conventional
Switchgear
Conventional
CT / VT's
Relay
X2
Relay
X1
Bay
Controller
Conventional
Switchgear
Relay
X2
Conventional
CT / VT's
Vendor specific protocols like LON, MVB, SPA,
Profibus, FIP, DNP3.0, Modbus etc
Hardwired with parallel Cu wires
Serial communications
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 9
What does IEC 61850 solve?
Control Centre
Router
Relay
X1
Bay
Controller
Intelligent
Switchgear
Non
conventional
CT/VT
Relay
X2
Relay
X1
Bay
Controller
Intelligent
Switchgear
Relay
X2
Non
conventional
CT/VT
HMI, Station
controller
Ethernet communications
Ethernet communications
Station Bus
Process Bus
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 10
The Digital Substation
CIT & NCIT
CTs and VTs
Enablers
-Ethernet
-Redundancy
-61850
-Station Bus
-Process Bus
-Precision Timing
-NCIT/MU
-Cyber Security
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 11
NCIT Advantages
• Cost Savings (particularly at voltages above 200kV)
− Compact and lightweight primary current and voltage transformers
− Space-efficient, easily transportable
• Digital Standard IEC 61850-9.2 - Interoperability
− Interoperability between conventional CT/VTs, other vendors supporting IEC
61850-9.2, and test equipment
− Ease of integration in the Total Digital Substation.
• Safety - Reliability - Availability
− No explosion risk
− No wired cross-site CT connection
• Measurement Improvement
− No saturation, no ferroresonance, accurate transient response
− High bandwidth: Wide dynamic range for Protection short circuits, whilst
retaining accuracy for low-current Measurement
• Exploitation Ease
− Ethernet distribution of sampled analogue values to multiple devices
− Ease of extension or modification without affecting physical wiring
− Measurement class accuracy and Protection dynamic range
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 12
Digital Substation Challenges
• Redundancy
• Extends to communication network
• Same considerations as with “traditional” substation
• Testing
• How to isolate and test
• Precision Timing
• Common time source needed
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 13
Architecture Redundancy Considerations
• There are numerous ways to increase the reliability and availability of
a digital substation through redundancy
− Redundant sensors
− Redundant IEDs
− Redundant networks
Station Bus (Redundant PRP)
Main
GOOSE A
GOOSE
B
Prot
B Backup
MUs A/B Main
MUs A/B
CB Control /
RTU
GOOSE & MMS
Prot
A
Main
GOOSE & MMS
Process Bus (Duplicated A/B)
Process Bus (Redundant PRP)
Switch (Process / Station bus
boundary)
SV
SV
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 14
SV considerations – isolation and testing
• Set IED into ‘Simulation’ mode
• IED processes SV frames with Test/Simulation indication
set
−Does not operate IED trip outputs
IED
Sim=TRUE
MU1
Simulator
MU1
(process) X
SV Sim=FALSE
SV Sim=TRUE
Prot
Functions
Trip
values Output
X
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 15
Merging Unit considerations – SV delays
• Different delay in samples from different MUs
−could be from different vendors
IEC 61850
Merging Unit 1
Ethernet
Switch
IA1, IB 1, IC 1
IEC 61850
Merging Unit 2
IEC 61850
Merging Unit 3
IY1
IA3, IB 3, IC3
IY 2
IA5, IB 5, IC5
IY 3
VA , VB , VC
Protection
IED
-
9
-
2
L
E
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 16
Merging Unit considerations – SV delays
• Need each MU to be accurately synchronized
−1 PPS, IEEE 1588 PTP
• IED processes global/local synchronization indication for SV received
−Adapts protection functions – e.g. inhibits current differential
−Alarms on loss of synchronization
• IED should align SV according to maximum time delay between subscribed Merging
Units
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 17
Presentation title - 01/01/2010 - P 17
Pilot Project – ENDESA, Spain
ENDESA substation:
SE Llobregat
145kV
Pilot Projects
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 18
Pilot Project – ENERGIENET, Denmark
ENERGINET: Denmark – Full digital solution
6 Underground 420 kV Cables differential monitoring
OHL
420kV
3000A
RF 1.2
Diff 1
Cable 1 - 420kV
1500A - RF 2
> 20km
NXMU ’s
In : 3 currents
Out : 2x 61850 9 -2LE
Diff 2
Redundancy
Cable 2 - 420kV
1500A - RF 2
> 20km
9 - 2LE 9 - 2LE
9 - 2LE
9 - 2LE
MICOM
P594
1PPS
MICOM
P594
1PPS
AIS scope:
• 72 COSI CT420
• 24 COSI NXMU
SAS scope:
• 24 P546
• 12 P594
x6
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on
that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without
liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 24/10/2013 – P 19
The Digital Substation: Conclusion
• The Digital Substation requires:
− A common, coherent solution integrated using modern communication
architectures
− An optimized solution for customers, with reduced costs of ownership and higher
performance
• This is supported by the application of IEC 61850 within the substation :
− Digitization of data at source
− Implementation of “real-time” communications
− Integration of all control, measurement, protection and monitoring functions
− Test features
www.alstom.com
With Alstom, preserve the environment.
Is printing this presentation really necessary?

More Related Content

What's hot

Solar Mini grid, Nano grid, Micro grid
Solar Mini grid, Nano grid, Micro gridSolar Mini grid, Nano grid, Micro grid
Solar Mini grid, Nano grid, Micro gridMD Jannatul Giyem
 
Alstom High Voltage Training Offer - Technical Institute
Alstom High Voltage Training Offer - Technical InstituteAlstom High Voltage Training Offer - Technical Institute
Alstom High Voltage Training Offer - Technical InstituteThorne & Derrick International
 
MY PROJECT-automatic load sharing of transformer by using GSM tecnique.
MY PROJECT-automatic load sharing of transformer by using GSM tecnique.MY PROJECT-automatic load sharing of transformer by using GSM tecnique.
MY PROJECT-automatic load sharing of transformer by using GSM tecnique.nikhilhiware
 
Electrical safety in power stations
Electrical safety in power stationsElectrical safety in power stations
Electrical safety in power stationsManohar Tatwawadi
 
INTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLERINTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLERNitish NIT
 
Under ground cables presention
Under ground cables presentionUnder ground cables presention
Under ground cables presentionRazu Khan
 
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...Thorne & Derrick International
 
Ring main unit presenattion
Ring main unit presenattionRing main unit presenattion
Ring main unit presenattionsnehalisable
 
Safety and order in electrical substations
Safety and order in electrical substationsSafety and order in electrical substations
Safety and order in electrical substationsYunz contracting
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substationsharique_64
 
Instrumentation cables rev2
Instrumentation cables rev2Instrumentation cables rev2
Instrumentation cables rev2GSS Srinivas
 
Smart Grid Cyber Security
Smart Grid Cyber SecuritySmart Grid Cyber Security
Smart Grid Cyber SecurityJAZEEL K T
 
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...Ali Sepehri
 
Principles of Cable Selection
Principles of Cable SelectionPrinciples of Cable Selection
Principles of Cable SelectionLeonardo ENERGY
 
Smart Grid- By Rahul Mehra
Smart Grid- By Rahul MehraSmart Grid- By Rahul Mehra
Smart Grid- By Rahul MehraRahul Mehra
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substationRaushanKumar582
 

What's hot (20)

33/11 KV SUBSTATION
33/11 KV SUBSTATION33/11 KV SUBSTATION
33/11 KV SUBSTATION
 
Solar Mini grid, Nano grid, Micro grid
Solar Mini grid, Nano grid, Micro gridSolar Mini grid, Nano grid, Micro grid
Solar Mini grid, Nano grid, Micro grid
 
Alstom High Voltage Training Offer - Technical Institute
Alstom High Voltage Training Offer - Technical InstituteAlstom High Voltage Training Offer - Technical Institute
Alstom High Voltage Training Offer - Technical Institute
 
Saudi Arabian Power Grid Code 2020
Saudi Arabian Power Grid Code 2020Saudi Arabian Power Grid Code 2020
Saudi Arabian Power Grid Code 2020
 
MY PROJECT-automatic load sharing of transformer by using GSM tecnique.
MY PROJECT-automatic load sharing of transformer by using GSM tecnique.MY PROJECT-automatic load sharing of transformer by using GSM tecnique.
MY PROJECT-automatic load sharing of transformer by using GSM tecnique.
 
Electrical safety in power stations
Electrical safety in power stationsElectrical safety in power stations
Electrical safety in power stations
 
INTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLERINTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLER
 
Under ground cables presention
Under ground cables presentionUnder ground cables presention
Under ground cables presention
 
LIGHTNING CATALOGUE
LIGHTNING CATALOGUELIGHTNING CATALOGUE
LIGHTNING CATALOGUE
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
400kV Undeground Cable Construction - Installation, Trenching & Jointing - Na...
 
Ring main unit presenattion
Ring main unit presenattionRing main unit presenattion
Ring main unit presenattion
 
Safety and order in electrical substations
Safety and order in electrical substationsSafety and order in electrical substations
Safety and order in electrical substations
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
 
Instrumentation cables rev2
Instrumentation cables rev2Instrumentation cables rev2
Instrumentation cables rev2
 
Smart Grid Cyber Security
Smart Grid Cyber SecuritySmart Grid Cyber Security
Smart Grid Cyber Security
 
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
High Voltage Gas Insulated Substation (GIS) Routine Tests According to IEEE C...
 
Principles of Cable Selection
Principles of Cable SelectionPrinciples of Cable Selection
Principles of Cable Selection
 
Smart Grid- By Rahul Mehra
Smart Grid- By Rahul MehraSmart Grid- By Rahul Mehra
Smart Grid- By Rahul Mehra
 
Gas insulated substation
Gas insulated substationGas insulated substation
Gas insulated substation
 

Similar to Digital Substation Evolution

Mobile Monday Switzerland #38 - Alstom Power presentation on Mobility and Ser...
Mobile Monday Switzerland #38 - Alstom Power presentation on Mobility and Ser...Mobile Monday Switzerland #38 - Alstom Power presentation on Mobility and Ser...
Mobile Monday Switzerland #38 - Alstom Power presentation on Mobility and Ser...MobileMonday Switzerland
 
Building Next Generation Transport Networks
Building Next Generation Transport NetworksBuilding Next Generation Transport Networks
Building Next Generation Transport NetworksInfinera
 
Elevator pitches from Digital Railways competition consortia building day
Elevator pitches from Digital Railways competition consortia building dayElevator pitches from Digital Railways competition consortia building day
Elevator pitches from Digital Railways competition consortia building dayKTN
 
Live demo of low-latency and timing-accurate mobile x-haul based on SDN-enabl...
Live demo of low-latency and timing-accurate mobile x-haul based on SDN-enabl...Live demo of low-latency and timing-accurate mobile x-haul based on SDN-enabl...
Live demo of low-latency and timing-accurate mobile x-haul based on SDN-enabl...ADVA
 
Stork Presentation on Migration (Willem Hazenberg)
Stork Presentation on Migration (Willem Hazenberg)Stork Presentation on Migration (Willem Hazenberg)
Stork Presentation on Migration (Willem Hazenberg)ARC Advisory Group
 
teltonika-networks-use-case-catalog-v1.2.pdf
teltonika-networks-use-case-catalog-v1.2.pdfteltonika-networks-use-case-catalog-v1.2.pdf
teltonika-networks-use-case-catalog-v1.2.pdfitsamihaland
 
Protection, Automation and Monitoring: SIPROTEC 5 v7.9/v8.0
Protection, Automation and Monitoring:  SIPROTEC 5 v7.9/v8.0Protection, Automation and Monitoring:  SIPROTEC 5 v7.9/v8.0
Protection, Automation and Monitoring: SIPROTEC 5 v7.9/v8.0Ryan O'Mara
 
Strainlabs - Wireless sensor technology for a predictable future
Strainlabs - Wireless sensor technology for a predictable futureStrainlabs - Wireless sensor technology for a predictable future
Strainlabs - Wireless sensor technology for a predictable futureGösta Rydin
 
Estimating the cost of a CCS System - Jean-François Léandri, Alstom
Estimating the cost of a CCS System - Jean-François Léandri, AlstomEstimating the cost of a CCS System - Jean-François Léandri, Alstom
Estimating the cost of a CCS System - Jean-François Léandri, AlstomGlobal CCS Institute
 
BRKIOT-2108.pdf
BRKIOT-2108.pdfBRKIOT-2108.pdf
BRKIOT-2108.pdfJokaTek
 
Splunk for Monitoring and Diagnostics Breakout Session
Splunk for Monitoring and Diagnostics Breakout SessionSplunk for Monitoring and Diagnostics Breakout Session
Splunk for Monitoring and Diagnostics Breakout SessionSplunk
 
Fluke Connect Condition Based Maintenance
Fluke Connect Condition Based MaintenanceFluke Connect Condition Based Maintenance
Fluke Connect Condition Based MaintenanceFrederic Baudart, CMRP
 
5G SA security: a comprehensive overview of threats, vulnerabilities and rem...
 5G SA security: a comprehensive overview of threats, vulnerabilities and rem... 5G SA security: a comprehensive overview of threats, vulnerabilities and rem...
5G SA security: a comprehensive overview of threats, vulnerabilities and rem...PositiveTechnologies
 
MohdRiyazKhan_Resume
MohdRiyazKhan_ResumeMohdRiyazKhan_Resume
MohdRiyazKhan_ResumeRIYAZ Khan
 
IRJET- Secure and Efficient Transmission Mechanism for Emergency Data in ...
IRJET-  	  Secure and Efficient Transmission Mechanism for Emergency Data in ...IRJET-  	  Secure and Efficient Transmission Mechanism for Emergency Data in ...
IRJET- Secure and Efficient Transmission Mechanism for Emergency Data in ...IRJET Journal
 
Asset Utilization Metrics Propel a Revival in Safety Solutions
Asset Utilization Metrics Propel a Revival in Safety SolutionsAsset Utilization Metrics Propel a Revival in Safety Solutions
Asset Utilization Metrics Propel a Revival in Safety SolutionsARC Advisory Group
 

Similar to Digital Substation Evolution (20)

Mobile Monday Switzerland #38 - Alstom Power presentation on Mobility and Ser...
Mobile Monday Switzerland #38 - Alstom Power presentation on Mobility and Ser...Mobile Monday Switzerland #38 - Alstom Power presentation on Mobility and Ser...
Mobile Monday Switzerland #38 - Alstom Power presentation on Mobility and Ser...
 
EWTEC_Presentation_v2
EWTEC_Presentation_v2EWTEC_Presentation_v2
EWTEC_Presentation_v2
 
Building Next Generation Transport Networks
Building Next Generation Transport NetworksBuilding Next Generation Transport Networks
Building Next Generation Transport Networks
 
Elevator pitches from Digital Railways competition consortia building day
Elevator pitches from Digital Railways competition consortia building dayElevator pitches from Digital Railways competition consortia building day
Elevator pitches from Digital Railways competition consortia building day
 
Live demo of low-latency and timing-accurate mobile x-haul based on SDN-enabl...
Live demo of low-latency and timing-accurate mobile x-haul based on SDN-enabl...Live demo of low-latency and timing-accurate mobile x-haul based on SDN-enabl...
Live demo of low-latency and timing-accurate mobile x-haul based on SDN-enabl...
 
Stork Presentation on Migration (Willem Hazenberg)
Stork Presentation on Migration (Willem Hazenberg)Stork Presentation on Migration (Willem Hazenberg)
Stork Presentation on Migration (Willem Hazenberg)
 
Smart Grid Deployment Experience and Utility Case Studies
Smart Grid Deployment Experience and Utility Case StudiesSmart Grid Deployment Experience and Utility Case Studies
Smart Grid Deployment Experience and Utility Case Studies
 
teltonika-networks-use-case-catalog-v1.2.pdf
teltonika-networks-use-case-catalog-v1.2.pdfteltonika-networks-use-case-catalog-v1.2.pdf
teltonika-networks-use-case-catalog-v1.2.pdf
 
Protection, Automation and Monitoring: SIPROTEC 5 v7.9/v8.0
Protection, Automation and Monitoring:  SIPROTEC 5 v7.9/v8.0Protection, Automation and Monitoring:  SIPROTEC 5 v7.9/v8.0
Protection, Automation and Monitoring: SIPROTEC 5 v7.9/v8.0
 
Strainlabs - Wireless sensor technology for a predictable future
Strainlabs - Wireless sensor technology for a predictable futureStrainlabs - Wireless sensor technology for a predictable future
Strainlabs - Wireless sensor technology for a predictable future
 
Estimating the cost of a CCS System - Jean-François Léandri, Alstom
Estimating the cost of a CCS System - Jean-François Léandri, AlstomEstimating the cost of a CCS System - Jean-François Léandri, Alstom
Estimating the cost of a CCS System - Jean-François Léandri, Alstom
 
BRKIOT-2108.pdf
BRKIOT-2108.pdfBRKIOT-2108.pdf
BRKIOT-2108.pdf
 
Splunk for Monitoring and Diagnostics Breakout Session
Splunk for Monitoring and Diagnostics Breakout SessionSplunk for Monitoring and Diagnostics Breakout Session
Splunk for Monitoring and Diagnostics Breakout Session
 
Fluke Connect Condition Based Maintenance
Fluke Connect Condition Based MaintenanceFluke Connect Condition Based Maintenance
Fluke Connect Condition Based Maintenance
 
5G SA security: a comprehensive overview of threats, vulnerabilities and rem...
 5G SA security: a comprehensive overview of threats, vulnerabilities and rem... 5G SA security: a comprehensive overview of threats, vulnerabilities and rem...
5G SA security: a comprehensive overview of threats, vulnerabilities and rem...
 
MohdRiyazKhan_Resume
MohdRiyazKhan_ResumeMohdRiyazKhan_Resume
MohdRiyazKhan_Resume
 
IRJET- Secure and Efficient Transmission Mechanism for Emergency Data in ...
IRJET-  	  Secure and Efficient Transmission Mechanism for Emergency Data in ...IRJET-  	  Secure and Efficient Transmission Mechanism for Emergency Data in ...
IRJET- Secure and Efficient Transmission Mechanism for Emergency Data in ...
 
Asset Utilization Metrics Propel a Revival in Safety Solutions
Asset Utilization Metrics Propel a Revival in Safety SolutionsAsset Utilization Metrics Propel a Revival in Safety Solutions
Asset Utilization Metrics Propel a Revival in Safety Solutions
 
Ge specialized Protection Numerical Relays
Ge specialized Protection Numerical RelaysGe specialized Protection Numerical Relays
Ge specialized Protection Numerical Relays
 
Ge network stability and control relay
Ge network stability and control relayGe network stability and control relay
Ge network stability and control relay
 

Recently uploaded

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 

Recently uploaded (20)

power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 

Digital Substation Evolution

  • 1. 10/22/2013 Movement to the full Digital Substation CIGRE Ravindranauth Ramlachan
  • 2. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 2 • Safety issues – equipment isolation, touch and step potentials, EMC • Copper – raw material cost has increased 400% in 10 years • Material cost – cubicle wiring and test costs, labour cost per wire end termination • Schematic design - verification cost, excessive on-site work content • Civil work costs – trays, troughing, cable access/egress… • Maintainability cost Why Digital - Wiring, wiring, wiring…….
  • 3. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 3 What is a Digital Substation? Digital substations are those which have embedded processing intelligence in order to implement part of their operational duties, and as such typically exceed the capability of their analogue predecessors. The intelligence adds: • Ease of use • Asset management • Modularity • Vendor interoperability • Real time awareness Realized by digitizing the data related to the primary process at the point where it is measured
  • 4. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 4 The Digital Substation – Architect Levels CIT & NCIT CTs and VTs Station Control Protection and Control Primary Equipment Process
  • 5. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 5 Key Drivers Improved Safety -Eliminate open circuit CTs Asset Optimisation -Intelligent monitoring of equipment Reduced Maintenance Cost -Condition-based maintenance Optimisation of New Investments Increased Reliability and Availability extensive self-diagnosis capability, redundancy Why install a digital substation? “Not only does it optimise overall lifecycle costs, it is easier to use. Asset managers now have a vital tool that, with less wiring and fewer commissioning tests, accommodates preventive maintenance and can extend transformer and switchgear lifetime. Digital substations are modular, so they can be tailored to system needs and open to third-party devices. It is easy to retrofit protection and control schemes with minimal outage constraints. Ultimately, operators manage a smarter grid, with better, more complete real-time situational awareness, making the system more available and secure.”
  • 6. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 6 Key Drivers Standardisation and Interoperability -Multi Vendor Ease of Refurbishment -Refurbish with minimum primary outage Improved communication capability -Data available to all levels Environmental Responsibility -Wiring is reduced by typically 80%. Why install a digital substation? “Not only does it optimise overall lifecycle costs, it is easier to use. Asset managers now have a vital tool that, with less wiring and fewer commissioning tests, accommodates preventive maintenance and can extend transformer and switchgear lifetime. Digital substations are modular, so they can be tailored to system needs and open to third-party devices. It is easy to retrofit protection and control schemes with minimal outage constraints. Ultimately, operators manage a smarter grid, with better, more complete real-time situational awareness, making the system more available and secure.”
  • 7. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 7 Technology Enablers and Standards • Ethernet (typically 100Mbit/s, moving towards 1Gb) • IEC 61850 −IEC 61850-8-1 and GOOSE Service −IEC 61850-9-2LE for Sample Values • IEC 62439-3 −PRP for redundant star architecture −HSR for redundant ring architecture • IEEE C37.118 – phasor measurement • Precision time synchronising (µs) −GPS (1pps) −IEEE 1588 • Non Conventional CTs (NCIT) & Merging Units (MU) • Cyber security
  • 8. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 8 What does IEC 61850 solve? Control Centre HMI, Station controller Gateway Relay X1 Bay Controller Conventional Switchgear Conventional CT / VT's Relay X2 Relay X1 Bay Controller Conventional Switchgear Relay X2 Conventional CT / VT's Vendor specific protocols like LON, MVB, SPA, Profibus, FIP, DNP3.0, Modbus etc Hardwired with parallel Cu wires Serial communications
  • 9. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 9 What does IEC 61850 solve? Control Centre Router Relay X1 Bay Controller Intelligent Switchgear Non conventional CT/VT Relay X2 Relay X1 Bay Controller Intelligent Switchgear Relay X2 Non conventional CT/VT HMI, Station controller Ethernet communications Ethernet communications Station Bus Process Bus
  • 10. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 10 The Digital Substation CIT & NCIT CTs and VTs Enablers -Ethernet -Redundancy -61850 -Station Bus -Process Bus -Precision Timing -NCIT/MU -Cyber Security
  • 11. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 11 NCIT Advantages • Cost Savings (particularly at voltages above 200kV) − Compact and lightweight primary current and voltage transformers − Space-efficient, easily transportable • Digital Standard IEC 61850-9.2 - Interoperability − Interoperability between conventional CT/VTs, other vendors supporting IEC 61850-9.2, and test equipment − Ease of integration in the Total Digital Substation. • Safety - Reliability - Availability − No explosion risk − No wired cross-site CT connection • Measurement Improvement − No saturation, no ferroresonance, accurate transient response − High bandwidth: Wide dynamic range for Protection short circuits, whilst retaining accuracy for low-current Measurement • Exploitation Ease − Ethernet distribution of sampled analogue values to multiple devices − Ease of extension or modification without affecting physical wiring − Measurement class accuracy and Protection dynamic range
  • 12. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 12 Digital Substation Challenges • Redundancy • Extends to communication network • Same considerations as with “traditional” substation • Testing • How to isolate and test • Precision Timing • Common time source needed
  • 13. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 13 Architecture Redundancy Considerations • There are numerous ways to increase the reliability and availability of a digital substation through redundancy − Redundant sensors − Redundant IEDs − Redundant networks Station Bus (Redundant PRP) Main GOOSE A GOOSE B Prot B Backup MUs A/B Main MUs A/B CB Control / RTU GOOSE & MMS Prot A Main GOOSE & MMS Process Bus (Duplicated A/B) Process Bus (Redundant PRP) Switch (Process / Station bus boundary) SV SV
  • 14. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 14 SV considerations – isolation and testing • Set IED into ‘Simulation’ mode • IED processes SV frames with Test/Simulation indication set −Does not operate IED trip outputs IED Sim=TRUE MU1 Simulator MU1 (process) X SV Sim=FALSE SV Sim=TRUE Prot Functions Trip values Output X
  • 15. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 15 Merging Unit considerations – SV delays • Different delay in samples from different MUs −could be from different vendors IEC 61850 Merging Unit 1 Ethernet Switch IA1, IB 1, IC 1 IEC 61850 Merging Unit 2 IEC 61850 Merging Unit 3 IY1 IA3, IB 3, IC3 IY 2 IA5, IB 5, IC5 IY 3 VA , VB , VC Protection IED - 9 - 2 L E
  • 16. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 16 Merging Unit considerations – SV delays • Need each MU to be accurately synchronized −1 PPS, IEEE 1588 PTP • IED processes global/local synchronization indication for SV received −Adapts protection functions – e.g. inhibits current differential −Alarms on loss of synchronization • IED should align SV according to maximum time delay between subscribed Merging Units
  • 17. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 17 Presentation title - 01/01/2010 - P 17 Pilot Project – ENDESA, Spain ENDESA substation: SE Llobregat 145kV Pilot Projects
  • 18. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 18 Pilot Project – ENERGIENET, Denmark ENERGINET: Denmark – Full digital solution 6 Underground 420 kV Cables differential monitoring OHL 420kV 3000A RF 1.2 Diff 1 Cable 1 - 420kV 1500A - RF 2 > 20km NXMU ’s In : 3 currents Out : 2x 61850 9 -2LE Diff 2 Redundancy Cable 2 - 420kV 1500A - RF 2 > 20km 9 - 2LE 9 - 2LE 9 - 2LE 9 - 2LE MICOM P594 1PPS MICOM P594 1PPS AIS scope: • 72 COSI CT420 • 24 COSI NXMU SAS scope: • 24 P546 • 12 P594 x6
  • 19. © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited. Presentation title - 24/10/2013 – P 19 The Digital Substation: Conclusion • The Digital Substation requires: − A common, coherent solution integrated using modern communication architectures − An optimized solution for customers, with reduced costs of ownership and higher performance • This is supported by the application of IEC 61850 within the substation : − Digitization of data at source − Implementation of “real-time” communications − Integration of all control, measurement, protection and monitoring functions − Test features
  • 20. www.alstom.com With Alstom, preserve the environment. Is printing this presentation really necessary?