1. HUAWEI TECHNOLOGIES CO., LTD. Page 1
Configuring RTN 950 Series for
Smart POC and FTK project
(Instruction Manual)
HUAWEI TECHNOLOGIES CO., LTD.
www.huawei.com
2. HUAWEI TECHNOLOGIES CO., LTD. Page 2
1. Setting of IP address on your Laptop
1.1 Right Click on
icon of Local Area
Connection (LAN)
1.2 Click on Properties
1.3 Go to Internet
Protocol (TCP/IP)
then click
Properties
3. HUAWEI TECHNOLOGIES CO., LTD. Page 3
1.4 Type in IPAddress then click on OK
ALWAYS USE THE FOLLOWING:
IPAddress: 129.9.0.99
Subnet mask: 255.255.0.0
(No need to filed-up the Default gateway
and DNS)
4. HUAWEI TECHNOLOGIES CO., LTD. Page 4
2. Open the U2000 Web LCT application (pre-installed)
3. Type in your user name and password to Login
User Name: admin
Password: admin
5. HUAWEI TECHNOLOGIES CO., LTD. Page 5
4. To Search for a NE (Network Element), click NE Search
4.1 Click on NE SEARCH first
before you Add NE
6. HUAWEI TECHNOLOGIES CO., LTD. Page 6
4.2 Click on
SEARCH
Note: Domain is
automatically set
(no need to input
7. HUAWEI TECHNOLOGIES CO., LTD. Page 7
Web LCT will search and detect available NEs
4.3 Available NE will appear
4.4 Click Add NE
8. HUAWEI TECHNOLOGIES CO., LTD. Page 8
4.6 After pressing OK, all
available NE will be added on
the screen (Communication
Status will be NORMAL)
4.5 Then click on OK
9. HUAWEI TECHNOLOGIES CO., LTD. Page 9
5. To Login into the NE
5.1 Highlight the NE you want to login
5.2 Click on NE Login
11. HUAWEI TECHNOLOGIES CO., LTD. Page 11
6. To configure the NE, check if the Login Status then click on NE Explorer
6.1 Highlight the NE you want to
configure
Status will be already Logged in
6.2 Click on NE Explorer
12. HUAWEI TECHNOLOGIES CO., LTD. Page 12
7. Web LCT will automatically detect the available board/card on the Slot Layout
(with color )
8. To install the cards, right click on the board then pressed “ADD”
Note: PIU, FAN and
CSH card will
automatically running
installed. Also slot 23
and 25 for ODU will
not detect until you
finished add the IFU2
boards.
8.1 Click add Physical
Boards
13. HUAWEI TECHNOLOGIES CO., LTD. Page 13
8.2 After you add all the
physical boards, slot 23
and 25 for ODU board
will appear.
8.3 Right click
the ODU board
then click the
add physical
board
14. HUAWEI TECHNOLOGIES CO., LTD. Page 14
9. Configuring NE attribute Site Name and Modifying NE
9.1 Highlight NE name
9.2 Highlight
NE attributes
9.3 Double click box under
NAME and type SITE NAME.
Then click apply and query.
15. HUAWEI TECHNOLOGIES CO., LTD. Page 15
9.4 Click Modify NE ID and a
dialog box will appear.
9.5 Type Site ID based on plan
assigned by TNP. Then click OK
NOTE: ID is a unique number.
16. HUAWEI TECHNOLOGIES CO., LTD. Page 16
10. Configuring 1+1 Protection
10.1 Highlight NE name
10.2 Highlight Link
Configuration
10.3 Click IF 1+1
Protection
10.4 Click New
19. HUAWEI TECHNOLOGIES CO., LTD. Page 19
11.4 Double Click the
box of IF Channel
Band and change the
band according to the
plan
11.5 Double Click the
box of Manually
Specified Module and
change the module
according to the plan
11.6 Double Click the box
of E1 Capacity and change
the capacity according to
the plan
11.7 Click Apply then
Query
20. HUAWEI TECHNOLOGIES CO., LTD. Page 20
12. Configuring Transmit Frequency and Transmit Power
12.4 Click apply then
query
12.3 Double click the
box of transmit
frequency and type the
frequency according to
link budget given by
TNP
12.2 Highlight ODU
interface
12. 1 Highlight 23-ODU
21. HUAWEI TECHNOLOGIES CO., LTD. Page 21
12.5 click the
power
attributes
12.6 Double click the box of transmit power and
type the power according to link budget given by
TNP 12.7 Click apply
and query
22. HUAWEI TECHNOLOGIES CO., LTD. Page 22
13. Configuring Cross-Connection
13.1 Highlight NE name
13.2 Highlight cross connection
configuration
13.3 Click New